guinea - economic planning and mining governance … development fund original project : economic...
TRANSCRIPT
AFRICAN DEVELOPMENT FUND
Original
PROJECT : ECONOMIC PLANNING AND MINING
GOVERNANCE SUPPORT PROJECT (PAPEGM)
COUNTRY : GUINEA
PROJECT APPRAISAL REPORT
OSGE DEPARTMENT
June 2013
Translated Document
Appraisal Team
Regional Director : Mr. F. PERRAULT , ORWB
Sector Director : Mr. I. LOBE NDOUMBE, OSGE
Division Manager : Mr. J-L. BERNASCONI , OSGE.1
Team Leader : Mr. A. TARSIM, Senior Economist, OSGE.1
TABLE OF CONTENTS
I - STRATEGIC THRUST AND RATIONALE ......................................................................... 1
1.1 Project Linkages with Country Strategy and Objectives ............................................................. 1
1.2 Rationale for Bank’s Involvement ............................................................................................... 2
1.3 Aid Coordination ......................................................................................................................... 4
II - PROJECT DESCRIPTION ...................................................................................................... 5
2.1 Project Objectives and Components ............................................................................................ 5
2.2 Technical Solutions Adopted and Alternatives Explored ............................................................ 7
2.3 Project Type ................................................................................................................................. 7
2.4 Project Cost and Financing Arrangements .................................................................................. 7
2.5 Project Target Area and Beneficiaries ......................................................................................... 9
2.6 Participatory Approach for Project Identification, Design and
Implementation ............................................................................................................................
9
2.7 Bank Group Experience and Lessons Reflected in Project Design ............................................. 9
2.8 Key Performance Indicators ........................................................................................................ 10
III- PROJECT FEASIBILITY ........................................................................................................ 11
3.1 Economic and Financial Performance ......................................................................................... 11
3.2 Environmental, Social and Gender Impact .................................................................................. 11
IV- PROJECT IMPLEMENTATION ........................................................................................... 12
4.1 Implementation Arrangements .................................................................................................... 12
4.2 Monitoring and Evaluation .......................................................................................................... 13
4.3 Governance .................................................................................................................................. 14
4.4 Sustainability ............................................................................................................................... 14
4.5 Risk Management ........................................................................................................................ 15
4.6 Knowledge Building .................................................................................................................... 15
V- LEGAL FRAMEWORK .......................................................................................................... 16
5.1 Legal Instrument .......................................................................................................................... 16
5.2 Conditions Associated with the Bank’s Involvement .................................................................. 16
5.3 Compliance with Bank Policies ................................................................................................... 16
VI- RECOMMENDATION ............................................................................................................. 16
ANNEX 1 : GUINEA’S COMPARATIVE SOCIO-ECONOMIC
INDICATORS
ANNEX 2: THE BANK’S PORTFOLIO IN GUINEA
ANNEX 3 : MAP OF PROJECT AREA
LIST OF TABLES
Table 1.3-1 : Technical Assistance Provided by Partners in the Public Finance
Management Domain
Table 2.1-1 Project Components and Estimated Cost in UAM
Table 2.4-1 Estimated Project Cost by Component
Table 2.4-2 Estimated Project Cost by Source of Financing
Table 2.4-3 Project Cost by Category of Expenditure
Table 2.4-4 Expenditure Schedule by Component
Table 2.7-1 Distribution of the Bank's Portfolio in Guinea
Table 4.2-1 Monitoring Stages and Feedback Loop
Table 4.5-1 Monitoring Stages and Feedback Loop
ii
Currency Equivalents
April 2013
Currency Unit GNF
UA 1 USD 1.50
UA 1 EUR 1.17
UA 1 GNF 10 590.10
Fiscal Year
1 January - 31 December
Acronyms and Abbreviations
ACGP Major Projects Administration and Control Agency
AfDB African Development Bank
ADF African Development Fund
ALSF African Legal Support Facility
BSD Strategy and Development Office
CPIA Country Policy and Institutional Assessment
CSP Country Strategy Paper
CTRCM Mining Agreements Review Technical Committee
CTSP Programme Monitoring Technical Unit
DNIP National Directorate of Public Investments
DNPIP National Directorate of Public Investment Programming
EITI Extractive Industries Transparency Initiative
EU European Union
FSF Fragile States Facility
GAP Governance Action Plan
GDP Gross Domestic Product
IMF International Monetary Fund
MEF Ministry of the Economy and Finance
MMG Ministry of Mines and Geology
MP Ministry of Planning
PADIPOC Project to Support Capacity Building in Debt, Public Investment and Control
Institutions Management
PAPEGM Economic Planning and Mining Governance Support Project
PARCGEF Economic and Financial Management Capacity Building Support Project
PAREF Economic and Financial Reform Support Programme
PFM Public Finance Management
PIP Public Investment Programme
PIS Public Investment System
PREMA Government Reform and Administrative Modernization Programme
PRS Poverty Reduction Strategy
PRSP Poverty Reduction Strategy Paper
PS-PRS Permanent Secretariat for the Poverty Reduction Strategy
TS Bank’s Ten-Year Strategy 2013-2022
UA Unit of Account
PCIU Project Coordination and Implementation Unit
UNDP United Nations Development Programme
WB World Bank
iii
Project Information Sheet
Client Information Sheet
BORROWER: Republic of Guinea
EXECUTING AGENCY: Project Coordination and Implementation Unit (PCIU)
Ministry of the Economy and Finance
Financing Plan
Source of Financing Amount
(in UA million) Instrument
ADF Grant 11.38 Institutional Support
Government of
Guinea
2.24 National Counterpart
Contribution
Total 13.62
ADF Financing Information
Grant Currency
UA
Interest Rate Type Not Applicable (N.A.)
Base Rate N.A.
Interest Rate Margin N.A.
Financing Margin N.A.
Commitment Charge N.A.
Other (Service) Charges N.A.
Grace Period N.A.
Indicative Time Frame
Activities Date
Appraisal April 2013
Grant Agreement Negotiations June 2013
Board Presentation July 2013
Effectiveness July 2013
First Disbursement October 2013
Project Closure 31 July 2017
Completion Report 4th
quarter 2017
iv
PROJECT SUMMARY
Project Overview
Project Name/Number: Economic Planning and Mining Governance Support
Project (PAPEGM) / P-GN-K00-008
Geographic Scope: National territory
Project Schedule: 48 months
Financing: UA 13.62 million or UA 11.38 million (ADF Grant) and UA 2.24
million (National counterpart contribution)
Operational Instrument: Institutional Support Project
Needs Assessment and
Relevance Governance deficiencies and weak institutional capacity are the major challenges to
the sustained and inclusive growth of the Guinean economy. In fact, despite the
huge soil and subsoil wealth and the adoption of successive poverty reduction
strategies, economic performance remains modest and the prevalence of poverty has
continued to increase, from 53% in 2007 to 55.2% in 2012. In addition,
shortcomings in managing planning tools and the lack of adequate expertise in the
management of mineral resources limit the Government's capacity to implement
public policy. Consequently, it is necessary to continue to support the country to
improve the implementation of its development policies and promote good
governance in the management of the mining sector in order to further leverage
resources to combat poverty more effectively.
Expected Outcomes The main expected outcomes are: (i) improved operation of the institutional
mechanism for monitoring poverty reduction strategy implementation at the
national, sectoral and regional levels to better assess the impact of public
investment projects and programmes; (ii) the establishment of a common platform
based on an integrated public investment programming and monitoring information
system; (iii) an increase in public revenue from the mining sector; and (iv) better
governance in the management of this sector.
Target Beneficiaries The main project beneficiaries are: (i) the State of Guinea owing to an improvement
in its financial resources; (ii) central, regional and sectoral entities responsible for
the implementation of the Poverty Reduction Strategy Priority Action Plan and
public investment projects; (iii) economic operators who could benefit from the
infrastructure put in place by the authorities; and (iv) the Guinean people as a
whole, who could take greater advantage of their country’s subsoil resources.
Comparative Advantages and
Value Added for the Bank
The Bank’s comparative advantages and value added in this operation stem from
the experience it acquired over the years in the design and implementation of
institutional capacity building projects in Member States. In addition, the synergy
between the various projects financed by the Bank to build capacity and reduce
poverty at sector level helps to provide holistic support to lessen the challenges to
the country’s growth and socio-economic development potential. Furthermore, the
Bank’s Guinea Country Office to be established will be an asset in strengthening
dialogue with the country’s authorities and in any assistance it could provide to
ensure successful project implementation within the prescribed timeframe.
