hapter 1 introdu tion - metro mining · hapter 1 - introdu tion gulf alumina ltd – skardon river...
TRANSCRIPT
CHAPTER 1 - INTRODUCTION
GULF ALUMINA LTD – SKARDON RIVER BAUXITE PROJECT
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-i
Page 1-i
TABLE OF CONTENTS
1.1 Purpose .............................................................................................................1-1 1.2 Project Proponent ..............................................................................................1-1 1.3 Proponents Environmental Record and Environmental Policy ..............................1-1 1.4 Project Overview ................................................................................................1-2 1.5 Legislative Framework ........................................................................................1-2 1.6 Project Location and Mining Leases ....................................................................1-3 1.7 Project Description .............................................................................................1-6 1.8 Rehabilitation ....................................................................................................1-9 1.9 Social and Economic Benefits ..............................................................................1-9 1.10 Project Alternatives .......................................................................................... 1-10 1.11 Environmental Impact Assessment ................................................................... 1-11 1.12 Environmental Authority Process ...................................................................... 1-11 1.13 Assessment Methodology................................................................................. 1-11 1.14 Risk Based Assessment ..................................................................................... 1-12 1.15 Environmental Management ............................................................................ 1-16 1.15.1 Environmental Management Plan ........................................................................... 1-16 1.15.2 Monitoring and Measurement ................................................................................. 1-16 1.15.3 Records Management .............................................................................................. 1-16 1.15.4 Reporting, Corrective and Preventive Action ........................................................... 1-16 1.15.5 Audits ....................................................................................................................... 1-16 1.15.6 Management Review ............................................................................................... 1-17 1.16 EIS Document Structure .................................................................................... 1-17
Tables
Table 1-1 Consequence of Impacts .......................................................................................... 1-13 Table 1-2 Risk Analysis Matrix (Consequence and Likelihood) ................................................ 1-15 Table 1-3 Chapters Structure ................................................................................................... 1-18 Table 1-4 Appendix List ............................................................................................................ 1-19
Figures
Figure 1-1 Regional Project Location ........................................................................................... 1-4 Figure 1-2 Project Area, Skardon River and Offshore Activity Areas and Cadastral
Boundaries ................................................................................................................. 1-5 Figure 1-3 Proposed Project Layout ............................................................................................ 1-8
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-1
Page 1-1
1. INTRODUCTION
1.1 Purpose
The purpose of this Environmental Impact Statement (EIS) document is to provide information to support the Skardon River Bauxite Project (the Project) environmental authority (EA) amendment application and Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) Referral.
The State and Commonwealth administering authorities must consider the environmental values of the area of the mining leases (MLs) and Project activities when it decides an application for an EA amendment in accordance with the Environmental Protection Act 1994 (EP Act) or a controlled action under the EPBC Act.
This document provides an assessment of the Project’s impact on the environmental values of the Project area and surrounds, including emissions and wastes from the Project. It assesses the risks to environmental values and proposes measures to mitigate impacts.
The EA process commenced on lodgement of the EA amendment application in March 2014. The Department of Environment and Heritage Protection (EHP) commence the decision stage for the grant of the EA once the EIS assessment report has been finalised. As the mining leases have already been granted, the EA will take effect on the day the EA is issued.
The approvals process for the Project is detailed in Chapter 2.
1.2 Project Proponent
The proponent, Gulf Alumina Ltd (Gulf Alumina) is a public company registered on 23 February 2004 in Sydney, NSW to explore and develop bauxite deposits in and around Australia. Gulf gained full ownership of the three Skardon River mining leases from ACC Ecominerals in January 2012. Gulf is currently the sole holder of the EA (EPML 00967013) for the Project’s three mining leases (MLs) - ML 40082, ML 40069 and ML 6025.
Gulf Alumina’s head office is located in Sydney at the following address:
Gulf Alumina Limited Suite 503, Level 5, 37 Bligh St, Sydney, NSW 2000 Telephone: (02) 9221 4689 Fax: (02) 9221 4686 Email: [email protected] Website address: www.gulfalumina.com.au ACN: 108 086 377
1.3 Proponents Environmental Record and Environmental Policy
The proponent has not been subject to proceedings under a law of the Commonwealth or State for the protection of the environment or the conservation and sustainable use of natural resources (and environmental law). Gulf Alumina’s environmental policy is provided in Appendix 11.
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-2
Page 1-2
1.4 Project Overview
The proposed Project involves mining of a bauxite ore body of 50 million tonnes (Mt). The planned mine production rate would initially be 3 million tonnes per annum (Mtpa) initially and would rise to 5 Mtpa subject to market conditions. The operational Project life is expected to be 10 years, with a construction period of approximately 1 year and post mining decommissioning and final rehabilitation period.
The total disturbance area for the bauxite mine across all three mining leases is approximately 1,515 ha - of which 139 ha has already been disturbed as part of the historical kaolin mining. Therefore the proposed bauxite mine will create an additional 1,376 ha of new disturbance.
Bauxite products would be transported via the existing and new haul roads to the Port of Skardon River and transhipped by barge to bulk carriers in deep water beyond the mouth of the river for export.
Construction is planned to commence in 2016 and bauxite mining and shipping would commence in 2017.
1.5 Legislative Framework
The existing mining leases are subject to an existing environmental authority (EA), number EPML 00967013 (formerly MIN104486212). This EA relates to mining of kaolin on the mining leases, which has ceased. On 20 January 2014, the Department of Natural Resources and Mines (DNRM) approved the existing mining leases to include mining bauxite. Gulf applied for an amendment for bauxite mining within the existing mining leases in March 2014 as the current EA only allows for mining kaolin and operating an associated kaolin plant. Environment and Heritage Protection (EHP) decided that the proposed amendment was a major amendment under sections 228 and 229 of the EP Act. On 19 May 2014, EHP notified Gulf that the amendment application required assessment by environmental impact statement (EIS).
