gs ep saf 021 - layout - pogc · gs ep saf 021 layout ... 4. location of the installation ......
TRANSCRIPT
Exploration & Production
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
GENERAL SPECIFICATION
Design of Field Facilities
GS EP SAF 021
Layout
Main Instructor for Derogation: ECI (Design of Field Facilities)
04 10/2009 Sections 2, 5, Appendices A and C updated. Appendix D created
03 10/2008 Complete review and update
02 10/2005 Addition of EP root to document identification
01 10/2003 Change of Group name and logo
00 04/2001 Old TotalFina SP SEC 021
Rev. Date Notes
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 2/64
Contents
1. Scope .......................................................................................................................4 1.1 Purpose .............................................................................................................................4 1.2 Applicability........................................................................................................................4
2. Reference documents.............................................................................................4
3. Terminology and definitions ..................................................................................6
4. Location of the installation.....................................................................................8 4.1 Choice of a location ...........................................................................................................8 4.2 Impacted area....................................................................................................................9 4.3 Site Contingency Plan .......................................................................................................9
5. General arrangement ..............................................................................................9 5.1 Methodology ......................................................................................................................9 5.2 Unit sorting.......................................................................................................................10 5.3 Unit configuration.............................................................................................................13 5.4 Interconnection units........................................................................................................20 5.5 Location of rooms in the installation ................................................................................20 5.6 Layout of integrated platforms .........................................................................................22 5.7 Temporary facilities..........................................................................................................24 5.8 Future extensions ............................................................................................................25
6. Equipment layout ..................................................................................................25
Annex 1 (Informative) - Methodology to select layout .....................................26
Appendix A - Spacing - Default distances tables .....................................................27
Appendix B - Arrangement of interconnections between units ..............................46 B1. Pipe-racks........................................................................................................................46 B2. Cable routes ....................................................................................................................46 B3. Bridges (offshore only).....................................................................................................46
Appendix C - Equipment layout .................................................................................48 C1. General ............................................................................................................................48
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 3/64
C2. Wells ................................................................................................................................49 C3. Unfired process equipment..............................................................................................50 C4. Fired equipment...............................................................................................................55 C5. Piping...............................................................................................................................57 C6. Flares and vents ..............................................................................................................58 C7. Storage ............................................................................................................................58 C8. Safety equipment.............................................................................................................59 C9. Buildings ..........................................................................................................................59 C10. Miscellaneous ..................................................................................................................60
Appendix D – Bibliographic references.....................................................................62
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 4/64
1. Scope
1.1 Purpose This general specification lays down the minimum safety requirements for the layout of installations, both onshore and offshore.
The dispositions of this specification are in accordance with API RP 14J recommendations unless appropriate justification corresponding to COMPANY practices and tolerances is brought.
The main recommendations for the layout of installations and the main steps of the methodology are included in Annex 1 of this document.
1.2 Applicability This specification is not retroactive.
It shall apply to new installations and to major modifications or extensions of existing installations, both onshore and offshore.
This specification does not cover:
• Exploration drilling temporary facilities
• FPSO’s and boats
• LNG plants
• Jetty and shoreline terminals
• Refining and marketing facilities.
2. Reference documents The reference documents listed below form an integral part of this General Specification. Unless otherwise stipulated, the applicable version of these documents, including relevant appendices and supplements, is the latest revision published at the EFFECTIVE DATE of the CONTRACT.
Standards
Reference Title
Not applicable
Professional Documents
Reference Title
API RP 14J Recommended Practice for Design and Hazards Analysis for Offshore Production Facilities
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 5/64
Regulations
Reference Title
Not applicable
Codes
Reference Title
Not applicable
Other documents
Reference Title
Statement Of Requirements (SOR)
Safety Concept
Operating Philosophy
Total General Specifications
Reference Title
GS EP ECI 001 Reference levels for offshore platforms
GS EP ELE 001 Electrical design criteria
GS EP ELE 079 Electrical apparatus for potentially explosive gas atmosphere
GS EP ELE 364 Electrical installations
GS EP LSO 110 Environmental effects considerations for helidecks
GS EP SAF 041 Technological Risk Assessment Methodology
GS EP SAF 216 Area classification
GS EP SAF 221 Safety rules for building
GS EP SAF 222 Safety rules for turbines, Diesel engines, gas engines and process units in sheltered or enclosed areas
GS EP SAF 227 Safety rules for fired heaters
GS EP SAF 253 Impacted area, restricted area and fire zones
GS EP SAF 261 Emergency Shut-Down and Emergency De-Pressurisation (ESD and EDP)
GS EP SAF 262 Pressure protection relief and hydrocarbon disposal systems
GS EP SAF 321 Fire pump stations and fire water mains
GS EP SAF 337 Passive fire protection: Basis of design
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 6/64
Reference Title
GS EP SAF 341 Location and protection on onshore hydrocarbon storage
GS EP SAF 351 Escape, evacuation and rescue from fixed installations
GS EP STR 002 Permanent lifting or handling devices for offshore installations
3. Terminology and definitions There are three types of statements in this specification, the “shall”, “should” and “may” statements. They are to be understood as follows:
Shall Is to be understood as mandatory. Deviating from a “shall” statement requires derogation approved by the COMPANY
Should Is to be understood as strongly recommended to comply with the requirements of the specification. Alternatives shall provide a similar level of protection and this shall be documented
May Is used where alternatives are equally acceptable
For the purpose of this specification, the following definitions shall apply (the terms defined in this section are often in bold characters in the text of the specification):
Area (impacted) Area that extends beyond the boundaries of the installation but which is nevertheless affected either permanently by normal operation of the facility (e.g. noise, radiation) or exceptionally by the consequences of an emergency situation caused by a major failure (COMPANY)
Area (restricted) Area within the boundaries of the installation and hence under the control of COMPANY, which is affected permanently by normal operation of the facility (e.g. noise, radiation) or exceptionally by the consequence of an emergency situation caused by a major failure (COMPANY)
Credible event Incident likely to occur within a concerned area. Used for the definition of fire zones. Consequences corresponding to a credible event of a given fire zone shall not impact other fire zones (COMPANY)
Emergency Control Centre
Place where emergency response personnel go to undertake their emergency duties (COMPANY). Equivalent to ISO-definition of Emergency Station
Emergency Response (ER)
Action taken by personnel on or off the installation to control and/or mitigate a hazardous event (ISO)
Equipment Any component or group of components specifically identified and itemised on the P&IDs (COMPANY)
Escape Route Route from an area of an installation leading to a muster area, a Temporary Refuge (TR), an embarkation area and/or means to escape (ISO)
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 7/64
Escape, Evacuation and Rescue (EER)
General term used to describe the range of possible actions including escape, muster, refuge, evacuation, escape to the sea and rescue/recovery (ISO)
Failure (major) A conceivable incident that can possibly occur on the facility. Used for the definition of the facility restricted area and impacted area (COMPANY)
Fire zone Area within the installation where equipments are grouped by nature and/or homogeneous level of risk attached to them. The partition into fire zones is such that consequences of a fire, flammable gas leak or an explosion corresponding to the credible event likely to occur in the concerned fire zone, shall not impact other fire zones to an extend where their integrity could be put at risk
FPSO Floating, Production, Storage and Offloading system includes, in addition to storage and offloading capability, facilities for receiving crude oil from producing wells and processing it for export by separating water and gas (OGP)
Fuel source Same as ISO definition of "source of release" (API)
General Arrangement (GA)
Also called Overall Plot Plan. Action of sorting and grouping equipment into units, defining their location considering environment, neighbourhood, unit inter-dependence and spacing to match safety and operability requirements (COMPANY)
Hazardous area and zone
A hazardous area is defined as a three dimensional space in which a flammable atmosphere may be expected to be present at such frequencies as to require special precautions for the control of potential ignition sources (IP 15). All other areas are referred to as non-hazardous areas (or safe areas) in this context. In a hazardous area three types of zones (0, 1 and 2) are recognised (IP 15)
Ignition source Source of temperature and energy sufficient to initiate combustion (API)
Installation Technical unit in which dangerous substances are produced, used, handled or stored, including all the equipment, structures, pipework, machinery, tools, private railway sidings, docks, unloading quays serving the installation, jetties, warehouses or similar structures, floating or otherwise, necessary for the operation of the installation (COMPANY from European Directive 96/82/EC, dated December 9th, 1996)
Layout Action of selecting the location of the installation, defining unit general arrangements and placing equipment within units (COMPANY)
Local Authority Organisation, body, office or individual responsible for approving the installation with regards to local applicable regulation and for defining jointly with COMPANY, approving and enforcing the Site Contingency Plan (COMPANY)
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 8/64
Lower Flammable Limit (LFL)
Lower concentration of gas (by volume and expressed in percentage) in a gas-air mixture that will form an ignitable mixture (API, NFPA)
Site Contingency Plan Plan describing all the measures planned for dealing with the scenarios deduced from the major risks calculated for the installations
Source of release Point from which flammable gas, liquid or a combination of both can be released into the atmosphere (ISO)
TEMPSC Totally Enclosed Motor Propelled Survival Craft: Craft capable of sustaining the lives of persons in distress from the time of abandoning the installation (ISO)
Units Areas within the installation resulting from its partition into a reasonable number of geographical and functional groups of equipment having the same type (hydrocarbon, pressure, inventory, ignition, etc.) and levels (high, medium, low) of risks (COMPANY).
4. Location of the installation The location of any new installation or any major extension of an existing installation shall be approved by COMPANY.
The choice of the location shall always be justified by a supporting dossier as described below, particularly when several locations can be initially envisaged.
4.1 Choice of a location The following surrounding facilities and their foreseeable extension shall be identified:
• Other petroleum or industrial installations
• Access roads, ground, sea (waterways) and air transportation networks
• Electrical power, water, telecommunication, distribution networks
• Presence and density of population, public buildings.
The following environmental conditions shall be identified:
• Soil conditions, relief
• Local specific risks such as seismicity, landslides (either onshore or submarine), floods, sand storms, permanent frost, typhoons
• Meteorological conditions (temperature, hygrometry, sun, rain, wind, snow, ice, fog, lightning)
• Sea conditions (water depth, swell, currents, salinity)
• Cold source vicinity (sea, river, air)
• Protection of nature (site, fauna, flora) and visual impact
• Security risks.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 9/64
The Local Regulation in force shall be complied with (e.g. the requirements imposed by the Local Authority).
The different criteria, factors and rankings in the decision-making process shall be recorded. The selection shall be justified in all cases. Special attention shall be given to the selected location when several options can be initially envisaged.
4.2 Impacted area Once a location has been selected:
• The impacted area around the installation is defined taking the major failures scenarios using the consequence analysis methods and criteria as specified in GS EP SAF 253
• Permanent settlements, public places and transport corridors encroaching the impacted area shall be particularly identified and the need to relocate them shall be specifically addressed.
4.3 Site Contingency Plan From the very beginning of this process and before a location is eventually selected, a preliminary Site Contingency Plan is prepared in close relationship with Local Authorities.
It shall be ensured that dispositions it includes regarding communication (alerting neighbourhood and Local Authorities), evacuation, rescue means to public and implementation of mitigation measures are fulfilling Local Authorities’ requirements.
The Site Contingency Plan may also cover areas extending beyond the impacted area but it is not the purpose of the present document to elaborate upon it.
5. General arrangement
5.1 Methodology Different approaches are possible to determine minimum distances between different fire zones and between units within the same fire zone.
COMPANY's practice is to proceed as follows:
• At Preliminary and Conceptual stages, issue a preliminary General Arrangement based on the recommendations provided in various General Specifications, including this one (in particular refer to Appendix A tables and figures), and/or COMPANY engineering expert judgment
• At Pre-Project stage, issue the plot plans and improved partitions between fire zones and units, using consequence analysis software(s) available in-house (refer to GS EP SAF 253)
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 10/64
• At Basic Engineering stage, issue layouts within units and, if proven necessary, carry-out further consequence analysis and/or a QRA1 to confirm/optimise distances and partition
• At Detailed Engineering stage, incorporate VENDOR data to finalise equipment layouts (refer to Appendix C for equipment location requirement and recommended distances between equipments).
Detailed work on General Arrangement (GA) shall not commence before :
• The location of the installation has been selected (refer to Section 4)
• The restricted area has been defined (as per GS EP SAF 253)
• The installation has been split into fire zones (as per GS EP SAF 253).
GA of any new installation or any major extension of an existing installation shall be subject to approval by COMPANY and shall incorporate all provisions for temporary facilities and/or future extensions.
5.2 Unit sorting
5.2.1 Main Principles
• Fire zones, unit partitions and number of units shall be coherent
• Unit partition: The split into units shall be compatible with the split into fire zones. Each unit is included into one, and only one, fire zone. A unit cannot sit over two fire zones. One fire zone can incorporate one or several units. Units are further divided into pieces of equipment, and bulk. Each fixed equipment belongs to one, and only one, unit. A piece of fixed equipment cannot belong to two units
• Fire-fighting and emergency capabilities: The capability for the active fire-fighting and emergency systems to operate efficiently on the biggest units within their fire zones and with maximum acceptable risk for the assets shall be ensured
• Risk level: Partition should be such that each unit is composed of elements (equipment and/or components) having comparable process risk levels
• Process flexibility and availability: The break-down into units should be such as to allow optimum operational flexibility and required availability. For instance in the case of an installation composed of two separators and two compressors, it shall be assessed whether it is preferable to group them into two identical processing trains comprising one separator and one compressor each, or into a separation unit (comprising both separators) and a compression unit (comprising both compressors). Input for such arrangement shall be provided by the OPERATING PHILOSOPHY
• Asset protection: The split into units shall be such that the risk acceptability criteria set forth in GS EP SAF 041 for assets is complied with
• Interconnection between units: An interconnecting unit is defined only if it links different process units and if it is mainly composed of all-welded piping with few flanges, or single run cables with few junction boxes. A pipe-way within a single process unit or with
1 QRA shall be used only on large projects or when imposed by applicable regulation and in order to keep individual risk within
acceptable limits. In practice QRA shall be carried out by the end of the basic engineering i.e. soon enough so as to allow feed back of its main findings into the layout, if necessary.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 11/64
numerous flanges, valves, vents, drains, etc., shall be considered as being part of the unit it pertains to. Offshore, bridges between platforms are interconnecting units
• Sub deluge zones: The possible partition into sub-deluge zones shall also be considered and made compatible with the unit sorting (Refer to GS EP SAF 253).
