Haringey Clinical Commissioning Group Governing Body Meeting Thursday, 13 September 2018 2.00pm 4.30pm Cypriot Centre Earlham Grove London N22 5HJ Item Title Lead Action Papers Page No. 1. INTRODUCTION 1.1 Welcome and Apologies Chair To note Oral - 1.2 Declarations of Interest Register Chair To note 1.2 3 1.3 Declarations of Gifts and Hospitality Chair To note Oral l - 1.4 Draft minutes of previous Governing Body meetings on 12 July 2018 Chair For approval 1.4 12 1.5 Action Log Chair For approval 1.5 30 1.6 Questions from the public Chair Oral - 2. OVERVIEW REPORTS 2.1 Accountable Officer’s Report Accountable Officer To note 2.1 30 3. DISCUSSION 3.1 Whittington Health Community Services Chief Executive, Whittington Health For discussion Present- ation - 4. CORPORATE BUSINESS AND BUSINESS CASES 4.1 STP Programme Update NCL Director of Strategy For discussion 4.1 33 4.2 System Intentions for 2019/20: Haringey CCG NCL Director of Performance, Planning and Primary Care For discussion 4.2 54 5. FINANCE AND PERFORMANCE 5.1 Finance Report Chief Finance Officer For discussion 5.1 63 5.2 Performance Report Director of Planning, Performance and Delivery For discussion 5.2 78 6. GOVERNANCE

Upload: others

Post on 18-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey Clinical Commissioning Group Governing Body Meeting

Thursday, 13 September 2018 2.00pm – 4.30pm Cypriot Centre

Earlham Grove

London N22 5HJ

Item Title Lead Action Papers Page No. 1. INTRODUCTION

1.1 Welcome and Apologies

Chair To note Oral -

1.2 Declarations of Interest Register

Chair To note 1.2 3

1.3 Declarations of Gifts and Hospitality

Chair To note Oral l -

1.4 Draft minutes of previous Governing Body meetings on 12 July 2018

Chair For approval

1.4 12

1.5 Action Log

Chair For approval

1.5 30

1.6 Questions from the public

Chair Oral -

2. OVERVIEW REPORTS

2.1 Accountable Officer’s Report Accountable Officer

To note 2.1 30

3. DISCUSSION

3.1 Whittington Health Community Services

Chief Executive, Whittington

Health

For discussion

Present-ation

-

4. CORPORATE BUSINESS AND BUSINESS CASES

4.1 STP Programme Update

NCL Director of Strategy

For discussion

4.1 33

4.2 System Intentions for 2019/20: Haringey CCG

NCL Director of Performance, Planning and Primary Care

For discussion

4.2 54

5. FINANCE AND PERFORMANCE

5.1 Finance Report

Chief Finance Officer

For discussion

5.1 63

5.2

Performance Report

Director of Planning,

Performance and Delivery

For discussion

5.2 78

6. GOVERNANCE

Page 2: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

6.1 6.1.1 6.1.2 6.1.3 6.1.4

Board Assurance Framework Haringey BAF Risks available here NCL Risk Register (August 2018) available here NCL Primary Care Committee in Common Risk Register (August 2018) available here NCL Joint Commissioning Committee Risk Register (August 2018) available here

Director of Planning,

Performance and Delivery

For discussion

To note

To note

To note

To note

6.1 113

7. ITEMS FOR INFORMATION AND ASSURANCE

7.1 Minutes of the Haringey and Islington CCGs Quality and Performance Committee in Common Meeting on 25 July 2018 – available here

Chair of Haringey and

Islington CCGs Quality and

Performance Committee in

Common

To note

7.2 Minutes of the Haringey & Islington CCGs Strategy & Finance Committee in Common meeting on 28 June 2018 – available here

Chair of Haringey and

Islington CCGs Strategy and

Finance Committee in

Common

To note

7.3 Minutes of the Haringey CCG Clinical Cabinet meeting on 5 July 2018 - available here

Chair of Haringey CCG

Clinical Cabinet

To note

7.4 Minutes of the NCL Joint Commissioning Committee Meeting on 7 June 2018 – available here Papers of the NCL Joint Commissioning Committee Meeting on 2 August 2018 – available here

Chair of NCL Joint

Commissioning Committee

To note

7.5 Minutes of the NCL Primary Care Commissioning Committee Meeting on 21 June 2018 – available here

Chair of NCL Primary Care

Commissioning Committee

To note

8. ANY OTHER BUSINESS

9. DATE OF NEXT MEETING - Thursday 15 November 2018

REGISTER OF INTERESTS

A register of members’ interests is available for viewing by the public. The register will be available at the meeting or during working hours within the Haringey CCG Office,

River Park House, 225 High Rd, Wood Green, London N22 8HQ.

Page 3: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey Clinical Commissioning Group Governing Body Meeting 13 September 2018

Report Title Declaration of Interest Register

Date of report 6 September 2018

Agenda Item

1.2

Lead Director /

Manager

Peter Christian Chair, Haringey CCG

Tel/Email

GB Member Sponsor

Peter Christian Chair, Haringey CCG

Report Author

Steve Beeho, Board Secretary Tel/Email [email protected]

Report Summary

Governing Body Members and attendees are asked to review the agenda and consider whether any of the topics might present a conflict of interest, whether those interests are already included within the Register of Interest, or need to be considered for the first time due to the specific subject matter of the agenda item. A conflict of interest would arise if decisions or recommendations made by the Governing Body or its Committees could be perceived to advantage the individual holding the interest, their family, or their workplace or business interests. Such advantage might be financial or in another form, such as the ability to exert undue influence. Any such interests should be declared either before or during the meeting so that they can be managed appropriately. Effective handling of conflicts of interest is crucial to give confidence to patients, tax payers, healthcare providers and Parliament that CCG commissioning decisions are robust, fair and transparent and offer value for money. If attendees are unsure of whether or not individual interests represent a conflict, they should be declared anyway.

Recommendation The Governing Body is asked to NOTE the Register of Interests and advise the meeting / Board Secretary of any changes.

Identified Risks

and Risk

Management

Actions

The risk of failing to declare an interest may affect the validity of a decision / discussion made at this meeting and could potentially result in reputational and financial costs against the CCG.

Conflicts of Interest

The purpose of the Register is to list interests, perceived and actual, of members that may relate to the meeting.

Page 4: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Resource

Implications

Not applicable.

Engagement

Not applicable.

Equality Impact

Analysis

Not applicable.

Report History and

Key Decisions

The Register of Interests is a standing item presented to every Governing Body Meeting.

Next Steps The Register of Interests is reviewed monthly.

Appendices

The Register of Interests.

Page 5: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey CCG Governing Body Declarations 6.9.18

From To Updated

Fin

an

cia

l In

tere

sts

No

n-F

inan

cia

l

Pro

fessio

nal

Inte

rests

No

n-F

inan

cia

l P

ers

on

al

Inte

rests

Morris House Group

Practice X Direct Practice Partner 17.8.17 29.6.18

The Morris House Group

Practice is a member of

Federated4Health, the

pan-Haringey federation

of GP practices.X Direct Practice Partner 17.8.17 29.6.18

The Morris House Group

Practice provides

anticoagulant care to

Haringey residents under

a contract with the CCG.

X Direct Practice Partner 17.8.17 29.6.18

The Morris House Group

Practice premises are

also used for the

provision of physiotherapy

services by Premier

Medical, who are charged

a nominal amount to

cover electricity and gas

etc.

X Direct Practice Partner 17.8.17 29.6.18

Local Medical Committee

(LMC) X Direct GP representative 17.8.17 29.6.18

NHS England

X Direct GP Trainer 17.8.17 29.6.18

Italian Medical Charity

X Direct Trustee 17.8.17 29.6.18

Fernlea Surgery X Direct Practice Partner 15.3.18 23.04.18

Fernlea Surgery is a

member of

Federated4Health, the

pan-Haringey federation

of GP practices.

X

Direct

Practice Partner 15.3.18 23.04.18

Fernlea Surgery premises

are also used for the

provision of MSK services

by Premier Health and

Sport Therapy Ltd, who

are charged a nominal

amount to cover

electricity and gas etc.

X Practice Partner 15.3.18 23.04.18

Talawa Fostering X Direct Medical adviser 15.3.18 23.04.18

Jewish Care Direct clinical governance committee

member15.3.18 23.04.18

New North London

synagogue X Direct Organiser of doctors' rota. 15.3.18 23.04.18

NHS England (London) X

Direct Senior clinical adviser 15.3.18 23.04.18

Central London

Community Healthcare

NHS Trust.

Indirect (wife)

Community paediatric

physiotherapist15.3.18 23.04.18

Action taken to mitigate risk

Nature of Interest

Declared Interest-

(Name of the

organisation and nature

of business)

Name

Current position (s) held-

i.e. Governing Body,

Member practice,

Employee or other

Date of Interest

Type of Interest

Is the interest

direct or

indirect?

Gino Amato

GP Partner, Morris House

Group Practice

North East GP Member,

Governing Body

Member, Governing Body

Member, Clinical Cabinet

Planned Care Lead,

Governing Body

Member, NMUH

Clinical Quality Review

Group

Simon Caplan

GP Partner, Fernlea

Surgery

North East

GP Member, Governing

Body

Member, Clinical Cabinet

Chair, A&E Delivery Board

(advised this had ceased

on 30.8.17)

Chair, Medicines

Management Committee

Page 6: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Muswell Hill Practice X Direct Practice Partner 15.3.18 25.04.18

Muswell Hill Practice is a

member of

Federated4Health, the

pan-Haringey federation

of GP practices.

X Direct Practice Partner 15.3.18 25.04.18

Muswell Hill Practice is a

member of WISH -

Urgent Care Centre

provider at Whittington

Hospital.

X Direct Practice Partner 15.3.18 25.04.18

Muswell Hill Practice

provides anticoagulant

care to Haringey residents

under a contract with the

CCG.

X Direct Practice Partner 15.3.18 25.04.18

The Hospital Saturday

Fund - a charity which

gives money to health

related issues.

X Direct Member 15.3.18 25.04.18

The Hospital Saturday

Fund - a charity which

gives money to health

related issues.

Indirect (wife) Patron 15.3.18 25.04.18

The Lost Chord Charity -

organises interactive

musical sessions for

people with dementia in

residential homes.

Indirect (wife) Patron 15.3.18 25.04.18

Federated4Health, the

pan-Haringey federation

of GP Practices

Indirect (Practice

manager ) Chair 15.3.18 25.04.18

Haringey Health

Connected, the federation

of west Haringey GP

practices

Indirect (Practice

manager )

Finance Manager 15.3.18 25.04.18

Vale Practice X Direct Practice Partner 15.3.18 27.04.18

Vale Practice is a

member of

Federated4Health, the

pan-Haringey federation

of GP practices.X Direct Practice Partner 15.3.18 27.04.18

The Vale Practice is a

member of WISH, the

Urgent Care Centre

Provider at Whittington

Health.

X Direct 15.3.18 27.04.18

WISH, the Urgent Care

Centre Provider at

Whittington Health.

XDirect

Director 15.3.18 27.04.18

NHS England X Direct GP appraiser 15.3.18 27.04.18

Frater Clinic (a private

clinic) X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Vale Practice X Indirect Husband is a practice partner. 1.3.18 27.04.18

Peter Christian

CCG Chair, West GP Lead

GP Partner, Muswell Hill

Practice

Member, Strategy and

Finance Committee

Member, Clinical Cabinet

Member, Health and

Wellbeing Board

Member, Collaboration

Board

Member, Remuneration

Committee

Member, STP Clinical

Cabinet and

Transformation Board

Dina Dhorajiwala

GP Partner, Vale Practice

West GP Member,

Governing Body

Member, Strategy and

Finance Committee

Member, Clinical Cabinet

Primary Care Lead,

Governing Body

Haringey Primary Care

Lead, Co-Commissioning

Committee, NCL NHS

Member, Primary Care

Steering Group

Member, Primary Care

Transformation Group

Member, Health and

Wellbeing Board

Page 7: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Simon Goodwin Chief Finance OfficerEast London Foundation

Trust X Indirect

Wife is Senior Manager at the

Trust 14.6.17 23.04.18

Islington CCG X

Chief Operating Officer

Member, Governing Body

Member, Finance and

Performance Committee

21.6.17 23.04.18

Sidney Estates Tenants

and Residents

Association,

Tower Hamlets

X Chair 21.6.17 23.04.18

Will Maimaris Interim Director of Public

Health, Haringey Council No interests to declare. 30.8.18

Queenswood Practice X Direct Practice Partner 15.3.18 30.04.18

Queenswood Practice is a

member of WISH, the

Urgent Care Provider at

Whittington Hospital. X Direct Practice Partner 15.3.18 30.04.18

Queenswood Medical

Practice takes part in

various funded research

projects, including

PANDA, Kare and North

Thames CRN Primary

Care Team X Direct Practice Partner 15.3.18 30.04.18

Catherine Herman

Lay Member, Governing

Body

Chair, Primary Care Co-

Commissioning

Committee, NCL NHS

Chair, Investment

Committee

Chair, Communications

and Engagement Sub-

Committee Member,

Remuneration Committee

Member, Audit Committee

Member, Quality and

Performance Committee

Member, Health and

Wellbeing Board

Member, Primary Care

Transformation Group

Member, Organisational

Development Group

Chair, Engagement

Network

No interests to declare. 15.3.18 23.4.18

Tony Hoolaghan

Chief Operating Officer

Member, Governing Body

Member, Strategy and

Finance Committee

David Masters

GP Partner, Queenswood

Practice

West Member, Governing

Body

Clinical Lead for Children

(including CAMHS and

child safeguarding)

Member, Investment

Committee

Chair, Safeguarding

Assurance meeting

Member, Clinical Cabinet

Page 8: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Queenswood Practice is a

member of

Federated4Health, the

pan-Haringey federation

of GP practices.X Direct Practice Partner 15.3.18

30.04.18

Queenswood Practice

arranges education

activities with our local

hospital teams, including

the Whittinghton Hospital

and Highgate Hospital. X Direct Practice Partner 15.3.18 30.04.18

Tavistock Clinic X Direct Systemic Therapist (one day a

week) 15.3.18 30.04.18

NHS England

(Whittington Health

scheme)

X Direct GP trainer 2.3.18 30.04.18

Hornsey Heath Care Ltd

that holds the lease at

Hornsey Central Health

Care

X Direct Director 30.04.18

Arcadian Gardens

X Direct Practice Partner 6.3.18 27.6.18

Arcadian Gardens is a

member of

Federated4Health, the

pan-Haringey federation

of GP practices.

X Direct Practice Partner 6.3.18 27.6.18

Central Haringey CHIN X Direct Joint Clinical Lead 6.3.18 27.6.18

Muswell Hill Practice

(CCG member practice)X Direct Registered patient 10.5.17 23.04.18

Royal Borough of

Kensington and Chelsea

Local Authority

X Indirect

Husband is Programme

Manager for Partners in

Practice, a social work training

programme.

15.5.18

Lawrence House Surgery X Direct Practice Partner 15.3.18 25.04.18

Lawrence House Surgery

is a member of

Federated4Health, the

pan-Haringey federation

of GP practices.

X Direct Practice Partner 15.3.18 25.04.18

Lawrence House Surgery

has merged with Dowsett

Rd Surgery and

Broadwater Farm Health

Centre.

X Direct Practice Partner 15.3.18 25.04.18

Lawrence House Surgery

also runs the Tottenham

Hale practice.X Direct Practice Partner 15.3.18 25.04.18

NHS England X Direct GP Trainer: Enfield and

Haringey GP Scheme. 15.3.18 25.04.18

NHS England X Direct GP appraiser 15.3.18 25.04.18

Whittington Health Indirect (wife) Consultant (based at St Ann's

Hospital) 15.3.18 25.04.18

David Masters

GP Partner, Queenswood

Practice

West Member, Governing

Body

Clinical Lead for Children

(including CAMHS and

child safeguarding)

Member, Investment

Committee

Chair, Safeguarding

Assurance meeting

Member, Clinical Cabinet

Sheena Patel

GP Partner, Arcadian

Gardens Surgery

Clinical Director, Central

Haringey,

Governing Body

Member, Governing Body

Member, Clinical Cabinet

Women’s Health Lead,

Governing Body

Member, QIPP Delivery

Group

Member, Primary Care

Steering Group

Helen Pettersen Accountable Officer

John Rohan

CCG Deputy Clinical Chair

North East GP Lead, CCG

Governing Body

GP Partner, Lawrence

House Surgery

Member, Governing Body

Chair, Strategy and

Finance Committee

Chair, Clinical Cabinet

Member, Primary Care

Steering Group

Member, QIPP Delivery

Group

Finance, Estates and

QIPP Lead, Governing

Body

Page 9: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

JS Medical Practice X Direct Advanced Nurse Practitioner 19.3.18 24.04.18

JS Medical Practice is a

member of

Federated4Health, the

pan-Haringey federation

of GP practices.

X Direct Advanced Nurse Practitioner 19.3.18 24.04.18

Islington COPD Steering

Group X Direct Attending Member 5.3.18 24.04.18

Camden, Islington and

Haringey Responsible

Prescribing Group

X Direct Attending Member 5.3.18 24.04.18

Money Advice Trust

(a national debt advice

charity)

X Direct Chair 01.07.16 23.04.18

Enfield CCG X Direct Member, Audit Committee 1.0114 23.04.18

Bounds Green Group

Practice X Direct Practice Partner 19.3.18 23.04.18

Bounds Green Group

Practice is a member of

the pan-Haringey GP

Federation X Direct Practice Partner 19.3.18 23.04.18

Sharon Seber

Adam Sharples

Lay Member, Governing

Body

Chair, Audit Committee

Chair, Remuneration

Committee

Member, Strategy and

Finance Committee

Member, Finance and

Performance Partnership

Board

Chair, IFR Panel

Member, NCL Joint

Commissioning

Committee

Lionel Sherman

GP Partner, Bounds Green

Practice

Member, Governing Body

Member, Clinical Cabinet

Chair, CCG CHC Funding

Panel

POLCE lead, CCG

Learning Disabilities Lead,

CCG

Member, QIPP Delivery

Group

Primary Care Health

Professional Member,

South East, Governing

Body

Advanced Nurse

Practitioner, JS Medical

Practice

Member, Quality and

Performance Committee

Member, Clinical Cabinet

Nurse Member, NCL Joint

Commissioning

Committee

Healthy Life Expectancy

Clinical Lead, Governing

Body

Chair, Increasing Healthy

Life Expectancy Group

Member, Primary Care

Steering Group

Page 10: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Dowsett Rd Surgery X Direct Practice Partner 18.1.17 2.7.18

Lawrence House Surgery

and Dowsett Rd Surgery

are both members of

Federated4Health, the

pan-Haringey federation

of GP practices.

X Direct Practice Partner 18.1.17 2.7.18

Whittington Health X Indirect

Husband is currently on a

Fixed Term Contract as a

Locum Consultant in

Endocrinology.

1.3.18 2.7.18

Sarah Timms

Consultancy Ltd X Direct Sole Director 19.2.18 23.04.18

Vale Practice X Direct Registered patient 19.2.18 23.04.18

Whittington Health X Indirect Daughter is employed in an

administrative role.15.8.18

Public Voice CIC (a

Community Interest

Company)

X Direct Chair of the Board 19.2.18 23.04.18

Healthwatch Haringey X Direct Chair, Steering Committee 19.2.18 23.04.18

Bernie Grant Arts Centre

Partnership X Direct Director 19.2.18 23.04.18

Nurse Member, Governing

Body

Chair, Quality and

Performance Committee

Member, Clinical Cabinet

Member, Investment

Committee

Member, Remuneration

Committee

Member, Organisational

Development Group

Member, NMUH Clinical

Quality Review Group

Member, Eligibility Panel

Chair, Primary Care

Transformation Group

Member, QIPP Delivery

Group

Sarah Timms

Sharon Grant

Chair, Healthwatch

Haringey

Haringey CCG Governing

Body Observer (With

Speaking Rights)

Dai Tan

Sessional GP Member,

Governing Body

Salaried GP, Lawrence

House Surgery

Practice Partner, Dowsett

Rd Surgery

Member, Clinical Cabinet

Member, Primary Care

Steering Group

Chair, CEPN Steering

Group

Member, Organisational

Development Group

Education and Workforce

Lead, Governing Body

Clinical Lead for Diabetes

Non-voting Governing Body attendees

Page 11: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Independent Advisory

Group, Metropolitan

Police Haringey

X Direct Member 19.2.18 23.04.18

Parliamentary researcher X Direct

Part-time-employment as a

Parliamentary Researcher on

Health issues for backbench

Labour MP

19.2.18 23.04.18

Consumers Association

(Which?)X Direct

Trustee and Director

(Unremunerated)19.2.18 23.04.18

Clare Henderson

Attendee of CCG

Governing Body

Director of Commissioning

Member, Strategy and

Finance Committee

Member, Clinical Cabinet

No interests declared

N/A 5.3.18 23.04.18

Will Huxter

NCL Director of Strategy

Attend any of the five

CCGs in NCL GroupN/A 23.04.18

Rachel Lissauer

Director, Wellbeing

Partnership

Attendee of CCG

Governing Body

Vale School

X Direct Co-opted Governor 13.7.17 29.6.18

Sarah Mcilwaine

Programme Director, Care

Closer to Home, North

London Partners

Non-Voting GB Member

Hillside (Islington-based

mental health charity)

X Direct Trustee 19.10.17 23.04.18

Paul Sinden

NCL Director of

Performance and Acute

Commissioning

Attend NCL Primary Care

Commissioning in

Common

Attend any of the five

CCGs in NCL Group

No interests to declare.

23.04.18

Alex Smith

Director of Performance,

Planning and Delivery

Non-Voting GB member

Member of Strategy and

Finance Committee

No interests declared

N/A 20.9.17 30.4.18

Islington CCGX Direct 10.7.17 02.05.18

Central and North West

London NHS Foundation

Trust X Indirect Husband is Director of Nursing 10.7.17 02.05.18

Whittington Health X Indirect

Son is working in

administrative post via Temp

Bank.

15.8.18

Jennie Williams

Director of Quality and

Nursing

Non-voting member,

Governing Body

Member, Quality and

Performance Committee

Sharon Grant

Chair, Healthwatch

Haringey

Haringey CCG Governing

Body Observer (With

Speaking Rights)

Page 12: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Draft Minutes of the

Meeting of the Haringey Clinical Commissioning Group Governing Body

Thursday 12 July 2018 at 1.30pm Cypriot Centre, Earlham Grove

Dr Peter Christian Chair of Haringey CCG, West Lead

Helen Pettersen Accountable Officer, North Central London CCGs

Dr Gino Amato GP Governing Body Member, North East Dr Simon Caplan GP Governing Body Member, North East

Dr Dina Dhorajiwala GP Governing Body Member, West

Dr David Masters GP Governing Body Member, West

Dr Sheena Patel GP Governing Body Member, Central Lead

Dr John Rohan GP Governing Body Member, North East Lead

Dr Lionel Sherman GP Governing Body Member, Central

Dr Daijun Tan GP Governing Body Member, Sessional

Sharon Seber GP Governing Body Primary Care Health Professional Member, South East

Catherine Herman Lay Member, Haringey CCG

Adam Sharples Lay Member, Haringey CCG Sarah Timms Nurse Member, Haringey CCG

Tony Hoolaghan Chief Operating Officer, Haringey CCG

Simon Goodwin Chief Finance Officer, North Central London CCGs In attendance:

Anthony Browne Deputy Chief Finance Officer, Haringey CCG

Clare Henderson Director of Commissioning, Haringey CCG

Alex Smith Director of Planning, Performance and Delivery, Haringey CCG

Sharon Grant Chair, Healthwatch Haringey (Observer with speaking rights) Will Maimaris Consultant in Public Health, Haringey Council

Steve Beeho Board Secretary, Haringey CCG (minutes)

1. INTRODUCTION

1.1 Apologies for Absence

1.1.1 Apologies were received from Jeanelle De Gruchy. Will Maimaris was attending on her behalf. As Jeanelle would shortly be beginning her secondment in Manchester, the Chair thanked her in her absence for her contribution to the achievements of the CCG.

1.2 Declarations of Interest

1.2.1 There were no additional declarations of interest.

1.3 Declarations of Gifts and Hospitality

1.3.1 There were no additional declarations of gifts or hospitality.

Page 13: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

2

1.4 Chair’s Introduction and Opening Remarks

1.4.1 The Chair formally welcomed all present to the meeting. In addition he welcomed

Chantelle Fatania (Consultant in Medicine, Haringey Public Heath) and Lorraine Wiener (Head of Quality, Islington CCG), who were both attending the meeting as observers.

