HAMPTON ROADS TRANSPORTATIONACCOUNTABILITY COMMISSION
Economic Vitality and Quality of Life Unlocking Hampton Roads
HRTAC Background and Project OverviewKevin B. Page
Executive Director
5/15/2019
CONGESTION/FUTURE CONNECTIVITY2040 Population
2040 Employment
2
The Stage is set for Regional Transportation Solution Consensus Building
• For two decades the Region has identified these projects
Unlocking
Ham
pton
Roads
3
MOVING THEREGIONFORWARDHRTAC/HRTFOverview
• Hampton Roads Transportation Fund created 2013 Acts of Assembly HB2313
• HRTAC created 2014 Acts of Assembly HB1253 – Hired Executive Director August 2015
• Empowered to procure, finance, build and operate highway, bridge, tunnel, rail and transit projects in Hampton Roads
• Authorized to use HRTF monies and tolls for new construction projects on new or existing highways, bridges and tunnels and to issue bonds using revenues to support bond debt
• Regional Collaboration ‐Works closely with the Hampton Roads Transportation Planning Organization (HRTPO) who determines Project Prioritization for the region
Unlocking
Ham
pton
Roads
4
19 Voting members
4 Non‐Voting Ex‐officio membersCommonwealth Transportation Board MemberVirginia Department of TransportationVirginia Department of Rail and Public TransportationVirginia Port Authority
• June 21, 2017 ‐Michael Hipple elected Chair and Linda Johnson elected Vice‐Chair• HRTAC is a political subdivision of the Commonwealth• Primarily funded with HB 2313 revenue (Hampton Roads Transportation Fund)
approved by the 2013 General Assembly
10 Cities 4 CountiesChesapeake Isle of WightFranklin James CityHampton SouthamptonNewport News YorkNorfolkPoquoson 5 VA General Assembly MembersPortsmouth Two Members of the SenateSuffolk Three Members of the House of
DelegatesVirginia BeachWilliamsburg
HRTACMembership
Unlocking
Ham
pton
Roads
5
Legislation:CongestionReliefHRTAC (HB 1253, 2014)• “…shall give priority to those projects that are expected to provide the greatest impact on reducing congestionfor the greatest number of citizens residing within Planning District 23…”
Statewide Prioritization Process (HB 2, 2014)• “…Hampton Roads highway construction districts…shall ensure that congestion mitigation…is weighted highest among the factors in the prioritization process…”• 45% weighted factor in Hampton Roads 6
Unlocking
Ham
pton
Roads
• Allows investment and provides liability protections• Allows counties to designate a representative• Allows all localities to have representation at the meetings if Chief Elected Officer or County Designee is unable to attend. Notice must be given 48 hours before meeting if regular member is unable to attend
• Administrative and operating expenses shall be paid by HRTAC Revenues
GeneralAssembly– 2016HRTACOmnibusBillHB1111
FineTuningHRTAC
7
Unlocking
Ham
pton
Roads
GeneralAssemblyActions– 2016Tolling
• Language within the State budget establishes new toll policy restricting CTB, VDOT, HRTAC, and NVTA from tolling existing un‐tolled lanes without General Assembly approval except on:• HOV/HOT Lanes• New Lane capacity• New bridges • Short segments of highways between existing toll
facilities• Legislation was adopted allowing better collection of unpaid toll bills
from other states• HRTAC now has state guidance on tolling
8
Unlocking
Ham
pton
Roads
DefiningtheRolesoftheHRTPOandHRTAC
Unlocking
Ham
pton
Roads
9
EVOLUTION OFHRTACProjects
• HRTPO Long Range Transportation Plan identifies priority projects in the constrained plan or vision plan as under study/development/construction
• HRTAC develops a six‐year and long range plans of finance to guide in project funding for development and construction – HRTAC feeds LRTP funding plans
