guidelines for allocation of hydro projects.pdf
TRANSCRIPT
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
1/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 0 5/23/20064
INDEXSl.No. Particulars Page No.
CHAPTER I
11.1
Background:Development of Hydro Power in India
11-2
1.2
Need for Private Sector Participation
2-3
2 Recent Initiatives of GOI to facilitate private sectorparticipation in Power -
3
2.1 The Electricity Act, 2003. 3
2.2 National Electricity Policy : 2005 3-4
2.3 Guidelines for determination of tariff by bidding process forprocurement of power by distribution licensees (ICBGuidelines) notified on 19thJanuary, 2005
4
3 Low level of participation of private sector in hydro sector Special requirements of Hydro Power Projects
4
3.1 Location specific nature of Hydro Potential 4-5
3.2 Funding of Hydro Projects Concerns of Financial Institutions 5-6
3.3
Back ending of tariff longer tenor loans
6
3.4 Integrated Transmission planning for Hydro Projects in a riverbasin
6-7
3.5 Development of multipurpose Large storage reservoir projects 7
CHAPTER II
1
Guidelines for Allocation of Hydro Sites:Objectives of the Guidelines
9
2. Requirements for selection of developers 10
2.1 Identification of Developer 10
2.2 Selection of Developer 10
2.3 Provision of 12% free power to the home state 10-11
2.4
Resettlement & Rehabilitation 11
2.5 Environment Protection 11
2.6 Payment Security through long term PPAs Co-terminus withlong term booking of transmission corridors and addressingthe concerns of the FIs.
12
2.7 Ensuring a time bound development 13
3 Allocation of Projects upto 100 MW 13
4 Allocation of Projects above 100 MW 14
4.1 Criteria for selection of developer 15
4.2 Minimum Bidding requirements 15
4.3 Bid Evaluation Methodology to be adopted by the SPV/State
Govt.
17
4.3.1 The standard information to be provided by the State Govt. inthe RFQ
17
4.3.2 The standard documentation to be provided by the State Govt.in the RFP
18
4.3.3 Final Evaluation of bids by the SPV/State Government 20
5 The Bid Process 21
6 Arbitration 21
7 Time table for Bid Process 21
8 Contract Award and Conclusion 21
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
2/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 1 5/23/20064
CHAPTER - 1
1. Background
1.1 Development of Hydro Power in India
India is a country with a dynamic economy growing at over
8% per annum. To meet the growing demand for energy, the
country is projected to require an addition in power generating
capacity of over 100,000 MW in the next 10 years. The bulk of
this capacity addition is expected to come from the main power
resource potential of the country i.e. coal and hydro power.
India is endowed with a large economically exploitablehydro potential assessed at about 84,000 MW at 60% load factor
equivalent to a probable installed capacity of 1,48,700 MW. Only
about 21% of this comprising of just over 32,000MW has been
exploited so far. However, the construction of hydel projects ismost challenging due to a number of factors such as difficult and
inaccessible locations, fragile and unpredictable geological
conditions, long gestation for projects, environmental issues likeforests and wild life aspects, resettlement and rehabilitation
problems etc.
The capacity addition in hydro since independence have not
grown in tandem with the additions in the thermal capacity, as
shown below: The hydro thermal ratio which stood at 46:54 in
the 70s has come down to24:76.
Hydro power being renewable, economical and environment
friendly is the preferred source of power particularly in the
context of rising fuel costs and environmental concerns of globalwarming. The government have accorded the highest priority tothe rapid development of hydro power and have launched the
50,000 MW hydro initiative under which 162 pre-feasibility
reports have been prepared. Work has just commenced on thepreparation of Detailed Project Reports for 78 projects totaling an
installed capacity of over 30,000 MW.
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
3/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 2 5/23/20064
1.2 Need for Private Sector Participation
The magnitude of investment and work involved is so huge that
even with the presence of state level utilities , Central Public
Sector Undertakings like the NHPC, SJVNL,NEEPCO, THDC, and
the entry of NTPC into hydro power development it may take
decades to even develop this capacity of 30,000 MW. It istherefore imperative that the private sector should also
participate in this programme.