In May 2015, Gulf proposed a change to the EA amendment application under Sections 236 – 238 of the EP Act to include additional bauxite resources. In May 2015, EHP determined that the proposed changes would be assessed as part of this EIS.
The proposed Project was referred on 14 August 2014 to the Commonwealth Department of the Environment (DoE) (EPBC 2014/7305). On 11 September 2014, the Minister for the Environment determined the proposed Project to be a controlled action under the Commonwealth EPBC Act. The controlling provisions are sections 18 and 18A (listed threatened species and communities), 20 and 20A (listed migratory species) and 23 and 24A (Commonwealth marine areas). On 18 February 2015 DoE approved an application to vary the original Referral to include resource extraction within ML 6025 south of Namaleta Creek. On 22 April 2015, DoE approved an application to vary the original Referral to increase the depth of bed levelling and the volume of material to be transferred by bed levelling.
Gulf submitted an Initial Advice Statement (IAS) and the draft Terms of Reference (ToR) for the Project’s EIS in September 2014. Following Gulf’s responses to the comments received on the draft ToR (under Section 45 of the EP Act), the final ToR was approved on 15 January 2015.
The Project will be assessed under the bilateral agreement between the Commonwealth and the State of Queensland using the EIS prepared under the EP Act.
The Project approvals process, including approvals required under other legislation, is described in Chapter 2.
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-3
Page 1-3
1.6 Project Location and Mining Leases
The Project will be located on Cape York Peninsula, approximately 90 km north of Weipa, in the Parish of Skardon within the Cook Shire. The regional Project location is shown in Figure 1-1. The relevant mining tenures are granted ML 6025 (1922ha), ML 40069 (260ha) and ML 40082 (1,743ha). The Port of Skardon River is within the Project’s mining leases. Some Project activities will occur outside of the mining leases such as barging of bauxite on the Skardon River and offshore transhipment.
The Project area (Project mining leases), Skardon River and offshore activity areas, and underlying and adjacent cadastral boundaries are shown in Figure 1-2. The lots intersected by the Project’s mining leases are owned by the Old Mapoon Aboriginal Corporation - Trustee for the benefit of Aboriginal people particularly concerned with the land and their ancestors and descendants, and under the Aboriginal Land Act 1991.
A detailed description of the Project location is provided in Chapter 4.
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
ML 6 02 5
ML 4 00 82 ML40 06 9
Gulf ofCarpentaria
HOPE VALEABORIGINAL
SHIREKOWANYAMAABORIGINAL
SHIRE
LOCKHART RIVERABORIGINAL
SHIRE
MAPOONABORIGINAL
SHIRE NAPRANUMABORIGINAL
SHIRE
NORTHERNPENINSULA
AREA REGIONAL
WEIPA TOWNAURUKUN
SHIRE
CAIRNSREGIONAL
COOKSHIRE
PORMPURAAWABORIGINAL
SHIRE
WUJAL WUJALABORIGINAL
SHIRE
TORRESSHIRE
TORRESSTRAIT ISLAND
REGIONAL
WEIPA
COOKTOWN
INNISFAIL
CAIRNS
KarumbaNormanton
ThursdayIsland
Coen
HopeVale
PortDouglas
PENINSULA DEVELOPMENTAL ROAD
KENNEDY HIGHWAY
CAPTAIN COOK HIGHWAY
BURK E DEVELOPME NTAL ROAD
BRUCEHIGHWAY
Aurukun
Bamaga
Kowanyama
Mapoon
WujalWujal
Napranum
Pormpuraaw
LockhartRiver
500000 600000 700000 800000 900000 1000000 110000081
0000
0
8100
000
8200
000
8200
000
8300
000
8300
000
8400
000
8400
000
8500
000
8500
000
8600
000
8600
000
8700
000
8700
000
8800
000
8800
000
Figure 1-1
G:\CLIENTS\E-TO-M\Gulf Alumina\GIS\Maps\EIS\Ch01_Intro\FIG_1_1_Project_Location_150812.mxd
Revision: R1
Date: 12/08/2015 Author: malcolm.nunn1:3,500,000Map Scale:
Coordinate System: GDA 1994 MGA Zone 54
Regional Project Location
0 25 50 75 100Kilometers
Gulf Alumina Limited
No warranty is given in relation to the data (including accuracy, reliability, completeness or suitability) and accept no liability (including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of or reliance upon the data. Data must not be used for direct marketing or be used in breach of privacy laws. Tenures © Geos Mining (2015). State Boundaries, Towns, Railways and Roads © Geoscience Australia (2015). Towns and LGA boundaries © State of Queensland (Department of Natural Resources and Mines) 2015.
LegendMining Lease Boundaries
!( TownsMain RoadRailways
Local Government BoundariesAURUKUN SHIRECAIRNS REGIONALCOOK SHIREHOPE VALE ABORIGINAL SHIREKOWANYAMA ABORIGINAL SHIRELOCKHART RIVER ABORIGINAL SHIREMAPOON ABORIGINAL SHIRE
NAPRANUM ABORIGINAL SHIRENORTHERN PENINSULA AREA REGIONALPORMPURAAW ABORIGINAL SHIRETORRES SHIRETORRES STRAIT ISLAND REGIONALWEIPA TOWNWUJAL WUJAL ABORIGINAL SHIRE
!
!
!
!
Queensland ROCKHAMPTON
BRISBANE
CAIRNS
TOWNSVILLE
±
Coral Sea
! (Sk
ardo
n Rive
rML
4008
2ML
4006
9Port
ofSk
ardo
n Rive
r
ML 60
25
Gulf o
fCa
rpenta
ria
Namaleta Creek
Lot 7
024 o
nMP
4115
9Lot 1
3 on
SP20
4113
Lot 1
onSP
1200
90
Lot 1
onSP
1200
90
Lot 1
onSP
1200
90
Lot 8
onMP
1446
6
Lot 1
2 on
SP20
4113
Lot 1
1 on
SP20
4113
5900
0059
5000
6000
0060
5000
6100
0061
5000
6200
0062
5000
8685000
8685000
8690000
8690000
8695000
8695000
8700000
8700000
8705000
8705000
!