Institution Building Because of the significant technical assistance and training component (85% of the
project amount) of PAPEGM, its implementation will help to build the technical
and operational capacity of Guinean senior officers working on the planning-
programming-budgeting-monitoring and evaluation chain throughout the country’s
Economic Administration. It will also provide this administration with modern
working tools (computer hardware and software).
v
Results-Based Logical Framework
Country and Project Name: Guinea - Economic Planning and Mining Governance Support Project (PAPEGM)
Project Goal: Contribute to capacity building in implementation of the poverty reduction, public investment management and mining sector
governance strategy.
RESULTS CHAIN
PERFORMANCE INDICATORS MEANS OF
VERIFICATION
RISKS/
MITIGATION
Indicator
(including ISC) Baseline Target
IMP
AC
T Inclusive growth is
accelerated by improving
economic governance
Average annual GDP growth
rate
3.9% in 2012 5.5% over the
2015-2018
period
MEF and MP data
Poverty survey
Incidence of poverty 55.2% in 2012 48% in 2018
OU
TC
OM
ES
Outcome I: PRS
implementation
monitoring and public
investment management
are strengthened
Social sector’s share in PIP
(% of PIP for women)
8.24% (0.6%) in
2012
12% (5%) in
2016
MEF and MP data
Risks:
(i) Inadequate
resources to
finance the PIP
(ii) Eviction of
mining
companies after
the review
process
Mitigation:
(i) Revenue
mobilization is
strengthened
(ii) Transparent
review process
Annual public investment
implementation rate 60% in 2012 80% in 2016
Outcome II: Mining
sector governance is
improved
Share of revenue derived
from the mining sector 30% in 2012
More than
40% in 2016
MEF and MMG
data
Guinea’s status in the EITI
process
Candidate country Compliant
country in 2014
OU
TP
UT
S
COMPONENT I: IMPROVING ECONOMIC PLANNING AND DEVELOPMENT POLICY IMPLEMENTATION Risk:
Weak capacity for
the implementation
of project activities
Mitigation:
Planned project
training activities
and UCEP’s support
will help to mitigate
this risk in
beneficiary entities
I.1.1 A PRS
implementation
monitoring framework is
operational
I.1.1.1 Operationality of the
PRS implementation
monitoring framework
Weak PRS
implementation
monitoring
framework
Operational
overall (central,
sectoral and
regional)
monitoring
framework
(2016)
PS-PRS reports
I.1.1.2 Operationality of
regional PRS monitoring
units
Only 1 operational
regional monitoring
unit
8 operational
regional
monitoring
units (2016)
PS-PRS reports
I.1.2 Staff in charge of
monitoring PRS
implementation are
trained and provided with
work tools
I.1.2 Number of staff trained
(% of women trained)
15 staffs trained 500 to 600 staff
are trained and
provided with
work tools
(2016) at least
25% of them
women
PS-PRS reports
I.1.3 PRSP III is
disseminated through the
Donor Conference
I.1.3 Organization of the
Donor Conference to
disseminate PRSP III
PRSP III is finalized
but not disseminated
Donor
Conference
organized
(2014)
MEF reports
I.2.1 The public
investment system (PIS) is
modernized
I.2.1.1 Operationality of PIS Absence of a PIS The PIS is
operational
before end-
2015
DNIP and DNPIP
reports
vi
I.2.1.2 Preparation of a
public investment monitoring
manual and standard project
sheets
No manual and
standard project
sheets
Monitoring
manual and
standard project
sheets are
prepared (2015)
DNIP and DNPIP
reports
I.2.2 The portfolio of
public investment projects
with feasibility studies is
available
I.2.2 Percentage of projects
with feasibility studies in the
PIP in year n
Low percentage of
feasibility studies
100% of
projects with
their feasibility
studies in the
year’s PIP in
2017
idem
COMPONENT II: IMPROVING MINING SECTOR GOVERNANCE AND TRANSPARENCY
II.1.1 The review of
mining agreements is
finalized
II.1.1 Percentage of mining
agreements reviewed
No mining
agreement is
reviewed
100% of
mining
agreements
reviewed
before end-
2016
CTRCM reports
II.2.1 Annual audits of
financial flows for the
EITI process are carried
out
II.2.1 Annual financial audits
are carried out
2011 reports et seq.
are not prepared
The 2011 and
2012 annual
audit reports
are finalized
before end-
2014
EITI-Guinea
reports
KE
Y A
CT
IVIT
IES
COMPONENTS RESOURCES
Component I: IMPROVING PUBLIC INVESTMENT MANAGEMENT AND THE
MOBILIZATION OF EXTERNAL FINANCING
- Technical assistance activities: provision of national and international experts and consulting
firms
- Human capacity building activities: training
- Material capacity building activities: computer hardware and office automation
Component II: IMPROVING MINING SECTOR GOVERNANCE
- Technical assistance activities
Resources:
Component A: UA 5.0 million
Component B: UA 7.164 million
Project management: UA 0.815 million
Contingencies and inflation: UA 0.648
million
Total: UA 13.627 million (UA 11.387
million from the ADF and UA 2.24
million from the Government)
vii
Provisional Project Implementation Schedule
2013 2014 2015 2016 2017
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
0. Preparatory activities
0.1 Project appraisal
0.2 Board presentation
0.3 Grant effectiveness
0.4 Selection of project management
team
0.5 Project launching mission
0.6 Preparation of procedures manual
1. Procurement of equipment and
supplies
1.1 IT hardware and software and
office automation
2. Technical assistance services
2.1 Preparation of BDs and drawing
up of shortlists
2.2 Launching of CB, bid evaluation
and contract award
2.3 Consulting services
3. Training
3.1 Preparation of BDs and drawing
up of shortlists
3.2 Launching of CB, bid evaluation
and contract award
3.3 Consultancy services
4. Operating expenses
5. Monitoring and evaluation
6. Steering committee meetings
7. Project supervision and mid-term
review
8. Closure of activities
9. Annual financial audits
1
REPORT AND RECOMMENDATION OF MANAGEMENT CONCERNING
AN ECONOMIC PLANNING AND MINING GOVERNANCE SUPPORT PROJECT
(PAPEGM) IN THE REPUBLIC OF GUINEA
This proposal submitted for Board approval concerns the award of a grant of UA 11.38
million from the Resources of the African Development Fund to the Republic of Guinea
for the financing of the Economic Planning and Mining Governance Support Project
(PAPEGM). This is an institutional support project that seeks to build capacity for the
implementation of the poverty reduction, public investment management and mining sector
governance improvement strategy. The specific objectives are to: (i) improve the
implementation of development policies and projects, and (ii) improve mining sector
governance and transparency. The expected project outcomes are: (i) improvement of the
institutional poverty reduction strategy implementation framework which was established at
the national, sectoral and regional levels to better assess the impact of projects and
programmes implemented; (ii) modernization of public investment programming tools by
establishing a common platform based on an integrated information system containing
specific modules for each stakeholder in the chain; (iii) increase in public revenue derived
from the mining sector; and (iv) transparency in the management of this sector.
I. STRATEGIC THRUST AND RATIONALE
1.1 Project Linkages with Country Strategy and Objectives
Government’s Medium-term Development Strategy
1.1.1 The Government’s medium-term economic guidelines have been defined in the
2011-2015 Five-Year Plan. Long-term guidelines will be defined in the “Guinea 2035”
Vision1 which is being finalized. The Five-Year Plan, which is the first sequence of the
implementation of the Vision, seeks to ensure sustainable growth that protects the
environment and benefits all social categories. It includes all Government actions and
provides guidance to private sector operators to supplement Government operations so as to
accelerate the country’s economic and social development. The four priority thrusts of the
third-generation Poverty Reduction Strategy Paper 2013-2015 (PRSP III)2 derive from the
general guidelines of the Plan which outlines the Government’s medium-term development
vision.
1.1.2 PRSP III, which is a specific instrument for alleviating poverty and achieving
MDGs, is the reference framework for the operations of technical and financial
partners. This strategy was designed with the Bank’s contribution through the Targeted
Support Project financed by the Fragile States Facility (FSF). It focuses on four strategic
thrusts, namely: (i) Governance and Capacity Building; (ii) Acceleration, Diversification and
Sustainability of Growth; (iii) Infrastructure Development; and (iv) Improvement of Access
to Basic Social Services. Furthermore, the authorities have, with the support of the FSF,
prepared a Government Reform and Administrative Modernization Programme (PREMA)
which seeks to: (i) redefine State duties; (iii) streamline public administration; (iii) strengthen
the coordination and efficiency of government work; and (iv) consolidate the decentralization
process.
