group design project final presentation

Upload: julianrp

Post on 03-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Group Design Project Final Presentation

    1/43

    SMART WATERSMART POWERH2.0

    Group 3 Members:

    Ryan McCartney (Project Leader)

    Julian Phatarfod (Liaison Officer)

    Ahmad Al IdelbiMehdi Bedja

    Divya Bhanderi

    Clinton Chan

    Grace Lee

    Steve Moore

    Charalambos Spanos

    FinalPresentation

    Clients:

    Dr. Ivan Stoianov (Imperial College)

    Dr. James Kierstead (Imperial College)

    Mr. Laurie Reynolds (Aquamatix)

    Mr. Danny Ball (Bristol Water)

  • 7/28/2019 Group Design Project Final Presentation

    2/43

    Water Utility Companies

    WATER UTILITIES!

    Water

    Customers!Pump

    Scheduling

    StorageReservoir

    Maintaining a regulated service to customers

  • 7/28/2019 Group Design Project Final Presentation

    3/43

    Water Utility Companies

  • 7/28/2019 Group Design Project Final Presentation

    4/43

    Current State of the Art

    Large Electricity Consumers!Approx. 3% of the UKs usage!Up to 90% from pumping!Aim to minimise pumping costs!

    Water UtilityCompanies !

  • 7/28/2019 Group Design Project Final Presentation

    5/43

    Water Utilities and National Grid

  • 7/28/2019 Group Design Project Final Presentation

    6/43

    Water Utilities and National Grid

    !!

    !NATIONAL

    GRIDTariffs andContracts

    WATERUTILITIES

    Managing large consumers of electricity

  • 7/28/2019 Group Design Project Final Presentation

    7/43

    Current State of the Art

    Large Electricity Consumers!Approx. 3% of the UKs usage!Up to 90% from pumping!Aim to minimise pumping costs!

    Electricity Bought in Advance!Time-of-use (TOU) Tariff!Minimise exposure to fluctuations!Less cost-effective!

    Water UtilityCompanies !

  • 7/28/2019 Group Design Project Final Presentation

    8/43

    Current State of the Art

    Large Electricity Consumers!Approx. 3% of the UKs usage!Up to 90% from pumping!Aim to minimise pumping costs!

    Electricity Bought in Advance!Time-of-use (TOU) Tariff!Minimise exposure to fluctuations!Less cost-effective!

    Pump Schedule!Avoid consuming during peak periods !Avoid penalty charge times (triad)!

    Water UtilityCompanies !

  • 7/28/2019 Group Design Project Final Presentation

    9/43

    Current State of the Art

    Large Electricity Consumers!Approx. 3% of the UKs usage!Up to 90% from pumping!Aim to minimise pumping costs!

    Electricity Bought in Advance!Time-of-use (TOU) Tariff!Minimise exposure to fluctuations!Less cost-effective!

    Pump Schedule!Avoid consuming during peak periods !Avoid penalty charge times (triad)!

    Fixed Speed Pumps!Inefficient !Cannot manage fluctuations!

    Water UtilityCompanies !

  • 7/28/2019 Group Design Project Final Presentation

    10/43

    National Grid

    !!

    !

    !

    !

    LoadBalancing

    Consumers(Demand)

    Generators(Supply)

    NATIONAL GRID

    Maintaining a regulated service to customers

  • 7/28/2019 Group Design Project Final Presentation

    11/43

    Energy Systems in the Future

    EU Renewables Obligations

    UK Target increase to15% by 2020

    Wind Power

    Highest renewable generation source (currently 5.7%)

    Stochastic Behaviour

    Unpredictable and uncontrollable generation

  • 7/28/2019 Group Design Project Final Presentation

    12/43

    Project ObjectiveTo assess the techno-economic feasibility of optimising pumpschedulingto enable water utility companies to actively participatein load balancing within electricity distribution grids in order to

    facilitate the increasing generation from renewable sources.

  • 7/28/2019 Group Design Project Final Presentation

    13/43

    !

    NATIONALGRID

    WATERUTILITIES

    !

    ManagingLarge

    Consumers

    FEASIBILITYSTUDY

    DomesticConsumers!

    LoadBalancing

    Generation

    (Supply)Consumption

    (Demand)

    Storage?