1.5 Minutes of the Previous Meeting

1.4.1 The Governing Body agreed the minutes of the Governing Body meeting held on 10 May 2018 as an accurate record, subject to section 5.2.2 being amended to state that Adam Sharples will be the Chair of the NCL Audit Committee in Common, rather than the Vice Chair.

1.6 Matters Arising

1.6.1 The Governing Body discussed the progress against the actions from the last meeting.

1.6.2 Alex Smith confirmed that an update on the Health Information Exchange would be brought to the Governing Body Seminar in October 2018.

1.6.3 Alex Smith noted that in addition to the update on the Memory Clinic included in the Performance and Quality Report, further details would also be presented at the next meeting of the Joint Commissioning Committee.

1.6.4 Adam Sharples observed that the breakdown of the charges incurred by the CCG for each private provider and the corresponding budget allocation highlighted the scale of the overspend at Highgate Hospital.

1.6.5 Assurance was given that the CCG is taking steps to control this. The CCG will be attending Clinical Quality Review Group (CQRG) meetings for this provider It was also

hoped that the MSK work would help to obviate the situation.

1.6.6 Sharon Grant confirmed that she had now received a response to the concerns raised

by the Reference Groups at the last Joint Partnership Board meeting, which she would now relay to the next meeting.

1.6.7 Jennie Williams noted the she had met with CCG colleagues to clarify the governance processes which other early e-referral adopters have in place, following on from the earlier concerns expressed about what happens when a patient referral is rejected. It was agreed that Jennie Williams would speak to Sheena Patel outside the meeting

about assurances the CCG has received regarding the volume of rejected referrals.

1.6.8 The Governing Body NOTED the action log.

1.6.9 ACTION 12/7-1: Jennie Williams to speak to Sheena Patel outside the meeting about

assurances the CCG has received regarding the volume of rejected referrals.

1.7 Questions From the Public

1.7.1 Ten questions had been submitted in advance from members of the public. The responses are appended to these minutes.

Page 14: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

3

1.7.2 In response to a follow-up comment about the lack of notice concerning a recent consultation, it was agreed that the CCG would look into how consultations can be promoted more effectively.

1.7.3 ACTION 12/7-2: Tony Hoolaghan to arrange for consultations to be promoted more

effectively.

2. Overview Reports

2.1 Accountable Officer’s Report

2.1.1 Helen Pettersen introduced the Accountable Officer’s Report, highlighting a number of

specific items.

2.1.2 Haringey CCG’s achievement of a ‘Green’ rating for its patient and local community

engagement under a new national assessment was welcomed, although it was recognised at the same time that further progress still needs to be made. Helen Pettersen thanked in particular the contribution made by the CCG’s partners (Public Voice, Healthwatch Haringey and the Bridge Renewal Trust) and the CCG’s

Communications and Engagement Team.

2.1.3 The CCG is currently awaiting NHS England’s approval of the business case to take

back in-house the contracting support function from NEL Commissioning Support Unit but in the meantime the necessary planning work was continuing.

2.1.4 Following feedback from the engagement on the draft Primary Care Strategy, the engagement period had been extended and the final version of the strategy would now be brought to the November Governing Body meeting for approval.

2.1.5 There was then a brief discussion of the recent meeting of the STP Advisory Committee. Peter Christian observed that it had highlighted tensions between different parties which he was optimistic would be worked through.

2.1.6 In response to potential concerns about accountability in the context of the STP, Helen Pettersen said that it was important to remember that no statutory bodies had delegated

authority to the STP and it therefore does not have a formal decision-making forum. She confirmed that it had been agreed that future agenda-setting needed to allow for more discussion of strategic issues and that future meetings of the Advisory Committee would be minuted and ultimately published on the North London Partners in Health and

Care website.

2.1.7 In response to a query from Adam Sharples, Tony Hoolaghan noted that the

membership of the two newly-created Committees in Common had initially been established on a ‘lift and shift’ basis, prior to further recalibration.

2.1.8 The Governing Body NOTED the Accountable Officer’s Report.

3. Business, Quality and Integrated Performance

3.1 Finance Report

Page 15: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

4

3.1.1 Anthony Browne provided an overview of the Finance Report, highlighting the following points:

At month 2 the CCG is reporting a £14k year to date deficit and forecasting to

plan at year end. Month 3 reporting, which had just closed, did not show a

significant variance from the Month 2 figures.

The CCG is already reporting significant pressure against its Continuing Care

spend – a more detailed report will be brought to a future meeting

The NMUH contract is projecting a material overspend – these figures will

require further examination across the patch

The 2018/19 QIPP target (£19.5m) is particularly challenging compared to

previous years, with the focus on avoiding admissions. There is currently a

financial risk around closing the £7.6m QIPP ‘gap’

A breakdown of the other financial risks and the mitigations identified to date

were set out in section 6.3.

3.1.2 Simon Goodwin then provided an overview of the summary of CCG financial variances

across NCL which would now be presented at future meetings. The summary showed £36m-£40m financial risk across NCL, with the level of Haringey risk sitting in the middle of the five CCGs.

3.1.3 He also noted that the increased NHS funding announced recently by Jeremy Hunt would be available from 2019/20, rather than the current financial year. He further cautioned that it was unclear at this stage how much of the increased funding would be

directed to CCGs and how the recent NHS staff pay awards will be funded.

3.1.4 The Governing Body then noted that Becky Booker, Director of Finance, Camden CCG

is leading on a piece of work to benchmark Continuing Care expenditure across NCL and a progress report will be brought to the Strategy and Finance Committee in due course.

3.1.5 John Rohan suggested that it would be helpful if the Governing Body could be provided with an outline of how the CCG will meet its QIPP targets in-year, in order to avoid a repetition of the pressures incurred in the previous financial year.

3.1.6 Anthony Browne confirmed that the CCG would be adopting the style of reporting modelled by Camden CCG with effect from the QIPP Delivery Group Meeting in early

August, followed by the Strategy and Finance Committee meeting later that month. The new format, combined with acute reporting data, will help the CCG to assess the level of financial risk better.

3.1.7 Adam Sharples highlighted that the CCG’s projected running costs were actually increasing, despite the recent organisational changes. Anthony Browne clarified that this was a function of the NHS reporting process and acknowledged that this ought to

be made clearer in future. More detail would be provided at the next meeting of the Strategy and Finance Committee. It was noted that the CCG is not permitted to spend its running cost budget on other areas of work.

3.1.8 Gino Amato suggested that if it would be helpful if the CCG could be notified of its financial allocation for the following financial year earlier than at present, to facilitate more effective planning.

Page 16: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

5

3.1.9 The Governing Body NOTED the financial position at Month 2.

3.2 Performance and Quality Report

3.2.1 Alex Smith provided an overview of the Performance and Quality Report, highlighting the following key points from the performance section:

The overall Referral to Treatment 18 Week Target was not met in April 2018,

although the CCG has been assured that that NMUH will soon be back on track

as their summer elective catch-up continues apace. A contract notice had been

issued to RFH as a result of their failure to meet this target since August 2017

Five of the eight targets for cancer had been met in April 2018. In light of regional

concern about NMUH’s achievement of the 62 day standard, the Cancer

Intensive Support Team has made recommendations which are to be addressed

in the Trust’s refreshed improvement plan

Urology and gastroenterology performance at NMUH remains challenging, with

endoscopy capacity a particular issue – as a result, NHS England and NHS

Improvement have asked commissioners to participate in a demand/capacity

review

The recent A&E performance at NMUH continues to improve and the provisional

figures for June place it 3% ahead of its improvement trajectory

Bed occupancy rates at NMUH remain high and are the single highest cause of

the trust’s performance breaches

The CCG will need to work closely with local trusts, Haringey Council and

Community Health Services to meet the target set by NHS England and NHS

Improvement to reduce ‘stranded patients’

The Community Health dashboard presented a mixed picture, with a significant

improvement in Child and Adolescent Mental Health Services (CAMHS)

performance off-set by a decrease in the percentage of Podiatry patients seen

within six weeks

Performance at the Memory Clinic has deteriorated, falling to 6.7% in April 2018.

The fact that the trust largely attributed this to workplace changes has led to the

CCG requesting a demand and capacity review. A new clinic specification is

being proposed by commissioners and GPs are being sought to strengthen the

clinical input to this.

3.2.2 Jennie Williams then provided a further update to the quality section of the report. A rapid review is being carried out following NMUH’s recent declaration of a new Never Event, concerning the insertion of an incorrect intraocular lens. A paper on the LUTS

(Lower Urinary Tract Symptoms) service will be presented at the Joint Overview and Scrutiny Committee meeting on 20 July 2018.

3.2.3 The Governing Body then discussed the report.

Page 17: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

6

3.2.4 Simon Caplan welcomed the improvements being made in Community Services but sought assurance that these were not being achieved at the expense of patients who are already in the system. Rachel Lissauer also noted the concern that follow-up appointments are being spaced out to accommodate the introduction of additional

clinics for first appointments. Alex Smith welcomed this feedback and said that he would raise this at the next meeting of the Transformation Group.

3.2.5 Adam Sharples welcomed the establishment of an agreed basis for assessing performance and hoped that this would form the basis for improvements going forward. However, he observed that the general level of Community Services performance was significantly below where it ought to be and the lack of timely data undermined the value

of the dashboard. The fact that the majority of urgent targets are not being met was a particular matter of concern.

3.2.6 The Governing Body then discussed potential steps that could be taken to improve the performance of the Memory Clinic, including the use of interim staff. Simon Goodwin cautioned that the CCG needs to be clear whether the number of referrals is actually increasing, as it may be the case that the resource is not keeping up with the level of

activity. It was agreed that Alex Smith would provide an update to the Governing Body.

3.2.7 Catherine Herman queried whether there had been any data to inform the Trust and

the CCG on patient satisfaction with the call centre used by Community Services for booking appointments. Jennie Williams confirmed that this issue would be raised at the next meeting of the Whittington Health Clinical Quality Review Group. She suggested that it would also be worth tracking the average length of time it takes for patients to

get through to a receptionist. Rachel Lissauer noted that the Trust had acknowledged at the Improvement Working Group that more needs to be done to improve communications with the public.

3.2.8 Simon Caplan highlighted that Community Services are currently not accessible on the e-Referral System (eRS) and suggested that the CCG should address this in the next round of Commissioning Intentions.

3.2.9 Sharon Grant expressed concern about the backlog of radiology reporting, (predominantly x-rays), which was currently being reviewed by Whittington Health. Gino

Amato clarified that these x-rays would have been reviewed by a doctor at the trust who would have drawn their own conclusions about any action that might need to be taken, but it was nevertheless unsatisfactory that the results not been reported further.

3.2.10 Jennie Williams confirmed that the trust had reviewed the backlog and had not identified any incidents of patient harm. An internal root cause analysis had been undertaken and a report will be taken shortly to the next Trust Board meeting, after which it will be

presented to the Clinical Quality Review Group.

3.2.11 It was agreed that Jennie Williams would update Sharon Grant outside the meeting

about the action being taken by BEHMHT to improve the timeliness of its complaints management.

3.2.12 The Governing Body NOTED the Performance and Quality Report.

3.2.13 ACTION 12/7-3: Clare Henderson to provide an update on the Memory Clinic.

Page 18: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

7

3.2.14 ACTION 12/7-4: Jennie Williams to update Sharon Grant outside the meeting about

the action being taken by BEHMHT to improve the timeliness of its complaints management.

4. Strategy and Development

4.1 Strategic Risk Report

4.1.1 Alex Smith provided an overview of the report, highlighting the changes over the past

two months to the CCG, NCL Joint Commissioning Committee and NCL-wide Risk Registers. The CCG currently had five ‘open’ risks rated at 12 and above.

4.1.2 It was noted that a new risk around diagnostic endoscopy capacity would be opened during the next review period.

4.1.3 The Governing Body NOTED the Strategic Risk Report.

5. Governing Body Committee Minutes

5.1 The Governing Body NOTED the minutes of the Audit Committee meeting held on 27

February 2018, the Clinical Cabinet meeting held on 3 May 2018, the Finance and

Performance Committee meeting held on 27 April 2018, the NCL Joint Commissioning Committee meeting held on 5 April 2018 and the NCL Primary Care Committee in Common meeting held on 19 April 2018.

6. Any Other Business

6.1 Adam Sharples informed the Governing Body that Catherine Herman had agreed to be the third member of the Haringey CCG Audit Committee. As a consequence, Catherine Herman would be stepping down as the CCG’s lay member representative on the Joint Commissioning Committee with effect from September 2018 and Adam Sharples would

be taking over this role. 7. Date of Next Meeting

7.1 Thursday, 13 September 2018.

Page 19: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Draft Minutes of the

Part II Meeting of the Haringey Clinical Commissioning Group Governing Body

Thursday 12 July 2018 at 1.30pm

Cypriot Centre, Earlham Grove Present:

Dr Peter Christian PC Chair of Haringey CCG, West Lead

Helen Pettersen HP Accountable Officer, North Central London CCGs

Dr Gino Amato GA GP Governing Body Member, North East Dr Simon Caplan SC GP Governing Body Member, North East

Dr Dina Dhorajiwala DD GP Governing Body Member, West

Dr David Masters DM GP Governing Body Member, West

Dr Sheena Patel SP GP Governing Body Member, Central Lead

Dr John Rohan JR GP Governing Body Member, North East Lead

Dr Lionel Sherman LS GP Governing Body Member, Central

Dr Daijun Tan DT GP Governing Body Member, Sessional

Sharon Seber SS GP Governing Body Primary Care Health Professional Member, South East

Catherine Herman CHr Lay Member, Haringey CCG

Adam Sharples ASh Lay Member, Haringey CCG Sarah Timms ST Nurse Member, Haringey CCG

Tony Hoolaghan TH Chief Operating Officer, Haringey CCG

Simon Goodwin SGo Chief Finance Officer, North Central London CCGs In attendance:

Anthony Browne AB Deputy Chief Finance Officer, Haringey CCG

Clare Henderson CHn Director of Commissioning, Haringey CCG

Alex Smith ASm Director of Planning, Performance and Delivery, Haringey CCG

Will Maimaris WM Consultant in Public Health, Haringey Council

Steve Beeho SB Board Secretary, Haringey CCG (minutes)

1. INTRODUCTION Action

1.1 Apologies for Absence

1.1.1 Apologies were received from Jeanelle De Gruchy. Will Maimaris was attending on her behalf.

1.2 Declarations of Interest

1.2.1 There were no additional declarations of interest.

2. Minutes of the Previous Meeting

2.1 The Governing Body agreed the minutes of the Governing Body meeting held on 10 May 2018 as an accurate record.

Page 20: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

2

3. Matters Arising

3.1 There were no matters arising.

4. Any Other Business

4.1 Tony Hoolaghan noted that the CCG would be undertaking a ‘refresh’ of clinical lead responsibilities using a similar approach to the one which Dominic Roberts had used in Islington.

5. Date of Next Meeting

5.1 Thursday, 13 September 2018.

Page 21: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey CCG Governing Body meeting – Thursday 12 July 2018

Questions from the public (received in advance of the meeting)

Question 1 - 3 from Rod Wells, Haringey Keep Our NHS Public

Question 1 relates to Item 2.1 Accountable Officer’s report, section 2

Engagement assessment rating.

1. HKONP note that the CCG believe “Patient and community engagement

is vital when it comes to improving health services within Haringey.”

However the recent consultation on draft policy for primary hip and knee

arthroplasty (replacement) run by London Choosing Wisely-who London

CCGs I understand contracted- was a dire failure to engage with the public

in Haringey . Ref https://www.healthylondon.org/our-work/london-

choosing-wisely/

Haringey residents were given 4 days to respond to a long and technical

consultation (by 4/6/18) which most would not be aware of. We understand

that up to 30 May no notification was received by Haringey Healthwatch of

this.

These proposed changes in the way patients may expect to receive surgical

treatments would affect people for years. HKONP believe the rushed way

the consultation was done and manner it was carried out fails any

“community engagement” test

HKONP want any future consultation on changes in people’s health to be

carried out properly, in good time, and in clear and plain language and ask

what steps Haringey CCG are taking to ensure this happens in future.

Answer: The London Choosing Widely engagement was a London – wide

exercise led by the Healthy London Partnership.

Response provided by the London Choosing Wisely programme

From the patient perspective, the London Choosing Wisely programme has had

support from Healthwatch England in cascading information to London’s

Healthwatch networks, whom the programme has also been contacting directly.

The Steering Group has two patient representatives and each Task and Finish

Group also has a patient representative supporting the development of each draft

London policy. The programme is engaging directly with patient-facing groups for

the relevant treatment areas too. There have been some concerns raised about

Page 22: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

the short timeline of the programme’s ‘sense check’ phase and wider

engagement with local patient groups. These concerns are being reviewed by

the London Choosing Wisely Steering Group and Programme Board.

Questions 2 - 3 relates to Item 3.1 Finance Report

2. I understand that the CCG has a financial plan to deliver a surplus of

£19k in 2018/19 from a deficit of £14 m and that this means

delivering “net efficiencies of £19.5m.” Any “efficiencies” could mean a

reduction in health services

Then the finance report states that “the net risk is £7.1m, (and )

the CCG does not have any reserves or mitigations set aside if these

risks materialise”

If so why is the CCG considering putting itself in this position? Is there

pressure from NHSE or the STP –North London Partners- to produce a

surplus of this size? If not should the CCG reduce the surplus and keep

more money for health services in Haringey?

Answer: The statutory requirement is to breakeven. CCGs typically budget

slightly better than breakeven, hence £19k in Haringey.

3. Given the above can the CCG explain in plain language what are the “STP Interventions” and how do you “stretch them”?

Can the CCG point me to how the “QIPP” will deliver the

“net savings of £11.8m.” as per para 4.1 - and will this involve cuts to

services?

Answer: STP interventions refer to the larger areas of QIPP (Quality, Innovation,

Productivity and Prevention) taking place across all Trusts in North Central

London. ‘Stretch’ is a term used to increase the level of efficiency where a

scheme has the opportunity to exceed original savings targets. We will ensure

language is clearer in future.

Focus on QIPP savings plans will be presented at future meetings. The CCG has

no plans to make cuts to services.

Question 4 from Liz Ciokajlo

Question 4 relates to Item 2.1 Accountable Officer’s Report - section 8

Osborne Grove Nursing Home

4. I am a daughter of a long standing resident of the home. We welcome Haringey Council's reverse decision to keep the home open and the seven remaining residents will stay before, during and after which future option is decided upon. My question is the CCG planning to protect the

Page 23: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

residents and raise the standards to CQC 'good' standard now in all areas by employing Pamela Edam to advise improvement and implement this advice, officially raising the CQC standard to 'good'? Also how is the CCG planning to protect the residents in the event of building works and expansion, given in the past at OGNH residents’ health has been significantly impacted when moved from one wing to another? Answer: As a Local Authority owned residential nursing home the responsibility for employing staff at Osbourne Grove and ensuring that residents and patients are kept safe sits with Haringey Local Authority. The CCG’s care homes team is supporting the Local Authority and staff within the home to ensure continuous improvement of the care delivered. With regard to the protection of residents in the event of building works, the CCG has been advised by the Director of Adult Social Services that all decisions made by the council will be made in the best interests of the residents. There will be a risk assessment made prior to building works and the CQC in their regulatory role will make a decision about whether it is appropriate for regulated activities to be delivered.

Question 5 from Gordon Peters, Older Persons Group

Question 5 relates to Item 2.1 Accountable Officer’s Report - section 8

Osborne Grove Nursing Home

5. What does the CCG see its role as in keeping Osborne Grove as a

nursing home, now that Haringey Council has agreed to do that?

Answer: Haringey CCG is keen to take part in the co-design of new or expanded

facilities at Osborne Grove. The Council has set up a steering group and the

CCG will take an active role in this.

Questions 6- 7 from Anne Gray

Question 6 relates to Item 1.5 Minutes from previous meeting, section 4.1.3

6. a) if assessment of continuing care needs is done at home, what steps

are taken to carry out a pre-assessment to ensure before they are

discharged that the patient will have someone to provide meals,

shopping, basic housework, medical, washing and toileting needs

? What are patients advised to do if these arrangements break down

(e.g. if a friend/relative who does not normally reside with them breaks

their commitment to be available, perhaps for some unavoidable reason

to do with employer demands or other car-ees, or goes sick

themselves?)

Page 24: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

b) How is continuing care coordinated with local authority domiciliary care?

c) Has the CCG evaluated the adequacy of the Home from Hospital service and are members aware of the misgivings of at least one local pensioners’ group about its adequacy?

Answer: a) The assessment of a patient’s needs prior to discharge is not undertaken by the continuing healthcare team so we cannot comment on the nature of that assessment. We are advised by the acute setting of the appropriate care package to meet the health and social care needs of the patient and commission a package accordingly. It is rarely, if ever, reliant on the ability of family members to provide care. Patients (and sometimes appropriately authorised family members) can decline CCG services if they wish to manage care themselves. In those circumstances a new application would have to be made to be re-referred for CHC assessment. If there is any breakdown in care arrangements for a funded care package the first point of call would be to the provider organisation for that care who would contact the appropriate commissioner of that care for advice, support or increased care provision.

b) Continuing healthcare does not involve local authority domiciliary care. In the event that a person is in receipt of local authority commissioned care, the funding responsibility for that care package is taken over by the CCG at the point the person is deemed eligible for continuing healthcare, which can only happen after a full assessment for eligibility. In those circumstances it has usually been an increase in care needs so the package of care is often recommissioned.

c) The Home from Hospital is commissioned by the London Borough of Haringey.

The Council evaluates the service via quarterly monitoring meetings which are informed by performance reporting from the provider (Bridge Renewal Trust). We evaluate patient satisfaction levels (surveyed by Bridge Renewal Trust after receiving a service), referral levels and outcomes against the terms of the contract, and we supplement this with wider stakeholder feedback. Any complaints would be shared with the commissioners during the quarterly evaluation or they may be received directly by the Council.

Where we receive any complaints about the service, these are investigated, and followed up with a quality assurance visit if required. We have not received any complaints regarding the service. In order to investigate the point raised in the question we would need further details which may be provided by emailing [email protected]

Question 7 relates to Item 3.2 Performance and Quality summary, section 3.3 and page 9 of the Performance and Quality summary report.

Page 25: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

7. Will the senior CHC nurses overseeing discharge routinely

communicate discharge information to GPs, or whose responsibility will

it be? What proportion of people discharged have no GP

registration? (may be common given low GP registration rate of recent

arrivals in Haringey).

Answer: The responsibility to ensure GPs receive discharge summaries within

24 hours of the patient being transferred or discharged lies with Trusts. CHC

teams do not have a role in overseeing discharge information to GPs. It is

very unlikely that patients with CHC needs do not have a GP because they

often have a long history of complex care needs. In situations where people

are unregistered, Trusts take an active role in encouraging registration.

Questions 8 - 10 from Joanna Bornat, Haringey Keep Our NHS Public

Question 8 relates to Item 5.2 Clinical Cabinet Minutes, section 2.1.1 Update on

BEHMT Haringey Mental Health Services

8. Is the CCG satisfied with the current situation relating to the provision of community based mental health services, their staffing and co-ordination between primary and secondary care, and might the CCG press BEHMT Mental Health Services to consider whether the future role of the St Ann’s site might be used to improve community mental health service provision given that, at present, plans appear to be for adult acute services only?

Answer: The CCG works continuously with BEHMHT, and our other partners

including the Council, to improve community mental health services. For

example, we are pleased to be launching the Primary Care Link Workers in the

Central area of Haringey over the summer, bringing mental health nurses into

general practice to advise GPs and patients, and to liaise between primary and

secondary care.

We are also facilitating discussion between primary and secondary care to

explore opportunities for joint working in the new primary care buildings that will

be opening over the coming years in Haringey.

The St Ann’s site redevelopment is focused on improving the mental health

inpatient wards, and this has been identified as a priority. However, we note that

the Trust is also seeking to improve the other facilities on the site that will be

under their management in future, to ensure their community teams have

appropriate facilities to operate from.

Question 9 relates to Item 5.4 Joint Commissioning minutes, section 3.1 Whittington Health Lower Urinary Tract service

9. Could the CCG provide an update on the situation with the Lower Urinary Trace Service at the Whittington Hospital, given that this service

Page 26: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

has yet to be restored after a very long period of closure and request dates for the ‘phased re-opening’ ( see minute 3.19) of this service?

Answer: Following a meeting of the Joint Commissioning Committee (JCC) of

North Central London CCGs and the Whittington Health NHS Trust Board, the

LUTS clinic has re-opened to new patients.

