Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; 20 November 2013

Upload: gabrielle-newsom

Post on 29-Mar-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry Day

Product Manager

LTC Garth Winterle

Deputy PM

Mr. John W. Daniele

DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.

20 November 2013

Page 2: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

2

Heavy Crane Industry DayAgenda

• 0815 Welcome LTC Nancy Hansen

• 0830 Introductions and Administration LTC Nancy Hansen• 0845 The Heavy Crane Requirement – Mission Gap LTC Nancy Hansen• 0900 Administrative/Purpose Patricia Pierce• 0910 Legal Statement Patricia Pierce• 0915 Contract Summary Patricia Pierce• 0945 Section B – Anticipated Proposal Requirements Patricia Pierce

• 1015 Section C – Scope of Work Subject Matter

Expert• 1100 Purchase Description Doris Strong• 1200 – 1400 LUNCH • 1400 Section D – Packaging Daniel Brumfield• 1415 Section F – Delivery Schedule Req./Storage Patricia Pierce• 1430 Section H – Special Contract Clauses Patricia Pierce• 1515 Section J – CDRLS/DIDS Linda Skidmore• 1530 Schedule of events Patricia Pierce• 1545 Questions Patricia Pierce

20 November 2013

Page 3: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayMission Gap

• The Type II Heavy Crane, NSN 3810-01-607-9674, is an all terrain, self deployable crane.

• This program represents a new range of lift for the Engineer Brigades of the Army. To date the nearest lift capability by a program of record is the 22 Ton capability AT422 all terrain crane (ATEC).

• Primary Mission: To lift heavy equipment to include MRAPS

3 20 November 2013

Page 4: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayAdministrative

• The official (non-draft) Request for Proposal, once released, will take precedence over prior information on ProcNet Heavy Crane site and over Industry Day information• ProcNet:

• http://contracting.tacom.army.mil/majorsys/heavycrane/heavycrane.htm

• ProcNet site will be continually updated with RFP information such as:• Draft Heavy Crane Purchase Description (PD)• Draft sections of RFP • Q&A • Industry Day Charts• Announcements

• List of conference attendees that have agreed to release of their names will be posted to the Heavy Crane ProcNet site

• It is the responsibility of Industry to check the website regularly!4 20 November 2013

Page 5: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurpose

• To provide potential Offerors RFP related information• To improve understanding of the requirements for the development of the Offerors formal solicitation• To provide forum for questions to be asked• Conference is for informational purposes only

• Our intent is to clearly communicate our strategy

• Government cannot reimburse costs of solicitation preparation except as otherwise provided for in FAR Part 31.205-18

5 20 November 2013

Page 6: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayContract Summary

Request for Proposal – W56HZV-13-R-0036• Contract Type

• Firm Fixed Price • Requirements Contract • FAR 15

• Ordering Period: • 5 years from contract award• 6 years with exercise of 1st year option; 7 years with exercise

of 2nd year option • Offerors are required to submit offer(s) electronically, via the

Army Single Face to Industry (ASFI) Online Bid Response System (BRS)

6 20 November 2013

Page 7: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayContract Summary

Request for Proposal – W56HZV-13-R-0036• All offerors must possess a SECRET Facility Security Clearance at the time of proposal submission• All offerors are limited to no more than two proposals in response to the Heavy Crane RFP• The successful offeror must be registered with the Department of Defense System for Award Management (SAM) at https://www.sam.gov• Additional information related to this RFP, prior its release, may be found at the following website:• https://contracting.tacom.army.mil/majorsys/HeavyCrane/Hea

vyCrane.htm

• The RFP, once released, will be posted on the following websites:• https://www.fbo.gov• https://contracting.tacom.army.mil/opportunity.htm7 20 November 2013

Page 8: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayAnticipated Proposal Requirements

• FAT/LOG Units• Production Units• Crane Attachments

Pile Driver w/ Install Kit Four Leg Sling Set Concrete Barrier Lifter Clamshell bucket Concrete bucket

• Basic Issue Items• Initial Service Package• Spare Parts Kit • Critical Stockage List (w/ prices) • Special Tools Kit (w/ tool box)• Hand off (price to include travel)

20 November 20138

• Armor Development Kit• Armor Kits• Simulators Development• Simulators *• Field Service