It is expected that the managerial capabilities and commercial
orientation of the private sector would minimize time delays.More importantly, involvement of the private sector would reduce
the need for funding of equity by the Public Sector. It is also,
expected that capital and operating efficiencies of the privatesector would help reduce tariffs. Summing up, involvement of
private sector in development of hydro potential becomesimperative due to:
Massive resource requirement.
Need for rapid development of hydro potential.
Efficient development of the potential within budgeted costs.
Capacity Additions Over The Years
0
20000
40000
60000
80000
100000
120000
1950
1960
1970
1980
1990
1995
2000
2005
(02/05)
Capacity(MW)
Total
Hydro
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
4/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 3 5/23/20064
2. Recent Initiatives of GOI to facilitate private sector
participation in Power
2.1 TheElectricity Act, 2003:
The Electricity Act, 2003 has put in place a liberal and progressiveframework for the electricity industry in India. It has removed/reduced
entry barriers to different segments. This is aimed at promotingcompetition and protecting interests of consumers. Regulatory
framework both at the central level and at the state level along with the
Appellate Tribunal for electricity has been put in place to provide
transparent regulation.
While thermal generation has been completely delicenced, hydro
projects presently only require clearances with respect to optimal
utilization of water and inter-State and public safety issues. The Policy
permits open access to transmission and allows construction of both
captive and group captive power plants. Power trading has been
recognized as a distinct licensed activity under the supervision of the
Central Electricity Regulatory Commission (CERC)/ State Electricity
Regulatory Commission (SERC) and with the numerous power trading
companies becoming operational, the marketing risks of private power
producers has considerably decreased.
2.2 National Electricity Policy : 2005The National Electricity Policy, announced by the Government in
February, 2005 has identified hydro generation as a thrust area
for development. The salient features are extracted below:
Hydroelectricity is a clean and renewable source of energy.
Maximum emphasis would be laid on the full development of the
feasible hydro potential in the country. Harnessing hydro potential speedily will also facilitate economic
development of States, particularly North-Eastern States, Sikkim,
Uttaranchal, Himachal Pradesh and J&K, since a large proportion of
our hydro power potential is located in these special categoryStates.
Hydro projects call for large initial capital investment but once
completed require no further fuel costs but only the O&Mexpenses once the debt has been serviced. Therefore, debt
financing of longer tenure would need to be made available for
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
5/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 4 5/23/20064
hydro projects. Central Government is committed to policies that
ensure financing of viable hydro projects.
2.3 Guidelines for determination of tariff by bidding process
for procurement of power by distribution licensees (ICBGuidelines) notified on 19thJanuary, 2005
Under the guidelines, competitive bidding for purchase of power
can be initiated by a distribution licensee for the development of
projects taking benefit of Section 63 of the Electricity Act, 2003.
The guidelines envisage the purchaser of power procuring the
site getting all the requisite clearances and then inviting bids
for developing the project at the lowest cost of power on the
basis of tariff.
3 Special requirements of Hydro Power projects
This Policy seeks to address issues that have come in the way of
speedy financial closure of projects already allotted. It alsoaddresses the unique requirements of the special category hill
States where most of the underdeveloped hydro potential exists.Some of these issues are discussed below :
3.1 Location specific nature of Hydro Potential
The formulations in the guidelines described above adequatelyaddress the requirements of distribution licencees when they seek
to procure power from independent power producers (IPPs) or seek
to develop sites under their control (e.g. load centre based
generation) in a competitive environment. However, most of the
undeveloped hydro power sites are located in hill States which areeither surplus in power already, or whose ability to consume power
would be much less than the hydro potential existing in the State.
These States would therefore have to necessarily produce power
for sale in other States. The existing guidelines require the
purchaser/distributing licensee to secure the site, obtain all
clearances and after acquisition of the required land, call for tariff
based bids for development of the project. It would be difficult for
power consuming utilities in load centres - far off from these hill
States - to do all this as they do not have any control over thepotential sites. The hill States would like to utilise the hydro
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
6/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 5 5/23/20064
potential as a source of revenue for developing their backward
areas. The hill States possessing the hydro potential must
therefore like to develop their hydro sites for sale of power to
other areas and at the same time securing benefits like 12% free
power for their own development.
