h - protection & controls

Upload: nguyentruong

Post on 07-Aug-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/20/2019 H - Protection & Controls

    1/121

    Designing in

    Engineering Risk Controls?

    H - Engineering Controls

    HAZARD ELIMINATION is better than

    PREVENTION is better than

    CONTROL is better than

    MITIGATION is better than

    EMERGENCY RESPONSE

    Inherently Safer Design Philosophy

    PASSIVE controls are more reliable thanACTIVE controls are more reliable than

    OPERATIONAL or PROCEDURAL controls.

    AND

    Prevent/Control/Mitigation Systems

    • Keep equipment within safe operating limits

    – Operational controls

    – Alarms

    – Trips

    • Minimize

    escalation by

    Containment > Isolation > Survival > Relieving

    H

     A

    Z

     A

    R

    D

    C

    O

    N

    S

    E

    Q

    U

    E

    N

    C

    E

    PREVENTION

    BARRIERS

    PREVENTION

    BARRIERS

    CONTROL - MITIGATION

    ESCALATION BARRIERS

    CONTROL - MITIGATION

    ESCALATION BARRIERS

    TOP EVENT

  • 8/20/2019 H - Protection & Controls

    2/122

    • Overpressure protection

    • Protective instrumentationto alert/alarm/control

    • Devices to maintain SafeOperating Limits

    • Ignition preventionmeasures

    • Fire/gas detection,alarms

    • Emergency shutdown,isolation, and flare

    • Fire protection

    • Evacuation/survivalequipment

    Class 1 Div. 1

    Prevent/Control/Mitigation Systems

    TO FLARE

    Emergency Isolation Valves

    1. Provide isolation between different hazards within asystem.

    2. Quickly interrupt flow through a system or preventgross movement of hazardous material into anexposed location.

    3. Block in specific pieces of hardware that may be

    involved in an incident.4. Cause an orderly shutdown of equipment.

    EIV’s are typically actuated into the closed position.

    Process Control

    • Measure all significant variables.

    • Control those variables which have

    the greatest influence on the process.

    Control Hazards

    • Determine independent and dependent variables.

    • Evaluate relative sensitivities.

    • Alarm flood.

    • Consider prevalent failure modes in system design,instrumentation, hardware including human error.

    Instrumentation & Control

  • 8/20/2019 H - Protection & Controls

    3/123

    • Incorrect sensing• Contamination of process stream• Inaccurate readings• Wrong response• Delayed response• Wrong sensor location• Defective actuator• Plugged or restricted impulse line• Process upset outside range of specified

    control loop.• Control valve failure

     AAA

    1

    Common Control Problems

    PSVs: Last overpressure barrier

    Process alarms/trips: The first barriers

  • 8/20/2019 H - Protection & Controls

    4/124

    Plant Area

    Gas

    OilWater 

    Well Fluids

    ESD Valve

    HighPressure

    Sensor 

    MechanicalRelief Valve

    to Flare

    Shutdown SystemLogic Solver 

    Control Room

    Operator Interface

    Separator 

    Safety Instrumented System

    • IEC 61508 (ISA S84.01) requires all criticalinstruments to demonstrate level of integrityrequired in design.

    • Analyze the reliability of the safety instrumentedfunction as an overall system

    •Each instrument loop must be individually

    analyzed to determine how and when failuresmight occur.

    • Required reliability may be achieved throughredundancy, increased testing, use of PLCs

    Safety Instrumented Systems

    SAFETY INTEGRITY

    LEVEL *

    PROBABILITY OF THE SYSTEM

    FAILING ON DEMAND (PFD)

    SIL-1 10-1 TO 10-2

    SIL-2 10-2 TO 10-3

    SIL-3 10-3 TO 10-4

    * SIL performance can be improved by th e addition of redundancy,

    more frequent testing, use of diagnostic fault detection, diverse

    sensors and control element selection.

    Safety Integrity Level - SIL

  • 8/20/2019 H - Protection & Controls

    5/125

    • Gas detection is used to determine the presenceof undesired vapors and gases at some specifiedconcentration.

    • Used to support some action or decision.

    • Sensor needs to be located where gas is mostlikely to accumulate.

    Gas Detection

    WHAT WE KNOW

    Concentration oftest gas at point ofmeasurement atspecific time.

    WHAT WE DON’T KNOW

    1. How much gas is present.

    2. How far the gas cloudextends.

    3. Concentration profile withinthe cloud.

    4. What other gases arepresent.

    5. How fast the gas is moving.

    Gas Detection – interpretation of results

    • Conduct a Fire HazardAnalysis to understandresidual risk that warrantsfire protection– Type of fire, size, duration

    Fire Protection

    •Fireproofing onstructural and processequipment (2-4 hr) and 30minutes on critical E&Isystems.

  • 8/20/2019 H - Protection & Controls

    6/126 

    • Fire water pump, supply, and deliverysystems– Fire hydrants and monitors

    – Deluge protection in critical areas such aspump bays.

    – Sprinkler systems

    – Foam Systems

    – Carbon dioxide

    systems

    Fire Protection

    Safety Critical Equipment

    • Define what equipment is “Safety Critical”

    – What % of all equipment?