1 The Vision is financed by the Bank using Fragile States Facility resources. 2 See Technical Annex A1.
2
1.1.3 The Bank’s intervention strategy in Guinea for the 2012-2016 period builds on
two pillars: (i) economic and financial governance3 and (ii) development support
infrastructure. The proposed Economic Planning and Mining Governance Support Project is
aligned with the first thrust of the PRSP and the first pillar of the Country Strategy Paper
(CSP). It is also consistent with the Bank’s 2013-2022 Strategy whose fourth operational
priority is governance and accountability in Member States.
1.1.4 The diagnosis of the Guinean public investment system in 2012 by the Bank and
the UNDP revealed major flaws4. To remedy the weaknesses identified, PAPEGM seeks to
improve implementation of the development and poverty reduction policy by strengthening
the planning-programming-budgeting–implementation-monitoring and evaluation chain of
development policies and projects. Lastly, the project supports the Government’s objective
of initiating a far-reaching structural reform programme in the mining sector to strengthen its
governance and significantly improve its contribution to public finance and the country’s
economic and social development. Since its launch, this reform programme has been
supported by the Economic and Financial Reform Support Programme (PAREF) financed by
a Bank budget support in 2011, especially through the adoption of a new mining code.
1.2 Rationale for Bank’s Involvement
1.2.1 Economic and Social Context: despite the huge soil (fertility and abundant rainfall)
and subsoil (two-thirds of the world’s bauxite reserves, large iron, diamond and gold
deposits, etc.) potential, Guinea remains one of the poorest countries in the world and is
ranked 178th
out of 186 countries in the 2012 Human Development Index (Technical Annex
A3). Aware of this paradox, in 2000 the Guinean authorities embarked on a process of
designing poverty reduction strategies, the third generation of which covers the 2013-2015
period, with Bank support. The implementation of these strategies has contributed to
improving the economic growth rate (from 1.9% in 2010 to 3.9% in 2012), moderating
inflation (12% in 2012 down from 20.48% in 2010 year on year) and reducing debt through
the Heavily Indebted Poor Countries (HIPC) Initiative. However, the incidence of poverty
rose from 53% in 2007 to 55.2% in 2012. Youth unemployment remains a concern and
joblessness now affects nearly 70% of those below 25 years of age. To address this situation,
it is therefore necessary to continue to support the country to effectively implement its
poverty reduction strategy and development policies as well as their dissemination to donors
and investors in order to mobilize the financial resources needed to implement the PRSP III
Priority Action Plan. The conduct of the last presidential election in a peaceful and
transparent manner as well as the formation of a new government is another reason for the
Bank to continue to support Guinea.
1.2.2 Development Planning and Public Investments Programming: soon after
achieving independence in 1958, Guinea, like most African countries, opted for economic
planning as a tool for the orientation and choice of the country’s economic and social
development model. This tool, which was abandoned in the 1980s in favour of a three-year
rolling programming followed by PRSPs, was revived in 2011. Accordingly, a 2011-2015
Five-year Socio-economic Development Plan, whose strategic thrusts underline the need to
ensure sustainable growth that protects the environment and benefits all social categories,
was released. The four priority thrusts of the third-generation PRSP 2013-2015 (see § 1.1.1
above) follow from the general guidelines of the Plan which outlines the Government’s
medium-term development vision. Against this backdrop, the Bank intends to support the
3 Pillar 1 of the CSP 2012-2016 seeks to achieve seven objectives (See Guinea CSP). PAGE contributes to achieving objectives (iv), (v),
(vi) and (vii). 4 See Technical Annex A2.
3
implementation of this new strategy underpinned by a Priority Action Plan (PAP) broken
down into Rolling Three-year Public Investment Programmes.
1.2.3 The analysis of the Guinean public investment system in 2012 by the Bank and
the UNDP revealed many weaknesses. At the institutional level: (i) the absence of a
comprehensive mechanism for the implementation, monitoring and evaluation of the 2011-
2015 Five-year Plan; (ii) the multitude of stakeholders in the area of project and programme
programming and monitoring, apart from project and programme implementation units; (iii)
the assignment of programming to two different ministries resulting in overlaps and
jurisdictional conflicts; and (iv) the non-operability of many Strategy and Development
Offices (BSDs) which are supposed to channel information from sectoral ministries to central
programming bodies operating in the Ministry of the Economy and Finance. Concerning
procedure: (i) indicative budgets are allocated to sectoral ministries on a non-transparent
basis which does not always reflect the Government’s development priorities; (ii) the absence
of a set of criteria for selecting projects and programmes under the Public Investment
Programme (PIP); and (iii) lack of standardized project documents at the various stages of the
project cycle.
1.2.4 It follows from the foregoing that the present organization of the public
investment programming system remains weak, resulting in resource wastage due to the
duplication of activities and conflicts between ministries whose activities are supposed to be
complementary (Finance and Planning). There is also weak capacity to prepare and process
project documents to ensure project viability. To remedy this situation, the Minister of State
in Charge of the Economy and Finance and the Minister of Planning, on the instructions of
the Head of State, in March 2013 co-signed a “Role Clarification Note” defining the role of
their respective ministerial departments regarding public investment management5. This
marks an important step in harmonizing the activities of both ministries prior to the
establishment of a common platform based on an integrated information system with specific
modules for each stakeholder in the chain selected by PAPEGM within the framework of its
activities.
1.2.5 Governance in the mining sector: bauxite is Guinea’s leading subsoil mineral
resource whose reserves are estimated at 40 billion tons, that is, about two-thirds of the
world’s reserves. Other minerals include gold (5 to 10 000 tons), diamond (20 million carats),
nickel (75 million tons) and iron (5 billion tons) which are exploited by foreign private
companies or semi-public corporations in which the State holds 15% to 49% of the share
capital under agreements concluded with the Guinean Government. On average, the annual
revenue derived from the exploitation of these resources accounted for 21.9% of overall State
revenue over the last 10 years compared to 40% during the 1980s and early 1990s. This drop
in State revenue is attributable to tax relief in the mining sector following the adoption of the
1995 Mining Code which sought to attract foreign private investors, but also and above all to
poor governance in the management of the sector. In fact, the level of taxation and regulation
is determined on a case-by-case basis because the Code is used only as a reference. All the
agreements that were negotiated in the 2000s were implemented on an ad hoc basis. The
consequence of these practices is that the tax conditions have never been the same for all
mining companies. Changes in contracts are sometimes negotiated under non-transparent
conditions.
1.2.6 To better safeguard its interests in the exploitation of mineral resources, which
remain the exclusive property of the Guinean State, the Government initiated major
reforms in 2011 to improve governance in the mining sector. Thus: (i) the National
Transitional Council adopted a new Mining Code on 9 September 2011 to replace the 1995
5 A study financed by the European Union is underway to identify the roles of various stakeholders in the planning mechanism.
4
Code; (ii) a National Mining Commission was established in 2012 to assess and negotiate
new projects; (iii) a Technical Committee for the Review of Mining Titles and Agreements
was established in April 2012 to review existing agreements in order to ensure that they
comply with the provisions of the legal framework in force; (iv) a Guinean Mining Heritage
Company (SOGUIPAMI) was set up; (v) a new mining register which is rid of the illegal
mining permits that were granted in the past was opened in 2012; and (vi) a Mining Zone
Safety Committee as well as a Mining Consultation and Community Management Committee
were established.
1.2.7 To enhance the reforms initiated in the mining sector, the Guinean Government
mandated the Bank and the African Legal Support Facility (ALSF) to support its
efforts to improve governance in the sector, particularly the review of existing mining
agreements. Under the terms of this mandate, the support expected from the two institutions
will focus on: (i) building the capacity of the mining administration, and (ii) support in the
review of mining agreements by placing local law firms and legal experts at the disposal of
Guinean authorities. The 18 mining agreements of which the State is a signatory will be
reviewed according to the provisional schedule that would have been established in two
phases, namely the titles and agreements legal review phase and the negotiation phase proper.
PAPEGM is a response to this request made by the Government to help it enshrine good
governance in the strategic mining sector whose financial benefits should help to increase the
State’s capability to reduce poverty and create jobs for youths (see Technical Annex A7).
