heaters

44
AWI 106 Att. 8 Rev. 1 22 Sep. 2007 Date/ Rev. 1 PRESENTATION ON FIRED HEATERS OF 1265 AROMATICS PROJECT, SHUAIBA KUWAIT Prepared by Raju Salvi (QC Inspector – Mechanical

Upload: raju-salvi

Post on 14-Apr-2017

322 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.1

PRESENTATION ON FIRED HEATERS OF 1265 AROMATICS

PROJECT, SHUAIBA KUWAIT Prepared by Raju Salvi (QC Inspector – Mechanical Equipments)

Page 2: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.2

FIRED HEATER OR FURNACE

Device for transferring heat from the combustion of a hydrocarbon

fuel into a process stream or streams requiring heating or

vaporization

Page 3: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.3

General Arrangement & Layout Of Heater

Convection

General Arrangement

Layout

Construction phases

• Radiant refractory on ground• Foundation check• Radiant section with coils• Convection section with coils• External crossovers• Hydrostatic test• Soot blower • Stack• FD & ID fan • Air preheater • Steam coil air preheater• Burners• Air duct• Flue gas duct• Platforms• Insulation• Fireproofing• Painting

Page 4: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.4

Types of Heaters

1. NATURAL DRAFT HEATER

2. BALANCED DRAFT HEATER

• Radiant • Convection (optional) • Stack

• Radiant • Convection • Stack• Forced Draft Fan• Air duct• Induced Draft Fan

Page 5: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.5

Types of Heaters

4. INDUCED DRAFT HEATER

3. FORCED DRAFT HEATER

• Radiant • Convection • Stack• Forced Draft Fan

• Radiant • Convection • Stack• Induced Draft Fan

Page 6: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.6

Natural Draft Heaters At Aromatics

KAR-F-21005 CHARGE HEATER

KAR-F-18064 HEAVY AROMATICS COLUMN

REBOILER

KAR-F-24007CHARGE HEATER

Cylindrical Heater With Vertical Coil

Box Heater With Arbor Coil

Page 7: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.7

Balanced Draft Heaters At Aromatics

KAR-F-18034 XYLENE COLUMN REBOILER

KAR-F-18035 XYLENE COLUMN REBOILER

KAR-F-21034 DEHEPTANIZER REBOILER

Twin Cylindrical Heater

With Vertical Coil

Cylindrical Heater With Vertical Coil

Page 8: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.8

Typical Radiant Coil Arrangement in Heaters

KAR-F-21005 - Charge Heater

KAR-F-18034 / 18035 - Xylene Column Reboiler

KAR-F-21034 - Dehepatnizer

KAR-F-18064 - Heavy Aromatics Column Reboiler

KAR-F-24007 - Charge Heater

Page 9: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.9

Typical Radiant Coil Arrangement in Heaters

Page 10: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.10

Typical Burner Arrangements In Heaters

HEATERS OF AROMATICS PROJECT

Page 11: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.11

Reference Procedural documents• ITP

• Radiant section erection instructions • Erection instructions APH etc• Corrosion inhibitor application • Refractory Application Procedure• Applicable WPS PQRs NDE PWHT• API 560 • ASME B31.3

Page 12: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.12

Refractory Of Radiant Modules VARIOUS TEMPERATURE CONTROLS Metal < 32°C Storage < 25°C Water 5 - 32°C Dry mix < 32°C Wet mix < 25°C

CURING & DRYING Water soaked gunny bags to be kept on

refractory lining followed by sprinkling of water at every ½ an hour time interval or whenever the refractory surface can be felt warm / hot by keeping palm on it

Curing period – 24 hours Natural air drying for next 48 hours Refractory lined panels can be shifted

after 72 hours of refractory application WOODEN FORM WORK Horizontal -1.5 x 1.5 m max (Area

<3 m2) Vertical -1.5 x .5 m H Application of grease HUMIDIFYING METHODS

(Humidifying 1st layer prior to starting 2nd layer)