!
!
!
ROCK
HAMP
TON
BRIS
BANE
CAIR
NS
TOW
NSVIL
LE
Quee
nslan
d
No w
arran
ty is
given
in re
lation
to th
e data
(inclu
ding a
ccura
cy, re
liabil
ity, c
omple
tenes
s or s
uitab
ility)
and a
ccep
t no l
iabilit
y (inc
luding
with
out li
mitat
ion, li
abilit
y in n
eglig
ence
) for a
ny lo
ss, d
amag
e or c
osts
(inclu
ding c
onse
quen
tial d
amag
e) rel
ating
to an
y use
of or
relia
nce u
pon t
he da
ta. D
ata m
ust n
ot be
used
for d
irect
marke
ting o
r be u
sed i
n bre
ach o
f priv
acy l
aws.
Imag
ery so
urced
from
Gulf A
lumina
(201
4). Te
nures
© G
eos M
ining
(201
5). S
tate B
ound
aries
and T
owns
© G
eosc
ience
Aus
tralia
(200
6). C
adas
tre ©
Stat
e of Q
ueen
sland
- Dep
artme
nt of
Natur
al Re
sourc
es an
d Mine
s (20
15).
±
Figur
e 1-2
Gulf A
lumina
Limi
ted
Lege
nd Minin
g Lea
se B
ound
aries
! (Po
rt of S
kardo
n Rive
rCa
dastr
e
Offsh
ore Tr
ansh
ipmen
t Area
Bed L
evell
ing Ar
ea
02.5
57.5
10Kil
ometr
es
G:\C
LIENT
S\E-TO
-M\G
ulf Al
umina
\GIS
\Map
s\EIS\
Ch01
_Intro
\FIG_
1_2_
Proje
ct_Ar
ea_a
nd_O
ffsho
re_15
0813
.mxd
Revis
ion: R
1
Date:
13/08
/2015
Auth
or: m
alcolm
.nunn
1:150
,000
Map S
cale:
Co
ordin
ate S
ystem
: GDA
1994
MGA
Zone
54
Proje
ct Ar
ea, S
kard
on R
iver a
nd O
ffsho
reAc
tivity
Are
as, a
nd C
adas
tre B
ound
aries
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-6
Page 1-6
1.7 Project Description
A detailed description of the Project activities is provided in Chapter 5.
The Project involves the construction and operation of an open cut bauxite mine in Western Cape York Peninsula. The Project involves mining a bauxite ore body of around 50 million tonnes (Mt) and is anticipated to initially produce 3 million tons per annum (Mtpa) bauxite suitable as direct shipping ore (DSO), which is expected to rise to 5 Mtpa subject to market conditions.
The DSO bauxite mining method involves vegetation clearing and grubbing, harvesting topsoil and subsoil, mining bauxite, placing mined subsoil on mined pit floor, placing harvested topsoil on subsoil and rehabilitating mined areas. The bauxite within the mining leases is less than 3 m thick, with an average DSO thickness of 1.7 m, and does not extend more than 6 m below the surface. Conventional open cut mining will be carried out after removing the topsoil and subsoil. Mining will occur 24 hours per day, 7 days per week. Mining of DSO bauxite is planned to occur during the dry season with shut down during heavy rain periods of the wet season, approximately 3 months from January to March.
DSO does not require beneficiation of the bauxite and hence beneficiation and associated tailings management are not part of the Project. The option for DSO bauxite therefore results in lower environmental impact than beneficiation of bauxite by avoiding tailings management and associated additional water and energy requirements.
The bauxite ore will be mined and transported via existing, upgraded haul roads to a crushing and stock pile facility at the Port of Skardon River. The bauxite product will be barged to bulk carrier vessels in deep water approximately 15 km beyond the mouth of the river for export. Construction is planned to commence in 2016 with bauxite mining and shipping in 2017 after the wet season period. For the purpose of feasibility study mine planning, it is assumed that mining commences in April 2017.
Life of Project activities and infrastructure that form part of the EIS assessment for the Project include:
A new wharf / barge loading facility within the Project’s existing mining leases and the gazetted Port
of Skardon River, constructed using piles and dolphins.
Barging of bauxite to the offshore transhipment location in deep water approximately 15 km
offshore from the Skardon River mouth, and transfer from barges to bulk carriers.
Bulk carrier movements with Australian waters.
Bed-levelling at the mouth of Skardon River to a depth of approximately 2.2 m below lowest
astronomical tide (LAT). Bed levelling would involve underwater reprofiling of shallow areas at the
seaward extent of the Skardon River mouth by pushing the crests of sand banks into deeper gutters.
No dredging is proposed; however, annual maintenance bed levelling is likely to be required.
Upgrade of the existing boat ramp and jetty infrastructure at the Port to improve access for vessel
supply of fuel, consumables, materials and site equipment.
New bauxite ore dump facility, mobile crushers, conveyor belt system and bauxite product stockpile
facility, all adjacent to the Port of Skardon River landing.
New workshop, warehouse, administration and crib room at the Port of Skardon River.
Additional bulk fuel storage if required, new fuel transfer pipeline, diesel transfer tanks and export
waste storage at the Port of Skardon River.
Use of existing landfills and, potentially a new landfill, for limited waste disposal.
Upgrade of the existing 15 km north-south haul road from the Port to the former wet plant area; a
new haul road system surrounding the kaolin mine overburden piles, upgrade of the crossing of
Namaleta Creek and an additional 1.5 km of haul roads south of Namaleta Creek.
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-7
Page 1-7
Temporary branch haul roads would be used to link with the existing haul road.
