guidance for the design of metal roofing and cladding to comply with approved document ... ·  ·...

45
GUIDANCE FOR THE DESIGN OF METAL ROOFING AND CLADDING TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB Nh2 (23) JANUARY 2002 MCRMA Technical Paper No. 14

Upload: trinhquynh

Post on 11-Apr-2018

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

GUIDANCE FOR THE DESIGN OFMETAL ROOFING AND CLADDINGTO COMPLY WITH APPROVEDDOCUMENT L2 : 2001

CI/SfB

Nh2(23)

JANUARY 2002

MCRMA Technical Paper No. 14

Page 2: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

PageForeword 1

Checklist for compliance with Approved Document L2 1

1.0 Introduction 3

2.0 Approved Document L2 42.1 Requirements of the Approved Document 42.2 Energy efficient design of the building fabric 52.3 Maximum areas of windows, doors and rooflights 62.4 Thermal bridging at junctions and around openings 62.5 BRE IP 17/01 72.6 Building air leakage 7

3.0 Methods for calculating heat loss through plane areas of cladding and roofing systems 93.1 The development of U-value calculation methods 93.2 Computer modelling 113.3 Theory 133.4 Examples 143.5 Summary 16

4.0 Thermal bridges 174.1 Introduction 174.2 Surface condensation and mould growth 174.3 Heat loss through thermal bridges 204.4 Examples of surface temperature and heat loss through thermal bridges 214.5 Example of the effect of thermal bridging on overall heat loss 224.6 Summary 23

5.0 Infra-red thermography 245.1 Thermal imaging 245.2 Conditions for a survey 255.3 Examples 265.4 Summary 27

6.0 Air tightness 276.1 Introduction 276.2 Whole building testing of air leakage 276.3 Air leakage parameters 306.4 Heat loss due to air leakage 306.5 Laboratory tests for individual components 316.6 Examples of testing carried out at BRE 316.7 Example of the effect of individual joint leakage on whole cladding leakage 336.8 Summary 34

7.0 Appendix 34

8.0 References 41

41

Contents

© The Metal Cladding & Roofing Manufacturers Association Limited, January 2002

MCRMA technical papers

1. Approved Document L Conservation of fuel andpower, 1995 edition HMSO 1994.

2. Approved Document L2 Conservation of fuel andpower in buildings other than dwellings. October2001.

3. DEFRA/DTLR Report: Limiting thermal bridgingand air leakage: Robust construction details fordwellings and similar buildings. The StationeryOffice, October 2001.

4. BS EN ISO 6946 : 1997 Building componentsand building elements – Thermal resistance andthermal transmittance – Calculation method.

5. BRE IP 17/01 Assessing the effect of thermalbridging at junctions and around openings BREAugust 2001.

6. CIBSE Guide A3 Thermal properties of buildingstructures CIBSE 1999.

7. BS EN 12524 : 2000 Building materials andproducts - Hygrothermal properties -Tabulateddesign values.

8. BRE Information Paper IP 5/98 : Metal cladding :assessing thermal performance

9. BS EN ISO 10211-1: 1996, Thermal bridges inbuilding construction - Heat flows and surfacetemperatures, Part 1. General calculationmethods

10. BS EN ISO 10211-2: 1996, Thermal bridges inbuilding construction - Heat flows and surfacetemperatures, Part 2 Linear thermal bridges.

11. BS 5250 :1989 British Standard Code of practicefor control of condensation in buildings.

12. BS EN ISO 13788:2001 : Hygrothermalperformance of building components andbuilding elements - Internal surface temperatureto avoid critical surface humidity and interstitialcondensation – Calculation methods

13. A practical guide to infra-red thermography forbuilding surveys, BRE Report 176, BRE 1991

14. A professional’s guide to testing housing forenergy efficiency, General Information Report64, Energy Efficiency Best Practice Programme,2000.

15. CIBSE Guide TM23:2000, Testing buildings forair leakage, CIBSE 2000.

16. BS EN 13829 : 2001 thermal performance ofbuildings – Determination of air permeability –Fan pressurisation method

17. BS EN 12114:2000 Thermal performance ofbuildings - Air permeability of buildingcomponents and building elements - Laboratorytest method.

No 1 Recommended good practice for daylightingin metal clad buildings

No 2 Curved sheeting manual

No 3 Secret fix design guide

No 4 Fire and external steel-clad walls: guidancenotes to the revised Building Regulations1992

No 5 Metal wall cladding design guide

No 6 Profiled metal roofing design guide

No 7 Fire design of steel sheet clad external wallsfor building: construction performancestandards and design

No 8 Acoustic design guide for metal roof andwall cladding

No 9 Composite roof and wall cladding designguide

No 10 Profiled metal cladding for roof and walls:guidance notes on revised BuildingRegulations 1995 parts L & F

No 11 Flashings for metal roof and wall cladding:design, detailing and installation guide

No 12 Fasteners for metal roof and wall cladding:design, detailing and installation guide

No 13 Composite slabs and beams using steeldecking: best practice for design andconstruction

Other publicationsThe Complete Package CDROM

Manufacturing tolerances for profiled metal roof andwall cladding

CladSafe latent defects insurance scheme: basicguide

LiabilityWhilst the information contained in this designguide is believed to be correct at the time of goingto press, the Metal Cladding and RoofingManufacturers Association Limited, its membercompanies and the Building ResearchEstablishment cannot be held responsible for anyerrors or inaccuracies and, in particular, thespecification for any application must checked withthe individual manufacturer concerned for a giveninstallation.

The diagrams of typical constructions in thispublication are illustrative only.

References

Page 3: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

This publication has been produced by the MetalCladding and Roofing Manufacturers Association(MCRMA) in collaboration with BRE, to assist thedesigners, manufacturers and installers of metalwalls and roofs to comply with the requirements ofApproved Document L2 of the BuildingRegulations, published in October 2001 to comeinto force in April 2002.

It describes the content of those parts of theApproved Document relevant to metal claddingand roofing systems and gives guidance as to:

The calculation of U-values

Allowing for thermal bridging at junctions andopenings

Infra-red surveys

Air leakage testing

The guidance is designed to be relevant to bothtwin skin and composite panel systems.

Calculation of U-values1. Approved Document L2 requires that the U-

values of metal site assembled and compositepanel walls and roofs must be less than or equalto 0.35 W/m2K and 0.25 W/m2K respectively.(The corresponding values in Scottish TechnicalStandard J are 0.30 W/m2K and 0.25 W/m2K).These values include associated componentssuch as gutters and smoke vents however,rooflights, windows and doors have separatevalues.

2. Because the method for calculating U-valuescontained in BS EN ISO 6496 and CIBSE GuideA does not apply to metal roofing and claddingsystems, more complex methods must be used.

3. If the construction is one of those covered inBRE IP 5/98, the U-value can be obtained fromthe graphs or other information in the IP andcorrected for air spaces and compression of theinsulation by the profiles using the equations inthe IP.

4. If the component contains independent linearfeatures that can be represented by a series oftwo-dimensional models, use a two-dimensionalmodel and combine the results from the differentmodels.

5. If the component contains repeating pointthermal bridges, such as clips, develop a three-dimensional model to calculate the heat flowsand then the U-value.

Thermal bridging1. Approved Document L2 requires that the

building fabric should be constructed so thatthere are no significant thermal bridges or gapsin the insulation layer(s) within the variouselements of the fabric, at the joints betweenelements and at the edges of elements such asthose around window and door openings. It isalso necessary to account for penetration of theinsulated envelope by features such as safetyharness posts or rafters which project to supporta canopy or gutter.

40 1

Foreword Checklist for compliancewith Approved Document L2

Summary of window and door lintels, jambsand sillsGap between window or door fmin = 0.46frame and cladding as Figs A.17 �= 1.27 W/mKand A.18

Frame moved forward in line with fmin = 0.67wall liner �= 0.69 W/mK

Insulation included between fmin = 0.91window or door frame and �= 0.23 W/mKstructural steel and cladding, asFig A.19 to A.24, but not A.20

Lintel with insulation included fmin = 0.80between window or door frame �= 0.43 W/mKand structural steel and cladding,but sill flashing crossing theinsulation, as Fig A.20

Point Thermal BridgesSome features of industrial buildings in which steelelements penetrate the insulation, exist at onlydiscrete points, and are not linear features like theother details discussed in this Appendix. Althoughtheir analysis is not a requirement of ApprovedDocument L, it should be recognised that they canbe sources of extra heat loss from the building and,more importantly, can locally lower the internalsurface temperature low enough to cause severesurface condensation, especially in high humiditybuildings. These features are much more variablethan the other details discussed above and theexamples below are included for illustration only.Individual calculations should be done wheneverany of these features are included in a highhumidity building. Two examples are shown in thefigures below:

a) a harness attachment post, which is a hollowsteel post, with 2mm thick walls, which isattached to the structural steel inside thebuilding and passes through the roof;

b) a girder, which is attached to the structuralsteelwork within the building and passes thoughthe insulated cladding to support, for example acanopy or eaves gutter.

For each example, the value of fmin and the extraheat loss in W/K, caused by each is quoted; the

total heat loss is found by multiplying this by thenumber of these features in the building.

Fig A.25: Harness attachment post

Fig A.26: Internal surface temperaturefmin = 0.77 , Heat loss = 0.17 W/K

Fig A.27: Canopy girder

Fig A.28: Internal surface temperaturefmin = 0.62 , Heat loss = 0.69 W/K

Page 4: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

2. It is necessary to consider both the risk ofcondensation on each individual thermal bridgeand the effect of the increased heat loss throughthermal bridges on the overall heat from thebuilding.

3. If a detail contains metal components crossingthe insulation that would not otherwise bepresent in a plane element, surfacecondensation may occur in humid environments.The severity of the bridge, and therefore the riskof condensation, is determined by the f-factor,which is calculated by modelling the structure. Ifthis type of thermal bridge is to be included in abuilding which is likely to have a humid internalenvironment, consideration should be given toredesigning the detail.

4. It is also necessary to calculate the contributionof the thermal bridges to the overall heat lossfrom the building by using the linear thermaltransmittance (�-value) and then following theprocedures specified in BRE IP17/01. If the totalheat loss through the thermal bridges is greaterthan 10% of that through the plane areas,individual details must be modified to reduce theloss through the bridges.

5. The parameters needed to comply with Part Lvia IP 17/01 (the f-value and the �-value) aregiven in this report for a range of details thatshould cover most metal clad buildings. Meansof improving the thermal performance of eachdetail are presented. It will be necessary to usea two-dimensional thermal model to calculatethe f-value and the �-value for all other details.

Infra-red surveys1. An infra-red survey, carried out by a competent

person, can be used to demonstrate that theinsulation is reasonably continuous over thewhole visible envelope of the building.

2. Given the right conditions, infra-red surveys canprovide useful qualitative information aboutthermal bridges and air infiltration but cannotquantify their effect, nor can they be used tomeasure the U-value of walls and roofs.

3. Infra-red surveys of the envelope of a buildingshould preferably be done from the inside andideally require calm, dry, cold and cloudyconditions; there may therefore be aconsiderable delay before conditions aresuitable. The conditions for external surveys areeven more restrictive.

4. For a survey to be successful, the buildingshould be heated for at least 12 hours beforethe survey, there should be no sun and no rainon the external surface.

5. The interpretation of infra-red surveys issubjective requiring experienced staff, especiallyin the presence of metal components, withemissivities much lower that those of otherbuilding materials. This may lead to disputesconcerning whether an apparent defect issignificant or not.

Air leakage1. Compliance with the Approved Document can

be demonstrated for buildings of floor area <1000 m2 by providing evidence that appropriatedesign details and building techniques havebeen used and that the work has been carriedout in ways that can be expected to achieveconformity.

2. Compliance with the Approved Document canbe demonstrated for buildings of any size bydemonstrating that the results of air leakagetests are satisfactory.

3. Pressurisation testing of whole buildings gives agood estimate of their energy loss from airinfiltration in practice.

4. The contribution of individual areas of thebuilding envelope to the overall leakage can beidentified and quantified by the use of smoketubes, infra-red surveys and reductive sealing.

5. The leakage through individual cladding systemsand the effect of sealing joints etc. can bemeasured in laboratory tests. The effect ofother components installed into the envelope,such as doors, windows, smoke vents etc.

2 39

Details 7, 8 and 9 : Door or windowlintel, jamb or sillAs these three details are essentially the samefrom the point of view of thermal bridging, theyhave been treated together.

If, as is shown in Figure A.17 or A.18, the windowor door frame is fixed to the structural frame withinthe cladding, leaving a gap of 50mm between theframe, the steel of the structural frame and the dripsill will form a marked thermal bridge.

Moving the window frame forward so that the outeredge is in line with the liner of the wall, bringssome improvement and moving further forward sothat it half overlaps the wall insulation is evenbetter, but this may cause structural difficulties.

If a 25mm layer of thermal insulation is placedbetween the structural framework and thewindow/door frame, either as insulation board orinfill insulation as shown in Figures A.19 to A.23,the thermal bridge is greatly reduced. However, ifas shown in Figure A.20, the sill flashing crossesthe insulation because there is no adequateattachment point on the outside, the benefit isreduced.

Fig A.17: Lintel in built up wall

Fig A.18: Lintel in composite panel wall

Fig A.19: Modified lintel in built up wall

Fig A.20: Modified lintel in composite panel wall

Fig A.21: Modified jamb in built up wall

Fig A.22: Modified jamb in composite panel wall

Fig A.23: Modified window sill in built up wall

Fig A.24: Modified window sill in composite panel wall

Page 5: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

should be quoted by the manufacturer. Theresults from these tests can be scaled up toestimate the leakage contribution of thecladding to the leakage of a full scale building,provided the cladding has been properlyinstalled.

6. Small scale tests have shown that properlyinstalled metal cladding will already complywith the new air leakage requirements and thatadditional sealing of internal side laps andvertical and horizontal perimeter joints willsubstantially further reduce the air leakagethrough the cladding systems of buildings to avery low level. The MCRMA thereforerecommends that side and end laps/joints andall perimeter joints should be effectively sealed,not only to reduce the air leakage but also toprovide vapour control. Attention has to bepaid to the leakage through all associatedelements within the envelope.

7. However well designed a system is; it will failand require expensive retesting, possiblydelaying the completion of a contract by manyweeks, if it has not been well installed. It istherefore essential that installation is carriedout by experienced contractors, is wellsupervised and follows the claddingmanufacturer’s guidance.

As part of the government’s programme to reducethe effects of global warming by limitinggreenhouse gas emissions from buildings,transport and industry, the 1995 version ofApproved Document L Conservation of fuel andpower 1, which applies until April 2002 has beenextensively revised. After consultation with industryand research bodies, an initial revised version ofthe Approved Document was published forconsultation in June 2000. After the replies fromthe consultation had been considered a reviseddocument was published as an ‘interim draft’, inApril 2001. After minor revisions and editorialchanges this version was published in October2001 and will come into force in April 2002. Thepublished Approved Document is available in twovolumes; L1, covering domestic buildings, and L2,covering buildings other than dwellings. This guidecovers the provisions of L22.

Approved Document L2 applies to only Englandand Wales, Scottish Technical Standard JConservation of fuel and power has been revised inparallel and will come into force at the same time.The revisions are generally the same as inApproved Document L2, with some significantdifferences:

• The elemental U-value for walls is required to be0.30 W/m2K, compared to 0.35 W/m2K inEngland and Wales.

• The category ‘roofs with integral insulation’ witha required U-value of 0.25 W/m2K, that wouldapply to both site assembled and compositepanel roofs in England and Wales does notappear in the Scottish Standard. Roofs up to a10˚ slope will be assessed as flat roofs requiring0.25 W/m2K, but it is possible that steeper roofscould be assessed as a pitched roof withinsulation between the rafters requiring 0.20W/m2K.

• The BRE IP 17/01 that covers thermal bridgingis not referenced in the Scottish Standard, thereis instead many more references to the BREReport Thermal insulation: avoiding risks.

• There is no requirement for post-completionthermal imaging surveys or pressurisationtesting in Scotland.

38 3

Introduction

or edge of the floor slab and extends 100mm downthe wall or slab; see Figure A.13 or A.14. Again, itis preferable to use a lightweight block or screed.

Summary: Drip sills1. As Fig A.11 or A.12

Medium weight blockwork (k=0.6) fmin = 0.48and steel flashing �= 1.10 W/mK

Light weight blockwork (k=0.11) fmin = 0.54and steel flashing �= 0.91 W/mK

Medium weight blockwork (k=0.6) fmin = 0.60and plastic flashing �=0.81 W/mK

2. As Fig A.13 or A.14

Medium weight blockwork (k=0.6) fmin = 0.84and insulation extended 100mm �= 0.22 W/mKdown the wall

Light weight blockwork (k=0.11) fmin = 0.91and insulation extended 100mm �= 0.10 W/mKdown the wall

Detail 6 : CornerPossible thermal bridging can result if the liner ofone side extends across the insulation on the otherside to touch the outside corner trim. Leaving agap of only 5mm between the liner and the outsidetrim can give significantly better performancehowever, stopping the liner short at the wall linergives the best performance, see Figure A.15.There is also a possible gap between the wallpanels that could allow outside air to penetrate tothe liner. If the panels stop short at the corner andthe resulting void is infilled with insulation (FigureA.16), the thermal bridge is effectively eliminated.

Fig A.15: Corner in built up wall

Fig A.16: Corner in composite panel wall

Summary of cornersLiner extends to touch the external fmin = 0.76corner trim �= 0.25 W/mK

Air gap between the insulation at fmin = 0.81the corner �= 0.20 W/mK

5mm gap between liner and fmin = 0.90external corner trim �= 0.07 W/mK

Liner taken back to liner of other fmin = 0.95cladding and gap infilled with �= 0.01 W/mKinsulation as Fig A.15 and A.16

Page 6: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

The new Approved Document includes a widerange of new requirements, including improvedefficiency of heating, mechanical ventilation and airconditioning systems, improved control of heating,hot water supply and lighting. However, the mostimportant changes with significant potential impactson the metal cladding and roofing industry are:

The U-values required for walls and roofs aresignificantly lower and more rigorous methods ofcalculating U-values have been introduced.It is required that more attention is given tothermal bridging at, for example, junctions andopenings.It is required that more attention is given tolimiting air leakage through the buildingenvelope.Post construction thermal imaging and airinfiltration testing may be required todemonstrate compliance with the Regulations.

A guide to ‘robust construction details’ for ‘domestictype constructions’

3that meet the requirements of

the Regulations, and do not lead to problems ofcondensation and mould or air infiltration, has beenpublished in association with the ApprovedDocuments (although it is relevant mainly toApproved Document L1, it also applies to, forexample, schools or small office buildings coveredby L2 but built with ‘domestic style’ details). Thispresent document provides guidance to assistbuilding designers and manufacturers and installersof metal cladding and roofing systems andassociated components to meet the requirementsof the new Approved Document L2 relevant to thebuilding fabric (i.e. it does not cover issues such asheating, hot water supply and lighting that arecovered in Approved Document L2). TheApproved Document makes reference to thisMCRMA/BRE guide as a means of demonstratingcompliance with the Regulations. ScottishTechnical Standard J does not reference either the‘domestic’ robust details or the current document.

2.1 Requirements of the ApprovedDocumentThe essential requirement of Approved DocumentL2 is summarised in the opening sentence ofclause 1.1 - all text in italics below is a direct quotefrom the Approved Document.

1.1 In order to achieve energy efficiency inpractice, the building and its services systemsshould be appropriately designed (Section 1) andconstructed (Section 2).

There are three methods of demonstratingcompliance with the standard, all of which involveconsideration of the design and construction ofthe building fabric and the design and operation ofthe services.

1.6 Three methods are given for demonstrating thatreasonable provision has been made for theconservation of fuel and power. These differentmethods offer increasing design flexibility in returnfor greater demands in terms of the extent ofcalculation required. However the overall aim is toachieve the same standard in terms of carbonemissions. The methods are:

a) an Elemental Method (paragraphs 1.7 – 1.68).This method considers the performance of eachaspect of the building individually. To complywith the provisions of Part L, a minimum level ofperformance should be achieved in each of theelements. Some flexibility is provided for tradingoff between different elements of theconstruction and between insulation standardsand heating system performance.

b) a Whole Building Method (paragraphs 1.69 –1.73). This method considers the performance ofthe whole building. For office buildings, theheating, ventilation, air conditioning and lightingsystems should be capable of being operatedsuch that they will not emit no more carbon thana benchmark based on the ECON 19 data.Alternative methods are also provided forschools and hospitals.

c) a Carbon Emissions Calculation Method(paragraphs 1.74 – 1.76). This method alsoconsiders the performance of the whole building,

4 37

Approved Document L2

Fig A.10: Valley gutter in composite panel roof

Making the gutter liner more robust and replacingthe gutter outer with a lower conductivity materialsuch as plastic where it cuts across the insulationwill reduce the thermal bridge, if the roof liner isstopped short as well so that the insulation layer iscontinuous, the thermal bridge will be largelyeliminated (Figure A.9). if the gutter could be madeas in Figure A.10, thermal bridging would benegligible.

Summary : valley guttersMetal gutter outer and roof liner fmin= 0.81crossing insulation (typical �= 1.50 W/mKcurrent construction)

Crossing gutter insulation with fmin = 0.95plastic with k=0.2 W/mK instead �= 0.17 W/mKof metal, liner stopped short asFig A.9

Gutter as Fig A.10 fmin = 0.95 �= 0.15 W/mK

Detail 5 : Drip sill at the base of a wallpanel supported on a masonry wall orground floor slabThis thermal bridge is particularly important as itoften extends the full length of the buildingperimeter. The intensity of the thermal bridgedepends on the interaction between the detailing ofthe cladding panel and the masonry wall and floorslab to which it is fixed.

If the cladding is connected to the wall or slab asshown in Figure A.11 or A.12, a very severethermal bridge is caused by conduction a) throughthe blockwork and brickwork, and b) through thesteel flashing, which is connected directly to theliner of the wall cladding. Use of lightweight

blockwork, or screed on a floor slab will reduce theseverity slightly; replacing the steel drip with plasticwill bring some further improvement.

Fig A.11: Drip sill in built up wall

Fig A.12: Drip sill in composite panel wall

Fig A.13: Modified drip sill in built up wall

Fig A.14: Modified drip sill in composite panel wall

More significant improvement can be achieved bymoving the drip so that it is fixed to the outer sheetof the cladding and installing a trim, fixed to theouter sheet and wall/floor. This trim supports sitefixed insulation infill that covers the top of the wall

Page 7: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

* Built-up metal or composite panel roofs are regarded as having integral insulation; this category is notincluded in Scottish Technical Standard J.

+ This value is 0.30 W/m2K in Scottish Technical Standard J.

but can be applied to any building type. Tocomply with the provisions of Part L, the annualcarbon emissions from the building should be nogreater than that from a notional building thatmeets the compliance criteria of the ElementalMethod. The carbon emissions from the pro-posed building and the notional building need tobe estimated using an appropriate calculation tool.

Many of the issues covered by the ApprovedDocument are the concern of the architect orservices installer and manager of the building.There are three issues, covered in this guide, thatare of special relevance to the building designers,and the designers, manufacturers and installers ofmetal cladding and roofing systems. These are:

energy efficient design of the complete buildingfabric;limiting the effect of thermal bridging, e.g. atjunctions, openings and penetrations;limiting air leakage through the building envelope.

2.2 Energy efficient design of thebuilding fabric 1.7 To show compliance following the ElementalMethod, the building envelope has to providecertain minimum levels of insulation…

1.8 The requirement will be met if the thermalperformances of the construction elements are noworse than those listed in Table 1

As well as lowering the required values, theApproved Document requires more rigorousmethods for calculating U-values, which take fullaccount of heat loss through repeating thermalbridges, such as spacers etc.

0.15 U-values should be calculated using themethods given in :

- for walls and roofs: BS EN ISO 6946.

The details of the BS EN ISO 69464 method aregiven in Appendix B of Approved Document L2however, it is made clear that this method does notapply to metal systems.

Appendix B: Calculation of U-values using theCombined Method

B4 The procedure in this appendix does not applyto elements containing metal connecting paths,for which the reader is directed to BRE IP 5/98for metal cladding, CAB and CWCT guidancefor curtain walls, and to BS EN ISO 10211-1and –2 for other cases

Section 3 describes how to calculate appropriateU-values using a number of analysis tools.

36 5

Exposed element U-value – W/m2K

Pitched roof with insulation between rafters 0.20

Pitched roof with insulation between joists 0.16

Flat roof or roof with integral insulation* 0.25

Walls, including basement walls 0.35+

Floors, including ground floors and basement floors 0.25

Windows, roof windows and personnel doors, (area weighted average for thewhole building), glazing in metal frames 2.2

Windows, roof windows and personnel doors, (area weighted average for thewhole building), glazing in wood or PVC frames 2.0

Rooflights 2.2

Vehicle access and similar large doors 0.7

Table 1: Standard U-values of construction elements

Fig A.5: Built up roof eaves

Fig A.6: Composite panel roof eaves

Summary : roof eavesRoof liner extends to touch the fmin = 0.76outer sheet or trim of wall, air �= 0.25 W/mKgap between wall and roof

5mm gap between roof liner fmin = 0.90and wall outer, air gap filed with �= 0.07 W/mKinsulation

Roof cladding liner taken back fmin = 0.95to wall liner, air gap filled with �= 0.01 W/mKinsulation as Fig A.5 or A.6

Detail 3 : Roof VergeThere are two possible thermal bridges in thissituation:

a) If the liner of the roof crosses the wall insulationto touch the outer sheet of the wall (or viceversa); the roof liner should be stopped levelwith the wall liner - see Figure A.7.

b) If a void is left between the roof and wallinsulation; this should be filled with site installedinsulation. - See Figure A.8.