    DomesticConsumers

    PumpScheduling

    (Optimisation)

    Non-RenewableEnergy

    RenewableEnergy

    Customers

    (Demand)

    Storage(Supply)

    !

    StorageReservoir

  • 7/28/2019 Group Design Project Final Presentation

    14/43

    Linear SystemDecoupling hydraulic model from optimisation process

    Single Matrix FormulationAvoidance of implicit equations

    Key AssumptionsNetwork segmentation to simplify the model

    Optimising Pump Schedule

  • 7/28/2019 Group Design Project Final Presentation

    15/43

    Optimising Pump Schedule

  • 7/28/2019 Group Design Project Final Presentation

    16/43

    Mass Balance Reservoir Pump

    [!]

    2!"2!

    [!!(!)]2!"2!

    ![!]

    2!!2!

    [!]2!!2!

    !!

    !

    .

    .

    .

    !!!

    !

    !

    !

    .

    .

    !!!

    =

    0

    .

    .

    .

    0

    !!

    !

    .

    .

    !!

    !

    !

    !!!

    .

    .

    .

    !!"

    !

    !

    !

    .

    .

    !"!

    0

    .

    .

    .

    0

    !

    .

    .

    !

    !

    !!!

    .

    .

    .

    !!"

    !

    !

    !

    .

    .

    !"!

    !!

    .

    .

    .

    !!

    !

    .

    .

    !

    !

    Upper Bound Lower Bound

    Constraints

  • 7/28/2019 Group Design Project Final Presentation

    17/43

    Hydraulics

    Flows&

    Pressures&&Tank&Levels&

  • 7/28/2019 Group Design Project Final Presentation

    18/43

    Affinity Laws

    Q = Flow

    N = Pump SpeedH = Total HeadP = Power

    Hydraulics

  • 7/28/2019 Group Design Project Final Presentation

    19/43

    !

    NATIONAL

    GRID

    LoadBalancing

    Generation(Supply)

    Consumption(Demand)

    Storage?

    DomesticConsumers

    Non-RenewableEnergy

    RenewableEnergy

    !

  • 7/28/2019 Group Design Project Final Presentation

    20/43

    Storage Issues

    UK installed pumped hydro capacity: 2800MW

    Equivalent to only 2.43% of the peak winter electricity demand

    Pumped Hydro Electrochemical

  • 7/28/2019 Group Design Project Final Presentation

    21/43

    0.00!

    20.00!

    40.00!

    60.00!

    80.00!

    100.00!

    120.00!

    0!

    5000!

    10000!

    15000!

    20000!

    25000!

    12:00 AM! 3:00 AM! 6:00 AM! 9:00 AM! 12:00 PM! 3:00 PM! 6:00 PM! 9:00 PM!

    EectySMkePce(MW

    PwGao(MW

    Settlement Period!

    Electricity Generation from different sources on

    02/03/2013!

    Coal!

    Electricity Spot Price!

    CCGT!

    Wind!

    Nuclear!

  • 7/28/2019 Group Design Project Final Presentation

    22/43

  • 7/28/2019 Group Design Project Final Presentation

    23/43

    Probability of Reaching Installed Capacity

  • 7/28/2019 Group Design Project Final Presentation

    24/43

    Electricity Spot Price Variability

  • 7/28/2019 Group Design Project Final Presentation

    25/43

    Low Renewables Penetration

  • 7/28/2019 Group Design Project Final Presentation

    26/43

    High Renewables Penetration

  • 7/28/2019 Group Design Project Final Presentation

    27/43

    Six different cases:

    Assessing impact of renewables

    Simulating emergency situations

    Case Studies

  • 7/28/2019 Group Design Project Final Presentation

    28/43

    Tank 1

    !! ! !! ! !! ! !!

    DemandNetwork

    Reservoir

    Pump

    Tank 2

    ! ! !! ! !! ! !!

