HAWC OBSERVATORYPRELIMINARY COST ANALYSISPRELIMINARY COST SUMMARY
PRE-FAB METAL BUILDINGITEM UNITS UNIT COST COST NOTES
Kirby Building
Lump Sum $1,545,510 $1,545,510
$16.76/
m2
Braemar #1
Lump Sum $786,032 $786,032 $12.73/
m2
Braemer #2
Lump Sum $1,087,425 $1,087,425
$11.35/
m2
Erection Lump Sum $1,328,000 $1,328,000
Foundation Excavation
1,591 m3 $7/m3 $11,137 Grade beam
Concrete Foundation
1,591 m3 $109/m3 $173,419 All inclusive
Curtains 15,46o m2 $77.62/m2 $1,200,000
30 mil
Column Boots
126 Each $250/Boot $ 31,500 30 mil
TOTAL COST
$3,831,481
Braemar #2
FLOATING COVERITEM UNITS UNIT COST COST NOTES
60 mil tension floating cover
26,650 m2 $78.80/m2 $2,100,000 60 mil 5 plyw/ tiedown
Curtains 15,460 m2 $64.68/m2 $1,000,000 30 mil
Foundation Excavation
512 m3 $7/m3 $3,586 Grade beam
Concrete Foundation
512 m3$109/m3 $55,808 Grade beam
Faraday Cage
Lump Sum $98,000 $98,000 14 lines
TOTAL COST
$3,257,394 Layfield cost
FLOATING COVER - BASISQuote from LayfieldFabric is 60 mil/5 Ply HypalonCover can be floated at 2m water depthCurtains attached to the bouyed tension cablesNon-corrosive cables at 3m+/-attached to grade
beamsDetailed to provide light-tight constructionHatch ports for access & maintenance from topsideRigid enough to support personnelROV available to support maintenance and
servicing
LINED PONDITEM UNITS UNIT
COSTCOST NOTES
Excavation 107,712 cu. meters
$ 3.73/cu. meter
$401,766
Subsurface Drain
4056 linear meters
$ 24.64/ meter
$107,000 $99,940 lines$7,057 EB&C
Embankment
24,868 cu. meters
$ 5.21/cu. meter
$129,562
Liner 29,448 sq. meters
$ 6.52/sq. meter
$192,000 30 ml thick
Bedding Material
8,889 cu. meters
$0.92/cu. meter
$8,178 1 foot thick
Spoil MaterialDisposal
82,844 cu. meters
$4.02/cu. meter
$333,033 ½ mile truck & drop
TOTAL COST
$ 1,171,539
COST SUMMARYITEM ITEM
POND $1,171,539 POND $1,171,539
METAL BUILDING
$3,831,481 FLOATING COVER
$3,257,394
SUBTOTALPOND/BUILDING
$5,003,020 SUBTOTALPOND/FLOAT COVR
$4,428,933