Fig A.7: Built up roof verge

Fig A.8: Composite panel roof verge

Summary : roof vergesRoof cladding and liner cut fmin = 0.79across wall insulation (or vice versa) �= 0.28 W/mK

Roof cladding stops short of wall fmin = 0.85liner, void unfilled �= 0.20 W/mK

Roof cladding stops short of wall fmin = 0.95liner, void filled with site installed �= 0.02 W/mKinsulation as Figs A.7 and A.8.

Detail 4 : Valley GutterThis detail can cause a very severe thermal bridgeif the metal outer layer of the gutter top and roofliner cut across the gutter insulation.

Fig A.9: Valley gutter in built up roof

Page 8: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

2.3 Maximum areas of windows, doorsand rooflights1.12 Provision should be made to limit the rate ofheat loss through glazed elements of the building.One way of complying would be to limit the totalarea of windows, doors and rooflights so that theydo not exceed the values given in Table 2 - unlesscompensated for in some way.

Table 2: Maximum area of openings unlesscompensating measures are taken

Trade off between construction elements1.14 In order to provide greater design flexibility,the U-values of construction elements and theareas of windows, doors and rooflights may varyfrom the values given in Table 1 and Table 2provided that suitable compensating measures aretaken. If glazing areas are reduced from thosegiven in Table 2, special care needs to be given toconfirm that levels of daylight are adequate.Guidance on designing for daylight is contained inCIBSE LG10.

1.15 Compliance with provisions of Part L would beachieved if:

a) the rate of heat loss from the proposed buildingdoes not exceed that from a notional building ofthe same size and shape that meets the criteriaset out in Table 1 and 2; and

b) the U-value of any part of an element is noworse than the values given in the followingTable 3.

Table 3: Poorest U-value acceptable when tradingoff between elements

Notes: 1 Whilst parts of these elements may (withinthe limits given in this table) have poorer U-valuesthan those given in Table 1, it will not normally bepractical to make sufficient allowances elsewherein the design for the whole element to be built tothese standards.

1.16 As further constraints on these methodshowever,

a) if the U-value of the floor in the proposedbuilding is better than the performance given inTable 1 with no added insulation, the betterperformance standard is to be adopted for thenotional building; and

b) if the area of openings in the proposed buildingis less than the values shown in Table 2, theaverage U-value of the roof, wall or floor cannotexceed the appropriate value in Table 1 by morethan 0.02 W/m2K.

c) no more than half the allowable rooflight areacan be converted into an increased area ofwindows and doors.

2.4 Thermal bridging at junctions andaround openingsThe Approved Document requires that

1.9 The building fabric should be constructed sothat there are no significant thermal bridges orgaps in the insulation layer(s) within the variouselements of the fabric, at the joints betweenelements and at the edges of elements such asthose around window and door openings.

1.10 One way of demonstrating compliance wouldbe to utilise details and practice that have beenindependently demonstrated as being satisfactory.For domestic style construction a selection of suchsatisfactory details is given in the robustconstruction details publication.

6 35

Building Type

Industrial andstoragebuildings

Windows anddoors as % of

the area ofexposed wall

15

Rooflights as% of area of

roof

20

Element

Parts of roof 1

Parts of exposed wall or floor1

Poorest acceptableU-value (W/m2K)

0.35

0.70

similar in both twin skin and composite panelsystems. The diagrams in the sections belowtherefore represent both systems. So, for example,a twin skin corner is shown in Figure A.1 and acomposite panel corner is shown in Figure A.2. Inthe figures, the features particularly relevant tothermal bridging are marked with bold italics.

Fig A.1: Corner detail in built-up system

Fig A.2: Corner detail in composite panel

Detail 1 : Roof Ridge

Provided that the insulation is continuous over theridge (as shown in Figures A.3 and A.4) and thedetail contains no metal crossing the insulation,other than any spacers normally present in the roofpanels (which are taken into account in thecalculation of the plane area U-value) this detailcauses a negligible thermal bridge.

Fig A.3: Built-up roof ridge

Fig A.4: Composite panel roof ridge

Summary of roof ridgeInsulation continuous over the ridge fmin = 0.91

� = 0.01 W/mK

Detail 2 : Roof EavesPossible thermal bridging can result if the liner ofthe roof extends across the wall insulation to touchthe outer trim. A gap between the wall and roofpanels can introduce cold air directly to the liner.

Leaving a gap of only 5mm between the roof linerand the outside trim can give significantly betterperformance however, stopping the roof liner shortat the wall liner as shown in Figures A.5 and A.6,gives the best performance. Filling any gapbetween the wall and roof panels with anappropriate site applied insulation is also importantfor optimum performance.

Page 9: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

1.11 An alternative way of meeting therequirements would be to demonstrate bycalculation or by adopting robust design practicesthat the performance of the building fabric is atleast as good as it would be by following paragraph1.10. BRE IP 17/01 and the MCRMA TechnicalPaper No 14 illustrate how this can be done.

See section 2.5 for discussion of BRE IP 17/015.

Section 2 of the Approved Document containsrequirements for demonstrating the thermal qualityof the completed building.

2.1 To avoid excessive thermal bridging,appropriate design details and fixings should beused (see paragraph 1.9). Responsibility forachieving compliance with the requirements of PartL rests with persons carrying out the work. In thecase of new buildings, that “person” will usually be,e.g. a developer or main contractor who has carriedout the work subject to Part L, directly or byengaging a subcontractor. The person responsiblefor achieving compliance should (if suitablyqualified) provide a certificate or declaration thatthe provisions meet the requirements of Part L2(a)(i.e. limiting the losses and gains through the fabricof the building); or they should obtain a certificateor declaration to that effect from a suitably qualifiedperson. Such certificates or declarations wouldstate:

a) that appropriate design details and buildingtechniques have been used and that the workhas been carried out in ways that can beexpected to achieve reasonable conformity withthe specifications that have been approved forthe purposes of compliance with Part L2; or

b) that infra-red thermography inspections haveshown that the insulation is reasonablycontinuous over the whole visible envelope.BRE Report 176 gives guidance on the use ofthermography for building surveys.

Section 4 discusses methods of meeting thisrequirement and section 5 discusses methods ofcarrying out infra-red surveys.

2.5 BRE IP 17/01BRE IP 17/015 gives the requirements for limitingthe risk of surface condensation or mould growth atnon-repeating thermal bridges and describes howto assess their thermal performance and how toincorporate the additional heat loss with thatthrough the remaining building fabric. Theguidance is intended for thermal bridges that arenot as recommended in the guide to ‘domestic’robust construction details and forms the basis ofthe treatment of the details in this BRE/MCRMAguide. For these details, it requires:

a) the calculation of the minimum temperaturefactor, fmin, on the inside surface of the thermalbridge and imposes limits on this depending onthe use of building and whether condensation ormould growth is likely to be a problem;

b) the calculation of the transmission heat losscoefficient or �-value (pronounced ‘psi value’)associated with the thermal bridge and imposeslimits on the total heat loss through all thethermal bridges in the building as a proportion ofthe heat loss through the unbridged fabric (i.e.the heat loss that takes account of the U-valuesof the plane areas).

Methods of calculating fmin and � anddemonstrating compliance with the Regulations arediscussed in sections 4.2 and 4.3 respectively. Arange of metal cladding and roofing details, thatshould cover most buildings currently beingdesigned and constructed are shown in theAppendix, together with appropriate fmin and�-values.

2.6 Building air leakageThe Approved Document requires that:

1.17 Buildings should be reasonably airtight toavoid unnecessary space heating and coolingdemand and to enable the effective performance ofventilation systems.

1.19 A way of meeting the requirement would be toincorporate sealing measures to achieve theperformance standard given paragraph 2.4. Someways of achieving satisfactory airtightness include:

34 7

and roof. These have to achieve the samestandard if the building is to meet the Part Lcriterion on testing.

2) As has been emphasised, the leakage valuesabove have assumed that the cladding has beenproperly installed to current standards.Measurements quoted in CIBSE Guide TM23,have shown that many industrial buildings in theUK are very leaky and would fail if tested to thePart L standard. However well designed asystem is; it will fail and require expensiveretesting, possibly delaying the completion of acontract by many weeks, if it has not been wellinstalled. It is therefore essential that installationis carried out by experienced contractors, is wellsupervised and follows the claddingmanufacturer’s guidance.

6.8 Summary of methods for airleakage testing of metal roofing andcladding1. Pressurisation testing of whole buildings gives a

good estimate of their energy loss from airleakage in practice.

2. The contribution of individual areas of thebuilding envelope to the overall leakage can beidentified and quantified by the use of smoketubes, infra-red surveys and reductive sealing.

3. The leakage through individual cladding systemsand other components and the effect of sealingjoints etc. can be measured in laboratory tests.The results from these tests can be scaled up toquantify the leakage contribution of well installedcladding to the leakage of a full scale building.

4. Details currently in use and installed to a goodstandard may meet the air leakagerequirements of Part L; however it isrecommended that side and end laps/joints andall perimeter joints should be effectively sealed,not only to reduce the air leakage but also toprovide vapour control.

5. However well designed a system is: it will fail andrequire expensive retesting, possibly delaying thecompletion of a contract by many weeks, if it hasnot been well installed. It is therefore essentialthat installation is carried out by experiencedcontractors, is well supervised and follows thecladding manufacturer’s guidance.

The following pages present some common detailsthat occur in industrial and commercial buildingswith metal cladding which are likely to lead tothermal bridges that affect the internal surfacetemperature and heat loss from the building. Theirlocations are shown on Figure 24. For each detail,the following information is presented:

1) A brief description of the detail and the possiblecauses of thermal bridging;

2) A diagram of a typical detail, with the importantfeatures that are likely to lead to thermal bridgeshighlighted.

3) The fmin and �-values of the standard detail thatdetermine its performance, calculated with Uwall

= 0.35 W/m2K and Uroof = 0.25 W/m2K.

4) In those cases where the usual detail is likely tolead to problems of low surface temperatures(low fmin-value) or high heat flow (high �-value),a range of modifications that might be made toimprove performance are discussed and theresulting fmin and �-values presented.

The diagrams are only intended to be indicativeand concentrate on thermal bridging issues. The fmin

and �-values quoted are typical of each detail;slightly different values may be calculated for aspecific system. Cladding manufacturers’ details fortheir specific systems should be used for design,provided that a cladding design on a particularbuilding adopts the same principles regardingthermal bridging, which are outlined in thediagrams and text. This Appendix should be readin conjunction with Section 4, which explains thesignificance of the f-value and the �-value, andhow to decide on appropriately detailed designs fora particular building.

The f-values and �-values shown in the sectionsbelow can be used directly by manufacturers anddesigners to demonstrate compliance with therequirements of Part L as shown in sections 4.2and 4.3 of this Technical Paper and in BREInformation Paper IP 17/01. The features thatcause thermal bridging at junctions, openings andother penetrations of the insulation are generally

Appendix : Details

Page 10: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

a) providing a reasonably continuous air barrier incontact with the insulation layer over the wholethermal envelope (including separating walls).Special care should be taken at junctionsbetween elements and around doors andwindows openings. For domestic typeconstructions, some satisfactory design detailsand installation practice are described in therobust details publication. Guidance for thedesign of metal cladding and roofing systems tominimise air infiltration is given in the MCRMATechnical Paper No 14.

b) Sealing gaps around service penetrations.

c) Draught-proofing external doors and windows.

Section 2 of the Approved Document containsrequirements for demonstrating that the completedbuilding has achieved a good standard ofairtightness and establishes a performancestandard:

2.2 Air barriers should be installed to minimise theadverse effects of air infiltration (see paragraph1.19). In this case too, certificates or declarationsshould be provided or obtained by the personscarrying out the work, stating:

a) for buildings of any size, that the results of airleakage tests carried out in accordance withCIBSE TM23 are satisfactory; or

b) alternatively for buildings of less than 1000m2

gross floor area, that appropriate design detailsand building techniques have been used, andthat the work has been carried out in ways thatcan be expected to achieve reasonableconformity with the specifications that have beenapproved for the purposes of compliance withPart L2.

2.3 Certificates or declarations such as thosementioned in paragraphs 2.1 and 2.2 may beaccepted by building control bodies as evidence ofcompliance. The building control body will however,wish to establish, in advance of the work, that theperson who will be giving the certificates ordeclarations is suitably qualified.

2.4 If using the CIBSE TM 23 pressure proceduresas the means of showing compliance:-

a) With effect from 1 October 2003, reasonableprovision would be test results showing that theair permeability (see paragraph 0.20) does notexceed 10 m3/h/m2 at an applied pressuredifference of 50 Pa.

b) In the period up to and 30 September 2003,reasonable provision in the event that initial testresults are unsatisfactory would be the results offurther tests carried out after appropriateremedial work showing:-

i) An improvement of 75% of the differencebetween the initial test result and the targetstandard of 10 m3/h/m2 at 50 Pa, OR, if lessdemanding

ii) A performance no worse than 11.5 m3/h/m2 at50 Pa.

Section 6 discusses methods of meeting thisrequirement.

8 33

6.7 Example of the effect of individualjoint leakage on whole claddingleakageTo illustrate the method of combining individual jointleakages to give the overall leakage from thecladding system, Figure 38 shows the building thatwas used to illustrate heat loss through thermalbridges in section 4.5. It is assumed that the wallsare covered with horizontal composite panels eachone metre wide by five metres long and the roof iscovered in a site assembled system with linersheets of the same size.

Fig 38: Typical industrial building showing leakagepaths at joints

Table 11 shows the length of each joint in theexternal envelope and the leakage characteristicsfor a standard construction and one upgraded withadditional seals. It should be noted that, at many ofthe details, for example the ridge and valley gutter,two sheets/panels meet; the length of joint will

therefore be twice the length of the detail. Theleakage values for each joint are based, as far aspossible, on the values measured in the BRE testsdiscussed in section 6.6; it should be recognisedhowever, that appreciably higher values may befound in practice.

Setting the leakage rates out like this readilyidentifies the contribution of individual leakagepaths facilitating the development of an appropriatereduction strategy, if necessary.

The exposed area of the building envelope, whichincludes the ground floor, is 6044 m2. This meansthat the air permeability for the cladding part of thenotional building is 2.68 m3/h/m2 at 50 Pa. Thisreduces to 0.23 m3/h/m2 at 50 Pa for the improvedbuilding. Both of these are well within the limit of10 m3/h/m2 at 50 Pa, imposed by ApprovedDocument L2. This suggests that metal claddingwhen properly installed to current standards,may be able to meet the requirements of Part L ofthe Regulations. It is however, important toemphasise two considerations here:

1) This calculation has assessed only the loss fromthe cladding, not the loss from the other parts ofthe building, such as blockwork walls at groundlevel and all the various penetrations of the walls

1995 standard Improved

Lengthm

Leakagem3/h/m @ 50 Pa

Total leakagem3/h at 50Pa

Leakagem3/h/m @ 50 Pa

Total leakagem3/hr @ 50Pa

12345

67891011

WallsBase perimeterSide jointTop perimeterEnd jointCorners

RoofEavesVergeRidgeValley gutterEnd lapsSide lapsTotal

200100020043248

12080.3240120480

2360

11.70.50.31.611.7

8.610.48.68.62.52.5

234050060691562

1032835

2064103212005900

16216

0.70.10.10.60.7

1.10.21.11.10.10.1

1401002025934132

1626413248236

1381

Table11:Contribution of individual joints to leakage from the cladding

Page 11: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

3.1 The development of U-valuecalculation methodsThe standard measure for calculating the heat lossthrough the building fabric is the U-value. Thisconcept, which has been in use for many years,applies to plane areas of the walls or roofs anddoes not take account of any extra heat loss at thejunctions between elements or around window andother openings, known as thermal bridges.

Until 1995, the Approved Document required thatall U-values were calculated by assuming thatconstructions could be represented by a series ofuniform layers as shown in Figure 1.

Fig 1: Construction made up of uniform layers

Fig 2: Temperature and heat flow through uniformconstruction

Figure 2 shows the temperature distribution fromwarm (red) to cold (blue) and heat flow lines withina uniform construction. In this case the heat flow ispurely one dimensional and the U-value is easilydefined as the reciprocal of the sum of the thermalresistances of the layers making up the structureand the internal and external surface resistances.So for a wall or roof containing n parallel layers:

Where Rso is the external surface resistance inm2K/W

Ri is the thermal resistance of the ith

layer in m2K/W

Rsi is the internal surface resistance inm2K/W.

Standardised values of the surface resistances arequoted in BS EN ISO 69464 Table 2, and CIBSEGuide A3

6, section 3.3.9 (See Table 4).

Table 4: Surface resistances in m2K/W

The thermal resistance of a material, R, dependson its thickness and thermal conductivity

R = d / � m2K/W (2)

Where: d is the thickness of the material in m;

� is the thermal conductivity in W/(mK).

Thermal conductivity values are tabulated in theCIBSE Guide A.36 Appendix 3.A7 and in BS EN12524 : 20007

Table 5 summarises typical values of some of themore important materials that are used in metalclad buildings. Conductivity values can vary andthe Approved Document allows the use of properlydocumented manufacturer’s values.

Table 5: Thermal conductivities of typical materials

32 9

Methods for calculating heatloss through plane areas ofcladding and roofing systems

Rsi

Rso

Upwards

0.10

0.04

Horizontal

0.13

0.04

Downwards

0.17

0.04

Direction of heat flow

MaterialMetalsSteelStainless steelAluminiumCopper

Other materialsTimberPVCPolyester resinPolycarbonate

InsulantsGlass fibreMineral woolExpanded polystyreneUrethane

Conductivity W/mK

6017160380

0.140.170.200.20

0.0400.0370.0350.022

Table 9: Results from pressurisation tests of siteassembled system

Fig 36: Areas of built up panel tested for airleakage

The results from this type of test can then be usedto assess the effect on leakage from a wholebuilding - see section 6.7.

6.6.3 Composite panel

Two flat composite panels wall constructions weretested:

a) Standard panels designed to achieve the 1995Approved Document L U-value of 0.45 W/m2K

This was made up of standard factory madepanels with profiled liner and outer sheets,containing 50mm of rigid urethane insulation.The panel to panel side joints had standardfactory installed compressible seals, the verticalperimeter and upper horizontal junctioncontained butyl seals. The lower horizontalperimeter was sealed with a butyl tape trapped

between the panels and lower horizontal rail, butlight could be seen from the outside indicatingthat the seal was not completely effective.

b) Sealed panel to achieve the proposed U-valueof 0.30 W/m2K

This was made up of standard factory madepanels with profiled liner and outer sheets,containing 80mm of rigid urethane insulation.The panel junctions, vertical perimeter andupper and lower horizontal junctions allincorporated additional sealing.

The effect on infiltration of sealing the four possibleleakage paths, shown in Figure 37, wasinvestigated.

In this case the dominant leakage path was thehorizontal gap at the base of the panel. Sealingthis eliminated 90% of the infiltration.

Table10: Results of pressurisation testing ofcomposite panels.

Fig 37: Areas of composite panel tested for airleakage

Description(see figure below)

Currentstandard

Improved

(1)Panel seam

(2)Lower horizontalperimeter junction

(3)Upper horizontalperimeter junction

(4)Vertical perimeterjunction

0.5

11.7

1.6

0.3

0.1

0.7

0.6

0.1

Air leakage at 50Pa[m3/h per linear meter]

Description(see figure below)

Currentstandard

Improved

(1)Liner sheetoverlaps

(2)Upper & lowerhorizontalperimeterjunctions

(3)Vertical perimeter

junctions

2.3

8.6

10.4

less than 0.1

1.1

less than 0.1

Air leakage at 50Pa[m3/h per linear meter]

Page 12: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

Metal cladding and roofing systems are made ofcombinations of materials, which differ in thermalconductivity by factors of over a thousand, in closeproximity. This has important consequences for themethods of calculating U-values.

By the early 1990s, it was recognised that manyconstructions contained details, such as mortarjoints in lightweight block work or timber studs inthe insulation of timber framed walls in whichincreased heat flow is caused by higherconductivity elements crossing insulation. The1995 revision to Approved Document L thereforerequired that these features, which are known asrepeated thermal bridges, be taken into accountwith the ‘proportional area method’. This assumesthat heat flow is still one dimensional through thewall or roof, but that the flow is locally higherthrough the bridging elements. For example,Figure 3 shows the temperature and heat flowthrough 100mm of mineral wool bridged by a40mm wide timber stud. It can be seen that,although there is some distortion of the heat flowand temperature fields at the edges of the stud, theflow is generally one-dimensional, with higher flowdensity through the stud at the centre of thepicture.

Fig 3: Temperature and heat flow through aninsulation layer bridged with a timber stud

The total heat flow and therefore the U-value arecalculated by adding the contributions of eachelement in proportion to their contribution to thetotal area. The thermal resistance of each layer ofthe construction that contains repeated thermalbridges is calculated from:

Where Fbr is the fraction of the wall area occupiedby the repeating thermal bridges

Rbr is the thermal resistance of therepeating thermal bridges in m2K/W.

Rnb is the thermal resistance of theremaining unbridged wall in m2K/W.

The individual layer thermal resistances are thenadded up as before to calculate the U-value withequation (1). This method assumes that there is nosideways flow of heat between the unbridged andbridged elements and therefore tends tooverestimate the thermal resistance andunderestimate the U-value.

This procedure assumes that, as shown in Figure3, a) the repeating thermal bridges are reasonablylarge, occupying say 10% of the wall area and b)the conductivity of the bridge is not very differentfrom the insulation; for example, the conductivity oftimber is only four times that of mineral wool.Metal roofs and cladding systems, on the otherhand, a) contain details in which the insulation isbridged by thin steel elements, such as zedspacers in a profiled metal roof, which occupy only0.1% of the area and have conductivities over athousand times higher than the insulation, and b)have profiled liner and outer sheets. Both of thesefactors cause distortions to the heat flow largeenough to make the proportional area method veryinaccurate. These lead to temperature and heatflow distributions like those shown in Figure 4, asection through a steel zed-spacer whichpenetrates 120mm of mineral wool. It is evidentthat heat flow is very far from one-dimensional inthis case.

It was recognised, therefore, even before the 1995Approved Document was available, that specialtechniques were needed for metal roofs andcladdings. The MCRMA and BRE collaborated ina computer modelling exercise to produce anInformation Paper IP 5/988, which gives morerealistic U-values than the proportional area orcombined methods for some metal claddingsystems.

10 31

V = 15444 m3. The ventilation rate, n, will be 0.28ach. Substituting these values into Equation (18)gives: Qleakage = 1502 W/K

The total fabric loss estimate in section 4.5 was2361 W/K, giving a total loss of 3863 W/K, 61% ofwhich is through the fabric and 39% by air leakage.

6.5 Laboratory tests for individualcomponents Individual components, a window in its frame or aspecific area of a liner sheet, with representativelaps, for example, can be tested in the laboratorywith the methods specified in BS EN 12114:200017.This involves sealing the component into a rigid airtight frame and measuring the flow rate resultingfrom a series of positive or negative pressuredifferences applied across it (Figure 35).

Fig 35: Diagram of laboratory air tightness apparatus

This test can provide values of a parameter that isuseful for characterising metal cladding and roofingsystems, the leakage per linear meter of joint orside lap, R50,j. This is derived by identifying the flowthrough an individual joint (Q50,j) by reductivesealing and then dividing by the length of jointunder test (lj).

R50,j = Q50,j /lj (19)

Once this is known for each type of joint in abuilding, the building leakage rate Q50 can beestimated from :

Where Lj is the total length of each type of joint inthe building. Section 6.6.2 gives an example ofusing the results from small scale tests to estimatethe air leakage from a building and the effect ofproviding additional seals.

6.6 Examples of testing carried out atBRE6.6.1 Test methodIn parallel with the infra-red surveys, described insection 5, BRE has been carrying out a series ofpressurisation tests on different metal claddingsystems at East Kilbride. Each cladding systemwas sealed into the PASSYS test cell anddepressurised as described above. A series ofrepeat tests was then carried out with varioussealing options to identify the contributions ofindividual joints. Two site assembled profiled metalwall constructions and two metal faced compositepanel wall constructions were tested.

6.6.2 Site assembled systemsThe two systems tested were:

a) Twin skin wall of typical construction intended toachieve the 1995 Approved Document L U-value of0.45 W/m2K

This was made up of profiled liner and outersheets, containing 83mm of glass wool insulationand a rail and bracket spacer system. The linerside laps and the liner vertical perimeter were notsealed. Liner fillers were included in the top andbottom horizontal perimeter and there wereapproximately four fasteners/metre, as is typicallyused at these points. There were no seals or fillersto the outer sheets.

b) Twin skin wall intended to achieve the originallyproposed U value of 0.30 W/m2K and achieve theair tightness requirements of Approved DocumentL2 :2001.