Box 1 - Support for the Transformation of the Guinean Economy: Efficient Allocation of
Revenue from the Mining Sector in Public Investment for Development The Bank has adopted a holistic approach in Guinea to address challenges to the country’s growth potential
through the effective use of its resources for economic transformation and social development. In fact, a series
of institutional support projects and reform support programmes financed by the Bank help to identify key
phases in the economic chain ranging from mining revenue mobilization, investment programming, priority-
based budgeting, budget execution and project monitoring to control and accountability regarding the use of
public resources. To that end, the Institutional Support Project (PARCGEF) provided support for the
development of legal, regulatory and institutional frameworks for the extractive sector so as to leverage the
financial resources derived from this sector and ensure revenue transparency (EITI). PARCGEF also supported
efforts to build the capacity of the taxation administration to help the Government in improving revenue control
and mobilization procedures. Downstream, the project supported efforts to build budget execution capacity,
particularly financial control and internal auditing. To consolidate the Bank’s support to this chain, PAPEGM
will provide support to improve resource allocation efficiency, particularly public investment programming.
Thus, the implementation of public investment projects in the infrastructure and other priority domains is an
intergenerational form of savings which ensures that the resources generated today by the mining sector will
yield dividends in future.
1.3 Aid Coordination
1.3.1 Donor operations fall within the framework of the implementation of the
Economic Reforms and Capacity Building Priority Actions Plan. A thematic group set up
for this component meets regularly to coordinate stakeholders in the domain. The Bank
participates regularly in these deliberations. Partners’ focus areas are distributed jointly
(Technical Annex A4). In the mining sector, the World Bank contributes in a complementary
manner to actions to build the capacity of all stakeholders at the central level as well as in
mining pools (Mining Project, USD 20 million). The IMF, which also encourages the review
of mining agreements, provides technical assistance to model their financial impacts and
estimate the potential additional revenue that the country may derive through this review
process.
1.3.2 The weak technical capacity of the country’s human resources limits its
capacity to play a leading role in coordinating the operations of its technical and
financial partners. However, the activities of this project, adopted by mutual agreement with
5
the authorities, were the subject of consultation with donors aimed at ensuring synergy and
complementarity of operations.
Table 1.3-1
Areas of Donor Intervention in Economic Governance FOCUS AREAS AND THEMES IN THE MATRIX OF ACTIONS TFP IN CHARGE PRSP III UNDP/ADB
MACRO-ECONOMY IMF
IMPLEMENTATION OF PRSP III AND PUBLIC INVESTMENTS AfDB/UNDP
BUDGET SUPPORT MANAGEMENT AfDB/WB
PUBLIC FINANCE MANAGEMENT Focus area 1 Strengthening of the Steering, Coordination and Monitoring of
Economic and Financial Reforms Focus area 2 Renovation of the Legal and Regulatory Framework for Public Finance
Management Focus area 3 Improvement of the Budget Programming and Preparation Process
Focus area 4
Improvement of Domestic Resource Management and Mobilization
Focus area 5
Strengthening of Public Expenditure Management
Focus area 6
Strengthening of Treasury Management
Focus area 7
Improvement of Transparency and Financial Governance Focus area 8
Institutional, Organizational and Human Capacity Building
EU
IMF
AfDB
AfDB/France
WB/EU/IMF
IMF
IMF
AfDB/WB/EU
1.3.3 The mining/extractive sector thematic group - Guinea participates very actively
in dialogue with the authorities on reforms in this sector. The group in which the Bank
participates regularly through missions or videoconferencing is chaired by the World Bank
since 2013. Donor intervention in this area is summarized in the table below.
Table 1.3-2
Areas of Donor Intervention in the Extractive Sector
FOCUS AREAS TFP IN CHARGE
Legal framework (Mining Code, Petroleum Code, implementing instruments) AFD/AfDB
Capacity building of stakeholders (training, equipment) WB/AfDB
Establishment of entities in charge of the sector (Guinean Mining Heritage
Company)
WB
Mining taxation and financial modelling IMF
Review of mining agreements AfDB/ALSF
EITI process AfDB/WB
II. PROJECT DESCRIPTION
2.1 Project Objectives and Components
2.1.1 The overall objective of the project is to contribute to building capacity for the
implementation of the poverty reduction, public investment management and mining
sector governance strategy. The specific objectives are to: (i) improve the implementation
of development policies and projects, and (ii) improve governance and transparency in the
mining sector.6
2.1.2 PAPEGM comprises two main components, namely: (i) Improvement of the
Implementation of Development Policies; and (ii) Improvement of Mining Sector
Governance and Transparency. The first component will seek to support the implementation
of PRSP III and to modernize the public investment programming and management system
(see § 1.2.2.). The second component seeks to support the review of mining agreements and
6 The analysis of the main constraints on and challenges faced in the implementation of development policies in the mining sector is
presented in Technical Annex C1.
6
improve transparency in the management of the mining sector to enable it to generate more
financial resources for the country (see § 1.2.5.)7. There is also provision for a third
component on project management.
2.1.3 The two project components are related: the resources generated by the mining
sector (second component) will be invested efficiently for development purposes through a
modern public investment programming and management system (first component). Table
2.1-1 below provides details on the project components, sub-components and cost. Technical
Annex B2 of this report provides the detailed costs of the activities of components as well as
a comprehensive list of goods and services to be procured under the project. In addition,
Technical Annex C1 d provides a detailed rationale for, and description of, project activities.
Table 2.1-1
Project Components and Estimated Cost in UA million
Component Name Estimated Cost Sub-component Description
Component 1.
Improvement of the
Implementation of
Development Policies
4.999 1.1 Poverty Reduction Strategy Implementation Support
Technical Assistance:
- Technical assistance for monitoring the implementation of the Poverty
Reduction Strategy at the Permanent Secretariat (three national
consultants)
- International technical assistance for coordinating the institutional system
for monitoring and evaluating the implementation of the PRS
- Technical assistance to regional PRS monitoring units (eight national
consultants)
Training: building the capacity of stakeholders in monitoring PRS implementation:
training on monitoring tools (PAP, indicator matrix) and on project management at
central and regional levels
Equipment: computer hardware/office furniture for the PS/PRS and regional units
Operation: reproduction of tools for PRS implementation monitoring and support
for the organization of monitoring missions/meetings
1.2 Modernization of Public Investment Programming and Management System
Technical Assistance:
- Technical assistance for strengthening public investment system tools:
establishment of an information system, preparation of procedures
manuals, conduct of a feasibility study on the establishment of a
documentation centre (UNDP)
- Technical assistance to cross-cutting entities for the development and
monitoring of the PIP: DNPIP/DNIP/ACGP (individual international
consultants)
- Technical assistance to ministerial departments (BSDs) for the preparation
of project information briefs to strengthen the projects portfolio
(Consulting firms with quality control by UNDP)
- Technical assistance for the organization of the donor conference to
disseminate the PRSP (event organization and communication firm)
- Conduct of strategic sectoral studies
Training: building stakeholders’ capacity in the public investment system: cross-
cutting (DNIP, DNPIP and ACGP) and sectoral (BSD, priority sectors) entities
Equipment: computer hardware / office furniture for cross-cutting and sectoral
entities
Operation: support for the organization of monitoring missions/meetings in cross-
cutting entities as well as for the organization of the Donor Conference
Component 2.
Improvement of Mining
Sector Governance and
Transparency
7.164
2.1 Support for the Review of Mining Agreements
Technical Assistance:
- Technical and legal assistance for the review of mining agreements
- Appointment of two legal experts to support the mining sector reform (at
MMG and the Presidency)
2.2 Support for the Improvement of Transparency in the Management of the
Mining Sector
Technical Assistance:
- Technical assistance to the EITI-Guinea Secretariat
- Preparation of financial flow reconciliation reports
Project Management 0.81 Project management
7 A note describing governance in Guinea's mining sector is presented in Technical Annex A2.1.
7
2.2 Technical Solutions Adopted and Alternatives Explored
During project preparation, several options, particularly institutional
arrangements, were considered. The scope of capacity building was such that it was
necessary to resort to trade-offs given the budgetary constraints imposed by financing
allocation (ADF Grant and Government’s contribution). Furthermore, the issue was raised as
to whether or not to opt for a Project Manager to manage some aspects of the project so as to
take into account the country’s fragility and weak institutional capacity in the implementation
of project activities.
Table 2.2 -1
Alternatives and Reasons for their Rejection
Elements Examined Brief Description Reasons for Rejection
Institutional
arrangements
Given the nature of the
first project component
which concerns
development policy and
public investment
programming issues, it
seemed logical to attach
the project to the Ministry
of Planning
This option was not chosen for two reasons: (i) unlike in other
countries, the PRSP and its Secretariat fall under the Ministry of the
Economy and Finance, (ii) the Project Implementation and
Coordination Unit (PCIU), which is already implementing a Bank
project (PARCGEF) as well as the World Bank's Capacity Building
Project, is attached to the Ministry of the Economy and Finance. To
reduce transaction costs, it was advisable for the same entity to
implement PAPEGM.