In order to re-open the clinic the Islington Clinical Commissioning Group (CCG)

and Whittington Health Trust Board has approved a Commissioning Service

Specification, which meets the recommendations set out in the report from the

Royal College of Physicians (RCP) Invited Review.

The RCP report says: “Based on all of the information considered by the review

team it was concluded that significant changes need to be made to ensure the

safety of patients currently being treated by the LUTS clinic.”

The Royal College of Physicians (RCP) Invited Service Review Panel

recommended that “until the future of the service has been determined by the

Trust and commissioners, no new patient referrals should be accepted into the

LUTS clinic”. In line with this recommendation the clinic has remained open to

existing patients, but the Trust has not accepted any new referrals since October

2015. Any clinician who wrote to make a referral during that time was advised

that the referral would not be accepted and that they should refer their patient

elsewhere. There is therefore no waiting list or backlog of patients for the

Whittington Health LUTS clinic.

A more detailed update on the LUTS clinic is available on Whittington Health’s

website.

Question 10 relates to Item 5.3 Finance and Performance Committee Minutes, section 2.6

10. Reference is made to the possibility of cutting down on contracts in order to prevent overspend. Could the CCG provide reassurance that this will not mean loss of provision of services or to any reduction in plans for service development for local people? And could the CCG also note that much of this important paper is not written in a way that is easily understood by members of the public?

Answer: Haringey CCG will be facing very difficult choices over the coming year

as we have a large savings programme to deliver, however, we do not have

plans in place to reduce current provision. Our focus will be on continuing to

transform services that will provide care closer to home and better value for

Page 27: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

money. This includes continuing to focus on areas such as reducing variation in

primary care, supporting people at home, introducing new ways of working such

as tele-dermatology and working with partners to take cost out of the system.

Your second point has been noted.

Page 28: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Page 1 of 2

Haringey CCG Governing Body: Action Log Item 1.6

Meeting Date

No. Action Description Lead Action Taken

12.7.18 1 Action Log To speak to Sheena Patel outside the meeting regarding assurances

about the volume of rejected e-referrals.

Jennie Williams Jennie Williams has liaised with Sheena Patel and Denise Pettit outside the meeting. There have been no formal escalations regarding rejections but will be kept under review.

12.7.18 2 Matters Arising To arrange for consultations to be

promoted more effectively.

Tony Hoolaghan The CCG Communications Team is looking into ways of raising awareness of consultations via the CCG website.

12.7.18 3 Performance and Quality Summary Report To provide an update to the

Governing Body on the Memory Clinic.

Clare Henderson An update is included in section four of the Performance Report. Healthwatch and other carer representatives have been

invited to be core members of the Dementia Strategy Group. The group is multi-agency and works together to create effective partnership-working, with an emphasis on improving the experience for people with Dementia and their

carers via a dementia care delivery plan. The membership of the group has been extended in order to ensure wider engagement and support of the delivery plan.

12.7.18 4 Performance and Quality Summary

Report To provide Sharon Grant with more detail about the action being taken

by BEH MHT regarding its failure

Jennie Williams An email summarising the action taken by the Trust was

sent to Sharon Grant on 12.7.18.

Page 29: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Page 2 of 2

to meet its complaints management performance target.

Page 30: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey Clinical Commissioning Group Governing Body Meeting 13 September 2018

Report Title Accountable Officer’s Report

Date of report 27 August 2018

Agenda Item

2.1

Lead Director /

Manager

Helen Pettersen Tel/Email [email protected]

GB Member Sponsor

Not applicable.

Report Author

Tony Hoolaghan Chief Operating Officer

Tel/Email [email protected]

Report Summary

This report updates the Governing Body on developments in the local NHS and wider policy issues.

Recommendation The Governing Body is asked to NOTE the Accountable Officer’s Report.

Identified Risks

and Risk

Management

Actions

Not applicable.

Conflicts of Interest

Not applicable.

Resource

Implications

Not applicable.

Engagement

Not applicable.

Equality Impact

Analysis

Not applicable.

Report History and

Key Decisions

Not applicable.

Next Steps Not applicable.

Appendices

Not applicable.

Page 31: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Accountable Officer’s Report

1 Introduction

1.1 This report focuses on the key activities that the senior team and I have been involved in since the

last Governing Body meeting and work progressed.

2 Haringey and Islington Wellbeing Partnership Expression of Interest to Healthy London

Partnership

2.1 In June, London areas were invited by the Healthy London Partnership (HLP) to put forward

expressions of interest to set out the ways how they might use the flexibilities of devolution in

London to progress with integration. These flexibilities include more joint regulation to support

joint working or support to enable people to work across transitional health and social care

boundaries. Haringey and Islington Wellbeing Partnership submitted a bid in which we set out an

ambition to test an expansion of our Care and Health Integrated Network (CHIN) work within two

geographical areas, one in Haringey and one in Islington. We would develop these as

'prototypes' of a holistic approach towards improving health and wellbeing within an area,

drawing on all assets and the full range of services available. Within the Welllbeing Partnership

there is an agreement that this work will be progressed locally and would be supported by , but is

not dependent on, additional resource through Healthy London Partnership.

3. Wellbeing Week

3.1 To mark our annual Health and Wellbeing week for our staff, we are hosting a range of activities

taking place from 24-28 September for all staff at Haringey CCG. The week is an opportunity to

promote the importance of staff wellbeing in the workplace. Our staff involvement group are also

taking a lead on the preparation for the week by hosting a range of activities. The week was a

huge success last year. We will also be applying for the London Workplace Charter to highlight

the work we do to support our staff wellbeing.

4. Draft Strategy for General Practice

4.1 NCL Clinical Commissioning Groups are developing a refreshed strategy focusing on general practice and which builds on previous collaborative strategies for NCL. A draft strategy has been developed through a dedicated task and finish group, which also included representation from CCGs, Healthwatch, nursing and the NCL GP federations. This group met six times between March and June 2018. We are now in the process of engaging on this draft. The timeline has been lengthened until October and November 2018, for the Primary Care Committee in Common and CCG Governing Bodies’ respective approvals.

4.2 Engagement is being clinically and locally led by each CCG through patient and public forums,

GP locality meetings, LMC meetings, primary care development meetings and letters to local

councillors. Where it is appropriate, some engagement is being done once across NCL e.g. Joint

Health Overview and Scrutiny Committee (JHOSC) and the Primary Care Committee in

Common.

4.3 Feedback to date has indicated that stakeholders would like to see greater clarity on what our

key priorities are (less is more), clearer examples of what will be different for patients, what

investment is available, stronger messages on prevention and self-care and a clearer message

on our vision for the workforce and new ways of working (e.g. using pharmacists in general

practice, portfolio working for GPs). All feedback is being considered as part of the development

of the final draft of the strategy.

Page 32: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

5. GP Patient Survey

5.1 The results of the national GP survey have been published this month by NHS England. This

year’s survey has been extensively redesigned - the aim is to help better understand and shape

areas for improvement in people’s experiences of general practice and evolving approaches to

delivering GP services. This means the majority of questions are not comparable with previous

years, and that no comparable data will be published by NHS England. CCGs in NCL will be

reviewing their data packs to consider the findings and identify the actions needed to deliver

improvement – particularly in relation to what patients have said about access.

5.2 Haringey CCG noted the slight overall improvement in overall satisfaction, from 79% to 80%, so

closer to the national average which dropped from 85% to 84%. There is significant variation

between practices, and our focus is on working with the practices that are at the low end of

patient satisfaction. Low patient satisfaction is a potential indicator of other performance issues.

6. Haringey CCG: Maternity and Cancer CCG assessments

6.1 In August, Haringey received its 2017/18 CCG assessments for cancer and maternity. The

assessments are based on performance against the indicators in the Integrated Assurance

Framework (IAF) for CCGs for these clinical areas. Haringey received a rating of ‘good’ for

maternity and ‘requires improvement’ for cancer.

6.2 Although the cancer IAF indicator for early stage diagnosis was achieved, patient experience,

one year survival rates and the 62 day urgent referral to treatment standard were not at the level

required. The focus that is being given in primary care regarding early diagnosis will ultimately

support improvements in survival rates and there is an improvement plan in place supported by

the cancer collaborative, CCG and NHSI regarding 62 day performance. A plan to improve

patient experience of cancer services at NMUH is also in place.

6.3 Contributing to the successful maternity rating has been progress between partners to improve

women’s experience of maternity services. We would like to thank all staff from across the

system involved in delivering these improvements and will continue to work with partners to

improve cancer services and outcomes across out system.

7. St Ann’s Hospital update 7.1 Barnet, Enfield and Haringey Mental Health Trust is rapidly progressing the plans for the brand

new mental health inpatient wards and other improvements at St Ann’s Hospital in Haringey . Plans will see the proceeds from the surplus land no longer needed for healthcare, which was sold to the GLA in March 2018, reinvested into the building of the new wards and other improvements.

7.2 The Trust expects to receive final approval from NHS Improvement in September this year. It has

already received final planning approval from Haringey Council in March 2018. Initial building work is due to begin around November 2018, with completion of the new inpatient building by late 2020 and the other improvements by late 2022.

7.3 The plans have widespread support, with backing from Haringey Council, Haringey CCG and wider stakeholders following two extensive public consultations and on-going stakeholder engagement. The project is affordable and will bear no additional costs to the Trust or NHS commissioners with the new facilities being fully funded from the sale of the surplus land.

Page 33: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey Clinical Commissioning Group Governing Body Meeting Thursday 12 September 2018

Report Title STP Programme Update

Agenda Item

4.1

Governing Body

Sponsor

Helen Pettersen Accountable Officer

Lead Director /

Manager

Will Huxter NCL Director of Strategy

Email [email protected]

Report Author

Will Huxter NCL Director of Strategy

Email [email protected]

Report Summary

The report provides an update on the work of the Sustainability and Transformation Partnership (STP) since April 2018. The aim is to ensure that Governing Body members are aware of the current and planned work being undertaken as part of the STP.

Recommendation The Governing Body is asked to NOTE the report.

Identified Risks

and Risk

Management

Actions

Not Applicable

Conflicts of Interest

Not Applicable

Resource

Implications

There are no direct resource implications arising from this report.

Engagement

Not Applicable

Equality Impact

Analysis

Not Applicable

Report History and

Key Decisions

This report is a follow-up to previous STP update reports.

Next Steps Not Applicable

Appendices Six Monthly Report

Page 34: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

STP Programme update

Haringey CCG Governing Body 13 September 2018

Will Huxter, Director of Strategy

Barnet, Camden, Enfield, Haringey & Islington CCGs

Page 35: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Ambition for the STP is built on existing CCG, Local

Authority and Provider values and strategy

Improve the health and wellbeing of the

local population

Reduce health inequalities

Maximise out of hospital care and build resilient

well supported communities

Ambitions of the STP

A partnership of the NHS and local authorities, working together with the public and patients where it’s the most efficient and effective way to deliver improvements.

Page 36: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

NLP Governance Structure

The Adult Social Care Programme runs alongside the STP workstreams

Page 37: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

4

The STP has no formal decision-making authority, beyond management of the

agreed programme, and the delegated budget for the STP central team.

Statutory bodies retain responsibility for decisions on funding commitments and

endorsement of the STP priorities.

Increasingly, the STP is being asked by NHS England and NHS Improvement to

co-ordinate and submit NCL-wide bids for funding – e.g. for Wave 4 capital, and

for digital revenue and capital. These are formally signed off by Helen Pettersen

as STP Convenor, on recommendation from the relevant STP workstream.

The Joint Commissioning Committee has delegated authority for acute

commissioning on behalf of the 5 CCGs. The Primary Care Committee in

Common has delegated authority for primary care commissioning on behalf of

the 5 CCGs.

Key points about STP governance

Page 38: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

5

Summary: Clincal and care workstream objectives

Workstream High level objectives

Urgent and Emergency Care • A consistent and reliable UEC service by 2021 that is accessible to the public, easy to navigate, inspires confidence, promotes consistent standards in clinical practice and leads to a reduction in variation of patient outcomes. Work focussing on Admissions avoidance, ambulatory care, end of life and discharge to assess.

Health and care closer to home

• A ‘place-based’ population health system of care base around neighbourhoods of 50-80k which draws together social, community, primary and specialist services underpinned by a systematic focus on prevention and supported self-care.

Mental Health • Working to address inequalities for those with SMI and provide consistent care. • Deliver services closer to home, reducing demand on the acute sector and mitigating the need for additional MH

inpatient beds.

Adult Social Care • Working to address care inequalities in provision and improving longer term strategic approach to workforce and care market.

Maternity • Delivery of the National Maternity Transformation programme through improved continuity and safety of perinatal care for women, working across professional and organisational boundaries to drive better patient experience and integrated care.

Children and Young people • Delivery of Health and social care services which are equitable, accessible, responsive and efficient, delivered locally wherever possible. Working closely with social care and council services to increase focus on promoting wellbeing, reducing health inequalities and improving social outcomes such as school readiness.

Cancer • Focus on the delivery of improved survival, reduced variation, improved patient experience, efficiency of service delivery including services closer to home, and, reduced costs and financial sustainability.

Planned Care • Deliver better value planned care, delivering efficiency savings and reducing unwarranted variation in planned care across providers.

• Review of orthopaedic services across providers.

Prevention • Driving system-wide approach to prevention and population health working to enable success in the overall STP strategy for care.

Page 39: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

UEC

• One of the first areas nationally to launch the new integrated urgent care model. This means that more people in NCL ringing 111 now speak directly with a clinician to try to resolve their issue.

• ‘Star divert numbers’ enable clinical staff to get through to a clinical expert for urgent advice and support by dialling the appropriate number. For 2017/18 star l ine activity increased 42%, from 751 calls in May 2017 to 1068 calls in April 2018 with a total of 11,929 calls recorded across the period.

• Mental health patients can now ring 111, and be directly transfer to crisis team for advice and support. 16 people in April who rang 111 with mental health issues were successfully transferred to a mental health team.

• Successful bid for enhanced mental health liaison services in A&E at University College Hospital in 2017/18, and North MiddlesexUniversity Hospital in 2018/19. This will enable us to place more mental health staff in hospitals so patients’ physical and mental health needs are cared for holistically.

• We have made it faster and safer for patients to get home from hospital by agreeing standard ways of working and working moreeffectively with social care. Use of the new discharge to assess pathways has increased by 50% over the past six months.

Planned Care

• Clinical advice & guidance now live across providers in NCL in 8 specialities with further specialties going live in November 2018.

• Tele-dermatology service to go live in 2018/19 to improve patient experience and performance for waiting times.

• Review of adult elective orthopaedic care commenced in March 2018 . Our ambition is to create a comprehensive adult elective orthopaedic service for NCL, which will be seen as a centre for excellence with an international reputation for patient outco mes and experience, education and research.

Health and Care Close to Home

• Since April 2018 it has been possible for residents to access GP services 8am-8pm across the whole of NCL through extended access.

• Established the first NCL Care and Health Integrated Networks and Quality Improvement Support Teams, focusing on improving quality and reducing unnecessary variation.

Mental Health

• Our perinatal mental health service operates across the five boroughs. Our community specialist perinatal mental health service s aw an additional 400 women in 2017/18 and plans to reach an additional 600 women in 2018/19.

• A new women’s psychiatric intensive care unit at Camden and Islington NHS Foundation Trust service opened in November 2017. A l l women who require intensive care services can now be treated close to where they live. All women have been repatriated back f rom out of area placements (OAPs) and we currently have zero women in OAPs.

Tangible benefits and delivery to date:

Page 40: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Overview of programmes impact and leadership

Ma

jor

fin

an

ce a

nd

act

ivit

yim

pa

ct fo

r 1

8/1

9

Workstream and leads Programme Primary impact Major Independencies

UECSRO: Sarah Mansuralli C CCG

Clinical leads:Chris Laing

Shakil Alam

Integrated urgent care £, Quality & Performance Digital

Admission avoidance £, Quality & Performance Digital, Workforce

Simplified discharge £, Quality & Performance Digital, Social Care

Last Phase of life £, Quality & Performance Digital, Social Care

Planned CareSRO: Marcel Levi

Clinical leads: Debbie Frost

Richard Jennings

Using NHS money wisely (POLCE) £, Q, Learning: Enactment of policy -

Clinical Advice and Navigation £, Q, Learning: working across acute & primary care Digital

Dermatology £, Q, Perf & Learning: Use of digital pathway Digital

Urology £ & Learning: upskill primary care HCCH

Orthopaedic review Proposed reduction in variation Q and £ -

Health and Care Closer to Home

SRO: Tony Hoolaghan H&I CCG Clinical lead: Katie Coleman

CHIN/Neighbourhood development Population health and wellbeing Workforce, Estates, Digital

Quality Improvement £ & Reduction in primary care variation Workforce

Social Prescribing Reduction in primary care variation Workforce

Mental HealthSRO: Paul Jenkins

Clinical leads: Vincent Kirchner

Jonathan BindmanAlex Warner

Improve the acute care pathway Reduction in bed requirement in future HCCH, Social Care

Improvement to CAMHS Quality improvements CYP

Mental Health Liaison services Quality and £ and perf UEC

Primary Care mental health (Inc. IAPT) Q & £ and Perf HCCH

Mental Health Workforce Future workforce development

MaternityDonald Peebles

Mai Buckley

Quality and safety Quality Digital

Improving personalisation and choice Quality Digital

Single point of access £ and Quality Digital , Workforce

Community services development Quality & NHS E recommendation HCCH

NCL collaborative working £ and Quality Workforce

Page 41: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

PreventionSRO: Julie Billett

Workforce for prevention Referrals to preventative services (inc MH) Workforce

Healthier environment Employee health and wellbeing and sickness rates Workforce

Healthier choices (maternity and Frailty) Child health outcomes, independent living Maternity, UEC

CancerSRO: Kathy Pritchard-Jones

Sustained delivery of cancer waits Quality & Performance Diagnostics capacity

Early diagnosis Quality (lives saved) HCCH, Prevention

Living with and beyond cancer Quality HCCH, Planned

Children and Young PeopleSRO: Charlotte Pomery

Paediatric surgery Quality UEC

Asthma Quality Prevention, HCCH

School readiness by 5 Child outcomes -

Paediatric admissions avoidance £, Quality and Performance UEC

EstatesSRO: Simon Goodwin

Develop NCL estates strategy Strategic priority, £, Quality improvement All

St Pancras development – C&I FT £, Quality improvement Mental Health

St Ann’s development - BEH £, Quality improvement All

Project Oriel Quality Improvement -

Reducing void spaces £, quality improvement All

DigitalSRO: David Sloman

Health Information Exchange Enabler for £ and Quality improvements Clinical Workstreams

Population Health Management Enabler for £ and Quality improvements Clinical Workstreams

WorkforceSRO: Siobhan Harrington

UEC preparation winter 2019 Performance and quality UEC, HCCH, Social

Portability (including passports, MAST) Performance and £ UEC, Maternity, Cancer

Temporary Staffing £ Provider productivity

Social & Primary care/Community/Place based Long term quality HCCH , Social Care

Analytics (workforce planning) £ enabler for new clinical models Digital

Overview of programmes impact and leadership

Page 42: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Provider Productivity

SRO: Tim Jaggard

Workforce £ Workforce

Procurement £ -

Facilities management £ -

Diagnostics £ and Quality Planned Care

SocialCare

SRO: Dawn Wakeling

Independent Care Sector Workforce Capacity and Quality HCCH, UEC, Workforce

Social Care Markets Increased Capacity & Quality; £; HCCH, UEC, MH, Workforce

Overview of programmes impact and leadership

Page 43: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Dedicated capacity now in place across majority of workstreams to facilitate working across partner organisations to deliver agreed STP initiatives.

Capacity to facilitate change

Workstream Programme lead Email Address

Adult Social Care Richard Elphick [email protected]

Cancer Nasar Turabi [email protected]

Children and Young People Sam Rostom [email protected]

Digital Interim to start in September [email protected]

Estates Dianne MacDonald [email protected]

Health and Care Closer to Home Sarah McIlwaine [email protected]

Maternity Julie Juliff [email protected]

Mental Health Chris Dzikiti [email protected]

Planned Care Donal Markey [email protected]

Prevention Mubasshir Ajaz [email protected]

Productivity Shahbaz Bhutta [email protected]

Orthopaedic review Anna Stewart [email protected]

Urgent and Emergency Care Alex Faulkes [email protected]

Workforce Sarah Young (interim) [email protected]

Page 44: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Digital: plan to deliver by 2020

11

Enable information to flow between all NHS providers and local authorities within NLP

Optimise spend on health and care information sharing across NLP

Enable population health management capability for NLP

Implement international IT standards to enable interoperability and support integrated care

Activate person held records (PHR) for NLP residents

Page 45: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Adult elective orthopaedic services review

• We think there may be opportunities to improve adult elective orthopaedic surgery in north central London by consolidating services onto fewer sites

• We are undertaking a review of these services to see if these improvements can be achieved

• The review has been established by North London Partners in Health and Care

• A review group led by local clinicians is coordinating the development of how this kind of care could be delivered in the future

• Clinical commissioners will make decisions on where and how this happens

• The review covers services in Barnet, Camden, Enfield, Haringey and Islington

12

Page 46: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Stages of the review

Stage 1Engage to get feedback on the draft case for change Propose a service model describing how services might be delivered in future, informed by feedbackStage 2Clinical commissioners consider the feedback from the engagement, agree a service model

Produce a pre-consultation business case

13

• Patients & residents• Providers• Clinicians• Clinical Commissioners

engagem

ent

Page 47: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Principles underpinning this review

• Co-production (everyone working collaboratively) • Evidence based service model (using evidence from trusted sources)• Clinically led collaborative approach which enables meaningful

engagement with all stakeholders, particularly front line clinical staff and the public (people involved in delivering and receiving care)

• Independent experts to provide challenge and advice• Sharing what we learn• Clear separation of decision-making functions • Flexible timelines to ensure we are properly engaging with

stakeholders and the public

14

Page 48: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Leadership and Review Group

Chair: Professor Fares Haddad (UCLH)CEO Sponsor and Project SRO: Rob Hurd (RNOH)

Review Group Members:Clinical representatives from each of the five largest providers of adult orthopaedic servicesTwo clinical commissioning representatives from NCL CCGsNHS England Specialised CommissioningTwo patient and public representatives (recruited by Healthwatch)NHS England Strategy and Reconfiguration

In attendance:Trust management leads from each of the five largest providers of adult orthopaedic servicesProgramme Director and Programme ManagerOther workstream leads as required

15

Page 49: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Adult elective orthopaedic services review

• We think there may be opportunities to improve adult elective orthopaedic surgery in north central London by consolidating services onto fewer sites

• We are undertaking a review of these services to see if these improvements can be achieved

• The review has been established by North London Partners in Health and Care

• A review group led by local clinicians is coordinating the development of how this kind of care could be delivered in the future

• Clinical commissioners will make decisions on where and how this happens

• The review covers services in Barnet, Camden, Enfield, Haringey and Islington

16

Page 50: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Ways to feed back

Seeking feed back by 19 October 2018

•Read the full case for change on our website:www.northlondonpartners.org.uk

• Email us: [email protected]

•Complete our online questionnaire

•Write to us: North London Partners in Health and Care, 5th Floor, 5 Pancras Square, London N1C 4AG

*Additional time will be allowed to hear more views if required

17

Page 51: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Financial benefits 2018/19:

• £35m worth of QIPP plans aligned to STP workstreams

• Successful with bid for 2 grants with Department of Health for Beyond Places of Safety worth £1.0 m and £0.8m

• £500k grant awarded from Health Education England

• £100k funding for engagement

• £100k awarded via RightCare to take forward work on Cardio Vascular Disease prevention

• NHS E funded dementia project manager

Breakdown of STP financial benefits (NCL-wide)

Page 52: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Supporting local QIPP plans and focus on delivery at scale

19

• Urgent and Emergency Care, Planned Care and Health and Care Close to Home workstreamsaligned to CCG QIPP plans to support in year financial delivery. This aligns to approximately £35m of acute QIPP schemes across NCL.

• Across the STP there has been close working with local CCG teams to align plans across the NCL CCGs, spread good practice and support CCGs to add to their pipeline opportunities.

• This work has resulted in a shared set of priorities across acute contracts (next slide). This will allow the opportunity for greater collaboration and implementation at pace and scale.

• STP and local teams are working through ‘local delivery teams’ at each acute site to drive changes and unblock issues. This includes directly supporting implementation of new ways of working and acceleration of local work.

• Work is underway to quantify new pipeline schemes that can feed into individual CCG QIPP plans.