This was made up of profiled liner and outersheets, containing 135mm of glass wool insulationand rail and bracket spacer system. The liner sidelaps and the liner vertical perimeter were sealedwith butyl tape. Liner fillers were included in thehorizontal perimeter, as before, but withapproximately ten fasteners/metre to improve thecompression of the fillers. There were no seals orfillers to the outer sheets.

The effect of sealing the three possible leakagepaths shown on Figure 36 on the leakage wasinvestigated.

Page 13: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

Fig 4: Distortion of temperature and heat flowcaused by zed spacer

The 2001 revision to the Approved Document hasintroduced a more rigorous method of dealing withrepeated thermal bridges, which is given in BS ENISO 69464. This standard deals with repeatedthermal bridges using the more complex ‘combinedmethod’, which is specified in more detail in CIBSEGuide A36 and in Appendix B of ApprovedDocument L22. This method carries out twocalculations assuming a) no sideways flow of heatbetween the insulation and bridging elements,which gives a maximum thermal resistance and b)unlimited sideways flow of heat, which gives aminimum resistance. The U-value is then taken asthe reciprocal of the average of these tworesistances. However both the British Standardand Appendix B of the Approved Document make itclear that this method does not apply to metal roofand wall cladding systems.

3.2 Computer modelling 3.2.1 PrinciplesClause B.4 of Approved Document L2, which statesthat the Combined Method for calculated U-valuesdoes not apply to elements containing metalconnecting paths, directs users to BRE IP 5/988 formetal cladding and to BS EN ISO 10211-19 and BSEN ISO 10211-210 for more general cases. Allthese methods are based on two- and three-dimensional modelling of temperatures and heatflows through construction details using a range ofsoftware packages.

The thermal models, that are standardised in BSEN ISO 10211-1, divide the construction to beanalysed into a number of homogenous materialblocks and then impose a two- or three-dimensional

grid over all. Figure 5 shows an example of a two-dimensional grid imposed on a twin skin systemwith a typical rail and bracket spacer detail.

Fig 5: Grid definition for spacer detail

After internal and external temperatures and heattransfer coefficients have been defined, the modelcarries out a series of approximations of increasingaccuracy to calculate the temperatures and heatflows at each of the nodes where the grid linesintersect. The total heat flow, which allows the U-value and temperatures at any specific points ofinterest such as the internal surface to becalculated, can then be displayed.

These models assume steady state internal andexternal conditions and that the material properties,such as thermal conductivity, are unaffected bychanges in temperature. If the model is to provideaccurate results it is essential that:

a) the model is extended away from the thermalbridge either into regions where the heat flow isunaffected by the presence of the bridge or to aline of symmetry between thermal bridges;

b) the grid, which defines the nodes, isappropriately specified, especially in areaswhere materials with very different thermalconductivities are in close contact.

BS EN ISO 10211-1 gives guidelines for both ofthese factors however, appropriate grid definitioncan be difficult, requiring considerable experience,especially in the case of metal roofing andcladding, which a) can contain metal spacers whichare small compared to the extent of the roof and b)has metal and insulation materials directly incontact. Incorrect grid definition can lead to errorsof 10 –20% in the calculated U-value.

30 11

used in parallel to provide more information:

Releasing smoke from smoke pencils or pufferswithin a building that is being pressurised can beused to visualise and identify specific flow paths.

An internal infra-red survey (see Figure 26) of adepressurised building in cold weather willrapidly reveal areas that are being chilled byincoming air.

Repeated testing of a building as successivespecific components are sealed, a techniqueknown as reductive sealing, can quantify thecontribution of each. For example, Figure 34shows the results from an initial test of a buildingas found, which gives a Q50 value of 13.8 m3s-1;sealing around all the window frames with tapeand repeating the test reduces this to 10.5 m3s-1,then sealing around all the doors as well,reduces Q50 further to 7.6 m3s-1.

The air leakage associated with a specificbuilding element or component can be testeddirectly by pressurisation. The component canbe isolated by containing the area of interestwithin a temporary sealed compartment; this hasthe advantage of requiring a smaller fan than isneeded for reductive sealing of a whole building.This method is further refined by the laboratorytest method described in BS EN 12114:2000 -see 6.4.

Fig 34: Results from an ‘as found’ test and twosuccessive stages of reductive sealing

6.3 Air leakage parametersTwo parameters are currently used to quantify theair leakage rate through the building envelope.These are the air leakage index and the airpermeability. Both are measured by the fanpressurisation technique and are expressed in termsof the volume flow of air per hour (m3 h-1) supplied tothe space, per square metre (m2) of buildingenvelope for a specified inside to outside pressuredifference of 50Pa; for example 10 m3h-1m-2 at 50Pa.

The two parameters differ in the way the externalbuilding envelope is defined. The air leakage indexdoes not include the solid ground floor area, whilethe air permeability does include the solid groundfloor. It is not possible to standardise on one airleakage parameter at present, because a)European Standard BS EN 13829 : 200116 andApproved Document L use air permeability and b)the historical database of air leakagecharacteristics that may be used to put a buildinginto context is based on air leakage index. Thechoice of which parameter to use is thereforedependant on the context of use however, forRegulation purposes the air permeability is theessential parameter, i.e. the floor area is taken intoaccount.

6.4 Heat loss due to air leakageThe heat loss from a building due to air infiltrationis given by:

Qleakage = �Cp.V.n / 3600 W/K (18)

Where �Cp is the heat capacity of the air

V is the building volume in m3

n is the ventilation rate in air changesper hour (ach)

As shown in section 6.4.2, if a building is testedand just complies with the standard of 10 m3/h/m2

at 50 Pa specified in section 2.4 of ApprovedDocument L, the average ventilation rate undertypical wind conditions can then be approximatelyestimated as A/(6 x S) ach.

In the case of the notional building discussed insection 4.5 : S = 3644 m2, A = 6044 m2 and

Page 14: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

3.2.2 Two-dimensional modellingMany metal wall and roofing systems (for examplethe zed-spacer roof shown in Figure 6) containlinear features, such as zed-spacers or spacer railsand liner and outer sheet profiles that, althoughthey run at right angles to each other, interact verylittle. They can therefore be modelled individually intwo dimensions as shown in Figures 7, 8 and 9 andthe results combined to give a realistic U-value ofthe structure. Note that as the models deal withrectangular elements, the inner and outer profileshave been approximated as a series of steps, thisintroduces a negligible error.

Fig 6: Roof with profiles and zed spacers at rightangles

Fig 7: Distortion of temperature and heat flowcaused by zed spacer

Fig 8: Distortion of temperature and heat flowcaused by liner profile

Fig 9: Distortion of temperature and heat flowcaused by outer profile

BRE IP 5/98, describes procedures for determiningthermal performance of some types of insulateddouble-skin metal roof and wall systems commonlyin use in the UK. The procedures, which takeaccount of the thermal bridging caused by thevarious metal connecting paths between the innerliner and outer sheet, are more realistic than othersimplified methods and provide a reasonablyaccurate assessment of the thermal performanceof such a system.

The two-dimensional computer package KOBRU,which is fully compatible with BS EN ISO 10211-1,was used to calculate the U-value of three differentrail and bracket spacer and z-spacer roofs a) with a25mm air gap between the spacer and the liner, b)with 25mm of insulation between the spacer andthe liner and c) with 50mm of insulation betweenthe spacer and the liner. The results revealed thatthe rail and bracket spacer had little effect on thethermal performance and could be ignoredprovided that the brackets are at least a metreapart. For the zed spacers, the U-value wascalculated as a function of insulation thickness,spacer centres and insulation conductivity and theIP includes graphs from which the U-value can beread for any combination of these parameters. ThisU-value can then be corrected for the effect of anycontinuous air spaces above the insulation and theeffect of the liner profiles intermittently compressingthe insulation.

12 29

During a test, all internal doors should be wedgedopen and, where appropriate, combustionappliances must be switched off and any openflues and air supply openings temporarily sealed.Flues from room-sealed appliances, such asbalanced flues in domestic appliances, do not needto be sealed. External doors and other purpose-made openings in the building envelope should beclosed and mechanical ventilation systems turnedoff, with the inlet and outlet grilles sealed. Firedampers and ventilation louvres should be closed.Drainage traps should contain water.

6.2.2 Data AnalysisThe data obtained from a fan pressurisation testconsist of volume flow rates, which need to becorrected for the difference between the density ofwarmer, indoor and colder, outdoor air, for a rangeof internal/external pressure difference values. Aplot of the volume flow rate (Q) versus pressuredifference (Dp) is drawn (Figure 33). The points lieon a curve, called the air leakage characteristiccurve of the building.

Fig 33: Typical results from pressurisation anddepressurisation tests

The relationship between the fan flow rate, andtherefore the air leakage of the building, and thepressure difference is of the form:

Q = C (�p)n (15)

Where C and n are constants that relate to thebuilding under test that can be found bytransforming equation (15) using natural logarithmsto give:

ln(Q) = ln(C) + n.ln(�p) (16)

Plotting ln(Q) against ln(�p) gives a straight linewith slope n and intercept ln(C). C and n are thenused to calculate the conventional value of the flowrate at a pressure difference of 50 Pa:Q50 = C(50)n.This, Q50, normally in m3/h, is reported as theparameter which defines the ‘leakiness’ of thebuilding.

Under very calm conditions, when all the measuredpoints lie close to one curve, Q50 may be estimateddirectly from the measured data; in more windyconditions when there will be considerably morescatter about the curve it is essential to derive Q50

from the values of C and n calculated from thefitted curve. The standard pressure difference of 50Pa is chosen, as it is much greater than the normalwind and stack pressure differences, which are 5 –10 Pa at most. However, this means that the Q50

value does not reflect the air infiltration into abuilding in practice. Comparison of pressurisationtest and tracer gas measurement in buildings hasshown that the following general rule can be usedfor office buildings, the average ventilation rate inair changes per hour is equal to Q50/(S x 60), whereS is the surface area of the walls and roof. As nosimilar comparison has been made for industrialbuildings, this relationship should be regarded as,at best, a very rough approximation.

If a building is tested and just complies with thestandard of 10 m3/h/m2 at 50 Pa specified insection 2.4 of Approved Document L, the total flowrate at 50 Pa, Q50, will be 10 x A m3/h, where A isthe area of walls, roof and floor. Substituting thisfor Q50 in the above expression means that theaverage ventilation rate under typical windconditions can then be estimated as A/(6 x S) airchanges per hour. This can then be used toassess the heat loss due to air leakage as shownin section 6.4.

6.2.3 Location of air leakage The cladding or roofing system is only one of thepossible leakage routes from a building and asimple fan pressurisation test quantifies the total airleakage of a building, but does not directly identifythe leakage paths. There are however, a number ofqualitative and quantitative methods that can be

Page 15: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

3.2.3 Three-dimensional modellingBRE IP 5/98 and KOBRU provide realistic methodsfor calculating U-values for those constructions,such as zed-spacers or rails, which contain linearfeatures that can be fully represented as individualor combined two-dimensional cross sections.Some constructions however, contain structuralelements such as aluminium clips that recurregularly both up and across a roof, and causelocal, relatively severe thermal bridging. These haveto be analysed with a full three-dimensional model,which generally has to be individually developed foreach case, a difficult and time consuming processfor a complex detail.

A number of software packages are available thatcan carry out three-dimensional analysis. BREuses a package called TRISCO, which is fullycompatible with BS EN ISO 10211-1 and thereforemeets the requirements of Approved Document L2.

3.3 Theory3.3.1 Calculation of effective U-valuesTo provide an effective U-value of the structure,taking account of the effect of the repeated thermalbridging caused by the spacers etc., a two-dimensional model must extend between the linesof symmetry on either side of a spacer, i.e. if thespacers are at 1800mm centres, the model mustbe 1800mm wide, see Figure 10.

Fig 10:The necessary extent of a 2D model tocalculate effective U-values

Similarly, a three-dimensional model should beextended to the points of symmetry between thespacers in both the dimensions in the plane of thewall or roof.

With inputs of appropriate internal and externaltemperatures and surface resistances (see Table4), a two-dimensional model will output Q2D, thetotal heat flow between inside and outside in W/m;a three-dimensional model will output Q3D in total

heat flow in W. The effective U-value will then becalculated from:

Where : L is the width of the 2D model in m (1.8in the example shown in Figure 10).

A is the area of the 3D model in m2.

Ti and Te are the internal and externaltemperatures in ˚C.

The model will also produce the internal surfacetemperatures necessary to determine the risk ofsurface condensation, see section 4. Also, theinternal surface temperature at the edge of themodel remote from the effect of the spacer etc., Tsi,can be used to calculate the unbridged U-value ofthe structure.

Where : Rsi is the internal surface resistance inm2K/W

3.3.2 Combining two-dimensional calculations3.3.2.1 Combination of a flat liner, a spacer anda profiled outerDevelop two 2D models:

1. A model of the spacer system with flat liner andouter sheets. This will include the specifiedinsulation thickness and any air gap between theouter sheet and the insulation and gives anoverall effective U-value = Uspacer.

2. A model with a flat liner, the specified insulationand air gap as above and a profiled outer sheet.This will give an overall effective U-value = Uouter1

and an unbridged U-value = Uouter2

The combined U-value Ucomb is then calculated asshown below.

28 13

reduced to give approximately equally spacedvalues (ideally between 5 and 10) of pressuredifference, with none lower than 10 Pa, and thereadings repeated at each point

The equipment can vary from a simple fanmounted in a replacement door and powered fromthe building’s electrical supply (Figure 31) thatdelivers up to 1 m3s-1 and is suitable for small‘domestic sized’ buildings, up to large externallymounted fans that have their own power supplyand can supply up to 30 m3s-1 (Figure 32) ; theseare used to test large non-domestic buildings. Insome cases it may be possible to use the building’sown HVAC system air supply fans. The pressuredifference is measured with a micromanometer withan operating range of at least 0 – 60 Pa andaccuracy of ±2 Pa. The external pressure shouldbe measured at a point at least 10m away from thebuilding to minimise local wind effects. The internalpressure must be measured at a point away fromthe direct influence of the pressurisation fan.

Fig 30: Diagrammatic representation of wholebuilding leakage test

Fig 31: Typical ‘Blower Door’ for testing domesticbuildings

Fig 32: Large fan for testing industrial buildings

A pressure test relies on the assumption that thepressure difference is uniform over the entirebuilding envelope. This imposes certain restrictionson the external climate parameters that prevailduring the test. Ideally the internal to externaltemperature difference should be less than 10˚Cand the wind speed should be less than 3 ms-1.Higher temperature differences lead to high stackpressure differences that distort the test results,especially in very tall buildings, and high windspeeds cause random pressure differences, whichmake accurate readings difficult. These conditionsare however, much less restricting than thosenecessary for infra-red surveys described in section5.2.

Page 16: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

3.3.2.2 Combination of a profiled liner, a spacerand a profiled outerTo assess the combined effect of the spacer andthe profiled liner and outer sheets, the followingsteps are necessary:

1) Develop two 2D models with a) a flat liner andprofiled outer giving Uouter and b) flat outer andprofiled liner giving Uliner

2) Calculate the total U-value of a combination ofthe liner and outer profile:

Where Ucomb1 is the combined U-value in W/m2K

Uliner is the U-value of the liner profilefrom KOBRU in W/m2K

Uouter is the U-value of the outer profilefrom KOBRU in W/m2K

Rsi and Rse are the inside and outsidethermal resistances in m2K/W

t is the thickness of the insulation in m

k is the thermal conductivity of theinsulation in W/mK

3) Calculate the insulation thickness neededbetween flat faces to give the same U-value thatresulted from the combined inner and outerprofiles i.e. Ucomb.

4) Use a liner profile calculation with the insulationthickness equal to the distance between the linerand spacer to calculate Uliner 2 and use this tocalculate the equivalent thickness of insulationunder the spacer

Fig 11: Calculation of the equivalent thickness ofinsulation under the spacer

5) Insert the two thicknesses derived in 4) and 5)into a 2D model of, for example, a zed spacerroof as shown in Figure 12, giving the bridgedU-value Ucomb2

Fig 12: The equivalent insulation thicknesses in thespacer model

3.3.3 Additional heat loss through repeatingpoint componentsSome features which pass through the insulation,such as the brackets in rail and bracket roofs orfasteners, can increase the heat loss through a roofor cladding. Once the additional heat loss throughan individual bracket or fastner Qadd W/˚C has beencalculated, (using three dimensional modelling), theeffect on the U-value may be calculated from�U = Qadd/nadd , where nadd is the number of suchfeatures/square metre of roof or wall surface.

For example, if a roof with U-value 0.25 W/m2K ispenetrated by 5.5 mm diameter stainless steelfasteners, with Qadd = 0.006 W/˚C, with 1.11fasteners/m2, �U will be 0.007 W/m2K. If steelfasteners with Qadd = 0.014 W/˚C were used, �Uwould be 0.015 W/m2K

3.4 Examples Example 1: A twin skinned roof with zed-spacers that can be assessed by combiningtwo-dimensional modelsThe roof is similar to that shown in Figure 6 with1.6mm steel zed spacers at 1800mm centres. Thespace between the inner and outer sheets is filled

14 27

circulation of cooler air entering the test roomthrough open door.

Fig 29: Twin skin constructionRemoving a 100 x 300 mm piece of insulationleaves a well defined cold area. The bright yellowarea, adjacent to the darker region representing themissing insulation, and the red area on the centralrail are due to the reflection of the inspection lamp.

5.4 Summary of the use of infra-redsurveys1. Infra-red surveys of the envelope of a building

should preferably be done from the inside andideally require calm, dry, cold and cloudyconditions; there may therefore be a considerabledelay before conditions are suitable. Theconditions for external surveys are even morerestrictive.

2. For a survey to be successful, the buildingshould be heated for at least 12 hours before thesurvey, there should be no sun and no rain onthe external surface.

3. Given the right conditions, infra-red surveys canprovide useful qualitative information aboutthermal bridges, air leakage and missing or wetinsulation.

4. The presence of metal components, withemissivities much lower that those of otherbuilding materials, can lead to confusing resultswhich need careful interpretation.

5. The interpretation of infra-red surveys issubjective,requiring experienced staff with aknowledge of metal cladding systems. This maylead to disputes concerning whether an apparentdefect is significant or not.

6. Rather than relying on thermal imaging, with thecomplications and ambiguities summarisedabove, it is preferable to rely on demonstratingsatisfactory design and installation.

6.1 Introduction As buildings become more highly insulated, theeffect of air leakage through the envelope onenergy consumption becomes relatively moreimportant. The new version of Approved DocumentL2 lays more stress on the need to achieve areasonable standard of airtightness, and makessuggestions as to how this might be achieved byappropriate sealing measures. It also suggests thatit may be necessary to demonstrate compliancewith a report from a ‘competent person’ thatappropriate design details and building techniqueshave been used or, for buildings larger than 1000m2

floor area, to carry out an air leakage test.

This section describes the background to airleakage testing and the factors that affect theresults in the case of metal walls and/or roofs. It ishowever, important to remember that the claddingsystem is only one of the areas of the buildingenvelope that contribute to the leakage. Junctionsand openings such as doors, loading bays,windows, rooflights, smoke vents and servicepenetrations may be more important. This sectionwill enable the manufacturers of cladding andassociated components to demonstrate that theirsystems or components are capable of beinginstalled to a specified standard of airtightness

6.2 Whole building testing of airleakage6.2.1 Test methodTechniques for the testing and analysis of the airleakage of buildings are described fully in CIBSEGuide TM23, which should be consulted fordetailed information15.

An air leakage test is carried out by mounting a fan(or fans) in a suitable aperture within the buildingenvelope, usually a doorway (Figure 30); runningthe fan to blow air into the building creates apressure difference across the building envelope.The fan speed is increased slowly to create apressure difference of about 50 Pa (1Pa = 1N/m2).At this setting the air volume flow through the fan,i.e. the air leakage through the building envelopeand the pressure difference across the buildingenvelope, is recorded. The fan’s speed is then

Air tightness

Page 17: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

with 120mm of mineral wool, with conductivity 0.04W/mK, and there is 25mm of insulation betweenthe liner and the zed-spacer. The outer profiles are35mm deep, at 170mm centres and the linerprofiles are 18mm deep, at 200mm centres.

The U-value of this system can be calculated byvarious methods:

a) Ignoring thermal bridging:In the absence of any bridging from the zedspacer or the profiles, the U-value of the roofwould be 0.32 W/m2K.

b) BRE IP 5/98Graph 5 on page 6 of BRE IP 5/98 gives U =0.36 W/m2K if the profiles are ignoredEquation 3 on page 4 of the IP, gives acorrection of 7 mm for the effect of the linerprofiles compressing the insulation, changingthe insulation thickness to 113mm, graph 5 thengives U=0.38 W/m2K.

c) Combination of two-dimensional modelsFollowing the steps specified in section 3.3.3.2

1) Uliner = 0.34, Uouter = 0.31.2) Rsi + Rse = 0.14, t= 0.12 and k = 0.04 giving Ucomb

= 0.330.3) Th = 0.115 m4) th = 0.0147 m.5) U = 0.40 W/m2K

Therefore ignoring thermal bridging completelyunderestimates the U-value by about 20% andusing IP 5/98 underestimates it by 5%.

Example 2: A composite panel fully filled withinsulationFigure 13 shows a representative section of acladding panel with profiled liner and outer sheets,fully filled with a foam insulation of conductivity 0.02W/mK. The thickness of the insulation, measuredfrom the lowest point of the top surface of the linerto the lowest point on the base of the outer sheet,is 80mm.

Fig 13: Representative section of composite panel

A simple one-dimensional calculation of the U-value taking account of the nominal 80mm ofinsulation alone, gives a U-value of 0.24 W/m2K.Separate two-dimensional calculations of the U-values resulting from the profiled liner and flat outerand profiled outer and flat liner, give : Uouter = 0.24W/m2K and Uliner = 0.25 W/m2K. Combining thesewith equation 8) gives U= 0.25 W/m2K. Although,at the insulation thicknesses necessary to complywith the elemental U-values in Approved DocumentL, the effect of the profiles is small, taking them intoaccount by simple proportional methods givesmisleading answers.

Example 3: Three-dimensional modellingFigures 14 and 15 show the results on an analysisof a detail of a profiled metal roof, containing 80mmof insulation of conductivity 0.037 W/mK betweenprofiled sheets. Aluminium clips, which are isolatedfrom the liner sheet with a thermal break pad, recurregularly at 400mm centres across the roof and at1500mm centres up the roof, these are thereforethe two horizontal dimensions of the model. Thefigures show the temperature on the liner and theheat flow into the roof. Both of these clearly showthe local effect of the thermal bridging due to theclip, despite the thermal pad, with the internalsurface temperature falling from 19.4˚C away fromthe clip to 16.4˚C immediately below the clip, andthe corresponding heat flows rising from 6.6 to 36.5W/m2.

26 15

The external façade must not be visibly wet

For visualisation of air leakage, the internalpressure must be at least 10 Pa lower thanexternal.

It can be seen that the conditions for a successfulsurvey are fairly restrictive. As surveys aregenerally carried out by specialist contractors whomay need to be booked some time in advance, itcan be very difficult to arrange a survey for anappropriate weather window. There may thereforebe a delay of several weeks before a survey can becarried out and if hand over of the building isdependent on completion of a survey, this cancause contractual difficulties. It is much better toremove the need for a survey by being able todemonstrate to a client that the cladding has beenproperly designed and installed.

5.3 Examples BRE has carried out a series of tests on differentmetal cladding systems using the PASSYS testcells at East Kilbride. These are well insulated, airtight, welded steel boxes, with a 2.7 metre aperturein one side - see Figure 25. Each cladding systemwas sealed into a heated test cell and, after thetemperatures had stabilised, an infra-red survey ofthe cladding details was carried out. These wereused to evaluate the suitability of such surveys forassessing the performance of cladding systems.During the surveys, various sealing options wereinvestigated and after testing the basic system, thecells were depressurised to investigate the effect ofair infiltration (see Section 6). Measured areas ofinsulation were then removed to investigate howwell the survey could reveal these ‘defects’.

Fig 25: Cladding panels under test at BRE

Figures 26-29 show examples of the type ofinformation that can be obtained from infra-redsurveys

Fig 26: Twin skin construction with ‘standard’ jointsand seals

Air leakage through the lower perimeter liner fillers,is cooling the bottom rail reducing the surfacetemperature from 19.9˚C to 15.1˚C.

Fig 27: Twin skin construction with improved sealsReducing the air flow has raised the surfacetemperature to 18.5˚C

Fig 28: Twin skin constructionRemoving a 100 x 150 mm section of insulationshows a well defined cold patch about 1.5 - 2˚Ccooler than the surrounding area. There is agenerally cooler region below the dashed line(representing the central horizontal rail) due to

Page 18: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

Fig 14: Temperature distribution on the base of asheeted metal roof with aluminium clips

Fig15: Heat flow distribution on the base of asheeted metal roof with aluminium clips

As the model is assumed to be representative ofthe whole roof the U-value can be calculated from:

In this case A = 0.4 . 1.5 = 0.6 m2 and Ti - Te = 20˚C.

If the thermal bridging is ignored by removing theclip from the model

Q = 5.09 giving U = 0.42 W/m2K

With a fully three-dimensional model as shown inFigures 14 and 15 with the correct clip size:

Q = 7.60 giving U = 0.63 W/m2K

In this case, ignoring the thermal bridgingunderestimates the U-value by over 30%.