5.2.2 Group of equipment With reference to API RP 14J, units shall be sorted out into nine different categories called "groups of equipment" (refer to table below) presenting homogeneous risks, both in terms of nature and level.
The objective is two-fold:
(i) Achieve segregation of fuel source from ignition source by separation of equipment
(ii) Define compatibility of units between each-other (refer to Section 5.2.3).
Group Type Main equipment Hazard
T1 Wellhead Wellheads, chokes, wellhead manifolds and headers
Fuel source
T2 Unfired process Manifold and headers, separators, heat exchangers, water treatment, pumps, compressors, unit enclosures, finger type slug catcher, metering
Fuel source
T3 HC storage Storage tanks, sump tanks, produced water treating tanks
Fuel source
T4 Fired process Fired equipment, fired heaters, TEG reboilers
Ignition source
T5 Machinery and power generation
Generators, electric equipment, air compressors, engines, turbines
Ignition source
T6 Buildings Living quarters, technical buildings, maintenance areas and buildings, offices, control room, sewage disposal, water makers
Ignition source
T7 Pipelines and risers Risers, pig launchers, pig traps Fuel source
T8 Vents Fuel source
T9 Flares Including burn pits Ignition source
5.2.3 Compatibility Units are compatible together when they can be located beside each other:
• Either without particular precautions dictated by safety that would come in addition to other considerations such as constraints of construction, operability or maintenance
• Or providing supplementary precautions (e.g. enlarged distance or separation wall) are duly implemented.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 12/64
Two units indicated as non compatible shall be located in two different fire zones.
Unit Compatibility T1 T2 T3 T4 T5 T6 T7 T8 T9
T1 Wellhead Y
T2 Unfired process N (1) Y
T3 HC storage (10) N (8) N (2) Y (3)
T4 Fired process N Y (4) N Y
T5 Machinery N (8) Y N Y Y
T6 Buildings N N (5) N (5) N (5) N (5) Y
T7 Pipelines and risers Y Y N (6) N N N Y
T8 Vents (9) N N (7) N N N N N (6) Y
T9 Flares N N (7) N N N N N (6) N Y
(1) Not compatible as a general rule however exception for unfired process units attached to wellhead unit e.g. test separator.
(2) Not compatible as a general rule except (i) unfired process units attached to storage unit e.g. pumping station for hydrocarbon transfer and (ii) small (less than 50 m3) propane storage used in cooling units and providing they are suitably protected (additional distance + embankment).
(3) Liquid hydrocarbon storage is not compatible with liquefied hydrocarbon storage.
(4) Units indicated as non compatible by API RP 14J but considered compatible by COMPANY if sufficient distance is provided (as per Appendix A or consequence analysis as per GS EP SAF 253).
(5) Buildings are not compatible with any other units. This restriction does not apply to technical buildings housing process (hazardous or non-hazardous) or utility.
(6) Not compatible as a general rule but it is tolerated that pipelines (excluding risers, manifolds, pig traps) can cross storage units or flare/vent areas if they are without flange and suitably protected against explosion (from storage units) and radiation (from storage units and flare/vent).
(7) Units indicated as non compatible by API RP 14J but COMPANY tolerates that flare/vent drum and auxiliaries (e.g. condensate pumps, purge/pilot gas skid) are in the flare/vent fire zone providing radiation criteria given in GS EP SAF 262 are fulfilled..
(8) Except for wells with pumping units.
(9) Cold vents (as per GS EP SAF 262) only. Degassing vents (as per GS EP SAF 262) compatible with all other units.
(10) This category includes both liquid hydrocarbon and liquefied HC storage.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 13/64
On highly congested installations, and in particular offshore, units cannot always be segregated by position. In order to provide sufficient independence, they shall be separated by passive fire and blast protection that can resist the effects of a fire or an explosion (based on the scenarios retained in the SAFETY CONCEPT and corresponding to the credible events) and conserve the following default fire and blast ratings after the fire or explosion has occurred:
• H-120 (or J-120 if and where relevant) within the impact distance of a process or hydrocarbon storage fire zones and for units necessary for Emergency Response and/or EER
• H-60 (or J-60 if and where relevant) within the impact distance of a process or hydrocarbon storage fire zones for non-EER or non-ER equipment
• A-0 in a non-hazardous area, but in the restricted area
• Blast protection ratings are evaluated according to the congestion within the platform
• No particular requirement outside the restricted area.
5.3 Unit configuration
5.3.1 Objectives Unit configuration shall be such that the main safety objectives listed below are fulfilled:
• Generic for any industrial installation
o To prevent logistics accidents, and in particular to pay attention to security and control of access (refer to Section 5.3.2), traffic (refer to Sections 5.3.3 & 5.3.5) and lifting (refer to Section 5.3.6)
o To ease operability of the installation with a special emphasis on accesses to working areas (refer to Section 5.3.7) and space reservations around equipment (refer to Section 5.3.8).
• Specific to hydrocarbon production, processing and storage installations
o To locate ignition sources and fuel sources with due consideration of wind, in order to prevent ignition after a gas release (refer to Section 5.3.9)
o To locate fuel sources with due consideration of wind, sea swell and current, to minimise the consequences of fires (refer to Section 5.3.9)
o To ease mitigation measures, and in particular facilitate access for Active Fire-Fighting (refer to Section 5.3.10)
o To provide adequate arrangements for safety to life, and in particular EER (refer to Section 5.3.11).
5.3.2 Security and control of access (onshore only) The installation under the control of COMPANY shall be closed to general public access.
The installation under the control of COMPANY shall be fenced. Refer to Figure 1 - Security and access control (typical onshore).
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 14/64
The installation shall be divided into a general service area and a plant area as defined below:
• The general service area comprises activities in relation with the outside world (T6 classification) and that cannot cause hydrocarbon hazards, such as parking lots, workshops, warehouses, offices, living quarters, control rooms, muster areas, embarkation area, bus stations or helidecks
• The plant area incorporates activities that can cause hydrocarbon or other chemical and ignition hazards, such as well heads (T1); process units, unfired or fired (T2 and T4); hydrocarbon storage units (T3); machinery and power generation (T5); pipelines and risers (T7); vents (T8); flares and burn pits (T9).
Entry point(s) from outside the installation to the general service area shall be located to meet security requirements. Entry points from the general service area to the plant area shall be located to meet safety requirements.
Direct access of public to the plant area shall be made impossible.
Access of public to the general service area shall be made normally possible via one single main entrance with a security check-point.
Other means of access shall be normally closed and limited to exceptional or emergency purposes e.g. exceptional heavy loads, Emergency Response or emergency exits.
The access from the general services area to the plant area shall be limited to authorised personnel only. The access of authorised personnel from the general service area to the plant area shall be made normally possible via a limited number of main entrances, preferably one with a safety check-point.
The other means of access between the general services area and the plant area shall be limited to exceptional or emergency purposes, with the same principles as above.
5.3.3 Access roads (onshore only) Access roads shall be segregated into three categories:
• Outside up to the security check point
• In the general services area
• In the plant area.
5.3.3.1 General for all access roads Access roads shall be practicable all year round and of adequate type for the vehicles that are likely to be used, in particular for the following: overall maximum weight, maximum axle weight, head and width clearance, roadway width and bending radius.
Special consideration shall be paid for snow, ice, defrosting and heavy rains conditions.
At least one access road shall remain passable in any combination of fire scenario and environment conditions.
Provision for the specific risks to the installation and its environment such as cattle guards, illuminating at night or under fog conditions, risk of water flood or heavy rains (e.g. monsoon) shall be considered.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 15/64
5.3.3.2 Additional requirements in the installation Inside the installation, the restrictions for traffic use and directions to reach the loading/unloading posts or the parking lots shall be clearly identified and marked.
Access roads shall conveniently stop at the muster areas in the general service area.
5.3.3.3 Additional requirements in the plant area The restrictions for entry into the plant area applicable to all vehicles shall be assessed taking into account type of engine, fuel and exhaust system.
Access ways in the plant area shall provide safe and easy access for any service vehicles (e.g. mobile fire-fighting means, crane or heavy truck), with (refer to Section 5.3.10 & Appendix C1.1):
• Adequate headway and width at overhead pipeline crossing points
• Capacity to bear the biggest load
• Adequate turning bend radius
• Where necessary, protection of access road nearby piping equipment against vehicle collision.
PREVALING WIND
FIRE ZONE #2FIRE ZONE #1
FIRE ZONE #3
HAZARD AREA (no public allowed)
UNIT 11 UNIT 12 UNIT 21 UNIT 22 UNIT 23
UNIT 31 UNIT 32
ACCESSTO PLANT
SECONDARYACCESS / EXIT
NON HAZARD AREA(public authorised)
Warehouse/workshopHigh occupancy bldg.
Safe utilities
hazardous storageload/unload area
Safety fence at edge of restricted area
Saf
ety
fenc
e
Sec
urity
fenc
e
MAIN ACCESS / EXIT(security check point)
PLANTAREA
GENERAL SERVICEAREA
Figure 1 - Security and access control (typical onshore)
5.3.4 Boat approach (offshore only) Boat landings shall not be on the same platform side as risers.
Boat landings should not be located above sea lines that are not suitably protected against maximum load impact by boats using the landing.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 16/64
Furthermore the boat-landing position shall take into account risks due to:
• Flare, vent and exhaust locations
• Wind, sea swell and current direction (refer to Section 5.3.9).
• Hazardous areas, including when wire-line operations are performed on any well.
The location of the landing should take into consideration the direction of the prevailing wind, swell and/or tidal currents in order to minimise the likelihood of collision by a drifting boat.
Boats should normally approach the boat-landings against swell and current.
Ideally boat landings should be downstream of the most stringent prevailing wind, swell or tidal current (see Figure 2 - Typical layout of offshore fixed platforms) downwind of the platform.
A perpendicular position (see Figure 3 - Typical layout of offshore integrated platform) to the prevailing weather and sea might be acceptable, but there could then be limitations on the operational envelop of the boat.
The position and operation of the boat landing shall take into consideration the possible presence of a jack-up or tender support rig alongside the platform including flaring from the platform, jack-up or tender support rig. Appropriate operational constraints shall be put in place whenever flaring takes place.
Where a boat landing platform location, orientation or approach procedure does not comply with the above, a risk assessment shall be carried out, and a justification dossier produced supporting the reasons why the boat landing does not comply with these requirements.
5.3.5 Helicopter approach Helideck position shall take into account risks due to:
• Flare, vent and exhaust locations
• Wind direction (refer to Section 5.3.9)
• Hazardous areas.
Helicopter should normally approach helidecks into the wind. The 210° approach sector shall be free, up to 1 km away, of any obstacle to air navigation and in particular of any flare, drilling mast/pole, crane and exhaust chimney.
For further details, refer to specification GS EP LSO 110.
5.3.6 Location of cranes and lifting devices Cranes and lifting devices shall be located aside loading/unloading posts.
Loading/unloading posts shall be close to the main ways of access but shall not encroach upon them.
• Offshore and shoreline crane. o Operational swing zones are prohibited above sea lines and risers unless they are
suitably protected against maximum load impact
o The loads shall not pass over supply boats, except for routine loading/unloading operations.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 17/64
o The routine operational swing zones of permanently installed cranes shall not pass over equipment containing hydrocarbon unless said equipment has been designed for resistance to impact from loads dropped by the crane or properly protected
o Crane movement above such equipment shall be limited to heavy maintenance activities. In these cases, the equipment shall be depressurised and drained and a specific procedure implemented or a lifting study and a dropped object risk assessment study shall be carried out.
• Onshore, the same recommendations shall be applied regarding swing zones over equipment containing hydrocarbon. Where a mobile crane is given preference over a set of fixed cranes, its possible and foreseeable operational locations shall be reserved and reinforced with concrete slabs. The safe access of mobile crane to its operational spots shall be demonstrated.
In all cases the crane operator shall have view over the whole swing zone and traffic around.
5.3.7 Access to working areas Access arrangement for all routine operations should be straightforward and simple.
Operation and inspection points should be accessible and visible from main floors or aisles, preferably without the help of ladders.
All equipment requiring human intervention (for operation, maintenance, inspection, etc.) with a periodicity of at least once a month should be provided with permanent and fixed access devices.
Equipment, instruments, valves hand-wheels and piping shall not protrude into access ways so as to cause a hazard or to obstruct the escape ways. For further details dealing with the minimum clearances of the access ways, refer to Appendix C1.1.
5.3.8 Space reservations around equipment Provisions shall be made to ensure that all routine operation involving handling of materials and equipment can be conducted in a safe manner.
Where simultaneous operations (SIMOPS) may take place between drilling or work-over and production, sufficient space shall be made available for pipe handling, mud handling, chemical delivery or sludge removal without interfering with the safety of personnel or with the safe operation of the installation.
Space shall also be provided for the lay-down of equipment during maintenance or replacement, particularly for large items, such as heat exchanger bundles, flame tubes, turbine and/or compressor shafts (overhauls).
5.3.9 Wind, sea swell and current Several main criteria shall be considered. Refer to Figure 2 - Typical layout of offshore fixed platforms.
5.3.9.1 Ignition of a gas cloud Flammable gas sources (release sources) shall not be located up the prevailing wind of any ignition source. This general rule may be deviated from in the specific case of integrated platforms (refer to Section 5.6).