Upgrade of the existing accommodation camp from 50 beds to 150 beds for the construction
workforce and maintained for mining operation, and upgrade of the sewage treatment system.
Use of the existing airstrip and relocated airstrip later in mine life, primarily for transport of workers.
A process water pumping station at the existing kaolin mine water storage pits with existing pipeline
to transfer water to water storage tanks at the Port of Skardon River. This pipeline will run adjacent
to the existing north- south haul road.
Upgrading or replacing the existing sediment retention dam for stormwater run-off from
infrastructure and stockpile areas at the Port of Skardon River.
Power will be supplied by three 1MW generators fitted on semi-trucks.
The proposed Project layout, with all mining areas and the Port infrastructure area is shown in Figure 1-3.
Water supply and mine site water management is described in Chapter 6. The annual water requirements for dust suppression, watering haul roads and plant and equipment washdown would be sourced from the existing kaolin mine water storages and shallow groundwater aquifers.
The offshore transhipment would occur in a defined area where bulk carriers (e.g. Panamax ships) will anchor. Barges will anchor adjacent to the bulk carriers for loading of bauxite ore.
Two barges, with a capacity of about 4,000 to 7,000 t per barge, will transfer bauxite ore to the bulk carriers, which will have an approximate capacity of 75,000 deadweight tonnes (dwt). Barges would work 24 hours (although crossing of the Skardon River mouth would be limited to approximately 18 hours of the day to avoid low tide), 7 days a week with a loading rate up to 2,000 tonnes/hour, for approximately 40 weeks per annum (i.e. excluding the wet season). At a bauxite production rate of 5 Mtpa, this will result in approximately 1.5 bulk carrier shipping movement per week, or 65 to 70 bulk vessel movements per annum.
It is expected that an average of 100 people will need to be accommodated during the bauxite infrastructure construction period of 30 weeks with a maximum workforce of 120 people. The Project would require approximately 160 employees during operation. Employees will be on a shift roster and hence not all employees will be at site at any one time. Employees would be accommodated in the upgraded accommodation camp during the construction and the mining operation phases. The Project workforce will be transported to the site by air and will be accommodated in camp on the Project area. The workforce will be 100% fly in fly out (FIFO), as it is not practical for the workforce to access the Project by road.
!(
ML40069
ML 6025
ML 40082
Port ofSkardon River
Skardon River
NamaletaCreek
Camp Area
Haul
Road
Existing Airstrip
New Airstrip
605000 610000 61500086
8500
0
8685
000
8690
000
8690
000
8695
000
8695
000
8700
000
8700
000
8705
000
8705
000
±
Figure 1-3
LegendMining Lease Boundaries
!( Port of Skardon RiverExisting Disturbance FootprintSouthern Haul Road
Proposed Bauxite Mining AreasBauxite Infrastructure Area
G:\CLIENTS\E-TO-M\Gulf Alumina\GIS\Maps\EIS\Ch01_Intro\FIG_1_3_Proposed_Project_Layout_150813.mxd
Revision: R1
Date: 13/08/2015 Author: malcolm.nunn1:100,000Map Scale:
Coordinate System: GDA 1994 MGA Zone 54
Proposed Project Layout
0 1 2 3 4 5Kilometers
Gulf Alumina Limited
!
!
!
!
Queensland
CAIRNS
BRISBANE
TOWNSVILLE
ROCKHAMPTON
±Dry Plant Area
Haul
Road
Landfill
WasteManagement
Area
BargeLoaders
New Airstrip
Airstrip
Haul Road
Fluvial Pit
Kaolin Piles
Claystone Overburden PileClaystone Pit
Water Pit
Borrow Pits
Borrow Pits
Settlement Dam
Previous Wet Plant
Fluvial Overburden Pile
Sand WasteContainment Dam Previous Pilot Plant
Settlement Pond
Bio-remediation Pad
No warranty is given in relation to the data (including accuracy, reliability, completeness or suitability) and accept no liability (including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of or reliance upon the data. Data must not be used for direct marketing or be used in breach of privacy laws. Imagery sourced from Gulf Alumina (2014). Tenures © Geos Mining (2015). State Boundaries and Towns © Geoscience Australia (2006).
Scale 1:40,000
Scale 1:15,000
Camp Expansion Area
Existing Camp Facility
1:15,000
Wharf and PortPlan Options
Option 1Option 2Both Options
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-9
Page 1-9
1.8 Rehabilitation
Project rehabilitation and decommissioning is detailed in Chapter 7.
A Rehabilitation Management Plan (RMP) will be developed to ensure that land disturbed by mining operations is effectively rehabilitated such that:
the agreed post-mining land use (likely native vegetation) is achieved
the site is stable, non-polluting and safe to humans and animals
stable environmental conditions are established which are able to be sustained
all relevant statutory requirements are complied with.
Progressive rehabilitation will occur throughout the life of the Project. Decommissioning and final rehabilitation of areas used for mining will be outlined in a Mine Closure Plan (MCP) and specific rehabilitation completion criteria, indicators and monitoring methods, will be provided in the RMP.
On the completion of mining, the following treatments will be undertaken:
Infrastructure will be removed and dismantled where required unless the landholder (Traditional
Owners) requests otherwise.
Vegetation cover will be restored and land will be returned to its agreed post-mining land use.
Erosion and sediment control structures will be constructed to maintain topsoil cover, landform
stability and prevent sedimentation of waterways.
Contaminated land will be remediated and assessed for any potential future contamination issues.
1.9 Social and Economic Benefits
The social and economic benefits and impacts of the Project are described in Chapter 25. In summary:
Capital expenditure of approximately $61 million will be invested into the economy.
Operational expenditure of approximately $134 million per annum will be invested into the
economy.
Approximately 160 direct jobs and many more indirect jobs will be created during operations.
Approximately 100 direct jobs and many more indirect jobs will be created during construction.
Royalties of approximately $325 million over the life of the Project will be generated.