3.5 Summary of U-value calculationmethods for metal roofing and cladding1. The method contained in BS EN ISO 6496 and

CIBSE Guide A does not apply to either twinskin or composite panel metal roofing andcladding systems.

2. If the construction is one of those covered inBRE IP 5/98, the U-value can be obtained from

the graphs or other information in the IP andcorrected for air spaces and compression of theinsulation by the profiles using the equations inthe IP.

3. If the component contains independent linearfeatures that can be represented by a series oftwo-dimensional models, use a two-dimensionalmodel and combine the results from the differentmodels.

4. If the component contains repeating pointthermal bridges, such as clips, develop a three-dimensional model to calculate the heat flowsand then the U-value.

16 25

appear much colder than their surroundings,although they are in fact at a similar temperature.

A further complication is caused by reflection ofthermal radiation. The reflectivity of a surface isequal to the emissivity value subtracted from one,therefore a metal surface will be very sensitive tothe temperatures of the people carrying out thesurvey, lights in the room, or equipment in thebackground.

In principle, it is possible to use thermal images toobtain quantitative measurements of surfacetemperatures that can be compared withtemperatures calculated using the methodsdescribed in section 4. However, in practice, thefactors outlined above make it difficult to obtainmore than a qualitative agreement between thepatterns of internal temperature distribution on theinternal surface. This difficulty is reflected in thetitle of the one available standard for infra-redsurveys, BS EN 13187:1999 : Thermalperformance of buildings - qualitative detection ofthermal irregularities in building envelopes - infra-red method. This means that it is not possibleto use thermal imaging surveys to measure U-values or quantify the effects of thermal bridges.

Areas on a thermal image of the inside of abuilding, which appear to have low surfacetemperatures compared to their surroundings, cantherefore be caused by :

a) low emissivity materials; these can usually beidentified visually and a correction factorincluded in the analysis;

b) increased heat flow through the componentcaused by thermal bridging due to the materialspresent or missing insulation;

c) increased heat flow due to moisture increasingthe thermal conductivity of thermal insulation;

d) evaporation of moisture from the surface;

e) cooling of the surface due to cold air infiltration.

The appearance of the thermal image can givesome guide to which of these problems is the likely

cause of any cold areas. For example, missinginsulation or thermal bridging gives a cold patchwith clearly defined edges, wet insulation gives adiffuse cold area and air infiltration has acharacteristically ‘feathery’ appearance.

When a building is surveyed from the outside, theeffect of factors b) and c) will be to increase thelocal external surface temperature compared tosurrounding areas. However, because the effectsof sun, wind and rain tend to blur out the thermalpatterns, external surveys are much less sensitivethan internal ones.

5.2 Conditions for a surveyDetailed guidance on thermal imaging surveys isgiven in a BRE Guide13 and an Energy EfficiencyOffice Best Practice Report14, which describe theconditions that are necessary for a meaningfulsurvey. The thermal conditions to which a buildingis exposed before and during a thermal imagingsurvey are very important. To minimise externalclimatic interference and to maximise thermalresolution the survey should, wherever possible, becarried out from within the building. In general, thefollowing conditions should be met:

For typical masonry constructions, the numericalvalue of the temperature difference between theinside and outside should be at least 3/U,where, U is the U-value of the wall or roof underinvestigation, for at least 24 hours before, andfor the duration of the survey; therefore atemperature difference of at least 8.5˚C isnecessary for a wall with U=0.35 W/m2K. Thislength of time may be relaxed to 12 hours in thecase of lightweight metal structures that respondmore rapidly to changes in temperature.

The outside air temperature variation should besmall and the internal air temperature should notvary by more than ±2˚C.

For at least 12 hours before and for the durationof the survey the building façade underinvestigation should not be exposed to sunshinesufficient to affect the results. The bestconditions are usually found on cold overcastdays.

Page 19: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

4.1 IntroductionFabric heat loss from buildings is calculated andtaken into account in the Regulations using the U-values of the plane surface of walls and roofs thatwere discussed in section 3. Further heat lossusually occurs at junctions such as between wallsand roofs, at gutters and around openings such aswindows, doors, rooflights and other penetrations.In these areas, known as thermal bridges, thegeometry of the structure and/or the presence ofhigh conductivity materials crossing the insulationlead to heat flows that are locally higher than insurrounding areas. These add to the total energydemand of the building.

A second consequence of thermal bridging is thelower internal surface temperatures caused by theincreased heat flow. Depending on theenvironmental conditions within the building andthe nature of the internal surfaces this can lead tosurface condensation or, less commonly inindustrial buildings, mould growth.

Figures 16 and 17 show the increased heat lossand lower surface temperatures through a cornerwhere two panels meet with the liner of onebridging the insulation of the other. This example isdiscussed further in the Appendix.

Fig 16: Increased heat flow caused by thermalbridging in corner

Fig 17: Lower temperatures caused by thermalbridging in corner

Approved Document L2 requires that the buildingfabric should be constructed so that there are nosignificant thermal bridges at the joints betweenelements and at the edges of elements such asthose around window and door openings. One wayof demonstrating compliance is to utilise details andpractice that have been demonstrated as beingsatisfactory. A selection of satisfactory details fordomestic style constructions is given in the reportcontaining standard details. BRE IP 17/01and thisMCRMA Technical Paper specify the criteria thathave to be met at all the thermal bridges on abuilding to avoid condensation or mould growth andexcessive heat loss. These are discussed insections 4.2 and 4.3.

4.2 Surface condensation and mouldgrowth4.2.1 The conditions for condensation andmould growthIn many buildings, especially housing, which haveabsorbent surfaces, the main consequence of thelowered surface temperatures caused by thermalbridges, is mould growth which, besides beingextremely unsightly, is a major cause of respiratoryallergies such as asthma. Mould growth, whichoccurs at a surface relative humidity of 80%, ishowever, very rare on the impermeable internalsurfaces of metal faced walls and roofs.Condensation, depositing drops of water on thesurface, which does not occur until the surfacerelative humidity has reached 100%, is much morelikely in this case. Even when condensationoccurs, often only a few grams per square metreaccumulates, seen as a fine mist on the surface,which rapidly disperses as temperatures rise. BREwork for the MCRMA has shown that at least 70g/m2 must accumulate before it will run from slopingsurfaces and 150g/m2 before dripping will occurfrom a horizontal surface.

The relationships between air and surfacetemperatures and humidity and the consequent riskof condensation or mould growth can besummarised on a psychrometric chart as shown inFigure 18.

24 17

present in a plane element, condensation mayoccur in humid environments. The severity ofthe bridge, and therefore the risk ofcondensation, is determined by the f-factorwhich is calculated by modelling the structure.Values of the f-factor for a range of details aregiven in the Appendix of this document.

5. If this type of thermal bridge is to be included ina building, which is likely to have a humidinternal environment, consideration should begiven to re-designing the detail.

6. It is also necessary to calculate the linearthermal transmittance (�-value) and do a heatloss calculation for the whole building. If thetotal heat loss through the thermal bridges isgreater than 10% of that through the planeareas, individual details must be modified toreduce the loss through the bridges. Values ofthe �-value for a range of details are given inthe Appendix of this document.

One way of demonstrating compliance with therequirements of Approved Document L2 is tosubmit evidence that an infra-red thermographyinspection has shown that the insulation is‘reasonably continuous over the whole visibleenvelope’. It is however, not clear how complete is‘reasonably continuous’, which could well begrounds for dispute in marginal cases. Also infra-red surveying is a complex process which, even if itis carried out under controlled conditions andanalysed carefully, requires a degree of subjectiveinterpretation by experienced operators who arefamiliar with metal cladding systems and buildings.

This section discusses methods for carrying outand interpreting infra-red surveys of buildings withmetal walls and/or roofs.

5.1 Thermal imagingThe instruments used in infra-red thermographymeasure the thermal radiation from an object andconstruct an image on a monitor. This image canbe in black and white, with brightness proportionalto the radiation intensity or have artificial coloursassigned to intensity bands. The radiation emittedby any object depends on:

a) the temperature of the surface;b) the emissivity of the surface

Emissivity is a parameter that depends on surfacetexture; some values for typical building materialsare:

Timber 0.85Plasterboard 0.90Brick 0.90Concrete 0.92Oil based paint 0.94Black lacquer 0.97Polished steel 0.07Galvanised steel 0.23Aluminium foil 0.09Anodised aluminium 0.55

If all the materials have similar emissivities, aninfra-red image can be interpreted as showingsurface temperatures. However, the lowemissivities of metal surfaces means that they will

Infra-red thermography Thermal bridges

Page 20: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

Air at 20˚C and 60 % relative humidity will have avapour pressure of 1.40 kPa (point A in Figure 18).If it is cooled at constant vapour pressure it willreach the mould growth limit of 80% relativehumidity at a surface temperature of 15.4˚C (pointC). If the surface is likely to promote mould growththis temperature imposes the limit for the thermaldesign of the building. If mould growth is unlikely,the risk of surface condensation then defines thenecessary temperature. Saturation andcondensation occur, when the relative humidityreach 100%, (point B); given the assumedconditions this occurs at 12.0˚C which imposes amuch less stringent design condition.

Conversely, if the air temperature is 20.0˚C and thesurface temperature is 14.0˚C, mould will occur ifthe internal humidity rises above 55% (point X),while condensation will not occur unless thehumidity rises above 68% (point Y).

Fig 18: Psychrometric chart showing the risk ofcondensation and mould growth

4.2.2 Surface temperature factorThe internal surface temperature of a point on abuilding, which determines the risk ofcondensation or mould growth (see below)depends on a) the internal and externalenvironmental temperatures and b) the thermalquality of the component. In masonry construction,the mass of the structure, which can cause theinternal surface to lag several hours after changesin the environmental temperatures is alsoimportant. However, profiled metal walls and roofsare much lighter weight and follow temperaturechanges much more rapidly. The thermal quality ofa particular part of the envelope can be assessed

irrespective of any particular environmentalconditions by calculating the temperature factor f,which is defined by:

where Ts is the local surface temperature

Te is the external air temperature

Ti is the internal air temperature.

Once the temperature factor of a specific detail,e.g. a corner, has been found by measurement orcalculation (see below) at specific internal andexternal temperatures, the surface temperature canbe found for any other combination ofenvironmental temperatures from:

4.2.3 Criteria for assessing buildingsThe robust standard details for domestic typeconstructions, produced for the guide toaccompany Approved Documents L1 and L2 havebeen assessed for the risk of mould growth usingthe criterion that the internal surface temperatureshould be kept above 15˚C, given internal andexternal temperatures of 20˚C and 0˚C respectively.This can be expressed as a minimum allowabletemperature factor, fmin, of 0.75 (using Equation 11).

There are various reasons why this may not be themost appropriate criterion for buildings with metalcladding and roofing:

a) The internal environment may be significantlydifferent from the fairly severe ‘domestic type’conditions, taken as 20˚C and 60% RH. Awarehouse will have a much lower internalhumidity, while a swimming pool or foodprocessing plant may be significantly more humid.

b) Most metal walls and roofs have hardimpermeable internal surfaces on which mouldgrowth is much less likely than surfacecondensation. Condensation occurs at asurface relative humidity of 100% as opposed tothe 80% necessary for mould growth. As

18 23

Table 7: Areas and U-values of the plane elements

Thermal bridges at junctions and openingsThe sketch in Figure 24 shows nine possiblethermal bridges in the notional building. The totallength and assumed �-value of each of these areshown, together with their product, in Table 8. Forsimplicity, it has been assumed the surrounds ofeach of the two doors and window are identical; inpractice it may be necessary to deal with theseseparately. The �-values have been chosen torepresent examples of current practice, some ofwhich produce relatively severe thermal bridges, asillustrated in section 4.4. In a real building theadded heat loss from features, such as projectinggirders supporting a canopy or gutter, or safetyharness posts, should also be considered.

Table 8: Lengths and �-values of each of thermalbridges shown in Figure 24

In this case �= ��L/ SAU = 245.5 / 2114.8 = 0.12,slightly exceeding the limit of �= 0.10 specified inIP 17/01 for non-domestic buildings for compliancewith the Regulations. It can be seen from Table 8that, although the window and door head andjambs are relatively severe thermal bridges withlarge �-values, their short length in this examplebuilding, means that their contribution to the overalltotal ��L is small (this would obviously not be thecase in a building with many more doors andwindows). Much more important are the valleygutter and the sill at the base of the building, whichboth have large �-values and long lengths. If thevalley gutter was modified as described in section4.4.2 to reduce its �-value to 0.17, this alonewould reduce ��L to 165.7 reducing � to 0.078,which complies with the Regulations. Alternatively,if the sill/drip was modified as described in theAppendix, reducing its �-value to 0.01, this wouldreduce ��L to 167.5 reducing � to 0.79.

This demonstrates that, provided that there is norisk of condensation given the particular internalenvironment, apparently quite large linear heattransmission (�-values) can be acceptable onindividual details, so long as the total heat lossfrom all the details on the building can becontrolled.

4.6 Summary of methods to reduce therisk of condensation and heat loss dueto thermal bridging1. It is necessary to consider both the risk of

condensation on each individual thermal bridgeand the effect of the increased heat loss throughthermal bridges on the overall heat from thebuilding.

2. Condensation, which occurs at a surface relativehumidity of 100%, is much more likely in metalconstructions than mould growth, which occursat a surface humidity of 80%.

3. Condensation is unlikely on ‘repeating thermalbridges’ such as spacers or profiles, but is morelikely on systems with discrete aluminium clips.

4. If a detail contains metal components crossingthe insulation that would not otherwise be

A.UW/K

U-valueW/m2K

Aream2

Plane element

180.2245.4

11.24.02.0

530.0542.1

600.0

0.350.35

0.72.02.0

2.20.25

0.25

514.8701.0

16.02.01.0

240.92168.2

2400.0

Side wallsEnd walls

Access doorPersonnel doorWindow

RooflightsRoof

Ground floor

�AU = 2114.8

L.�W/K

�-valueW/mK

Lengthm

Thermal Bridge

1.2

30.0

8.0

90.0

80.0

6.0

9.0

21.0

0.3

0.01

0.25

0.10

1.50

0.41

0.25

1.50

1.50

0.30

120

120

80

60

195

24

6

14

1

1) Ridge

2) Eaves

3) Verge

4) Valley Gutter

5) Sill

6) Corner

7) Window or doorhead

8) Window or doorjamb

9) Window sill

��L= 245.5

Page 21: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

discussed above, that will impose a significantlyless stringent requirement on surfacetemperatures.

c) Metal cladding has little thermal mass comparedto domestic constructions and will thereforerespond rapidly to overnight falls in temperaturethat would be smoothed out by a masonry wall.

Surface temperature criteria, which define fmin andwhich are more appropriate to industrial buildingshave been established using the methodologyspecified in BS EN ISO 13788.

4.2.4 BS EN ISO 13788The current standard for the design of buildingsagainst condensation risks is BS 5250:198911,which includes calculation procedures for surfaceand interstitial condensation risk as appendices Cand D. A new CEN standard BS EN ISO13788:200112 which contains more complexcalculation procedures, has recently beenintroduced, and consequently the BS 5250appendices are being withdrawn. BS 5250 iscurrently being extensively revised and a newversion, which makes reference to the calculationprocedures in BS EN ISO 13788, will be availablein early 2002.

BS EN ISO 13788 contains a method forcalculating the necessary thermal quality ofbuilding envelopes to avoid either condensation ormould growth, which includes categorisingbuildings into a number of ‘climate classes’depending on their likely internal environment. Thisclassification uses the difference between theinside and outside vapour pressure, the ‘vapourexcess’, which is determined by the moisturegeneration rate, the volume of the building and theventilation rate. The fact that ventilation rates varyas more windows are opened in warmer weather isallowed for by assuming that a) the vapour excessis constant below 0˚C as all windows are closedand b) the vapour excess falls linearly to zero at anexternal temperature of 20˚C, when the building isassumed to be well ventilated. This gives theboundaries between the classes shown in Figure19, which also shows the internal relative humidity

at an outdoor temperature of 0˚C and an indoortemperature of 20˚C.

Fig 19: Variation of internal humidity classes withexternal temperature

In the case of air conditioned buildings in which theinternal humidity is controlled independently of theexternal environment the set values of thetemperature and relative humidity should be usedto calculate the internal moisture load.

Different building types fall into the different classesshown on Figure 19 and summarised in Table 6,with the minimum f-values which are required toavoid condensation in the different internalenvironments

Table 6: Internal humidity classes and the minimumtemperature factor necessary to prevent condensation

The BS EN ISO 13788 methodology leads to thetemperature factors necessary to avoidcondensation shown in Table 6. These temperaturefactors can be put into context by comparing them

22 19

Humidityclass

Building Type Minimumf value

1

2

3

4

5

Storage areas

Offices, shops

Dwellings with low occupancy

Dwellings with high occupancy,

sports halls, kitchens,

canteens; buildings heated

with un-flued gas heaters

Special buildings, e.g. laundry,

brewery, swimming pool

0.30

0.50

0.65

0.80

0.90

4.4.2 Valley gutter In the purlin hung valley gutter shown schematicallyin Figure 22, the steel gutter top and roof claddingliner are penetrating through the insulation layer,suggesting that severe thermal bridging is likely.Because, as noted in section 3.2, the simulationprograms work on rectangular shapes, the roofpanel, which would be sloping down to the gutter inpractice, has been flattened out. This makes littledifference to the calculated internal surfacetemperature values. Figure 23 shows thecalculated temperatures for internal and externaltemperatures of 20˚C and 0˚C respectively.Because of the thermal bridging caused by thegutter top and the metal liner, the internal surfacetemperature is reduced to 13.7˚C, giving f=0.69.This means that this detail would work adequatelyin a warehouse, but in a sports hall or factory withany wet process, and especially a swimming pool,there would be a risk of condensation.

Analysis of the heat flows gives �=1.5 W/mK,suggesting that this detail is a much moresignificant extra source of heat loss from thebuilding, than the ridge above.

Fig 22: Valley gutter detail

Fig 23: Calculated temperatures on base of valleygutter and roof lining

If the gutter top is modified so that the part thatcrosses the insulation is made of a rigid plastic withconductivity = 0.2, the f-factor rises to 0.84 and the�-value falls to 0.66, significantly improving theenergy performance. If the liner of the main roofdoes not cross the insulation, the f-factor rises to0.95 and the �-value falls to 0.17, considerablyreducing the thermal bridge.

4.5 Example of the effect of thermalbridging on overall heat lossTo illustrate the relative effect of differentcomponents, the fabric heat loss through thenotional building shown in Figure 24 wascalculated; The contribution of air leakage to thetotal heat loss is estimated in section 6.4.

Fig 24: Notional industrial building showingthermal bridges

The building is assumed to be a typical mediumsized industrial unit with the dimensions shown onthe sketch. There is just one large vehicle door, apersonnel door and one office window in one of theend walls; 10% of the roof area is made up ofrooflights. The nine possible thermal bridgesidentified on the sketch are discussed below.

Plane elementsTable 7 shows the areas and U-values of each ofthe plane elements and their product that issummed to calculate � AU. In the example shown,it has been assumed that each of the U-values isequal to the required value quoted in the table inparagraph 1.8 of Approved Document L2. Inpractice, specific values would be quoted by thesystem suppliers and it would also be necessary totake account of other components such as smokevents or gutters.

Page 22: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

with the values, in the absence of thermal bridging,for :

a) a single steel sheet 0.5mm thick, with noinsulation, gives f = 0.28, i.e. there would becondensation in all building types;

b) a roof light made up of two sheets ofpolycarbonate separated by a 20mm air gapgives f = 0.59;

c) two steel sheets separated by 50mm of mineralwool gives f = 0.93.

Example 1:

We wish to prevent surface condensation in awarehouse, in climate class 1, with internaltemperature of 15˚C when the externaltemperature falls to -5˚C. The requiredtemperature factor from Table 6 is 0.3, so the fabricmust be designed so that the internal surfacetemperature is above –5 + 0.3.(15 – (-5)) = 1˚C(equation 12)

Example 2 :

We wish to prevent surface condensation in aswimming pool, in climate class 5, with internaltemperature of 25˚C when the externaltemperature falls to -5˚C. The requiredtemperature factor from Table 6 is 0.9, so the fabricmust be designed so that the internal surfacetemperature is above –5 + 0.9.(25 – (-5)) = 22˚C(equation 12)

4.2.5 Surface temperature calculationsBesides calculating heat flows and U-values, thetwo - and three-dimensional analysis softwaredescribed in section 3 also calculates the internalsurface temperature and therefore the risk ofcondensation or mould growth.

The zed-spacers and similar repeated thermalbridges that can be analysed in two dimensionshave little effect on the internal surfacetemperature. For example, the detail analysed asexample 1 in Section 3.3 gives a minimum internalsurface temperature of 18.7˚C with internal andexternal temperatures of 20˚C and 0˚C respectively.

This gives f = 0.935, which means that thisconstruction would not pose a risk of internalsurface condensation with any reasonable internalenvironment. Similarly, the point thermal bridgescaused by brackets or fasteners discussed insection 3.3.3 do not lower the f-value below 0.9. Itis however, important to remember that, unlessthe vapour control layer is complete, there maybe a risk of interstitial condensation within thestructure, particularly in high humidityenvironments.

The detail shown as example 2 in Section 3.3,which requires three-dimensional modelling, givesa minimum surface temperature of 16.4˚C belowthe clip, (Figure 14) for the same environmentalconditions. This means that f=0.82, so that thisdetail would not be suitable for a swimming poolbut would not give problems with any otheroccupancy.

More serious problems can arise at non-repeatingthermal bridges at the junctions between walls androofs, at valley gutters or at openings such asdoors and windows and other steelworkpenetrations. The severity of the problem dependson whether the detail leads to any metalpenetrations of the insulation layer other than thosedue to the standard spacers in the plane areas ofwall and roof, that have been taken into accountalready. Examples of surface temperatures onthermal bridges are shown in section 4.4.

Although their inclusion is not required by theRegulations, ‘point’ thermal bridges caused bypenetrations of the building envelope, such assafety harness posts or protruding girders tosupport a canopy or gutter, can cause localisedvery low surface temperatures, see the Appendixfor further details.

4.3 Heat loss through thermal bridges4.3.1 Linear thermal transmission -�-valueHeat loss through linear thermal bridges isexpressed in terms of the linear thermaltransmittance or �-value. This is the extra heatloss through the thermal bridge over and above theheat loss through the adjoining plane elements.

20 21

For example, Figure 20 shows a corner in whichthe liner of one composite wall panel bridges theinsulation of the other; this could apply equally wellto a twin skin system in which the liner of one wallbridged the insulation of the other. The model isextended sufficiently far along either panel so thatthe temperature and heat flow at the edges isunaffected by the presence of the thermal bridge.In practice this has to be about one metre, rathermore than is shown here. A two-dimensionalthermal model is used to calculate the heat flowfrom the inside to the outside and the �-value isthen calculated from:

Where Q is the heat flow through the model inW/m

Ti and Te are the inside and outsidetemperatures in ˚C

UA and UB are the U values of A and Bin W/m2K

DA and DB are the lengths of cladding Aand B out from the inside corner in m

Then if the total length of this corner detail is L m,its contribution to the heat loss from the building isL�W/K. The contributions of all the thermalbridges in the building can be added giving a totalheat loss of ��.L W/K. This can then be added tothe plane area heat loss to give the total fabric heatloss of �A.U + ��.L.

Fig 20: Calculation of �-value

BRE IP 17/01 contains a table of �-values forthermal bridges in typical domestic constructions; ifthe calculated �-values in the building underdesign are less than or equal to these values, then

no further action is necessary. If the thermalbridges under investigation do not appear in thistable, which is most likely in the case of industrialbuildings, the �-value for the building fabric must becalculated, where:

To satisfy the Regulations � must be less than orequal 0.16 for domestic buildings and less than orequal 0.10 for non-domestic buildings. The lowervalue for non-domestic buildings reflects the factthat their larger size means that thermal bridgesare relatively less important. Section 4.5 gives anexample of the effect of specific thermal bridges onthe calculation of the �-value for a typical industrialbuilding

Although their inclusion is not required by theRegulations, ‘point’ thermal bridges caused bypenetrations of the building envelope such assafety harness posts or protruding girders tosupport a canopy or gutter, can cause additionalheat loss; see the Appendix for further details.

4.4 Examples of surface temperatureand heat loss through thermal bridges4.4.1 Roof ridge The ridge detail, shown in Figure 21, contains nopenetrations of the insulation, apart from thespacers on either side, which are part of the basiccladding and will have been taken into account inthe calculation of the cladding U-value.

Analysis of this ridge detail gives fmin = 0.91 and�=0.01 W/mK. These confirm, as expected fromthe drawing, that this detail will not cause anycondensation problems in any of the building typesshown in Table 6 and will lead to a very smalladdition to the heat loss from the building.

Fig 21: Ridge detail with no apparent thermalbridging that is likely to lead to internalsurface condensation

EXTERNAL PROFILEFOAM FILLER

ZED SPACER ANDPLASTIC FERRULE

INNER RIDGECLOSER FLASHING

LINERPURLINS

Page 23: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

with the values, in the absence of thermal bridging,for :

a) a single steel sheet 0.5mm thick, with noinsulation, gives f = 0.28, i.e. there would becondensation in all building types;

b) a roof light made up of two sheets ofpolycarbonate separated by a 20mm air gapgives f = 0.59;

c) two steel sheets separated by 50mm of mineralwool gives f = 0.93.