Sprinkling water Kaoseal Plastic sheet

POURING & TROWELLING Thickness to be built up In single

layer Finishing by wood & not by trowel

Page 13: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.13

Refractory Of Radiant Modules CRACKS CRITERIA

> 3 mm to be repaired > 1.5 mm spaced at < 300 mm to be repaired > 1.5 mm & < 3 mm, vendor’s decision considering various factors: General quality of lining Zone & length of crack Conditions under which cracks 1st became apparent < 1.5 unsticking out of lining from

casing to be repaired

HAMMER TEST CRITERIA

Hammer test on curing completion Weight of hammer – 450 gms / 1

pound 610 x 610 mm grid area for arch 920 x 920 mm grid area for walls Hollow areas of 150 x 150 mm to be

repaired

REPAIR CRITERIA

Stripping repair area down to casing Edge of stripped area like dovetail profile Smaller dimension of dovetail profile on lining surface

side Vibration apparatus not to be used Minimum area 300 x 300 mm to be removed for

repair work Minimum 3 anchors to be exposed

Page 14: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.14

Construction Phase

Sample Size in mm100 x 100 x

100 100 x 100 x 100250 x 100 x

100

 

Mixing Water

%

§ Apparent Density

± 15 %Kg / mc

§ Compressive Strength

(- 20 %)N / mm2

Linear

Shrinkage mm

Refractory PC 105 8 7 - 9 3 7 0 8 1 . 5 - 0 . 3%

Refractory PC 124 I 3 5 – 3 9 9 8 0 3 . 5 - 0 . 2 5%

Preinstallation Test Of Insulating Castable Refractory:

Samples preferably to be casted in metal case

SERVICE TEMPERATURE OF REFRACTORY MATERIAL : 1100°C

§ Samples are tested after drying in oven at 110°C

Page 15: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.15

Refractory Of Radiant Modules

Surface Preparation

Anchor orientation & tectyl application

Inspection ActivitiesSurface free from oil grease & mill scales.

Inspection Activities• Anchor type • Anchor material SS 304 / 310 (Color coding to avoid intermixing)• Anchor dimensions & orientation• Anchor tightness• Temperature 10 - 32°C• DFT / WFT – 250 / 100

Radiant floor panel

Radiant module 2

Problems faced• Surface found rusting at inspection time • KN & TCM mutually agreed for inspection as & when it is ready against witness point as per ITP

Problems faced• Shop welded nuts breaking on anchor tightness• Re-welding nuts • 250 micron DFT not achievable with one coat• TCM advised 100 WFT

Page 16: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.16

Refractory Of Radiant Modules

Radiant module 2 & 3

Radiant module 4

Problems faced

• Even though all the three methods of humidifying refractory used, still cracks observed in the second layer of refractory application

• It was summer season so water in the second layer of refractory was getting evaporated faster as well as traveling into 1st layer leading to cracks

• Winter season arrived so cracks were under control as 1st layer of refractory was humidified by sprinkling of water

Page 17: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.17

After application of refractory layers

Progressive sampling testingof refractory per 20 tonnes

Radiant module 2 with single layer refractoryPC 105

Radiant module 2 with double layer refractoryPC 105 & PC 124 I

Page 18: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.18

REFRACTORY DATAHEATER ITEM

THK mm PC 105

PC 124 I

PC 105

PC 124 I

KAR-F-18034 A

M-I 75 75 1.55 2.3

M-II 75 75 10.235 14.98

M-III 75 75 10.33 14.95

M-IV 75 75 0.75 2.175

ROOF 75 125 3.45 7.78

CON BRID 75 125 2.78 6.56

FLOOR   200   7.95

  Tons  29.095 56.695

HEATER ITEMTHK mm PC

105PC

124 IPC 105

PC 124 I

KAR-F-18034 B

M-I 75 75 1.52 2.35

M-II 75 75 10.36 14.88

M-III 75 75 10.54 14.98

M-IV 75 75 0.745 2.405

ROOF 75 125 3.48 7.825

FLOOR   200   7.95

   Tons 26.645 50.39

Page 19: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.19

REFRACTORY DATAHEATER ITEM

THK mm PC 105

PC 124 I

PC 105

PC 124 I

KAR-F-21034

M-I 75 75   2.85

M-II 75 75 2 26.695

M-III 75 75 13.36 25.32

M-IV 75 75 13.45 12

ROOF 110 90 8.52 10

FLOOR 75 125 4.72 8.395

   Tons 42.05 85.26

HEATER ITEM

THK mm PC 105

PC 124 I

PC 105

PC 124 I

KAR-F-21005

M-I SW 75 75 1.78 2.405

M-I EW 125 75 0.77 0.93

M-II SW 75 75 11.2 15.965

M-II EW 125 75 4.455 6.43

M-III SW 75 75 14.45 20.88

M-III EW 125 75 5.8 6.72

ROOF 125 75 9.82 8.67

FLOOR 160 75 5.9 4

   Tons 54.175 66

Page 20: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.20

REFRACTORY DATA

HEATER ITEMTHK mm PC

105PC

124 I

PC 105

PC 124 I

KAR-F-24007 FLOOR 120 75 1.04 1

KAR-F-18064 FLOOR   215   3.35

Refractory PC 105

209 TONS

Refractory PC 124 I

367.925 TONS

TOTAL CONSUMPTION

Page 21: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.21

Radiant Module 1& Floor

Radiant Module 1 – 4 nos.