• HRTAC allocates funds to specific projects, asks that the HRTPO add them to the TIP
• The CTB selects the Local Preferred Alternative, maintains Statewide Transportation Improvement Program, allocates state funding to projects in Six Year Improvement Program – awards Smart Scale funding
• VDOT assists in project readiness and construction through HRTAC/VDOT MOA and HRTAC project construction agreements
Plan
•HRTPO (Long‐Range Transportation Plan with HRTAC Input)•Prioritizes Projects Based on Project Readiness with HRTAC Input
Program•HRTAC (Six‐Year and Long Range Plans of Finance)•CTB (Six‐Year Improvement Program)•HRTPO (Adds HRTAC Projects to Transportation Improvement Program)
Finance & Deliver•HRTAC (Regional Tax Funding/Bonding, Toll Revenues/Bonding, and Smart Scale Grants – Contracts with VDOT or Others to Deliver Projects)•VDOT – Smart Scale Funding (Constructs Projects Contracted by HRTAC)
Unlocking
Ham
pton
Roads
10
2040LRTP: RegionalPriorityProjects
• I‐64 Peninsula Widening• I‐64/I‐264 InterchangeI• I‐64 Southside Widening/High‐Rise Bridge ‐ Phase 1II
•Hampton Roads Crossing: Alternative A ‐ HRBTIII
• I‐64 Southside Widening/High‐Rise Bridge ‐ Phase 2IV
• I‐64/Fort Eustis Blvd Interchange•US Route 460/58/13 Connector•Bowers Hill Interchange
V
‘Sequencing Based on Project Readiness’
A major step forward in Regional Consensus Building ‐ February 18, 2016
11
19 Voting members
4 Non‐Voting Ex‐officio membersCommonwealth Transportation Board MemberVirginia Department of TransportationVirginia Department of Rail and Public TransportationVirginia Port Authority
• June 21, 2017 ‐Michael Hipple elected Chair and Linda Johnson elected Vice‐Chair• HRTAC is a political subdivision of the Commonwealth• Primarily funded with HB 2313 revenue (Hampton Roads Transportation Fund)
approved by the 2013 General Assembly
10 Cities 4 CountiesChesapeake Isle of WightFranklin James CityHampton SouthamptonNewport News YorkNorfolkPoquoson 5 VA General Assembly MembersPortsmouth Two Members of the SenateSuffolk Three Members of the House of
DelegatesVirginia BeachWilliamsburg
HRTACMembership
Unlocking
Ham
pton
Roads
12
I‐64 Peninsula Widening: Segment 1 Project Cost: $114 Million $100 Million Federal/State Funds $14 Million HRTAC Completed and Opened to the Public
December 1, 2017
I‐64 Peninsula Widening: Segment 2 Estimated Project Cost: $176 Million Under Construction Estimated Completion: May 2019 $176 Million HRTAC
I‐64 Peninsula Widening: Segment 3 Estimated Project Cost: $244 Million Under Construction Estimated Completion: 2021 $121 Million Federal/State Funds $123 Million HRTAC
I‐64/HRBT Widening Estimated Project Cost: $3.862 Billion Under Construction Estimated Completion: 2025 $3.562 Billion HRTAC
I‐64/I‐264 Interchange Improvements Phase 1 ‐ Under Construction: $157 Million Estimated Completion: 2019 Phase 2 – Under Construction: $195 Million Estimated Completion: 2021 Phase 3 ‐ Design Funded: $10 Million $69 Million Federal/State Funds $2.8 Million Local $290 Million HRTAC
I‐64 Southside/High‐Rise Bridge Widening Phase 1 – Construction Pending: $530 Million Estimated Completion: 2021 $98 Million Federal/State Funds $432 Million HRTAC
Hampton Roads Regional Connectors Study Study Funded: $3 Million $3 Million HRTAC (+ $4 Million HRTAC Contingency)
April 2019
Hampton Roads Regional Transportation Priority Projects“Moving Projects Forward – HRTAC Investments”
Projects Planned and Prioritized by HRTPO, Powered by HRTAC
Bowers Hill Interchange Estimated Project Cost: $659 Million Study Funded: $4 Million $4 Million HRTAC