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 18/64
5.3.9.2 Ignition of liquid hydrocarbon spills The potential sources of liquid hydrocarbon spillage from production/processing units (release sources) should not be located up the prevailing wind of any ignition source.
5.3.9.3 Fire escalation Any hazardous area shall be located down the prevailing wind of any hazardous area of lesser danger.
In particular, the accommodations and non-hazardous areas shall be located up (preferred option) or perpendicular (alternative option) to the prevailing wind of hydrocarbon production/processing units.
5.3.9.4 Flares and cold vents Ignited flares are sources of ignition and should not be located down-wind of sources of flammable gas (or should be located far enough from them), except where flare are high enough to avoid any risk.
Conversely, the risk of flame-out where the flares become sources of fuel (i.e. release source) shall be considered.
Cold vents (refer to GS EP SAF 262) are source of release (i.e. fuel source) and could become ignition sources in case of accidental ignition.
As a consequence of the flares and cold vents being both sources of release and ignition, their preferred location is perpendicular to the prevailing wind.
5.3.9.5 Escape, Evacuation and Rescue (EER) EER routes and systems shall be located up the prevailing wind of hazardous areas. TEMPSC which can head for a safe place by their own, should be located up and on the sides parallel to the prevailing wind. Life-rafts best location is on the sides parallel to the prevailing wind (refer to Section 5.3.11 & GS EP SAF 351 for further details).
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 19/64
Radioroom
TEMPSC
TEMPSC
TEMPSC
RISERS
BOAT
LA
ND
ING
BOAT
LA
ND
ING
AIR
INTA
KE
S
Sou
rces
of ig
nitio
n
Saf
eut
ilitie
sLo
w h
azar
dar
eaHig
h ha
zard
area
VENT
ELEVATEDFLARES
Zone 1 hazardous area Zone 2 hazardous area
210°
Hel
icopt
er approach sector
LIVINGQUARTERS
UTILITYPLATFORM
PROCESSPLATFORM
BOAT
APP
ROAC
H SE
CTO
R
PREVAILINGWIND
Life raft
Life raft
Life raft TEMPSC
BOAT UNLOADINGPOSITION
Figure 2 - Typical layout of offshore fixed platforms
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 20/64
5.3.10 Fire-fighting-related requirements The maximum unit size shall be compatible with the maximum fire zone size (refer to GS EP SAF 253 for further details).
Monitors shall either be accessible in case of fire, or alternatively they shall be remote controlled. Monitor control panels shall be shielded from thermal radiation coming from any potential fire.
The access ways shall be designed in such a manner that each unit handling hydrocarbon is accessible over the whole length of its sides, the loop surrounding them shall be connected to the general access system at a minimum of two points distant from one another and preferably from opposite side of the unit.
Access for active fire-fighting shall be possible under any combination of fire scenario and weather conditions. In particular, units shall be convex and should preferably be rectangular.
The layout shall be such that the fire water can be contained, or drained, to preclude any risk of liquid running fire.
5.3.11 Escape, Evacuation and Rescue systems In addition to provisions for normal operation, the layout shall incorporate specific requirements to face an emergency situation.
Escape, Evacuation and Rescue (EER)-related requirements in the SAFETY CONCEPT shall be considered as mandatory for safety to life, and shall prevail over any assets protection, operability or technical constraints for unit layout.
The EER facilities, including temporary refuges, shall be located with due consideration for wind, sea swell and current (refer to Section 5.3.9) in addition to requirement mentioned in GS EP SAF 351.
5.4 Interconnection units Appendix B provides guidelines for the arrangement of interconnections between units such as pipe-racks, cable routes and bridges. It does not deal with other location and protection cases, for which another general safety specification is available:
• ESDV’s (refer to GS EP SAF 253 & GS EP SAF 261)
• Flare network (refer to GS EP SAF 262)
• Fire main ring (refer to GS EP SAF 321).
5.5 Location of rooms in the installation The location of rooms in the installation shall be selected with a particular attention, and shall be supported by a specific justification dossier for approval by COMPANY.
The different rooms in the installation shall be classified either as:
• Technical rooms or
• Control rooms or
• Laboratories (and other rooms containing fuel sources as analyser shelters) or
• Workshops and warehouses or
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 21/64
• Offices or
• Living quarters.
No pipe penetration is allowed inside any rooms if piping contains hydrocarbons or hazardous substances.
No GRP piping transporting water is allowed inside any room if water hammer phenomenon is to be expected.
5.5.1 Technical rooms Technical rooms are not permanently manned and their occupancy is strictly limited to few authorised persons performing controlled activities.
They contain ignition sources (but no fuel source) and therefore they shall be either located in a safe area or constitute a safe area (ventilation/pressurisation with HVAC air intakes in safe area, and air locks) as close as possible from process or equipment (refer to GS EP SAF 216).
Technical rooms that are necessary in Emergency Response or EER operations shall be adequately fire and blast-proofed and shall conserve, after the fire and explosion, their specified fire and blast rating (refer to GS EP SAF 337).
5.5.2 Control rooms Control rooms are permanently manned and their normal occupancy shall be strictly limited to few authorised persons performing controlled activities.
Under no circumstances control rooms shall constitute a Temporary Refuge or the Emergency Control Centre.
Control rooms shall either be located in a safe area or constitute a safe area (pressurisation with HVAC air intakes in safe area and air locks).
Onshore, control rooms shall be at sufficient distance to ensure that consequences (based on major failures as per GS EP SAF 253) do not put their integrity at risk (outside the Restricted Area). Control rooms installed in the Restricted Area and that perform functions that must remain operational for Emergency Response and/or are required to control sustained operation of remote facilities shall be adequately pressurised, fire and blast-proofed and shall conserve, after a possible fire or explosion, their specified fire and blast ratings (same as in Section 5.5.1). In this particular case, they shall be surrounded on all external faces by an area approximately 30 metres wide left totally unobstructed.
Offshore, it is recommended to locate control rooms in the accommodation quarters in order to reduce the exposure of hazards generated by process units.
5.5.3 Laboratories and analyser shelters In the limit of what is technically achievable, laboratories should be located as far as possible from main fuel sources.
Laboratories should be located in a non-hazardous area. If a laboratory is located inside a hazardous area, its HVAC system shall be designed in agreement with the requirements of GS EP SAF 216.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 22/64
Analyser shelters may be in the immediate vicinity of the units they serve providing they are not used for other duties. Their HVAC system shall be designed in agreement with the requirements of GS EP SAF 216.
5.5.4 Workshops and warehouses Workshops and warehouses can be permanently manned. They constitute premises where, or around which, various uncontrolled hazardous activities may take place (e.g. traffic, hot work).
Onshore, workshops and warehouses shall be located in the general services area (refer to Section 5.3.2).
Offshore, workshops and warehouses should be at sufficient distance of units handling hazardous material so that they are not exposed to a flammable gas cloud at LFL in the case of an incident corresponding to a major failure (refer to GS EP SAF 253). If not possible, they shall be isolated from the rest of the installation by a gas-tight, fire and blast proof partition rated H-120.
5.5.5 Offices2 Onshore offices shall be located in the general service area (refer to Section 5.3.2), away from sources of hazards, at sufficient distance to ensure that consequences (based on major failures as per GS EP SAF 253) do not put their integrity at risk.
Offshore offices shall be located preferably on the accommodation platform except if protected by a fire and blast proof wall and if openings are oriented towards a safe area.
5.5.6 Living quarters3 Living quarters (LQ’s) are permanently manned.
Living Quarters shall be located in the safest area within the installation, so that life is not endangered in case of an explosion (and subsequent fire) from the process & utilities areas.
Onshore LQ’s shall be located in an inherently safe area as the general services area (refer to Section 5.3.2), or offsite and outside the restricted area.
Offshore, they should preferably be installed on a specific platform without process, storage, well and major utility equipment. Wherever this specific requirement cannot be fulfilled, the recommendations in Section 5.6 shall apply.
5.6 Layout of integrated platforms Offshore integrated platforms can present specific layout problems caused by their congestion, incompatible units arranged close to each other, and their position with respect to the prevailing wind. As a result some of the requirements conveyed by the present specification are not practicably attainable. The general arrangement of integrated platforms shall therefore be subject to a particular study and shall be supported by a justification dossier for approval by
2 Office occupancy is not limited and all persons in offices are considered mentally capable and awake. Occupancy
can however include persons that are physically disabled or that are not aware of the specific hazards of an installation containing hydrocarbon.
3 Living Quarters occupancy is not limited and can include persons that are physically disabled that are not aware of the specific hazards of an installation containing hydrocarbon and/or can be sleeping, thus slowing down their capacity to react in case of an emergency. In addition living quarters can contain special hazards and in particular some fuel sources and ignition sources e.g. kitchen, laundry, boilers and waste temporary storage.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 23/64
COMPANY, and the following set of rules is provided as a guideline (refer to Figure 3 - Typical layout of offshore integrated platform):
• Permanently manned rooms, muster areas, emergency control centre, radio room and evacuation means in accordance with the requirement of GS EP SAF 351 shall be grouped and located upwind the rest of the installation
• Temporary Refuges and means of evacuation shall be provided in the hazardous area for Emergency Response and evacuation of the personnel that cannot escape from the downwind part of the installation in case of an emergency. Capacity of TR and means of evacuation shall be based on the OPERATING PHILOSOPHY and SAFETY CONCEPT requirements. By default, a capacity of 50% of the POB shall be taken
• Permanently manned rooms, ER and EER facilities shall be separated from the rest of the installation by a fire and blast proof wall, H-120 fire rated, as high as the equipment it protects and presenting no open section with the exception of access ways to the plant area, at the edges of the platform
• Safe utility units (e.g. air compressors or water injection) shall be grouped upwind the units containing hydrocarbon and shall constitute a buffer zone between the permanently manned area and the process areas
• Units requiring fresh air to be drawn from safe locations (e.g. HVAC, power plant, gas turbines) shall be located upwind of any hazardous areas
• Units containing ignition sources shall be either located upwind units containing fuel sources or enclosed in pressurised premises
• Hazardous units shall be segregated by their increasing level of hydrocarbon risks. The most severe hazards shall be downwind and farther away from the living quarters
• Integrated flares tips shall be located downwind the installation, at a sufficient distance and height from hazardous areas to avoid ignition of a flammable gas cloud or a liquid hydrocarbon spillage to sea
• The structure of the elevated flares and the main flares headers shall be blast and fire proofed to ensure they are kept operational over the time it takes to complete an Emergency De-Pressurisation (refer to GS EP SAF 337)
• One lateral side of the platform shall be devoted to boat traffic and heavy lifts, and the opposite lateral side shall be reserved to risers and ESDV’s.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 24/64
High hazard area
Low hazard area
PR
EVA
ILIN
G W
IND
Machinery & sources of ignitionR
ISER
S
BO
AT
LAN
DIN
G
BO
AT
AP
PR
OAC
H S
ECTO
R
Air intakes
Safe utilities (buffer area)
210°
heli
copt
er
ELEVATED
TR TR
Fired heater
Life Raft
Life Raft
TEM
PSC
TEMPSC
Structure with passive fire protection
Zone 2 hazardous areaZone 1 hazardous area
VENT
TEM
PSC
FLARE
H LIVING QUARTERS CONTROL ROOM
OFFICES
approach sector
Radio room
Bla
st p
roof
/ fir
e pr
oof w
all
Figure 3 - Typical layout of offshore integrated platform
5.7 Temporary facilities The layout shall take into account the temporary facilities such as construction campsite and temporary accommodations, temporary power generation and other utilities or early production systems.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 25/64
These facilities shall form part of the project, shall be identified separately (considering they might have been forgotten in the STATEMENT OF REQUIREMENTS and can produce specific hazards) and shall be represented in dotted lines on all plot plans and elevations, until their complete de-commissioning and removal.
In the case of "grassroots" installations, particular consideration shall be paid to all measure likely to ensure the required safety standards during the period when simultaneous operations (SIMOPS) between construction and production activities will take place, i.e. from commissioning up to a few months after start-up. Four main configurations can be identified that may entail impact on layout:
• The construction campsite and temporary accommodations are likely to be manned for a significant period of time after oil and gas-in
• Construction activities are likely to continue while part of the process plant is already on stream, especially when initial production is obtained through an Early Production System (EPS) and more especially so when said EPS shares some systems (generally piping) with final units
• Temporary utilities, such as power generation, are kept operational until the new facilities have proven reliable
• Mechanical completion (and hence commissioning and start-up) of units operating in parallel (e.g. separation or compression trains) are time staggered and lead inevitably to a lengthened period of simultaneous construction and production operation.
5.8 Future extensions The layout shall take future foreseen extensions into account, as per STATEMENT OF REQUIREMENTS. This includes, but not limited to, additional wells, increased water handling, secondary or tertiary recovery systems, additional process trains and, as mentioned above, their associated construction area and related safe accesses.
Future extensions shall be represented in dotted lines on all plot plans and elevations. Their location should be such that the amount of work to be carried out in the vicinity of live equipment is limited or even totally avoided.
6. Equipment layout The spacing between equipment within a unit shall meet the requirements stipulated in the hazardous area classification and/or the equipment specification for hazardous area suitability. Refer to GS EP SAF 216.
The requirements for equipment location and recommended distances between equipment are given in Appendix C.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Annex 1
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 26/64
Annex 1 (Informative) - Methodology to select layout
The following main principles should be applied:
• Containment of hydrocarbon: Hazardous releases to atmosphere of both liquid and gaseous compounds should be minimized as much as possible and the quick removal of any accumulated hazardous released product should be achieved.
• Prevention of ignition: Ignition sources should be segregated from fuel sources, and non hazardous areas from hazardous areas.
• Mitigation: Consequences of fires and explosions should be minimized, with respect to escalation and ease of access for fire-fighting.
• EER: Adequate measures for emergency situation should be provided.