Page 53: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

NCL wide priorities delivery at scale:

Across NCL, the top schemes by value are shared across the four main acute providers. These are summarised below:

20

Number of times scheme appears within top 15

Workstream Royal Free NMUH UCLH Whitt Total

Planned Care POLCE 1 1 1 1 4Planned Care Diagnostics - Pathology 1 1 1 1 4UEC Adult Admission Avoidance - Rapid Response Services 1 1 1 1 4UEC Ambulatory Care 1 1 1 1 4UEC Simplified Discharge 1 1 1 1 4UEC IUC 1 1 1 1 4UEC Last Phase of Life 1 1 1 1 4Health and Care Closer to Home CHIN & QIST initiatives combined 1 1 1 1 4Planned Care MSK 1 1 1 1 4UEC Reducing NEL Admissions for Children 1 1 1 3UEC ED Front Door Streaming & Redirection 1 1 1 3Planned Care Gastroenterology & Colorectal Surgery 1 1 2Planned Care Clinical Advice and Navigation (CAN) 1 1 2Planned Care Gynaecology 2 2Planned Care Camden Clinical Assessment Service (CCAS) 1 1Planned Care Urology 1 1Health and Care Closer to Home Universal Offer Review 1 1Planned Care Teledermatology 1 1 1 1 4UEC HIU / LAS - Frequent Attenders 1 1Planned Care Dermatology - minor skin lesions 1 1UEC Stroke Prevention 1 1Planned Care STT Cancer Pathway 1 1

Page 54: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey Clinical Commissioning Group

Governing Body Meeting Thursday, 13 September 2018

Report Title System Intentions for 2019/20: Haringey CCG

Date of report 30 August 2018

Agenda

Item

4.2

Lead Director /

Manager

Paul Sinden, Director of Performance, Planning and Primary Care Alex Smith, Director of Planning, Performance and Delivery Clare Henderson, Director of Commissioning

Tel/Email [email protected] [email protected] [email protected]

GB Member Sponsor

Not Applicable

Report Author

Seonaid Henderson, Head of Performance and Planning

Tel/Email [email protected] 0203 688 2785

Report Summary

This report sets out system intentions and provisional commissioning intentions for 2019/20, and the backdrop to the development of North Central London (NCL) System Intentions for 2019/20. It should be noted that these are provisional system/commissioning intentions and are subject to change as the financial impact of them is assessed.

Recommendation The Governing Body is asked to:

NOTE the report; and

COMMENT on this iteration of System Intentions and local Commissioning Intentions for 2019/20.

Identified Risks

and Risk

Management

Actions

The main risks to delivering system intentions for 2019/20 are:

The need to align CCG and provider operating plans to support a reduction in system costs; and

The need to better align system incentives to support delivery of System and Transformation Plan (NCL) priorities and reduce system costs.

Conflicts of Interest

The report was prepared in accordance with conflict of interest guidance

Resource

Implications

Plans for 2019/20 will need to be developed within CCG resource envelopes and encompass run-rates from 2018/19 adjusted for demographic growth, the impact of the NCL Sustainability and Transformation Plan (STP), local QIPP interventions, and the impact of national planning guidance.

Page 55: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Engagement

Intentions should reflect the priorities identified through engagement with patients and public. Local CCG engagement timelines will be built into the process for generating system intentions, as well as being informed by on-going engagement structures. Haringey CCG strives to engage with patients, partners and residents throughout the commissioning cycle to ensure that local people have a voice. We have a strategic approach which is set out in our engagement strategy to demonstrate how we involve patients and wider stakeholders in services we commission. In 2018, the CCG was rated ‘Green’ as part of a national assessment undertaken by NHS England. Haringey CCG wants to make real and sustainable improvements to the health and wellbeing of the people living in the borough. Effective engagement will help us to improve health outcomes and make the best use of public resources. We will continue to work with patients, carers, and the public to listen to their views, and we will continue to involve them in decisions about commissioning, developing, and improving health services.

Equality Impact

Analysis

The report was written in accordance with the provisions of the Equali ty Act 2010.

Report History and

Key Decisions

System Intentions for 2019/20 were considered by the Joint Commissioning

Committee Seminar held on 5 July 2018 and by the Joint Commissioning

Committee held on 2 August 2018. The System Intentions for 2019/20 were

considered at the Strategy and Finance Committee on 30 August 2018.

Next Steps System intentions and commissioning intentions for 2019/20 will be further

developed with feedback from:

CCG Strategy and Finance Committees;

The five NCL CCG Governing Bodies in September 2018;

The NCL Sustainability and Transformation Plan Chief Executives Group

(commissioners and providers) in September 2018;

The outcome of the NCL STP Integrated Care Systems workshop to be held in

October 2018;

Priorities set out in the NHS Ten-Year Plan to be published in autumn 2018.

Before 30 September 2018 all providers in North Central London will have been

sent intentions and supporting technical guidance (with notice where required) for

2019/20.

Appendices

1. Haringey CCG Notices

Page 56: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

1. Introduction

This report sets out system intentions and provisional commissioning intentions for 2019/20, and the

backdrop to the development of North Central London System Intentions for 2019/20.

Any service changes described in this report are also subject to scrutiny via a business case at the

relevant committee or board, during the course of the commissioning cycle, which evaluate the quality,

safety, financial viability and strategic fit of any proposal. Commissioning intentions therefore do not

represent formal commitments to act, but do ensure commissioners have legally given notice on the

pipeline of activities they would like to work jointly with providers on, as notice needs to legally be given

to exit contracts or change service configurations in alignment with a strict planning timetable.

Intentions for 2019/20 will consist of the following:

1. System intentions - Following on from the after action review of the 2018/19, contract round system

intentions for 2019/20 seek to identify a few high-level priorities, agreed by all parties to the STP that

will then be translated into operating plans and provider contracts for the year;

2. Commissioning intentions – that provide a more detailed view of how system intentions will be

delivered locally, plus any local intentions for CCGs that sit outside of the STP; and

3. Supporting technical guidance – identifying any areas requiring formal contract notice to providers

for 2019/20

System intentions and commissioning intentions for 2019/20 will be further developed in response to feedback from:

CCG Strategy and Finance Committees;

The five NCL CCG Governing Bodies in September 2018;

The NCL STP Chief Executives Group (commissioners and providers) in September 2018;

The outcome of the NCL STP Care Systems workshop to be held in October 2018; and

Priorities set out in the NHS Ten-Year Plan to be published in autumn 2018.

Before 30 September 2018 all providers in North Central London will have been sent intentions and

supporting technical guidance (with notice where required) for 2019/20.

2. System Intentions

The high-level priorities for 2019/20 seek to focus on what is best required to meet the needs of the local

population, rather than taking an institutional approach. NCL will seek support for the collective

commitment to reduce system costs and to ensure that any unintended consequences of that for

individual organisations is mitigated.

To take this forward there will need to be a single local delivery plan for the year for both commissioners

and providers, with the plan developed and signed-off by combined clinical and executive leadership to

assure inclusion in operating plans and delivery during the year. Local Delivery Groups, aligned to each

provider, will lead in-year delivery.

The high-level system priorities for 2019/20 to address the strategic challenges faced by NCL are

identified below:

A focus on prevention to tackle the broader determinants of health and reduce health inequalities,

and to deliver this, extend the scope of work with the third sector and utilisation of community

assets;

Further developing integrated care systems across health and care services as part of our move to

population based health models and to better tackle the broader determinants of health;

Page 57: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

To support our move to population based health models this means redefining community services

contracts to an outcomes based approach for future years, allowing greater flexibility in service

redesign to support the development of Care and Health Integrated Networks (CHINs), and

establishing integrated services across health and care for admission avoidance and discharge from

hospital;

Building resilience in general practice including developing primary care at scale alongside the

emerging GP Federations;

The redesign of outpatient pathways building on service models developed in 2018/19 including

Clinical Advice and Navigation;

Continuing to deliver value and reduce variations in care, building on the work to date in both

primary care and secondary care to reduce unwarranted variations in care;

Delivering investment in prevention and primary care will require historic growth in acute contract

baselines to be halted. Aligned to this, system intentions are designed to deliver off -setted cost

reductions for acute providers. This will be supported by:

Joint work on provider cost improvement plans and CCG QIPP programmes to help providers

reduce their costs; and

Joint development of system incentives as below;

Trialling new system incentives and contract forms to promote a reduction in system costs and

better align incentives to the service models being developed through the NCL STP:

In 2019/20 to support STP service developments a focus on outpatient and elective pathways,

community services outcomes, and streaming in emergency departments to support urgent

treatment centre designations and winter resilience are proposed;

CCGs will also work with providers on opportunities for whole contract form changes for adoption in

2019/20 or future years; and

In preparation for contracts for 2019/20 and onwards, CCGs would therefore like to ‘shadow-run’

alternative contract forms in 2018/19 to ensure that any changes support delivery of the STP and

balance risk equitably across the system.

The delivery of enablers for the above, including:

Roll-out of the Health Information Exchange across North Central London;

Provider collaboration initiatives including opportunities for common procurement, repatriation of

activity, and exploring further opportunities for mutual aid across providers to support delivery of

NHS Constitution targets for cancer, referral-to-treatment times, and A&E;

Delivery of the estates strategy for NCL based on the one-public estate approach to support the

development of a place-based approach to our community estate and increase operational

efficiency; and

Workforce, including the work by Community Education Provider Networks (CEPN), to develop the

workforce to support our strategic service changes with a focus on skill-mix, recruitment and

retention, collaboration across providers including “passporting”, and portfolio careers.

3. Commissioning Intentions

The information below sets out how Haringey CCG intends to achieve the priorities within the 2019/20

system intentions and any other local intentions it is required to issue. These intentions are provisional at

this stage and have been developed through the following process:

Commissioning managers in each commissioning area have collated intentions based on their

work programme, giving due to regard to the Joint Strategic Needs Assessment (JSNA), relevant

national or regional guidance/policy, patient and public feedback, contract and outcome

monitoring, value for money analysis and any available assessments of quality and safety.

Page 58: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

The Executive Management Team (EMT) and Heads of Planning and Performance from

Haringey and Islington CCGs have undertaken a joint review taking into account fit with NCL

STP strategy and local business plans.

EMT and Heads of Planning and Performance have determined which commissioning intentions

require a formal notice (see Appendix 1) and which of those are already part of an existing

workplan which might lead to future transformation, for example, joint work to develop a new

MSK clinical model.

The next steps are for feedback to be collated on both the system intentions (Joint Commissioning

Committee (JCC), all five CCG Governing Bodies and Strategy and Finance Committees) and

commissioning intentions (Haringey and Islington CCG Governing Bodies and Strategy and Finance

Committee). This will allow intentions to be further refined ahead of formal notice being given on 30

September 2018 to all providers in NCL. It should be noted that further intentions are likely to be added

as work to agree consistent QIPP initiatives across the STP continues.

Community and Acute Commissioning Intentions:

Haringey CCG intends to achieve the priorities within the 2019/20 system intentions through the

following community health and acute intentions:

As part of the Wellbeing Partnership, commissioners and providers have agreed to collaborate in

the development of a new MSK clinical model for Haringey and Islington which will include, a

single point of clinical triage, increased community provision and a programme of provider led

improvements to existing services. This pathway redesign is aligned to national best practice and

aims to ensure more people are treated in community based care.

As part of the Well Being Partnership programme of work to improve intermediate care, Haringey

CCG intends to review and re-specify the Community Rehabilitation Teams service to deliver

improvements for Haringey service users.

As part of the Wellbeing Partnership programme of work to improve services for Children and

Young People within Haringey, a joint review of Specialist Therapies will take place with the

London Borough of Haringey which aims to agree new specifications being agreed for all

therapies. This will deliver earlier intervention and prevention of speech and language issues.

As part of the Wellbeing Programme, Islington and Haringey CCGs will review against best

practice all elements of our frailty services in order to consider the current provision and identify

any gaps or priority needs. This will be done in a way that is aligned to guidance contained in

NHS England’s ‘Frail older people – Safe, compassionate care’ practical guide for commissioners

and will ultimately aim to support people in community settings better and reduce unnecessary

hospital admissions.

Haringey CCG intends to draft a new service specification and model for children's community

nursing provided by North Middlesex University Hospital. The new model will aim to ensure more

children can be cared for in community settings, without the need for hospital

attendance/admission.

As part of NCL wide work to develop primary care at scale and strengthen care closer to home,

wound management and leg ulcer treatment services will be procured at CHIN level. This work

aims to ensure better outcomes for patients, ensuring community services are proactive and high

quality, in a way that reduces the need for hospital attendance.

As part of NCL wide work to improve Urgent and Emergency Care, Haringey CCG and Islington

CCG will be exploring opportunities to align and integrate our stroke and neuro-rehab pathways

and community and inpatient rehabilitation services in order to improve and expand access to

Early Supported Discharge (ESD). This will improve outcomes for patients and enhance their

recovery. Aligning and integrating pathways will also improve value for money.

Page 59: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

In alignment with NCL wide work, Haringey CCG will seek to develop revised payment

mechanisms that incentivise providers to focus on overall pathway outcomes, and to shift care

from acute to primary and community settings. This is likely to be a staged process, with shadow

tariffs in place first.

Haringey CCG’s acute intentions support the redesign of pathways that build upon service models

developed in 2018/19.

As part of the London Five Point Cancer Improvement Plan, Haringey CCG will require North

Middlesex University Hospital to sustainably implement Straight to Test for upper and lower

gastro intestinal 2-week wait referrals. This will improve outcomes for patients with cancer,

contribute to improving survival rates and help enable this important constitutional target to be

delivered.

As part of NCL wide work to improve planned care pathways, new pathways will be implemented

for planned urology care, ear nose and throat, gynaecology, ophthalmology, chronic kidney

disease and physiotherapy for women’s bowel services. This will improve the effectiveness and

efficiency of pathways in line with recognised good practice.

As part of NCL wide work the recommendations from the orthopaedics planned care review will

be implemented across NCL and the pain management pathways reviewed. The aim of this work

is to improve outcomes for patients and the effectiveness of the pathway, in line with recognised

good practice.

Taking into account the outcomes of the ‘National Consultation on Evidence -Based Interventions,

July 2018’, the new sector wide Procedures of Limited Clinical Effectiveness (POLCE) policy will

be implemented by all providers.

Mental Health Commissioning Intentions

Haringey CCG intends to, subject to a positive evaluation, extend the primary care mental health

service for the whole of Haringey. The mental health link worker service, nurses and occupational

therapists, work in collaboration with secondary mental health services and primary care to

deliver a range of interventions including clinical advice and guidance and access to services to

prevent emergency admissions.

Haringey CCG will continue to support Barnet, Enfield and Haringey Mental Health Trust (BEH

MHT) to introduce mental health link workers in the ‘Central’ CHIN.

Haringey CCG intends to review and re-specify the Crisis Response and Home Treatment

Teams to strengthen the crisis and acute intervention pathways and models delivering

improvements for Haringey service users.

Haringey CCG intends to work closely with BEH MHT to improve the dementia pathway including

the memory clinic. This work aims to improve patient experience, reduce waiting times, improve

post diagnosis-support, and implement the requirements of the NICE guidelines on ‘Dementia:

assessment, management and support for people living with dementia and their carers, June

2018’.

As part of NCL wide work, and subject to a successful evaluation, Haringey CCG intends to

extend Improving Access to Psychological Therapies (IAPT) for people with long term conditions

introducing more long term physical health condition pathways, potentially in cardiology and

chronic pain. This work aims to support people to better manage their long term condition,

improving outcomes and ultimately reducing costs to the health and care system.

Haringey CCG intends to increase the non-long term conditions (LTC) psychological therapies to

meet NHS England access target requirements towards 21%. This will be achieved through the

expansion of the outreach functions providing a preventative approach to the identification and

management of mild to moderate mental health issues. Enhanced provision will also be

Page 60: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

implemented in priority areas, which may include behavioural therapy for couples and specialist

support for 18-25 year olds not suited to Cognitive Behavioural Therapy (CBT).

In order to better support recovery and in line with NHS England policy, Haringey CCG intends to

implement improvements to the rehabilitation and accommodation pathway in-line with the BEH

MHT Out of Area Treatment reduction plan. These improvements may include step down models

such as discharge to assess or intermediate care support and treatment options for people with

complex needs requiring further assessment for safe discharge home or to a new setting.

Haringey CCG intends to recommission Tier 2 CAHMS services to further improve alignment with

national policy published in the ‘Department of Health/NHS England: Future in Mind: Promoting,

protecting and improving our children and young people’s mental health and wellbeing, 2015’ and

in line with NHS England’s ‘Model Specification for Child and Adolescent Mental Health Services:

Targeted and Specialist levels (Tiers 2/3)’.

In line with NCL STP strategy, Haringey CCG will work with partners to develop sustainable

mental health liaison services that are compliant with national Core 24 requirements (those

services that need nationally to be delivered 24/7). This will support all main emergency

departments and acute hospitals and aims to improve the responsiveness of services to people

experiencing an acute mental health crisis.

Haringey CCG intends to commission an evening crisis café service, to work with the psychiatric

liaison service and the crisis response and home treatment team service.

Haringey CCG intends to reduce the number of people with severe mental illness who are in

residential care, supported living or who are homeless by strengthening their community and at -

home care and support, using personal health budgets to personalise support across NHS and

Social Care services. This is in alignment with the NHS England’s ‘National Expansion Plan for

Personal Health Budgets, June 2017’ and will support people in primary and secondary care to

be more physically active and improve wellbeing. This initiative is informed by the good practice

developed regionally by Islington CCG, which is an NHSE Personalisation Demonstrator site.

As part of delivering the new ‘NICE guidelines for Attention Deficit Hyperactivity Disorder

(ADHD), March 2018’, mental health commissioners are working together to scope out the

service model for a specialist ADHD and Autism Spectral Disorder (ASD) neurodevelopmental

disorders (NDD) service that would cover Camden, Islington and Haringey CCGs. Processes are

underway to scope a procurement and contracting model for the three CCGs and if this goes

ahead then a procurement process will be initiated in December 2018, which could potentially

identify a new service provider by autumn 2019. The new service model will improve post

diagnosis support and include voluntary and community sector engagement.

4. Technical guidance

Acute Contracts for 2019/20 and 2020/21 (early indications point to a minimum two-year contract

process) will be consistent with national planning guidance, and an indicative timetable is set out below

that mirrors the timetable for the 2018/19 planning round. This will be updated once national planning

guidance is published in autumn 2018.

Page 61: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

The contract round will have to account for the following:

Lessons learned from the 2018/19 contracting and planning round.

Agreement of operational planning and contracting principles to ensure a consistent approach for

planning and setting contract baselines;

Agreement of key planning assumptions for growth, the impact of QIPP and 2018/19 run -rate for

baseline setting;

The publication of tariffs for 2019/21 tariffs, following an engagement process in autumn 2018. The

report sets out early indications for 2019/21 tariffs with potential material changes to outpatient and

non-elective tariffs;

Any changes to the revised standard acute contract including any new mandated contract forms;

The approach for setting contract baselines for each individual year as part of any multi-year contract;

The approach to setting non-acute baselines;

Identification of local variations to the Standard Contract:

Local tariffs to support delivery of Sustainability and Transformation Plan (STP) initiatives;

Marginal rates;

Claims and challenges;

Penalties/sanctions;

Timetable and approach to generating 2019/20 STP and QIPP schemes and including them in

2019/20 contract baselines; and

Local escalation process where progress is slipping against the timetable above, and to avo id the

need to refer contracts to NHS England and NHS Improvement for resolution.

Page 62: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Appendix 1 - Haringey CCG Notices

Reference

number

Programme

Area

Commissioning

purpose and

rationale

Lead

commissioner Coverage

Commissioning

Lead (name)

inc. contact

details

System Intention detail Providers

impacted on

H&ICCG2

c/f for

19/20

Children and

Young People:

Autism

Diagnostic

Pathw ay

Recommissioning of the service to

improve quality of

care including

post-diagnostic

support in line

w ith the new

NICE guidelines

on ADHD (March

2018) and Autism

Spectrum

Disorder (2011)

Haringey

CCG

Multiple

CCGs

Michele.guimarin

@nhs.net and

Kathryn.collin1@n

hs.net

As part of delivering the new ‘NICE guidelines for

Attention Deficit Hyperactivity Disorder (ADHD),

March 2018’, mental health commissioners are

w orking together to scope out the service model for a

specialist ADHD and Autism Spectral Disorder (ASD)

neurodevelopmental disorders (NDD) service that

w ould cover Camden, Islington and Haringey CCG.

Processes are underw ay to scope a procurement and

contracting model for the three CCGs and if this goes

ahead then a procurement process w ill be initiated in

December 2018, w hich could potentially identify a new service provider by autumn 2019. The new

service model w ill improve post discharge support

and include voluntary and community sector

engagement.

All

acute

pro

vid

ers

HCCG 39

Children and

Young People

(CAMHS)

Recommissioning

service in line w ith

NHS England’s ‘Model

Specif ication for

CAMHS: Targeted

and Specialist

levels (Tiers 2/3).

NHS Haringey

CCG

NHS

Haringey

CCG

michele.guimarin

@nhs.net

Dependent on the outcomes of public

consultation/engagement requirements, Haringey

CCG intends to recommission Tier 2 CAMHS services

to further improve alignment w ith national policy

published in the ‘Department of Health/NHS England:

Future in Mind: Promoting, improving and protecting

our children and young people’s mental health and

w ellbeing (2015)’ and in line w ith NHS England’s

‘Model Specif ication for Child and Adolescent Mental

Health Services: Targeted and Specialist levels (Tiers

2/3).

NM

UH

WH

RF

L

H&ICCG3 Intermediate

care

Recommissioning

service to better

support people to

be cared for

outside of acute

hospital settings

Islington

CCG

Multiple

CCGs

Jacob Wheeler

(jacob.w heeler@

islington.gov.uk)

and Marco Inzani

(marco.inzani@

nhs.net)

The intermediate care system across Haringey and

Islington w ill be redesigned in collaboration w ith users and providers in order to improve outcomes for

patients and services users. This w ork w ill affect all

elements of Intermediate Care, and w ill be

operationally led in order to determine impact on

existing contracts.

UC

LH

WH

CN

WLF

T

NM

UH

Page 63: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey Clinical Commissioning Group Governing Body Meeting

13 September 2018

Report Title Haringey CCG Finance Report as at 31 July 2018

Date of report 29 August 2018

Agenda

Item

5.1

Lead Director /

Manager

Anthony Browne Deputy Chief Finance Officer

Tel/Email 020 3688 1394 [email protected]

GB Member Sponsor

Simon Goodwin Chief Finance Officer

Report Author

Scott Hunn Head of Finance (HCCG)

Tel/Email 020 3688 2727 [email protected]

Report Summary

This paper sets out for the Governing Body, the Haringey CCG financial position at the end of July 2018 (month 4). The 2018/19 financial plan for the CCG is to deliver an in year surplus of £19k at the year-end. At month 4 the CCG is reporting a £514k year to date deficit and forecasting to plan at year end. Based on April to June activity and an estimate for July the financial position of the CCG’s acute contracts reports forecast over-performance of £14.0m at month 4, this has been mitigated by the release of the acute demand reserves, contingency and the impact of QIPP in the latter part of the year. In order to deliver the control target of a £19k surplus the CCG are required to deliver net efficiencies of £19.5m. The CCG has developed £15.8m of schemes and set aside investment of £3.9m to support their delivery. Work is on-going to identify additional efficiencies in-year to cover the £7.6m of unidentified efficiencies. The delivery of our planned in-year surplus of £19k is subject to a number of risks, particularly in year acute over performance, delivery of the STP Interventions & QIPP programme and increased continuing healthcare activity. The net risk is £8.1m, the CCG does not have any reserves or mitigations set aside if these risks materialise. This financial position has been reported to NHS England as part of the monthly monitoring process.

Recommendation The Governing Body is asked to NOTE the financial position at month 4.

Page 64: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Identified Risks

and Risk

Management

Actions

This report is one element used to monitor the Clinical Commissioning Group’s financial performance in terms of adherence to core statutory duties.

Conflicts of Interest

Not applicable.

Resource

Implications

There are no direct resource implications for this paper, as it is not a project proposal for additional internal resourcing, nor is it assuming additional external resourcing.

Engagement

Not applicable.

Equality Impact

Analysis

No Equality Impact Assessment is planned or has been undertaken for the finance report itself, though individual QIPP schemes undergo the assessment.

Report History and

Key Decisions

Not applicable.

Next Steps Updates to be provided at all Governing Body meetings.

Appendices

Financial position of all five NCL CCGs.