I‐64 Peninsula Widening: Ft. Eustis Blvd. Interchange
Estimated Project Cost: $320 Million Included in 2040 LRTP
Hampton Roads Regional Priority ProjectsESTIMATED OPENINGYEAR
PROJECT ESTIMATED PROJECT COST ($MILLIONS)
2017‐2022 I‐64 Peninsula – Segments 1, 2, and 3 $534
2019‐2021 I‐64/I‐264 Interchange – Phases I and II $352
2019 I‐64/I‐264 Interchange – Phase III Study $10
2021 I‐64 Southside/High‐Rise Bridge – Phase I $530
2025 I‐64/Hampton Roads Bridge‐Tunnel $3,862
2037 I‐64 Southside/High‐Rise Bridge – Phase II $1,700
2037 Bowers Hill Interchange $659
2038 I‐64/Fort Eustis Blvd Interchange $320
Vision PlanI‐564/I‐664 Connector (Patriots Crossing)I‐664/Monitor‐Merrimac Memorial Bridge‐TunnelVA 164/164 Connector
Unlocking
Ham
pton
Roads
13
MOVING THEREGIONFORWARDSIGNIFICANTPROGRESS
• Current HRTAC Projects Under Agreement:• ~ $5.17B total value $4.64B HRTAC Funded
• Recent HRTAC Accomplishments:• Cut Ribbon on I‐64 Peninsula Widening Segment 1 project
• Broke Ground I‐64 Southside Widening/High Rise Bridge Project Phase I ‐ January 2018
• Inaugural HRTAC/HRTF Bond Offering ‐ January 2018
• Adopted HRTAC Short and Long‐Range funding plans – June 2018
• Confirmed $3.562B HRBT Expansion Project Funding Plan/TIP Amendment – December 2018
• April 2019 – HRTAC/VDOT Executed HRBT Project Agreement
Unlocking
Ham
pton
Roads
14
Description: Widen 5.4 miles of I‐64 to include new general purpose lane and widening of 6 existing bridges.
Images source: VDOT
Jefferson Ave. exit 255 to Rte. 238 exit 247
Cost: $114 million
Status: Completed and open to the
Public(December 1 , 2017)
I-64 Peninsula Widening – Segment 1
15
Description: Widen 6.7 miles of I‐64 to include new general purpose lane, reconstruction of existing lanes, and widening of 9 existing bridges.
Images source: VDOT
Rte. 238 exit 247 to Rte. 199 exit 242
Cost: $176 million
Status: Notice to Proceed (NTP) February 2016(est. completion date May 2019)
I-64 Peninsula Widening – Segment 2
16
16
Description: Widen 8.2 miles of I‐64 to include new general purpose lane, replacing two existing bridges, and widening of 4existing bridges.
Image source: VDOT
Rte. 199 exit 242 to Rte. 199 exit 234
Cost: $244 million
Status: Notice to Proceed (NTP) January 2018
(est. completion date Sept. 2021)
I-64 Peninsula Widening – Segment 3
17
Description: Widen WB I‐264 between Twin Bridges and I‐264, construct new 2‐lane flyover ramp, 2‐lane EB I‐264 CD road, exit ramp from WB I‐64 to new CD road.
I‐64/I‐264 Ramp Improvements
Cost: $157 million
Status: Project Notice to Proceed (NTP) October 2016
(est. completion date October 2019)
I-64/I-264 Interchange – Phase 1 Source: VDOT
Source: VDOT
18
Description: Extend CD road from Newtown Rd. to Witchduck Rd., reconfigure Newtown Rd. & Witchduck Rd. Interchanges, Construct Greenwich Rd. flyover.
I‐264/Newtown Rd. to I‐264/Witchduck Rd. Interchanges
Cost: $195 million
Status: Notice to Proceed (NTP) February
2018(est. completion date September 2021)
I-64/I-264 Interchange – Phase 2 Source: VDOT
Source: VDOT
19
Description: Widen 8.75 miles of I‐64 to include new managed lane and left shoulder, widen six existing bridges, replace one existing bridge, and construct new High Rise Bridge – Phase 1.
Widen from I‐64/I‐464 to I‐64/I‐264/I‐664 at Bowers Hill
Cost: $532 million
Status: Phase I Notice to Proceed (NTP) November 2017
(est. completion date July 2021)
I-64 Southside Widening/High Rise Bridge – Phase 1Source: VDOT
Source: VDOT
20
Description: Expand the Hampton Roads Bridge Tunnel and provide 6‐lane capacity on I‐64 from the Settlers Landing Rd. Interchange to the I‐564 Interchange.