In addition, layout should meet other requirements (valid for any other industrial facility) and in particular ensure easy operation (monitoring and maintenance), cater for vehicle and personnel traffic, security, safe working conditions, access for operation and maintenance, low impact to others (noise, toxicity, pollution, risk, etc.) and protection of the environment. Furthermore, layout should incorporate provisions for future extensions.
The methodology to select the layout of an installation includes three main steps:
• Choice of the location of the installation (refer to Section 4)
• General arrangement of units inside the installation (refer to Section 5)
• Layout of equipment in units (refer to Appendix C).
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 27/64
Appendix A - Spacing - Default distances tables
Distances between fire zones Although not specifically included into the scope of the present General Specification, the table of default fire zones (FZ) and Restricted Area (RA) distances (refer to Table A1) is enclosed hereafter for better linkage with tables of default distances between units (refer to Table A2 through to Table A9 and Figure A2 through to Figure A9)).
It is reminded that distances between fire zones mentioned in Table A1 are onshore default distances, to be used for preliminary General Arrangement or quick check and that, in all cases, calculation of distances based on consequence analysis to match a set of pre-defined impact criteria are required. It is also reminded that these distances may be reduced or enlarged if physical partitions (e.g. fire and blast proof walls) are implemented. Refer to GS EP SAF 253 for more details.
Distances between units within their own fire zone COMPANY has established a set of default onshore distance tables (Tables A2 to A9) and subsequent sketches (Figures A1 to A9) for proper implantation of units within their own fire zones. Distances indicated in Tables and Figures A2 to A9 are not only dictated by safety considerations, but also and principally by constraints of construction, operability, access and maintenance. They represent COMPANY best engineering judgement, in terms of typical layout. Distances in tables below are devised to:
• Provide adequate safety to life in all cases
• Provide high degree of protection of the environment (although applicable requirements may vary from place to place)
• Provide a good (but not maximum) capacity to protect the asset in case of an incident
• Incorporate all foreseeable provisions for construction, operation, maintenance and inspection routine tasks with the possible exception of highly hazardous simultaneous operation.
Distances indicated in Tables and Figures A2 to A9 are plane horizontal 2D distances between the closest points of two different units (battery limits), without any obstacle and assuming that adequate safety features (e.g. fire-fighting systems, ESD system and qualification of personnel) are provided.
Onshore, default distances of Tables and Figures A2 to A9 may be reduced or enlarged. Distances between units shall then be supported by a justification dossier for approval by COMPANY.
Offshore, Tables and Figures A2 to A9 can be used as guidelines. However, the general arrangement of offshore platforms is subject to a particular study, based on best industry practices and recommendations given in Section 5.6, supported by a justification dossier for approval by COMPANY
There is no minimum distance between equipment and the unit battery limit, providing access to the equipment is granted (refer to Appendix C for distances between equipment).
The distance tables proposed below do not deal (at least in detail) with some specific cases, in particular onshore overhead hydrocarbon storage tanks (refer to GS EP SAF 341), FPSO’s, LNG plants, shorelines terminals and buried storage, for which either another general specification is available or a specific study is to be carried-out.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 28/64
Table A1 – Onshore default Fire Zones (FZ) and Restricted Area (RA) distances
Rem
inde
r: Th
is ta
ble
prov
ides
ons
hore
def
ault
Fire
Zon
es (F
Z) a
nd R
estr
icte
d A
rea
(RA
) di
stan
ces
and
not d
ista
nces
bet
wee
n eq
uipm
ents
or u
nits
with
in a
Fire
Zon
e.
Not
e :
All
dist
ance
s in
met
res.
D
ista
nces
take
n fro
m e
dge
of u
nit o
r equ
ipm
ent g
ener
atin
g Fi
re Z
one
or R
estri
cted
Are
a.
FZR
A11
1213
2122
3132
3341
4243
4445
46
11E
rupt
ive
oil /
gas
-lifte
d oi
l / g
as w
ell
5020
050
12N
on-e
rupt
ive
oil w
ell
1515
050
1513
Wat
er in
ject
ion
/ wat
er p
rodu
ctio
n w
ell
7.5
5050
157.
5
21N
on b
urie
d st
orag
e10
030
010
010
010
010
022
Bur
ied
stor
age
(1)
40 (1
)20
0 (1
)50
40 (1
)40
(1)
100
40 (1
)
31La
rges
t tan
k ca
paci
ty (2
) ≤ 1
0 00
0 m
370
(2)
170
(2)
70 (2
)70
(2)
70 (2
)10
070
(2)
70 (2
)
32La
rges
t tan
k ca
paci
ty (2
) ≤ 2
0 00
0 m
311
0 (2
)21
0 (2
)11
0 (2
)11
0 (2
)11
0 (2
)11
0 (2
)11
0 (2
)11
0 (2
)11
0 (2
)
33La
rges
t tan
k ca
paci
ty (2
) > 2
0 00
0 m
315
0 (2
)25
0 (2
)15
0 (2
)15
0 (2
)15
0 (2
)15
0 (2
)15
0 (2
)15
0 (2
)15
0 (2
)15
0 (2
)
41G
as w
ith o
pera
ting
pres
sure
> 7
0 ba
rg (3
)60
(3)
250
60 (3
)60
(3)
60 (3
)10
060
(3)
7511
0 (2
)15
0 (2
)60
(3)
42G
as w
ith o
pera
ting
pres
sure
≤ 7
0 ba
rg40
200
5040
4010
040
(1)
70 (2
)11
0 (2
)15
0 (2
)60
(3)
4043
LPG
pro
cess
100
200
100
100
100
100
100
100
110
(2)
150
(2)
100
100
100
44O
il or
con
dens
ate
proc
ess
8020
080
8080
100
8080
110
(2)
150
(2)
8080
100
8045
Slu
g ca
tche
r (4)
8025
080
8080
100
8080
110
(2)
150
(2)
8080
100
8080
46U
tiliti
es (u
sing
fuel
gas
) (5)
3050
5030
3010
040
(1)
70 (2
)11
0 (2
)15
0 (2
)60
(3)
4010
080
8030
51G
ener
al S
ervi
ce a
rea
(6)
NA
NA
200
150
5030
020
0 (1
)17
0 (2
)21
0 (2
)25
0 (2
)25
020
020
020
025
050
61Fl
ares
, col
d ve
nts,
bur
n pi
ts (7
)N
A15
020
015
015
030
020
0 (1
)17
0 (2
)21
0 (2
)25
0 (2
)25
020
020
020
025
015
0
(1) :
Def
ault
dist
ance
s pr
ovid
ed a
ll st
orag
e liq
uid
outle
ts a
re b
urie
d up
to th
e au
tom
atic
isol
atio
n va
lve.
(2) :
Def
ault
dist
ance
s to
be
take
n fro
m e
dge
of c
rude
oil
stor
age
tank
bun
ded
area
; eac
h co
ntai
ning
a s
ingl
e st
orag
e ta
nk. L
imit
bund
siz
e to
a m
axim
um o
f 700
0 m
2 .(3
) :
A
dd 1
5 m
etre
s if
oper
atin
g pr
essu
re a
bove
150
bar
g.(4
) :
Fi
nger
or v
esse
l-typ
e sl
ug c
atch
er w
ith V
liq >
50
m3 o
r P x
Vga
s > 1
000
bar
.m3 .
(5) :
May
als
o in
clud
e sa
fe u
tiliti
es o
n la
rge
plan
ts.
(6) :
(7) :
Flar
es, c
old
vent
s, b
urn
pits
Fire
Zon
es a
re p
ositi
oned
out
side
the
plan
t Res
trict
ed A
rea.
Con
vers
ely,
pla
nt is
pos
ition
ed o
utsi
de th
e R
estri
cted
Are
a ge
nera
ted
by fl
ares
, ven
ts, b
urn
pits
. (8
) :
D
efau
lt di
stan
ce to
ens
ure
that
flar
es, c
old
vent
s, b
urn
pits
are
inde
pend
ant.
Gen
eral
Ser
vice
are
a co
ntai
ns li
ving
qua
rters
, offi
ces,
con
trol r
oom
s, fi
re s
tatio
n, w
orks
hops
and
war
ehou
ses,
gua
rd h
ouse
, saf
e ut
ilitie
s, m
uste
r are
as, e
mba
rkat
ion
area
, gar
bage
inci
nera
tor,
helid
ecks
, wor
ship
room
s an
d re
crea
tion
area
s, lo
gist
ics
build
ings
, tel
ecom
she
lter a
nd ra
dio
mas
t, pe
trol s
tatio
n pa
rkin
g lo
ts a
nd b
us s
tatio
ns.
Gen
eral
Ser
vice
are
a Fi
re Z
one
is p
ositi
oned
out
side
the
plan
t Res
trict
ed A
rea.
FLAR
ES15
015
0 (8
)
CR
UD
E O
IL S
TOR
AG
E
PRO
CES
S &
UTI
LITI
ES
BU
ILD
ING
SN
A5161
WEL
LS
LPG
STO
RAG
E
Def
ault
Fire
Zon
es a
nd R
estri
cted
Are
a di
stan
ces
are
to b
e us
ed fo
r pre
limin
ary
Gen
eral
Arr
ange
men
t or q
uick
che
ck. I
n al
l cas
es, c
alcu
latio
n of
dis
tanc
es b
ased
on
cons
eque
nce
anal
ysis
as
per G
S E
P SA
F 25
3 ar
e re
quire
d to
take
in
to a
ccou
nt S
ite s
peci
fic d
esig
n ch
arac
teris
tics.
WEL
LSLP
G S
TOR
AGE
CR
UD
E O
IL S
TOR
AGE
PRO
CES
S &
UTI
LITI
ESB
UIL
DIN
GS
FLAR
ES
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 29/64
Figure A1 – Typical sketch of onshore General Arrangement
45 46
44
4341
PIP
ELI
NES
FZ :
80 m
13FZ
: 7.
5 m
12FZ
: 15
m
11FZ
: 50
m AC
CE
SS11
RA
: 20
0 m
12R
A :
150
m
13R
A :
RA : 250 m
(3) FZ :
RA : 250 m RA : 200 m
FZ :
100
m
FZ :
30 m
RA : 50 m
FZ :
80 m
RA : 200 m
22RA : 200 m
21RA : 300 m
22FZ
: 40
m
21FZ
: 10
0 m
61R
A :
150
m
RA : 170 m
RA : 210 m
RA : 250 m
31
32
33
FZ : 70 m
31FZ : 1
10 m
32FZ : 1
50 m
3351
RIG
AR
EA
60 m
PIP
ER
AC
KS
ER
UPT
IVE
OIL
/GAS
-LIF
TED
OIL
/GAS
WEL
L11
WE
LLS
NO
N-E
RU
PTIV
E O
IL W
ELL
12
WAT
ER
INJE
CTI
ON
/ W
ATER
PR
OD
UC
TIO
N W
ELL
13
NO
N B
UR
IED
STO
RAG
E21
BU
RIE
D S
TOR
AGE
22
LAR
GE
ST T
AN
K C
AP
ACIT
Y ≤
10 0
00 m
³ 31
LAR
GE
ST T
AN
K C
AP
ACIT
Y ≤
20 0
00 m
³ 32
LAR
GE
ST T
AN
K C
AP
ACIT
Y >
20 0
00 m
³ 33
GAS
WIT
H O
PER
ATI
NG
PR
ES
SUR
E >
70 b
arg
41
LPG
PR
OC
ESS
43
OIL
OR
CO
ND
ENSA
TE P
RO
CES
S44
SLU
G C
ATC
HER
45
UTI
LITI
ES
( USI
NG
FU
EL
GA
S )
46
GEN
ER
AL S
ER
VIC
E A
RE
A (O
UT
OF
PLAN
T AR
EA)
51
FLA
RE
S, C
OLD
VE
NTS
, BU
RN
PIT
S61
LPG
STO
RAG
E
CR
UD
E O
IL S
TOR
AG
E
PR
OC
ES
S &
UTI
LITI
ES
BU
ILD
ING
S
FLA
RE
S
LEG
EN
D:
PER
IMET
ER F
EN
CE
FIR
E Z
ON
E (F
Z)R
ES
TRIC
TED
AR
EA (R
A)
NO
TE:
(3) A
DD
15
ME
TRE
S IF
OPE
RAT
ING
PR
ESS
UR
E IS
ABO
VE
150
barg
.
ITEM
50 m
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 30/64
Table A2 – Onshore distances between units within well Fire Zone
All
dist
ance
s in
met
res.
WEL
L FI
RE
ZON
EA
BA
Wel
ls s
paci
ng(1
)
BP
erim
eter
fenc
e20
0N
A
(1) :
No
defa
ult d
ista
nce
prov
ided
; dis
tanc
es s
hall
be g
over
ned
by d
rillin
g rig
con
side
ratio
ns.
Not
es :
Uni
ts n
orm
ally
ass
ocia
ted
with
wel
ls in
a w
ell c
lust
er a
rea,
suc
h as
gas
or l
iqui
d pr
oces
s un
its, t
est s
epar
ator
and
au
xilia
ries,
pig
trap
s, c
hem
ical
sto
rage
, ven
ts/fl
ares
/bur
n pi
ts, b
uild
ings
, ove
rhea
d po
wer
line
s, fi
re fi
ghtin
g un
it (ta
nk a
nd p
umps
), ga
s or
liqu
id m
eter
ing
stat
ions
, fire
d he
ater
s un
it, D
iese
l sto
rage
, etc
... s
hall
be lo
cate
d ou
tsid
e th
e w
ell F
ire Z
one
in d
edic
ated
and
inde
pend
ant F
ire Z
one(
s), a
s pe
r tab
les
A2
to A
9.Fo
r def
ault
dist
ance
s be
twee
n Fi
re Z
ones
, ref
er to
Tab
le A
1.