All aspects of the
project are managed
by the implementation
unit selected (PCIU)
According to institutional
implementing
arrangements, the project
also had to manage the
implementation of the
key IT component which
is one of its planned
activities
This solution was rejected because of the complexity of the IT
component and the modern programming system it plans to set up for
the various stakeholders, namely DNPIP, DNIP, ACGP and BSDs in
sectoral ministries and the regional directorates of the Ministry of
Planning. The delegated project management option was chosen for
this project component for the benefit of the UNDP. This option is
also justified by rapid implementation, flexibility and the partner’s
experience in the domain. Thus, the project will partly rely on
procurement methods that, to some extent, give priority to
specialized institutional partners (UNDP) through direct negotiations,
in accordance with the Bank’s rules of procedure. This will also have
the advantage of improving the implementation of activities in the
country’s fragility context.
The multiplicity of
agencies involved in
the planning and
management of
investment projects
and the scale of needs
expressed
The processing of needs
expressed should, in
principle, be based on the
terms of reference of each
stakeholder in the
planning-programming-
budgeting-monitoring and
evaluation chain
Given the overlap between the functions identified in the terms of
reference of various stakeholders, namely DNPIP, DNIP, ACGP and
BSDs, the decision was taken not to finance the activities of these
agencies that are mutually compatible. Accordingly, project study
and preparation activities will be financed in BSDs rather than ACGP
which should focus on the physical and financial monitoring of major
investment projects.
2.3 Project Type
This is an institutional support project financed by an ADF Grant which seeks to
improve the implementation of development policies and projects and to promote governance
in the mining sector.
2.4 Project Cost and Financing Arrangements
2.4.1 The overall project cost, net of taxes, is estimated at UA 13.628 million, of
which UA 11.061 million in foreign exchange and UA 2.567 million in local currency. This cost includes a 2% provision for physical contingencies and a 3% provision for price
escalation for expenditure in foreign exchange and in local currency. As shown in Table 2.4-
2, 80% of the project base cost, excluding provision for contingencies and price escalation, is
financed with ADF resources and 16% with national counterpart contributions. The detailed
8
cost table is presented in Technical Annex B2 of this report. The summary table below
presents the overall project cost by component.
Table 2.4-1
Estimated Project Cost by Component
Components Cost in USD Thousand Cost in UA Thousand
In % FE LC Total FE LC Total
COMPONENT 1:
STRENGTHENING
IMPLEMENTATION OF THE
COUNTRY’S DEVELOPMENT
POLICIES
5971.42 1523.33 7494.75 3983.07 1016.09 4999.16 37%
COMPONENT 2: IMPROVEMENT OF MINING
SECTOR GOVERNANCE 9630.90 1110.10 10741.00 6424.03 740.46 7164.49 52%
COMPONENT 3: PROJECT
MANAGEMENT AND
COORDINATION (PCIU) 190.30 1032.41 1222.71 126.93 688.64 815.57 6%
Total Base Cost 15 792.62 3 665.84 19 458.46 10 534.03 2 445.20 12 979.23 95%
Provision for Physical
Contingencies 2% 315.85 73.32 389.17 210.68 48.90 259.58 2%
Provision for Price Escalation 3% 473.78 109.98 583.75 316.02 73.36 389.38 3%
Total Project Cost 16 582.25 3 849.13 20 431.38 11 060.73 2 567.46 13 628.19 100%
Note: The exchange rate used is indicated in the introduction to the report (page (iii))
Table 2.4-2
Estimated Project Cost by Source of Financing in UA Thousand Source of Financing Cost in FE Cost in LC Total Cost in UA In %
ADF 10 534.03 310.74 10 844.77 80%
Government 0.00 2 134.45 2 134.45 15%
Project Base Cost 10 534.03 2 445.19 12 979.22 95%
Contingencies and inflation 526.70 122.26 648.96 5%
Total 11 060.73 2 567.45 13 628.18 100%
2.4.2 Tables 2.4-3 and 2.4-4 present the estimated project cost by expenditure category
and the implementation schedule. The detailed cost is presented in Technical Annex B1.
Table 2.4-3
Project Cost by Expenditure Category in UA Thousand Expenditure Category Cost in FE Cost in LC Total Cost % in FE
A. Goods 584.44 230.36 814.80 6%
B. Services 9 949.59 1 105.51 11 055.10 85%
C. Operation 0.00 1 109.32 1 109.32 9%
Total Base Cost 10 534.03 2 445.20 12 979.23 95%
Provision for Contingencies 526.70 122.26 648.96 5%
Total Project Cost 11 060.73 2 567.46 13 628.19 100%
Table 2.4-4
Expenditure Schedule by Component in UA Thousand
Components 2013 -2014 2015 2016 2017 Total
COMPONENT 1: STRENGTHENING
IMPLEMENTATION OF THE COUNTRY’S
DEVELOPMENT POLICIES
799.06 1 680.04 1 470.04 1 050.03 4 999.16
COMPONENT 2: IMPROVEMENT OF MINING
SECTOR GOVERNANCE 7 003.74 64.30 56.26 40.19 7 164.49
COMPONENT 3: PROJECT MANAGEMENT
AND COORDINATION (PCIU) 15.75 266.61 266.61 266.61 815.57
Project Base Cost 7 818.54 2 010.95 1 792.91 1 356.82 12 979.23
Contingencies and Inflation 390.93 100.55 89.65 67.84 648.96
Total 8 209.47 2 111.50 1 882.56 1 424.66 13 628.19
In % of Total Project Cost 60% 15% 14% 10% 100%
9
2.5 Project Target Area and Beneficiaries
The project target area is the national territory of Guinea. The main project
beneficiary is the State of Guinea because its financial resources will be increased through a
rise in mining royalties and greater transparency in the management of the sector. The
technical and operational capacity of central, regional and sectoral entities responsible for the
implementation of the PRS Priority Action Plan and public investment programmes will be
strengthened through the implementation of a comprehensive training programme comprising
five modules including the project cycle, programming techniques, and monitoring and
evaluation of development projects. Economic operators could also benefit from the
infrastructure put in place by the authorities through public investment projects. Lastly, the
entire Guinean population would take maximum advantage of their country’s subsoil
resources.
2.6 Participatory Approach for Project Identification, Design and Implementation
The Bank’s Team adopted a participatory approach during project
preparation and appraisal by closely involving the Guinean Government’s technical
services in its activities. It especially consulted professional organizations of the mining
sector whose voluntary and active participation in the review of previous agreements
concluded with the State is crucial to the success of the reforms initiated by the Government
in the sector. It also sampled the opinions of various technical and financial partners
operating in domains related to those covered by PAPEGM (World Bank, European Union,
IMF, etc.) in order to ensure synergy between the operations of the country’s technical and
financial partners.
2.7 Bank Group Experience and Lessons Reflected in Project Design
2.7.1 The Bank’s active portfolio in Guinea as at 31 May 2013 comprised 10 on-going
operations for a total amount of UA 71.064 million, with an overall satisfactory performance
of 2.61 on 3. The detailed situation of the portfolio is presented in Annex 2. In the areas of
governance and economic and financial reforms in particular, recent Bank operations in
Guinea comprise two institutional support projects and a policy-based programme8.
2.7.2 Major achievements of past operations include the institutional support of
PADIPOC (closed in 2012, completion report - ADF/BD/IF/2012/126), the establishment of
bases for public investment programming and the creation of synergy between control bodies
in Guinea (Technical Annex A5). The on-going second institutional support, PARCGEF,
seeks to improve budget management and strengthen tax revenue mobilization. For its part,
the Economic and Financial Reforms Support Programme (PAREF), which was closed in
2012, helped to strengthen internal control systems and government procurement. It also
helped to support the implementation of major reforms related to governance in the mining
sector such as the adoption of the new Mining Code. It should also be noted that the targeted
support financed by the FSF in 2011 contributed to the design of PREMA whose
implementation will contribute to modernizing public administration as a whole. It also
contributed to the conduct of the poverty survey which served as one of the completion point
triggers and helped to implement PRSP III. Furthermore, the project contributed to finalizing
the 2012-2014 Public Investment Programme. PAPEGM will strengthen and support the
8 The Project to Support Capacity Building in Debt, Public Investment and Control Institutions Management - PADIPOC (completed in
2012); The Economic and Financial Reforms Support Programme - PAREF (completed in 2012); The Economic and Financial
Management Capacity Building Support Project - PARCGEF (approved in 2011); The Targeted Support Project co-financed with UNDP (approved in 2011).