It is vital for the countrys security and prosperity that storage of
water to be increased. Given the nature of the monsoon system,
the volume of storage built the storage of water in the country is
inadequate compared to the needs. There are very few suitable
sites for construction of multipurpose storage projects and these
should be developed as storage type schemes thereby harnessing
their full potential. The water stored could not only generate power
but would also provide other benefits like irrigation, drinking, watersupply, flood control, etc. Moreover construction of large storage
dams is the most effective method for controlling floods.
3.2 Funding of Hydro Projects Concerns of FinancialInstitutions (FIs):
One of the main factors responsible for the slow development ofhydro projects in the private sector has been the reluctance of FIs
to fund these projects given the huge risks of geological andhydrological uncertainties, delays in land acquisition,
rehabilitation and resettlement issues, law and order problems
and natural calamities - in addition to the general problems ofIPPs like payment security etc. The financial institutions(FIs) who
have the largest stake in the project (as they fund about 70% of
the total project cost) have been seeking credit enhancement
through guarantees against such specific risks. However,
encouraged by the various provisions of the Electricity Act, 2003such as open access, recognition of power trading and setting up
of regulatoy commissions, the financial institutions are no longer
looking for Government guarantees and have reiterated that
there would be no dearth of funds for good projects with viable
tariffs promoted by credible developers.
An Inter-Institutional Group (IIG) with the MD,SBI as its
convener and representatives from other financial institutions and
the Ministry of Power has been constituted to facilitate financialclosure of private sector power projects. The IIG has been
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
7/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 6 5/23/20064
instrumental in getting financial closure for a large number of
projects and its experience has shown that projects with
competitive tariffs covered by long-term power purchase
commitments are essential requirement for funding by FIs.
Rather than depend upon Guarantees by Govt., the FIs instead,evaluate projects on the basis of tariffs of the project, ability of
the developer to bring in the required equity and technical
expertise for completing the project on time. Given the unique
tariff structure characteristic of hydro stations (of high tariffs
during the initial years which progressively decrease as debt gets
repaid), a long term PPA which incentivises meeting timely
payment by utilities in the initial years in return for purchase of
low cost power in the later years is considered a major payment
security mechanism. The FIs, therefore, would like sale of powerto be tied up with power purchase agreements covering the full
tenure of the loan such that it not only
a) ensures full repayment of debt to lenders
b) but also facilitates availability of cheaper power toconsumers who are required to pay higher tariff during
the initial years. This incentivises adherence to theconditions of the PPA and timely payments during the
initial years of higher tariffs.
3.3 Back ending of tariff longer tenor loans
A special requirement of hydel projects is the availability of long-
term funding at reasonable interest rates for back ending of
tariffs so that the cost of power during the initial years is
reasonable. The FIs perceive a lower payment security risk if the
first year tariff is reasonable and are reluctant to fund projectswith high first year tariff even if it is demonstrated that the tariff
would be reasonable in the later years. Institutions like the
Power Finance Corporation have developed special schemes for
funding hydro projects with tenures of upto 25 years to address
this concern.
3.4 Integrated Transmission planning for Hydro Projects in ariver basin:
Hydro projects are generally located in remote areas and requirelong dedicated transmission lines to carry power to the load
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
8/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 7 5/23/20064
centres. This not only adds to the cost of power but also
increases the risk associated with hydro projects as the
availability of the transmission line would have to be
synchronized with the commencement of generation. Further,
since hydro potential generally exists along the river valley itwould be necessary to optimize the transmission system given
the difficult terrain and limited availability of space. It is,
therefore, necessary that a detailed transmission plan be
prepared for the river valley and the plan implemented keeping in
view the timing of completion of projects and optimizing the
redundancies for future capacities. The Central Electricity
Regulatory Commission (CERC) in its recent order has required
that the transmission corridor would have to be booked for a
minimum period of 25 years to qualify as long-term user. PowerPurchase Agreements would therefore have to also reflect this
development and coincide for at least this period of 25 years.