I‐64 from Settlers Landing Rd. Interchange to I‐564 Interchange
Estimated Cost: $3.8 billion
Status: April 2019, HRTAC/VDOT executed funding agreement. DB contract signed by VDOT (estimated completion 2025)
I-64/HRBT Widening Source: VDOT
Source: VDOT
*Estimates are expressed in Year of Expenditure (YOE) in order to account for inflation
21
22
HRBT Project Cost and HRTAC Cost Share• Total project cost is $3.862B – Including South Trestle Bridges
• $3.300B DB contract and $562M other costs
• South Trestle costs: $95M DB price and $14M other costs, totaling $109Mo Allocable project development and contingency costs to South Trestle is
based on its share in the $3.300B DB price.
• $3.753B net of South Trestles is the adjusted total value of the HRBT capacity improvement project.
• Options not included in the project total include I‐564 Direct Connectors and Bridge Repair Option Work (not deemed as Deferred/Preventive Maintenance Work).
inmillions
HRBTProjectCost SouthTrestle NetofSouthTrestle(New
Capacity Project)
ProjectDevelopment(PE&CEI) $122 $4 $118
Right‐of‐Way $15 $15
Design‐BuildContract(NottoExceed) $3,300 $95 $3,205
NoExcusesIncentive $90 $90
Contingency $335 $10 $325
Total $3,862 $109 $3,753
23
HRBT Maximum HRTAC Financial Commitment
• HRTAC’s Maximum HRTAC Financial Commitment is $3.562B ‐ which includes $345M of anticipated toll revenue funding and will be reduced dollar‐for‐dollar in receipt of additional non HRTF funding.
• After subtracting $345M of anticipated toll revenue, HRTF funding will not exceed $3.217B.
• Any SMART SCALE or other non‐HRTF funding awards (USDOT INFRA grant funds) will reduce the $3.217B HRTF commitment dollar‐for‐dollar.
Unlocking
Ham
pton
Roads
24
HRBT Financing in the FY2020 ‐ FY2026 Program of Projects• Assume HRTAC receives $345M toll revenue debt proceeds for construction of
HRBT (toll revenue leveraging under discussion with VDOT).
• Assume $200M SMART SCALE is awarded.
• Maximum $3.217B HRTF funding; cost savings and other non‐HRTF grant awards will reduce HRTF funding and release the commitment at close out.
• Approximately half of the maximum $3.217B HRTF funding will be provided with HRTF debt proceeds and the remaining half with HRTF paygo cash.
• In addition, HRTF paygo cash is expected to fund debt service reserve funds of approximately $100M (the funds earn interest and can be used towards the last debt service payment).
Proposed HRBT Project in the Program of Projects
HRTAC HRTF HRTAC Toll Revenue VDOT Total
Project Budget $3,017M $345M $200M $3,562M
HRTAC HRTF Commitment (released at close out pending savings or other non-HRTF fund awards)
$200M $200M
Total $3,217M $345M $200M $3,762M
in millions
Unlocking
Ham
pton
Roads
25
Project Costs and Expenses & Funding Sources
TotalOperating/HRTF Fees $14 $6 $6 $6 $6 $6 $6 $6 $56 $56I-64 Peninsula Widening $416 $78 $41 $534 $313 $221I-64/I-264 Interchange Improvement $286 $44 $24 $8 $362 $290 $67 $5I-64 Southside/High Rise Bridge $254 $197 $79 $530 $432 $98Project Development $45 $1 $46 $46HRBT $76 $362 $1,115 $699 $538 $587 $346 $40 $3,762 $3,562 $200Total $1,091 $686 $1,264 $713 $544 $593 $352 $46 $5,289 $4,699 $586 $5
Funding SourcesPrior Years
FY 2020
FY 2021
FY 2022
FY 2023
FY 2024
FY 2025
FY 2026 Total
VDOT Funds $280 $64 $34 $8 $200 $586Other Local Funds $5 $5HRTAC Cost Share $805 $623 $1,230 $705 $544 $393 $352 $46 $4,699Total $1,091 $686 $1,264 $713 $544 $46 $5,289
HRTAC Project Costs and Expenses
VDOT Funds
Other Local Funds
HRTAC Cost Share
FY 2022
FY 2023