10
achievements of the Targeted Support Project, particularly the implementation of the PRS
and public investment programming.
2.7.3 The design of PAPEGM took into account lessons learned from the
implementation of these projects. The PADIPOC completion report underscored the need
to enhance the selectivity of new operations. Thus, the Bank’s intervention, through
PAPEGM, focuses on two domains: monitoring of the implementation of development policy
and mining sector governance. This will also help to strengthen complementarity with
PARCGEF which is being implemented. Furthermore, to avoid difficulties related to non-
compliance with the Bank’s Rules of Procedure for the Procurement of Goods and Services
noted during the implementation of PADIPOC, the Project Coordination and Implementation
Unit (PCIU) will be the executing agency of PAPEGM. PCIU staff were trained in the
Bank’s rules and procedures and acquired practical experience with the implementation of
PARCGEF. In addition, the Bank’s Field Office in Guinea, whose establishment is planned,
will allow for better monitoring of implementation of its projects in the country. Staff will be
trained with expertise available in the Bank’s Office in Dakar.
2.8 Key Performance Indicators
2.8.1 The key performance indicators identified for assessing expected outcomes on
completion of this project are presented in the results-based logical framework. These
are mainly:
Box 2: Key Performance Indicators
Output indicators
o The overall PRS operational monitoring framework is available by 2016
o 500 to 600 officials of services in charge of investment programming are trained by 2016
o A computerized investment programming system is available before end-2015
o 100% of mining agreements are reviewed before end-2016
o The 2011 and 2012 annual audit reports for the EITI process are finalized before end-2014
Outcome indicators
o The share of the social sector in the PIP increases from 8.24%, of which 0.6% devoted to
women in 2012, to 12% of which 5% devoted to women in 2016
o The annual public investment execution rate increases from 60% in 2012 to 80% in 2016
o The share of budgetary revenue derived from the mining sector rises from 30% in 2012 to
more than 40% in 2016
o Guinea acquires compliant-country status in the EITI process in 2014
Impact indicators o The country’s economic growth rate rises from 3.9% in 2012 to 5.5% on average in
2015-2018 o The incidence of poverty drops from 55.2% in 2012 to 48% in 2018
2.8.2 PCIU, which is the Project Implementation Unit, will be responsible for
collecting and analysing data needed for the verification of these indicators. The project
will recruit and train a monitoring and evaluation expert to this end. He will, in collaboration
with the beneficiary entities, develop performance indicators that will be validated by the
Monitoring Committee and submitted to the Bank for approval. The indicators will be
regularly monitored and analysed in the project’s half-yearly and annual progress reports.
11
III. PROJECT FEASIBILITY
3.1 Economic and Financial Performance
This project will not generate direct revenue, which would allow for the
determination of its financial return. However, its performance can be evaluated on the
basis of its direct and indirect economic and social outcomes in the medium and long terms.
Regarding expected economic and financial benefits, the project will enable the State to
improve tax revenue mobilization, particularly mining tax revenue, and ensure more efficient
public resource management. The project will also enhance transparency in the management
of the mining sector and foster its progressive integration into the national economy.
3.2 Environmental, Social and Gender Impact
Environmental Issues
3.2.1 This project will have no direct negative impact on the environment since its
activities are limited to training, technical assistance, studies and logistics, including office
supplies and IT equipment. However, considering the country’s abundant natural resources,
particularly mineral resources, their exploitation for development purposes may cause soil
degradation and destruction of the ecosystem. The Guinean Government will have the
opportunity to take these considerations into account during the review of mining agreements
explicitly provided for under PAPEGM. In Guinea, a number of statutory instruments govern
the management of environmental impacts. These include Ordinance No. 045/PRG/SGG/87,
amended by Ordinance No. 022/PRG/89 of 10 March 1987, Decree No. 199/PRG/89 of 18
November 1989 governing the conduct of environmental impact assessments and, more
recently, Order No. 990 of 15 March 1990 to regulate the contents, methodology and
procedure of environmental impact assessments. Furthermore, the country has ratified most
international agreements relating to environmental management. Although new mining
projects necessitating the conduct of environmental impact assessments comply with, and
refer to, these instruments, there is no environmental impact assessment plan in old mining
companies.
Social Issues
3.2.2 Socially, it should be noted that the living conditions of the Guinean population
have deteriorated, as illustrated in recent years by the increase in the incidence of
poverty at the national level, from 53% in 2007 to 55.2% in 2012, with its corollary of the
joblessness of youths 61% of whom are university graduates. These unemployed graduates
now constitute a major concern for the authorities. The overall response to this situation
consists in the diligent implementation of PAPEGM components. In fact, a quantified Priority
Action Plan whose implementation should help to reduce poverty and promote employment-
generating activities for youths is appended to the PRSP. In addition, PAPEGM will finance
the organization of a donor conference to mobilize external resources to implement the
Government’s investment programme. Lastly, the review of mining agreements, which is
financed by PAPEGM, will increase the State’s domestic budgetary resources so as to more
effectively combat poverty.
12
Gender Issues
3.2.3 Gender inequalities in Guinea worsened with the Gender Inequality Index
(GII) increasing from 0.228 in 2009 to 0.439 in 2012. Although progress has been made in
primary education with a girl/boy ratio of 0.84 in 2011, the socio-economic situation of
women in Guinea remains insecure. They are under-represented in the civil service and in
political life, although the National Transitional Council which serves as Parliament is
chaired by a woman. Only 26% of civil servants are women with limited responsibilities. To
address this situation, the Government adopted its national “gender” policy in January 2011
by which it seeks to eradicate gender disparities through a systemic approach involving all
sectors and all key economic and social development players of the country. The
implementation of PAPEGM will help to improve the monitoring of implementation of PRSP
III which targets women and children through specific priority actions. Also, the project’s
support for the consolidation of public investment management will contribute to building
economic infrastructure to improve the quality of life of the entire Guinean population,
particularly women. Within the framework of PAPEGM, women who are employees of
beneficiary entities such as DNPIP, DNIP, BSDs and ACGP will benefit from training
provided according to the programme prepared under the project. While preparing the
training programme, the Executing Agency will, in conjunction with the entity concerned,
ensure that the proportion of women among nominees ranges between 25% and 30% so as to
promote gender equality in beneficiary entities.
Forced Resettlement
3.2.4 The project will not entail population displacement.
IV. PROJECT IMPLEMENTATION
4.1 Implementation Arrangements
4.1.1 Institutional Implementation Arrangements: the Project Steering Committee will
be chaired by the Secretary-General of the Ministry of the Economy and Finance, coordinated
by the Technical Programme Monitoring Unit (CTSP) and comprising directors of the project
beneficiary structures. It will provide guidance and approve budgets, quarterly project
implementation status reports and annual financial statements before their submission to the
Bank. The Project Coordination and Implementation Unit (PCIU) established by Order No.
A/2011/2978/MEF/CAB/SGG of 9 January 2011 to manage all institutional support and
capacity building projects in Guinea will ensure the day-to-day implementation of activities.
This institutional arrangement is suitable because it helps to harmonize the operations of
donors, pool resources needed for project implementation and ensure greater consistency and
efficiency for the attainment of expected outcomes. PCIU, which will be responsible for the
implementation of PAPEGM, comprises, in addition to the Coordinator, an Administrative
and Financial Officer (AFO), a Procurement Officer, a Monitoring and Evaluation Officer
and an Accounting Officer. The financial management components (budgeting, accounting,
internal control and financial reporting) will operate following PARCGEF mechanisms which
are to be adapted. Thus, annual budget preparation, quarterly budget execution reports,
commitment accounting based on the OHADA accounting system, internal control
formalized in a procedures manual, financial statements comprising a supply and use table,
balance sheets, financial statement notes and annexes providing details on balance sheet
columns will be the key elements of the financial and accounting management system.
Concerning procurement, the Procurement Officer has sufficient experience in enforcing the
Bank’s Rules of Procurement Procedure through his involvement in the implementation of
13
PARCGEF. The PCIU project management capacity evaluation conducted by the Bank is
satisfactory.
4.1.2 Procurements: Bank-financed procurements will be conducted in accordance with
national competitive bidding procedures (goods). Procurement will comply with the Bank’s
Rules of Procedure (May 2008 edition, revised in July 2012) using standard Bank documents
for international competitive bidding (goods) and shortlist of consulting firms (services). The
terms and conditions for the procurement of goods, works and services financed by the Bank
and the procurement plan are presented in Annex B5. The Bank will collaborate with UNDP
to establish a public investment monitoring information system and train key users of the
system. This collaboration will be based on a delegated project management agreement.