Page 65: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

HARINGEY CLINICAL COMMISSIONING GROUP Finance Report for the period to 31 May 2018

1 Introduction

1.1 This paper sets out for the Governing Body, the financial position at the end of May 2018 (month 2).

2 Executive Summary

2.1 The 2018/19 financial plan for the CCG is to deliver an in year surplus of £19k at the year-end.

2.2 At month 2 the CCG is reporting a £14k year to date deficit and forecasting to plan at year end. It should be noted that the position is largely based on one month’s data, therefore it is too early in the financial year for any activity trends to emerge.

2.3 In order to deliver the control target of a £19k surplus the CCG are required to deliver net efficiencies of £19.5m. The CCG has developed £15.8m of schemes and set aside investment of £3.9m to support their delivery. Work is on-going to identify additional efficiencies in-year to

cover the £7.6m of unidentified efficiencies. 2.4 The delivery of our planned in-year surplus of £19k is subject to a number of risks, particularly in year acute over performance, delivery of the STP Interventions & QIPP programme and

increased continuing healthcare activity. The net risk is £7.1m, the CCG does not have any reserves or mitigations set aside if these risks materialise. 2.5 This financial position has been reported to NHS England as part of the monthly monitoring

process. 3 Financial Position at Month 2

3.1 Financial performance can be summarised as follows:

Page 66: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

3.2 The 2018/19 financial plan for the CCG is to deliver an in-year surplus of £19k at the year-end.

3.3 At month 2 the CCG is reporting a year to date deficit of £14k and forecasting to plan at year end. 3.4 The most significant points to note include:

The position is based on one month’s data and therefore it is too early in the financial year for any activity trends to emerge.

Activity data provided by the main providers is reasonable however contract plans still

require correct point of delivery apportionment from Trusts ahead of Month 3 reporting.

Out of Sector provider data varies. Not all providers have submitted data and in some instances the data is incomplete.

On this basis acute contracts have been reported to plan.

The Continuing Healthcare budget is over-performing by £109k at month 2 but is forecast to be in line with plan at year-end.

Running cost budget of £6,398k is forecast to plan at month 2.

Budget Actual

£'000 £'000 £'000 £'000 £'000

Resource Allocation - 70,823 - 70,823 - - 414,519 -

Acute Contracts (In and Out of Sector) 39,620 39,620 - 227,502 -

Other Acute 3,092 3,091 1- 18,554 -

Acute Commissioning 42,712 42,711 1- 246,057 -

Mental Health 6,909 6,909 - 41,457 0-

Continuing Care 3,658 3,767 109 21,946 -

Community Services 3,130 3,130 - 18,777 0-

Primary Care Prescribing 4,849 4,849 - 29,096 0-

Primary Care 199 199 0- 1,195 0-

PRC Delegated Co-Commissioning 6,776 6,776 0- 43,231 0-

Primary Care 111 & OOH Integrated Care 408 408 - 2,450 0-

Programme Corporate Cost 814 778 35- 4,882 -

Non-Acute Commissioning 26,743 26,816 74 163,033 0-

Running Costs 1,056 1,000 55- 6,398 -

0.5% Contingency 310 310 - 1,858 -

Demand Reserve - - - 2,846- -

(Surplus) / Deficit 3- 14 17 19- 0-

YTDFOT Variance 

Variance 

Page 67: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

4 QIPP Delivery

4.1 The 2018/19 QIPP plan for the CCG is a net £19.5m. The CCG has QIPP identified which are expected to delivery net savings of £11.8m. This includes £12.3m of acute schemes and £3.5m of Non Acute schemes offset by investments of £3.9m to support delivery of the QIPP schemes. £7.6m of “unidentified” QIPP remains in the plan.

4.2 In order to bridge the gap a repository of QIPP ‘work in progress’ is maintained and used to

support scheme generation. Governance and assurance is provided at Strategy and Finance Committee with the QIPP Delivery Group (QDG) responsible for operational and detailed

monitoring of each scheme.

4.3 In addition QDG is focussing on ‘stretch’ STP interventions and alignment of provider CIPs with commissioner QIPPs to achieve greater savings. The CCG is continuing to work closely with the Right Care delivery team to identify further opportunities from variation analysis. The

current ‘work in progress’ has a value of £3m and is in the process of being validated clinically and financially.

5 Financial Risks

5.1 The delivery of our planned in-year surplus of £19k is subject to a number of risks, particularly in year acute over performance, delivery of the STP Interventions & QIPP programme and increased continuing healthcare activity.

5.2 The CCG on a monthly basis makes an assessment of its key financial risks and mitigations. This is also a key element of the monthly financial report submitted to NHS England. These risks and mitigations represent the level of net risk from delivering a surplus of £7.1m.

6.3 The current assessment of financial risks and mitigations is set out below:

6.4 As highlighted above, the current assessment of net financial risk is around £7.1m. This position reflects an assessment of acute over-performance, under-delivery of QIPP/STP interventions and increased non-acute activity. It is evident from the above that the CCG does

Assessment of Risks & Mitigations - 2018/19

Full Value Probability

Adjusted

Value

Risks £m % £m

Acute Contract over-performance of 3% at a marginal rate of 50% 3.7 71% 2.600

Under delivery of QIPP/STP interventions. 23.4 21% 4.992

Increased in year CHC activity 2.0 50% 1.000

Increased in year Prescibing activity 1.0 50% 0.500

Increased activity at private providers and out of area mental health providers 1.0 50% 0.500

Pay awards @ 3% 0.2 50% 0.100

Total Risk 31.3 9.7

Mitigations

Contingency (1.9) 100% (1.9)

Delay/reduce STP investment (3.9) 20% (0.8)

Total Mitigations (5.8) (2.6)

Net Risk/(Mitigation) 25.5 7.1

Page 68: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

not have any significant mitigations if these risks materialise. The CCG will continue to monitor these and any emerging risks closely looking to identify further mitigations where possible. 6 Recommendation The Governing Body is asked to NOTE the financial position at month 2.

Scott Hunn

June 2018

Page 69: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Finance Report 2018-19

Month 4 (July 2018)

Lead Director: Anthony Browne

Author: Scott Hunn

Page 70: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

NCL CCG Summary Financial Position at

Month 4

• This table sets out the aggregate position across the five NCL CCGs.

• There is an annual plan to deliver a £0.22m surplus.

• There is a YTD adverse variance at M4 of (£3.77m) mostly at Enfield (£3.3m). Each CCG is reporting a

FOT on plan.

• There is an adverse YTD QIPP variance (£3.58m). The FOT QIPP variance is (£13.41m)

• There is an overall Net risk of (£42.13m) to the achievement of NCL CCG financial plans, a net

deterioration in the risk position by £3.1m since M3.

• The 18/19 target underlying position was for a £14.2m surplus. At M4 the forecast is for a £11.65m

deficit, a net deterioration of £3.4m since M3 (mostly at Barnet).

Bottom line QIPP Net risks Net risks Net risks Underlying position

Annual PlanYTD Var. FOT Var.

YTD Var.

YTD Var. FOT Var.FOT Var.

previous month

current month Movement 18/19 Plan

M4 Forecast

£m £m £m £m % £m % £m £m £m £m £m

Barnet 0.20 0.16 0.00 (0.15) 96% (1.35) 93% (3.55) (6.42) (2.87) 3.50 0.18

Camden 0.00 0.08 (0.00) (1.41) 79% (3.34) 87% (9.82) (9.63) 0.19 0.00 (9.60)

Enfield 0.00 (3.33) (0.00) (1.75) 74% 0.00 100% (15.77) (15.77) 0.00 1.40 (3.99)

Haringey 0.02 (0.51) (0.00) 0.00 100% (4.82) 75% (7.87) (8.11) (0.23) 1.80 1.77

Islington 0.00 (0.16) (0.00) (0.27) 92% (3.90) 75% (2.02) (2.20) (0.18) 7.50 (0.00)

Total 0.22 (3.77) 0.00 (3.58) 84% (13.41) 87% (39.03) (42.13) (3.09) 14.20 (11.65)

Page 71: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

• Summary Financial Position: The 2018/19

financial plan for the CCG is to deliver a

surplus of £19k at the year-end. At month 4,

the CCG is reporting a £514k year to date

over-performance and forecast to plan at

year end. There continue to be significant

levels of risks that may impact on the CCGs

financial position further, these relate to

QIPP, acute activity and CHC.

• Acute: Based on April to June activity the

financial position of the CCG’s acute

contracts reports forecast over-performance

of £14.0m at month 4, this has been

mitigated by the release of the acute demand

reserves, contingency and the impact of

QIPP in the latter part of the year.

• Non Acute: The CHC budget is seeing

increased levels of activity and costs in the

first four months of the year and is currently

under review.

• QIPP: The QIPP Programme is forecast to

deliver £14.7m (75%) of the £19.5m plan.

Additional schemes are being worked

through to mitigate the current under delivery

and to provide cover against any future

deterioration in the financial position.

Executive SummarySummary financial position (£m)

Bud Actual Var Bud FOT Var

Revenue Resource Limit 143.9 143.9 - 416.6 416.6 -

Acute 86.8 87.8 1.0 243.2 245.6 2.4

Non-Acute 52.6 52.6 0.0 159.6 158.8 (0.9)

Corporate & Running Costs 3.9 3.9 0.1 11.8 12.1 0.3

Total Operational 143.3 144.4 1.1 414.7 416.5 1.9

Total Non Operational 0.6 - (0.6) 1.9 (0.0) (1.9)

Total Expenditure 143.9 144.4 0.5 416.5 416.5 0.0

Surplus / (Deficit) 0.0 (0.5) (0.5) 0.0 0.0 (0.0)

Acute performance (£m)

Bud Actual Var Bud FOT Var

North Mid 27.0 28.4 1.4 77.1 82.5 5.4

Whittington 28.9 29.3 0.4 82.4 86.4 4.0

Other Acute 30.9 30.1 (0.8) 83.7 76.7 (7.0)

Total Acute 86.8 87.8 1.0 243.2 245.6 2.4

Prior month 243.2 245.7 2.4

18/19 QIPP programme (£'m)

Bud Actual Var Bud FOT Var

Planned care 1.1 1.1 - 5.7 6.9 1.3

CC2H 0.5 0.5 - 2.0 1.8 (0.2)

UEC 0.9 0.9 - 4.1 4.9 0.8

Other Acute 0.1 0.1 - 0.5 0.7 0.2

Other Schemes (0.6) (0.6) - 7.2 0.4 (6.8)

Net QIPP 2.1 2.1 - 19.5 14.7 (4.8)

YTD Full Year

YTD Full Year

Trust / ServiceYTD Full Year

Page 72: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Material Changes from the prior month FOT are:

• QIPP slippage of £4.8m.

• Deterioration in acute performance of £3.5m,

partially offset by the application of the marginal

rate (£1.6m).

• Phasing of QIPP plan adjusted to reflect forecast

delivery of £6.7m in latter part of the year.

• Investment reduction of £1m withheld to offset

QIPP under delivery.

Financial Bridge – Plan to Forecast Outturn

The forecast outturn at month 4 is a surplus of £19k which is in line with the agreed

NHSE control total.

0.0 0.0

1.6

0.0 13.7 0.4

(4.8) (10.9)

(21.0)

(16.0)

(11.0)

(6.0)

(1.0)

4.0

17/18 Plan QIPP slippage Acuteperformance

Marginal rate Prior year items Mitigations Other FOT

Driven By:

• £4.5m Whittington Health

• £5.4m North Middlesex

• £1.6m Royal Free London

• £2.8m UCLH

• £0.8m Out of Sector

• £0.4m Private Providers

Applied at:

• £0.5m Whittington Health

• £1.0m Royal Free London

• £0.2m UCLH

Applied at:

• £5.0m Acute Demand Reserve

• £6.7m QIPP Delivery

• £2.0m Delay/Reduce Investment

M2 M3 M4 Var

Plan (0.1) 0.0 0.0 0.0

QIPP Slippage - 0.0 (4.8) (4.8)

Acute performance - (7.4) (10.9) (3.5)

Marginal rate - - 1.6 1.6

Prior year items - - - -

Mitigations - 6.0 13.7 7.7

Other - 1.4 0.4 (1.0)

FOT - (0.0) 0.0 0.0

Page 73: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

• Haringey CCG is reporting breakeven but has

identified £8.7m of Risk with £0.6m of

Mitigations. This position has been reported to

NHSE.

• The Acute Risk consists of £4.8m QIPP

slippage and £2.0m of over performance on

agreed contracts.

• Community Services mitigation relates to the

potential delayed investments supporting QIPP.

• Continuing Health Care risk consists of £0.2m

QIPP slippage and £0.6m increased activity

and package of care prices.

• Primary Care Services risk of £0.3m relates to

QIPP slippage.

Risk and Mitigations

An assessment of risks and opportunities that may impact on the CCGs financial

position further has been estimated at £8.1m over and above the forecast position.

Risk and mitigations (£m)

Last Current Change Best Worst

FOT 0.0 0.0

Acute Services (6.9) (6.8) 0.0 - (6.8)

Mental Health - - - - -

Community Health 0.6 0.6 (0.0) 0.6 (0.0)

Continuing Care (1.0) (0.8) 0.2 - (0.8)

Primary Care Services (0.5) (0.3) 0.2 - (0.3)

PC Co-Commissioning - - - - -

Other Programmes - (0.7) (0.7) - (0.7)

Running Costs (0.1) (0.0) 0.1 - (0.0)

Total (7.9) (8.1) (0.2) 0.6 (8.7)

Page 74: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

All CCGs are forecasting to hit plan. However, there is £42.13m overall net risk to the achievement of the plan, which means delivery will be challenging.

9

NCL summary Financial Position

Source: Non-ISFE return

• This table sets out the aggregate position across the f ive NCL CCGs.

• There is a annual plan to deliver a £0.22m surplus.

• There is a YTD adverse variance at M4 of (£3.77m) mostly at Enfield (£3.3m). Each CCG is reporting a FOT on plan.

• There is an adverse YTD QIPP variance (£3.58m). The FOT QIPP variance is (£13.41m)

• There is an overall Net risk of (£42.13m) to the achievement of NCL CCG financial plans, a net deterioration in the risk position by £3.1m since M3.

• The 18/19 target underlying position w as for a £14.2m surplus. At M4 the forecast is for a £11.65m deficit, a net deterioration of £3.4m since M3

(mostly at Barnet).

Bottom line QIPP Net risks Net risks Net risks Underlying position

Annual

Plan

YTD

Var.

FOT

Var.

YTD

Var.

YTD

Var.

FOT

Var.

FOT

Var.

previous

month

current

monthMovement 18/19 Plan

M4

Forecast

£m £m £m £m % £m % £m £m £m £m £m

Barnet 0.20 0.16 0.00 (0.15) 96% (1.35) 93% (3.55) (6.42) (2.87) 3.50 0.18

Camden 0.00 0.08 0.00 (1.41) 79% (3.34) 87% (9.82) (9.63) 0.19 0.00 (9.60)

Enfield 0.00 (3.33) 0.00 (1.75) 74% 0.00 100% (15.77) (15.77) 0.00 1.40 (3.99)

Haringey 0.02 (0.51) 0.00 0.00 100% (4.82) 75% (7.87) (8.11) (0.23) 1.80 1.77

Islington 0.00 (0.16) 0.00 (0.27) 92% (3.90) 75% (2.02) (2.20) (0.18) 7.50 (0.00)

Total 0.22 (3.77) 0.00 (3.58) 84% (13.41) 87% (39.03) (42.13) (3.09) 14.20 (11.65)

Table 1 - NCL CCG Summary Financial Position - Month 4 18/19

Page 75: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

The CCG is forecasting to deliver the plan, although there is significant risk in relation to QIPP delivery and acute activity

1

Executive Summary

Summary financial position (£m)

YTD Full YearBud Actual Var Bud FOT Var

Revenue Resource Limit 129.4 129.4 - 405.7 405.7 -

Acute 76.0 78.3 2.3 226.4 230.8 4.3

Non-Acute 50.5 50.5 0.0 162.8 163.0 0.2

Programme Corporate Costs 1.2 1.1 (0.1) 6.6 6.6 (0.1)

Corporate & running costs 1.7 1.7 - 5.1 5.1 -

Total Operational 129.4 131.6 2.3 400.9 405.4 4.4

Total Non Operational - (2.1) (2.1) 4.8 0.3 (4.4)Total Expenditure 129.4 129.5 0.2 405.7 405.7 0.0Surplus / (Deficit) - (0.2) (0.2) - (0.0) (0.0)

Acute performance (£m)

Trust / Service

YTD Full YearBud Actual Var Bud FOT Var

£m £m £m £m £m £m

Whittington 33.5 34.6 1.1 99.5 101.6 2.1

UCLH 23.7 24.6 0.9 70.9 72.3 1.4

Other Acute 18.8 19.1 0.3 56.0 56.8 0.7

Total In Sector

76.0 78.3 2.3 226.4 230.7 4.3

Prior month 226.9 229.7 2.818/19 QIPP programme Gross (£'000)

YTD Full YearBud Actual Var Bud FOT Var

£m £m £m £m £m £m

CC2H 0.72 0.50 (0.22) 2.44 1.84 (0.60)

Planned Care 0.45 0.58 0.13 4.59 4.39 (0.20)

UEC 0.72 0.89 0.17 3.58 3.53 (0.05)

Other Schemes 1.46 1.10 (0.36) 6.57 3.53 (3.04)

QIPP Programme 3.34 3.07 (0.28) 17.18 13.29 (3.89)

Summary position

o Year to date the CCG is showing a £0.2m adverse variance against plan,

however maintains a breakeven forecast outturn (FOT) whilst further

analysis of QIPP and performance levels are completed.

o Acute Data - To date the CCG has only received Month 3 (flex) data and

are mindful of the risk of using a small sample to draw full year conclusions. The adverse variance of £2.3m is based on QIPP slippage and the effect of

this is offset with non recurrent items within the Acute Demand Reserve. The

Acute Demand Reserve is fully utilised to achieve the FOT position.

o Non Acute - The majority of Mental Health and Community contracts are

block arrangements but there has been notification of a £0.2m FOT cost

pressure on the Learning Disabilities pooled budget.

o Continuing Healthcare has a reported £0.1m overspend YTD but this is

expected to reduce as the work for the agreed CHC QIPP has started.

o Prescribing data has only been received for April and May and as yet, as in

all years, the full year forecast is not available until August.

o Contracts – There is a large element of QIPP that is not included within

Whittington, UCLH and RFL contracts and this represents a significant risk to delivery of the CCG control total.

Page 76: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

The forecast outturn is breakeven – QIPP slippage and acute performance have been offset by reserves (Acute Demand and Contingency)

2

Bridge

Material changes from the prior month FOT are:

• QIPP slippage of (£1.3m);

• Acute performance has deteriorated by (£1.1m);

• Prescribing now forecasting an underspend of £0.8m; and

• Remaining contingency of £1.5m held at M3 has been

released

Total acute variance is split between QIPP slippage £0.3m and over performance £0.4m

Release of contingency

Driven by:• Prescribing of £0.8m;

partially offset by• CHC overspend of

£0.7m (above QIPP slippage of £0.8m)

Bridging items (£m)

M2 M3 M4 Var

Plan 0.2 0.2 0.2 -

QIPP Slippage - (0.0) (1.3) (1.3)

Acute performance - (0.4) (1.5) (1.1)

Mitigations - 1.3 2.8 1.5

Other - (0.9) 0.1 1.0

Movement - - - -

0.0 0.0

4.4

0.0

(3.9)

(0.5)

(5.0)

(4.0)

(3.0)

(2.0)

(1.0)

-

1.0

2.0

3.0

4.0

18/19 Plan QIPP slippage Acute performance Mitigations Other FOT

Page 77: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Risk & Mitigations

There is a £2.2m net risk for Islington CCG reported to NHSE. This Risk not reported in position & should it materialise will be a pressure to CCG bottom line

8

o This is the basis of the month 4 return to NHSE. Islington CCG is reporting breakeven but has identified £7.3m of Risk with £5.1m of Mitigations

o The Acute Risk consists of £1.6m QIPP slippage and £2.6m of over performance on agreed contracts.

o For the Acute Mitigations the continued levels of over performance are being challenged and data is being further analysed to ensure over performance is not linked to QIPP slippage.

o Mental health services has some over performance in Pooled budgets but this is being managed within other areas.

o Continuing Health Care Services risk relates to the delay is patient assessments that are behind the QIPP target

o Primary Care Services relates to risk on Prescribing charges (NCSO and Category M). These may be offset by underspends elsewhere in Primary Care, predominantly CCG staffing.

o Islington CCG has a ‘Stretch’ QIPP target of £3.3m. QIPP shemes are being identified but due to the time taken to initiate there is a risk that £2.3m will not be achieved in 18/19.

Table 8 - Risk & Mitigations

Risk and mitigations (£m)

Emergent risk

Best Case

Worst Case

Last month

Current month Change Mitigations

Med Case

FOT (0.0) (0.0) (0.0)

Acute Services (4.0) (4.2) (0.1) 4.0 - (0.2) (4.2)

Mental Health (0.0) - 0.0 - - - -

Community Health (0.2) (0.2) - 0.2 - 0.1 (0.2)

Continuing Care (0.2) (0.1) 0.0 - - (0.1) (0.1)

Primary Care Services (0.5) (0.5) (0.0) 0.6 - 0.1 (0.5)

PC Co-Commissioning - - - - - - -

Unidentified QIPP (2.3) (2.3) - 0.3 - (2.0) (2.3)

Running Costs (0.1) - 0.1 - - -

Total (7.2) (7.3) (0.1) 5.1 (0.0) (2.2) (7.3)

Page 78: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey Clinical Commissioning Group Governing Body Meeting Thursday, 13 September 2018

Report Title Performance Report

Date of report: 29 August 2018

Agenda Item

5.2

Lead Director /

Manager

Alex Smith, Director of Planning, Performance and Delivery, Haringey and Islington CCGs

Tel/Email [email protected] 07712 729703

GB Member Sponsor

Not applicable.

Report Author

Seonaid Henderson, Head of Planning and Performance, Haringey CCG

Tel/Email [email protected] 0203 688 2785

Report Summary

This report provides an overview of the performance of Mental Health, Community Health Services, Ambulance services and other key non-acute standards Acute Performance information is reported at the Joint Commissioning Committee (JCC) and the papers for JCC have been made available to the Governing Body. As the Governing Body will be aware (due to reporting timetable differences) the performance report contain different months’ activity. This is stated within the relevant sections of the P&Q summary.

Recommendation The Governing Body is asked to NOTE the contents of this report.

Identified Risks

and Risk

Management

Actions

Not applicable.

Conflicts of Interest Not applicable.

Resource

Implications

Not applicable.

Engagement Not applicable.

Equality Impact

Analysis

Not applicable.

Report History and

Key Decisions

Not applicable.

Next Steps Not applicable.

Appendices Performance & Quality Report - Governing Body Summary

Page 79: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

1. Executive Summary

The Performance and Quality Summary (P&Q) and this report provide an overview of the performance of Mental Health, Community Health Services, Ambulance services and other key non-acute standards in Haringey. Acute Performance information is reported at the Joint Commissioning Committee (JCC) and the papers for JCC have been made available to the

Governing Body. As it is widely seen as a ‘system target’, dependent on multiple agencies to deliver, this paper also provides an overview on A&E performance.

As the performance of acute services is already reported to the Governing Body via the Joint Commissioning Committee report reporting on acute services had been removed from this report to avoid duplication. The Performance and Quality Summary produced by North East

London Commissioning Support Unit (NEL CSU) will report performance of A&E (including the London Ambulance Service performance), Mental Health and Community Services. It should be noted that sections of the report contain different months’ activity, due to the

reporting timetable. This is stated as clearly as possible within the report and near-time local intelligence is also included, where relevant. 2. Accident & Emergency (A&E)

The provider level performance for the A&E four hour waiting standard for June 18 is shown below Main provider A&E performance for the A&E four hour waiting standard:

Our main provider, NMUH, achieved the standard expected within the NHS Operating Plan trajectory for NMUH for 2018/19. The target was 86% while performance for June 2018 was 89.7%. NMUH Performance Update

The A&E standard is dependent on multi-agency working to delivery, including through non-acute providers and social care.