    Pump

    DemandNetwork

    Case Studies

    Simplified Network for Optimisation

    Tank Demand Profiles

  • 7/28/2019 Group Design Project Final Presentation

    29/43

    Key Performance Indicators

    Results of Case Studies assessed on:

  • 7/28/2019 Group Design Project Final Presentation

    30/43

    Current state of pump optimisation

    Low renewables penetration

    Relies on avoiding peak tariff period

    Case Study I

    NullScenario

  • 7/28/2019 Group Design Project Final Presentation

    31/43

    Linear optimisation of pump schedule

    Low renewables penetration (5.7%)

    Spot market prices for real time price fluctuations

    Case Study II

  • 7/28/2019 Group Design Project Final Presentation

    32/43

    Linear optimisation of pump schedule

    High renewables penetration (15%)

    Spot market prices with additional volatility to model wind effects

    Case Study III

  • 7/28/2019 Group Design Project Final Presentation

    33/43

    Simulation of a pipe burst

    Low renewables penetration

    Burst lasts for two hours;

    modelled as a fourfold increase indemand at the industrial node

    Case Study IV

  • 7/28/2019 Group Design Project Final Presentation

    34/43

    Storm surge simulation: change of reservoir limits

    Low renewables penetration

    Surge not to pass above 50% of net capacity of tanks

    Case Study V

  • 7/28/2019 Group Design Project Final Presentation

    35/43

    Simulation of pump maintenance work

    Low renewables penetration

    Booster pump is forced offline for two hours

    Case Study VI

  • 7/28/2019 Group Design Project Final Presentation

    36/43

    Results Summary

    Case Study I II III IV V VI

    Cost

    []

    Carbon[kg]

    Efficiency[%]

    EnergyUsage

    [MWh]

    119.96 100.45 92.98 102.53 100.9 101.2

    477.55 441.62 397.73 466.81 447.02 450.66

    N/A 16.26 22.49 14.53 15.89 15.64

    0.871 0.805 0.725 0.851 0.815 0.822

  • 7/28/2019 Group Design Project Final Presentation

    37/43

    National Grid: Balancing Mechanism!

    Hours 240 mins

    BM Start Up STORDemand Management

    Fast Start

    Fast Reserve

    FCDM

    Frequency Response

    Real Time

    5 mins

    RESPONSETIME

    2 mins

  • 7/28/2019 Group Design Project Final Presentation

    38/43

    National Grid: Balancing Mechanism!

    Hours 240 mins

    BM Start Up STORDemand Management

    Fast Start

    Fast Reserve

    FCDM

    Frequency Response

    Real Time

    5 mins

    RESPONSETIME

    2 mins

  • 7/28/2019 Group Design Project Final Presentation

    39/43

    Balancing by Demand Reduction

  • 7/28/2019 Group Design Project Final Presentation

    40/43

    Risk Assessment!!

    !

    !

    !

    Very%

    High%

    !

    !!

    !!

    !!

    %

    High%

    ! !!!

    !!

    %Mediu

    m%

    !!

    !

    !

    !!

    %

    Low%

    ! !!

    !

    %

    !

    Low% Medium% High% Very%High%

    Impact'

    Probability

    '

    Lack!of!sufficient!

    water!pressure!!

    Increased!Spot!

    price!volatility!

    !

    Burst!pipes!due!to!

    pressure!surges!

    !

    Policy!reversal:

    Reduction!in!

    renewables!

    Model!error!

    !

  • 7/28/2019 Group Design Project Final Presentation

    41/43

    Sustainability

    Future Renewable Scenarios

    Making water utility companies compatible with future energy systems

    Carbon Optimisation

    Shifting focus from cost to carbon - potential multi objective function

    Pump Efficiency

    Improving pumps from fixed to variable speed

  • 7/28/2019 Group Design Project Final Presentation

    42/43

    Recommendations

    Optimise

    Implement pump schedule optimisation model

    Invest

    Improve efficiency of pumps with variable speed drives

    Balance

    Provide a load balancing service to the National Grid (STOR)

    SMART WATERH2 0

  • 7/28/2019 Group Design Project Final Presentation

    43/43

    SMART WATERSMART POWERH2.0

    Final

    Presentation

    Thank you for attending.

    Please feel free to ask any questions.

    Many thanks to Laurie Reynolds, Simon Bunn, Danny Ball

    and the support from our clients at Imperial College

    Visit our website at:

    www.h2point0.org

    Folllow us on Twitter:

    @SmartWaterGDP

    #GPDesignPS

    http://www.h2point0.org/http://www.h2point0.org/