Radiant Floor Panels & Module 2

Inspection ActivitiesFoundation check, orientation, elevation, leveling, verticality, joint fit up, bolting

•Inspection ActivitiesOrientation, elevation, floor panel to panel joint fit up, Weld visual of: Gusset plates Floor panel to panel joints

Problem faced• Gusset plates of floor support columns mismatching

• Removed & re-welded gusset plates

Problem faced• Base plate’s holes mismatching

• Holes enlarged by machining • Joint inspection at the time of pouring concrete

Page 22: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.22

Radiant Module 2 & 3

Radiant Module 2 – 10 nos.Inspection Activities

Orientation, elevation, leveling, verticality, joint fit up, boltingWeld visual of inside seal welding of bolted joints including module 1

Radiant Module 3 – 10 nos.

Problem faced• Gap of 5 to 20 mm observed in the joint fit up • Shim provided• Coil support holes not as per drawing• Drilled new holes with additional stiffening plates

Splice joint

Interlocking arrangement to be considered while erecting radiant

panels

Page 23: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.23

Splice Joints Of Radiant M 1, 2 & 3

Inspection Activities

Refractory of vertical & horizontal field splice bolted joints of radiant module 1 2 3

• Surface preparation

• Anchor fixing & orientation

• Tectyl application DFT

• Single layer refractory

• Visual inspection & hammer test

Page 24: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.24

Radiant Coils

ASTM A297 Gr HK to ASTM Gr 304Jump overs to be welded at site

Page 25: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.25

Radiant Coils

Radiant coils – 4 passes

Inspection Activities• Orientation • Elevation & leveling • Verticality • Freeness in tube guides, resting on • Coils resting on supports without any gap• Fit up, weld visual, RT – 100%• Weld visual of bar & pin• Weld visual of socket & tube guide• External coil supports bolting & weld visual Problem faced• Gap of maximum 25+ mm observed between bottom of return bend elbow of coil & coil support top

• Coil shop weld joints were cut & length reduced of coil to rest properly on coil support

Page 26: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.26

Radiant Module 4

• Orientation

• Elevation & leveling

• Joint fit up & bolting

• Weld visual of inside seal welding of bolted joints

Inspection Activities

Problem faced• Holes mismatching between M3 & M4 • Preassembly of M4 carried out to assess: a) Field splice joint’s b) Correct pitch of holes

Page 27: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.27

Splice Joints Of Radiant M 4 Inspection Activities

Refractory of vertical & horizontal field splice bolted joints of radiant module 4

• Surface preparation

• Anchor fixing & orientation

• Tectyl application DFT

• Single layer refractory

• Visual inspection & hammer test

Page 28: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.28

Convection section

Convection Bottom Module (54 tons) Convection Middle Module (89.5 tons)

Convection Top Module (63 tons)

Inspection activities

• Orientation

• Elevation & leveling

• Verticality

• Joint fit up & bolting

Page 29: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.29

Convection coils

Jump over to be installed & welded at site after removal of convection header boxes

Page 30: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.30

External Crossovers

Inspection Activities For Convection Coils & External CrossoversLeveling, fit up, weld visual, RT,

Page 31: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.31

External Crossover Supports

Inspection Activities:• Gap between guide & shoe• Weld visual of support structure

Page 32: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.32

QUANTITY OF FIELD WELD COIL JOINTS HEATER   COIL MATERIAL SPECIFICATION RADIANT CONVECTION CROSSOVER

   

Size(OD x Thk) Inch X mm Qty

Size(OD x Thk) Inch X mm Qty

Size(OD x Thk) Inch X mm Qty

18034 A ASTM 106 Gr B 8 x 8.18 56 6 x 7.11 48 6 x 7.11 27

            8 x 8.18 4

               