Representatives• Instructor & Key

Personnel Training• NET Training

Development• Storage• Data Items (Logistics) • Interim Contractor

Logistics• Operator and Maintainer

NET Classes*Simulator prices for years 2 through 7

Page 9: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayAnticipated Proposal Requirements

20 November 20139

• Meeting Agenda and Minutes • ECPs • IUID Reports• Inventory List/DA 3161• Accountability Report• Warranty Performance Report• FSR report• FSR IRDO Data• FACARS• Configuration Change Reports• ICLS Reports

• NMWRS (Engine, Transmission, Axles and Boom)• IETM -10 Operator/-23&P manual• Lubrication Order• Armor Manual • Pile Driver Manual • NMWR and Pile Driver RPSTL• Special Packaging• NET OP and FLM classes• Simulator Test plan/ Instruction/Student guides• Provisioning• EDFP• Transportability/Safety/Hazardous/Diagnostics reports• Test Support• LORA/Log Demo

NOTE: Not all logistics will be procured in the first year, therefore, all logistics will require prices for year 1 and year 2.

CDRLS NSP Items Separately Priced Items

Page 10: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayProposal Pitfalls

• There is a difference between your small business volume and the small business subcontracting plan• There are several items that are also used outside of the evaluation process to determine contractor eligibility for award• Small business• Contractor responsibility• Fair and reasonable price

• Make sure your numbers in the pricing spreadsheets are correct and in the proper columns• Be sure that your complete proposal submission is on time

20 November 201310

Page 11: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry Day

SECTION C SCOPE OF WORK

20 November 201311

Page 12: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C – Special Tools

• Clarification• BII/COEI – cost incurred as determined by delivery order• ISP/SPK – cost incurred as determined by delivery order• Special Tools – cost incurred as determined by delivery order

20 November 201312

Page 13: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C – Basic Issue Item (BII)/COEI

• What is BII?• Basic Issue Items are the minimum essential items required to

place the equipment in operation, to operate it, perform routine operator maintenance and services, and to perform emergency repairs.

• What is COEI?• Components of End Item are the minimum essential items

required to place the equipment in operation, to operate it, perform routine operator maintenance and services, and to perform emergency repairs that are removed and separately packaged for transportation or shipment. • Examples are Pile Driver and Sling Set

20 November 201313

Page 14: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C - ISP/SPK/Special Tools

• What is the Initial Service Pack?• The Initial Service Pack (ISP) includes all service parts required to meet warranty service

intervals and perform the first scheduled maintenance in the first year of service.

• What is SPK?• The Spare Parts Kit includes items likely to be replaced due to normal wear or

unscheduled maintenance in the first year of service.

• What’s the difference?• ISP is scheduled maintenance (according to TMs)• SPK is unscheduled maintenance (based on commercial failure data)

• What are Special Tools?• Fabricated tools that are made by the Contractor• Used on a single end item• Supplied for military applications only• Designed to perform a specific task for use on a specific end item or component• Not available in common tool load (GMTK, FRS, SATS)• The offeror MUST provide any special source and calibration documentation for special

tools and TMDE

20 November 201314

Page 15: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C - Provisioning

• Provisioning• Provisioning requires three key elements: the Provisioning Parts List (PPL),

Engineering Data for Provisioning (EDFP), and the Pre-Procurements Screening (PPS).• The (PPL) is the identification of all repair parts, special tools and diagnostic

equipment that supports the Heavy Crane. The PPL shall be prepared in accordance with Government Electronics and Information Technology Association (GEIA-STD-0007) and (GEIA-HB-0007).• The (EDFP) is used to indicate the physical characteristics, location and

function of the item being provisioned. The EDFP shall be prepared in accordance with American Society of Mechanical Engineers (ASME Y14.24-2012). • The (PPS) shall ensure that the characteristics data of parts (i.e. common

hardware) match the required characteristics data as directed by production. For example, if the requirement for a screw is brass coating, the screening should ensure that the selected common hardware National Stock Number (NSN) specifies brass coating.

20 November 201315

Page 16: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C - Provisioning

• Provisioning Reviews• The Contractor shall host several provisioning reviews, each lasting 10 days,

throughout the duration of the contract. Each event will review any complete assemblies major or minor with a minimum of 1,600 lines per event.• The Contractor shall provide the following to support the provisioning review

effort: Provisioning Parts List (PPL) in a format compatible with TACOM Logistics

Modernization program (LMP) provisioning system in 1388-2B format. Guidance for 1388-2B format is contained in (GEIA-STD-0007) and (GEIA-HB-0007).