3.5 Development of multipurpose Large storage reservoirprojects
i) Importance of storage reservoirs for India - India gets mostof its rainfall during 3 to 4 months and experiences very hot
summers. Yet, its per-capita storage capacity for water is amongthe lowest in the world and many regions face frequent droughts.
There is a need to build such reservoirs in the upper reaches of
the rivers before they enter the plains as suitable sites are mostlyin the hills.
Past experience has shown that Large storage reservoir
multipurpose projects like Tehri Dam and Sardar Sarovar project
have unique problems of R&R, Co-ordination with state irrigationdepartments and environmental and forest clearance related
issues. Experience has also shown that such project are prone to
time and cost overruns for many extraneous reasons not within
the control of the project developer. These guidelines do not
cover large storage reservoir multipurpose hydro projects, having
live storage capacity of more than 30 days, and envisage that
such projects be only taken up through MOUs with Government /
Public Sector Agencies and Private Sector as being done
currently. However, such MOUs should be transparentlynegotiated and must necessarily consider Central and State PSUs
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
9/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 8 5/23/20064
in the process of selection. The MOUs must ensure that all actual
contracts are awarded under the ICB guidelines with fixed price,
time certain commitments.
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
10/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 9 5/23/20064
CHAPTER-II
GUIDE LINES FOR ALLOCATION OF HYDRO SITES FOR
DEVELOPMENT:
1 Objectives of the Guidelines:1.1. To enhance hydroelectric generation capacity in the Eleventh
Plan and beyond..
1.2. To bring about uniformity in the approach of State Governments
towards allocation of hydro sites.
1.3. To create an enabling and conducive environment for the
accelerated development of hydro power projects including IPPs,
by harmonizing the interests of various stake holders such as
State Govts., displaced persons, power consumers, funding
agencies, project developers etc.1.4. To ensure allocation of hydro sites in a fair and transparent
manner keeping in mind the optimal development of the riverbasin.
1.5. To ensure safety and adherence to relevant construction,
operation and maintenance standards in compliance of the
regulations being framed by CEA (under various section 73,
section 177 clause 2(b) and section 53 clause (a) & (b) of theElectricity Act 2003) and ensure construction and operation of
projects optimizing generation at the site.1.6. To ensure development of the required transmission network in
an optimal manner meeting the integrated requirements of the
projects in the river basin.1.7 Ensure funding of projects by FIIs by meeting their concerns of
payment security through long-term power purchase
commitments.
1.8 Ensure adequate compliance on Vital issues like proper
rehabilitation of Project Affected Families (PAFs) in compliance ofthe National Policy on Resettlement and Rehabilitation (NPERR -
2003) and taking up environment protection measures in
compliance to provisions of Environment Clearance issued by
Ministry of Environment and Forests (MOEF) and as envisaged in
the EIA/EMP including Catchment Area Treatment and
social/community development.
2. Requirements for selection of Developers
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
11/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 10 5/23/20064
2.1 Pre-Qualification of Developers
Utmost care needs to be taken while identifying developers in the
interest of transparency and timely development of the project
so as to only ensure a time bound development but also deliveryof power at the most competitive rates to the consumers in line
with the overall national objective of exploiting hydro resources to
the benefit of consumers. The pre-qualification of the developer
must be done in a transparent manner by laying down in
advance the eligibility, evaluation criteria and method of
selection. The evaluation of potential developer should inter-alia
be on their financial and technical strengths and their past track
record.
2.2 Selection of Developer
The selection of the successful developer from the pre-qualified
developers should be on the basis of tariff based bidding. The
competing bidders must be required to post a bid bond(suggested figure is in the vicinity of Rs.5-10 lakhs/MW) and a
performance bond (suggested figure is Rs.10-20 lakhs/MW.)Failure, to take up the project within a prespecified time, after the
award should lead to a call on the bid bond and award to the nextqualified bidder. The performance bond should be linked to
achieving specific milestones in a predefined timeframe and
subject to call in case of non-performance as per the PERTschedule.