Taxes of approximately $434 million over the life of the Project will be generated.
Indigenous groups will receive benefits under the current traditional owner agreement.
Indigenous landowners will receive a share of mining lease royalty payments.
The Port of Skardon River (as operated by Ports North) will be further developed.
Infrastructure (airstrip, accommodation, dams, roads and Port) will be upgraded or developed. In
agreement with the landowners (traditional owners), these may be retained to improve the
functionality of the land.
Commitments by the proponent to assist with land management type activities (e.g. weed and pest
management and fire management) will be implemented.
Economic stimulation generated as a result of wages and additional demand for goods and services is expected to have beneficial effects at the local level. Revenue generated for the state and federal government in the form of taxes and royalties will assist in the funding of a wide range of services to the
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-10
Page 1-10
benefit of the community. The Project is expected to have a beneficial impact on Indigenous people residing in the local area and Cape York region through the provision of increased business opportunities, employment, education and training opportunities.
1.10 Project Alternatives
Project alternatives are considered in terms of location of activities, design of infrastructure and types of activities proposed.
The location of mining is dictated by the location of the bauxite resource. However where the bauxite resource encroaches on sensitive areas (e.g. low lying areas such as wetlands or tidal areas) buffer areas have been proposed that will limit encroachment. Bauxite mining is proposed using conventional open cut methods, with various options for the type of excavation and haulage equipment.
The proponent has elected to direct ship ore. This means that no beneficiation of the bauxite ore and resulting tailings management is required. As a consequence significantly less water is required for the Project, thereby minimising impacts on water sources, and there are no impacts associated with tailings management.
The proponent has taken advantage of existing infrastructure in the Project area, associated with the former kaolin mine, to minimise the Project disturbance area. This includes using the existing Port area, airstrip, camp and haul roads. Two options were considered for the haul road crossing of Namaleta Creek. The preferred option involves upgrading the existing crossing of Namaleta Creek. The second option involved extending the haul road along the eastern and southern boundary of the mining leases, with a crossing of Namaleta Creek upriver from the existing crossing. The preferred option was selected as it minimises the ecological and hydrological impacts in comparison to the second option, minimises haul distance and potentially improves hydrological flows compared to the current crossing design.
The Project area is located in a remote area that is not feasibly accessible by public road by the workforce or for the supply of equipment, fuels and material. Therefore the proponent intends to transport workers by air, and equipment, fuels and material by sea. No off tenement road upgrades are proposed, thereby avoiding disturbance activities off tenement.
The options considered for water supply to the Project have focussed on supply from existing dams associated with the former kaolin mine and, when required, extraction from shallow aquifers. This avoids the need to construct additional surface water collection dams or target water from deep aquifers associated with the Great Artesian Basin, thereby minimising hydrological impacts from sourcing water for the Project.
The Port of Skardon River (and its associated disturbance area and infrastructure) already exists and hence the proposal to upgrade the infrastructure at the Port for the Project will result in the least amount of additional impact. Various options are being considered for the exact location of additional or upgraded Port infrastructure, but these are all centred on the existing Port location. The wharf upgrade at the Port will be designed and located to avoid the need for dredging, thereby minimising impacts on the marine environment. The wharf construction method (piles and dolphins) minimises impacts to the marine environment in comparison to other construction methods.
Due to the shallow depth of the mouth of the Skardon River, some bed levelling is required so that barge movements between the Port and the offshore transhipment area are economic. Having barges with a draft shallow enough to cross the mouth of the Skardon River would result in inefficiencies and increased vessel movements. In order to minimise impacts, dredging, involving removal, transport and disposal of subsurface materials at an alternative location, is not proposed. The proponent has balanced the minimum depth of bed levelling required with the need to operate barges efficiently.
In order to minimise the offshore transhipment impact, no fixed infrastructure is proposed offshore.
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-11
Page 1-11
Should the Project not proceed, the economic and social benefits summarised in Section 1.9 and Chapter 25 will not be realised. This EIS describes the potential social, economic and environmental impacts of the Project and measures to manage and mitigate those impacts. On balance the socio-economic benefits of the Project outweigh the residual social, economic and environmental impacts of the Project.
1.11 Environmental Impact Assessment
The purposes of an environmental impact assessment and production of an EIS, as addressed in this EIS are as follows:
to assess the potential adverse and beneficial environmental, economic and social impacts of the
Project; and management, monitoring, planning and other measures proposed to minimise any
adverse environmental impacts of the Project
to consider feasible alternative ways to carry out the Project
to give enough information about the above matters to the Commonwealth and State authorities
and the public
to prepare or propose environmental management plans for the Project to inform the
environmental authority application
to give information to other Commonwealth and State authorities to help them make informed
decisions
to meet any assessment requirements under the EPBC Act as the Project is a controlled action under
a bilateral agreement;
to allow the State to meet its obligations under a bilateral agreement.
1.12 Environmental Authority Process
The EA process commenced on lodgement of the EA amendment application. EHP will commence the decision stage for the grant of the EA once the EIS assessment report has been finalised.
As the mining leases are granted, the EA will take effect on the day the EA is issued.
Chapter 4 of the EP Regulation prescribes the regulatory requirements with which the administering authority is required to comply for making environmental management decisions — including the issuing of an EA. To facilitate this, EHP has developed a set of model conditions for resource projects, which form the basis for proposed EA conditions and general environmental protection commitments in the EIS. The EIS describes impact mitigation measures in the context of these model conditions.
Environmentally relevant activities (ERAs) are prescribed activities for which approval is required. The ERAs potentially triggered by the Project are described in Chapter 2. Under Schedule 2A of the EP Act, the Project is for ‘mining bauxite’ which has an aggregate environmental score (AES) of 97.