Ons
hore
, no
units
are
inst
alle
d w
ithin
the
wel
l Fire
Zon
e , w
hich
is le
ft fre
e fo
r dril
ling
rig fa
cilit
ies.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 31/64
Figure A2 – Typical sketch of onshore well Fire Zone
41
RA
: 250
m
RA
: 200
m
FZ :
40 m
FZ
: 50
m
FZ
: 7.5
m
FZ
: 15
m
RA
: 50
m
RA
: 15
0 m
RA
: 200
m
51
RIG
AC
CES
S AR
EA
RA : 150 m
PIP
ELI
NE
13
12
11
61
12
11
FZ :
60 m
42 4113
A 42
41 42
15m
ER
UPT
IVE
OIL
/GA
S-LI
FTED
OIL
/GAS
WEL
L11
WE
LLS
NO
N-E
RU
PTIV
E O
IL W
ELL
12
WAT
ER IN
JEC
TIO
N /
WA
TER
PR
OD
UC
TIO
N W
ELL
13
GEN
ERAL
SER
VIC
E AR
EA (O
UT
OF
PLAN
T AR
EA)
51
BU
ILD
ING
S
FLA
RE
S, C
OLD
VE
NTS
, BU
RN
PIT
S61
FLA
RE
S
GAS
WIT
H O
PER
ATI
NG
PR
ESSU
RE
> 70
bar
g41
PR
OC
ESS
& U
TILI
TIE
S
GAS
WIT
H O
PER
ATI
NG
PR
ESSU
RE ≤
70 b
arg
42
PIG
TR
APS
A
ITE
M
LEG
EN
D:
PER
IMET
ER F
ENC
EFI
RE
ZO
NE
(FZ)
RES
TRIC
TED
AR
EA (R
A)D
ISTA
NC
ES
BETW
EEN
UN
ITS
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 32/64
Table A3 - Distances between units within flare Fire Zone
Rem
inde
r :
Not
es :
FLAR
E FI
RE
ZON
E (1
)A
BC
DE
FA
Elev
ated
flar
e 15
0 (2
)
BBu
rn p
it15
015
0 (2
)
CEn
clos
ed g
roun
d fla
re15
015
030
DFl
are
KO
dru
m +
aux
iliarie
s13
0 (3
)13
0 (3
)30
NA
EC
old
vent
150
150
150
130
(3)
150
(2)
FPe
rimet
er fe
nce
150
150
3030
150
NA
(0) :
(1) :
Flar
es, c
old
vent
s, b
urn
pits
Fire
Zon
es a
re c
alcu
late
d w
ith R
estri
cted
Are
a cr
iteria
(Ref
er to
GS
EP S
AF 2
53) a
nd a
re th
eref
ore
equi
vale
nt.
(2) :
(3) :
All d
ista
nces
in m
etre
s.D
ista
nces
take
n fro
m e
dge
of u
nit.
For c
omm
odity
pur
pose
s, th
e di
ffere
nt ty
pes
of d
ispo
sal s
yste
ms
are
furth
er re
ferr
ed a
s 'fl
ares
', an
d re
fere
nce
is m
ade
to 'f
lare
fire
zon
e' fo
r 'd
iffer
ent t
ypes
of d
ispo
sal s
yste
ms
fire
zone
s'.
This
tabl
e pr
ovid
es o
nsho
re d
efau
lt di
stan
ces
betw
een
diffe
rent
type
s of
dis
posa
l sys
tem
s (0
) (diff
eren
t typ
es o
f fla
res
and
vent
s)
Ons
hore
, no
units
are
inst
alle
d w
ithin
the
flare
Fire
Zon
e , w
ith th
e po
ssib
le s
ingl
e ex
cept
ion
of th
e fla
re K
O d
rum
.Fo
r def
ault
dist
ance
s be
twee
n Fi
re Z
ones
, ref
er to
Tab
le A
1.
Def
ault
valu
e to
ens
ure
that
flar
es, b
urn
pits
or c
old
vent
s ar
e in
depe
nden
t. Sh
ould
it n
ot b
e th
e ca
se, t
hen
a m
axim
um d
ista
nce
of 1
0 m
etre
s to
be
inst
alle
d be
twee
n tw
o fla
re ti
ps o
n th
e sa
me
stru
ctur
e, tw
o bu
rner
s in
the
sam
e bu
rn-p
it, o
r tw
o ve
nt ti
ps o
n th
e sa
me
stru
ctur
e, in
line
with
GS
EP S
AF 2
62.
Flar
e K
O d
rum
and
aux
iliarie
s ca
n be
loca
ted
in fl
are
Fire
Zon
e pr
ovid
ing
radi
atio
n cr
iteria
giv
en in
GS
EP
SAF
262
are
fulfi
lled.
How
ever
, it i
s re
com
men
ded
to lo
cate
them
out
side
the
flare
Fire
Zon
e.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 33/64
Figure A3 – Typical sketch of onshore flare Fire Zone
RA
= 15
0 m
RA =
150
m
B
A
OR
E
130
m
DC
FLAR
E LI
NES
FRO
M P
RO
CES
S30 m
30 m30
m
ELE
VATE
D F
LAR
EA
BU
RN
PIT
B
EN
CLO
SED
GR
OU
ND
FLA
RE
C
FLA
RE
KO
DR
UM
+ A
UXI
LIAR
IES
D
CO
LD V
ENT
E
DES
CR
IPTI
ON
ITE
M
LEG
EN
D:
PER
IME
TER
FEN
CE
FIR
E ZO
NE
(FZ)
RE
STR
ICTE
D A
REA
(RA)
DIS
TAN
CES
BET
WEE
N U
NIT
S
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 34/64
Table A4 - Distances between units within process Fire Zone
Rem
inde
r :
Not
es :
All d
ista
nces
in m
etre
s.D
ista
nces
take
n fro
m e
dge
of u
nit.
PRO
CES
S FI
RE
ZON
EA
BC
DE
FG
HI
JK
LM
NA
Pig
traps
NA
BG
as m
eter
ing
stat
ion
15 (6
)7.
5C
Liqu
id e
xpor
t pum
ping
/ m
eter
ing
stat
ion
15 (6
,7)
15 (6
,7)
7.5
DG
as p
roce
ss u
nit (1
)15
(6)
15 (6
)15
(6)
15 (6
)
EO
il / c
onde
nsat
e pr
oces
s un
it (2
)15
(6)
15 (6
)15
(6)
15 (6
)15
(6)
FG
as c
ompr
essi
on u
nit (3
)30
3030
3030
15G
Ope
n an
d cl
osed
dra
in d
rum
s +
auxi
liarie
s15
1515
1515
30N
AH
Mai
n pi
pe ra
ck7.
57.
57.
57.
57.
57.
57.
5N
AI
LPG
pro
cess
uni
t (4)
3030
3030
3045
307.
5N
AJ
Oily
wat
er tr
eatm
ent u
nit
3030
3030
3045
7.5
7.5
30N
AK
Fire
d he
ater
s un
it30
(8)
30 (8
)30
(8)
30 (8
)30
(8)
45 (6
)30
7.5
6030
30L
Tech
nica
l / E
&I ro
om15
1515
1515
15 (6
)7.
57.
515
3030
(8)
7.5
MC
ontro
l roo
m (p
erm
anen
tly m
anne
d) (5
)30
3030
3030
30 (6
)30
3060
3030
(8)
NA
NA
NPe
rimet
er fe
nce
250
250
200
250
200
250
5025
020
050
30 (8
)30
30N
A
(1) :
Incl
udes
gas
sep
arat
ion,
deh
ydra
tion
units
, sw
eete
ning
uni
ts, d
ewpo
intin
g un
its, t
urbo
-exp
ande
rs, m
olec
ular
sie
ves,
fuel
gas
uni
t. (2
) :In
clud
es o
il an
d co
nden
sate
sep
arat
ion,
des
altin
g un
its, s
tabi
lisat
ion
units
.(3
) :In
clud
es s
crub
bers
and
coo
ling
units
.(4
) :In
clud
es fr
actio
natio
n un
its a
nd tr
eatm
ent u
nits
.(5
) :
(6) :
Add
15 m
if n
orm
al o
pera
ting
pres
sure
> 7
0 ba
rg.
(7) :
Add
15 m
if li
quid
is L
PG.
(8) :
Add
15 m
if d
uty
> 10
MW
.
This
tabl
e pr
ovid
es o
nsho
re d
efau
lt di
stan
ces
betw
een
units
with
in th
e pr
oces
s Fi
re Z
one
and
not b
etw
een
units
per
tain
ing
to d
iffer
ent f
ire z
ones
. Fo
r def
ault
dist
ance
s be
twee
n Fi
re Z
ones
, ref
er to
Tab
le A
1.
Con
trol r
oom
sha
ll be
ade
quat
ely
pres
suris
ed, f
ire a
nd b
last
-pro
ofed
and
sha
ll co
nser
ve, a
fter a
pos
sibl
e fir
e or
exp
losi
on, i
ts s
peci
fied
fire
and
blas
t rat
ings
. It
shal
l be
surr
ound
ed o
n al
l ext
erna
l fac
es b
y an
are
a ap
prox
imat
ely
30 m
etre
s w
ide
left
tota
lly u
nobs
truct
ed.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 35/64
Figure A4 – Typical sketch of onshore process Fire Zone
J K
I
GE
D
F
RA : 50 m
RA : 200 m
BC
OR
RA : 50 m
RA : 250 m
H
ED
RA : 200 m
M 30 mRA :
A
RA : 250 m
PIP
ELI
NES
BR
A : 2
50 m
C
L RA : 30 m
RA : 250 m
RA : 250 m
15 m
15 m
30 m
30 m
30 m (6)
15 m
15 m
RA
: 200
m
45 m
30 m
RA : 30 m
7.5 m
45 m
60 m
30 m
15 m
15 m
15 m 15 m
7.5 m
RA
: 250
m
30 m
PIG
TR
APS
A
GA
S M
ETE
RIN
G S
TATI
ON
B
LIQ
UID
EXP
OR
T P
UM
PIN
G /
MET
ERIN
G S
TATI
ON
C
GA
S P
RO
CE
SS
UN
ITD
OIL
/ C
ON
DE
NS
ATE
PR
OC
ESS
UN
ITE
GA
S C
OM
PR
ES
SIO
N U
NIT
F
DES
CR
IPTI
ON
ITEM
OP
EN
AN
D C
LOS
ED
DR
AIN
DR
UM
S +
AU
XIL
IAR
IES
G
MA
IN P
IPE
RA
CK
H
LPG
PR
OC
ES
S U
NIT
I
OIL
Y W
ATE
R T
RE
ATM
EN
T U
NIT
J
FIR
ED
HE
ATE
RS
UN
ITK
TEC
HN
ICA
L / E
&I R
OO
ML
CO
NTR
OL
RO
OM
(PE
RM
AN
EN
TLY
MAN
NE
D)
MNO
TE:
(6) A
DD
15
ME
TRE
S IF
NO
RM
AL
OP
ERA
TIN
G P
RES
SUR
E IS
> 7
0 ba
rg.
LEG
END
:P
ERIM
ETER
FEN
CE
FIR
E ZO
NE
(FZ)
RE
STR
ICTE
D A
RE
A (R
A)D
ISTA
NC
ES
BE
TWEE
N U
NIT
S
(6)
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 36/64
Table A5 - Distances between units within utility Fire Zone
Rem
inde
r :
Not
es :
All d
ista
nces
in m
etre
s.D
ista
nces
take
n fro
m e
dge
of u
nit.
UTI
LITY
FIR
E ZO
NE
AB
CD
EF
GH
IJ
KL
MN
OP
APr
opan
e st
orag
e (1
)15
BPr
opan
e lo
adin
g po
st30
30C
Ove
rhea
d po
wer
line
s10
030
NA
DEl
ectri
cal s
ubst
atio
n10
030
157.
5E
Fire
d he
ater
s un
it10
030
4530
30F
Pow
er g
ener
atio
n un
it in
clud
ing
emer
genc
y10
030
4515
30 (5
)15
GTe
chni
cal /
E&I
room
100
3030
NA
30 (5
)15
7.5
HFi
re fi
ghtin
g un
it (ta
nks
and
pum
ps)
100
3045
3030
(5)
3015
NA
IW
ater
trea
tmen
t uni
t10
030
3030
307.
57.
515
7.5
JFu
el g
as u
nit
100
3045
3030
(5)
3030
3030
7.5
KC
hem
ical
sto
rage
100
3045
3030
(5)
3030
3015
30N
AL
Air /
N2 u
nits
100
3030
3030
7.5
7.5
157.
530
15N
A
MSt
eam
gen
erat
ion
unit
100
3045
3030
(5)
3030
3030
3030
30N
AN
Con
trol r
oom
(2) (p
erm
anen
tly m
anne
d)10
030
4530
30 (5
)30
NA
3030
3030
3030
NA
OD
iese
l sto
rage
(200
0 m
3 max
.(3) ) +
aux
iliarie
s10
030
4530
30 (5
)30
1515
7.5
307.
57.
530
30N
AP
Perim
eter
fenc
e10
045
(4)
3030
(5)
3030
307.
530
3015
3030
30N
A
(1) :
(2) :
(3) :
Die
sel s
tora
ge w
ith a
cap
acity
larg
er th
an 2
000
m3
shal
l be
loca
ted
in th
e oi
l sto
rage
Fire
Zon
e.(4
) :G
ener
ally
, ove
rhea
d po
wer
line
arr
ival
sta
tion
loca
ted
at th
e pe
rimet
er fe
nce
to a
llow
acc
ess
by e
lect
rical
dis
tribu
tion
Com
pany
.(5
) :Ad
d 15
m if
dut
y >
10 M
W
This
tabl
e pr
ovid
es o
nsho
re d
efau
lt di
stan
ces
betw
een
units
with
in th
e ut
ility
Fire
Zon
e an
d no
t bet
wee
n un
its p
erta
inin
g to
diff
eren
t fire
zon
es.
