guidance for preparing a p6 schedule
TRANSCRIPT
-
7/31/2019 Guidance for Preparing a P6 Schedule
1/19
PRIMAVERAP6TrainingConductedon27and28Nov2011,DEBAJHeadoffice
(GuidanceforPreparingSchedule)
SCHEDULEPREPARATIONFORNEWPROJECT
1. All Programs Primavera Project Management
Click to open
-
7/31/2019 Guidance for Preparing a P6 Schedule
2/19
Click to open
Enter password as admin
Click to open
2. Enter password as admin OK
3. OK
-
7/31/2019 Guidance for Preparing a P6 Schedule
3/19
PRIMAVERAINITIALSETTINGS
i. Enter hours as per the project requirement.
ii. Enter Starting day of the week.
ADMINPREFERENCES
-
7/31/2019 Guidance for Preparing a P6 Schedule
4/19
iii. Use Default settings
iv. Use Default settings
-
7/31/2019 Guidance for Preparing a P6 Schedule
5/19
vi. Use Default settings
v. Use Default settings
-
7/31/2019 Guidance for Preparing a P6 Schedule
6/19
viii. Use Default settings
vii. Select headers and footers as per your requirement.
-
7/31/2019 Guidance for Preparing a P6 Schedule
7/19
ix. Use Default settings
USERPREFERENCES
i. Select time units day/ hours as per the requirement.
-
7/31/2019 Guidance for Preparing a P6 Schedule
8/19
ii. Select date format as per the requirement.
iii. Select currency option as dollar.
-
7/31/2019 Guidance for Preparing a P6 Schedule
9/19
iv. Use Default settings.
v. Use Default settings.
-
7/31/2019 Guidance for Preparing a P6 Schedule
10/19
vi. Use Default settings.
vii. Use Default settings.
-
7/31/2019 Guidance for Preparing a P6 Schedule
11/19
viii. Use Default settings.
ix. Use Default settings.
-
7/31/2019 Guidance for Preparing a P6 Schedule
12/19
x. Use Default settings.
Note - 1: Right click and select all options by tick mark
-
7/31/2019 Guidance for Preparing a P6 Schedule
13/19
Note - 2: Set the language to English. This will be the default for our company.
Click to open
4. File New
-
7/31/2019 Guidance for Preparing a P6 Schedule
14/19
5. Click next
7. Enter planned start
6. Enter project ID & project Name
Click next
Enter planned start
Enter project IDEnter project name
Click next
Click next
-
7/31/2019 Guidance for Preparing a P6 Schedule
15/19
9. Click next
8. Select responsible manager
Enter responsible manager
Click next
10. Click next
Click next
Click next
-
7/31/2019 Guidance for Preparing a P6 Schedule
16/19
11. Click finish
Note: EnsureyoucreatedyourOBS&EPSalready.HereIconsideryouhavecreatedintrainingsessionitself
Itisonetimecreationonly.Noneedtocreateforeveryproject
Click next
12. Add WBS WBS
13. Create calendar Create / modify the calendar
Add
-
7/31/2019 Guidance for Preparing a P6 Schedule
17/19
16. Enter activity ID & activity name. Follow next and enter Activity detail.
Click nextEnter activity ID
Enter activity name
Add / modify the calendar
14. Add / modify the calendar
15. Add activities toActivities
Add
Note:
Activitytypedefault Taskdependent,Duration
type fixeddurationandUnits, %Progress
Physical%,selectyourcalendar
-
7/31/2019 Guidance for Preparing a P6 Schedule
18/19
17. Enter the duration for each activity.
Note:
Ensureitisindaysorhours.Ifyouwanttochange,gotoEdit Userpreferences
selecthoursordaysasyouwanttoinput)18. Make relationship as per requirement.
Note:Take
abackup
by
export
-
7/31/2019 Guidance for Preparing a P6 Schedule
19/19
Check DATA date
before running a
schedule.
19. Run the schedule.
Note:
Datadatecannotbereversed.Oncerunthescheduleforwardthen,thenyoucannot
runagainatbackdate.Soensureyoutookbackupbeforerunningtheschedule.