1.13 Assessment Methodology
The methods used to obtain and present the information in this EIS include:
desktop review of regulatory requirements and relevant government policies and guidelines
desktop review of available data from local, state and federal government data sets (including EIS
material from nearby mine projects)
baseline environmental studies, including fieldwork (undertaken as denoted in chapters)
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-12
Page 1-12
identification and assessment of potential impacts requiring assessment through specialist studies
including baseline studies
community consultation
compilation of relevant information in the EIS documents.
The impact assessment examines the existing environmental values of the Project area for each element of assessment and then determines the potential impacts associated with the Project’s construction, operation, decommissioning and rehabilitation phases. Where required, baseline studies were undertaken to establish environmental values.
1.14 Risk Based Assessment
A risk framework has been adopted to assess the risk to the environment, people, land use / property and the community from Project activities. The risk framework combines the consequence and likelihood of a particular impact, after consideration of proposed mitigation measures (i.e. residual risk), and assigns a risk level of low, medium, high or extreme.
The consequence (incorporating duration, magnitude and intensity) of the impacts to the environment, people, land use / property and the community is described in Table 1-1 for consequences that are insignificant, minor, moderate, major and severe. Consequence is considered in relation to the existing environmental conditions and sensitivity of the value, receptor or resource.
Table 1-2 describes the likelihood of a particular impact and combines this with consequence to determine a risk ranking.
Sk
ard
on
Riv
er B
auxi
te P
roje
ct
C
hap
ter
1 -
Intr
od
uct
ion
Pag
e 1
-13
Pag
e 1
-13
Tab
le 1
-1
Co
nse
qu
ence
of
Imp
act
s
Typ
e o
f Lo
ss
Co
nse
qu
en
ce
1
(In
sign
ific
ant)
2
(M
ino
r)
3 (
Mo
de
rate
) 4
(M
ajo
r)
5 (
Seve
re)
Imp
act
to
Pe
op
le
Min
or
inju
ry.
Slig
ht
neg
ativ
e im
pac
t o
n in
div
idu
al
hea
lth
.
Sign
ific
ant
rep
ort
able
in
jury
Maj
or
imp
act
on
hea
lth
o
f se
vera
l peo
ple
.
Maj
or
inju
ry t
o o
ne
or
mo
re p
erso
ns.
Seve
re h
ealt
h im
pac
ts
on
a n
um
ber
of
peo
ple
.
Sin
gle
fata
lity
Seve
re ir
reve
rsib
le d
isab
ility
o
r im
pai
rmen
t.
Mu
ltip
le f
atal
itie
s.
Maj
or
per
man
ent
neg
ativ
e h
ealt
h im
pac
ts o
n a
larg
e n
um
ber
of
peo
ple
Imp
act
to
Pro
per
ty
/ La
nd
Use
Co
uld
cau
se m
ino
r d
amag
e <$
10K
C
ou
ld c
ause
mo
der
ate
d
amag
e $
10K
to
$1
00
K
Co
uld
cau
se m
ajo
r d
amag
e $
10
0K
to
$1
M
Co
uld
cau
se s
ever
e d
amag
e $
1M
to
$1
0M
U
np
lan
ned
min
e cl
osu
re
dam
age
>$1
0M
<1%
of
pro
per
ty
dir
ectl
y im
pac
ted
1
– 5
% o
f p
rop
erty
d
irec
tly
imp
acte
d
5 -
20
% o
f p
rop
erty
d
irec
tly
imp
acte
d
20
- 5
0%
of
pro
per
ty d
irec
tly
imp
acte
d
>50
% o
f p
rop
erty
dir
ectl
y im
pac
ted
Insi
gnif
ican
t ch
ange
to
wat
er a
vaila
bili
ty
Min
or,
tem
po
rary
ch
ange
to
wat
er a
vaila
bili
ty w
ith
al
tern
ativ
e su
pp
lies
read
ily a
vaila
ble
Maj
or,
tem
po
rary
ch
ange
to
wat
er
avai
lab
ility
wit
h
alte
rnat
ive
sup
plie
s av
aila
ble
Seve
re, l
on
g te
rm c
han
ge t
o
wat
er a
vaila
bili
ty w
ith
al
tern
ativ
e su
pp
lies
dif
ficu
lt
to o
bta
in
Per
man
ent
chan
ge t
o
wat
er a
vaila
bili
ty, n
o
alte
rnat
ive
sup
plie
s
Insi
gnif
ican
t in
dir
ect
imp
acts
, lan
d
pro
du
ctiv
ity
un
chan
ged
Mo
der
ate
ind
irec
t im
pac
ts w
ith
iso
late
d
chan
ges
to la
nd
p
rod
uct
ivit
y, e
asily
m
itig
ated
Mo
der
ate
ind
irec
t im
pac
ts w
ith
bro
ad
chan
ges
to la
nd
p
rod
uct
ivit
y, r
equ
irin
g st
and
ard
mit
igat
ion
s
Seve
re in
dir
ect
imp
acts
wit
h
larg
e sc
ale
chan
ges
to la
nd
p
rod
uct
ivit
y, r
equ
irin
g co
mp
lex
mit
igat
ion
s
Cat
astr
op
hic
ind
irec
t im
pac
ts w
ith
per
man
ent
chan
ges
to la
nd
p
rod
uct
ivit
y th
at c
ann
ot
be
mit
igat
ed
Sk
ard
on
Riv
er B
auxi
te P
roje
ct
C
hap
ter
1 -
Intr
od
uct
ion
Pag
e 1
-14
Pag
e 1
-14
Typ
e o
f Lo
ss
Co
nse
qu
en
ce
1
(In
sign
ific
ant)
2
(M
ino
r)
3 (
Mo
de
rate
) 4
(M
ajo
r)
5 (
Seve
re)
Imp
act
to
Envi
ron
me
nt
Neg
ligib
le r
ever
sib
le
envi
ron
men
tal
imp
act
req
uir
ing
very
min
or
or
no
re
med
iati
on
. A
lte
rati
on
or
dis
turb
ance
to
ec
osy
stem
wit
hin
n
atu
ral v
aria
bili
ty.