For d
efau
lt di
stan
ces
betw
een
Fire
Zon
es, r
efer
to T
able
A1.
Prop
ane
max
imum
con
side
red
stor
age
is 5
0 m
3 , prov
idin
g ve
ssel
s ar
e su
itabl
y pr
otec
ted
and
fire
proo
fed.
Pro
pane
is fo
r uni
ts c
oolin
g pu
rpos
es o
nly.
15
met
res
indi
cate
s di
stan
ces
betw
een
two
prop
ane
vess
els.
Con
trol r
oom
sha
ll be
ade
quat
ely
pres
suris
ed, f
ire a
nd b
last
-pro
ofed
and
sha
ll co
nser
ve, a
fter a
pos
sibl
e fir
e or
exp
losi
on, i
ts s
peci
fied
fire
and
blas
t rat
ings
. It s
hall
be s
urro
unde
d on
all
exte
rnal
face
s by
an
area
app
roxi
mat
ely
30 m
etre
s w
ide
left
tota
lly u
nobs
truct
ed.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 37/64
Figure A5 – Typical sketch of onshore utility Fire Zone
MJ F
E
DC J
KO
A A
L
HG
30 m
30 m
30 m
30 m
30 m
30 m
30 m
15 m
15 m
45 m
45 m
30 m
30 m
30 m 15 m
7.5
m
15 m
30 m 30 m
30 m
30 m
100
m
RA
: 10
0 m
15 m30 m
N
100 m
B
RA
: 45
m
(5)
AP
RO
PA
NE
STO
RA
GE
+ L
OAD
ING
PO
ST
ITE
M
B
OV
ER
HE
AD
PO
WE
R L
INES
C
ELE
CTR
ICA
L S
UBS
TATI
ON
D
FIR
ED
HE
ATE
RS
UN
ITE
PO
WE
R G
EN
ER
ATI
ON
UN
IT IN
CLU
DIN
G E
MER
GE
NC
YF
TEC
HN
ICA
L / E
&I R
OO
MG
FIR
E F
IGH
TIN
G U
NIT
(TAN
KS A
ND
PU
MP
S)H
WA
TER
TR
EA
TMEN
T U
NIT
I
FUE
L G
AS
UN
ITJ
CH
EM
ICA
L S
TOR
AG
EK
AIR
/ N
2 U
NIT
SL
STE
AM
GE
NE
RA
TIO
N U
NIT
M
CO
NTR
OL
RO
OM
(PE
RM
AN
EN
TLY
MAN
NED
)N
DIE
SE
L S
TOR
AG
E (2
000
m³ m
ax.)
+ AU
XIL
IAR
IES
O
DE
SCR
IPTI
ON
LOA
DIN
G P
OST
NO
TE:
(5)
AD
D 1
5 M
ETR
ES
IF D
UTY
> 1
0MW
LEG
END
:P
ER
IME
TER
FEN
CE
FIR
E Z
ON
E (F
Z)R
ES
TRIC
TED
AR
EA (R
A)D
ISTA
NC
ES
BE
TWE
EN U
NIT
S
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 38/64
Table A6 - Distances between units within slug catcher Fire Zone
Rem
inde
r :
Not
es :
SLU
G C
ATC
HER
FIR
E ZO
NE
AB
CD
EF
ASl
ug c
atch
er (1
)30
BPi
g tra
ps15
NA
CLi
quid
-rec
eivi
ng v
esse
l (2) +
pum
ps7.
515
15D
Cat
ch /
spilla
ge p
it (2
)30
3030
NA
EC
hem
ical
sto
rage
uni
t7.
57.
57.
57.
5N
AF
Perim
eter
fenc
e25
025
025
050
50N
A
(1) :
Fing
er o
r ves
sel-t
ype
slug
cat
cher
with
Vliq
> 5
0 m
3 or P
x V
gas >
1 0
00 b
ar.m
3 .(2
) :
Ap
plic
able
to fi
nger
-type
slu
g ca
tche
rs o
nly.
All d
ista
nces
in m
etre
s.D
ista
nces
take
n fro
m e
dge
of u
nit.
Uni
ts n
ot li
sted
in h
ere
belo
w ta
ble
are
loca
ted
outs
ide
the
slug
cat
cher
Fire
Zon
e.
This
tabl
e pr
ovid
es o
nsho
re d
efau
lt di
stan
ces
betw
een
units
with
in th
e sl
ug c
atch
er F
ire
Zone
and
not
bet
wee
n un
its p
erta
inin
g to
diff
eren
t fire
zon
es.
For d
efau
lt di
stan
ces
betw
een
Fire
Zon
es, r
efer
to T
able
A1.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 39/64
Figure A6 – Typical sketch of onshore slug catcher Fire Zone
RA
: 25
0 m
PIPELINES
FZ : 80 m
B
E
FZ : 8
0 m
AC
D
FROM OUTSIDE
RA : 250 m
7.5 m
15 m
7.5
m
30 m
(FIN
GE
R T
YP
E S
LUG
CAT
CH
ER
)
7.5
m
SLU
G C
ATC
HER
A
PIG
TR
APS
B
LIQ
UID
- R
EC
EIV
ING
VES
SEL
+ PU
MP
SC
CA
TCH
/ S
PIL
LAG
E PI
TD
CH
EM
ICA
L S
TOR
AG
E U
NIT
E
DE
SCR
IPTI
ON
ITE
M
LEG
END
:P
ER
IME
TER
FE
NC
EFI
RE
ZO
NE
(FZ)
RE
STR
ICTE
D A
REA
(RA)
DIS
TAN
CE
S B
ETW
EEN
UN
ITS
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 40/64
Table A7 - Distances between units within LPG storage Fire Zone
Rem
inde
r :
Not
es :
LPG
STO
RAG
E FI
RE
ZON
EA
BC
DE
FG
HA
Abov
e gr
ound
sto
rage
uni
t(1
)
BU
nder
grou
nd o
r und
er-e
mba
nkm
ent s
tora
ge u
nit
2 (2
)1
CLP
G p
umpi
ng s
tatio
n15
(3)
15N
AD
LPG
met
erin
g st
atio
n15
(3)
157.
5N
AE
Load
ing
post
30 (4
)30
(4)
30 (4
)30
(4)
30F
Tech
nica
l / E
&I ro
om45
(3)
3030
3030
(4)
7.5
GM
ain
pipe
rack
15 (3
)15
7.5
7.5
30 (4
)30
NA
HP
erim
eter
fenc
e30
020
020
020
045
3020
0N
A
(1) :
Vess
el to
ves
sel d
ista
nce
= 1.
5 x
diam
eter
of l
arge
st v
esse
l (sp
here
or b
ulle
t) +
5 m
etre
s, w
ith a
min
imum
of 3
0 m
etre
s.(2
) :U
nder
grou
nd o
r und
er-e
mba
nkm
ent s
tora
ge u
nit P
SV d
isch
arge
to b
e lo
cate
d 10
met
res
away
from
abo
ve g
roun
d ad
jace
nt s
tora
ge u
nit.
(3) :
Dis
tanc
e fro
m e
dge
of re
tent
ion
basi
n.(4
) :Lo
adin
g po
sts
are
loca
ted
outs
ide
the
LPG
sto
rage
Fire
Zon
e, in
thei
r ded
icat
ed a
nd s
epar
ated
Fire
Zon
es.
This
tabl
e pr
ovid
es o
nsho
re d
efau
lt di
stan
ces
betw
een
units
with
in th
e LP
G s
tora
ge F
ire Z
one
and
not b
etw
een
units
per
tain
ing
to d
iffer
ent f
ire
zone
s.
All
dist
ance
s in
met
res.
Dis
tanc
es ta
ken
from
edg
e of
uni
t.U
nits
not
list
ed in
her
e be
low
tabl
e ar
e lo
cate
d ou
tsid
e th
e LP
G s
tora
ge F
ire Z
one.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 41/64
Figure A7 – Typical sketch of onshore LPG storage Fire Zone
C D F
RA
: 20
0 m
RA
: 20
0 m
RA
: 20
0 m
RA
: 30
m
RA : 200 mB
RA : 300 m
A
G
E
BFZ
:
AFZ
: 10
0 m
RA
: 45
m
AB
30 m
(1)
7.5 m 30 m
45 m
:
15 m
15 m
E
E
RA
: 45
m
30 m E
30 m
:
BA
7.5
m
7.5
m
A B C D E F G
ITEM
AB
OV
E G
RO
UN
D S
TOR
AGE
UN
IT
UN
DE
RG
RO
UN
D O
R U
ND
ER
-EM
BA
NK
MEN
T ST
OR
AGE
UN
IT
LPG
PU
MP
ING
STA
TIO
N
LPG
ME
TER
ING
STA
TIO
N
LOA
DIN
G P
OST
TEC
HN
ICA
L / E
&I R
OO
M
MA
IN P
IPE
RAC
K
DES
CR
IPTI
ON
LEG
END
:P
ER
IME
TER
FEN
CE
FIR
E Z
ON
E (F
Z)R
ES
TRIC
TED
AR
EA (R
A)D
ISTA
NC
ES
BE
TWEE
N U
NIT
S
40 m
(1) V
ES
SE
L TO
VE
SSE
L D
ISTA
NC
E :
-
1.5
x Ø
OF
LAR
GE
ST V
ESSE
L +
5 m
-
MIN
IMU
M O
F 30
m
NO
TE:
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 42/64
Table A8 - Distances between units within crude oil storage Fire Zone
Rem
inde
r :
Not
es :
OIL
STO
RAG
E FI
RE
ZON
EA
BC
DE
FG
AC
rude
oil
stor
age
unit
(1)
BO
il pu
mpi
ng s
tatio
n15
(2)
NA
CO
il m
eter
ing
stat
ion
15 (2
)7.
5N
AD
Load
ing
post
30 (3
)30
(3)
30 (3
)30
ETe
chni
cal /
E&I
room
45 (2
)30
3030
(3)
7.5
FM
ain
pipe
rack
15 (2
)7.
57.
530
(3)
30N
AG
Perim
eter
fenc
e25
020
020
045
3020
0N
A
(1) :
Tank
to ta
nk d
ista
nce
= di
amet
er o
f lar
gest
tank
if la
rges
t tan
k ca
paci
ty >
150
0 m
3 or 0
.5 x
dia
met
er o
f lar
gest
tank
if la
rges
t tan
k ca
paci
ty ≤
150
0 m
3 .(2
) :D
ista
nce
from
edg
e of
rete
ntio
n ba
sin.
(3) :
Load
ing
post
s ar
e lo
cate
d ou
tsid
e th
e oi
l sto
rage
Fire
Zon
e, in
thei
r ded
icat
ed a
nd s
epar
ated
Fire
Zon
es.
This
tabl
e pr
ovid
es o
nsho
re d
efau
lt di
stan
ces
betw
een
units
with
in th
e cr
ude
oil s
tora
ge F
ire Z
one
and
not b
etw
een
units
per
tain
ing
to d
iffer
ent
fire
zone
s.
All d
ista
nces
in m
etre
s.D
ista
nces
take
n fro
m e
dge
of u
nit.
Uni
ts n
ot li
sted
in h
ere
belo
w ta
ble
are
loca
ted
outs
ide
the
crud
e oi
l sto
rage
Fire
Zon
e.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 43/64
Figure A8 – Typical sketch of onshore crude oil storage Fire Zone
B C
E
RA
: 20
0 m
RA
: 20
0 m
RA
: 20
0 m
RA
:
RA : 170 m - CAPACITY ≤ 10000 m³
RA : 210 m - CAPACITY ≤ 20000 m³
F
D
FZ :
70 m
RA
: 45
m
A
30 m
(1)
7.5 m 30 m
45 m
15 m
FZ :
110
m
FZ :
150
m
D
D
RA
: 45
m
30 m D
D
RA
: 45
m
30 m D
RA : 250 m - CAPACITY > 20000 m³
7.5
m
7.5
m15
m
A B C D E F
ITE
MC
RU
DE
OIL
STO
RAG
E U
NIT
OIL
PU
MP
ING
STA
TIO
N
OIL
ME
TER
ING
STA
TIO
N
LOA
DIN
G P
OST
TEC
HN
ICA
L / E
&I R
OO
M
MA
IN P
IPE
RA
CK
DE
SCR
IPTI
ON
(1) T
AN
K T
O T
AN
K D
ISTA
NC
E :
-
Ø O
F LA
RG
ES
T TA
NK
(CA
PAC
ITY
> 15
00m
³)
- 0
.5 x
Ø O
F LA
RG
ES
T TA
NK
(CAP
ACIT
Y ≤
1500
m³)
NO
TE:
LEG
EN
D:
PE
RIM
ETE
R F
EN
CE
FIR
E Z
ON
E (F
Z)R
ES
TRIC
TED
AR
EA (R
A)D
ISTA
NC
ES
BE
TWE
EN U
NIT
S
CA
PA
CIT
Y ≤
100
00 m
³
CA
PA
CIT
Y ≤
200
00 m
³
CA
PA
CIT
Y >
200
00 m
³
30 m
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 44/64
Table A9 - Distances between units within building Fire Zone
Rem
inde
r :
Not
es :
BU
ILD
ING
FIR
E ZO
NE
AB
CD
EF
GH
IJ
KL
MN
ALi
ving
qua
rters
7.5
BO
ffice
s7.
57.
5C
Wor
ksho
p/w
areh
ouse
1515
15D
Con
trol r
oom
7.5
7.5
15N
AE
Labo
rato
ry15
1515
15N
AF
Fire
sta
tion
3030
3030
30N
AG
Gua
rd h
ouse
7.5
7.5
157.
515
30N
AH
Boi
ler r
oom
(1)
15 (1
)15
(1)
15 (1
)15
(1)
15 (1
)30
15 (1
)N
AI
Ele
ctric
al s
ubst
atio
n30
3030
3030
3030
307.