Example 1:

We wish to prevent surface condensation in awarehouse, in climate class 1, with internaltemperature of 15˚C when the externaltemperature falls to -5˚C. The requiredtemperature factor from Table 6 is 0.3, so the fabricmust be designed so that the internal surfacetemperature is above –5 + 0.3.(15 – (-5)) = 1˚C(equation 12)

Example 2 :

We wish to prevent surface condensation in aswimming pool, in climate class 5, with internaltemperature of 25˚C when the externaltemperature falls to -5˚C. The requiredtemperature factor from Table 6 is 0.9, so the fabricmust be designed so that the internal surfacetemperature is above –5 + 0.9.(25 – (-5)) = 22˚C(equation 12)

4.2.5 Surface temperature calculationsBesides calculating heat flows and U-values, thetwo - and three-dimensional analysis softwaredescribed in section 3 also calculates the internalsurface temperature and therefore the risk ofcondensation or mould growth.

The zed-spacers and similar repeated thermalbridges that can be analysed in two dimensionshave little effect on the internal surfacetemperature. For example, the detail analysed asexample 1 in Section 3.3 gives a minimum internalsurface temperature of 18.7˚C with internal andexternal temperatures of 20˚C and 0˚C respectively.

This gives f = 0.935, which means that thisconstruction would not pose a risk of internalsurface condensation with any reasonable internalenvironment. Similarly, the point thermal bridgescaused by brackets or fasteners discussed insection 3.3.3 do not lower the f-value below 0.9. Itis however, important to remember that, unlessthe vapour control layer is complete, there maybe a risk of interstitial condensation within thestructure, particularly in high humidityenvironments.

The detail shown as example 2 in Section 3.3,which requires three-dimensional modelling, givesa minimum surface temperature of 16.4˚C belowthe clip, (Figure 14) for the same environmentalconditions. This means that f=0.82, so that thisdetail would not be suitable for a swimming poolbut would not give problems with any otheroccupancy.

More serious problems can arise at non-repeatingthermal bridges at the junctions between walls androofs, at valley gutters or at openings such asdoors and windows and other steelworkpenetrations. The severity of the problem dependson whether the detail leads to any metalpenetrations of the insulation layer other than thosedue to the standard spacers in the plane areas ofwall and roof, that have been taken into accountalready. Examples of surface temperatures onthermal bridges are shown in section 4.4.

Although their inclusion is not required by theRegulations, ‘point’ thermal bridges caused bypenetrations of the building envelope, such assafety harness posts or protruding girders tosupport a canopy or gutter, can cause localisedvery low surface temperatures, see the Appendixfor further details.

4.3 Heat loss through thermal bridges4.3.1 Linear thermal transmission -�-valueHeat loss through linear thermal bridges isexpressed in terms of the linear thermaltransmittance or �-value. This is the extra heatloss through the thermal bridge over and above theheat loss through the adjoining plane elements.

20 21

For example, Figure 20 shows a corner in whichthe liner of one composite wall panel bridges theinsulation of the other; this could apply equally wellto a twin skin system in which the liner of one wallbridged the insulation of the other. The model isextended sufficiently far along either panel so thatthe temperature and heat flow at the edges isunaffected by the presence of the thermal bridge.In practice this has to be about one metre, rathermore than is shown here. A two-dimensionalthermal model is used to calculate the heat flowfrom the inside to the outside and the �-value isthen calculated from:

Where Q is the heat flow through the model inW/m

Ti and Te are the inside and outsidetemperatures in ˚C

UA and UB are the U values of A and Bin W/m2K

DA and DB are the lengths of cladding Aand B out from the inside corner in m

Then if the total length of this corner detail is L m,its contribution to the heat loss from the building isL�W/K. The contributions of all the thermalbridges in the building can be added giving a totalheat loss of ��.L W/K. This can then be added tothe plane area heat loss to give the total fabric heatloss of �A.U + ��.L.

Fig 20: Calculation of �-value

BRE IP 17/01 contains a table of �-values forthermal bridges in typical domestic constructions; ifthe calculated �-values in the building underdesign are less than or equal to these values, then

no further action is necessary. If the thermalbridges under investigation do not appear in thistable, which is most likely in the case of industrialbuildings, the �-value for the building fabric must becalculated, where:

To satisfy the Regulations � must be less than orequal 0.16 for domestic buildings and less than orequal 0.10 for non-domestic buildings. The lowervalue for non-domestic buildings reflects the factthat their larger size means that thermal bridgesare relatively less important. Section 4.5 gives anexample of the effect of specific thermal bridges onthe calculation of the �-value for a typical industrialbuilding

Although their inclusion is not required by theRegulations, ‘point’ thermal bridges caused bypenetrations of the building envelope such assafety harness posts or protruding girders tosupport a canopy or gutter, can cause additionalheat loss; see the Appendix for further details.

4.4 Examples of surface temperatureand heat loss through thermal bridges4.4.1 Roof ridge The ridge detail, shown in Figure 21, contains nopenetrations of the insulation, apart from thespacers on either side, which are part of the basiccladding and will have been taken into account inthe calculation of the cladding U-value.

Analysis of this ridge detail gives fmin = 0.91 and�=0.01 W/mK. These confirm, as expected fromthe drawing, that this detail will not cause anycondensation problems in any of the building typesshown in Table 6 and will lead to a very smalladdition to the heat loss from the building.

Fig 21: Ridge detail with no apparent thermalbridging that is likely to lead to internalsurface condensation

EXTERNAL PROFILEFOAM FILLER

ZED SPACER ANDPLASTIC FERRULE

INNER RIDGECLOSER FLASHING

LINERPURLINS

Page 24: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

discussed above, that will impose a significantlyless stringent requirement on surfacetemperatures.

c) Metal cladding has little thermal mass comparedto domestic constructions and will thereforerespond rapidly to overnight falls in temperaturethat would be smoothed out by a masonry wall.

Surface temperature criteria, which define fmin andwhich are more appropriate to industrial buildingshave been established using the methodologyspecified in BS EN ISO 13788.

4.2.4 BS EN ISO 13788The current standard for the design of buildingsagainst condensation risks is BS 5250:198911,which includes calculation procedures for surfaceand interstitial condensation risk as appendices Cand D. A new CEN standard BS EN ISO13788:200112 which contains more complexcalculation procedures, has recently beenintroduced, and consequently the BS 5250appendices are being withdrawn. BS 5250 iscurrently being extensively revised and a newversion, which makes reference to the calculationprocedures in BS EN ISO 13788, will be availablein early 2002.

BS EN ISO 13788 contains a method forcalculating the necessary thermal quality ofbuilding envelopes to avoid either condensation ormould growth, which includes categorisingbuildings into a number of ‘climate classes’depending on their likely internal environment. Thisclassification uses the difference between theinside and outside vapour pressure, the ‘vapourexcess’, which is determined by the moisturegeneration rate, the volume of the building and theventilation rate. The fact that ventilation rates varyas more windows are opened in warmer weather isallowed for by assuming that a) the vapour excessis constant below 0˚C as all windows are closedand b) the vapour excess falls linearly to zero at anexternal temperature of 20˚C, when the building isassumed to be well ventilated. This gives theboundaries between the classes shown in Figure19, which also shows the internal relative humidity

at an outdoor temperature of 0˚C and an indoortemperature of 20˚C.

Fig 19: Variation of internal humidity classes withexternal temperature

In the case of air conditioned buildings in which theinternal humidity is controlled independently of theexternal environment the set values of thetemperature and relative humidity should be usedto calculate the internal moisture load.

Different building types fall into the different classesshown on Figure 19 and summarised in Table 6,with the minimum f-values which are required toavoid condensation in the different internalenvironments

Table 6: Internal humidity classes and the minimumtemperature factor necessary to prevent condensation

The BS EN ISO 13788 methodology leads to thetemperature factors necessary to avoidcondensation shown in Table 6. These temperaturefactors can be put into context by comparing them

22 19

Humidityclass

Building Type Minimumf value

1

2

3

4

5

Storage areas

Offices, shops

Dwellings with low occupancy

Dwellings with high occupancy,

sports halls, kitchens,

canteens; buildings heated

with un-flued gas heaters

Special buildings, e.g. laundry,

brewery, swimming pool

0.30

0.50

0.65

0.80

0.90

4.4.2 Valley gutter In the purlin hung valley gutter shown schematicallyin Figure 22, the steel gutter top and roof claddingliner are penetrating through the insulation layer,suggesting that severe thermal bridging is likely.Because, as noted in section 3.2, the simulationprograms work on rectangular shapes, the roofpanel, which would be sloping down to the gutter inpractice, has been flattened out. This makes littledifference to the calculated internal surfacetemperature values. Figure 23 shows thecalculated temperatures for internal and externaltemperatures of 20˚C and 0˚C respectively.Because of the thermal bridging caused by thegutter top and the metal liner, the internal surfacetemperature is reduced to 13.7˚C, giving f=0.69.This means that this detail would work adequatelyin a warehouse, but in a sports hall or factory withany wet process, and especially a swimming pool,there would be a risk of condensation.

Analysis of the heat flows gives �=1.5 W/mK,suggesting that this detail is a much moresignificant extra source of heat loss from thebuilding, than the ridge above.

Fig 22: Valley gutter detail

Fig 23: Calculated temperatures on base of valleygutter and roof lining

If the gutter top is modified so that the part thatcrosses the insulation is made of a rigid plastic withconductivity = 0.2, the f-factor rises to 0.84 and the�-value falls to 0.66, significantly improving theenergy performance. If the liner of the main roofdoes not cross the insulation, the f-factor rises to0.95 and the �-value falls to 0.17, considerablyreducing the thermal bridge.

4.5 Example of the effect of thermalbridging on overall heat lossTo illustrate the relative effect of differentcomponents, the fabric heat loss through thenotional building shown in Figure 24 wascalculated; The contribution of air leakage to thetotal heat loss is estimated in section 6.4.

Fig 24: Notional industrial building showingthermal bridges

The building is assumed to be a typical mediumsized industrial unit with the dimensions shown onthe sketch. There is just one large vehicle door, apersonnel door and one office window in one of theend walls; 10% of the roof area is made up ofrooflights. The nine possible thermal bridgesidentified on the sketch are discussed below.

Plane elementsTable 7 shows the areas and U-values of each ofthe plane elements and their product that issummed to calculate � AU. In the example shown,it has been assumed that each of the U-values isequal to the required value quoted in the table inparagraph 1.8 of Approved Document L2. Inpractice, specific values would be quoted by thesystem suppliers and it would also be necessary totake account of other components such as smokevents or gutters.

Page 25: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

Air at 20˚C and 60 % relative humidity will have avapour pressure of 1.40 kPa (point A in Figure 18).If it is cooled at constant vapour pressure it willreach the mould growth limit of 80% relativehumidity at a surface temperature of 15.4˚C (pointC). If the surface is likely to promote mould growththis temperature imposes the limit for the thermaldesign of the building. If mould growth is unlikely,the risk of surface condensation then defines thenecessary temperature. Saturation andcondensation occur, when the relative humidityreach 100%, (point B); given the assumedconditions this occurs at 12.0˚C which imposes amuch less stringent design condition.

Conversely, if the air temperature is 20.0˚C and thesurface temperature is 14.0˚C, mould will occur ifthe internal humidity rises above 55% (point X),while condensation will not occur unless thehumidity rises above 68% (point Y).

Fig 18: Psychrometric chart showing the risk ofcondensation and mould growth

4.2.2 Surface temperature factorThe internal surface temperature of a point on abuilding, which determines the risk ofcondensation or mould growth (see below)depends on a) the internal and externalenvironmental temperatures and b) the thermalquality of the component. In masonry construction,the mass of the structure, which can cause theinternal surface to lag several hours after changesin the environmental temperatures is alsoimportant. However, profiled metal walls and roofsare much lighter weight and follow temperaturechanges much more rapidly. The thermal quality ofa particular part of the envelope can be assessed

irrespective of any particular environmentalconditions by calculating the temperature factor f,which is defined by:

where Ts is the local surface temperature

Te is the external air temperature

Ti is the internal air temperature.

Once the temperature factor of a specific detail,e.g. a corner, has been found by measurement orcalculation (see below) at specific internal andexternal temperatures, the surface temperature canbe found for any other combination ofenvironmental temperatures from:

4.2.3 Criteria for assessing buildingsThe robust standard details for domestic typeconstructions, produced for the guide toaccompany Approved Documents L1 and L2 havebeen assessed for the risk of mould growth usingthe criterion that the internal surface temperatureshould be kept above 15˚C, given internal andexternal temperatures of 20˚C and 0˚C respectively.This can be expressed as a minimum allowabletemperature factor, fmin, of 0.75 (using Equation 11).

There are various reasons why this may not be themost appropriate criterion for buildings with metalcladding and roofing:

a) The internal environment may be significantlydifferent from the fairly severe ‘domestic type’conditions, taken as 20˚C and 60% RH. Awarehouse will have a much lower internalhumidity, while a swimming pool or foodprocessing plant may be significantly more humid.

b) Most metal walls and roofs have hardimpermeable internal surfaces on which mouldgrowth is much less likely than surfacecondensation. Condensation occurs at asurface relative humidity of 100% as opposed tothe 80% necessary for mould growth. As

18 23

Table 7: Areas and U-values of the plane elements

Thermal bridges at junctions and openingsThe sketch in Figure 24 shows nine possiblethermal bridges in the notional building. The totallength and assumed �-value of each of these areshown, together with their product, in Table 8. Forsimplicity, it has been assumed the surrounds ofeach of the two doors and window are identical; inpractice it may be necessary to deal with theseseparately. The �-values have been chosen torepresent examples of current practice, some ofwhich produce relatively severe thermal bridges, asillustrated in section 4.4. In a real building theadded heat loss from features, such as projectinggirders supporting a canopy or gutter, or safetyharness posts, should also be considered.

Table 8: Lengths and �-values of each of thermalbridges shown in Figure 24

In this case �= ��L/ SAU = 245.5 / 2114.8 = 0.12,slightly exceeding the limit of �= 0.10 specified inIP 17/01 for non-domestic buildings for compliancewith the Regulations. It can be seen from Table 8that, although the window and door head andjambs are relatively severe thermal bridges withlarge �-values, their short length in this examplebuilding, means that their contribution to the overalltotal ��L is small (this would obviously not be thecase in a building with many more doors andwindows). Much more important are the valleygutter and the sill at the base of the building, whichboth have large �-values and long lengths. If thevalley gutter was modified as described in section4.4.2 to reduce its �-value to 0.17, this alonewould reduce ��L to 165.7 reducing � to 0.078,which complies with the Regulations. Alternatively,if the sill/drip was modified as described in theAppendix, reducing its �-value to 0.01, this wouldreduce ��L to 167.5 reducing � to 0.79.

This demonstrates that, provided that there is norisk of condensation given the particular internalenvironment, apparently quite large linear heattransmission (�-values) can be acceptable onindividual details, so long as the total heat lossfrom all the details on the building can becontrolled.

4.6 Summary of methods to reduce therisk of condensation and heat loss dueto thermal bridging1. It is necessary to consider both the risk of

condensation on each individual thermal bridgeand the effect of the increased heat loss throughthermal bridges on the overall heat from thebuilding.

2. Condensation, which occurs at a surface relativehumidity of 100%, is much more likely in metalconstructions than mould growth, which occursat a surface humidity of 80%.

3. Condensation is unlikely on ‘repeating thermalbridges’ such as spacers or profiles, but is morelikely on systems with discrete aluminium clips.

4. If a detail contains metal components crossingthe insulation that would not otherwise be

A.UW/K

U-valueW/m2K

Aream2

Plane element

180.2245.4

11.24.02.0

530.0542.1

600.0

0.350.35

0.72.02.0

2.20.25

0.25

514.8701.0

16.02.01.0

240.92168.2

2400.0

Side wallsEnd walls

Access doorPersonnel doorWindow

RooflightsRoof

Ground floor

�AU = 2114.8

L.�W/K

�-valueW/mK

Lengthm

Thermal Bridge

1.2

30.0

8.0

90.0

80.0

6.0

9.0

21.0

0.3

0.01

0.25

0.10

1.50

0.41

0.25

1.50

1.50

0.30

120

120

80

60

195

24

6

14

1

1) Ridge

2) Eaves

3) Verge

4) Valley Gutter

5) Sill

6) Corner

7) Window or doorhead

8) Window or doorjamb

9) Window sill

��L= 245.5

Page 26: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

4.1 IntroductionFabric heat loss from buildings is calculated andtaken into account in the Regulations using the U-values of the plane surface of walls and roofs thatwere discussed in section 3. Further heat lossusually occurs at junctions such as between wallsand roofs, at gutters and around openings such aswindows, doors, rooflights and other penetrations.In these areas, known as thermal bridges, thegeometry of the structure and/or the presence ofhigh conductivity materials crossing the insulationlead to heat flows that are locally higher than insurrounding areas. These add to the total energydemand of the building.

A second consequence of thermal bridging is thelower internal surface temperatures caused by theincreased heat flow. Depending on theenvironmental conditions within the building andthe nature of the internal surfaces this can lead tosurface condensation or, less commonly inindustrial buildings, mould growth.

Figures 16 and 17 show the increased heat lossand lower surface temperatures through a cornerwhere two panels meet with the liner of onebridging the insulation of the other. This example isdiscussed further in the Appendix.

Fig 16: Increased heat flow caused by thermalbridging in corner

Fig 17: Lower temperatures caused by thermalbridging in corner

Approved Document L2 requires that the buildingfabric should be constructed so that there are nosignificant thermal bridges at the joints betweenelements and at the edges of elements such asthose around window and door openings. One wayof demonstrating compliance is to utilise details andpractice that have been demonstrated as beingsatisfactory. A selection of satisfactory details fordomestic style constructions is given in the reportcontaining standard details. BRE IP 17/01and thisMCRMA Technical Paper specify the criteria thathave to be met at all the thermal bridges on abuilding to avoid condensation or mould growth andexcessive heat loss. These are discussed insections 4.2 and 4.3.

4.2 Surface condensation and mouldgrowth4.2.1 The conditions for condensation andmould growthIn many buildings, especially housing, which haveabsorbent surfaces, the main consequence of thelowered surface temperatures caused by thermalbridges, is mould growth which, besides beingextremely unsightly, is a major cause of respiratoryallergies such as asthma. Mould growth, whichoccurs at a surface relative humidity of 80%, ishowever, very rare on the impermeable internalsurfaces of metal faced walls and roofs.Condensation, depositing drops of water on thesurface, which does not occur until the surfacerelative humidity has reached 100%, is much morelikely in this case. Even when condensationoccurs, often only a few grams per square metreaccumulates, seen as a fine mist on the surface,which rapidly disperses as temperatures rise. BREwork for the MCRMA has shown that at least 70g/m2 must accumulate before it will run from slopingsurfaces and 150g/m2 before dripping will occurfrom a horizontal surface.

The relationships between air and surfacetemperatures and humidity and the consequent riskof condensation or mould growth can besummarised on a psychrometric chart as shown inFigure 18.

24 17

present in a plane element, condensation mayoccur in humid environments. The severity ofthe bridge, and therefore the risk ofcondensation, is determined by the f-factorwhich is calculated by modelling the structure.Values of the f-factor for a range of details aregiven in the Appendix of this document.

5. If this type of thermal bridge is to be included ina building, which is likely to have a humidinternal environment, consideration should begiven to re-designing the detail.

6. It is also necessary to calculate the linearthermal transmittance (�-value) and do a heatloss calculation for the whole building. If thetotal heat loss through the thermal bridges isgreater than 10% of that through the planeareas, individual details must be modified toreduce the loss through the bridges. Values ofthe �-value for a range of details are given inthe Appendix of this document.

One way of demonstrating compliance with therequirements of Approved Document L2 is tosubmit evidence that an infra-red thermographyinspection has shown that the insulation is‘reasonably continuous over the whole visibleenvelope’. It is however, not clear how complete is‘reasonably continuous’, which could well begrounds for dispute in marginal cases. Also infra-red surveying is a complex process which, even if itis carried out under controlled conditions andanalysed carefully, requires a degree of subjectiveinterpretation by experienced operators who arefamiliar with metal cladding systems and buildings.

This section discusses methods for carrying outand interpreting infra-red surveys of buildings withmetal walls and/or roofs.

5.1 Thermal imagingThe instruments used in infra-red thermographymeasure the thermal radiation from an object andconstruct an image on a monitor. This image canbe in black and white, with brightness proportionalto the radiation intensity or have artificial coloursassigned to intensity bands. The radiation emittedby any object depends on:

a) the temperature of the surface;b) the emissivity of the surface

Emissivity is a parameter that depends on surfacetexture; some values for typical building materialsare:

Timber 0.85Plasterboard 0.90Brick 0.90Concrete 0.92Oil based paint 0.94Black lacquer 0.97Polished steel 0.07Galvanised steel 0.23Aluminium foil 0.09Anodised aluminium 0.55

If all the materials have similar emissivities, aninfra-red image can be interpreted as showingsurface temperatures. However, the lowemissivities of metal surfaces means that they will

Infra-red thermography Thermal bridges

Page 27: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

Fig 14: Temperature distribution on the base of asheeted metal roof with aluminium clips

Fig15: Heat flow distribution on the base of asheeted metal roof with aluminium clips

As the model is assumed to be representative ofthe whole roof the U-value can be calculated from:

In this case A = 0.4 . 1.5 = 0.6 m2 and Ti - Te = 20˚C.

If the thermal bridging is ignored by removing theclip from the model

Q = 5.09 giving U = 0.42 W/m2K

With a fully three-dimensional model as shown inFigures 14 and 15 with the correct clip size:

Q = 7.60 giving U = 0.63 W/m2K

In this case, ignoring the thermal bridgingunderestimates the U-value by over 30%.

3.5 Summary of U-value calculationmethods for metal roofing and cladding1. The method contained in BS EN ISO 6496 and

CIBSE Guide A does not apply to either twinskin or composite panel metal roofing andcladding systems.

2. If the construction is one of those covered inBRE IP 5/98, the U-value can be obtained from

the graphs or other information in the IP andcorrected for air spaces and compression of theinsulation by the profiles using the equations inthe IP.

3. If the component contains independent linearfeatures that can be represented by a series oftwo-dimensional models, use a two-dimensionalmodel and combine the results from the differentmodels.

4. If the component contains repeating pointthermal bridges, such as clips, develop a three-dimensional model to calculate the heat flowsand then the U-value.

16 25

appear much colder than their surroundings,although they are in fact at a similar temperature.

A further complication is caused by reflection ofthermal radiation. The reflectivity of a surface isequal to the emissivity value subtracted from one,therefore a metal surface will be very sensitive tothe temperatures of the people carrying out thesurvey, lights in the room, or equipment in thebackground.

In principle, it is possible to use thermal images toobtain quantitative measurements of surfacetemperatures that can be compared withtemperatures calculated using the methodsdescribed in section 4. However, in practice, thefactors outlined above make it difficult to obtainmore than a qualitative agreement between thepatterns of internal temperature distribution on theinternal surface. This difficulty is reflected in thetitle of the one available standard for infra-redsurveys, BS EN 13187:1999 : Thermalperformance of buildings - qualitative detection ofthermal irregularities in building envelopes - infra-red method. This means that it is not possibleto use thermal imaging surveys to measure U-values or quantify the effects of thermal bridges.

Areas on a thermal image of the inside of abuilding, which appear to have low surfacetemperatures compared to their surroundings, cantherefore be caused by :

a) low emissivity materials; these can usually beidentified visually and a correction factorincluded in the analysis;

b) increased heat flow through the componentcaused by thermal bridging due to the materialspresent or missing insulation;

c) increased heat flow due to moisture increasingthe thermal conductivity of thermal insulation;

d) evaporation of moisture from the surface;

e) cooling of the surface due to cold air infiltration.

The appearance of the thermal image can givesome guide to which of these problems is the likely

cause of any cold areas. For example, missinginsulation or thermal bridging gives a cold patchwith clearly defined edges, wet insulation gives adiffuse cold area and air infiltration has acharacteristically ‘feathery’ appearance.

When a building is surveyed from the outside, theeffect of factors b) and c) will be to increase thelocal external surface temperature compared tosurrounding areas. However, because the effectsof sun, wind and rain tend to blur out the thermalpatterns, external surveys are much less sensitivethan internal ones.

5.2 Conditions for a surveyDetailed guidance on thermal imaging surveys isgiven in a BRE Guide13 and an Energy EfficiencyOffice Best Practice Report14, which describe theconditions that are necessary for a meaningfulsurvey. The thermal conditions to which a buildingis exposed before and during a thermal imagingsurvey are very important. To minimise externalclimatic interference and to maximise thermalresolution the survey should, wherever possible, becarried out from within the building. In general, thefollowing conditions should be met:

For typical masonry constructions, the numericalvalue of the temperature difference between theinside and outside should be at least 3/U,where, U is the U-value of the wall or roof underinvestigation, for at least 24 hours before, andfor the duration of the survey; therefore atemperature difference of at least 8.5˚C isnecessary for a wall with U=0.35 W/m2K. Thislength of time may be relaxed to 12 hours in thecase of lightweight metal structures that respondmore rapidly to changes in temperature.

The outside air temperature variation should besmall and the internal air temperature should notvary by more than ±2˚C.