Min
or
reve
rsib
le
envi
ron
men
tal i
mp
act
req
uir
ing
min
or
rem
edia
tio
n. M
easu
rab
le
chan
ges
to e
cosy
stem
co
mp
on
ents
.
May
re
sult
in s
mal
l d
ecre
ases
to
a lo
cal
po
pu
lati
on
th
at w
ou
ld b
e re
solv
ed w
ith
ou
t fu
rth
er
mit
igat
ion
. An
y p
op
ula
tio
n
chan
ges
resu
ltin
g fr
om
m
ino
r im
pac
ts w
ou
ld f
all
wit
hin
nat
ura
l flu
ctu
atio
ns
of
a lo
cal p
op
ula
tio
n, t
hat
is
, wit
hin
th
e n
orm
al
carr
yin
g ca
pac
ity
of
the
area
.
Mo
der
ate
reve
rsib
le
envi
ron
men
tal i
mp
act
wit
h s
ho
rt t
erm
eff
ect
req
uir
ing
mo
der
ate
rem
edia
tio
n.
Mea
sura
ble
ch
ange
s to
ec
osy
stem
co
mp
on
ents
w
ith
ou
t m
ajo
r ch
ange
in
fun
ctio
n. R
eco
very
in 1
-
2 y
ears
fo
llow
ing
the
even
t.
May
res
ult
in a
su
bst
anti
al c
han
ge t
o a
lo
cal p
op
ula
tio
n, w
hic
h
wo
uld
no
t le
ad t
o
exti
nct
ion
at
any
leve
l.
Maj
or
en
viro
nm
enta
l im
pac
t w
ith
med
ium
ter
m e
ffec
t re
qu
irin
g si
gnif
ican
t re
med
iati
on
. Mea
sura
ble
ch
ange
s to
eco
syst
em
com
po
nen
ts w
ith
maj
or
chan
ge in
fu
nct
ion
. Rec
ove
ry
in 3
- 1
0 y
ears
fo
llow
ing
the
even
t.
May
be
det
rim
enta
l or
to t
he
spec
ies
or
com
mu
nit
y at
a
po
pu
lati
on
sca
le. H
igh
n
egat
ive
imp
acts
may
re
sult
in
loca
l ext
inct
ion
or
dec
lines
an
d a
co
nse
qu
ent
sub
stan
tial
d
ecre
ase
in a
bu
nd
ance
an
d
po
pu
lati
on
via
bili
ty a
t la
rger
sc
ales
. Hig
h n
egat
ive
imp
acts
m
ay a
lso
be
qu
alif
ied
by
the
con
serv
atio
n s
tatu
s o
f th
e va
lue
bei
ng
affe
cted
.
Extr
eme
en
viro
nm
enta
l im
pac
t w
ith
lon
g te
rm
effe
ct r
eq
uir
ing
maj
or
rem
edia
tio
n r
egu
lato
ry
inte
rven
tio
n o
r p
rem
atu
re
clo
sure
of
the
op
erat
ion
. Lo
ng
term
an
d p
oss
ibly
ir
reve
rsib
le d
amag
e to
1 o
r m
ore
eco
syst
em f
un
ctio
ns.
R
eco
very
, if
at a
ll, >
10
ye
ars
follo
win
g th
e ev
ent.
Wo
uld
res
ult
in t
he
regi
on
al e
xtin
ctio
n o
f a
spec
ies
or
com
mu
nit
y o
r in
ca
tast
rop
hic
dec
lines
an
d a
co
nse
qu
ent
sub
stan
tial
d
ecre
ase
in a
bu
nd
ance
an
d
po
pu
lati
on
via
bili
ty a
t th
e N
atio
nal
or
Stat
e s
cale
.
Imp
act
to
Co
mm
un
ity
Slig
ht
neg
ativ
e
imp
act
on
ind
ivid
ual
s in
loca
l
com
mu
nit
y.
Flar
e u
p o
f is
sues
in
affe
cte
d c
om
mu
nit
ies.
Med
ia c
riti
cism
.
Sign
ific
ant
pu
blic
crit
icis
m, e
.g.
com
mu
nit
y co
mp
lain
ts.
Med
ia o
r N
GO
‘tak
e u
p
the
issu
e’.
Maj
or
neg
ativ
e im
pac
t
on
eco
no
mic
via
bili
ty.
Loss
of
com
mu
nit
y’s
eco
no
mic
via
bili
ty. S
ign
ific
ant
dam
age
to r
ep
uta
tio
n o
f th
e
op
erat
ion
s.
Pu
blic
inte
rnat
ion
al
con
dem
nat
ion
. Maj
or
bre
akd
ow
n o
f so
cial
ord
er
in a
ffec
ted
co
mm
un
ity.