5J
Inci
nera
tor (2
)30
(2)
30 (2
)30
(2)
30 (2
)30
(2)
30 (2
)30
(2)
30 (2
)30
(2)
NA
KO
verh
ead
pow
er li
nes
4545
4545
4545
4545
1545
NA
LSe
wag
e tre
atm
ent p
lant
/ sa
nita
ry la
ndfil
l60
6060
6060
6060
3060
3045
NA
MTe
leco
m s
helte
r / ra
dio
mas
t (3)
30 (3
)30
(3)
30 (3
)30
(3)
30 (3
)30
(3)
30 (3
)30
(3)
30 (3
)30
(3)
45 (3
)30
(3)
NA
NPe
rimet
er fe
nce
3030
3030
3030
530
3030
(4)
3030
(3)
NA
(1) :
Boi
ler u
sing
flam
mab
le g
as o
nly.
Dis
tanc
es n
ot re
quire
d fo
r boi
lers
usi
ng n
on h
azar
dous
liqu
id fu
el (d
iese
l oil)
or e
lect
rical
pow
er.
(2) :
Dis
tanc
es to
inci
nera
tor c
an b
e re
duce
d if
inci
nera
tor a
nd a
ppur
tena
nces
are
isol
ated
by
H-1
20 fi
re ra
ted
parti
tions
(ref
er to
GS
EP
SA
F 33
7).
(3) :
Use
tabl
e di
stan
ces
or (m
ast h
eigh
t + (2
0 %
or 5
met
res)
) whi
chev
er th
e la
rges
t.(4
) :G
ener
ally
, ove
rhea
d po
wer
line
arri
val s
tatio
n lo
cate
d at
the
perim
eter
fenc
e to
allo
w a
cces
s by
ele
ctric
al d
istri
butio
n C
ompa
ny.
This
tabl
e pr
ovid
es o
nsho
re d
efau
lt di
stan
ces
betw
een
units
with
in th
e bu
ildin
g Fi
re Z
one
and
not b
etw
een
units
per
tain
ing
to d
iffer
ent f
ire z
ones
. Fo
r def
ault
dist
ance
s be
twee
n Fi
re Z
ones
, ref
er to
Tab
le A
1.
All
dist
ance
s in
met
res.
Dis
tanc
es in
dica
ted
in p
rese
nt ta
ble
are
not o
nly
dict
ated
by
safe
ty c
onsi
dera
tions
, but
als
o an
d pr
inci
pally
by
cons
train
ts o
f con
stru
ctio
n, o
pera
bilit
y, a
cces
s an
d m
aint
enan
ce. T
hey
repr
esen
t CO
MPA
NY
best
eng
inee
ring
judg
emen
t, in
term
s of
Gen
eral
Ser
vice
are
a ty
pica
l lay
out.
Dis
tanc
es ta
ken
from
edg
e of
uni
t.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix A
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 45/64
Figure A9 – Typical sketch of onshore building Fire Zone
HE
D
J
AA
B
M
G
CC
FI
L
K
30 m
15 m
15 m
7.5
7.5
7.5
5 m
30 m
30 m
30 m
15 m
30 m
30 m
30 m
30 m
30 m
(3)(3)
30 m30 m
30 m30 m
30 m
30 m60 m
15 m
15 m
30 m
K
15 m
30 m
A B C D E F G H
ITE
MLI
VIN
G Q
UAR
TER
S
OFF
ICES
WO
RK
SH
OP
/ W
AR
EH
OU
SE
CO
NTR
OL
RO
OM
LAB
OR
ATO
RY
FIR
E S
TATI
ON
GU
AR
D H
OU
SE
BO
ILE
R R
OO
M
DE
SC
RIP
TIO
N
I J K L M
ELE
CTR
ICA
L S
UBS
TATI
ON
INC
INE
RAT
OR
OV
ER
HE
AD
PO
WE
R L
INES
SE
WA
GE
TR
EA
TME
NT
PLA
NT
/ SAN
ITA
RY
LAN
DFI
LL
TELE
CO
M S
HE
LTE
R /
RAD
IO M
AST
(3)
MA
ST
HE
IGH
T +
(20%
OR
5m
.) O
R 3
0m, W
HIC
H E
VER
IS L
AR
GE
STN
OTE
:
LEG
END
:P
ER
IME
TER
FEN
CE
FIR
E Z
ON
E (F
Z)R
ES
TRIC
TED
AR
EA
(RA
)D
ISTA
NC
ES
BE
TWEE
N U
NIT
S
mm
m
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix B
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 46/64
Appendix B - Arrangement of interconnections between units
Appendix B provides guidelines for the arrangement of interconnections between units such as pipe-racks, cable routes and bridges.
B1. Pipe-racks Pipe-ways within a single process unit can be provided with numerous flanges, valves, vents, drains and shall be considered as being part of the unit.
Pipe-runs between different process units shall be grouped in pipe-racks (overhead or ground level), with the exception of pipes that are to be buried for specific reasons (e.g. freezing, protection against fire, explosion or traffic). Pipe-racks should be as straight as practicable and shall be located outside process units.
The main pipe-racks mainly consist of all welded piping, and the number of flanges, valves, vents, drains or sample points shall be strictly limited.
Pipe-rack runs above access ways shall be minimised. Crossings of access ways should be at right angles and not above access way junctions and bends. Pipe-racks should not pass over the main access ways for mobile fire-fighting means. A very special emphasis shall be put on the routing and location of the flare header (or sub-header) pipe rack that shall minimise its exposure to external hazards such as traffic accident, fire or explosion in a process unit or others.
Overhead pipe-racks should preferably contain one single layer of piping. In a multi-layer pipe-rack, pipes carrying corrosive fluids shall be on the bottom level. Cable trays supported by pipe-racks shall be above the piping layer. Cable trays shall be so arranged that any foreseeable operation carried out on the below piping layer will not cause damage to the electrical cable trays. This may be achieved by suitable spacing between layers or the use of mechanical shielding. The flare headers shall be on the bottom level layer.
Pipe-runs outside the plant area should be on pipe tracks at grade level.
B2. Cable routes Cable routes, cable segregation and cable installation shall be as per GS EP ELE 079 and GS EP ELE 364.
B3. Bridges (offshore only) Bridges between platforms normally constitute escape ways and primary means of evacuation and shall therefore not be exposed to high hazards, such as those coming from risers and/or high pressure equipment. Bridges used as escape ways and primary means of evacuation shall remain passable under any prevailing weather conditions. If necessary or imposed by local regulation a QRA shall be carried out to determine the best bridge location with respect to such hazards as risers or high pressure gas piping.
Net clearance above sea level shall include high tide, swell and, wherever possible, the air draught of the supply boats normally posted to the concerned installation.
Bridges between platforms shall be free of any equipment with the single exception of fire monitors located at a convenient distance from the platforms. Bridges shall not pass under the routine operation swing zones of cranes and shall not be considered as temporary storage areas for loading/unloading operations.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix B
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 47/64
The bridges should normally consist in two levels with:
• The lower level devoted to main access and moderate load carriage and shall have minimum clearances of 2.3 m (height) and 1.2 m (width) or width of design load + 0.8 m, whichever the largest
• The upper level devoted to the routing of pipes and cables, with a secondary access way having a 0.8 m minimum width clearance.
Both bridge level floors should preferably be grating.
Bridge movement shall be compatible with an easy balance of personnel walking on it, and the fixed point should preferably be located on the platform of first access.
Bellows shall be carefully positioned so as to allow an easy inspection and minimise the consequences of a leak (refer to Appendix C3).
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 48/64
Appendix C - Equipment layout
C1. General
C1.1 Access ways and clearances The dimensions of the means of egress from any building are specified in GS EP SAF 221.
The dimensions of the Escape routes from the installation, which are part of the EER facilities, are specified in GS EP SAF 351.
Clearances for electrical equipment to be installed inside technical rooms and outdoors shall be as per GS EP ELE 001 and GS EP ELE 364.
This section is intended to specify the minimum requirements for the access ways and clearances that are not part of the required means of egress or escape routes and that should be provided where operation or inspection are required with a periodicity of at least once a month.
Minimum access ways clearance
Vehicles Pedestrians
Width 5 m
• Normal walkway: 1.0 m
• Elevated platform: 0.8 m
• Walkway receiving two or more routes: 1.2 m
• Maintenance access around equipment: 1.2 m
Headroom 4.5 m
• Normal walkway: 2.2 m
• Elevated platform: 1.9 m
• Maintenance access under equipment: 0.76 m
For dimensions of stairs, ramps, means of egress and routine access for personnel, refer to GS EP SAF 221.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 49/64
C1.2 Routine operation
Equipment Piece of equipment Requirement for location Recommended distance
Actuator and hand-wheel
May be conveniently reached when standing at grade level or from a permanent platform.
N/A
Horizontal spindle Between 0.75 and 1.5 metre above the grade or platform.
Should be 1 metre above grade level or platform.
Vertical spindle Between 1 and 1.5 metre above the grade or platform.
Should be 1.1 metre above grade level or platform.
Valve
Local position indicator
Clearly visible from working floor.
Positive isolations
Spades, spectacle blinds, removable spools
Accessible during operation without any requirement for scaffolding if access required with a periodicity of at least once a month.
N/A
Sampling Should be located at grade or accessible from a permanent platform.
Best location 1 metre above floor level.
Emergency showers and eyewash stations
Close to locations where personnel may be exposed to injurious or corrosive material such as laboratory, chemical injection skids, methanol storage or transfer units.
• < 15 metres away from hazard.
• 3 to 6 metres if possible or if the fluid is highly corrosive or irritative.
C2. Wells Distance between wells shall be governed by the rig foot print and by the need (addressed in the STATEMENT OF REQUIREMENTS and/or SAFETY CONCEPT) to keep wells in operation while the rig is performing drilling or work-over activities on an adjacent well.
X-mas trees and wellhead assemblies shall be accessible from any side for operation and maintenance. Casing pressure gauges shall be readable from grade or from a permanent fixed platform.
The wells spacing shall take into consideration wellhead series and all foreseeable multiple completions.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 50/64
The minimum width clearance around wellheads and appurtenances (e.g. chokes, valves, instruments, actuators) shall be 0.8 metre; the minimum clearance at grade or platform level shall be 1.2 metre.
Sufficient space reservation shall be available for drilling, workover, wire-line, stimulation or other well servicing activities, without interfering with production installation or production personnel.
To avoid collision between wells during drilling, a slot spacing of 2.3 m for a 24” Conductor Pipe (CP) and 2.5 m for a 30” CP is recommended.
C3. Unfired process equipment
Equipment Requirement for location Recommended distance
• Accessible from any side for operation and maintenance.
• Preferably, should be in open air at or near above grade level.
• Where handling flammable or toxic fluids, shall not be located in pits to meet any requirement (NPSH or others).
• Provide adequate space for lifting and handling facilities for maintenance.
• Provide retention basin.
• Retention basin preferably sloping downwards so that liquid hydrocarbons are collected and routed away from the ignition source.
• Provide adequately ventilated shelters for machine requiring in-situ maintenance or where a protection from the environment is required.
Pumps
LPG transfer pumps
• In open air.
• Preferably at the outer sides of installation, in a dedicated fire zone.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 51/64
Equipment Requirement for location Recommended distance
Pumps handling hydrocarbon at pressures above 35 barg
• Can be grouped together (and matching access requirement as per Appendix C1.1).
• Onshore, > 5 metres away from other pump units.
• Offshore, > 3 metres away from other pump units.
Air-coolers4 • Hot air emitted shall not be a hazard or an inconvenience to personnel.
• No adverse effect on the operation of adjacent equipment.
• Onshore, ground around air coolers gravelled to limit dust movement.
• Onshore, space underneath air coolers latticed wherever necessary.
• Offshore, air coolers installed on the edge or in cantilever over the edge of the platform5.
• > 10 metres away from fired equipment (heaters) and hot spots (chimneys)6.
• Not be above or within less than 5 metres to fuel sources (e.g. compressors and pumps handling hydrocarbons)7.
• Minimum headroom of 2.5 metres for induced draught and 3 metres for forced draught, if access underneath is provided for inspection.
Shell/Tube exchangers8
• Bundle shall be readily withdrawn without any hindrance into an escape route or traffic path.
• Provide adequate space for lifting and handling facilities for maintenance.
• Provide space reservation for 2 bundles (the defective and the new one) for bundle replacement9.
Cooling towers10
• Should be downwind from the rest of installation.
4 Air-coolers shall be considered as having a high ability in promoting the spread of a fire, and particular attention shall be paid to
their location with respect to any areas of special fire risk. 5 If not possible, it shall be assessed whether the deck under air coolers shall be open gratings or tight. 6 These distances are given considering that the air movement increases the fire spread and that the failure of a tube could
release additional combustible fluid to the fire. 7 Air-cooler may be located above pipe-racks, where practicable and economical, providing valves and flanges are avoided
underneath. 8 Units handling HFC-134 should be preferably located in their own fire zone, in such a way that the risk of HFC-134 to be
decomposed in toxic products when exposed to fire is minimized and/or shall be adequately fitted with passive fire protection. 9 Where economical and practicable, shell/tube exchangers may be stacked. 10 Cooling towers are a source of HC release and the fog they may generate should not cause corrosion or obstruct vision.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 52/64
Equipment Requirement for location Recommended distance
Filters • Provide access so that the cartridges can readily be changed-out from grade or from a permanent fixed platform.
• Provide adequate space for lifting and handling facilities for maintenance.
• Provide space reservation for 2 cartridges (the old one and the new one) for cartridge change-out.
• No equipment allowed above filters.
Process vessels
• All instruments, stand pipes or sampling points on one side of process vessels.
• Horizontal process vessels preferably perpendicular to the main pipe-rack onto which they are connected.