Provisioning Parts List (PPL) and accompanying hardcopy EDFP drawing. Provisioning Line Item Sequence Number (PLISNs) with National Stock

Numbers (NSNs), with hard copy of Pre-Procurement Screening (PPS). An electronic copy of the Logistics Support Analysis (LSA-036). Guidance for

(LSA-036) is contained in (GEIA-STD-0007) and (GEIA-HB-0007).

20 November 201316

Page 17: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C - Publications

• Validation• This Contractor-led event shall take place before first draft delivery.• Contractor shall provide a plan and schedule for the Validation.• The Government will observe Validation on a regular basis.• The Contractor shall provide a report with draft delivery.

• Quality Assurance• All publication drafts submitted to the Government shall be free of:

Spelling errors Grammatical errors Format inconsistencies Title/nomenclature inconsistencies

• Publication Guidance• MIL-STD 40051-1B/2B• DE Publications Style Guide• Requirements Matrices

20 November 201317

Page 18: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C – Integrated Logistics Support

• The Contractor shall provide Field Service Representatives (FSR) who will provide on-site technical support (both CONUS and OCONUS), during contingency and non-contingency operations. • The Contractor shall supply personal tool kits, communications,

and IT equipment to contractor FSR personnel deployed in support of the Heavy Crane.  • All maintenance and parts shall be provided by the Contractor at

Conditional Material Release• Anticipated time frame until Organic FMR is 2 years• This will be for CONUS and OCONUS support

• CONUS and Non-contingency OCONUS• CONUS is defined as any location in the continental United States.

OCONUS is defined as any location outside the continental United States. • Contingency is defined as operations in locations in support of

deployments in hostile areas. Non-contingency is defined as operations in fielding or deployments in support of normal operations in CONUS or OCONUS (e.g., Germany).

20 November 201318

Page 19: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C - Simulators

• 8 Simulators with 4 Instructor Operator Stations shall be provided. • Shall have the ability to simulate basic and advanced lifting operations

Clamshell Hook block with spreaders and slings Day/night operations Realistic audio cues Dual lift

• Shall have the ability to collect Performance Data (real time) Loads moved (equipment, containers, soil, etc.) Cycle Times Emphasis on safety while developing crane skills

o Reaction to alarms (two blocking, over load) assisted with LMI/SLI Indicator o Collisions (Suspended Load)o Reaction to faults and malfunctions (loss of engine power, hydraulic failures,

outrigger failure, etc.)

• Shall have interactive environmental modeling Visibility (rain, fog, snow and haze) Wind (speed, direction, and gusting) Time of day Shadows Terrain

20 November 201319

Page 20: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C - Simulators

• Simulator Highlights• Replicates operators compartment of actual equipment

Gauges, indicators, switches, displays Form, fit and function (joysticks, foot controls and switches

necessary for operation) Audio cues (engine, warning buzzers, malfunctions, etc)

• Ability for common access card reader for logging student information• 3 Degrees of Freedom (pitch, yaw, roll)• Intercom system (student to instructor)• Capable of virtual simulation of armored configuration• 180 degree horizontal and 60 degree vertical field of view• Emergency shutdown button

20 November 201320

Page 21: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C – New Equipment Training

• In-Process Reviews (IPRs)• Held at Contractor’s facilities a maximum of four times per year• Contractor shall have all training documentation available for Government

review

• Training Material Verification• Held at Contractor’s facilities• Contractor shall conduct two training classes (one OPNET and one FLMNET)• Contractor shall use the course training materials developed under this

contract• Training Materials approved at Training Material Verification will be used at

I&KPT

• Instructor and Key Personnel Training (I&KPT)• Held at contractor’s facilities• Contractor shall conduct two training classes (one OPNET and one FLMNET) • Contractor shall use the course training materials approved from Training

Material Verification• Training materials approved at successful I&KPT will become the final NET

materials• Assume target audience is individuals that are instructors, skilled crane

operators, and mechanics20 November 201321

Page 22: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C – New Equipment Training