2.3 Provision of 12% free power to the home state
Government of India, vide its O.M. dated 17th
May, 1989 haveapproved that since the Home States are increasingly finding it
difficult to locate alternative land and resources for rehabilitation
of the oustees in hydro-electric projects. They, need to be
suitably assisted by giving incentives, such as the (proposed)12%
free power, to enable them to take care of the problems of
rehabilitation in the areas affected by the hydro-electric projects.
Without such assistance and incentives, considerable hydel
potential of the country would remain unutilized. Accordingly, the
State Government shall be entitled to realize 12% free powerfrom the project for local area development and mitigation of
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
12/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 11 5/23/20064
hardships to the project affected people in line with the Govt. of
India policy.
It is proposed to continue with this provision so that the home
state retains its right to realize 12% free power from hydel
projects over 25 MW capacity, for local area development,mitigation of hardships to the project affected people and also
overall economic development of the state, in line with the
Government of India policy.
In case of projects having unviable tariffs in the initial years, the
12% free power to the home state can be staggered in a manner
such that it is kept low in the initial years and higher in the latter
years so as to average 12% over the life of the project
2.4 Resettlement & RehabilitationThe Rehabilitation and Resettlement of the Project affected
people should be undertaken by the State Govt. (or got doneunder its supervision) to at least meet the minimum requirements
of the National Policy on Resettlement and Rehabilitation for
Project Affected Families -2003 (NPRR-2003). The total moneyspent on the project development including land acquisition would
be recovered from the developer and loaded on to the projectcost upfront, at the time of allocation, based on the DPR
assessment. However all subsequent enhancements/increaseduring the R&R implementation would be to the account of the
State Govt. in line with the GOI Policy of provision of 12% free
power to the host state for mitiagation of hardships to the localpopulation.
2.5 Environment ProtectionThe project developer should be made responsible to ensure strict
compliance to the provisions of the Environment Clearance issuedby the Ministry of Environment & Forests, and implement various
environmental measures envisaged in the EIA/EMP, including
Catchment Area Treatment (CAT) and social/community
development..
2.6 Addressing concerns of the FIs and meeting requirementsof the tariff policy-a) payment security mechanisms and
b) booking of transmission corridors.
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
13/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 12 5/23/20064
a) payment security mechanisms
The project developer would be expected to enter into a long
term PPA with the tariff being determined either under Sec. 63 of
the Electricity Act 2003. The Payment security mechanism shallconsist of :
Revolving Letter of credit (LC) by distribution licensee
Escrow Account claims against the receivables of
distribution uitilty, signed and finalized at the time of PPA
Empowerment to developers to directly supply to HT
consumers in the event of default as per provisions of the
Electricity Act 2003
In cases where the sites have already been allocated, the
developer could offer bids for supply of electricity on the basis ofallocated site and if such a bid isselected and a PPA is executed
incorporating the above security structure, the financial closure
could be achieved on the basis of the PPA so concluded.
b) Booking of transmission corridors.
It is, necessary that the transmission for evacuation ofpower from the project is planned keeping in view the timing of
completion of the project and optimizing the redundancies for
future capacities. In accordance with CERC guidelines.
3. Allocation of projects upto 100 MW:
3.1 After the launch of the Private Power Policy in 1991, the initial
project development by the private power project developerswas through the MOU route. During January-February, 1995,
vide No. A-32/95-IPC dated 18.1.1995 and 15.2.1995, it was
stipulated that power projects could only be awarded to private
developers through the process of competitive bidding after the
cut off date of 18.2.1995. The instructions were reiterated vide
No. A-40/95-IPC dated 11.9.1995. Thereafter this condition was
slightly relaxed in the Hydel Policy announced in August, 1998,
wherein States were allowed to select developers though theMOU route for hydel projects upto a capacity of 100 MW. Theseinstructions were reiterated vide No. A-32/95_IPC.1(Vol.II)
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
14/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 13 5/23/20064
dated 3.7.2002 wherein it was also clarified that wherever the
power projects are developed on the MOU route, the State
Governments would have to ensure that the EPC contract is
finalized on the basis of International Competitive bidding.