18034 B ASTM 106 Gr B 8 x 8.18 56 6 x 7.11 48 6 x 7.11 25

            8 x 8.18 4

               

18035 A ASTM 106 Gr B 8 x 8.18 56 6 x 7.11 48 6 x 7.11 27

            8 x 8.18 4

               

18035 B ASTM 106 Gr B 8 x 8.18 56 6 x 7.11 48 6 x 7.11 25

            8 x 8.18 4

               

18064 ASTM 106 Gr B         5 x 6.55 12

               

               

21034 ASTM 106 Gr B 8 x 8.18 36 6 x 7.11 18 6 x 7.11 36

               

               

21005 ASTM 106 Gr B     5 x 6.55 24    

  SA 335 Gr P11 TO P22 4 x 6.02 120        

  SA 335 Gr P11 42 x 16 2        

               

24007 ASTM A 335 Gr P9         6 x 10.97 2

            8 x 12.7 3

Page 33: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.33

DISSIMILAR WELDINGSERIAL HEATER MATERIAL 1 MATERIAL 2

1 KAR-F-18034 A / BKAR-F-18035 A / B

KAR-F-21034

ASTM A 106 Gr B SS TP 304 / 310 / 316

2 KAR-F-18034 A / BKAR-F-18035 A / B

ASTM A 297 Gr HK ASTM A 182 Gr 304

3 KAR-F-24007 ASTM A 335 Gr P9 SS TP 316 L

KAR-F-18034 A / BKAR-F-18035 A / B

KAR-F-21034

ASTM A 297 Gr HK ASTM A 297 Gr HK

Page 34: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.34

Hydrostatic Test Schematic Sketch

Test Pack Activities• Test pack documentation• Approval of test pack• Hydrostatic test

Design Pressure / Test Pressure (Kg/cm2)KAR-F-18034 A / B, KAR-F-18035 A / B - 16 / 31.8KAR-F-21034, KAR-F-21005 - 17 / 33.8 KAR-F-18064 - 10.5 / 20.9KAR-F-24007 - 40 / 79.1

Page 35: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.35

Floor Refractory & BurnersInspection Activities• Surface preparation • DFT of tectyl • Visual inspection

• Hammer test

Floor of KAR-F-18034 / 35 Floor of KAR-F-24007

HEATER PC 105 PC 124 I FIRE BRICK

KAR - F -18034 / 35

0 200 65

KAR - F -18064

0 215 65

KAR - F -21005

160 75 65

KAR - F -21034

75 125 65

KAR - F -24007

100 75 65

Detail of refractory thickness used in floorGA of floor refractory

Page 36: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.36

Stack

Stack Support Structure

Stack Module 1 2 3 (63, 15, 23 tons)

Stack Module 4 5 & Off take duct (24.5 tons)

Inspection Activities

Orientation, elevation, leveling, verticality Joint fit up & bolting

Problem faced• Stack refractory damaged during transportation

• Repair identified & repaired

Page 37: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.37

Auxiliaries

Soot Blowers

Forced Draft Fan

APH

Induced Draft Fan, APH, SAPH

Page 38: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.38

Air Duct (FD Fan To Plenum)Bypass air

Plan View

Elevation

71 0C

227

0 C

Page 39: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.39

Air Duct (Plenum To Burners)

Plan View

Elevation

Page 40: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.40

Flue Gas Duct

Stack to APH

ID F

an t

o St

ack

Plan

Elevation

Elevation

APH to ID Fan

318 0C

179 0C

Page 41: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.41

Flue

Gas

Duc

tID

Fan

to

Stac

k

Flue

Gas

Duc

tSt

ack

to A

PH

Flue Gas Duct APH to ID Fan

Stack

ID Fan

APH

Flue Gas Duct

Air Duct

APH Bypass

FD Fan

Assembled Heater

Page 42: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.42

Other Jobs Insulation From steam coil air preheater upto

burner duct including air heater bypass duct

Fireproofing Main radiant structure columns & Radiant floor structure columns Painting

Page 43: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.43

PROCESS FLOW DIAGRAMS

KAR-F-18034 / 18035

KAR-F-24007

Page 44: Heaters

AWI 106 Att. 8 Rev. 1 22 Sep. 2007

Date/ Rev.44

PROCESS FLOW DIAGRAMS

KAR-F-18064

KAR-F-21005 &

KAR-F-21034