A&E performance has continued to stablilise for the six weeks leading up to 19 August 2018. This is largely due to the implementation of the new Emergency Department (ED) operating model:

Week Provisional Performance Target (improvement

trajectory)

w/e 19th August 2018 84.81% 89%

w/c 12th August 2018 89.54% 89%

w/e 5th August 2018 87.44% 89%

w/e 29th July 2018 86.12% 86%

Provider Performance June 18

Lead commissioner

North Middlesex University Hospital 89.7% Haringey CCG

Whittington Health NHS Trust 90.6% Islington CCG

Page 80: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

w/e 22nd July 2018 83.76% 86%

w/c 15th July 2018 86.70% 86%

Under NHS Operating Plan guidance, NMUH is planning to achieve 90% by September 2018

and 95% by March 2019. Making the step changes necessary to consistently achieve these targets continues to require collaborative and system wide efforts across all partner agencies, managed via the Safer, Faster, Better Programme and overseen by the A&E Delivery Board.

NMUH has exceeded trajectory targets in three of the last six weeks, against a number of challenges including an unprecedented heatwave and CPE infection outbreak. The Safer, Faster, Better Programme (overseen by A&E Delivery Board) has developed a number of High Impact Initiatives which aim to further support ED improvements, including through a breaches

in minors reduction plan and a multi-agency plan to tackle LOS challenges which impact on flow. The weekly breach analyses continues to show bed management (i.e. lack of available beds) to

be the main reason for breaches, accounting for approximately 40% of all breaches over the above six week period. This emphasises the importance of LOS work both within NMUH and between multi-agency partners. Delayed Transfers of Care (DToC) Performance

DToCs at NMUH have been an increasing issue in recent weeks. One of the reasons for this increase has been challenges associated with care home provision. Work is also being

undertaken in partnership with Haringey Local Authority to understand reasons behind apparent increases in social care DTOCs. Weekly multi-agency platinum command meetings attended by Executive level sponsors from

NMUH and Haringey/Enfield CCGs have been established to understand and unblock internal and external reasons for delay amongst patients who have the longest delayed discharges (21 days +). Learning from these meetings is being incorporated into system improvement plans. This approach is in line with good practice mandated within the National Length of Stay

initiative, whereby all systems must reduce the number of patients who experience the longest delays significantly by December 2018. This is because of the safety issues concerned with deconditioning and resultant impact on flow. Continuing Healthcare (CHC) in the acute setting

Haringey CCG continues to perform well with 0% of assessments taking place in an acute setting and 98%+ eligibility decisions on cases with a positive NHS CHC Checklist, being made

within 28 days of the receipt of the checklist (target 80%) in May 2018. 3. Whittington Health (WH) Community Health Services (CHS)

The full report showing the performance for each service against the maximum and average waiting time for urgent and routine appointments is shown in main performance pack. The number of patients seen in the latest month is also indicated.

The community services report shows that in June, for Haringey CCG, eight community services at Whittington Health achieved performance of 95% or above for routine appointments. This compares to ten in May 2018.

Page 81: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

A number of areas that did not achieved their service target did however demonstrate significant improvements in performance in June 2018:

Physiotherapy (from 50% to 77.8%);

MSK – CATS (from 75.2% to 88%); and

Podiatry (from 62.9% to 74.8%)

The Community Services improvement work stream has focused mainly on podiatry, bladder and bowel, nutrition and dietetics and lymphoedema. Whittington Health and the Wellbeing Partnership identified these services for improvement based on their high waiting times, service throughput and recruitment and retention issues. The service improvement work’s focus is on

workforce, efficiency, estates and improving patient satisfaction. Each of these services have observed improvement in performance since improvement work started. The table below summarises when the reduction in waiting times is expected to be achieved by. Service improvement delivery timeline:

Service Agreed date for achievement of target

Podiatry Oct 18

Bladder and Bowel Adults Dec 18

Nutrition and Dietetics Oct 18

Lymphoedema Sept 18

Now that these work streams are well-established further areas are being added to the scope of the improvement work which are summarised in table below. Service improvement delivery timeline for extended scope Service Improvement objective Agreed date for

achievement of target

Intermediate Diabetes Service

Patients are able to expect and receive prompt and accurate assessment and care to enable them to live healthy and independent lives. Reduce the number of inappropriate referrals and support GP/Practice education of Type 2 diabetes.

Dec 18

Respiratory Service

The service will reduce the waiting times for Pulmonary Rehabilitation, in the longer term, the impact of earlier interventions will contribute to a reduction in hospital admissions.

Dec 18

Intermediate Care

The service will continue to ensure patients are seen on time according to clinical need(s) and are offered a rehab programme where necessary.

Dec 18

Community Reablement Team (CRT)

The service will continue to ensure patients are seen on time according to clinical need(s) and are offered a rehab programme where necessary.

Dec 18

Integrated Community Therapy Team (ICTT)

The service aims to improve access rates and see clients in a timely manner, preserve independence for clients living in their own home for longer and reduce the number of cancellations by the team.

Dec 18

Bladder and Bowel (Children and Adults)

The work will address capacity issues with recruitment scheduled. Performance improvement plans include a first point of access, senior team organisational development work and a focus on operational efficiencies.

Feb 19

School Nursing

The work will address capacity issues and an increase in number of referrals, particularly with safeguarding. Recruitment is planned for

Sept 18

Page 82: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

nurses. A review of Emergency Department and Multi-Agency Safeguarding Hub referrals is underway by the safeguarding team. Improvements are expected by September 2018.

Parents & Infants Psychological Services (PIPS)

Address capacity issues (new trainee starting in October 2018) Dec 18

4. Barnet, Enfield & Haringey Mental Health Trust (BEH MHT)

Out of area placements

This relates to people being admitted to an adult acute bed out of the Barnet, Enfield and Haringey area, and is an area of particular focus with NHS England. It also has significant

impact on North Central London’s Sustainability and Transformation Partnerships’ (NCL’s STP) aim of staying within the current mental health acute bed base, and for Haringey CCG and BEH MHT in terms of quality and sustainability. Haringey’s monthly figure for June 2018 was 200 days; a reduction from an average of 325 per month over the previous six months. BEH MHT

led a Perfect Week exercise in August 2018 which has led to the agreement of a significant number of actions and changes, including opening a new acute ward in Barnet to support the trust wide position on this performance. Delayed Transfer of Care (DToC)/Length of stay on acute wards

Haringey Mental Health Delayed Transfer of Care (DToCs) were increased to 5.3% of bed days in June 2018 against a target of 2.5%. A Trust-wide DToC reduction plan has been approved

and is being implemented by the tri-borough System Resilience Lead. Memory Clinic Service (MCS)

Haringey CCG is reassured that the service meets the Memory Service National Accreditation Programme (MSNAP) standard of 12 weeks for people who require complex investigations to determine a diagnosis, standards which have been published by the Royal College of Psychiatrists. However, the service has continued to not provide referral to diagnosis within six

weeks and significant collaborative work is being undertaken between commissioners and BEH operational and clinical leads to improve the pathway. As part of the wider tri-borough and NCL commissioning arrangements, we have engaged the NCL performance and improvement manager who has undertaken an initial demand and capacity review of the service. This will

help to identify issues in relation to the future SLA and to understand current pressures. Recommendations from the demand and capacity review of the service are being shared with Haringey CCG in mid-September. Haringey CCG officers have been meeting with the memory clinic service and The Haynes

dementia hub service, launched in June this year, to create opportunities for people to be referred to post diagnostic support quicker and reduce the need for the memory clinic to offer follow on appointments routinely. This has released some capacity to offer appointments to reduce the waiting list.

Haringey CCG is also actively supporting the development of a memory clinic service Service Level Agreement for all three memory service clinics within Barnet, Enfield & Haringey Mental Health Trust that will ensure equitable standards across BEH for services from 2019.

Page 83: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

We have agreed with our local authority colleagues and the wider dementia care strategy group to develop a co-produced action plan to ensure that all services within Haringey are working

towards the recent NICE guidance on dementia care ‘Dementia: assessment, management and support for people living with dementia and their carers’. https://www.nice.org.uk/guidance/ng97 This has significant guidance on assessment and diagnosis tools and will support more efficient

approaches that will ultimately reduce waiting times and improve quality of post diagnostic support. Membership for the dementia care strategy group includes carer representatives, NMUH, LBH and BEHMT. Membership will be extended from September this year to include increased carer representation. We will also extend an invitation to Healthwatch colleagues to

ensure that we are engaging the widest audience possible to influence the development of the pathway for both patients and their families and carers. An additional invitation has been sent to NHS England regional dementia care leads.

The demand and capacity review will offer a view on whether the current service has the resource to meet the current six week target in all cases. However, the service is MSNAP accredited and has additionally been rated as outstanding by CQC and therefore the general offer is deemed to be of a high standard. The results of the demand and capacity review will

support the consideration of a sustainable approach and it is recommended that a business case will be developed to incorporate reducing the current waits, improve the 6 week target to all applicable cases and to consider the impact of improved pathways both into the service and earlier discharge into post diagnostic support services. The business case will highlight where

efficiencies can be made and what further resource may be required. It is important to note that 32% of people require more than one assessment or diagnostic meeting – something that will require significantly longer than six weeks (dependent on

complexity). However, waiting times from referral to diagnosis for those patients with particularly complex presentations still fall within good practice guidelines. As a result of the need for a second or third appointment, which will apply to one third of all available appointment slots, the number of slots available for the initial assessment and diagnosis appointments has reduced.

The recent NICE guidance on dementia will support more efficient and timelier diagnosis times for dementia potentially reducing the number of second and third appointments. As part of the Dementia Care Strategy, we are working closely with clinical and operational

leads to ensure the service is supported, particularly post diagnosis, to be able to signpost both clients and their families to support services. This will reduce the number of follow on appointments that people may need following their diagnosis and ensure people are supported in the optimal care setting. Haringey CCG are seeking Healthwatch involvement in the dementia

care strategy group. The dementia strategy group met in July and is chaired jointly by HCCG and Haringey social services and has further membership from colleagues from BEH, NMUH, carer representation,

social services and the independent sector. This is where the collaborative work of commissioners comes together with wider stakeholders. It has been working to support the wider dementia care pathway and particularly the flows following diagnosis from the memory clinic service. With Dr Gino Amato offering to support the work of the group, we are hoping to

increase the focus on supporting the referrals into the service even more. Since July the Group has:

Re-drafted dementia care protocols and these will be signed off for wider circulation to

primary and secondary care colleagues following the next strategy meeting in September

Linked the dementia care navigators (1.5WTE) with the Haynes dementia care hub that was launched earlier this year

Page 84: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Agreed to update its overall action plan and focus on the ensuring a multi-agency plan to support the recently published NICE guidance.

Early Intervention Psychosis (EIP)

The Haringey service continues to meet the two-week RTT target of 50%, with performance of

75% in June 2018. Increasing Access to Psychological Therapies (IAPT)

Local June 2018 data showed the IAPT recovery rate was 58.2% (target 50%) and Haringey’s IAPT service continues to improve and exceed all targets. Both the IAPT six weeks and 18 weeks waiting time standards were achieved in June 2018 (93.4% and 100% respectively). Children and Young People Mental Health (CYPMH)

Quarter four 2017/2018 national data is now available. Prior to the data release there was a one-off special data collection by NHS Digital/NHS England for all the providers to contribute.

Local data has previously shown that performance is better than the information NHS England formally publish. This is because it captures activity from our local voluntary sector providers who were not yet able to upload their activity to the national reporting toolkit in a way that is compliant with recent information governance legislation. Therefore the non-submitting local

providers were able to submit their activity and the CCGs signed these off. Haringey CCG achieved 27.3% (2017/18) with the Mental Health Services Data Set (MHSDS) data. Once all local providers’ manual updates were included, Haringey CCG achieved 31.8% against the 30% standard.

There is a local action plan in place at BEH MHT to increase access. Commissioners have been working with NHS England/CSU representatives to develop a local way of uploading the voluntary sector activity sustainably on Haringey CCG’s behalf in accordance with General Data

Protection Regulation (GDPR) standards to the NHS Bureau Service. 5. Quality Premium (QP)

The QP award is based on measures that cover a combination of national and local priorities and reflect the quality of the health services commissioned. Quality Premium 2017/18

The total value of the Quality Premium in 2017/18 was £1,434,000. Payments are usually made in month nine (December 2018) of the financial year. The Quality Premium due in month nine

2018/19 is based on the performance for 2017/18. There were five national measures (early cancer diagnosis, GP access and experience, continuing healthcare, bloodstream infections and mental health) and two local measures (one

of which is the mental health measure and the other is the expected prevalence of people with atrial fibrillation). The indicators for these measures were:

1. For CCGs to show an improvement in early cancer diagnosis (increase proportion

diagnosed at stages 1 or 2);

Page 85: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

2. That the GP survey indicates 85% of respondents said that they had a good experience of making an appointment or that there was a 3 percent increase

(between July 2017 and July 2018 survey results);

3. For CCGs to ensure that in more than 80% of cases with a positive NHS Continuing Health Care (CHC), assessments took place within 28 days, and that less than 15%

of all NHS Continuing Health Care assessments take place in an acute hospital;

4. For CCGs to demonstrate they are reducing Gram Negative Bloodstream Infections (GNBSIs) and inappropriate antibiotic prescribing in at risk groups; and

5. For CCGs to demonstrate a reduction in the number of out of area mental health

placements.

The final data has not yet been confirmed for 2017/18. However, early indications are that at least four of the national improvement measures have not been met (early cancer diagnosis, overall experience of making a GP appointment, CHC assessments and Out of Area Placements) and reductions in gram negative bloodstream infections and inappropriate

antibiotic prescribing will be met. The value of the quality premium paid will be reduced by 25% for each of the constitutional measures which are not met. Of the four constitutional measures, the latest data for 2017/18

shows that at least three of these standards were not met. These were A&E 4 hour waits, Cancer 62 day waits (GP referral to first definitive treatment and Category A RED 1 ambulance calls). The constitutional standard of referral to treatment within 18 weeks (92% of patients) was met. This means that the payment any of the national or local measures which were met will be

reduced by 75%. The current estimate of the likely Quality Premium payment based on the performance for 2017/18 is £93,250.

Quality Premium 2018/19

The 2018/19 Quality Premium scheme guidance published by NHS England in April 2018 has

been restructured to include an incentive on non-elective demand management. In keeping with the 2017/18 Quality Premium, the maximum payment for a CCG is expressed as £5 per head of population, calculated in the same methodology as for CCG running costs,

and made as a programme allocation (this is in addition to a CCG’s main financial allocation and its running costs allowance). Emergency Demand Management Indicators (£210M national allocation):

Page 86: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Indicator Rationale Weighting

Type 1 A&E

Attendances

Total number of type 1 A&E attendances for 2018/19 is no greater than their

total planned number of type 1 A&E attendances in 2018/19. These will be

measured as simply the difference between actual and plan e.g. [2018/19

actual attendances] - [2018/19 planned attendances]

Non-Elective

admissions with zero

length of stay

Total number of actual non-elective admissions with LOS =0 days in 2018/19

is no greater than their total planned number of non-elective admissions with

LOS = 0 days in 2018/19. These will be measured as simply the difference

between actual and plan e.g. [2018/19 actual attendances] - [2018/19 planned

attendances]

Non-Elective

admissions with

length of stay of 1 day

or more

Total number of actual non-elective admissions with LOS >=1 days in 2018/19

is no greater than their total planned number of non-elective admissions with

LOS >=1 days in 2018/19. This will be measured as simply the difference

between actual and plan

i.e. [2018/19 actual admissions] - [2018/19 planned admissions].

50%

50%

Page 87: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Quality Indicators (£68M national allocation):

*CCGs can select one local indicator which will be worth 15% of the QP for the Quality

Indicators. In 2017 Haringey CCG chose expected prevalence of people with atrial fibrillation as its local indicator for the 2017/2019 quality premium and this has been retained for the 2018/19 scheme.

Quality, Financial and Constitutional Gateways will again be core requirements for payment in 2018/19. However, given the introduction of an emergency demand management element and to remain aligned with Operating Plan guidance, NHS England have suspended the operation of the tests relating to Ambulance response times and 4 Hour A&E.

No. Simple QP Inidcator name Target BaselineYTD

PerformanceWeighting

1 Cancer diagnosed at early stage. 60% 56% 56% (2016 Q4) 17.00%

2GP Survey - patients experienceing a good service when making

an appointment.68% In July 2019 65% (August 2018) 65% (August 2018) 17.00%

NHS CHC Checklist decicsion made within 28 days. Above 80% To be Compliant 83% - Q1 2018/19

Less than 15% of NHS CHC Checklists take place in acute hospital

settingBelow 15% To be Compliant 11% - Q1 2018/19

4

Improved Access to Children & Young People’s Mental Health

Services: The increase in activity to enable children and young

people aged under 18 with a diagnosable Mental Health

condition to receive treatment in NHS funded community

services.

Above 32% 27.3% (2017/18) 27.3% (2017/18) 17.00%

The reduction target in all E coli BSI reported at CCG level below 159 155 - March 2018 155 - March 2018 5.10%

Collection and reporting of a core primary care data set for all E

coli casesNo Target No Target Ongoing 2.55%

A 30% reduction in the number of Trimethoprim items prescribed

to patients aged 70 years or greater

30% below the

June 2015-May

2016 baseline

1854 1574 (May 2018) 3.40%

(STAR-PU) must be equal to or below England 2013/14 mean

performance value of 1.161 items per STAR-PUBelow 1.161 0.645 (March 2018) 0.645 (May 2018) 1.70%

(STAR-PU) equal to or below 0.965 items per STAR-PU (A STAR-PU

(or Specific Therapeutic group Age-sex Related Prescribing Unit)

is a value calculated to reflect not only the number of patients in

a practice, but also the age and sex mix of that group)

Below 0.965 0.645 (March 2018) 0.645 (May 2018) 4.25%

6Improvement in the proportion of people with atrial fibrillation

with CHADSVASC2 score>273.53% (Oct 2017) 72.53% (Oct 2017)

Next data due Nov

201815.00%

5

3 17.00%

Page 88: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

NHS constitution gateway indicators are therefore:

Some of the measures can be reported on monthly, some quarterly and others annually (as performance is derived from national surveys). A summary of performance for indicators, which are available to be reported on, will be included within the next Performance report. 6. London Ambulance Service (LAS)

The new national ambulance response time standards were established under the Ambulance

Response Programme Initiative (ARP) led by NHS England. The aim of the ARP is to ensure that:

• The sickest patients receive the fastest response • All patients get the best response allocated to them • No one is left waiting for an unacceptably long time for an ambulance to arrive

The new ambulance response time standards are summarised below.

Category Basic definition Response time standard

Category 1

Life threatening injuries and illness (e.g. anaphylactic shock or bee sting)

Response time with an average of 7 minutes Response before 15 minutes for 9 out of 10 calls (90th centile)

Category 2

Emergency calls (e.g. stroke) Response time with an average of 18 minutes Response before 40 minutes for 9 out of 10 calls (90th centile)

Category 3

Urgent calls (e.g. uncomplicated diabetes – some of these may be treated in patient’s own home)

Response before 120 minutes for 9 out of 10 calls (90th centile)

Category 4

Less urgent likely requiring transport or hear and treat

Response before 180 minutes for 9 out of 10 calls (90th centile)

The four new patient categories are:

Category One – Life Threatening Category Two – Emergencies Category Three – Urgent Category Four– Less Urgent

IndicatorMarch 2018

(Baseline)

% Reduction

of QP

The number of patients on an incomplete pathway

not to be higher in March 2019 than in March 2018 19,250 50%

Maximum two month (62-day) wait from urgent GP

referral to first definitive treatment for cancer81.13% 50%

Page 89: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

The LAS performance for June 2018 against the national standards is shown in the table below:

Category Measure National

Standard April May June

1 Mean response time 7 minutes 00:06:52 00:06:54 00:07:17

90th centile 15 minutes 00:11:15 00:11:21 00:11:46

2 Mean response time 18 minutes 00:16:54 00:18:41 00:20:02

90th centile 40 minutes 00:33:16 00:38:11 00:40:52

3 Mean response time 60 minutes n/a 00:55:50 01:01:12

90th centile 120 minutes 01:49:47 02:12:40 02:22:53

4 90th centile 180 minutes 02:05:05 02:24:33 02:28:17

In June 2018, LAS achieved four out of the seven measures against the national standards

when evaluating city-wide performance. The table below shows the LAS Performance by STP for June 2018:

NCL achieved the C1 90th Centile target and the C4 90th Centile target. The LAS C4 90th centile has been well within the 3 hour standard for the eight months since ARP was implemented

The table below shows a further breakdown for Haringey CCG in June 2018: C1 Mean C1 90th

Centile

C2 Mean C2 90th

Centile

C2 Mean C3 90th

Centile

C4 90th

Centile

National

Standard

7

minutes

(00:07:00)

15

minutes

(00:15:00)

18

minutes

(00:18:00)

40

minutes

(00:40:00)

60

minutes

(01:00:00)

120

minutes

(02:00:00)

180

minutes

(03:00:00)

Haringey

CCG 00:07:33 00:11:27 00:22:43 00:48:08

01:27:35 03:15:29 01:50:38

Haringey CCG achieved C1 90th Centile and C4 90th Centile. Most other CCGs had similar performance. Drivers of underperformance included delays with handovers by Acute Trusts and increased demand for Category 1.

Hospital handovers have a direct impact on performance, particularly across non-life threatening categories as ambulances are less available for conveyances. It has been recognised by regulators nationally that Ambulance services will not be in a position

to meet ARP standards straight away and performance management against these standards comes into effect in September 2018.

Page 90: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey CCG Governing Body

Performance and Quality Report August 2018

Page 91: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Contents

Item Page

Haringey CCG A&E Summary 3

Whittington Health NHS Trust Community Services Dashboards 4

Haringey CCG Mental Health Performance Dashboards 8

NMUH A&E Performance Summary 11

NMUH Quality Summary 13

Barnet, Enfield and Haringey MH Trust Dashboards and Summary

London Ambulance Service

14

17

2

Page 92: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Key Messages

A&EFrom April 2018 CCG level A&E Performance is no longer measured as a quality premium indicator. As with CCG Operating Plans performanceis measured at provider level with CCGs responsible for the performance of the providers for which they are lead commissioners. The mainproviders for Haringey CCG patients performed as below for June 2018 against the four hour waiting standard:

North Middlesex University Hospital 89.7%Whittington Health NHS Trust 90.6% (Lead Commissioner Islington CCG)

At North Middlesex University Hospital, the local improvement trajectory of 86% was achieved. The key issues were;

• Lower than anticipated streaming of patients via the Urgent Care Centre (approximately 46% through June 2018, against a trajectory of50%), though this is strong performance in comparison to other NCL Trusts. A training plan is place, which will run through until the end ofAugust 2018, with the intention of reducing minors breaches.

• Longer than expected waiting times in ambulatory care for triage, though this has been reducing since early May 2018, from highs of 50minutes, to 28 minutes at the end of June 2018.

• Insufficient discharges, particularly, earlier in the day and lower than expected number of patients utilising the Discharge to Assesspathways. This causes flow pressures from ED, resulting in bed management issues accounting for the majority of breaches.

The Whittington Health NHS Trust/Islington CCG System revised the Accident and Emergency Improvement Plans in May 2018 with an improvement trajectory to achieve and sustain 95% from September 2018 onwards. A Rapid Improvement Plan to support this was agreed in May 2018 and is reviewed and updated monthly at the Accident and Emergency Delivery Board.