4.1.3 Disbursements and flow of funds: the planned methods for disbursement of
PAPEGM funds by the Bank are reimbursement, direct payment and working capital which
PCIU has already experimented with the implementation of PARCGEF. Regarding working
capital, a special account will be opened to receive grant resources in foreign exchange and a
sub-account in local currency. An escrow account opened in the name of the Republic of
Guinea will receive part of the ADF resources and the counterpart contribution to be used to
pay international consulting firms recruited to assist the Government of Guinea in reviewing
mining agreements and supporting reforms to improve governance in the mining sector. The
functioning of the escrow account, of which the Government is holder, will be specified in an
escrow agreement outlining all the terms and conditions for contribution, functioning and
auditing of the account. The Bank will train staff upon project start.
4.1.4 Auditing: financial and accounting audits will be conducted by an independent firm
recruited for a period of one financial year renewable depending on the quality of its services
and for a maximum period of three financial years, based on Bank-approved terms of
reference. Audit reports should be submitted annually to the Bank no later than six months
following the close of the financial year.
4.1.5 Financial management: PAPEGM will be implemented under the supervision of the
Technical Programme Monitoring Unit (CTSP) which is the Steering Committee and the
Project Coordination and Implementation Unit (PCIU) which is the implementation unit, both
of which are attached to the Ministry of the Economy and Finance. The Manual of
Administrative, Financial and Accounting Procedures prepared by PCIU in February 2013
will govern the internal control of PAPEGM. It deals with the Unit’s administrative and
personnel management modules, and financial and accounting management modules. The
principle of segregation of incompatible duties is enshrined therein. The setting up and
configuration of the TOMPRO software for the above-mentioned projects as well as the
qualified and experienced financial management staff in service will be an asset for budget
execution monitoring and regular preparation of accounting and financial statements.
4.2 Monitoring and Evaluation
4.2.1 The project will be implemented over a 48-month period. This timeline is
considered reasonable in view of the scope of activities to be implemented and project
implementation timeframes in Guinea. The Project Implementation Unit will define
monitoring and evaluation mechanisms. A monitoring and evaluation officer will be recruited
and trained to monitor project outputs and outcomes in accordance with the formats of the
Bank’s reports on implementation and outputs. A monitoring software will also be provided
to the Implementation Unit. The Bank will carry out (i) periodic supervision missions at the
rate of two per year, and (ii) a mid-term review to assess project implementation
14
performance. At the end of the project, the Bank and the Ministry of the Economy and
Finance will prepare a completion report.
4.2.2 As soon as the Grant Agreement is effective, a launch mission will be fielded to
reinforce the training of project management team leaders in the Bank’s procedures. Supervision missions will be carried out at least twice a year. Quarterly and annual progress
reports will be prepared and submitted to the Bank. The table below presents the major
indicative stages of monitoring.
Table 4.2 – 1
Stages of Monitoring and Feedback Loop
SCHEDULE MILESTONES MONITORING ACTIVITIES / FEEDBACK
July 2013 Loan approval by the Board Notification to the Government
July 2013 Loan effectiveness Signature of Grant Protocol
September 2013 Launch mission Training of project officers
September 2013 AGPM UNDB; national and regional newspapers
September 2013 Fulfilment of conditions precedent to
first disbursement
Opening of a special account;
Establishment of EGP
October 2013 Launching of first activities Preparation of programme of work
November 2013 Preparation and launch of CBs Preparation by beneficiary entities
January 2014 Evaluation of bids
March 2014 Signature of contracts, orders for goods
and start of provision of services
Carried out by contractors, verified by the project
team and focal points
2013 – 2017 Implementation of other project
activities Quarterly and annual progress reports
2013 – 2017 Supervision missions and mid-term
review mission Mission reports
2013 – 2017 Annual project audits Audit reports
October 2017 Project completion Completion report
4.3 Governance
4.3.1 Poor governance, illustrated by the spread of corruption throughout the entire
administrative machinery and the culture of impunity, has been the major cause of the
country’s economic decline in recent years. Guinea was ranked 154th
out of 174 countries in
the world in the 2012 Corruption Perception Index (CPI) and 40th
in Africa, as against 4th
in
the world and 1st in Africa in 2006. In 2012, the country occupied the bottom ranks in the Mo
Ibrahim Index on good governance, ahead of 11 other African countries ranked last. The
economic cost of poor governance, particularly corruption, is reflected by embezzlement,
wastage of public resources and loss of budgetary revenue due to fraud and tax evasion
facilitated by corrupt officials. To combat this phenomenon, the Government has embarked
on reforms over the last two years to improve public finance and procurement as well as to
build the country’s institutional capacity.
4.3.2 Concerning project financial governance, the executing agency will keep
separate project accounts using software acquired with ADF Grant resources, enabling
it to carry out cost accounting and produce reports showing expenditure by component,
category and source of financing. Project accounts will be audited annually by a firm
recruited for that purpose. Financial and audit reports will be submitted to the ADF within six
months following the close of the accounting period.
4.4 Sustainability
The sustainability of project outcomes depends primarily on Government’s
commitment to further streamline the planning, programming, budgeting, monitoring and
evaluation of the country’s development to optimize the impacts of public policies being
implemented. PAPEGM will mainly contribute to improving the management of Guinea’s
15
mining sector and make the most of the financial resources derived from the mining sector to
meet recurrent costs and enhance its capability to more effectively combat poverty. Officials
of the Ministry in charge of the mining sector will be trained on issues relating to the
management of mining agreements within the framework of the project. They will also be
involved in the review of mining agreements to promote sustainable learning-by-doing. The
second advantage of project implementation is the dissemination of knowledge through the
implementation of a comprehensive training programme in new information technologies and
varied technical domains for more than 400 senior officers and support staff, 24% of them
women in government services dealing with economic issues. The assimilation of this know-
how and mastery of modern management tools will help to improve staff qualification and
performance in the Guinean Public Administration. Lastly, improvement of the quality of
human resources by Government through public employee turnover will help to strengthen
project sustainability.
4.5 Risk Management
The organization of legislative elections could lead to risks of political instability in
Guinea. However, the strong involvement of the international community, combined with the
continued implementation of reforms will strengthen the foundations of the democratic
process and help ease the political situation and ensure proper conduct of parliamentary
elections in 2013. Besides this risk, the table below presents a summary of residual risks
(other than those related to governance and sustainability) and mitigative measures.
Table 4.5 – 1
Risks and Mitigative Measures RISKS MITIGATION Financial risk: the
implementation of the PRS
requires substantial financial
resources
Greater efforts to mobilize domestic resources are made with the support of PARCGEF.
Better governance in the mining sector will generate additional financial resources.
Risk of eviction of some mining
operators following the review of
agreements
The conduct of the review process in a transparent manner with the involvement of private
partners and the assistance of the Bank and ALSF should reassure mining operators.
Weak capacity: for the
implementation of project
activities
Training provided under the project and the support of PCIU will help to mitigate this risk.
Furthermore, the opening of the Bank’s Field Office in Guinea will contribute to
improving the implementation of project activities.
4.6 Knowledge Building
The project has adopted an important technical assistance component
comprising international and national experts. It provides for the training of Guinean
senior officers in areas such as planning, programming, budgeting and monitoring and
evaluation, tools for ensuring transition from planning to programming, project and
programme implementation and monitoring and evaluation, results-based management and
results-based monitoring and evaluation system, from project identification to the preparation
of project documents including cost estimate, and project selection procedures, automated
programming system and physical and financial project and programme monitoring. This
form of knowledge building and mastery of modern management techniques are beneficial to
the public administration which will gradually develop into a veritable development
administration.
16
V. LEGAL FRAMEWORK
5.1 Legal Instrument
The proposed legal instrument for the financing of the Economic Planning and
Mining Governance Support Project is an ADF Grant which will be concluded between the
ADF and the Republic of Guinea.
5.2 Conditions Associated with the Bank’s Involvement
5.2.1 Conditions Precedent to Grant Effectiveness: the effectiveness of the ADF Grant
shall be subject to the signing by stakeholders of a memorandum of understanding.
5.2.2 Conditions Precedent to First Grant Disbursement: the first disbursement of ADF
Grant resources shall be subject to fulfilment by the Donee of the following condition:
(i) Provide evidence of opening an account in a bank acceptable to the Fund into which
ADF Grant resources will be deposited (see § 4.1.3.).