For at least 12 hours before and for the durationof the survey the building façade underinvestigation should not be exposed to sunshinesufficient to affect the results. The bestconditions are usually found on cold overcastdays.

Page 28: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

with 120mm of mineral wool, with conductivity 0.04W/mK, and there is 25mm of insulation betweenthe liner and the zed-spacer. The outer profiles are35mm deep, at 170mm centres and the linerprofiles are 18mm deep, at 200mm centres.

The U-value of this system can be calculated byvarious methods:

a) Ignoring thermal bridging:In the absence of any bridging from the zedspacer or the profiles, the U-value of the roofwould be 0.32 W/m2K.

b) BRE IP 5/98Graph 5 on page 6 of BRE IP 5/98 gives U =0.36 W/m2K if the profiles are ignoredEquation 3 on page 4 of the IP, gives acorrection of 7 mm for the effect of the linerprofiles compressing the insulation, changingthe insulation thickness to 113mm, graph 5 thengives U=0.38 W/m2K.

c) Combination of two-dimensional modelsFollowing the steps specified in section 3.3.3.2

1) Uliner = 0.34, Uouter = 0.31.2) Rsi + Rse = 0.14, t= 0.12 and k = 0.04 giving Ucomb

= 0.330.3) Th = 0.115 m4) th = 0.0147 m.5) U = 0.40 W/m2K

Therefore ignoring thermal bridging completelyunderestimates the U-value by about 20% andusing IP 5/98 underestimates it by 5%.

Example 2: A composite panel fully filled withinsulationFigure 13 shows a representative section of acladding panel with profiled liner and outer sheets,fully filled with a foam insulation of conductivity 0.02W/mK. The thickness of the insulation, measuredfrom the lowest point of the top surface of the linerto the lowest point on the base of the outer sheet,is 80mm.

Fig 13: Representative section of composite panel

A simple one-dimensional calculation of the U-value taking account of the nominal 80mm ofinsulation alone, gives a U-value of 0.24 W/m2K.Separate two-dimensional calculations of the U-values resulting from the profiled liner and flat outerand profiled outer and flat liner, give : Uouter = 0.24W/m2K and Uliner = 0.25 W/m2K. Combining thesewith equation 8) gives U= 0.25 W/m2K. Although,at the insulation thicknesses necessary to complywith the elemental U-values in Approved DocumentL, the effect of the profiles is small, taking them intoaccount by simple proportional methods givesmisleading answers.

Example 3: Three-dimensional modellingFigures 14 and 15 show the results on an analysisof a detail of a profiled metal roof, containing 80mmof insulation of conductivity 0.037 W/mK betweenprofiled sheets. Aluminium clips, which are isolatedfrom the liner sheet with a thermal break pad, recurregularly at 400mm centres across the roof and at1500mm centres up the roof, these are thereforethe two horizontal dimensions of the model. Thefigures show the temperature on the liner and theheat flow into the roof. Both of these clearly showthe local effect of the thermal bridging due to theclip, despite the thermal pad, with the internalsurface temperature falling from 19.4˚C away fromthe clip to 16.4˚C immediately below the clip, andthe corresponding heat flows rising from 6.6 to 36.5W/m2.

26 15

The external façade must not be visibly wet

For visualisation of air leakage, the internalpressure must be at least 10 Pa lower thanexternal.

It can be seen that the conditions for a successfulsurvey are fairly restrictive. As surveys aregenerally carried out by specialist contractors whomay need to be booked some time in advance, itcan be very difficult to arrange a survey for anappropriate weather window. There may thereforebe a delay of several weeks before a survey can becarried out and if hand over of the building isdependent on completion of a survey, this cancause contractual difficulties. It is much better toremove the need for a survey by being able todemonstrate to a client that the cladding has beenproperly designed and installed.

5.3 Examples BRE has carried out a series of tests on differentmetal cladding systems using the PASSYS testcells at East Kilbride. These are well insulated, airtight, welded steel boxes, with a 2.7 metre aperturein one side - see Figure 25. Each cladding systemwas sealed into a heated test cell and, after thetemperatures had stabilised, an infra-red survey ofthe cladding details was carried out. These wereused to evaluate the suitability of such surveys forassessing the performance of cladding systems.During the surveys, various sealing options wereinvestigated and after testing the basic system, thecells were depressurised to investigate the effect ofair infiltration (see Section 6). Measured areas ofinsulation were then removed to investigate howwell the survey could reveal these ‘defects’.

Fig 25: Cladding panels under test at BRE

Figures 26-29 show examples of the type ofinformation that can be obtained from infra-redsurveys

Fig 26: Twin skin construction with ‘standard’ jointsand seals

Air leakage through the lower perimeter liner fillers,is cooling the bottom rail reducing the surfacetemperature from 19.9˚C to 15.1˚C.

Fig 27: Twin skin construction with improved sealsReducing the air flow has raised the surfacetemperature to 18.5˚C

Fig 28: Twin skin constructionRemoving a 100 x 150 mm section of insulationshows a well defined cold patch about 1.5 - 2˚Ccooler than the surrounding area. There is agenerally cooler region below the dashed line(representing the central horizontal rail) due to

Page 29: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

3.3.2.2 Combination of a profiled liner, a spacerand a profiled outerTo assess the combined effect of the spacer andthe profiled liner and outer sheets, the followingsteps are necessary:

1) Develop two 2D models with a) a flat liner andprofiled outer giving Uouter and b) flat outer andprofiled liner giving Uliner

2) Calculate the total U-value of a combination ofthe liner and outer profile:

Where Ucomb1 is the combined U-value in W/m2K

Uliner is the U-value of the liner profilefrom KOBRU in W/m2K

Uouter is the U-value of the outer profilefrom KOBRU in W/m2K

Rsi and Rse are the inside and outsidethermal resistances in m2K/W

t is the thickness of the insulation in m

k is the thermal conductivity of theinsulation in W/mK

3) Calculate the insulation thickness neededbetween flat faces to give the same U-value thatresulted from the combined inner and outerprofiles i.e. Ucomb.

4) Use a liner profile calculation with the insulationthickness equal to the distance between the linerand spacer to calculate Uliner 2 and use this tocalculate the equivalent thickness of insulationunder the spacer

Fig 11: Calculation of the equivalent thickness ofinsulation under the spacer

5) Insert the two thicknesses derived in 4) and 5)into a 2D model of, for example, a zed spacerroof as shown in Figure 12, giving the bridgedU-value Ucomb2

Fig 12: The equivalent insulation thicknesses in thespacer model

3.3.3 Additional heat loss through repeatingpoint componentsSome features which pass through the insulation,such as the brackets in rail and bracket roofs orfasteners, can increase the heat loss through a roofor cladding. Once the additional heat loss throughan individual bracket or fastner Qadd W/˚C has beencalculated, (using three dimensional modelling), theeffect on the U-value may be calculated from�U = Qadd/nadd , where nadd is the number of suchfeatures/square metre of roof or wall surface.

For example, if a roof with U-value 0.25 W/m2K ispenetrated by 5.5 mm diameter stainless steelfasteners, with Qadd = 0.006 W/˚C, with 1.11fasteners/m2, �U will be 0.007 W/m2K. If steelfasteners with Qadd = 0.014 W/˚C were used, �Uwould be 0.015 W/m2K

3.4 Examples Example 1: A twin skinned roof with zed-spacers that can be assessed by combiningtwo-dimensional modelsThe roof is similar to that shown in Figure 6 with1.6mm steel zed spacers at 1800mm centres. Thespace between the inner and outer sheets is filled

14 27

circulation of cooler air entering the test roomthrough open door.

Fig 29: Twin skin constructionRemoving a 100 x 300 mm piece of insulationleaves a well defined cold area. The bright yellowarea, adjacent to the darker region representing themissing insulation, and the red area on the centralrail are due to the reflection of the inspection lamp.

5.4 Summary of the use of infra-redsurveys1. Infra-red surveys of the envelope of a building

should preferably be done from the inside andideally require calm, dry, cold and cloudyconditions; there may therefore be a considerabledelay before conditions are suitable. Theconditions for external surveys are even morerestrictive.

2. For a survey to be successful, the buildingshould be heated for at least 12 hours before thesurvey, there should be no sun and no rain onthe external surface.

3. Given the right conditions, infra-red surveys canprovide useful qualitative information aboutthermal bridges, air leakage and missing or wetinsulation.

4. The presence of metal components, withemissivities much lower that those of otherbuilding materials, can lead to confusing resultswhich need careful interpretation.

5. The interpretation of infra-red surveys issubjective,requiring experienced staff with aknowledge of metal cladding systems. This maylead to disputes concerning whether an apparentdefect is significant or not.

6. Rather than relying on thermal imaging, with thecomplications and ambiguities summarisedabove, it is preferable to rely on demonstratingsatisfactory design and installation.

6.1 Introduction As buildings become more highly insulated, theeffect of air leakage through the envelope onenergy consumption becomes relatively moreimportant. The new version of Approved DocumentL2 lays more stress on the need to achieve areasonable standard of airtightness, and makessuggestions as to how this might be achieved byappropriate sealing measures. It also suggests thatit may be necessary to demonstrate compliancewith a report from a ‘competent person’ thatappropriate design details and building techniqueshave been used or, for buildings larger than 1000m2

floor area, to carry out an air leakage test.

This section describes the background to airleakage testing and the factors that affect theresults in the case of metal walls and/or roofs. It ishowever, important to remember that the claddingsystem is only one of the areas of the buildingenvelope that contribute to the leakage. Junctionsand openings such as doors, loading bays,windows, rooflights, smoke vents and servicepenetrations may be more important. This sectionwill enable the manufacturers of cladding andassociated components to demonstrate that theirsystems or components are capable of beinginstalled to a specified standard of airtightness

6.2 Whole building testing of airleakage6.2.1 Test methodTechniques for the testing and analysis of the airleakage of buildings are described fully in CIBSEGuide TM23, which should be consulted fordetailed information15.

An air leakage test is carried out by mounting a fan(or fans) in a suitable aperture within the buildingenvelope, usually a doorway (Figure 30); runningthe fan to blow air into the building creates apressure difference across the building envelope.The fan speed is increased slowly to create apressure difference of about 50 Pa (1Pa = 1N/m2).At this setting the air volume flow through the fan,i.e. the air leakage through the building envelopeand the pressure difference across the buildingenvelope, is recorded. The fan’s speed is then

Air tightness

Page 30: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

3.2.3 Three-dimensional modellingBRE IP 5/98 and KOBRU provide realistic methodsfor calculating U-values for those constructions,such as zed-spacers or rails, which contain linearfeatures that can be fully represented as individualor combined two-dimensional cross sections.Some constructions however, contain structuralelements such as aluminium clips that recurregularly both up and across a roof, and causelocal, relatively severe thermal bridging. These haveto be analysed with a full three-dimensional model,which generally has to be individually developed foreach case, a difficult and time consuming processfor a complex detail.

A number of software packages are available thatcan carry out three-dimensional analysis. BREuses a package called TRISCO, which is fullycompatible with BS EN ISO 10211-1 and thereforemeets the requirements of Approved Document L2.

3.3 Theory3.3.1 Calculation of effective U-valuesTo provide an effective U-value of the structure,taking account of the effect of the repeated thermalbridging caused by the spacers etc., a two-dimensional model must extend between the linesof symmetry on either side of a spacer, i.e. if thespacers are at 1800mm centres, the model mustbe 1800mm wide, see Figure 10.

Fig 10:The necessary extent of a 2D model tocalculate effective U-values

Similarly, a three-dimensional model should beextended to the points of symmetry between thespacers in both the dimensions in the plane of thewall or roof.

With inputs of appropriate internal and externaltemperatures and surface resistances (see Table4), a two-dimensional model will output Q2D, thetotal heat flow between inside and outside in W/m;a three-dimensional model will output Q3D in total

heat flow in W. The effective U-value will then becalculated from:

Where : L is the width of the 2D model in m (1.8in the example shown in Figure 10).

A is the area of the 3D model in m2.

Ti and Te are the internal and externaltemperatures in ˚C.

The model will also produce the internal surfacetemperatures necessary to determine the risk ofsurface condensation, see section 4. Also, theinternal surface temperature at the edge of themodel remote from the effect of the spacer etc., Tsi,can be used to calculate the unbridged U-value ofthe structure.

Where : Rsi is the internal surface resistance inm2K/W

3.3.2 Combining two-dimensional calculations3.3.2.1 Combination of a flat liner, a spacer anda profiled outerDevelop two 2D models:

1. A model of the spacer system with flat liner andouter sheets. This will include the specifiedinsulation thickness and any air gap between theouter sheet and the insulation and gives anoverall effective U-value = Uspacer.

2. A model with a flat liner, the specified insulationand air gap as above and a profiled outer sheet.This will give an overall effective U-value = Uouter1

and an unbridged U-value = Uouter2

The combined U-value Ucomb is then calculated asshown below.

28 13

reduced to give approximately equally spacedvalues (ideally between 5 and 10) of pressuredifference, with none lower than 10 Pa, and thereadings repeated at each point

The equipment can vary from a simple fanmounted in a replacement door and powered fromthe building’s electrical supply (Figure 31) thatdelivers up to 1 m3s-1 and is suitable for small‘domestic sized’ buildings, up to large externallymounted fans that have their own power supplyand can supply up to 30 m3s-1 (Figure 32) ; theseare used to test large non-domestic buildings. Insome cases it may be possible to use the building’sown HVAC system air supply fans. The pressuredifference is measured with a micromanometer withan operating range of at least 0 – 60 Pa andaccuracy of ±2 Pa. The external pressure shouldbe measured at a point at least 10m away from thebuilding to minimise local wind effects. The internalpressure must be measured at a point away fromthe direct influence of the pressurisation fan.

Fig 30: Diagrammatic representation of wholebuilding leakage test

Fig 31: Typical ‘Blower Door’ for testing domesticbuildings

Fig 32: Large fan for testing industrial buildings

A pressure test relies on the assumption that thepressure difference is uniform over the entirebuilding envelope. This imposes certain restrictionson the external climate parameters that prevailduring the test. Ideally the internal to externaltemperature difference should be less than 10˚Cand the wind speed should be less than 3 ms-1.Higher temperature differences lead to high stackpressure differences that distort the test results,especially in very tall buildings, and high windspeeds cause random pressure differences, whichmake accurate readings difficult. These conditionsare however, much less restricting than thosenecessary for infra-red surveys described in section5.2.

Page 31: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

3.2.2 Two-dimensional modellingMany metal wall and roofing systems (for examplethe zed-spacer roof shown in Figure 6) containlinear features, such as zed-spacers or spacer railsand liner and outer sheet profiles that, althoughthey run at right angles to each other, interact verylittle. They can therefore be modelled individually intwo dimensions as shown in Figures 7, 8 and 9 andthe results combined to give a realistic U-value ofthe structure. Note that as the models deal withrectangular elements, the inner and outer profileshave been approximated as a series of steps, thisintroduces a negligible error.

Fig 6: Roof with profiles and zed spacers at rightangles

Fig 7: Distortion of temperature and heat flowcaused by zed spacer

Fig 8: Distortion of temperature and heat flowcaused by liner profile

Fig 9: Distortion of temperature and heat flowcaused by outer profile

BRE IP 5/98, describes procedures for determiningthermal performance of some types of insulateddouble-skin metal roof and wall systems commonlyin use in the UK. The procedures, which takeaccount of the thermal bridging caused by thevarious metal connecting paths between the innerliner and outer sheet, are more realistic than othersimplified methods and provide a reasonablyaccurate assessment of the thermal performanceof such a system.

The two-dimensional computer package KOBRU,which is fully compatible with BS EN ISO 10211-1,was used to calculate the U-value of three differentrail and bracket spacer and z-spacer roofs a) with a25mm air gap between the spacer and the liner, b)with 25mm of insulation between the spacer andthe liner and c) with 50mm of insulation betweenthe spacer and the liner. The results revealed thatthe rail and bracket spacer had little effect on thethermal performance and could be ignoredprovided that the brackets are at least a metreapart. For the zed spacers, the U-value wascalculated as a function of insulation thickness,spacer centres and insulation conductivity and theIP includes graphs from which the U-value can beread for any combination of these parameters. ThisU-value can then be corrected for the effect of anycontinuous air spaces above the insulation and theeffect of the liner profiles intermittently compressingthe insulation.

12 29

During a test, all internal doors should be wedgedopen and, where appropriate, combustionappliances must be switched off and any openflues and air supply openings temporarily sealed.Flues from room-sealed appliances, such asbalanced flues in domestic appliances, do not needto be sealed. External doors and other purpose-made openings in the building envelope should beclosed and mechanical ventilation systems turnedoff, with the inlet and outlet grilles sealed. Firedampers and ventilation louvres should be closed.Drainage traps should contain water.

6.2.2 Data AnalysisThe data obtained from a fan pressurisation testconsist of volume flow rates, which need to becorrected for the difference between the density ofwarmer, indoor and colder, outdoor air, for a rangeof internal/external pressure difference values. Aplot of the volume flow rate (Q) versus pressuredifference (Dp) is drawn (Figure 33). The points lieon a curve, called the air leakage characteristiccurve of the building.

Fig 33: Typical results from pressurisation anddepressurisation tests

The relationship between the fan flow rate, andtherefore the air leakage of the building, and thepressure difference is of the form:

Q = C (�p)n (15)

Where C and n are constants that relate to thebuilding under test that can be found bytransforming equation (15) using natural logarithmsto give:

ln(Q) = ln(C) + n.ln(�p) (16)

Plotting ln(Q) against ln(�p) gives a straight linewith slope n and intercept ln(C). C and n are thenused to calculate the conventional value of the flowrate at a pressure difference of 50 Pa:Q50 = C(50)n.This, Q50, normally in m3/h, is reported as theparameter which defines the ‘leakiness’ of thebuilding.

Under very calm conditions, when all the measuredpoints lie close to one curve, Q50 may be estimateddirectly from the measured data; in more windyconditions when there will be considerably morescatter about the curve it is essential to derive Q50

from the values of C and n calculated from thefitted curve. The standard pressure difference of 50Pa is chosen, as it is much greater than the normalwind and stack pressure differences, which are 5 –10 Pa at most. However, this means that the Q50

value does not reflect the air infiltration into abuilding in practice. Comparison of pressurisationtest and tracer gas measurement in buildings hasshown that the following general rule can be usedfor office buildings, the average ventilation rate inair changes per hour is equal to Q50/(S x 60), whereS is the surface area of the walls and roof. As nosimilar comparison has been made for industrialbuildings, this relationship should be regarded as,at best, a very rough approximation.

If a building is tested and just complies with thestandard of 10 m3/h/m2 at 50 Pa specified insection 2.4 of Approved Document L, the total flowrate at 50 Pa, Q50, will be 10 x A m3/h, where A isthe area of walls, roof and floor. Substituting thisfor Q50 in the above expression means that theaverage ventilation rate under typical windconditions can then be estimated as A/(6 x S) airchanges per hour. This can then be used toassess the heat loss due to air leakage as shownin section 6.4.

6.2.3 Location of air leakage The cladding or roofing system is only one of thepossible leakage routes from a building and asimple fan pressurisation test quantifies the total airleakage of a building, but does not directly identifythe leakage paths. There are however, a number ofqualitative and quantitative methods that can be

Page 32: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

Fig 4: Distortion of temperature and heat flowcaused by zed spacer

The 2001 revision to the Approved Document hasintroduced a more rigorous method of dealing withrepeated thermal bridges, which is given in BS ENISO 69464. This standard deals with repeatedthermal bridges using the more complex ‘combinedmethod’, which is specified in more detail in CIBSEGuide A36 and in Appendix B of ApprovedDocument L22. This method carries out twocalculations assuming a) no sideways flow of heatbetween the insulation and bridging elements,which gives a maximum thermal resistance and b)unlimited sideways flow of heat, which gives aminimum resistance. The U-value is then taken asthe reciprocal of the average of these tworesistances. However both the British Standardand Appendix B of the Approved Document make itclear that this method does not apply to metal roofand wall cladding systems.

3.2 Computer modelling 3.2.1 PrinciplesClause B.4 of Approved Document L2, which statesthat the Combined Method for calculated U-valuesdoes not apply to elements containing metalconnecting paths, directs users to BRE IP 5/988 formetal cladding and to BS EN ISO 10211-19 and BSEN ISO 10211-210 for more general cases. Allthese methods are based on two- and three-dimensional modelling of temperatures and heatflows through construction details using a range ofsoftware packages.

The thermal models, that are standardised in BSEN ISO 10211-1, divide the construction to beanalysed into a number of homogenous materialblocks and then impose a two- or three-dimensional

grid over all. Figure 5 shows an example of a two-dimensional grid imposed on a twin skin systemwith a typical rail and bracket spacer detail.

Fig 5: Grid definition for spacer detail

After internal and external temperatures and heattransfer coefficients have been defined, the modelcarries out a series of approximations of increasingaccuracy to calculate the temperatures and heatflows at each of the nodes where the grid linesintersect. The total heat flow, which allows the U-value and temperatures at any specific points ofinterest such as the internal surface to becalculated, can then be displayed.

These models assume steady state internal andexternal conditions and that the material properties,such as thermal conductivity, are unaffected bychanges in temperature. If the model is to provideaccurate results it is essential that:

a) the model is extended away from the thermalbridge either into regions where the heat flow isunaffected by the presence of the bridge or to aline of symmetry between thermal bridges;

b) the grid, which defines the nodes, isappropriately specified, especially in areaswhere materials with very different thermalconductivities are in close contact.

BS EN ISO 10211-1 gives guidelines for both ofthese factors however, appropriate grid definitioncan be difficult, requiring considerable experience,especially in the case of metal roofing andcladding, which a) can contain metal spacers whichare small compared to the extent of the roof and b)has metal and insulation materials directly incontact. Incorrect grid definition can lead to errorsof 10 –20% in the calculated U-value.

30 11

used in parallel to provide more information:

Releasing smoke from smoke pencils or pufferswithin a building that is being pressurised can beused to visualise and identify specific flow paths.

An internal infra-red survey (see Figure 26) of adepressurised building in cold weather willrapidly reveal areas that are being chilled byincoming air.

Repeated testing of a building as successivespecific components are sealed, a techniqueknown as reductive sealing, can quantify thecontribution of each. For example, Figure 34shows the results from an initial test of a buildingas found, which gives a Q50 value of 13.8 m3s-1;sealing around all the window frames with tapeand repeating the test reduces this to 10.5 m3s-1,then sealing around all the doors as well,reduces Q50 further to 7.6 m3s-1.

The air leakage associated with a specificbuilding element or component can be testeddirectly by pressurisation. The component canbe isolated by containing the area of interestwithin a temporary sealed compartment; this hasthe advantage of requiring a smaller fan than isneeded for reductive sealing of a whole building.This method is further refined by the laboratorytest method described in BS EN 12114:2000 -see 6.4.

Fig 34: Results from an ‘as found’ test and twosuccessive stages of reductive sealing

6.3 Air leakage parametersTwo parameters are currently used to quantify theair leakage rate through the building envelope.These are the air leakage index and the airpermeability. Both are measured by the fanpressurisation technique and are expressed in termsof the volume flow of air per hour (m3 h-1) supplied tothe space, per square metre (m2) of buildingenvelope for a specified inside to outside pressuredifference of 50Pa; for example 10 m3h-1m-2 at 50Pa.

The two parameters differ in the way the externalbuilding envelope is defined. The air leakage indexdoes not include the solid ground floor area, whilethe air permeability does include the solid groundfloor. It is not possible to standardise on one airleakage parameter at present, because a)European Standard BS EN 13829 : 200116 andApproved Document L use air permeability and b)the historical database of air leakagecharacteristics that may be used to put a buildinginto context is based on air leakage index. Thechoice of which parameter to use is thereforedependant on the context of use however, forRegulation purposes the air permeability is theessential parameter, i.e. the floor area is taken intoaccount.

6.4 Heat loss due to air leakageThe heat loss from a building due to air infiltrationis given by:

Qleakage = �Cp.V.n / 3600 W/K (18)

Where �Cp is the heat capacity of the air

V is the building volume in m3

n is the ventilation rate in air changesper hour (ach)

As shown in section 6.4.2, if a building is testedand just complies with the standard of 10 m3/h/m2

at 50 Pa specified in section 2.4 of ApprovedDocument L, the average ventilation rate undertypical wind conditions can then be approximatelyestimated as A/(6 x S) ach.

In the case of the notional building discussed insection 4.5 : S = 3644 m2, A = 6044 m2 and

Page 33: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

Metal cladding and roofing systems are made ofcombinations of materials, which differ in thermalconductivity by factors of over a thousand, in closeproximity. This has important consequences for themethods of calculating U-values.

By the early 1990s, it was recognised that manyconstructions contained details, such as mortarjoints in lightweight block work or timber studs inthe insulation of timber framed walls in whichincreased heat flow is caused by higherconductivity elements crossing insulation. The1995 revision to Approved Document L thereforerequired that these features, which are known asrepeated thermal bridges, be taken into accountwith the ‘proportional area method’. This assumesthat heat flow is still one dimensional through thewall or roof, but that the flow is locally higherthrough the bridging elements. For example,Figure 3 shows the temperature and heat flowthrough 100mm of mineral wool bridged by a40mm wide timber stud. It can be seen that,although there is some distortion of the heat flowand temperature fields at the edges of the stud, theflow is generally one-dimensional, with higher flowdensity through the stud at the centre of thepicture.