These guidelines seek to continue this dispensation available tothe states to develop hydro power projects upto the capacity of
100 MW, through private developers, under the MOU route
subject to the condition that wherever the power projects are
developed on the MOU route, the State Governments ensures
that the EPC contract is finalized by the developer(s), on the
basis of International Competitive bidding.
4. Allocation of Projects above 100 MW:
Promotion of competition in the electricity industry is one of the
key objectives of the Electricity Act, 2003. Power purchase costsconstitute the largest element for distribution licensees.
Procurement of power at competitive rates by utilities will
optimize the overall costs and facilitate development of power
markets. International experience has shown that competition in
wholesale electricity markets has actually led to reduction inprices of electricity bringing significant benefit for consumers.
The IPP experience has highlighted the critical importance of
government intervention to
Tie up transmission/evacuation requirements
Assist in obtaining environmental & other statuotory
clearances
Coordination with states and bulk power purchasers
for achieving financial closure.
There exists a vast hydro potential in some of the states which is
more than their own requirements. There is a need for harnessing
this potential, which is surplus to the requirements of the home
state, in the overall interest of the country. This would afford the
dual benefits of economic and local area development to the host
State through revenues of 12% free power and provision of
cheaper power to the other power deficit states of the country.
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
15/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 14 5/23/20064
To ensure that the development of hydro projects larger than 100
MW takes place in a time bound manner and a shelf of
meaningful and bankable PRs, duly vetted by an agency of
ingternational repute, are available within a reasonable time
frame of next 3 years, the Central Government will adopt suchfacilitating mechanisms as constitution of task forces, Shell
Companies and other statutory / non-statutory bodies which
would take action for
- Preparation of project report.
- Land acquisition and preliminary R&R.
- Formulation of R&R plan and assessment of cost thereof
- Preparation for EIA & EMP reports.
- Various approvals and statutory clearances.- Aggregating demand for power from the licensees of
different States.- Power Evacuation System, Load Flow Study.
The above facilitating mechanism by the Central Government is
only illustrative in nature and not exhaustive. The role of the
Central Government will be facilitated through its Shell Company/ SPV / facilitating organization. It is expected that for
expeditious development of hydro power projects a separate shellCompany/SPV would be created for each large hydro project.
Each Shell Company / SPV will then work independently to reach
a stage where major tie-ups, statutory clearances and linkagesare in placeexcept for project covered by para 3.5 (Chapter I).
Selection of final developer will be through a Tariff based ICB.
The Shell Company / SPV will be thereafter transferred to the
successful bidders for execution.
4.1 Criteria for selection of developer
In the case where the host state is developing the hydro site for
its own consumption i.e. the SERC of the host state is the
competent authority for adopting the tariff of the project under
Sec 63 of the EA-2003, the state may itself or though an
SPV/Shell Company as outlined for the Central Goverment, invite
tariff based bids for development of the site in accordance withthe ICB guidelines notified on 19.01.2005.
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
16/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 15 5/23/20064
However, in case where the site is being developed primarily for
sale of power to other states i.e. the saleable energy will be sold
to other states and CERC is the competent authority for accepting
the tariff of the project under Sec 63 of the EA-2003, the hoststate is expected to necessarily avail the multi stake holder
facilitation mechanism of Govt. of India as outlined in para 3.0
above. The shell company/SPV after obtaining the Site would
proceed with the development of the site to reach a stage where
major tie ups, statutory clearances, linkages are in place and
thereafter the shell company/SPV/(hereafter referred to as theSPV) will be transferred to the successful bidder selected througha tariff based ICB.