• No equipment over process vessels unless there is a tight deck in between.
• Onshore, at least 5 metres wide of unobstructed access on one side and normal access for operation (refer to Appendix C1.1) on the other sides.
• Offshore, at least 3 metres wide of unobstructed access on one side and a second access fulfilling the requirement of Appendix C1.1.
Process gas compressors
Offshore
• Preferably on the upper deck
• No equipment on top of process compressors except the seal-oil tank.
> 3 metres between compressors (from edge of skid).
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 53/64
Equipment Requirement for location Recommended distance
Onshore
• Downwind, on the periphery of their fire zone and as far as possible from ignition sources.
• Preferably perpendicular to the pipe-rack they are connected to.
• Provide an unobstructed access on two sides (a).
• Provide an unobstructed access on the third side facing the pipe-rack (b).
• No equipment on top of process compressors except the seal-oil tank.
• (a) > 5 metres wide.
• (b) 10 metres wide
Driven by gas turbines
• Very special attention shall be paid to the location of degassing vents (lube oil tank) with regards to hot surfaces (e.g. chimneys).
• No equipment on top of process compressors except the seal-oil tank.
> 5 metres to hot spots11
Desalters • On the periphery of the fire zone they pertain to, preferably downwind12.
• No equipment over desalters unless there is a tight deck in between.
• Heater-treaters, i.e. electrostatic desalters in which a flame tube is installed to enhance coalescence are not recommended onshore and are prohibited offshore.
• Offshore, 5 metres away from other process vessels.
• Onshore, 7.5 metres away from other process vessels.
11 Auto-ignition temperature of gas released by breathing vent may drop below 100°C. 12 Considering the large hydrocarbon inventory contained
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 54/64
Equipment Requirement for location Recommended distance
Sub-surface water pumps
• Provide protection against boat collision.
• Where practical, should not be on a side of the platform where a boat landing is provided.
• Provide sufficient head clearance above sub-surface water to allow change-out.
• Provide adequate space for lifting and handling facilities for maintenance.
• Provide space reservation for 2 pumps and/or motors (the defective and the new) for their replacement.
Bellows/ jambles
In open air outside process units13 > 10 metres off the edge of the platform
13 Bellows/jambles constitute a weak point and are likely to become a release source.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 55/64
C4. Fired equipment
Equipment Requirement for location Recommended distance
Fired heaters14 Refer to GS EP SAF 227
• Should preferably be at the outer sides of the installation in a dedicated fire zone.
• Away from fuel sources.
• Minimum spacing as per Appendix A, Tables A2 and A4 or as stipulated by local applicable regulation, whichever is greater.
• Whenever practical, should be at higher elevation than storage equipment or other bulk quantities.
• No equipment above fired heaters.
• Fired equipment comprising a fire tube, such as glycol re-boilers, shall be located and arranged so that the fire tube can readily be withdrawn without any projection to an escape route.
• The bolted flange should not be oriented towards an escape route or a traffic path.
• Provide adequate space for lifting and handling facilities for maintenance in particular for fire tube replacement.
Refer to GS EP SAF 227
14 Fired heater should be regarded as a main cause of hazard. They are permanent source of ignition. For further details and in
particular exhaust chimney, refer to GS EP SAF 227.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 56/64
Equipment Requirement for location Recommended distance
Machinery15 Refer to GS EP SAF 222
• Any source of ignition should be located at higher elevation than storage equipment (or other bulk quantities of hydrocarbon).
• Air intakes (HVAC, gas turbines, internal combustion engines, air compressors, etc.) located away from areas where air contamination by dust, flammable or toxic gas can occur (a).
• Air intakes (HVAC, gas turbines, internal combustion engines, air compressors, etc.) located preferably upwind the installation (a).
• Separate air intakes and discharges to avoid cross contamination by re-circulation, taking into account natural wind effects (b).
• Locate air discharges16 from HVAC systems so that the waste air emitted is not a hazard or inconvenience to personnel and has no adverse effect on the operation of adjacent equipment.
• Air exhausts shall not create a specific hazard for air traffic, especially during approach.
• (a) > 2 metres from any classified hazardous area.
• (b) > 6 metres.
• Turbine exhaust shall be at least 30 metres away from the helidecks.
15For further details and in particular exhaust chimneys, refer to GS EP SAF 222. 16 Air discharges from ventilation systems serving hazardous areas shall be considered as sources of release and shall be sited
accordingly.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 57/64
C5. Piping
Equipment Requirement for location Recommended distance
Risers, riser ESDV’s and conductor pipes
• Should be positioned or protected to minimize the likelihood of damage caused by ship impact and/or dropped objects.
• Riser ESDV’s should be located where they are unlikely to be affected by fires and explosion or any other damage.
• Wherever above requirement is not achievable, protect riser ESDV against radiation, blast, missiles and falling objects.
• Riser ESDV’s should be located to allow access for operation, maintenance and inspection.
• Risers are strictly prohibited under accommodation buildings with the single possible exception of existing installations and where the riser is protected with a Sub-Sea Isolation Valve (SSIV).
Pig trap • Oriented such as any failure of pig trap could not affect the integrity of the installation or of the nearby assets (e.g. temporary rig or bridged platform).
• Not oriented towards a main access way or a traffic path.
• Horizontal.
• Provide adequate space for lifting and handling facilities for maintenance.
A minimum headroom of 0.76 metre above grade or platform for adequate drainage and inspection under the pig traps.
Manifolds • Pay particular attention to the access to and the operation of valves (refer to Appendix C1.2).
• Adequate space for lifting and handling facilities for valves change-out shall be provided.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 58/64
C6. Flares and vents
Equipment Requirement for location
Flares and burn pits
• Refer to GS EP SAF 253 & GS EP SAF 262.
• In the case of several flares or burn pits operating in parallel within the same fire zone, distances indicated in Appendix A - Table A3, are given by default and shall in any case be subject to a particular radiation and dispersion calculation note. These calculations shall address the particular requirements relative to simultaneous operation (e.g. tip maintenance) set forth in the OPERATING PHILOSOPHY.
Vents • Should be grouped as far as it is practicable.
• Vents creating a Zone 1 hazardous area17 should release in one single point as far as possible from manned areas and from sources of ignition.
• In addition to dispersion calculation (flammable gas and toxic gas when applicable) cold vents shall also be calculated to fulfil radiation criteria as per GS EP SAF 253 & GS EP SAF 262.
Flare piping Refer to Section 5.3.3 of the main document & Appendix C1.1.
C7. Storage
Equipment Requirement for location Recommended distance
Storage tanks and vessels
Bullet vessels should be oriented such as in case of any explosion of the vessel the effects of the missile impacts of the ends of the vessel are minimized (for further details refer to GS EP SAF 341).
Trucks loading/unloading stations
• For flammable and combustible liquids, should be located near the plant gates to avoid truck traffic near process areas.
HC loading/ unloading stations
LPG loading/unloading stations18
• Should preferably be installed at the outer sides of the installation in a dedicated fire zone. The main roads to and from loading stations shall not cross the rest of the installation.
The main roads to and from loading stations shall not run parallel to the rest of the installation at a distance of less than 100 metres.
17 For specific requirement related to vents hazardous areas classification, refer to GS EP SAF 216. 18 Shall be considered as a main cause of hazard.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 59/64
Equipment Requirement for location Recommended distance
Metering units
• Accessible from any side for operation and maintenance.
• Preferably be positioned at or just above grade.
• No equipment and no pipe-rack allowed above metering units.
Minimum spacing between 2 branches: 1.2 metres.
C8. Safety equipment
Equipment Requirement for location Recommended distance
Fire-fighting equipment19
• As away as possible from equipment that could release a flammable gas un-ignited cloud.
• Preferably upwind the rest of the plant.
Fire monitors shall be 15 metres away from the edge of the fire zone they protect.
Life saving equipment
Refer to GS EP SAF 351.
PSVs and TSVs20
• Be readily accessible and fitted with all necessary access platforms and working areas for safe intervention21.
C9. Buildings
C9.1 Accommodation buildings and technical rooms Guidance about internal arrangement within living quarters and office building is provided in GS EP SAF 221.
Rules for the location of building depending upon their type and environment are provided in Section 5.5 of the main document. In addition and in the absence of special safety requirement, all building shall be spaced so as to provide clearance for access as per requirements set forth in Appendix C1.1.
C9.2 Process or utility buildings In the case of process or utility units being enclosed in buildings (e.g. to ensure sufficient protection against adverse weather conditions) the rules applicable to outdoor units remain applicable with the exception that minimum distances shall be considered from the edge of buildings instead of edge of units, in spite of the additional internal clearance between units and building walls.
19 For further details, refer to GS EP SAF 321. 20 For further details, refer to GS EP SAF 262. 21 PSV’s and TSV’s are likely to undergo frequent dismantling for calibration.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 60/64
Considering also that building require adequate ventilation, it shall be checked that ventilation air intakes and exhaust position remain compatible with the position of other units (either outdoor or enclosed) regarding hazardous area classification.
C10. Miscellaneous
C10.1 Air gap All safety equipment or process equipment having a safety function shall never be located in or under the air gap on an offshore installation.
The only exception to this requirement is for inlet and outlet ESDV’s that are located (by order of preference) as per Figure C1 - Offshore platforms ESDVs locations:
• Option 1: onto the drain deck just above the air gap (and below the cellar deck, this one being plated)
• Option 2: onto the cellar deck with adequate passive protection (PFP or separation wall)
• Option 3: within the air gap space. In that case, the design of ESDV’s and their associated instrumentation & piping (as well as their supports) shall take into consideration the maximum wave loads developed on each item of equipment.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix C
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 61/64
Cellar deck
Drain deck
Air Gap (1)
Centennial wave height (1)
Max surge height +
MHWS (1)
Separation wall
(1) Refer to GS EP ECI 001
LAT (1)
Option 1
Option 3
Option 2
Figure C1 - Offshore platforms ESDVs locations
C10.2 Cranes and lifting devices Refer to GS EP STR 002.
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix D
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 62/64
Appendix D – Bibliographic references
Professional Documents
Reference Title
GE GAP 2.5.2 Guideline on oil and chemical plant layout and spacing
CCPS Guidelines for facility siting and layout
Regulations
Date Object Modified date Object
10/01/1969 Arrêté du 10 janvier 1969 fixant les règles d'aménagement et d'exploitation des usines de traitement de pétrole brut, de ses dérivés et résidus
12/09/1973 Arrêté du 12 septembre 1973 relatif aux règles d'aménagement et d'exploitation des usines de traitements de pétrole brut, des ses dérivés et résidus
04/09/1967 Arrêté du 4 septembre 1967 relatif aux règles d'aménagement et d'exploitation des usines de traitements de pétrole brut, de ses dérivés et résidus
19/11/1975 Arrêté du 19 novembre 1975 relatif aux règles d'aménagement et d'exploitation des usines des traitements de pétrole brut, de ses dérivés et résidus
Date Object Modified date Object
19/11/1975 Arrêté du 19 novembre 1975 relatif aux règles d’aménagement et d’exploitation des dépôts d’hydrocarbures et des titulaires d’autorisations spéciales d’importation de produits pétroliers
09/11/1972 Arrêté du 9 novembre 1972 fixant les règles d’aménagement et d’exploitation des dépôts d’hydrocarbures liquides
28/04/2008 Arrêté du 28 avril 2008 portant modification de l’arrêté du 9 novembre 1972 relatif aux règles d’aménagement et d’exploitation des dépôts d’hydrocarbures liquides et de l’arrêté du 9 novembre 1972 relatif à l’aménagement et l’exploitation de dépôts d’hydrocarbures liquéfiés
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix D
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 63/64
Regulations
Date Object Modified date Object
09/09/1993 Arrêté du 9 septembre 1993 modifiant l'arrêté du 9 novembre 1989 relatif aux conditions d'éloignement auxquelles est subordonnée la délivrance des nouveaux réservoirs de gaz combustibles liquéfiés
02/06/2000 Arrêté du 2 juin 2000 modifiant l'arrêté du 9 novembre 1989 relatif aux conditions d'éloignement auxquelles est subordonné la délivrance des nouveaux réservoirs de gaz combustibles liquéfiés
30/10/2001 Arrêté du 30 octobre 2001 modifiant l'arrêté du 9 novembre 1989 relatif aux conditions d'éloignement auxquelles est subordonnée la délivrance des nouveaux réservoirs de gaz combustibles liquéfiés
05/06/2003 Arrêté du 5 juin 2003 modifiant l'arrêté du 9 novembre 1989 relatif aux conditions d'éloignement auxquelles est subordonnée la délivrance des nouveaux réservoirs de gaz combustibles liquéfiés
09/11/1989 Arrêté du 9 novembre 1989 relatif aux conditions d'éloignement auxquelles est subordonnée la délivrance des nouveaux réservoirs de gaz combustibles liquéfiés
02/01/2008 Arrêté du 2 janvier 2008 relatif aux stockages contenant plus de 50 tonnes de gaz inflammables liquéfiés relevant du régime de l'autorisation au titre de la rubrique n° 1412 de la nomenclature des installations classées à l'exception des stockages réfrigérés ou cryogéniques
Abroge et remplace l'arrêté du 9 novembre 1989 modifié (art. 16)
Exploration & Production
General Specification Date: 10/2009
GS EP SAF 021 Rev: 04
Appendix D
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 64/64
Regulations
Date Object Modified date Object
10/05/1993 Arrêté du 10 mai 1993 relatif au stockage de liquide inflammable sous pression
02/01/2008 Arrêté du 2 janvier 2008 relatif aux stockages contenant plus de 50 tonnes de gaz inflammables liquéfiés relevant du régime de l’autorisation au titre de la rubrique n° 1412 de la nomenclature des installations classées à l’exception des stockages réfrigérés ou cryogéniques
Abroge et remplace l’arrêté du 10 mai 1993 (art. 15)