Fig 3: Temperature and heat flow through aninsulation layer bridged with a timber stud

The total heat flow and therefore the U-value arecalculated by adding the contributions of eachelement in proportion to their contribution to thetotal area. The thermal resistance of each layer ofthe construction that contains repeated thermalbridges is calculated from:

Where Fbr is the fraction of the wall area occupiedby the repeating thermal bridges

Rbr is the thermal resistance of therepeating thermal bridges in m2K/W.

Rnb is the thermal resistance of theremaining unbridged wall in m2K/W.

The individual layer thermal resistances are thenadded up as before to calculate the U-value withequation (1). This method assumes that there is nosideways flow of heat between the unbridged andbridged elements and therefore tends tooverestimate the thermal resistance andunderestimate the U-value.

This procedure assumes that, as shown in Figure3, a) the repeating thermal bridges are reasonablylarge, occupying say 10% of the wall area and b)the conductivity of the bridge is not very differentfrom the insulation; for example, the conductivity oftimber is only four times that of mineral wool.Metal roofs and cladding systems, on the otherhand, a) contain details in which the insulation isbridged by thin steel elements, such as zedspacers in a profiled metal roof, which occupy only0.1% of the area and have conductivities over athousand times higher than the insulation, and b)have profiled liner and outer sheets. Both of thesefactors cause distortions to the heat flow largeenough to make the proportional area method veryinaccurate. These lead to temperature and heatflow distributions like those shown in Figure 4, asection through a steel zed-spacer whichpenetrates 120mm of mineral wool. It is evidentthat heat flow is very far from one-dimensional inthis case.

It was recognised, therefore, even before the 1995Approved Document was available, that specialtechniques were needed for metal roofs andcladdings. The MCRMA and BRE collaborated ina computer modelling exercise to produce anInformation Paper IP 5/988, which gives morerealistic U-values than the proportional area orcombined methods for some metal claddingsystems.

10 31

V = 15444 m3. The ventilation rate, n, will be 0.28ach. Substituting these values into Equation (18)gives: Qleakage = 1502 W/K

The total fabric loss estimate in section 4.5 was2361 W/K, giving a total loss of 3863 W/K, 61% ofwhich is through the fabric and 39% by air leakage.

6.5 Laboratory tests for individualcomponents Individual components, a window in its frame or aspecific area of a liner sheet, with representativelaps, for example, can be tested in the laboratorywith the methods specified in BS EN 12114:200017.This involves sealing the component into a rigid airtight frame and measuring the flow rate resultingfrom a series of positive or negative pressuredifferences applied across it (Figure 35).

Fig 35: Diagram of laboratory air tightness apparatus

This test can provide values of a parameter that isuseful for characterising metal cladding and roofingsystems, the leakage per linear meter of joint orside lap, R50,j. This is derived by identifying the flowthrough an individual joint (Q50,j) by reductivesealing and then dividing by the length of jointunder test (lj).

R50,j = Q50,j /lj (19)

Once this is known for each type of joint in abuilding, the building leakage rate Q50 can beestimated from :

Where Lj is the total length of each type of joint inthe building. Section 6.6.2 gives an example ofusing the results from small scale tests to estimatethe air leakage from a building and the effect ofproviding additional seals.

6.6 Examples of testing carried out atBRE6.6.1 Test methodIn parallel with the infra-red surveys, described insection 5, BRE has been carrying out a series ofpressurisation tests on different metal claddingsystems at East Kilbride. Each cladding systemwas sealed into the PASSYS test cell anddepressurised as described above. A series ofrepeat tests was then carried out with varioussealing options to identify the contributions ofindividual joints. Two site assembled profiled metalwall constructions and two metal faced compositepanel wall constructions were tested.

6.6.2 Site assembled systemsThe two systems tested were:

a) Twin skin wall of typical construction intended toachieve the 1995 Approved Document L U-value of0.45 W/m2K

This was made up of profiled liner and outersheets, containing 83mm of glass wool insulationand a rail and bracket spacer system. The linerside laps and the liner vertical perimeter were notsealed. Liner fillers were included in the top andbottom horizontal perimeter and there wereapproximately four fasteners/metre, as is typicallyused at these points. There were no seals or fillersto the outer sheets.

b) Twin skin wall intended to achieve the originallyproposed U value of 0.30 W/m2K and achieve theair tightness requirements of Approved DocumentL2 :2001.

This was made up of profiled liner and outersheets, containing 135mm of glass wool insulationand rail and bracket spacer system. The liner sidelaps and the liner vertical perimeter were sealedwith butyl tape. Liner fillers were included in thehorizontal perimeter, as before, but withapproximately ten fasteners/metre to improve thecompression of the fillers. There were no seals orfillers to the outer sheets.

The effect of sealing the three possible leakagepaths shown on Figure 36 on the leakage wasinvestigated.

Page 34: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

3.1 The development of U-valuecalculation methodsThe standard measure for calculating the heat lossthrough the building fabric is the U-value. Thisconcept, which has been in use for many years,applies to plane areas of the walls or roofs anddoes not take account of any extra heat loss at thejunctions between elements or around window andother openings, known as thermal bridges.

Until 1995, the Approved Document required thatall U-values were calculated by assuming thatconstructions could be represented by a series ofuniform layers as shown in Figure 1.

Fig 1: Construction made up of uniform layers

Fig 2: Temperature and heat flow through uniformconstruction

Figure 2 shows the temperature distribution fromwarm (red) to cold (blue) and heat flow lines withina uniform construction. In this case the heat flow ispurely one dimensional and the U-value is easilydefined as the reciprocal of the sum of the thermalresistances of the layers making up the structureand the internal and external surface resistances.So for a wall or roof containing n parallel layers:

Where Rso is the external surface resistance inm2K/W

Ri is the thermal resistance of the ith

layer in m2K/W

Rsi is the internal surface resistance inm2K/W.

Standardised values of the surface resistances arequoted in BS EN ISO 69464 Table 2, and CIBSEGuide A3

6, section 3.3.9 (See Table 4).

Table 4: Surface resistances in m2K/W

The thermal resistance of a material, R, dependson its thickness and thermal conductivity

R = d / � m2K/W (2)

Where: d is the thickness of the material in m;

� is the thermal conductivity in W/(mK).

Thermal conductivity values are tabulated in theCIBSE Guide A.36 Appendix 3.A7 and in BS EN12524 : 20007

Table 5 summarises typical values of some of themore important materials that are used in metalclad buildings. Conductivity values can vary andthe Approved Document allows the use of properlydocumented manufacturer’s values.

Table 5: Thermal conductivities of typical materials

32 9

Methods for calculating heatloss through plane areas ofcladding and roofing systems

Rsi

Rso

Upwards

0.10

0.04

Horizontal

0.13

0.04

Downwards

0.17

0.04

Direction of heat flow

MaterialMetalsSteelStainless steelAluminiumCopper

Other materialsTimberPVCPolyester resinPolycarbonate

InsulantsGlass fibreMineral woolExpanded polystyreneUrethane

Conductivity W/mK

6017160380

0.140.170.200.20

0.0400.0370.0350.022

Table 9: Results from pressurisation tests of siteassembled system

Fig 36: Areas of built up panel tested for airleakage

The results from this type of test can then be usedto assess the effect on leakage from a wholebuilding - see section 6.7.

6.6.3 Composite panel

Two flat composite panels wall constructions weretested:

a) Standard panels designed to achieve the 1995Approved Document L U-value of 0.45 W/m2K

This was made up of standard factory madepanels with profiled liner and outer sheets,containing 50mm of rigid urethane insulation.The panel to panel side joints had standardfactory installed compressible seals, the verticalperimeter and upper horizontal junctioncontained butyl seals. The lower horizontalperimeter was sealed with a butyl tape trapped

between the panels and lower horizontal rail, butlight could be seen from the outside indicatingthat the seal was not completely effective.

b) Sealed panel to achieve the proposed U-valueof 0.30 W/m2K

This was made up of standard factory madepanels with profiled liner and outer sheets,containing 80mm of rigid urethane insulation.The panel junctions, vertical perimeter andupper and lower horizontal junctions allincorporated additional sealing.

The effect on infiltration of sealing the four possibleleakage paths, shown in Figure 37, wasinvestigated.

In this case the dominant leakage path was thehorizontal gap at the base of the panel. Sealingthis eliminated 90% of the infiltration.

Table10: Results of pressurisation testing ofcomposite panels.

Fig 37: Areas of composite panel tested for airleakage

Description(see figure below)

Currentstandard

Improved

(1)Panel seam

(2)Lower horizontalperimeter junction

(3)Upper horizontalperimeter junction

(4)Vertical perimeterjunction

0.5

11.7

1.6

0.3

0.1

0.7

0.6

0.1

Air leakage at 50Pa[m3/h per linear meter]

Description(see figure below)

Currentstandard

Improved

(1)Liner sheetoverlaps

(2)Upper & lowerhorizontalperimeterjunctions

(3)Vertical perimeter

junctions

2.3

8.6

10.4

less than 0.1

1.1

less than 0.1

Air leakage at 50Pa[m3/h per linear meter]

Page 35: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

a) providing a reasonably continuous air barrier incontact with the insulation layer over the wholethermal envelope (including separating walls).Special care should be taken at junctionsbetween elements and around doors andwindows openings. For domestic typeconstructions, some satisfactory design detailsand installation practice are described in therobust details publication. Guidance for thedesign of metal cladding and roofing systems tominimise air infiltration is given in the MCRMATechnical Paper No 14.

b) Sealing gaps around service penetrations.

c) Draught-proofing external doors and windows.

Section 2 of the Approved Document containsrequirements for demonstrating that the completedbuilding has achieved a good standard ofairtightness and establishes a performancestandard:

2.2 Air barriers should be installed to minimise theadverse effects of air infiltration (see paragraph1.19). In this case too, certificates or declarationsshould be provided or obtained by the personscarrying out the work, stating:

a) for buildings of any size, that the results of airleakage tests carried out in accordance withCIBSE TM23 are satisfactory; or

b) alternatively for buildings of less than 1000m2

gross floor area, that appropriate design detailsand building techniques have been used, andthat the work has been carried out in ways thatcan be expected to achieve reasonableconformity with the specifications that have beenapproved for the purposes of compliance withPart L2.

2.3 Certificates or declarations such as thosementioned in paragraphs 2.1 and 2.2 may beaccepted by building control bodies as evidence ofcompliance. The building control body will however,wish to establish, in advance of the work, that theperson who will be giving the certificates ordeclarations is suitably qualified.

2.4 If using the CIBSE TM 23 pressure proceduresas the means of showing compliance:-

a) With effect from 1 October 2003, reasonableprovision would be test results showing that theair permeability (see paragraph 0.20) does notexceed 10 m3/h/m2 at an applied pressuredifference of 50 Pa.

b) In the period up to and 30 September 2003,reasonable provision in the event that initial testresults are unsatisfactory would be the results offurther tests carried out after appropriateremedial work showing:-

i) An improvement of 75% of the differencebetween the initial test result and the targetstandard of 10 m3/h/m2 at 50 Pa, OR, if lessdemanding

ii) A performance no worse than 11.5 m3/h/m2 at50 Pa.

Section 6 discusses methods of meeting thisrequirement.

8 33

6.7 Example of the effect of individualjoint leakage on whole claddingleakageTo illustrate the method of combining individual jointleakages to give the overall leakage from thecladding system, Figure 38 shows the building thatwas used to illustrate heat loss through thermalbridges in section 4.5. It is assumed that the wallsare covered with horizontal composite panels eachone metre wide by five metres long and the roof iscovered in a site assembled system with linersheets of the same size.

Fig 38: Typical industrial building showing leakagepaths at joints

Table 11 shows the length of each joint in theexternal envelope and the leakage characteristicsfor a standard construction and one upgraded withadditional seals. It should be noted that, at many ofthe details, for example the ridge and valley gutter,two sheets/panels meet; the length of joint will

therefore be twice the length of the detail. Theleakage values for each joint are based, as far aspossible, on the values measured in the BRE testsdiscussed in section 6.6; it should be recognisedhowever, that appreciably higher values may befound in practice.

Setting the leakage rates out like this readilyidentifies the contribution of individual leakagepaths facilitating the development of an appropriatereduction strategy, if necessary.

The exposed area of the building envelope, whichincludes the ground floor, is 6044 m2. This meansthat the air permeability for the cladding part of thenotional building is 2.68 m3/h/m2 at 50 Pa. Thisreduces to 0.23 m3/h/m2 at 50 Pa for the improvedbuilding. Both of these are well within the limit of10 m3/h/m2 at 50 Pa, imposed by ApprovedDocument L2. This suggests that metal claddingwhen properly installed to current standards,may be able to meet the requirements of Part L ofthe Regulations. It is however, important toemphasise two considerations here:

1) This calculation has assessed only the loss fromthe cladding, not the loss from the other parts ofthe building, such as blockwork walls at groundlevel and all the various penetrations of the walls

1995 standard Improved

Lengthm

Leakagem3/h/m @ 50 Pa

Total leakagem3/h at 50Pa

Leakagem3/h/m @ 50 Pa

Total leakagem3/hr @ 50Pa

12345

67891011

WallsBase perimeterSide jointTop perimeterEnd jointCorners

RoofEavesVergeRidgeValley gutterEnd lapsSide lapsTotal

200100020043248

12080.3240120480

2360

11.70.50.31.611.7

8.610.48.68.62.52.5

234050060691562

1032835

2064103212005900

16216

0.70.10.10.60.7

1.10.21.11.10.10.1

1401002025934132

16264132482361381

Table11:Contribution of individual joints to leakage from the cladding

Page 36: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

1.11 An alternative way of meeting therequirements would be to demonstrate bycalculation or by adopting robust design practicesthat the performance of the building fabric is atleast as good as it would be by following paragraph1.10. BRE IP 17/01 and the MCRMA TechnicalPaper No 14 illustrate how this can be done.

See section 2.5 for discussion of BRE IP 17/015.

Section 2 of the Approved Document containsrequirements for demonstrating the thermal qualityof the completed building.

2.1 To avoid excessive thermal bridging,appropriate design details and fixings should beused (see paragraph 1.9). Responsibility forachieving compliance with the requirements of PartL rests with persons carrying out the work. In thecase of new buildings, that “person” will usually be,e.g. a developer or main contractor who has carriedout the work subject to Part L, directly or byengaging a subcontractor. The person responsiblefor achieving compliance should (if suitablyqualified) provide a certificate or declaration thatthe provisions meet the requirements of Part L2(a)(i.e. limiting the losses and gains through the fabricof the building); or they should obtain a certificateor declaration to that effect from a suitably qualifiedperson. Such certificates or declarations wouldstate:

a) that appropriate design details and buildingtechniques have been used and that the workhas been carried out in ways that can beexpected to achieve reasonable conformity withthe specifications that have been approved forthe purposes of compliance with Part L2; or

b) that infra-red thermography inspections haveshown that the insulation is reasonablycontinuous over the whole visible envelope.BRE Report 176 gives guidance on the use ofthermography for building surveys.

Section 4 discusses methods of meeting thisrequirement and section 5 discusses methods ofcarrying out infra-red surveys.

2.5 BRE IP 17/01BRE IP 17/015 gives the requirements for limitingthe risk of surface condensation or mould growth atnon-repeating thermal bridges and describes howto assess their thermal performance and how toincorporate the additional heat loss with thatthrough the remaining building fabric. Theguidance is intended for thermal bridges that arenot as recommended in the guide to ‘domestic’robust construction details and forms the basis ofthe treatment of the details in this BRE/MCRMAguide. For these details, it requires:

a) the calculation of the minimum temperaturefactor, fmin, on the inside surface of the thermalbridge and imposes limits on this depending onthe use of building and whether condensation ormould growth is likely to be a problem;

b) the calculation of the transmission heat losscoefficient or �-value (pronounced ‘psi value’)associated with the thermal bridge and imposeslimits on the total heat loss through all thethermal bridges in the building as a proportion ofthe heat loss through the unbridged fabric (i.e.the heat loss that takes account of the U-valuesof the plane areas).

Methods of calculating fmin and � anddemonstrating compliance with the Regulations arediscussed in sections 4.2 and 4.3 respectively. Arange of metal cladding and roofing details, thatshould cover most buildings currently beingdesigned and constructed are shown in theAppendix, together with appropriate fmin and�-values.

2.6 Building air leakageThe Approved Document requires that:

1.17 Buildings should be reasonably airtight toavoid unnecessary space heating and coolingdemand and to enable the effective performance ofventilation systems.

1.19 A way of meeting the requirement would be toincorporate sealing measures to achieve theperformance standard given paragraph 2.4. Someways of achieving satisfactory airtightness include:

34 7

and roof. These have to achieve the samestandard if the building is to meet the Part Lcriterion on testing.

2) As has been emphasised, the leakage valuesabove have assumed that the cladding has beenproperly installed to current standards.Measurements quoted in CIBSE Guide TM23,have shown that many industrial buildings in theUK are very leaky and would fail if tested to thePart L standard. However well designed asystem is; it will fail and require expensiveretesting, possibly delaying the completion of acontract by many weeks, if it has not been wellinstalled. It is therefore essential that installationis carried out by experienced contractors, is wellsupervised and follows the claddingmanufacturer’s guidance.

6.8 Summary of methods for airleakage testing of metal roofing andcladding1. Pressurisation testing of whole buildings gives a

good estimate of their energy loss from airleakage in practice.

2. The contribution of individual areas of thebuilding envelope to the overall leakage can beidentified and quantified by the use of smoketubes, infra-red surveys and reductive sealing.

3. The leakage through individual cladding systemsand other components and the effect of sealingjoints etc. can be measured in laboratory tests.The results from these tests can be scaled up toquantify the leakage contribution of well installedcladding to the leakage of a full scale building.

4. Details currently in use and installed to a goodstandard may meet the air leakagerequirements of Part L; however it isrecommended that side and end laps/joints andall perimeter joints should be effectively sealed,not only to reduce the air leakage but also toprovide vapour control.

5. However well designed a system is: it will fail andrequire expensive retesting, possibly delaying thecompletion of a contract by many weeks, if it hasnot been well installed. It is therefore essentialthat installation is carried out by experiencedcontractors, is well supervised and follows thecladding manufacturer’s guidance.

The following pages present some common detailsthat occur in industrial and commercial buildingswith metal cladding which are likely to lead tothermal bridges that affect the internal surfacetemperature and heat loss from the building. Theirlocations are shown on Figure 24. For each detail,the following information is presented:

1) A brief description of the detail and the possiblecauses of thermal bridging;

2) A diagram of a typical detail, with the importantfeatures that are likely to lead to thermal bridgeshighlighted.

3) The fmin and �-values of the standard detail thatdetermine its performance, calculated with Uwall

= 0.35 W/m2K and Uroof = 0.25 W/m2K.

4) In those cases where the usual detail is likely tolead to problems of low surface temperatures(low fmin-value) or high heat flow (high �-value),a range of modifications that might be made toimprove performance are discussed and theresulting fmin and �-values presented.

The diagrams are only intended to be indicativeand concentrate on thermal bridging issues. The fmin

and �-values quoted are typical of each detail;slightly different values may be calculated for aspecific system. Cladding manufacturers’ details fortheir specific systems should be used for design,provided that a cladding design on a particularbuilding adopts the same principles regardingthermal bridging, which are outlined in thediagrams and text. This Appendix should be readin conjunction with Section 4, which explains thesignificance of the f-value and the �-value, andhow to decide on appropriately detailed designs fora particular building.

The f-values and �-values shown in the sectionsbelow can be used directly by manufacturers anddesigners to demonstrate compliance with therequirements of Part L as shown in sections 4.2and 4.3 of this Technical Paper and in BREInformation Paper IP 17/01. The features thatcause thermal bridging at junctions, openings andother penetrations of the insulation are generally

Appendix : Details

Page 37: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

2.3 Maximum areas of windows, doorsand rooflights1.12 Provision should be made to limit the rate ofheat loss through glazed elements of the building.One way of complying would be to limit the totalarea of windows, doors and rooflights so that theydo not exceed the values given in Table 2 - unlesscompensated for in some way.

Table 2: Maximum area of openings unlesscompensating measures are taken

Trade off between construction elements1.14 In order to provide greater design flexibility,the U-values of construction elements and theareas of windows, doors and rooflights may varyfrom the values given in Table 1 and Table 2provided that suitable compensating measures aretaken. If glazing areas are reduced from thosegiven in Table 2, special care needs to be given toconfirm that levels of daylight are adequate.Guidance on designing for daylight is contained inCIBSE LG10.

1.15 Compliance with provisions of Part L would beachieved if:

a) the rate of heat loss from the proposed buildingdoes not exceed that from a notional building ofthe same size and shape that meets the criteriaset out in Table 1 and 2; and

b) the U-value of any part of an element is noworse than the values given in the followingTable 3.

Table 3: Poorest U-value acceptable when tradingoff between elements

Notes: 1 Whilst parts of these elements may (withinthe limits given in this table) have poorer U-valuesthan those given in Table 1, it will not normally bepractical to make sufficient allowances elsewherein the design for the whole element to be built tothese standards.

1.16 As further constraints on these methodshowever,

a) if the U-value of the floor in the proposedbuilding is better than the performance given inTable 1 with no added insulation, the betterperformance standard is to be adopted for thenotional building; and

b) if the area of openings in the proposed buildingis less than the values shown in Table 2, theaverage U-value of the roof, wall or floor cannotexceed the appropriate value in Table 1 by morethan 0.02 W/m2K.

c) no more than half the allowable rooflight areacan be converted into an increased area ofwindows and doors.

2.4 Thermal bridging at junctions andaround openingsThe Approved Document requires that

1.9 The building fabric should be constructed sothat there are no significant thermal bridges orgaps in the insulation layer(s) within the variouselements of the fabric, at the joints betweenelements and at the edges of elements such asthose around window and door openings.

1.10 One way of demonstrating compliance wouldbe to utilise details and practice that have beenindependently demonstrated as being satisfactory.For domestic style construction a selection of suchsatisfactory details is given in the robustconstruction details publication.

6 35

Building Type

Industrial andstoragebuildings

Windows anddoors as % of

the area ofexposed wall

15

Rooflights as% of area of

roof

20

Element

Parts of roof 1

Parts of exposed wall or floor1

Poorest acceptableU-value (W/m2K)

0.35

0.70

similar in both twin skin and composite panelsystems. The diagrams in the sections belowtherefore represent both systems. So, for example,a twin skin corner is shown in Figure A.1 and acomposite panel corner is shown in Figure A.2. Inthe figures, the features particularly relevant tothermal bridging are marked with bold italics.

Fig A.1: Corner detail in built-up system

Fig A.2: Corner detail in composite panel

Detail 1 : Roof Ridge

Provided that the insulation is continuous over theridge (as shown in Figures A.3 and A.4) and thedetail contains no metal crossing the insulation,other than any spacers normally present in the roofpanels (which are taken into account in thecalculation of the plane area U-value) this detailcauses a negligible thermal bridge.

Fig A.3: Built-up roof ridge

Fig A.4: Composite panel roof ridge

Summary of roof ridgeInsulation continuous over the ridge fmin = 0.91

� = 0.01 W/mK

Detail 2 : Roof EavesPossible thermal bridging can result if the liner ofthe roof extends across the wall insulation to touchthe outer trim. A gap between the wall and roofpanels can introduce cold air directly to the liner.

Leaving a gap of only 5mm between the roof linerand the outside trim can give significantly betterperformance however, stopping the roof liner shortat the wall liner as shown in Figures A.5 and A.6,gives the best performance. Filling any gapbetween the wall and roof panels with anappropriate site applied insulation is also importantfor optimum performance.

Page 38: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

* Built-up metal or composite panel roofs are regarded as having integral insulation; this category is notincluded in Scottish Technical Standard J.

+ This value is 0.30 W/m2K in Scottish Technical Standard J.

but can be applied to any building type. Tocomply with the provisions of Part L, the annualcarbon emissions from the building should be nogreater than that from a notional building thatmeets the compliance criteria of the ElementalMethod. The carbon emissions from the pro-posed building and the notional building need tobe estimated using an appropriate calculation tool.

Many of the issues covered by the ApprovedDocument are the concern of the architect orservices installer and manager of the building.There are three issues, covered in this guide, thatare of special relevance to the building designers,and the designers, manufacturers and installers ofmetal cladding and roofing systems. These are:

energy efficient design of the complete buildingfabric;limiting the effect of thermal bridging, e.g. atjunctions, openings and penetrations;limiting air leakage through the building envelope.

2.2 Energy efficient design of thebuilding fabric 1.7 To show compliance following the ElementalMethod, the building envelope has to providecertain minimum levels of insulation…

1.8 The requirement will be met if the thermalperformances of the construction elements are noworse than those listed in Table 1

As well as lowering the required values, theApproved Document requires more rigorousmethods for calculating U-values, which take fullaccount of heat loss through repeating thermalbridges, such as spacers etc.

0.15 U-values should be calculated using themethods given in :

- for walls and roofs: BS EN ISO 6946.

The details of the BS EN ISO 69464 method aregiven in Appendix B of Approved Document L2however, it is made clear that this method does notapply to metal systems.

Appendix B: Calculation of U-values using theCombined Method

B4 The procedure in this appendix does not applyto elements containing metal connecting paths,for which the reader is directed to BRE IP 5/98for metal cladding, CAB and CWCT guidancefor curtain walls, and to BS EN ISO 10211-1and –2 for other cases

Section 3 describes how to calculate appropriateU-values using a number of analysis tools.