• The contractor shall develop courses of instruction to train operators and maintainers on the Heavy Crane.• Directed towards new technologies not currently in the Army system or

different from current systems in the field.• Operator and Operator Maintenance (OPNET)

Prerequisite requires possession of valid military driver’s license for 22½ ton or higher crane

40 hours in duration with a 3:1 student to machine and instructor ratio – 6 students maximum

Include operator safety, general crane safety, load handling, Preventative Maintenance Checks and Services (PMCS)

Covers load planning/sling load angles plus lifting equipment inspection Include a written examination and hands-on performance evaluation – minimum

score is 80%

• Field Level Maintenance (FLMNET) 40 hours in duration with a 6:1 student to instructor ratio – 12 students maximum Covers minimal operation characteristics, field level PMCS, troubleshooting,

diagnosis and repair of the Heavy Crane Covers quarterly, semi-annual, and annual crane inspection procedures and

repairing/replacing procedures for any load bearing equipment Include a written examination and hands-on performance evaluation – minimum

score is 80%20 November 201322

Page 23: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C - New Equipment Training

• NET Training• When called up in a Delivery Order, the contractor shall conduct

NET Classes• Use Government approved training materials• Government will provide 30 days notification for CONUS and 90

days notification for OCONUS• The contractor shall receive a favorable evaluation from at least

80% of students as performance evaluation• Course Completion

• Contractor shall deliver Training Course Completion Report upon completion of each class

Includes student roster, student surveys, and trip report

• Instructor Certification and Credentials Instructors are required to be certified by the International Board of

Standards for Training Developers and Instructors (IBSTDI) or military equivalent

Contractor shall provide proof of certification to the Procuring Contracting Officer (PCO)

20 November 201323

Page 24: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C - Packaging

• General Packaging Considerations• Environmental Concerns (Time in storage, transportation of

items, corrosion)• Packaging coding process and how data is used

• Data Deliverables• The Military packages two kinds of items, selective and special.

Selective items are simpler and smaller items, while special items are more complex and requires more complex packaging.• Selective (ASCII text file)• Special (ASCII text file, Special Packaging

Instruction,Validation Report)

• Shipping and Storage (Validation)

• Guidance• MIL-STD-2073• MIL-STD-129

20 November 201324

Page 25: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection C - IUID

• For those components specifically identified in the DFARs clause 252.211-7003, the contractor shall identify all items that may require an IUID and submit an IUID Marking Plan.• The contractor shall create the IUID and marking method in accordance with MIL-STD-130N. The contractor shall use IUID Construct #2.• The contractor shall use MIL-STD-130N, as a guide when developing the “System” data plate. The end item UID marking shall be embedded on the system data plate.• The prime contractor has the responsibility to furnish IUID data to the IUID registry. The contractor shall register and validate all IUIDs with the DoD IUID Registry and shall ensure all item parent/child relationships are accurately recorded in the IUID Registry.• The contractor shall provide evidence of validation and verification of a predetermined representative sample of the data matrix marks on each NSN bearing IUID in a report

20 November 201325

Page 26: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection F – Delivery and Performance

• Delivery and Performance - FAT• FAT delivery is 270 days after Delivery Order (DO) issued

• Delivery and Performance - PRODUCTION• DO issued PRIOR TO Government approval of FAT – delivery shall

start 180 calendar days after FAT approval• DO issued AFTER Government approval of FAT – delivery shall start

180 calendar days after DO is issued• See FAR Clause 52.216-19, Order Limitations, for quantity

limitations• Acceleration of DOs is NOT acceptable without written approval

from the Contracting Officer• Storage

• The Government may require the contractor to store and maintain the Heavy Cranes that the Government has shipped in place• The contractor shall maintain the Heavy Cranes in accordance

with its standard commercial procedures to preclude deterioration• See Section F.3 of the RFP for all storage requirements

20 November 201326

Page 27: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection H – Special Contract Clauses

• NOTE: Below is a listing of some provisions. Please read solicitation for complete description of all provisions• H.1 Ordering Year – The first ordering year begins with the date of award

of the contract. • H.2 Other Customers - The contract is for requirements that come

through the Department of the Army. • H.3 Export Control Notice - Technical data may be subject to the

requirements of various export control statutes, regulations, etc. • H.6.1 Government Furnished Equipment/Materials - The prime contractor

is responsible to return all USG furnished equipment.• H.6.2 Government Furnished Equipment/Materials - The Government will

provide the contractor applicable GFE to support testing and logistics support package development.

