    PROJECT PLAN

    Group Five Design

    Or de lAcadie British Side

    Document Revision #: 1.0

    Date of Issue: January 31, 2012

    Project Manager:Ryan MacLeod

  • 8/3/2019 Group 5 - Project Plan

    2/23

    Project Plan Or de lAcadie British Side

    Approval Signatures

    Approved by: Business Project Leader Approved by: IM/IT Project Leader

    Prepared by: Business Project Manager Prepared by: IM/IT Project Manager

    Reviewed by: Quality Assurance Manager

    Version 1.0 January 31, 2012 Page i

  • 8/3/2019 Group 5 - Project Plan

    3/23

    Project Plan Or de lAcadie British Side

    Table of Contents

    1. Project Overview.....................................................................................1

    1.1 Purpose, Scope, and Objectives............................................................................1

    1.2 Assumptions, Constraints and Risks......................................................................1

    1.3 Project Deliverables................................................................................................1

    1.4 Schedule and Budget Summary.............................................................................2

    1.5 Evolution of the Plan...............................................................................................2

    1.6 References............................................................................................................ .2

    1.7 Definitions and Acronyms.......................................................................................3

    2. Project Organization...............................................................................4

    2.1 External Interfaces..................................................................................................4

    2.2 Internal Structure....................................................................................................4

    2.3 Roles and Responsibilities.............................................................................. .......4

    3. Managerial Process Plans......................................................................5

    3.1 Start-up Plan.............................................................................................. ............5

    3.1.1 Estimates....................................................................................................................5

    3.1.2 Staffing.......................................................................................................................5

    3.1.3 Resource Acquisition..................................................................................................6

    3.1.4 Project Staff Training..................................................................................................7

    3.2 Work Plan...............................................................................................................7

    3.2.1 Work Breakdown Structure........................................................................................7

    3.2.2 Schedule Allocation....................................................................................................8

    3.2.3 Resource Allocation...................................................................................................9

    3.3 Project Tracking Plan................................................................................... ........10

    3.3.1 Requirements Management.....................................................................................10

    3.3.2 Schedule Control......................................................................................................10

    3.3.3 Quality Control..........................................................................................................10

    3.3.4 Reporting..................................................................................................................10

    3.3.5 Project Metrics..........................................................................................................10

    3.4 Risk Management Plan.................................................................................. ......11

    3.5 Project Closeout Plan...........................................................................................11

    4. Technical Process Plans.....................................................................12

    4.1 Process Model.....................................................................................................12

    4.2 Methods, Tools, and Techniques.........................................................................12

    4.3 Infrastructure.......................................................................................................12

    OrganizationGroup Five Design

    Title/SubjectOr de lAcadie British Side

    Number1.0

    Owner RM Approved by SP Date January 31, 2012 Version Page ii

  • 8/3/2019 Group 5 - Project Plan

    4/23

    Project Plan Or de lAcadie British Side

    4.4 Product Acceptance....................................................................................... .....12

    5. Supporting Process Plans.................................................................14

    5.1 Configuration Management........................................................................... ......14

    5.2 Verification and Validation...................................................................................14

    5.3 Documentation............................................................................................... .....14

    5.4 Quality Assurance.............................................................................................. .15

    5.5 Reviews and Audits.............................................................................................15

    5.6 Problem Resolution.............................................................................................15

    5.7 Process Improvement..........................................................................................16

    6. Additional Plans..................................................................................17

    7. Project Evolution.................................................................................18

    7.1 Project support and maintenance........................................................................18

    7.2 Follow-up projects............................................................................................ ...18

    7.1 Project Support and Maintenance...................................................................................17

    7.2 Follow-up Projects..........................................................................................................17

    OrganizationGroup Five Design

    Title/SubjectOr de lAcadie British Side

    Number1.0

    Owner RM Approved by SP Date January 31, 2012 Version Page iii

  • 8/3/2019 Group 5 - Project Plan

    5/23

    Project Plan Or de lAcadie British Side

    Document Change Control

    This section provides control for the development and distribution of revisions to theProject Charter up to the point of approval. The Project Charter does not change

    throughout the project life cycle, but rather is developed at the beginning of the project

    (immediately following project initiation approval, and in the earliest stages of project

    planning). The Project Charter provides an ongoing reference for all project stakeholders.The table below includes the revision number (defined within your Documentation Plan

    Outline), the date of update/issue, the author responsible for the changes, and a briefdescription of the context and/or scope of the changes in that revision.

    Revision Number Date of Issue Author(s) Brief Description of Change

    1.0 Jan. 31, 2012 RM First Edition

    OrganizationGroup Five Design

    Title/SubjectOr de lAcadie British Side

    Number1.0

    Owner RM Approved by SP Date January 31, 2012 Version Page iv

  • 8/3/2019 Group 5 - Project Plan

    6/23

    Project Plan Or de lAcadie British Side

    1. Project Overview

    This section of the IM/IT Project Management Plan provides an overview of thepurpose, scope and objectives of the project for which the Plan has been written, the

    project assumptions and constraints, a list of project deliverables, a summary of the

    project schedule and budget, and the plan for evolving the IM/IT ProjectManagement Plan.