FY 2026
Prior Years
FY 2020
FY 2021
FY 2024
FY 2025
Proposed FY2020‐FY2026 Update
Unlocking
Ham
pton
Roads
26
HRTAC Projected Cash Flow FY 2020 to FY 2026
FY 2020 FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 FY 2026 TotalHRTF .7% local Sales Tax Funds $145 $148 $152 $155 $159 $163 $167 $1,088HRTF 2.1% Fuel Tax Funds $55 $56 $56 $56 $56 $57 $57 $394
Total HRTF Revenue $200 $204 $208 $212 $215 $220 $224 $1,482
HRTAC Toll Revenues $4 $4 $4 $4 $16HRTF Interest Income $5 $15 $7 $2 $2 $2 $3 $36HRTF Investment Income $8 $5 $2 $1 $2 $19HRTAC HRTF Revenue Debt Proceeds $301 $778 $556 $378 $177 $2,190HRTAC Toll Revenue Debt Proceeds $75 $230 $40 $345
Total Available HRTAC Funding $514 $1,002 $773 $597 $472 $456 $273 $4,088
HRTAC Cost Share $623 $1,230 $705 $544 $393 $352 $46 $3,893HRTAC Debt Service $26 $34 $59 $59 $59 $84 $115 $436HRTAC Debt Service Reserve $33 $54 $20 $107
Total Annual Expenditure $681 $1,264 $764 $658 $472 $436 $161 $4,437
Carryover Balance From Previous Year $580 $414 $151 $160 $100 $100 $120Remaining HRTAC Funds Unobligated $414 $151 $160 $100 $100 $120 $231
HRTAC Projected Cash Flow
Proposed FY2020‐FY2026 Update
Unlocking
Ham
pton
Roads
27
Overall HRTAC Financial Plan Funding Mix
• Funded projects including HRBT are financed with well‐balanced sources including HRTF pay‐go, HRTF bonds, HRTF TIFIA loans, toll revenue TIFIA loan, and VDOT Funds.
Unlocking
Ham
pton
Roads
28
HRTAC 2045 Long Range Funding Plan Update
• Modifications include adjustments in Approved Projects to reflect amended contract values due to float down adjustments to certain projects
• Updated HRBT cost• 460/58/13 project was eliminated due to HRTPO action in FY2019
Approved Projects HRBT HRB II Bower's Hill
InterchangeFt. Eustis
InterchangeTotal FV
CostFunded by HRTF Debt
Funded by Toll Debt
Funded by HRTAC Pay-Go
Funded by VDOT and Other Pay-
Go
2045 (With Toll Revenues to HRTAC)Inflated Costs (MM) $1,415 $3,762 $1,729 $659 $320
Fiscally Constrained Construction End Year 2022 2026 2037 2037 2038
$7,885 $4,020 $345 $2,860 $660
Proposed FY2045 Update
Unlocking
Ham
pton
Roads
VDOT Proposed Hampton Roads Express Lanes Network – Region Needs to Weigh In
• Segment 1 – Operational
• Segment 2 – Under Construction
• Segment 3 & Segment 4 –Traffic and Revenue Study and Concept of Operations Underway
29
Source: V
A Secretary of Transpo
rtation
Source: VA Secretary of Transportation
HRBTFundingPoints• HRTPO submitted application for $200M Smart Scale funding for HRBT ‐ HRTAC funding plan is reliant on these funds
• Current assumptions include HRTAC’s forecast of toll revenues and the Commission’s approved plans include all net toll revenues being used to support HRTAC projects – Master Tolling Agreement is a work in progress
30
Unlocking
Ham
pton
Roads
31
HighwayNetworkofProgress
Unlocking
Ham
pton
Roads
NextSteps
32
Unlocking
Ham
pton
Roads
• HRTAC will continue work to develop solutions and continue construction of HRTAC’s approved/funded projects and advance short and long range plans
• HRTAC will also work with the HRTPO and impacted jurisdictions to study the remaining projects not selected in the SEIS Alternative A (Regional Connectors Study)
• HRTAC will continue to support VDOT in project development efforts for the Bowers Hill Interchange and the I‐64/I‐264 environmental and preliminary engineering studies
• Continue public discussion on how to calibrate funding options, advance project readiness, and continue preparations for future bonding/financing of projects
www.hrtac.org