• H.7 Non-Road Equipment Engine Emissions Requirements - Environmental Protection Agency (EPA)'s Tier IV non-road exhaust emission standards require the engine manufacturers to use pollution control technologies. Therefore, no vehicles delivered under this contract shall utilize Tier IV engines.

20 November 201327

Page 28: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection J – CDRLS /Data Item Descriptions (DIDS)

• What is a data item description (DID)?• A DID is a completed document that defines the data required of a

contractor. The document specifically defines the data content, format, and intended use. It is located on every CDRL

• Where can I obtain a copy of a specific DID?• If you know the DID number, you can use the ASSIST Quick Search. Simply

enter the 5-digit DID number (do not use revision letters) in the search filed labeled [Document Number] and click on the [Submit] button.

• Is there a website that lists all data item descriptions?• All active and canceled DIDs are indexed in the ASSIST database. Once

logged on, to print a preformatted listing of all DIDs in Adobe PDF format, click on the [DIDs] link on the left side of the page to get to the [DIDs Menu] and then click on the link for the [DIDs Browser]. The DIDs Browser allows you to generate a list of active DIDs, canceled DIDs, or all DIDs (both active and canceled). This same screen allows you to filter results by standardization area, preparing activity, or preparing service, or to search for DIDs by keywords. The resultant list will be generated in HTML but may be saved as a preformatted report in Adobe PDF format by clicking on the [Report] button at the bottom of the screen. The list may also be exported in Microsoft Excel format by clicking on the [Spreadsheet] button at the bottom of the screen.

20 November 201328

Page 29: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DaySection J – Data Item Descriptions (DIDS)

• Where can I find an online copy of DoD 5010.12-L, "Acquisition Management Systems and Data Requirements Control List (AMSDL)"?• The AMSDL which formerly listed all DIDs, was canceled in

2007, as all DIDs have been incorporated into the ASSIST database.

• Source: http://www.dsp.dla.mil/APP_UIL/displayPage.aspx?action=content&accounttype=displayHTML&contentid=22• ASSIST Website: http://quicksearch.dla.mil

20 November 201329

Page 30: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry Day

20 November 201330

Purchase Description

Page 31: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

Supplemental Armor Set/ Crew Protection Kit Proposed ballistic solution may be presented as an A kit/B-kit or A-kit/C-

kit solution The threat level may be obtained from Director, U.S. Army Research

Laboratory, ATTN: AMSRD-ARL-WM-TA, Aberdeen Proving Ground, MD 21005-5066

Gaps: In the past, window frames, door seams, bolt joints and air supply openings have resulted in test failures

Environment testing: (wind, sand, dust): panel and door sealing is critical Removal time: no hard requirement but should be a design consideration Ballistic performance: transparent armor at temperature extremes

(ambient, low and high) Coupon testing: required for new ballistic solutions (opaque, transparent,

production) Transparent armor: environmental testing- solar and heat effects Safety consideration: Ingress/egress, emergency egress, door dampers

and vehicle stability Heating and cooling of cab(s) with armor

20 November 201331

Page 32: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

Supplemental Armor Set/ Crew Protection Kit Operator protection/Operator Cab Shall survive against a minimum protection of class 1 for the operator’s cab

and class 2 for the driver’s cab ( as defined in the Army Research Report, Analysis of Threat Projectiles For Protection of Light Tactical Vehicles, ARL-RP-89, dated December 2004)

The CPK shall be in the form of a two part “A-Kit/B-Kit”. The A-Kit

• Consist of permanent, non-removable portions of integral components and mounting provisions that allow the mounting of the B-Kit.

• Include armor protection to those portions of the cabs, which by basis of design, would make it difficult or impossible for upgrading to full crew protection.

• Consist of underside ballistic protection to include, but not limited to, armored floor panels. • Incorporate any vehicle modifications required to allow the cranes to accept and operate

with the armor package. • Installed during production on every vehicle

The B-Kit• Consists of multiple components that need to be individually installed on the crane. The B-

Kit consists of all components required to completely up-armored operators and driver’s cabs.

