hamish westwater · pre-drill, garten schedule was to deliver first production end q1 2019 however,...
TRANSCRIPT
HAMISH WESTWATER – PROJECTS GROUP MANAGER
1. Introduction
2. Beryl Hub / Garten Opportunity
3. The Leadership Challenge
4. Critical Success Factors
Culture & Leadership – Setting the Expectation
Early Stakeholder Engagement – Challenging the Norm
Fit for Purpose Design / Collaboration
5. Meeting The Challenge - Accelerated Schedule
6. Delivering The Scope - Facilities
7. Final Outcome – Key Lessons Learned
INTRODUCTION / AGENDA
2
Beryl area lies in the UK North Sea around 200 miles NE of Aberdeen in blocks 9/13, 9/18 & 9/19
Beryl First Production in 1976
Acquired by Apache 2011
In excess of 230 Development Wells (47 subsea wells) in total
Garten (6km SE of Beryl A)
Discovery Well - March 18
First Production – Nov 18
BERYL HUB / GARTEN FIELD
3
Beryl Bravo
Beryl AlphaNevis
Ness
Buckland
Storr
Callater
Garten
Skene
GARTEN PROJECT – THE CHALLENGE
4
Pre-Drill, Garten Schedule was to deliver First Production end Q1 2019
However, significantly better than expected wellbore logs brought around a challenge to accelerate production into Q4 2018 and maximise value to Apache
Culture & Leadership
Set clear expectations
Facilitate approvals
Empower the team
Challenge The Norm
Identify critical path
Challenge history
Ask what can be done to accelerate
Early Stakeholder Engagement
Identify Stakeholders that
can influence schedule
Explain Challenge and work
together to deliver
Fit For Purpose Design /
Collaboration
Utilise existing design
Don’t optimise the unknown
Trust the Supply Chain
GARTEN PROJECT – CRITICAL SUCCESS FACTORS
5
Culture & Leadership – Setting the Expectation Clear Leadership and expectations communicated from the Management Team
All in-house Functions co-located and empowered to act – Apache Core Values
Operations and Projects working closely together to deliver change – Operational Excellence
Working Managers
Decisive, Invested
and Committed
Fire in the Belly
Sees the Big Picture and Translates into Action
Best Answer
Wins
Communicates Effectively
GARTEN PROJECT – CRITICAL SUCCESS FACTORS
6
Early Stakeholder Engagement – Challenge the Norm
Review of the Critical Path identified many Stakeholder activities out with Apache’s direct control but within our sphere of influence:
Commercial CTIA
Commercial TPOSA
FDP/ES Submission & Approval
PWA Approvals
Safety Case Update
By engaging early and challenging the norm with the Regulatory Bodies and our Partners, we successfully changed timelines and ways of working to accelerate all critical path approvals:
Commercial CTIA
Commercial TPOSA
FDP/ES Submission & Approval
PWA Approvals
Safety Case Update
All negotiated and approved in < 8 monthsSetting a new benchmark
(In many cases, Approval times vastly accelerated)
GARTEN PROJECT – CRITICAL SUCCESS FACTORS
7
Fit For Purpose Design - Collaboration Tried, Tested and Trusted Supply Chain - Utilising in place Service Agreements
Exploit trusted relationships and Asset knowledge (Existing proven design)
Maximise responsiveness and reactiveness
Highly Optimised schedule prepared including multiple parallel scopes and approvals
MEETING THE CHALLENGE - ACCELERATED SCHEDULE
8
ACTIVITY
Garten Development
Appraise CP2
Topsides & Subsea FEED Complete CP3
Post Drill Basis of Design Issue
Drilling and Completion
Commercial CTIA
Commerical TPOSA
FDP/ES Submission
FDP/ES Approval
PWA Approvals
Detailed Eng & Des
Proc & Fab [inc. Long Leads]
Topsides Construction CP4
Subsea Installation CP4
Commissioning & Start-Up CP5
First Oil
Project Close Out
2017 2019
Q1Q4 Q2
2018
Q1 Q3 Q4
Milestone
DELIVERING THE SCOPE - FACILITIES
9
FINAL OUTCOME / LESSONS LEARNED
10
Outcome: Discovery to First Production in < 8 months
3 zone smart completion
Subsea well tied back through Buckland bundle (utilising existing infrastructure)
Production re-routed from A6 to E4 riser (utilising existing infrastructure)
Topsides designed to deliver minimum 15mbd with potential upside of 25mbd via twin flowlines to existing platform infrastructure
Project future proofed for future production wells and water injection once reservoir characteristics known and fully understood
Key Lessons: Possible to Maximise Value by accelerating production
Historical Norms (internal and external) can be challenged and improved
Design to the P50 case and where possible use existing infrastructure and standardise where possible
Put Trust in your team and Trust the Supply Chain