4.2 Minimum Bidding requirementsA pre-requisite for meaningful competitive bidding is that the
prospective developers have access to a reasonably reliable
Project Report (PR). A PR with all the relevant data is the basicrequirement for a prospective bidder that will enable it to
properly estimate the various elements of cost and make ameaningful bid on tariff. PRs for hydroelectric projects of
capacities greater than 100 MW would require verycomprehensive studies from the point of view of hydrology,
geology, seismology, meteorology, etc. meeting the CEAs
Guidelines for formulation of project reports for power projectsand CWCs Guidelines for preparation of Detailed Project Reports
of Irrigation and multi-purpose schemes It would not be prudent
to expect each of the developers to spend their time and money
on investigations even prior to the event of putting in their bids.
For the preparation of DPRs the following two options are
available:
(i) The SPV/State Governments could undertake to get the PRs
of identified projects at their cost. In the interest of
development of these projects this exercise should be done
in a time bound manner so that apart from the power being
available early, the State Government also starts getting its
returns early. This exercise will lead to a shelf of projectswith PRs which can be offered to agencies selected on the
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
17/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 16 5/23/20064
basis of tariff based competitive bidding leading to early
development of the project, quicker returns flowing to the
State and reasonable tariff for the consumers at large.
(ii) Such of the State Governments which are keen to have
these PRs prepared by the Central Government agenciesmay approach the Central Agencies to get these PRs
prepared. Ministry of Power would facilitate this exercise by
making appropriate provisions either in its budget or
through the SPV. In either of these two options a mandatory
condition would be that the agency selected for developing
this project through competitive bidding shall reimburse the
cost of the PR to the SPV .
(iii) The PRs so prepared would be got vetted by another
reputed agency . This would not only ensure that the issuesrelating to dam safety, river basin optimization etc.are
adequately addressed but would also address importantinterstate issues.
4.3 Bid Evaluation Methodology to be adopted by the
SPV/State Govt.:The bidding process must be a two-stage process featuring a
separate request for qualification (RFQ) and a request forproposal (RFP).
4.3.1 The standard information to be provided by the StateGovt. in the RFQ should inter-alia include but need not belimited to the following:
The SPV / State Govt. should publish the RFQ notice in at
least two national newspapers, the Government website and
trade magazines and also accord it wide publicity. Thebidding shall necessarily be by way of international
competitive bidding (ICB). For the purpose of issue of RFQ
the minimum conditions to be met by the bidder shall be
specified in the RFQ notice along with the evaluation criteria
thereof. Standard documentation to be provided by the
State Government in the RFQ shall include the following: PR
(duly vetted by the competent authority) containing the
requisite hydrological, geological, meteorological and
seismological data and basic dam design and project outlineas per CEAs Guidelines for formulation of project reports
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
18/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 17 5/23/20064
for power projects and CWCs Guidelines for preparation of
Detailed Project Reports of Irrigation and multi-purpose
schemes
Site details including land acquired, details of project
affected people (PAP)and project affected families(PAF). The minimum conditions, both financial and past track
record, required to be fulfilled by the developer and the
evaluation criteria thereof.
In cases of the projects, where electricity is being procured
by licensees of other states also, the RFQ Evaluation
Committee should include
Representative of host State Government
Representative of an FI
CEO, of the SPV / Shell Company.The same Committee could also select consultant for
Projects Report.
4.3.2 The standard documentation to be provided by the SPV/State Government. in the RFP should inter-alia include the
following: Technical requirements on minimum capacity and other
technical requirements/conditions to be met by thedeveloper, which must also be in conformity with the
requirements of CWC/CEA for optimum basin development.
Issues relating to flood control, irrigation, drinking water,navigation, inter-State requirements must be addressed by
the SPV /State Government and the final responsibility for
ensuring clearances /permission from the relevant
authorities for these issues would rest with the SPV / State
Government as per CEAs Guidelines for formulation ofproject reports for power projects and CWCs Guidelines
for preparation of Detailed Project Reports of Irrigation and
multi-purpose schemes.
The time period within which the developer must complete
critical milestones must be spelt out upfront and the
developers informed that failure to adhere to the agreed
time line could result in cancellation of allocation of the
project.
Default conditions including sluggish progress, cure thereofand penalties would also be clearly stated.