• Driver Cab: When specified, the crane shall be provided with a complete A-Kit/B-Kit. The driver’s cab CPK solution survive against a minimum protection of class 3 as defined in the Army Research Report, Analysis of Threat Projectiles For Protection of Light Tactical Vehicles, ARL-RP-89, dated December 2004 is desired.

20 November 201332

Page 33: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

Lifting Capability• The Type II Heavy Crane with and without Crew Protection Kit (CPK):

Shall be capable of lifting a minimum of 100,000 pounds at a 10 ft. radius.

Able to transverse the load a minimum of 270 degrees (45 to 315 azimuth using zero (0) as straight ahead) load with outriggers fully extended. The load shall not pass over any part of the crane to include the outriggers.

Able to lift straight up and down (no transverse required) a load 323” long, 106” wide, 156” high, weighing 80,000 lbs (40 Tons) from the rear, and sides with a 2 ft. horizontal clearance from the crane and outriggers.

The load must be able to be lifted high enough to place the load onto the back the family of M870 trailers.

• NOTE: 100K at 10 ft radius is used to size the proposed crane At no time should load be lifted over the crane or outriggers The 40 ton lift does not need to rotate around the crane

20 November 201333

Page 34: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

Travel Speed• The crane with and without CPK, without load, shall be capable of achieving and maintaining

an average on-road travel speed (primary and secondary roads) of 40 mph (Threshold), 50 mph (Objective). System shall be able to achieve an average off-road (cross-country) of 15 mph (Threshold); 40 mph (Objective).

• Classification of roads Primary Roads – Two or more lanes, all weather, maintained, hard surface (paved) roads

with good driving visibility used for heavy and high density traffic.  These roads have lanes with a minimum width of 108 inches (2.75 M), road crown to 20 degrees and the legal maximum GVW/GCW for the country or state is assured for all bridges.  These roads are surfaces having Root Mean Square (RMS) value of 0.1 inch (2.54 mm).

Secondary Roads –Two lanes, all weather, occasionally maintained, hard or loose surface (e.g. large rock, paved, crushed rock, gravel) intended for medium-weight, low-density traffic.  These roads have lanes with minimum width of 98.5 inches (2.5 m) and no guarantee that the legal maximum GVW/GCW for the country or state is assured for all bridges.  These roads are surfaces having a RMS value varying between 0.3 inch (7.63 mm) - 0.6 inch (15.24 mm).

Off Roads/ Cross Country (Trails) – One lane, dry weather, unimproved, seldom maintained loose surface roads, intended for low-density traffic.  Trails have a minimum width of 98.5 inches (2.5 M), no large obstacles (boulders, logs, and stumps) and no bridging.  These are surfaces having a RMS value varying between 0.5 inches (12.7 mm) - 1.5 inches (38.1 mm).

20 November 2013PEO CS&CSS Overview 34

Page 35: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

Travel Speed continued• NOTE:

Example of course located at Aberdeen Proving Grounds (APG)o Primary Roads- Perryman Test Area- Paved Road (PTA-P) Course. o Secondary Roads – Perryman Test Area-Secondary Road A (PTA-A); Munson Test

Area-Gravel Road (MTA-G). o Off Road (cross country) –Munson Test Area – Belgian Block (MTA-BB);

Perryman Test Area Cross-Country Course No. 2 (PTA-2)

20 November 2013PEO CS&CSS Overview 35

Page 36: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

20 November 2013PEO CS&CSS Overview 36

Page 37: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

20 November 201337

Page 38: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

20 November 201338

Page 39: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

Reach• The boom shall be a hydraulically operated, telescoping type,

consisting of a base section and sliding section(s). The boom shall be capable of elevation from the horizontal to a vertical angle of not less than 70 degrees. • The reach shall be at least 100ft (minimum 100ft boom with

jib or 100ft boom) (T).

• NOTE: 100 ft reach is the requirement. Requirement can be met with either

option

20 November 201339

Page 40: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

Transportability• Air Transportability

Drive-on drive-off configuration (under its own power) with operator in the driver’s seat shall be capable of transport by C-5 and C-17 aircraft (T)

MIL-HDBK-1791 is available for guidance. Air transportable while filled to a minimum 25 percent, up to a maximum 75

percent, fuel capacity• Marine Transport

Marine transportable on LCU‑2000 class and larger vessels/ships. Weight, dimensions, and drive-on, drive-off abilities shall conform to MIL-STD-

1366 for each transportable unit• Rail Transport

Rail transportable in CONUS and NATO countries without restrictions Reference MIL-STD- 810, MIL-STD-1366 and SDDCTEA Pamphlet 70-1

• Highway Transportability Road legal (with permits). The maximum axle loads shall meet minimum requirements for highway

transport within the continental U.S.• Transport prep time

Preparation and tie-down for all modes of transport shall be completed in 4 hours or less with 3 soldiers or less.