    • Define what maintenance and testing regime is

    required for “Safety Critical Equipment”

    – SCE needs to work when you want it to

    Safety critical equipment (SCE)• Equipment that has the greatest influence on

    the safety of:– People

    – Environment

    – Integrity of equipment

    • Identifies equipment that is most critical tothe management of major accident hazards

    • Allows management to optimise maintenanceand inspection of equipment to manage MAR’s

    • Recorded in registers that includeperformance standards

  • 8/20/2019 H - Protection & Controls

    7/127 

    Critical equipment assessments

    In general, static equipment, e.g. hydrocarbon duty piping,is not considered SCE unless there is a reasonableexpectation that the equipment might fail in service,e.g. due to corrosion

    “80-20” Rule Equipment-Risk Distribution

    Safety-Related Devices (pressure)

    • Maintain Equipment in Design Envelope– Relief valves

    – Bursting discs

    – Vacuum breakers

    – Restriction orifices

    – Flame arrestors

    – High integrityprotective systems

    – Check valves

    – Flow-limiting control valves

    – Fire resistant insulation

    Full Equipment

    Inventory

    Safety Critical

    Equipment List

  • 8/20/2019 H - Protection & Controls

    8/128 

    Evacuation / Survival equipment is SCE

    How do you ensure youget what you want?

    Safe Plant?

    Codes, Standards, ETPs

    Design reviews

    Eng and Tech Authorities

    Approved contractors/vendors

    Certification / Handover

    BP Capital Value Process

    Design and Construction Assurance

    How do you ensure you getwhat you want?

  • 8/20/2019 H - Protection & Controls

    9/129

    Capital Value Process

     APPRAISE

    DSP

    Gate

    DSP

    GateSELECT

    DSP

    GateEXECUTE

    Capital Value Process

    DSP

    GateDEFINE OPERATEDSP

    Gate

    Finalize project

    scope, cost and

    schedule and

    getproject funded

    Produce an

    operating asset

    consistent

    with scope,cost and

    schedule

     Main ProjectCVP Staged  deliverables

    Front End Loading

    Select the

    preferred

    project

    option(s)

    Determine

    project feasibility

    and alignment

    with businessstrategy

    Evaluate asset

    to ensure

    performance to

    specifications andmaximum return to

    the shareholders

    YEAR 1 YEAR 2 YEAR 3

    CONCEPTUAL

    WHAT IF

    TECHNOLOGY SAFETY

    REVIEWS

    TECHNOLOGYSCREENING STUDIES

    PFD DEVELOPMENT

    PLOT PLANREVIEW

    CONSEQUENCEMODELING

    INHERENT SAFETY

    REVIEWS

    FIRE CODES

    FIRE PROTECTIONREVIEWS

    ENGINEERING QUALITY REVIEWS

    H&M BALANCESPRODUCTION

    MODELING

    WHAT IF ANALYSIS HAZOPS

    PRE-STARTUPSAFETY REVIEWS

    REVIEW OF PROCESSSAFETY CONCEPTS

    REVIEW OF SPEC

    DEVIATIONS

    SCENARIOPLANNING

    LOPA

    RE-VISIT FACILITYSITING

    Safety Reviews in Projects

    What is a PHSSER?

    Project Health, Safety, Security and Environment Review

    • Seven reviews matching key gates of Projectdevelopment

    • Face-to-face discussion withproject/contractor/operations personnel

    • Focuses only on HSSE issues not schedule and cost• Team of independent, experienced specialists• Reports findings and recommendations to client and

    project

    ETP GP 48-01 HSSE Review of Projects

  • 8/20/2019 H - Protection & Controls

    10/1210

    PHSSER Alignment with CVP

     APPRAISE

    DSP

    Gate

    DSP

    GateSELECT

    DSP

    GateEXECUTE

    Capital Value Process

    DSP

    GateDEFINE OPERATEDSP

    Gate

    Finalize project

    scope, cost and

    schedule and

    getproject funded

    Produce an

    operating asset

    consistent

    with scope,cost and

    schedule

     Main ProjectCVP Staged  deliverables

     HSSE Review Requirements

    Pre-Startup

    PHSSER 

    Front End Loading

    Construction

    PHSSER 

    Operate

    PHSSER 

    Detailed 

    Engineering

    PHSSER 

    Pre-Sanction

    PHSSER 

    Select

    PHSSER 

    Appraise

    PHSSER 

    Select the

    preferred

    project

    option(s)

    Determine

    project feasibility

    and alignment

    with businessstrategy

    Evaluate asset

    to ensure

    performance to

    specifications andmaximum return to

    the shareholders

    BP Grangemouth - UK

    Case History – CH9

    Case History 9-Grangemouth Power

    1999 – BP Grangemouth Refinery, UK

    • New 33kV Sub Station in main power feed

    • Sub Station commissioning in stages

    • Full power tripped new Sub Station

    • Site not able to recover and almost the entire siteexperienced an electrical shutdown.

  • 8/20/2019 H - Protection & Controls

    11/1211

    The Incident

    What Happened

    • Two wires in the protection circuit were interchanged.

    • Full Over-current protection testing not completed.

    • Protection coped when first half board commissioned

    • Protection tripped after second half board was switched

    in took full power.

    • Site not able to recover and almost the entire site

    experienced an electrical shutdown.

    Major Lessons Learned

    • Be sure you have tested allfunctionality beforecommissioning

    • Reviews may not catcheverything.

    P r e - s t a r t  u  p  S a f e t  y  R e v i e w s P r o c e s s  S a f e t  y  A u d i t 

  • 8/20/2019 H - Protection & Controls

    12/12

     Al l Tr ip Checks have been tested???

    Grangemouth July 1999Incomplete 33kV Breaker TestsComplex Shutdown