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
19/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 18 5/23/20064
Dam design, safety and other technical, operational and
safety criteria to be met by the developer including the
provisions of the IEGC/State Grid Code, relevant orders of
the proper commission, regulations framed by CEA under
section 73 , section 177 clause 2(b) and section 53 clause(a) & (b) of the Electricity aAct 2003 etc., as applicable.
Requirements to be met by the project developer to
demonstrate his ability to raise the required finances from
the FIs at the time of submission of bids. This would
accelerate the process of financial closure and development
of the hydroelectric project within a stipulated time.
The SPV / State Government must clearly stipulate the exit
option conditions for the lead developer so that the project
development is not delayed/held up indefinitely in case ofsuch a contingency.
The RFP shall also provide the maximum period within whichthe selected developer must commission the project. This
shall ordinarily not be less than four years from the date of
allocation of site to the developer and would be project
specific.
The RFP shall also specify the liquidated damage that wouldapply in the event of delay in commissioning of the project.
The project developer must be required to submit a detailedaction plan within six months of allotment with clearly
identifiable intermediate milestones. In the case of
inordinate delays and failure to meet the milestones theallotment should be liable for cancellation and should
invariably be cancelled if the project implementation is not
being pursued in line with this policy.
The cost on R & R, environmental measures, Catchment
Area Treatment, land acquisition including social andcommunity development should be frozen before issuance of
RFP and duly indicated therein. The State Government
should be solely responsible to provide land ( both private,
and government) in a phased manner in accordance with the
schedule agreed with the developer.
4.3.3 Final Evaluation of bids by the SPV/State Government
:
The bid must be evaluated solely on the basis of thecomposite levellised tariff quoted by the bidder.
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
20/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 19 5/23/20064
The project developer must demonstrate his commitments
to the tariff through duly initialed and authenticated PPAs at
the indicative tariff with the distribution utilities, for at least
90% of the design energy. The remaining power upto 10%
could be operated on merchant basis. Formation of consortium by the bidders may be permitted.
In such cases the consortium shall identify a lead member
and all correspondence from the bid process shall be done
by the lead member. The lead member shall not ordinarily
have an exit option before the commissioning of the project.
The SPV / State Government may specify technical and
financial criteria and lock in requirements for the lead
member of the consortium, if required.
The SPV / State Govt. shall ensure evaluation of the bids forall projects on inter-state rivers in line with CEAs/CWCs
optimal development plan of the river basin.
In cases of the projects, where electricity is being procured
by licensees of other states also, Final Bid Evaluation for
selection of developer would be by an Evaluation Committee
which includes- Chairperson/CEO of the lead FI;
- Representative of host State Government;- Representative of the power Purchasers
- CEO, of the SPV / Shell Company.
The evaluation committee shall reject all bids if the
composite tariffs quoted are not aligned to the prevailing
market prices.
5. The Bid process
The bid process adopted should be as outlined in the tariff based
guide lines of GOI issued on 19.1.2005.
6 Arbitration:
The State Government will establish an amicable dispute
resolution mechanism in accordance with the provisions of the
Indian Arbitration and Conciliation Act, 1996. The ADR shall be
mandatory and time-bound to minimize disputes regarding thebid process and the documentation thereof.
-
7/21/2019 GUIDELINES FOR ALLOCATION OF HYDRO PROJECTS.pdf
21/21
Guidelines for development of Hydro Electric Projects Sites
Sanjay Chadha Page 20 5/23/20064
7. Time table for Bid Process:
The SPV / State Government must in advance indicate a time
table for conclusion of the bidding process. However, the SPV /
State Government may give extended time frame based onprevailing circumstances and such alternations shall not be
construed to be a deviation from these guidelines.
8. Contract Award and Conclusion:
The Award of site to the selected developer consequent to the
selection process in accordance with the terms and conditions as
finalized shall be concurred by the State Government.
Consequent to the signing of the award the evaluation committeeshall provide a proper certification on adherence to these
guidelines and to the bid process established. The finalagreement along with certification of the evaluation committee
shall also be forwarded to the appropriate regulatory commissions
for approval under Section 62 or adoption under Section 63 of theElectricity Act, 2003.