20 November 201340

Page 41: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

20 November 201341

Transportability• Important to note:

Air Transportability: Ground pressure is key

Tables provided support transport limits, not design limitations.

Page 42: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

20 November 201342

Transportability• NOTE:

Marine Transport: The approach/departure ramp angle 15 degrees with no ramp aids

Tables provided support transport limits, not design limitations.

Page 43: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

20 November 201343

Transportability• NOTE:

Rail: 3 areas of the world (Korea, Europe , NATO); rail impact testing (MIL-STD-810)

Tables provided support transport limits, not design limitations.

Page 44: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayPurchase Description Requirements

20 November 201344

Transportability• NOTE:

Highway: Transport with permits may be required. Permits may also vary per state.

Tables provided support transport limits, not design limitations.

Page 45: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry DayTentative Schedule of Events

• Target Date of RFP Release: February 2014• Number of Days on the Street: 60 days• Target Award: October 2014

20 November 201345

Page 46: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Heavy Crane Industry Day

Questions

Thank you for your attendance!

20 November 201346

Page 47: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

Backup Slides

20 November 201347

Page 48: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

48

• Blocks A. Contract Line Item Number (CLIN)• The CLIN associated with the CDRL.

B. Exhibit• DFARS Subpart 204.7101 requires the DD Form 1423 to be a

contract exhibit versus an attachment.

C. Category• Identifies and groups individual data items.

D. System/Item• The system or item the data will support.

E. Contract/PR No• RFP or Contract Number

HEAVY CRANE INDUSTRY DAYContract Data Requirements List (CDRLS)

20 November 2013

Page 49: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

49

• Blocks F. Contractor• The name of the contractor.

G. Prepared by• The name of the CDRL Preparer.

H. Date• The date the CDRL was prepared.

I. Approved by• The name of the individual approving the CDRL.

J. Date• The date the CDRL was approved.

HEAVY CRANE INDUSTRY DAYContract Data Requirements List (CDRLS)

20 November 2013

Page 50: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

50

• Blocks 1. Data Item number• DFARS Subpart 204.7105(c)-identifies CDRL.

2. Title of Date Item • The title shall be identical to the title of the DID.

3. Subtitle• A subtitle referencing the item to which the specific data item applies-title

as referenced in the SOW.

4. Authority• The DID number. If the DID is being tailored by the CDRL, add "(T)" after the

DID Number in this block.

5. Contract Reference• Specific paragraph(s) of the SOW that point to the CDRL.

HEAVY CRANE INDUSTRY DAYContract Data Requirements List (CDRLS)

20 November 2013

Page 51: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

51

• Blocks

7. DD250 Requirement• DD 250 Form code designates the requirement for inspection & acceptance.

DD-None atSource; final inspection at destination.

8. Approval Code• “A” designated written approval is required before distribution of final data

item

9. Distribution Statement Required• Indicates the distribution statement; letter code is in accordance with DoD

Directive 5230.24.

10. Frequency• Indicates the frequency of submittals. “AS REQ” –as required.

HEAVY CRANE INDUSTRY DAYContract Data Requirements List (CDRLS)

20 November 2013

Page 52: Heavy Crane Industry Day Product Manager LTC Garth Winterle Deputy PM Mr. John W. Daniele DISTRIBUTION STATEMENT A. Approved for public release; distribution

52

• Blocks 11. As of Date• This is the data for which the data needs to be current. Further explanation

is provided in Block 16.

12. Date of First Submission• The initial submission date. “AS REQ”-as required.

13. Date of Subsequent Submission• If data items are required more than once, the dates for subsequent

submissions are given.

14. Distribution• The code letter in accordance with DoD directive 5230.4. “A” means

approved for public release.

15. Total 16. Remarks• The total number of copies required.

HEAVY CRANE INDUSTRY DAYContract Data Requirements List (CDRLS)

20 November 2013