Sk
ard
on
Riv
er B
auxi
te P
roje
ct
C
hap
ter
1 -
Intr
od
uct
ion
Pag
e 1
-15
Pag
e 1
-15
Tab
le 1
-2
Ris
k A
na
lysi
s M
atr
ix (
Co
nse
qu
ence
an
d L
ikel
iho
od
)
C
on
seq
uen
ce
Ty
pe
of
Loss
1
(In
sign
ific
ant)
2
(M
ino
r)
3
(Mo
der
ate
) 4
(M
ajo
r)
5
(Sev
ere)
Likelihood
A
(Alm
ost
C
erta
in)
The
even
t h
as o
ccu
rred
fre
qu
entl
y: o
ccu
rs o
ne
or
mo
re
tim
es p
er y
ear
and
is li
kely
to
re
-occ
ur
wit
hin
1 y
ear
>90
%
chan
ce
Med
ium
(M
) H
igh
(H
) H
Ex
trem
e (E
) E
B
(Lik
ely)
The
even
t h
as o
ccu
rred
bu
t is
no
t fr
equ
ent:
occ
urs
less
th
an o
nce
per
yea
r an
d is
like
ly t
o r
e-o
ccu
r w
ith
in 5
ye
ars
50
-90
%
chan
ce
M
M
H
H
E
C
(Po
ssib
le)
The
even
t h
as h
app
ened
in t
he
bu
sin
ess
in t
he
pas
t 1
0
year
s o
r co
uld
hap
pen
wit
hin
th
e n
ext
10
yea
rs
30
-50
%
chan
ce
Low
(L)
M
H
H
H
D
(Un
likel
y)
The
even
t h
as h
app
ened
in t
he
bu
sin
ess
in t
he
pas
t 2
0
year
s o
r co
uld
hap
pen
wit
hin
th
e n
ext
20
yea
rs
10
-30
%
chan
ce
L L
M
M
H
E (Rar
e)
The
even
t h
as n
ever
bee
n k
no
wn
to
occ
ur
in t
he
bu
sin
ess
and
it is
hig
hly
un
like
ly t
hat
it w
ill o
ccu
r w
ith
in
less
th
an t
he
nex
t 2
0 y
ears
<10
%
chan
ce
L L
M
M
M
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-16
Page 1-16
1.15 Environmental Management
1.15.1 Environmental Management Plan
Gulf Alumina has prepared an environmental management plan (EM Plan) for the Project based on the information provided in this EIS, which is provided in Appendix 13. The EIS covers all aspects of environmental management for the Skardon River Bauxite Project, as required by the Project’s ToR.
Gulf Alumina manages the decommissioned kaolin mine (in care and maintenance) under a Plan of Operations and Rehabilitation Plan, with the current plan covering the period from February 2015 to February 2016. Financial assurance has been provided to the State, based on the expected rehabilitation of the kaolin mine. Much of the infrastructure (e.g. wet plant) has been decommissioned and removed from the site. In addition, the existing EA for the mining leases conditions environmental management of the kaolin mine whilst in care and maintenance.
The EM Plan covers the proposed Project and rehabilitation of the decommissioned kaolin mine that formerly operated on the Project’s mining leases (MLs), previously owned and operated by ACC Ecominerals and Skardon River Kaolin (SRK). The EM Plan provides the framework for environmental management of kaolin mine and Project activities during construction and operation. Where required, plans for environmental management during construction and operation activities will be developed prior to those activities commencing, and will be based on the EM Plan.
1.15.2 Monitoring and Measurement
The proposed monitoring plan for each environmental value is contained within the chapters of this EIS. Environmental monitoring will address meeting any EA conditions and environmental legal obligations, implementation of the operational controls developed, as well as progress towards objectives and targets. Monitoring plans will be developed that outline the environmental monitoring to be undertaken, including monitoring sites, parameters, frequency, procedures or methods, and records to be kept. Monitoring records will be kept and results reviewed on an as required basis to determine ongoing compliance.
1.15.3 Records Management
Records will be kept to demonstrate compliance with the EA and other identified environmental legal obligations.
1.15.4 Reporting, Corrective and Preventive Action
Statutory reporting requirements will be identified as part of the environmental legal obligations and undertaken as per the reporting requirements. To ensure continual improvement, any non-conformance with the EA conditions will be investigated and reported as per the EA requirements, including corrective and/or preventative actions. Where identified, amendments will be made to environmental management plans, EA or operational procedures or plans, based on the outcomes of investigations.
1.15.5 Audits
An audit schedule will be developed to ensure the effective implementation of environmental management and compliance with the EA and other legal obligations. Internal audits will be conducted at regular intervals to cover the scope of all environmental requirements and will be planned based on environmental risk and previous performance.
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-17
Page 1-17
1.15.6 Management Review
A management review will occur on an annual basis to determine the suitability, adequacy and effectiveness of environmental management. Audit results, evaluations of environmental legal compliance and compliance with the environmental objectives will be taken into consideration. The output of the management review will include changes to environmental objectives and targets and the environmental policy consistent with the commitment to continual improvement.
1.16 EIS Document Structure
The structure of this EIS is provided in Table 1-3 and Table 1-4 below comprising:
chapters describing the approvals process, the Project and, for each identified environmental
aspect, the environmental values, potential impacts, risk assessment and mitigation measures
appendices supporting the chapters, including management plans, draft environmental authority
conditions (as proposed by the proponent) and specialist technical reports on identified
environmental aspects.
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-18
Page 1-18
Table 1-3 Chapters Structure
Chapter Chapter Title
Executive Summary
1 Introduction
2 Approvals
3 Public Consultation
4 Location
5 Construction and Operations
6 Water Management
7 Rehabilitation and Decommissioning
8 Non-mining Waste
9 Climate
10 Geology, Topography and Soils
11 Land Use and Land Contamination
12 Water Values and Quality
13 Hydrology and Hydrogeology
14 Flooding
15 Terrestrial Ecology
16 Aquatic Ecology
17 Coastal Processes
18 Marine Ecology
19 Air Quality and Greenhouse Gas
20 Noise and Vibration
21 Landscape and Visual Amenity
22 Transport and Maritime Operations
23 Hazards and Safety
24 Cultural Heritage
25 Social and Economic Impacts
26 Matters of National Environmental Significance
27 References
Skardon River Bauxite Project Chapter 1 - Introduction
Page 1-19
Page 1-19
Table 1-4 Appendix List
Appendix Appendix Name
1 Commitments Register
2 Acronyms and Abbreviations
3 Terms of Reference cross-reference table
4 Water Management
5 Terrestrial Ecology
6 Aquatic Ecology
7 Stygofauna
8 Marine Ecology and Coastal Processes
9 Air Quality
10 Noise and Vibration
11 Gulf Alumina Ltd Environmental Policy
12 EPBC Act Protected Matters Search
13 Environmental Management Plan
14 Draft Environmental Authority Conditions