36 5

Exposed element U-value – W/m2K

Pitched roof with insulation between rafters 0.20

Pitched roof with insulation between joists 0.16

Flat roof or roof with integral insulation* 0.25

Walls, including basement walls 0.35+

Floors, including ground floors and basement floors 0.25

Windows, roof windows and personnel doors, (area weighted average for thewhole building), glazing in metal frames 2.2

Windows, roof windows and personnel doors, (area weighted average for thewhole building), glazing in wood or PVC frames 2.0

Rooflights 2.2

Vehicle access and similar large doors 0.7

Table 1: Standard U-values of construction elements

Fig A.5: Built up roof eaves

Fig A.6: Composite panel roof eaves

Summary : roof eavesRoof liner extends to touch the fmin = 0.76outer sheet or trim of wall, air �= 0.25 W/mKgap between wall and roof

5mm gap between roof liner fmin = 0.90and wall outer, air gap filed with �= 0.07 W/mKinsulation

Roof cladding liner taken back fmin = 0.95to wall liner, air gap filled with �= 0.01 W/mKinsulation as Fig A.5 or A.6

Detail 3 : Roof VergeThere are two possible thermal bridges in thissituation:

a) If the liner of the roof crosses the wall insulationto touch the outer sheet of the wall (or viceversa); the roof liner should be stopped levelwith the wall liner - see Figure A.7.

b) If a void is left between the roof and wallinsulation; this should be filled with site installedinsulation. - See Figure A.8.

Fig A.7: Built up roof verge

Fig A.8: Composite panel roof verge

Summary : roof vergesRoof cladding and liner cut fmin = 0.79across wall insulation (or vice versa) �= 0.28 W/mK

Roof cladding stops short of wall fmin = 0.85liner, void unfilled �= 0.20 W/mK

Roof cladding stops short of wall fmin = 0.95liner, void filled with site installed �= 0.02 W/mKinsulation as Figs A.7 and A.8.

Detail 4 : Valley GutterThis detail can cause a very severe thermal bridgeif the metal outer layer of the gutter top and roofliner cut across the gutter insulation.

Fig A.9: Valley gutter in built up roof

Page 39: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

The new Approved Document includes a widerange of new requirements, including improvedefficiency of heating, mechanical ventilation and airconditioning systems, improved control of heating,hot water supply and lighting. However, the mostimportant changes with significant potential impactson the metal cladding and roofing industry are:

The U-values required for walls and roofs aresignificantly lower and more rigorous methods ofcalculating U-values have been introduced.It is required that more attention is given tothermal bridging at, for example, junctions andopenings.It is required that more attention is given tolimiting air leakage through the buildingenvelope.Post construction thermal imaging and airinfiltration testing may be required todemonstrate compliance with the Regulations.

A guide to ‘robust construction details’ for ‘domestictype constructions’

3that meet the requirements of

the Regulations, and do not lead to problems ofcondensation and mould or air infiltration, has beenpublished in association with the ApprovedDocuments (although it is relevant mainly toApproved Document L1, it also applies to, forexample, schools or small office buildings coveredby L2 but built with ‘domestic style’ details). Thispresent document provides guidance to assistbuilding designers and manufacturers and installersof metal cladding and roofing systems andassociated components to meet the requirementsof the new Approved Document L2 relevant to thebuilding fabric (i.e. it does not cover issues such asheating, hot water supply and lighting that arecovered in Approved Document L2). TheApproved Document makes reference to thisMCRMA/BRE guide as a means of demonstratingcompliance with the Regulations. ScottishTechnical Standard J does not reference either the‘domestic’ robust details or the current document.

2.1 Requirements of the ApprovedDocumentThe essential requirement of Approved DocumentL2 is summarised in the opening sentence ofclause 1.1 - all text in italics below is a direct quotefrom the Approved Document.

1.1 In order to achieve energy efficiency inpractice, the building and its services systemsshould be appropriately designed (Section 1) andconstructed (Section 2).

There are three methods of demonstratingcompliance with the standard, all of which involveconsideration of the design and construction ofthe building fabric and the design and operation ofthe services.

1.6 Three methods are given for demonstrating thatreasonable provision has been made for theconservation of fuel and power. These differentmethods offer increasing design flexibility in returnfor greater demands in terms of the extent ofcalculation required. However the overall aim is toachieve the same standard in terms of carbonemissions. The methods are:

a) an Elemental Method (paragraphs 1.7 – 1.68).This method considers the performance of eachaspect of the building individually. To complywith the provisions of Part L, a minimum level ofperformance should be achieved in each of theelements. Some flexibility is provided for tradingoff between different elements of theconstruction and between insulation standardsand heating system performance.

b) a Whole Building Method (paragraphs 1.69 –1.73). This method considers the performance ofthe whole building. For office buildings, theheating, ventilation, air conditioning and lightingsystems should be capable of being operatedsuch that they will not emit no more carbon thana benchmark based on the ECON 19 data.Alternative methods are also provided forschools and hospitals.

c) a Carbon Emissions Calculation Method(paragraphs 1.74 – 1.76). This method alsoconsiders the performance of the whole building,

4 37

Approved Document L2

Fig A.10: Valley gutter in composite panel roof

Making the gutter liner more robust and replacingthe gutter outer with a lower conductivity materialsuch as plastic where it cuts across the insulationwill reduce the thermal bridge, if the roof liner isstopped short as well so that the insulation layer iscontinuous, the thermal bridge will be largelyeliminated (Figure A.9). if the gutter could be madeas in Figure A.10, thermal bridging would benegligible.

Summary : valley guttersMetal gutter outer and roof liner fmin= 0.81crossing insulation (typical �= 1.50 W/mKcurrent construction)

Crossing gutter insulation with fmin = 0.95plastic with k=0.2 W/mK instead �= 0.17 W/mKof metal, liner stopped short asFig A.9

Gutter as Fig A.10 fmin = 0.95 �= 0.15 W/mK

Detail 5 : Drip sill at the base of a wallpanel supported on a masonry wall orground floor slabThis thermal bridge is particularly important as itoften extends the full length of the buildingperimeter. The intensity of the thermal bridgedepends on the interaction between the detailing ofthe cladding panel and the masonry wall and floorslab to which it is fixed.

If the cladding is connected to the wall or slab asshown in Figure A.11 or A.12, a very severethermal bridge is caused by conduction a) throughthe blockwork and brickwork, and b) through thesteel flashing, which is connected directly to theliner of the wall cladding. Use of lightweight

blockwork, or screed on a floor slab will reduce theseverity slightly; replacing the steel drip with plasticwill bring some further improvement.

Fig A.11: Drip sill in built up wall

Fig A.12: Drip sill in composite panel wall

Fig A.13: Modified drip sill in built up wall

Fig A.14: Modified drip sill in composite panel wall

More significant improvement can be achieved bymoving the drip so that it is fixed to the outer sheetof the cladding and installing a trim, fixed to theouter sheet and wall/floor. This trim supports sitefixed insulation infill that covers the top of the wall

Page 40: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

should be quoted by the manufacturer. Theresults from these tests can be scaled up toestimate the leakage contribution of thecladding to the leakage of a full scale building,provided the cladding has been properlyinstalled.

6. Small scale tests have shown that properlyinstalled metal cladding will already complywith the new air leakage requirements and thatadditional sealing of internal side laps andvertical and horizontal perimeter joints willsubstantially further reduce the air leakagethrough the cladding systems of buildings to avery low level. The MCRMA thereforerecommends that side and end laps/joints andall perimeter joints should be effectively sealed,not only to reduce the air leakage but also toprovide vapour control. Attention has to bepaid to the leakage through all associatedelements within the envelope.

7. However well designed a system is; it will failand require expensive retesting, possiblydelaying the completion of a contract by manyweeks, if it has not been well installed. It istherefore essential that installation is carriedout by experienced contractors, is wellsupervised and follows the claddingmanufacturer’s guidance.

As part of the government’s programme to reducethe effects of global warming by limitinggreenhouse gas emissions from buildings,transport and industry, the 1995 version ofApproved Document L Conservation of fuel andpower 1, which applies until April 2002 has beenextensively revised. After consultation with industryand research bodies, an initial revised version ofthe Approved Document was published forconsultation in June 2000. After the replies fromthe consultation had been considered a reviseddocument was published as an ‘interim draft’, inApril 2001. After minor revisions and editorialchanges this version was published in October2001 and will come into force in April 2002. Thepublished Approved Document is available in twovolumes; L1, covering domestic buildings, and L2,covering buildings other than dwellings. This guidecovers the provisions of L22.

Approved Document L2 applies to only Englandand Wales, Scottish Technical Standard JConservation of fuel and power has been revised inparallel and will come into force at the same time.The revisions are generally the same as inApproved Document L2, with some significantdifferences:

• The elemental U-value for walls is required to be0.30 W/m2K, compared to 0.35 W/m2K inEngland and Wales.

• The category ‘roofs with integral insulation’ witha required U-value of 0.25 W/m2K, that wouldapply to both site assembled and compositepanel roofs in England and Wales does notappear in the Scottish Standard. Roofs up to a10˚ slope will be assessed as flat roofs requiring0.25 W/m2K, but it is possible that steeper roofscould be assessed as a pitched roof withinsulation between the rafters requiring 0.20W/m2K.

• The BRE IP 17/01 that covers thermal bridgingis not referenced in the Scottish Standard, thereis instead many more references to the BREReport Thermal insulation: avoiding risks.

• There is no requirement for post-completionthermal imaging surveys or pressurisationtesting in Scotland.

38 3

Introduction

or edge of the floor slab and extends 100mm downthe wall or slab; see Figure A.13 or A.14. Again, itis preferable to use a lightweight block or screed.

Summary: Drip sills1. As Fig A.11 or A.12

Medium weight blockwork (k=0.6) fmin = 0.48and steel flashing �= 1.10 W/mK

Light weight blockwork (k=0.11) fmin = 0.54and steel flashing �= 0.91 W/mK

Medium weight blockwork (k=0.6) fmin = 0.60and plastic flashing �=0.81 W/mK

2. As Fig A.13 or A.14

Medium weight blockwork (k=0.6) fmin = 0.84and insulation extended 100mm �= 0.22 W/mKdown the wall

Light weight blockwork (k=0.11) fmin = 0.91and insulation extended 100mm �= 0.10 W/mKdown the wall

Detail 6 : CornerPossible thermal bridging can result if the liner ofone side extends across the insulation on the otherside to touch the outside corner trim. Leaving agap of only 5mm between the liner and the outsidetrim can give significantly better performancehowever, stopping the liner short at the wall linergives the best performance, see Figure A.15.There is also a possible gap between the wallpanels that could allow outside air to penetrate tothe liner. If the panels stop short at the corner andthe resulting void is infilled with insulation (FigureA.16), the thermal bridge is effectively eliminated.

Fig A.15: Corner in built up wall

Fig A.16: Corner in composite panel wall

Summary of cornersLiner extends to touch the external fmin = 0.76corner trim �= 0.25 W/mK

Air gap between the insulation at fmin = 0.81the corner �= 0.20 W/mK

5mm gap between liner and fmin = 0.90external corner trim �= 0.07 W/mK

Liner taken back to liner of other fmin = 0.95cladding and gap infilled with �= 0.01 W/mKinsulation as Fig A.15 and A.16

Page 41: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

2. It is necessary to consider both the risk ofcondensation on each individual thermal bridgeand the effect of the increased heat loss throughthermal bridges on the overall heat from thebuilding.

3. If a detail contains metal components crossingthe insulation that would not otherwise bepresent in a plane element, surfacecondensation may occur in humid environments.The severity of the bridge, and therefore the riskof condensation, is determined by the f-factor,which is calculated by modelling the structure. Ifthis type of thermal bridge is to be included in abuilding which is likely to have a humid internalenvironment, consideration should be given toredesigning the detail.

4. It is also necessary to calculate the contributionof the thermal bridges to the overall heat lossfrom the building by using the linear thermaltransmittance (�-value) and then following theprocedures specified in BRE IP17/01. If the totalheat loss through the thermal bridges is greaterthan 10% of that through the plane areas,individual details must be modified to reduce theloss through the bridges.

5. The parameters needed to comply with Part Lvia IP 17/01 (the f-value and the �-value) aregiven in this report for a range of details thatshould cover most metal clad buildings. Meansof improving the thermal performance of eachdetail are presented. It will be necessary to usea two-dimensional thermal model to calculatethe f-value and the �-value for all other details.

Infra-red surveys1. An infra-red survey, carried out by a competent

person, can be used to demonstrate that theinsulation is reasonably continuous over thewhole visible envelope of the building.

2. Given the right conditions, infra-red surveys canprovide useful qualitative information aboutthermal bridges and air infiltration but cannotquantify their effect, nor can they be used tomeasure the U-value of walls and roofs.

3. Infra-red surveys of the envelope of a buildingshould preferably be done from the inside andideally require calm, dry, cold and cloudyconditions; there may therefore be aconsiderable delay before conditions aresuitable. The conditions for external surveys areeven more restrictive.

4. For a survey to be successful, the buildingshould be heated for at least 12 hours beforethe survey, there should be no sun and no rainon the external surface.

5. The interpretation of infra-red surveys issubjective requiring experienced staff, especiallyin the presence of metal components, withemissivities much lower that those of otherbuilding materials. This may lead to disputesconcerning whether an apparent defect issignificant or not.

Air leakage1. Compliance with the Approved Document can

be demonstrated for buildings of floor area <1000 m2 by providing evidence that appropriatedesign details and building techniques havebeen used and that the work has been carriedout in ways that can be expected to achieveconformity.

2. Compliance with the Approved Document canbe demonstrated for buildings of any size bydemonstrating that the results of air leakagetests are satisfactory.

3. Pressurisation testing of whole buildings gives agood estimate of their energy loss from airinfiltration in practice.

4. The contribution of individual areas of thebuilding envelope to the overall leakage can beidentified and quantified by the use of smoketubes, infra-red surveys and reductive sealing.

5. The leakage through individual cladding systemsand the effect of sealing joints etc. can bemeasured in laboratory tests. The effect ofother components installed into the envelope,such as doors, windows, smoke vents etc.

2 39

Details 7, 8 and 9 : Door or windowlintel, jamb or sillAs these three details are essentially the samefrom the point of view of thermal bridging, theyhave been treated together.

If, as is shown in Figure A.17 or A.18, the windowor door frame is fixed to the structural frame withinthe cladding, leaving a gap of 50mm between theframe, the steel of the structural frame and the dripsill will form a marked thermal bridge.

Moving the window frame forward so that the outeredge is in line with the liner of the wall, bringssome improvement and moving further forward sothat it half overlaps the wall insulation is evenbetter, but this may cause structural difficulties.

If a 25mm layer of thermal insulation is placedbetween the structural framework and thewindow/door frame, either as insulation board orinfill insulation as shown in Figures A.19 to A.23,the thermal bridge is greatly reduced. However, ifas shown in Figure A.20, the sill flashing crossesthe insulation because there is no adequateattachment point on the outside, the benefit isreduced.

Fig A.17: Lintel in built up wall

Fig A.18: Lintel in composite panel wall

Fig A.19: Modified lintel in built up wall

Fig A.20: Modified lintel in composite panel wall

Fig A.21: Modified jamb in built up wall

Fig A.22: Modified jamb in composite panel wall

Fig A.23: Modified window sill in built up wall

Fig A.24: Modified window sill in composite panel wall

Page 42: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

This publication has been produced by the MetalCladding and Roofing Manufacturers Association(MCRMA) in collaboration with BRE, to assist thedesigners, manufacturers and installers of metalwalls and roofs to comply with the requirements ofApproved Document L2 of the BuildingRegulations, published in October 2001 to comeinto force in April 2002.

It describes the content of those parts of theApproved Document relevant to metal claddingand roofing systems and gives guidance as to:

The calculation of U-values

Allowing for thermal bridging at junctions andopenings

Infra-red surveys

Air leakage testing

The guidance is designed to be relevant to bothtwin skin and composite panel systems.

Calculation of U-values1. Approved Document L2 requires that the U-

values of metal site assembled and compositepanel walls and roofs must be less than or equalto 0.35 W/m2K and 0.25 W/m2K respectively.(The corresponding values in Scottish TechnicalStandard J are 0.30 W/m2K and 0.25 W/m2K).These values include associated componentssuch as gutters and smoke vents however,rooflights, windows and doors have separatevalues.

2. Because the method for calculating U-valuescontained in BS EN ISO 6496 and CIBSE GuideA does not apply to metal roofing and claddingsystems, more complex methods must be used.

3. If the construction is one of those covered inBRE IP 5/98, the U-value can be obtained fromthe graphs or other information in the IP andcorrected for air spaces and compression of theinsulation by the profiles using the equations inthe IP.

4. If the component contains independent linearfeatures that can be represented by a series oftwo-dimensional models, use a two-dimensionalmodel and combine the results from the differentmodels.

5. If the component contains repeating pointthermal bridges, such as clips, develop a three-dimensional model to calculate the heat flowsand then the U-value.

Thermal bridging1. Approved Document L2 requires that the

building fabric should be constructed so thatthere are no significant thermal bridges or gapsin the insulation layer(s) within the variouselements of the fabric, at the joints betweenelements and at the edges of elements such asthose around window and door openings. It isalso necessary to account for penetration of theinsulated envelope by features such as safetyharness posts or rafters which project to supporta canopy or gutter.

40 1

Foreword Checklist for compliancewith Approved Document L2

Summary of window and door lintels, jambsand sillsGap between window or door fmin = 0.46frame and cladding as Figs A.17 �= 1.27 W/mKand A.18

Frame moved forward in line with fmin = 0.67wall liner �= 0.69 W/mK

Insulation included between fmin = 0.91window or door frame and �= 0.23 W/mKstructural steel and cladding, asFig A.19 to A.24, but not A.20

Lintel with insulation included fmin = 0.80between window or door frame �= 0.43 W/mKand structural steel and cladding,but sill flashing crossing theinsulation, as Fig A.20

Point Thermal BridgesSome features of industrial buildings in which steelelements penetrate the insulation, exist at onlydiscrete points, and are not linear features like theother details discussed in this Appendix. Althoughtheir analysis is not a requirement of ApprovedDocument L, it should be recognised that they canbe sources of extra heat loss from the building and,more importantly, can locally lower the internalsurface temperature low enough to cause severesurface condensation, especially in high humiditybuildings. These features are much more variablethan the other details discussed above and theexamples below are included for illustration only.Individual calculations should be done wheneverany of these features are included in a highhumidity building. Two examples are shown in thefigures below:

a) a harness attachment post, which is a hollowsteel post, with 2mm thick walls, which isattached to the structural steel inside thebuilding and passes through the roof;

b) a girder, which is attached to the structuralsteelwork within the building and passes thoughthe insulated cladding to support, for example acanopy or eaves gutter.

For each example, the value of fmin and the extraheat loss in W/K, caused by each is quoted; the

total heat loss is found by multiplying this by thenumber of these features in the building.

Fig A.25: Harness attachment post

Fig A.26: Internal surface temperaturefmin = 0.77 , Heat loss = 0.17 W/K

Fig A.27: Canopy girder

Fig A.28: Internal surface temperaturefmin = 0.62 , Heat loss = 0.69 W/K

Page 43: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

PageForeword 1

Checklist for compliance with Approved Document L2 1

1.0 Introduction 3

2.0 Approved Document L2 42.1 Requirements of the Approved Document 42.2 Energy efficient design of the building fabric 52.3 Maximum areas of windows, doors and rooflights 62.4 Thermal bridging at junctions and around openings 62.5 BRE IP 17/01 72.6 Building air leakage 7

3.0 Methods for calculating heat loss through plane areas of cladding and roofing systems 93.1 The development of U-value calculation methods 93.2 Computer modelling 113.3 Theory 133.4 Examples 143.5 Summary 16

4.0 Thermal bridges 174.1 Introduction 174.2 Surface condensation and mould growth 174.3 Heat loss through thermal bridges 204.4 Examples of surface temperature and heat loss through thermal bridges 214.5 Example of the effect of thermal bridging on overall heat loss 224.6 Summary 23

5.0 Infra-red thermography 245.1 Thermal imaging 245.2 Conditions for a survey 255.3 Examples 265.4 Summary 27

6.0 Air tightness 276.1 Introduction 276.2 Whole building testing of air leakage 276.3 Air leakage parameters 306.4 Heat loss due to air leakage 306.5 Laboratory tests for individual components 316.6 Examples of testing carried out at BRE 316.7 Example of the effect of individual joint leakage on whole cladding leakage 336.8 Summary 34

7.0 Appendix 34

8.0 References 41

41

Contents

© The Metal Cladding & Roofing Manufacturers Association Limited, January 2002

MCRMA technical papers

1. Approved Document L Conservation of fuel andpower, 1995 edition HMSO 1994.

2. Approved Document L2 Conservation of fuel andpower in buildings other than dwellings. October2001.

3. DEFRA/DTLR Report: Limiting thermal bridgingand air leakage: Robust construction details fordwellings and similar buildings. The StationeryOffice, October 2001.

4. BS EN ISO 6946 : 1997 Building componentsand building elements – Thermal resistance andthermal transmittance – Calculation method.

5. BRE IP 17/01 Assessing the effect of thermalbridging at junctions and around openings BREAugust 2001.

6. CIBSE Guide A3 Thermal properties of buildingstructures CIBSE 1999.

7. BS EN 12524 : 2000 Building materials andproducts - Hygrothermal properties -Tabulateddesign values.

8. BRE Information Paper IP 5/98 : Metal cladding :assessing thermal performance

9. BS EN ISO 10211-1: 1996, Thermal bridges inbuilding construction - Heat flows and surfacetemperatures, Part 1. General calculationmethods

10. BS EN ISO 10211-2: 1996, Thermal bridges inbuilding construction - Heat flows and surfacetemperatures, Part 2 Linear thermal bridges.

11. BS 5250 :1989 British Standard Code of practicefor control of condensation in buildings.

12. BS EN ISO 13788:2001 : Hygrothermalperformance of building components andbuilding elements - Internal surface temperatureto avoid critical surface humidity and interstitialcondensation – Calculation methods

13. A practical guide to infra-red thermography forbuilding surveys, BRE Report 176, BRE 1991

14. A professional’s guide to testing housing forenergy efficiency, General Information Report64, Energy Efficiency Best Practice Programme,2000.

15. CIBSE Guide TM23:2000, Testing buildings forair leakage, CIBSE 2000.

16. BS EN 13829 : 2001 thermal performance ofbuildings – Determination of air permeability –Fan pressurisation method

17. BS EN 12114:2000 Thermal performance ofbuildings - Air permeability of buildingcomponents and building elements - Laboratorytest method.

No 1 Recommended good practice for daylightingin metal clad buildings

No 2 Curved sheeting manual

No 3 Secret fix design guide

No 4 Fire and external steel-clad walls: guidancenotes to the revised Building Regulations1992

No 5 Metal wall cladding design guide

No 6 Profiled metal roofing design guide

No 7 Fire design of steel sheet clad external wallsfor building: construction performancestandards and design

No 8 Acoustic design guide for metal roof andwall cladding

No 9 Composite roof and wall cladding designguide

No 10 Profiled metal cladding for roof and walls:guidance notes on revised BuildingRegulations 1995 parts L & F

No 11 Flashings for metal roof and wall cladding:design, detailing and installation guide

No 12 Fasteners for metal roof and wall cladding:design, detailing and installation guide

No 13 Composite slabs and beams using steeldecking: best practice for design andconstruction

Other publicationsThe Complete Package CDROM

Manufacturing tolerances for profiled metal roof andwall cladding

CladSafe latent defects insurance scheme: basicguide

LiabilityWhilst the information contained in this designguide is believed to be correct at the time of goingto press, the Metal Cladding and RoofingManufacturers Association Limited, its membercompanies and the Building ResearchEstablishment cannot be held responsible for anyerrors or inaccuracies and, in particular, thespecification for any application must checked withthe individual manufacturer concerned for a giveninstallation.

The diagrams of typical constructions in thispublication are illustrative only.

References

Page 44: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

Metal Cladding & Roofing Manufacturers Association Ltd106 Ruskin Avenue Rogerstone Newport South Wales NP10 0BD01633 895633 | [email protected] | www.mcrma.co.uk

Page 45: Guidance For The Design Of Metal Roofing And Cladding To Comply With Approved Document ... ·  · 2015-05-01TO COMPLY WITH APPROVED DOCUMENT L2 : 2001 CI/SfB (23) ... Approved Document

THE METAL CLADDING & ROOFING MANUFACTURERS ASSOCIATION LIMITED

18 MERE FARM ROADPRENTON . WIRRALCHESHIRE CH43 9TT

TELEPHONE: 0151 652 3846FACSIMILE: 0151 653 [email protected]

www.mcrma.co.uk

THE METAL CLADDING & ROOFING MANUFACTURERS ASSOCIATION LIMITED

GUIDANCE FOR THE DESIGN OFMETAL ROOFING AND CLADDINGTO COMPLY WITH APPROVEDDOCUMENT L2 : 2001

MCRMA Technical Paper No. 14

CI/SfB

Nh2(23)

JANUARY 2002

£12.00incl. P&P

desig

ned

by S

even

thpl

anet

prin

ted b

y Hu

tson

Fastp

rint L

imite

d