Haringey CCGA&E Summary

3

Page 93: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

4

Whittington Health NHS TrustCommunity Services Dashboard

Mar-18 Apr-18 May-18

8.10% 8.00% 8.30%

58994 53835 62439

96.50% 96.20% 95.90%

779 1206 1181

New birth vis i ts % within 2 weeks 90.50% 89.40% 92.70%

8 week review % within 8 weeks 40.10% 38.00% 48.20%

HR1 % within 15 months 64.50% 65.30% 74.50%

HR2 % within 30 months 60.50% 56.90% 63.60%

New birth vis i ts % within 2 weeks 96.40% 94.40% 93.00%

8 week review % within 8 weeks 66.10% 68.10% 73.50%

HR1 % within 15 months 81.50% 69.40% 80.00%

HR2 % within 30 months 76.50% 77.80% 76.70%

District nurs ing - 48 hour response time (a l l CCGs) 86.70% 83.20% 91.00%

District nurs ing - 2 hour response time (a l l CCGs) 92.50% 86.70% 88.90%

ICSU Service Name%

Threshold

Target

WeeksMar-18 Apr-18 May-18

Avg Wait

(May-18)

No of Pts

Seen

%

Threshold

Target

WeeksMar-18 Apr-18 May-18

Avg Wait

(May-18)

No of Pts

Seen

CYP CAMHS >95% 8 70.10% 66.20% 67.80% 6.6 149 >95% 2 100.00% 100.00% 0

CYP Child Development Services >95% 8 66.70% 44.20% 62.30% 1.2 53 >95% 2 0

CYP Community Children's Nursing >95% 2 78.70% 84.10% 85.70% 7.9 84 >95% 1 100.00% 100.00% 100.00% 0.2 9

CYP Community Paediatrics Services >95% 12 80.60% 59.10% 86.50% 5.1 37 >95% 1 46.30% 36.40% 43.10% 5.1 51

CYP Haematology Service >95% 12 100.00% 100.00% 100.00% 1 8 >95% 2 0

CYP Looked After Children >95% 4 55.60% 80.00% 79.20% 4.4 24 >95% 2 0

CYP Occupational Therapy >95% 8 46.40% 19.20% 30.40% 13.3 23 >95% 2 0

CYP Physiotherapy >95% 8 54.70% 55.70% 47.80% 7.5 92 >95% 2 0

CYP PIPS >95% 12 100.00% 100.00% 100.00% 4.5 18 >95% 0

CYP School Nursing >95% 12 81.70% 90.80% 88.00% 5.3 100 >95% 0

CYP Speech and Language Therapy >95% 6 33.70% 35.90% 34.60% 9.4 185 >95% 2 12.50% 0.00% 4 <5

IM Bladder and Bowel - Children >95% 12 57.10% 28.60% 37.50% 13.8 16 >95% 0

EUC Community Matron >95% 6 100.00% 100.00% 95.70% 1.1 47 >95% 2 0

IM Adult Wheelchair Service >95% 8 100.00% 87.10% 97.80% 3.7 46 >95% 2 0.00% 0

IM Cardiology Service >95% 6 93.10% 100.00% 100.00% 2.7 18 >95% 2 0.00% 0.00% 100.00% 1.3 6

IM Community Rehabilitation (CRT) >95% 12 94.40% 97.70% 95.40% 3.6 131 >95% 2 62.10% 62.90% 56.50% 2.2 23

IM Community Rehabilitation (ICTT) >95% 12 84.20% 78.10% 84.80% 5.8 349 >95% 2 42.50% 29.30% 37.90% 3.6 87

IM Diabetes Service >95% 6 66.40% 65.70% 72.20% 5.4 108 >95% 2 100.00% 100.00% 100.00% 0.5 <5

IM Intermediate Care (REACH) >95% 6 85.70% 86.30% 80.60% 5 93 >95% 2 81.40% 60.70% 41.40% 3.3 29

IM Paediatric Wheelchair Service >95% 8 83.30% 80.00% 100.00% 5.6 <5 >95% 2 0

IM Respiratory Service >95% 6 80.00% 53.20% 36.40% 6.2 107 >95% 2 15.60% 6.50% 0.00% 8.2 6

PPP Bladder and Bowel - Adult >95% 12 51.80% 44.30% 50.40% 14.7 496 >95% 2 0.00% 0.00% 0

PPP Musculoskeletal Service - CATS >95% 6 94.90% 81.60% 76.00% 4.3 119 >95% 2 0.00% 0.00% 75.00% 2 <5

PPP Musculoskeletal Service - Routine >95% 6 83.90% 89.50% 92.10% 3.5 1539 >95% 2 1.3 15

PPP Nutrition and Dietetics >95% 6 72.50% 74.60% 83.90% 3.5 211 >95% 2 72.50% 74.60% 83.90% 0

PPP Podiatry (Foot Health) >95% 6 58.20% 38.20% 59.70% 5.3 645 >95% 2 58.20% 38.20% 59.70% 3 9

PPP Lymphodema Care >95% 6 83.30% 73.30% 95.20% 3.1 21 >95% 2 0

PPP Tissue Viability Service >95% 6 0 >95% 2 81.00% 74.70% 69.40% 1.9 98

80% in 2 hours

Routine Referral Urgency Urgent Referral Urgency

Is l ington HV

reviews

95%

95% in 2 days

FFT% Pos i tive (a l l CCGs) >90%

FFT responses (a l l CCGs) >1500

Haringey HV

reviews

95%

Whittington Health - NELCSU CCGs

KPI Measure Target threshold

DNA rate% <10%

Face to Face contacts

ICSU Service Name%

Threshold

Target

WeeksApr-18 May-18 Jun-18

Avg Wait

(June-18)

No of Pts

Seen

%

Threshold

Target

WeeksApr-18 May-18 Jun-18

Avg Wait

(June-18)

No of Pts

Seen

CYP CAMHS >95% 8 66.40% 67.10% 60.90% 7.8 133 >95% 2 100.00% 100.00% 0

CYP Child Development Services >95% 8 43.40% 62.30% 56.50% 1.1 46 >95% 2 0

CYP Community Children's Nursing >95% 2 82.40% 85.20% 83.30% 10.3 77 >95% 1 100.00% 100.00% 100.00% 0.2 7

CYP Community Paediatrics Services >95% 12 59.10% 84.20% 83.30% 6.4 48 >95% 1 39.10% 44.20% 31.00% 6.4 42

CYP Haematology Service >95% 12 100.00% 100.00% 100.00% 0.8 11 >95% 2 0

CYP Looked After Children >95% 4 75.00% 78.60% 77.30% 6.9 22 >95% 2 0

CYP Occupational Therapy >95% 8 19.20% 30.40% 31.80% 16.6 22 >95% 2 0

CYP Physiotherapy >95% 8 55.70% 47.30% 54.30% 7.9 92 >95% 2 0

CYP PIPS >95% 12 100.00% 100.00% 70.00% 7.7 10 >95% 0

CYP School Nursing >95% 12 89.70% 86.50% 76.80% 7.7 95 >95% 0

CYP Speech and Language Therapy >95% 6 35.80% 35.90% 42.20% 8.8 211 >95% 2 0.00% 33.30% 5 <5

IM Bladder and Bowel - Children >95% 12 28.60% 37.50% 26.70% 11.5 15 >95% 0

EUC Community Matron >95% 6 100.00% 95.70% 100.00% 0.7 43 >95% 2 0

IM Adult Wheelchair Service >95% 8 87.10% 97.80% 85.70% 4.1 28 >95% 2 0

IM Cardiology Service >95% 6 100.00% 100.00% 100.00% 1.9 33 >95% 2 0.00% 100.00% 81.80% 1.4 11

IM Community Rehabilitation (CRT) >95% 12 96.90% 95.50% 92.60% 4.7 136 >95% 2 62.90% 56.50% 68.80% 2.1 32

IM Community Rehabilitation (ICTT) >95% 12 78.10% 84.90% 89.20% 5 296 >95% 2 29.30% 37.50% 43.40% 3 99

IM Diabetes Service >95% 6 65.70% 71.60% 67.10% 5.5 143 >95% 2 100.00% 100.00% 50.00% 6 <5

IM Intermediate Care (REACH) >95% 6 86.30% 80.60% 73.30% 6.7 165 >95% 2 60.70% 41.40% 45.80% 3.3 24

IM Paediatric Wheelchair Service >95% 8 80.00% 100.00% 66.70% 6.6 <5 >95% 2 0

IM Respiratory Service >95% 6 53.20% 36.40% 63.60% 4.9 110 >95% 2 6.50% 0.00% 100.00% 1.4 <5

PPP Bladder and Bowel - Adult >95% 12 42.20% 50.00% 60.80% 12 143 >95% 2 0.00% 0

PPP Musculoskeletal Service - CATS >95% 6 81.60% 76.00% 89.60% 3.8 469 >95% 2 0.00% 75.00% 100.00% 1.3 <5

PPP Musculoskeletal Service - Routine >95% 6 89.40% 92.10% 92.60% 3.8 1469 >95% 2 68.20% 73.30% 42.90% 2.7 7

PPP Nutrition and Dietetics >95% 6 74.30% 83.90% 89.70% 3.6 184 >95% 2 0

PPP Podiatry (Foot Health) >95% 6 38.20% 59.70% 72.80% 4.9 588 >95% 2 38.20% 59.70% 72.80% 3.6 3

PPP Lymphodema Care >95% 6 73.30% 95.20% 95.00% 2.9 20 >95% 2 0

PPP Tissue Viability Service >95% 6 96.30% 93.90% 99.00% 1.5 97 >95% 2 100.00% 0.4 <5

Routine Referral Urgency Urgent Referral Urgency

Page 94: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

5

Whittington Health NHS TrustCommunity Services Dashboard

Mar-18 Apr-18 May-18

8.50% 8.80% 9.00%

25275 23099 26551

96.50% 96.20% 95.90%

779 1206 1181

New birth vis i ts % within 2 weeks 90.50% 89.40% 92.70%

8 week review % within 8 weeks 40.10% 38.00% 48.20%

HR1 % within 15 months 64.50% 65.30% 74.50%

HR1 % within 30 months 60.50% 56.90% 63.60%

District nurs ing - 48 hour response time (a l l CCGs) 86.70% 83.20% 91.00%

District nurs ing - 2 hour response time (a l l CCGs) 92.50% 86.70% 88.90%

ICSU Service Name%

Threshold

Target

WeeksMar-18 Apr-18 May-18

Avg Wait

(May-18)

No of Pts

Seen

%

Threshold

Target

WeeksMar-18 Apr-18 May-18

Avg Wait

(May-18)

No of Pts

Seen

CYP CAMHS >95% 8 66.70% 100.00% 75.00% 4.6 <5 >95% 2 0

CYP Child Development Services >95% 8 100.00% 80.00% 100.00% 0.9 7 >95% 2 0

CYP Community Children's Nursing >95% 2 66.70% 70.00% 83.30% 2.7 6 >95% 1 0

CYP Community Paediatrics Services >95% 12 78.90% 50.00% 93.30% 5.6 15 >95% 1 46.30% 25.70% 35.00% 5.6 40

CYP Haematology Service >95% 12 100.00% 100.00% 1 6 >95% 2 0

CYP Looked After Children >95% 4 100.00% 100.00% 84.60% 5.8 13 >95% 2 0

CYP Occupational Therapy >95% 8 50.00% 0.00% 0.00% 23.4 8 >95% 2 0

CYP Physiotherapy >95% 8 44.90% 42.90% 50.00% 8.1 36 >95% 2 0

CYP PIPS >95% 12 100.00% 100.00% 100.00% 4.8 17 >95% 0

CYP School Nursing >95% 12 73.20% 85.70% 74.30% 7.9 35 >95% 0

CYP Speech and Language Therapy >95% 6 29.10% 28.10% 31.50% 9.5 73 >95% 2 12.50% 0.00% 4 <5

IM Bladder and Bowel - Children >95% 12 0 >95% 0

EUC Community Matron >95% 6 100.00% 100.00% 92.00% 1.4 25 >95% 2 0

IM Adult Wheelchair Service >95% 8 100.00% 87.10% 97.80% 3.7 45 >95% 2 0.00% 0

IM Cardiology Service >95% 6 95.00% 100.00% 100.00% 2.9 9 >95% 2 100.00% 1.7 <5

IM Community Rehabilitation (CRT) >95% 12 83.30% 100.00% 100.00% 6 <5 >95% 2 100.00% 0.1 <5

IM Community Rehabilitation (ICTT) >95% 12 84.30% 78.30% 83.90% 6.1 329 >95% 2 42.70% 27.50% 37.20% 3.7 86

IM Diabetes Service >95% 6 59.10% 60.30% 65.50% 5.8 55 >95% 2 100.00% 100.00% 100.00% 1 <5

IM Intermediate Care (REACH) >95% 6 100.00% 0.00% 100.00% 1.3 <5 >95% 2 100.00% 100.00% 100.00% 0.9 <5

IM Paediatric Wheelchair Service >95% 8 83.30% 80.00% 100.00% 5.6 <5 >95% 2 0

IM Respiratory Service >95% 6 68.40% 33.30% 26.90% 7.1 67 >95% 2 7.10% 6.50% 0.00% 8.2 6

PPP Bladder and Bowel - Adult >95% 12 42.90% 55.30% 66.00% 12.2 286 >95% 2 0.00% 0

PPP Musculoskeletal Service - CATS >95% 6 93.70% 79.20% 75.20% 4.5 50 >95% 2 0.00% 0.00% 50.00% 2.4 <5

PPP Musculoskeletal Service - Routine >95% 6 79.00% 88.00% 90.80% 3.5 884 >95% 2 1.6 7

PPP Nutrition and Dietetics >95% 6 84.00% 79.00% 90.30% 3.1 113 >95% 2 0

PPP Podiatry (Foot Health) >95% 6 64.30% 34.70% 62.90% 5.1 340 >95% 2 64.30% 34.70% 62.90% 2.2 <5

PPP Lymphodema Care >95% 6 66.70% 81.80% 100.00% 2.6 11 >95% 2 0

PPP Tissue Viability Service >95% 6 0 >95% 2 88.00% 95.70% 66.70% 2.1 24

95% in 2 days

80% in 2 hours

Routine Referral Urgency Urgent Referral Urgency

>95%

FFT% Pos i tive (a l l CCGs) >90%

FFT responses (a l l CCGs) >1500

Haringey HV

reviews

Face to Face contacts

Whittington Health - Haringey CCG

KPI Measure Target threshold

DNA rate% <10%

ICSU Service Name%

Threshold

Target

WeeksApr-18 May-18 Jun-18

Avg Wait

(June-18)

No of Pts

Seen

%

Threshold

Target

WeeksApr-18 May-18 Jun-18

Avg Wait

(June-18)

No of Pts

Seen

CYP CAMHS >95% 8 100.00% 75.00% 66.70% 6.6 <5 >95% 2 0

CYP Child Development Services >95% 8 80.00% 100.00% 100.00% 0.2 10 >95% 2 0

CYP Community Children's Nursing >95% 2 70.00% 83.30% 100.00% 2.8 10 >95% 1 0

CYP Community Paediatrics Services >95% 12 50.00% 93.30% 90.50% 6.9 21 >95% 1 25.70% 35.00% 16.70% 6.9 30

CYP Haematology Service >95% 12 100.00% 100.00% 0.6 <5 >95% 2 0

CYP Looked After Children >95% 4 100.00% 84.60% 100.00% 3 6 >95% 2 0

CYP Occupational Therapy >95% 8 0.00% 0.00% 11.10% 27.6 9 >95% 2 0

CYP Physiotherapy >95% 8 42.90% 50.00% 77.80% 6.4 27 >95% 2 0

CYP PIPS >95% 12 100.00% 100.00% 62.50% 8.4 8 >95% 0

CYP School Nursing >95% 12 85.70% 75.00% 75.90% 7.4 58 >95% 0

CYP Speech and Language Therapy >95% 6 28.10% 31.50% 28.20% 9.9 71 >95% 2 0.00% 50.00% 5 <5

IM Bladder and Bowel - Children >95% 12 0 >95% 0

EUC Community Matron >95% 6 100.00% 92.00% 100.00% 0.8 22 >95% 2 0

IM Adult Wheelchair Service >95% 8 87.10% 97.80% 88.90% 3.9 27 >95% 2 0

IM Cardiology Service >95% 6 100.00% 100.00% 100.00% 2.1 17 >95% 2 100.00% 0.00% 2.7 <5

IM Community Rehabilitation (CRT) >95% 12 100.00% 100.00% 100.00% 5.6 <5 >95% 2 100.00% 100.00% 0.7 <5

IM Community Rehabilitation (ICTT) >95% 12 78.30% 83.90% 88.30% 5.2 274 >95% 2 27.50% 37.20% 43.60% 3 94

IM Diabetes Service >95% 6 60.30% 65.50% 63.00% 5.8 81 >95% 2 100.00% 100.00% 0.00% 11.9 <5

IM Intermediate Care (REACH) >95% 6 0.00% 100.00% 0.00% 31.4 <5 >95% 2 100.00% 100.00%

IM Paediatric Wheelchair Service >95% 8 80.00% 100.00% 66.70% 6.6 <5 >95% 2

IM Respiratory Service >95% 6 33.30% 26.90% 54.70% 5.4 75 >95% 2 6.50% 0.00%

PPP Bladder and Bowel - Adult >95% 12 55.30% 66.00% 59.30% 13.4 59 >95% 2

PPP Musculoskeletal Service - CATS >95% 6 79.20% 75.20% 88.00% 3.9 251 >95% 2 0.00% 50.00%

PPP Musculoskeletal Service - Routine >95% 6 88.00% 90.80% 92.20% 3.7 805 >95% 2 70.60% 71.40% 33.30% 2.8 <5

PPP Nutrition and Dietetics >95% 6 79.00% 90.30% 91.90% 3.4 99 >95% 2 0

PPP Podiatry (Foot Health) >95% 6 34.70% 62.90% 74.80% 5 282 >95% 2 34.70% 62.90% 74.80% 1.1 <5

PPP Lymphodema Care >95% 6 81.80% 100.00% 91.70% 3 12 >95% 2 0

PPP Tissue Viability Service >95% 6 100.00% 95.80% 100.00% 1.7 27 >95% 2

Routine Referral Urgency Urgent Referral Urgency

Page 95: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Key Messages

Community Services The main areas of concern within the Community Services are, Bladder and bowel, nutrition and dietetics, podiatry and lymphedema. Whilst all four areas are underperforming, there has been improvement across each over the past three months. Whittington Health NHS Trust has provided a detailed breakdown of those services not meeting current access standards, the reasons for the performance, actions to address it and anticipated dates for recovery at a service level. Anticipated dates for recovery of the waiting time positions for services range from August 2018 to March 2019.

On July 24th 2018 Islington CCG issued a contract performance notice to Whittington Health to ‘ formally raise concerns regarding on-going under performance in regards to waiting times into the CAMHs emotional health and behaviour pathways’. Discussions around a recovery plan to return the service to a reasonable waiting time position will take place in August 2018.

Haringey CCGCommunity Services Summary

6

Page 96: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Whittington Health NHS TrustPerformance & Quality Summary

7

Key issue Priority actions

Community Access and Waiting Times

At the July 2018 meeting of the Community Service Improvement Group it was noted that although many waiting time indicators on the community performance dashboard were red, there was an upward trajectory in terms of improvement, for each of the specific areas identified for improvement by the group:

Bladder and bowel April 50.7%, May: 57.3%, June: 68.3%.Nutrition and dieteticsApril 74.1%, May: 83.2%, June: 87.9%.PodiatryApril 37.9%, May: 59.8%, June: 69.3%.LymphedemaApril 73.3%, May: 95.2%, June: 94.1%.

Whittington Health have provided a detailed breakdown of those services not meeting current access standards, the reasons for the performance, actions to address it and anticipated dates for recovery at a service level. Anticipated dates for recovery of the waiting time positions for services range from August 2018 to March 2019.

• Update following Community Service Improvement Group in July 2018

• Formal notes from the meeting were not available at the time of writing however:

• It was agreed that children and young people services were a priority and future meetings of the Community Service Improvement Group would be split to allow distinctive time allocations for discussion of adult services and discussion of children and young people services.

• Themes from the discussion around children and young people services were:

• Data Quality for children and young people services is not as good as for adult services – particularly around urgent and routine definitions

• The need to look at the overall paediatric workforce and workload

• Assess how staff can be best utilised to support provision across services rather than based on historical departmental boundaries

• A strategic plan for community services for children and young people, based on analysis of demand and capacity, to be brought to the Community Service Improvement Group by the end of August 2018.

Page 97: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey CCGMental Health Performance Dashboard

*Latest data is provisional and unpublishedNHS Digital data published by NHS DigitalLocal data derived from Provider reports to NHS England 8

Theme KPI/Measure SourceReporting

PeriodActual Standard

Current Month and Previous Month's Trend

Blue = Actual Red = Target

Dementia Diagnosis Rate (Age

65+)NHS Digital Jun-18 67.43% 66.7%

The percentage of RTT First

Episode Psychosis (FEP) periods

within 2 weeks of referral. *

NHS Digital Jun-18 75.00% 50%

Proportion of patients on CPA who

were followed up within 7 days after

discharge from psychiatric inpatient

care

NHS Digital 2017-18 Q4 98.77% 95%

Proportion of admissions to acute

wards that were gate kept by the

CRHT teams

NHS Digital 2017-18 Q4 97.37% 95%

Proportion of Children and Young

people with eating disorders

(routine cases) that wait 4 weeks or

less from referral to start of NICE-

approved treatment

NHS Digital 2017-18 Q4 91.67% 95%

Proportion of Children and Young

people with eating disorders (urgent

cases) that wait 1 week or less from

referral to start of NICE-approved

treatment

NHS Digital 2017-18 Q4 100.00% 95%

HARINGEY

CCG

MENTAL

HEALTH

68.60% 68.50% 67.67% 67.20% 67.82% 68.27% 67.80% 67.61% 68.50% 67.90% 67.70% 67.76% 67.43%

Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18

50.00% 62.50% 75.00% 80.00% 77.78% 62.50%100.00%

75.00% 60.00% 57.14%87.50% 92.86% 75.00%

Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18

99.28% 99.33% 100.00% 98.77%

2017-18 Q1 2017-18 Q2 2017-18 Q3 2017-18 Q4 2018-19 Q1

96.12%99.32% 100.00%

97.37%

2017-18 Q1 2017-18 Q2 2017-18 Q3 2017-18 Q4 2018-19 Q1

92.86%

100.00%

91.67%

2017-18 Q1 2017-18 Q2 2017-18 Q3 2017-18 Q4 2018-19 Q1

50.00%

100.00% 100.00%

2017-18 Q1 2017-18 Q2 2017-18 Q3 2017-18 Q4 2018-19 Q1

Page 98: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

NHS Digital data published by NHS Digital

Local data derived from Provider reports to NHSE

9

Haringey CCGImproving Access to Psychological Therapies

Performance Dashboard

Theme KPI/Measure SourceReporting

PeriodActual Standard

Current Month and Previous Month's Trend

Blue = Actual Red = Target

% Waited less than 6 weeks for a

course of treatment (for those

finishing a course of treatment)

NHS Digital Apr-18 93.00% 75%

% Waited less than 18 weeks for a

course of treatment (for those

finishing a course of treatment)

NHS Digital Apr-18 99.00% 95%

Reliable Recovery Rate NHS Digital Apr-18 53.00%

Recovery Rate NHS Digital Apr-18 54.00% 50%

Recovery Rate - QUARTERLY NHS Digital 2017-18 Q4 53.00% 50.00%

Access Rate NHS Digital Apr-18 1.81% 1.40%

Access Rate - QUARTERLY NHS Digital 2017-18 Q4 4.29% 4.20%

BME % of Numbers Entering

Treatment - QUARTERLYNHS Digital 2017-18 Q4 56.33%

HARINGEY

CCG IAPT

96.00% 94.00% 93.00%97.00% 98.00% 95.00% 93.00% 94.00% 92.00% 92.00% 94.00% 93.00%

May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18

100.00% 99.00% 99.00% 100.00% 100.00% 100.00% 96.00% 98.00% 98.00% 99.00% 98.00% 99.00%

May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18

47.00% 52.00% 47.00% 50.00% 53.00% 49.00% 49.00% 45.00% 47.00% 45.00% 57.00% 53.00%

May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18

50.00% 55.00% 50.00% 54.00% 56.00% 51.00% 52.00% 51.00% 48.00% 50.00% 60.00% 54.00%

May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18

1.70% 1.57%1.13% 1.24%

1.56%

0.94%

1.54%

0.87%

1.49% 1.39% 1.41%1.81%

May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18

51.00% 53.00% 52.00% 53.00%

2017-18 Q1 2017-18 Q2 2017-18 Q3 2017-18 Q4

4.36%3.94%

3.34%

4.29%

2017-18 Q1 2017-18 Q2 2017-18 Q3 2017-18 Q4

55.74% 53.99% 54.27% 56.33%

2017-18 Q1 2017-18 Q2 2017-18 Q3 2017-18 Q4

Page 99: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

10

Key Messages

Barnet Enfield and Haringey Mental Health Trust Crisis Resolution and Home Treatment TeamIn April 2018 the performance reporting changed to 95% having a “Face to face assessment within 4 hours for those triaged as Urgent - clinically

appropriate following referral to Crisis Resolution and Home Treatment Team”. This has been monitored for three months and in June 2018 Barnet Enfield and Haringey Mental Health Trust reported 26.1% (161 out of a total of 617 referrals) were assessed within four hou rs, if the clinically triaged figures are used 36.9% were assessed (82 out of 222 referrals). A three month review is required on the impact of the new clinically triaged as appropriate including a commentary on change in service outcomes as the services are seeing / assessing less clients within four hours since the changes were implemented.