5.3 Compliance with Bank Policies
This project is in line with the orientations of the Bank’s 2013-2022 Ten-Year
Strategy, particularly the pillar on governance. It is also consistent with the Policy on
Expenditure Eligible for Bank Group Financing.
VI. RECOMMENDATION
Management hereby recommends that the Board of Directors approve the proposal
to award an ADF Grant not exceeding UA 11.38 million to the Republic of Guinea to finance
the Economic Planning and Mining Governance Support Project under the conditions set
forth in this report.
ANNEX 1
Year Guinea Africa
Develo-
ping
Countries
Develo-
ped
Countries
Basic Indicators
Area ( '000 Km²) 2011 246 30 323 98 458 35 811Total Population (millions) 2012 10,5 1 070,1 5 807,6 1 244,6Urban Population (% of Total) 2012 36,4 40,8 46,0 75,7Population Density (per Km²) 2012 41,6 34,5 70,0 23,4GNI per Capita (US $) 2011 440 1 609 3 304 38 657Labor Force Participation - Total (%) 2012 39,7 37,8 68,7 71,7Labor Force Participation - Female (%) 2012 45,2 42,5 39,1 43,9Gender -Related Dev elopment Index Value 2007-2011 0,425 0,502 0,694 0,911Human Dev elop. Index (Rank among 186 countries) 2012 178 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2007-2011 43,3 40,0 22,4 ...
Demographic Indicators
Population Grow th Rate - Total (%) 2012 2,5 2,3 1,3 0,3Population Grow th Rate - Urban (%) 2012 4,0 3,4 2,3 0,7Population < 15 y ears (%) 2012 42,6 40,0 28,5 16,6Population >= 65 y ears (%) 2012 3,3 3,6 6,0 16,5Dependency Ratio (%) 2012 85,0 77,3 52,5 49,3Sex Ratio (per 100 female) 2012 102,2 100,0 103,4 94,7Female Population 15-49 y ears (% of total population) 2012 23,1 49,8 53,2 45,5Life Ex pectancy at Birth - Total (y ears) 2012 54,5 58,1 67,3 77,9Life Ex pectancy at Birth - Female (y ears) 2012 56,2 59,1 69,2 81,2Crude Birth Rate (per 1,000) 2012 37,9 33,3 20,9 11,4Crude Death Rate (per 1,000) 2012 12,5 10,9 7,8 10,1Infant Mortality Rate (per 1,000) 2012 85,0 71,4 46,4 6,0Child Mortality Rate (per 1,000) 2012 135,4 111,3 66,7 7,8Total Fertility Rate (per w oman) 2012 5,1 4,2 2,6 1,7Maternal Mortality Rate (per 100,000) 2010 610,0 417,8 230,0 13,7Women Using Contraception (%) 2012 12,2 31,6 62,4 71,4
Health & Nutrition Indicators
Phy sicians (per 100,000 people) 2004-2010 10,0 49,2 112,2 276,2Nurses (per 100,000 people)* 2004-2009 4,3 134,7 187,6 730,7Births attended by Trained Health Personnel (%) 2007-2010 46,1 53,7 65,4 ...Access to Safe Water (% of Population) 2010 74,0 67,3 86,4 99,5Access to Health Serv ices (% of Population) 2000 80,0 65,2 80,0 100,0Access to Sanitation (% of Population) 2010 18,0 39,8 56,2 99,9Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 1,4 4,6 0,9 0,4Incidence of Tuberculosis (per 100,000) 2011 183,0 234,6 146,0 14,0Child Immunization Against Tuberculosis (%) 2011 93,0 81,6 83,9 95,4Child Immunization Against Measles (%) 2011 58,0 76,5 83,7 93,0Underw eight Children (% of children under 5 y ears) 2008-2011 20,8 19,8 17,4 1,7Daily Calorie Supply per Capita 2009 2 652 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2010 4,8 5,9 2,9 8,2
Education Indicators
Gross Enrolment Ratio (%)
Primary School - Total 2010-2012 98,0 101,9 103,1 106,6 Primary School - Female 2010-2012 90,9 98,4 105,1 102,8 Secondary School - Total 2010-2012 41,7 42,3 66,3 101,5 Secondary School - Female 2010-2012 32,4 38,5 65,0 101,4Primary School Female Teaching Staff (% of Total) 2011 29,2 43,2 58,6 80,0Adult literacy Rate - Total (%) 2010 41,0 67,0 80,8 98,3Adult literacy Rate - Male (%) 2010 52,0 75,8 86,4 98,7Adult literacy Rate - Female (%) 2010 30,0 58,4 75,5 97,9Percentage of GDP Spent on Education 2008-2011 3,1 5,3 3,9 5,2
Environmental Indicators
Land Use (Arable Land as % of Total Land Area) 2011 11,6 7,6 10,7 10,8Annual Rate of Deforestation (%) 2000-2009 0,5 0,6 0,4 -0,2Forest (As % of Land Area) 2011 26,5 23,0 28,7 40,4Per Capita CO2 Emissions (metric tons) 2009 0,1 1,2 3,1 11,4
Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :
UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.
Note : n.a. : Not Applicable ; … : Data Not Available.
COMPARATIVE SOCIO-ECONOMIC INDICATORS
Guinea
May 2013
0
20
40
60
80
100
120
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
Infant Mortality Rate( Per 1000 )
Guine a Africa
0
200
400
600
800
1000
1200
1400
1600
1800
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
GNI Per Capita US $
Guine a Africa
0,0
0,5
1,0
1,5
2,0
2,5
3,0
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
Population Growth Rate (%)
Guinea Africa
1
11
21
31
41
51
61
71
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
Life Expectancy at Birth (years)
Guine a Africa
ANNEX 2
THE BANK’S PORTFOLIO IN GUINEA Updated in May 2013
Sector/Project Approval
Date
Signature
Date
Complet.
Date
Source
of Finan.
Approved
(UA) Disbur. (UA)
%
Disbur.
Project
Perfor. Risks
TOMBO-GBESSIA
ROAD REHABILITATION
PROJECT
13.07.05 22.07.05 30.12.13 ADF Grant
8 250 000 5 998 411.1 72.70 2.01 PPP
GUINEA – SUPPLEMENTARY GRANT
29.04.09 13.05.09 31.12.13 ADF
Grant 5 170 000 3 038 901.44 58,78 - Not rated
REHABILITATION OF
ELECTRICAL GRIDS 29.10.08 13.05.09 31.12.13
ADF
Grant 12 000 000 8 387 546.25 69.90 2.26 Non-PP
RURAL
ELECTRIFICATION
PROJECT
21.01.11 15.02.11 31.12.15 ADF Grant 14 960 000 278 002.99 1.98 2.36 Non-PP
STUDY ON THE
GUINEA-MALI
ELECTRICITY GRID INTERCONNECTION
PROJECT
12.01.11 15.02.11 31.06.14 ADF
Grant 1 667 000 0.00 0.00 - Not rated
Total
Infrastructure/Energy 42 047 000 17 702 861.78 42.10 2.21
EDUCATION IV 13.07.05 22.07.05 30.06.13 ADF
Grant 14,000,000 12 262 999.27 87.59 2.0 Non-PP
PDSD HTE AND M.
GUINEA PHASE II 09.02.11 15.02.11 31.12.13
ADF
Grant 5 000 000 1 708 141.24 33.16 2.78 Non-PP
Total Social Sector 19 000.00 13 971 140.51 73.53 2.39
ECONOMIC AND
FINANCIAL MANAGEMENT
CAPACITY
BUILDING SUPPORT PROJECT (PARCGEF)
31.01.11 15.02.11 31.12.14 ADF
Grant 7 544 000 1 292 271.74 11.05 2.48 Non-PP
NATIONAL
STATISTICS DEVELOPMENT
STRATEGY SUPPORT
PROJECT (NSDS)
30.06.11 18.08.11 31.12.13 FSF
Grant 1 136 000 681 600.00 60.00 - Not rated
SUPPORT FOR PRSP
III PROCESS 27.06.11 29.07.11 30.06.13
FSF
Grant 1 337 000 802 200.00 60.00 2.31 Non-PP
Total Multi-Sector 10 017 000 2 776 071.74 27.71 2.49 3 NR
GRAND TOTAL – 10
On-going Projects 71 064 000 34 450 074.03 48.48 % 2.61
1 PPP
7 Non-PP
ANNEX 3
MAP OF PROJECT AREA
This map has been provided by the staff of the African Development Bank Group exclusively for the use of the readers of
the report to which it is attached. The names used and the borders shown do not imply on the part of the AfDB Group and its
members any judgment concerning the legal status of a territory nor any approval or acceptance of these borders.