Early Intervention in Psychosis Commissioners are working with Barnet Enfield and Haringey Mental Health Trust to finalise the evidence required from the Ear ly Intervention in Psychosis services in terms of the National Institute for Health and Care Excellence compliant treatments and timely access. The Early Intervention in Psychosis Network Report on the recent audit of all EIP teams in England have been received with a Trust overview and Essential Standards included in the report. It is recommended that in addition to the audit evidence a plan with traject ory on the move to using structured clinical coded recording (SNOMED CT) and outcome measures is required.

Children and Adolescent Mental Health Services There are two main priorities firstly the time waiting to first appointment (standard 13 weeks) and the Access to Treatment (second appointment). The overall waiting list for Children and Young People increased by 25 to 866 in June 2018 with 212 in June 2018 waiting over 13 weeks. The Children and Young People seen within 13 week waiting time for first appointment decreased in June 2018 to 73.8% The number of children and young people seen who waited over 13 weeks improved to 98 in June 2018. Barnet Enfield and Haringey Mental Health Trust are reporting staff shortages within the Barnet and Enfield Child and Adolescent Mental Health Services which has led to an increase in long waits.

Reporting against the Five Year Forward View Improving Access Rate to Children and Young People Mental has increased to 32% for 2018 / 2019 for the proportion of children and young people aged 0-18 with a diagnosable mental health condition who have received treatment (two attendances). Barnet Enfield and Haringey Mental Health Trust contributed cumulatively April - June 2018 3026 treatment (second) contacts to the 2018 /2019 standard, therefore achieving 14.2% against the expected 8%. The Haringey Services are showing acontribution below expected at 5.1% against 8% expected.

Haringey CCGMental Health Summary

Page 100: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

North Middlesex University Hospital A&E Performance

11

Key issue Priority actions

A&EPerformance at North Middlesex University Hospital showed further improvement, from 85.16% in May 2018 to 89.67% in June 2018. Whilst the national standard has not been achieved, the local improvement trajectory of 86% was achieved.

The key factors impacting performance are:• Insufficient streaming of patients via

the Urgent Care Centre, though performance is strong in comparison to other NCL Trusts

• Longer than expected waiting times in ambulatory care

• Slow discharges from the wards, with insufficient patients ‘home before lunch’ and lower than expected number of patients utilising the ‘Discharge to Assess’ pathways. This causes flow pressures from ED, resulting in bed management issues accounting for the majority of breaches.

There is a recovery plan in place to help improve the 4 hour A&E performance. The main areas of focus remain the same as the previous month, namely, improving streaming, streamlining the ambulatory care pathway and greater focus on early discharge planning and admission avoidance.

Emergency Department Flow

• Continue to embed the new Emergency Departmentflow model, focussing on changes on the ‘Fit2Sit’ space and optimising processes within the model and is expected to be embedded by mid July 2018.

• Specialty visits to build relationships between specialties and the Emergency Department planned and completion on-going. Visits to be completed by mid July 2018, followed by time to test and embed the new ways of working with specialties.

• The training plan continues as part of the embedding period of the flow model; this is anticipated to continue until end of August 2018, to support a reduction in minors breaches.

Wards• Regular reviews of Red2Green are undertaken, to identify the key delays and devise specific

actions to address these. • An enhanced stranded patients review commenced on 02 July 2018 to address top delay

reasons. • There is greater focus on reducing length of stay, by implementing several initiatives:

• Optimising the number of patients utilising Discharge to Assess pathways, by undertaking a ward by ward engagement plan with clear communications.

• A ‘home first’ focus• Embedding a trusted assessor initiative• Increasing the use of NM@Home to complete acute care at home; a meeting is

scheduled for 29 July 2018 between the Trust and the community teams, to identify gaps in provision and agree appropriate use of all services.

Page 101: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

North Middlesex University Hospital A&E Performance

12

Page 102: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

North Middlesex University HospitalQuality Summary

13

Key issue Priority actions

Serious Incidents (SI)North Middlesex University Hospital reported three Serious Incidences in June 2018. Incidents were reported in the following categories:

• One Suboptimal Care

• Diagnostics

• Falls

At the end of June 2018 there were 20 reports overdue for submission and eight Further Information Requests made.

Haringey CCG and North Middlesex University Hospital continue to meet to support timely submission and closure of Serious Incident investigation reports and good progress is being made.

North Middlesex University Hospital has revised its Serious Incident investigation process and has introduced dedicated Serious Incident investigators for a trial period to improve the quality and timeliness of investigation reports. The revised Serious Incident process was shared with the July 2018 Clinical Quality Review Group meeting. The Trust has recruited additional staff to the Governance Team to ensure a more robust process is in place

The July 2018 Clinical Quality Review Group meeting received assurance that the Trust Serious Incident and Learning Group identify any immediate actions required in response to an Serious Incident, and ensures that the service or team is aware and addresses the issues raised. The overdue status of a report investigation is not affecting immediate action implementation.

Commissioners are continuing to work with North Middlesex University Hospital to ensure only essential further information requests require a response. Additional comments and recommendations will be submitted to the Trust but a response is not required in order to close the investigation report.

Governance and Risk Improvement Process

The June 2018 Trust Board mandated the establishment of a Trust wide Governance and Risk Improvement Process. The process gives direction to existing risk and governance initiatives to ensure delivery of the Trust strategic objectives.

The Governance and Risk Improvement Process Steering Group has met twice since the June 2018 Board. Meetings are now bi monthly to ensure momentum is maintained.

Six additional Governance Team members have been recruited.

The Serious Incident and Duty of Candour processes have been reviewed and revised. Audit plans have been aligned with Governance and Risk Improvement Process deliverables. Nine staff have been trained in to undertake Structured Judgement Reviews.

NHS Improvement has agreed to support the Trust in key areas of the process.

Page 103: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Barnet, Enfield and Haringey MH TrustMental Health Performance Dashboard

14

*Latest data is provisional and unpublishedNHS Digital data published by NHS DigitalLocal data derived from Provider reports to NHSE

Theme SourceReporting

PeriodActual Standard

Current Month and Previous Months' Trend

Blue = NHS Digital Green = Local Data Red = Target

NHS Digital May-18 85.71% 50%

NHS Digital 2017-18 Q4 99.52% 95%

NHS Digital 2017-18 Q4 97.86% 95%

% Assessments begun within 1

hour in A&ELocal Data Jun-18 70.00% 95%

% Assessments begun within 4

hours in AMULocal Data Jun-18 60.00% 95%

% Assessments begun within 24

hours on wardsLocal Data Jun-18 84.00% 95%

% Assessments begun within 1

hour in A&ELocal Data Jun-18 89.00% 95%

% Assessments begun within 24

hours on wardsLocal Data Jun-18 96.00% 95%

KPI/Measure

BEH MENTAL

HEALTH

TRUST

The percentage of RTT First Episode

Psychosis (FEP) periods within 2 weeks

of referral. *

Proportion of patients on CPA who were

followed up within 7 days after discharge

from psychiatric inpatient care

Proportion of admissions to acute wards

that were gate kept by the CRHT teams

North

Mid

dle

sex

Barn

et

64.29%

90.91%78.57% 73.68% 66.67% 76.47%

90.48%

62.50%84.62% 81.25% 87.50% 77.78% 85.71% 85.71%

Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18

98.74% 99.76% 99.76% 99.52%

2017-18 Q1 2017-18 Q2 2017-18 Q3 2017-18 Q4

98.72% 99.45% 98.64% 97.86%

2017-18 Q1 2017-18 Q2 2017-18 Q3 2017-18 Q4

85.0% 82.0% 76.0% 73.0% 67.0%76.0% 72.0%

82.0% 88.0% 89.0% 92.0% 86.0% 81.0%72.0% 70.0%

Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18

78.0%56.0% 52.0%

68.0% 72.0% 77.0%61.0%

85.0% 71.0% 81.0% 91.0% 81.0%64.0% 63.0% 60.0%

Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18

90.0% 93.0% 89.0% 92.0%77.0%

92.0% 87.0% 91.0% 91.0% 95.0% 97.0% 94.0% 88.0%75.0%

84.0%Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18

95.0% 95.0%89.0% 93.0% 94.0% 92.0% 92.0%

98.0% 95.0% 95.0% 95.0% 94.0% 95.0%86.0% 89.0%

Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18

100.0% 100.0%

90.0%

100.0% 100.0% 100.0%93.0%

98.0% 100.0% 98.0% 98.0% 98.0% 98.0%94.0% 96.0%

Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18

Page 104: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Barnet, Enfield and Haringey Mental Health Quality and Performance Summary

15

Key issue Priority actions

Care Quality Commission

Barnet Enfield and Haringey Mental Health Trust was subject to

a comprehensive Care Quality Commission inspection in

September 2017 following which the Trust was awarded an

overall rating of ‘Requires Improvement’.

Two of the Trust’s mental health services were awarded a rating

of ‘Outstanding’, three were rated as ‘Good’ and three were

rated as ‘Requires Improvement’.

Barnet, Enfield and Haringey Mental Health Trust was subject to an unannounced inspection of two additional services in quarter four 2017/18.Recommendations were made in relation to nutrition and hydration, care planning, medicines management, physical health care and consultant cover.

Barnet Enfield and Haringey Mental Health Trust has shared the Trust wide

action plan addressing the Must Do and Should Do recommendations. All

actions arising from Care Quality Commission inspections are being

incorporated into the single Trust wide plan. Barnet, Enfield and Haringey

Mental Health Trust is holding bi-monthly meetings to review service area

evidence and update the plan.

The full updated plan was shared with the July 2018 Clinical Quality Review

Group meeting; the Trust is reporting good progress with implementing and

completing actions. In addition commissioners received an exception

report outlining the closed actions and those that are behind schedule.

Commissioners received actions plans for the two wards visited during the

March 2018 unannounced inspections. Progress with implementing

actions is being monitored on a quarterly basis together with the Trust wide

plan.

Page 105: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

16

Key issue Priority actions

Early Intervention in Psychosis - Performance

There are concerns about Barnet Enfield and Haringey Mental Health Trust evidencing compliance with the NICE Standards for Early Intervention in Psychosis. In June 2018 all three teams achieved the standard for starting NICE compliant treatments within two weeks of referrals with suspected first episode of psychosis.

Commissioners continue to invest an additional £800k for Early

Intervention in Psychosis Services. Implement agreed Cluster 10 Service

Specification when approved within CCG Governance processes.

Develop and implement a Child and Adolescent Mental Health Service specification to include the Early Intervention in Psychosis standard.

Commissioners to agree the measures for assessing the impact on access and National Institute for Health and Care Excellence compliance of the additional £800k investment.

Early Intervention in Psychosis - Data Quality and Recording

There have been issues with the assurance about reporting of the Barnet Enfield and Haringey Mental Health Trust data related to Early Intervention in Psychosis performance standards when comparing data sources i.e. Mental Health Services Data Set, Unify submissions and local data. The submissions are via SDCS from April 2018.

The EIP Network Report on the recent audit of all EIP teams in England have been received with a Trust overview and Essential Standards included in the report. It is recommended that in addition to the audit evidence a plan with trajectory on the move to using structured clinical coded recording (SNOMED CT) and outcome measures is required

A revised Data Quality Improvement Plan is being discussed for 2018/19 .

It is recommended that in addition to the audit evidence a plan with

trajectory on the move to using structured clinical coded recording

(SNOMED CT) and outcome measures is required DIALOG (quality of life

and treatment satisfaction questionnaire) and Questionnaire on the

Process of Recovery (QPR) .

Barnet, Enfield and Haringey Mental Health Quality and Performance Summary

Page 106: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

London Wide Ambulance Service Performance (LAS)

17Data Source: LAS Monthly Performance Report

The four new patient categories are:Category One – Life Threatening Category Two – EmergenciesCategory Three – Urgent Category Four– Less Urgent

With the introduction of the new Ambulance Response Programme performance reporting is being reviewed by London Ambulance Service and commissioners. London Ambulance Service have provided both CCG and pan-London summary reports for June 2018. This gives a summary of performance against the new standards for the whole of London.

Page 107: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

London Wide Ambulance Service Performance (LAS)

24Data Source: London Ambulance Service Performance Report

The four new patient categories are:Category One – Life Threatening Category Two – EmergenciesCategory Three – Urgent Category Four– Less Urgent

The table below shows the seven key ambulance performance measures profiled by the Sustainability Performance Programme Areas. Two areas performance achieved two out of seven ambulance measures, North Central London and North West London. North Central London performance was lower across all the unmet standards across the areas and London overall. Category One mean standard has a safety standard of nine minutes and all areas where within this.

Page 108: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

London North Central LondonAmbulance Service Performance

19

The four new patient categories are:Category One – Life Threatening Category Two – EmergenciesCategory Three – Urgent Category Four– Less Urgent

Data Source: London Ambulance Service Performance Report

Page 109: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

London North Central LondonAmbulance Service Performance

• London Ambulance Service previously noted the North Central London performance (which has consecutively achieved only two of the seven standards since month one) and have investigated the Category Four (less urgent) activity in Enfield specifically. Two Sustainability and Transformation Planning areas achieved two out of the seven ambulance standards the other areas achieved four out of seven ambulance standards.

• In month two, six calls were made by Acute trusts to book ambulances the evening before they were required for morning conveyances, triggering six hour dispatch waits each time. London Ambulance Service have since brought this issue to the attention of those Trusts and in month three the Category Four performance has improved accordingly.

• Within the North Central London CCGs three out of five CCG areas did not achieve four out of seven ambulance standards; Enfield CCG area achieved one (Category One 90th Centile – Emergencies), Barnet CCG area achieved two (Category One 90th

Centile – Emergencies and Category Four 90th Centile – Less Urgent) and Islington CCG area achieved two (Category One 90th

Centile – Emergencies and Category Four 90th Centile – Less Urgent).

• Within the North Central London CCG areas two out of five CCGs achieve four or more ambulance standards, Haringey CCG four out of seven and Camden CCG six out of seven

• A monthly Ambulance Acute Transformation meeting was established in July 2018 to oversee the implementation of the improvement plans, patient flow process mapping and suggested improvement. The group includes representative from each site (Barnet and Royal Free), London Ambulance Services, East of England Ambulance Services, NEL Commissioning Support Unit and Barnet CCG.

20

Page 110: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

London NCL Ambulance Service Performance NHS Haringey CCG Area

21

Page 111: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Quality Assurance Sign-off

22

Section Written By

Performance Mita Joshi and Julie Starr

Quality Ros Murphy

Final Sign Off by: Richard PearsonDate: 7 August 2018

Page 112: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

To know more

If you would like to discuss any elementof this presentation, please contact:

Mita Joshi Tel: 0203 688 1120Email: [email protected]

www.nelcsu.nhs.uk

Page 113: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Haringey Clinical Commissioning Group Governing Body Meeting 13 September 2018

Report Title Board Assurance Framework

Date of report 23 August 2018

Agenda Item

6.1

Lead Director /

Manager

Alex Smith, Director of Planning, Performance and Delivery

Tel/Email [email protected]

GB Member Sponsor

Adam Sharples, Lay Member for Audit and Governance

Report Author

Andrew Spicer, NCL Head of Governance and Risk

Tel/Email

[email protected]

Report Summary

This report is the Governing Body Board Assurance Framework (‘BAF’). It captures the most serious risks that have been identified as threatening the achievement of the CCG’s four strategic objectives. In July 2018 the NCL Audit Committee in Common approved a new style Governing Body risk report which strengthens the Governing Body’s strategic oversight and focus on the CCG’s key risks and helps to ensure a consistent approach to strategic risk reporting across NCL. This is the first report in the new style. Key risks from the NCL Primary Care Co-Commissioning Committee in Common (‘NCL PCC’) risk register, NCL Joint Commissioning Committee (‘NCL JCC’) risk register and NCL Risk Register are reported to the Governing Body to ensure visibility and oversight. Risks from the NCL JCC risk register and the NCL risk register are from an NCL perspective. However, risks from the NCL PCC risk register can be from either a local perspective or a pan-NCL perspective depending on the risk. Board Assurance Framework (‘BAF’) There are 9 risks on the risk register with 4 risks reaching the threshold of 12 or higher for inclusion on the BAF. The Governing Body-level risks on the BAF can be found here Key Highlights: Risk 10 - A failure to improve performance against the A&E target at NMUH in line with the requirements of the planning guidance for 2018/19 (Threat) : A&E at NMUH is failing to meet the national performance target but has stabilised over the summer months. Significant multi-agency planning is being undertaken as winter is expected to be challenging. There is a continued risk that A&E performance will worsen during the winter months because of the significant service pressures expected so actions are focused on effective winter planning and maintaining the current stable performance levels through a potentially difficult winter. Risk 43 - A failure to deliver a balanced Financial Plan in 2018/19 (Threat): The CCG has reviewed financial controls in place in order to control budgetary

Page 114: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

pressures or mitigate overspending. Effective mitigation of this risk is also dependent on delivery of the CCG's QIPP and transformation programme and other long term structural changes such as new contract forms with acute providers. The CCG is focussing on QIPP delivery, enhancing financial governance, and the development of new pipeline QIPP schemes for 2019-20 onwards. Haringey CCG Risk Register- New Risk The following risk has been added to the Haringey CCG risk register: Risk 44 – Cancer performance is being affected at NMUH as a result of Insufficient endoscopy diagnostic capacity due to unfilled staff vacancies (Threat). The risk has not reached the threshold for escalation to the BAF and so will be monitored by the Executive Team and the appropriate Governing Body committee. NCL Risk Register There are 9 risks on the NCL Risk Register with 1 risk having a current risk score of 15 or higher. The full version of the NCL Risk Register can be found here. Key Highlights: NCL 9: Delivering Financial Balance Across NCL CCGs (Threat): Given the scale of the financial ask it is possible that the identified actions, even if they are all implemented, will not deliver financial balance. Future mitigations are therefore being sought. This risk links with risk 43. NCL Primary Care Co-Commissioning Committee in Common Risk Register There are 13 risks on the NCL Primary Care Co-Commissioning Committee in Common (‘NCL PCCC’) Risk Register with 1 risk having a current risk score of 15 or higher. The full version of the NCL PCCC Register can be found here. Key Highlights: Risk 18 - Primary Care Support England (Threat): NHSE do not plan to bring any aspect of the contract back in house, but are pursuing active contract management in response to the National Audit Office report and recommendations. This issue remains a standing item on the NCL PCCC’s agenda. NCL Joint Commissioning Committee Risk Register There are 24 risks on the NCL Joint Commissioning Committee (‘NCL JCC’) Risk Register with 8 risks having a current risk score of 15 or higher. The full version of the NCL Risk Register can be found here. Key Highlights: JCC 10 - Mobilisation of STP and QIPP plans (Threat) And JCC 22- CSU In-Housing of Services (Threat): The in-housing of NELCSU to provide greater support and capacity for delivery of STP interventions is underway but the full extent of the financial risk of London sector in-housing of CSU services has not yet been finalised and mitigated. This has now delayed the approval of the in -housing of CSU services by NHS England which also includes North Central London. A joint financial review by NHS England and the CSU is to be implemented by mid-September 2018.

Page 115: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Recommendation The Governing Body is asked to REVIEW the BAF highlight report and provide feedback on the risks.

Identified Risks

and Risk

Management

Actions

The BAF is a risk management document which highlights the most significant risks to the achievement of the CCG’s strategic objectives.

Conflicts of Interest

Conflicts of interest are managed robustly and in accordance with the CCG’s conflicts of interest policy.

Resource

Implications

Updating of the BAF is the responsibility of each risk owner and their respective directorates. The Governance Team helps to support this by providing monitoring, guidance and advice.

Engagement

The BAF report is presented to each Governing Body meeting. The Governing Body includes clinicians, lay members and representatives of patients and other key stakeholders.

Equality Impact

Analysis

This report was written in accordance with the provisions of the Equality Act 2010.

Report History and

Key Decisions

The BAF was last reviewed by the Governing Body in July 2018. Risks are kept under review by the risk owners and by the committees of the Governing Body.

Next Steps To continue to manage risk across the organisation in a robust way.

Appendices

The following documents are included:

BAF Risks Highlight Report;

Risk Scoring Key.

Page 116: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Risk ID Risk Title Risk Owner Strategic Update MAR MAY JUL SEP

10 A failure to improve

performance against

the A&E target at

NMUH in line with the

requirements of the

planning guidance for

2018/19 (Threat)

Tony Hoolighan, Chief

Operating Officer

A&E at NMUH is failing to meet the national performance target

but has stabilised over the summer months.  Significant multi-

agency planning is being undertaken as winter is expected to

be challenging.  There is a continued risk that A&E

performance will worsen during the winter months because of

the significant service pressures expected so actions are

focused on effective winter planning and maintaining the

current stable performance levels through a potentially difficult

winter.

15 15 15 15 15

26 Risk of BEH MHT failing

to deliver the required

‘must do’ and ‘should

do’ improvements

required, after the Trust

was rated as ‘requires

improvement’ following

an inspection by the

CQC in December

2015 (Threat)

Jenny Williams, Director of

Nursing and Quality

The Trust shared its Improvement Plan at the April CQRG

meeting with agreement that CQRG will receive monthly

exception reports of compliance with due actions, and quarterly

presentation of the full plan. There were two unannounced

CQC inspections during quarter four to Magnolia Unit and

Silver Birches ward. The final report is yet to be published, but

the Trust had received informal feedback at the time of the

inspection indicating that improvement is needed in providing

nutrition and hydration, care planning, medicines management

and physical health care.

12 12 12 12 8

42 Continued overspend

on the Continuing

Healthcare (CHC)

budgets, resulting in the

CCG being unable to

meet its financial duty

to deliver services

within its resources

(Threat)

Clare Henderson, Director of

Commissioning

A significant amount of work has been undertaken to

understand the causes and drivers of CHC activity and spend.

This is supported by working with partner organisations through

a comprehensive multi-agency action plan with related QIPP

schemes and a review of the entire CHC function. An SRO for

CHC has been appointed across the NCL CCGs to support an

effective and efficient CHC function and clinical leads are being

engaged.

16 16 16 16 8

43 A failure to deliver a

balanced Financial Plan

in 2018/19 (Threat)

Simon Goodwin, Chief

Finance Officer

The CCG has reviewed financial controls in place in order to

control budgetary pressures or mitigate overspending.

Effective mitigation of this risk is also dependent on delivery of

the CCG's QIPP and transformation programme and other

long term structural changes such as new contract forms with

acute providers.  The CCG is focussing on QIPP delivery,

enhancing financial governance, and the development of new

pipeline QIPP schemes for 2019-20 onwards.”

20 20 20 16

Risk Key

Risk Improving

Risk Worsening

Risk neither improving nor worsening but working towards target

Risk of positon worsening so actions taken are to maintain the current level

Haringey CCG BAF Risks- Highlight Report2018/19

Movement From

Last Report

Target Risk

ScoreCurrent Risk Score

Page 117: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

Risk Scoring Key This document sets out the key scoring methodology for risks and risk management.

1. Overall Strength of Controls in Place There are four levels of effectiveness: Level Criteria

Zero The controls have no effect on controlling the risk. Weak The controls have a 1- 60% chance of successfully controlling the risk.

Average The controls have a 61 – 79% chance of successfully controlling the risk Strong The controls have a 80%+ chance or higher of successfully controlling the risk

2. Risk Scoring

This is separated into Consequence and Likelihood. Consequence Scale: Level of Impact on the Objective

Descriptor of Level of Impact on the Objective

Consequence for the Objective

Consequence Score

0 - 5% Very low impact Very Low 1

6 - 25% Low impact Low 2 26-50% Moderate impact Medium 3

51 – 75% High impact High 4 76%+ Very high impact Very High 5

Likelihood Scale: Level of Likelihood the Risk will Occur

Descriptor of Level of Likelihood the Risk will Occur

Likelihood the Risk will Occur

Likelihood Score

0 - 5% Highly unlikely to occur

Very Low 1

6 - 25% Unlikely to occur Low 2 26-50% Fairly likely to occur Medium 3

51 – 75% More likely to occur than not

High 4

76%+ Almost certainly will occur

Very High 5

Page 118: Haringey Clinical Commissioning Group Item Title Lead ... · Such advantage might be financial or in another form, such as the ... X Direct Appraisal lead and appraiser 15.3.18 27.04.18

3. Level of Risk and Priority Chart

This chart shows the level of risk a risk represents and sets out the priority which should be

given to each risk:

LIKELIHOOD

CONSEQUENCE

Very Low

(1)

Low (2)

Medium (3)

High (4)

Very High

(5)

Very Low (1)

1 2 3 4 5

Low (2)

2 4 6 8 10

Medium (3)

3 6 9 12 15

High (4)

4 8 12 16 20

Very High (5)

5 10 15 20 25

1-3

Low Priority

4-6

Moderate Priority

8-12

High Priority

15-25

Very High Priority