    1.1 Purpose, Scope, and Objectives

    The British characters currently have minimal interaction within the game. Toenhance game play for all characters, this project looks to increase the game play for

    the British side characters by adding more interactions within the game world.

    This will be accomplished by attempting to incorporate NPCs (Non Player

    Characters) that will help in communication between British characters. As well as apuzzle system, that allows the players to translate French clues into English, which

    helps the British characters find treasure. There will be a limited number of words

    included in the translation system to make it less tedious for the players.

    Weaponry and fighting will be left out of any of the enhancements as we try to add

    to the British game play experience. The interaction between characters other thanBritish ones will be left for a different development team.

    Upon completion of the project it will be integrated into the pre-existing frameworkfor Or de lAcadie. The project will be stand alone from additional add-ons being

    developed by other teams. The success of the project will depend on the complete

    integration of at least one of the planned features. Failure to have a workingenhancement will be considered a failure of the project.

    1.2 Assumptions, Constraints and Risks

    A key assumption is that the British characters in the game have basic movements,

    such as walking around. Another assumption is that the current game is working and

    easily modifiable. The assumption is that the game is robust and flexible to change.

    A major constraint is the unfamiliarity with the openwonderland framework and with

    only two months to become familiar with it. Also, the projects process could belonger than what was initially planned, so this may cause delays or possibly

    incomplete parts. Also, working with the code that is already in place may cause

    problems if it is not intuitive and robust.

    1.3 Project Deliverables

    The project will deliver software written in Java in conjunction with the framework

    of openwonderland. The software will contain add-on enhancements for the Britishcharacters in the game. Hard copies of the following documents will be given to Dr.

    Reilly:

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 1

  • 8/3/2019 Group 5 - Project Plan

    7/23

    Project Plan Or de lAcadie British Side

    Project Charter

    SRS & Project Plan

    Design sketches and evaluation notes

    System Design & Detailed Design Docs

    Documented Code Base

    Test Plan

    Test Reports

    User Manual

    Deployment Guide

    Minutes of Project Meetings

    All reviews (both given and received)

    The list of items will be delivered no later than March 29, 2012 along with a working

    demo of the project.

    1.4 Schedule and Budget Summary

    No money will be spent over the duration of the project.

    1.5 Evolution of the Plan

    Each stage of the process will come with a review of the plan to ensure that it

    matches the current flow of the project. An unscheduled update will be done with theconsent and knowledge of the customer. If changes are made to the plan a new

    version number will be issued, the original version starts at 1.0 and will increase

    accordingly.

    1.6 References

    Project Charter Group Five Designs, Version 1.1, January 27 2012, Stu Penner,

    Group Five Design

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 2

    Milestone/Deliverable Planned Completion Date

    Project charter January 20, 2012

    Project plan, requirements document January 31, 2012

    Prototype 1: throwaway February 14, 2012

    Design documents February 28, 2012

    Prototype 2: implementation steel thread March 13, 2012

    Updated documents March 27, 2012

    User manual March 27, 2012

    Deployment guide March 27, 2012

    Demo March 29, 2012

  • 8/3/2019 Group 5 - Project Plan

    8/23

    Project Plan Or de lAcadie British Side

    1.7 Definitions and Acronyms

    openwonderland An open source virtual world. Written in Java, it comes with alarge support network of already created add-ons and features.

    IM/IT Information Management/Information Technology

    SRS Software Requirements Specification

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 3

  • 8/3/2019 Group 5 - Project Plan

    9/23

    Project Plan Or de lAcadie British Side

    2. Project Organization

    2.1 External Interfaces

    The customer, Dr. Derek Reilly, will be informed of any changes to the organizationthat occur over the course of the project. He will also contribute any suggestions for

    changes he feels are necessary for a successful completion of the project.

    2.2 Internal Structure

    Given that our team consists only of four members, there will be a small portion of

    separated tasks taken on by each team member. For example, the following tasks will

    be handled by all members of the team; documentation, development, qualityassurance, testing, and validation of the final product. Project management will be

    given to a specific individual.

    2.3 Roles and Responsibilities

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 4

    Role Responsibilities

    Project ManagerEnsures project is on track, interacts with sponsor, delegates tasks to

    software engineers

    Software Engineer Planning through all stages, software development, software testing

    Sponsor Provides guidance and direction to ensure project is on track.

    Sponsor

    Project Manager

    SoftwareEngineer

    SoftwareEngineer

    SoftwareEngineer

    Software

    Engineer

  • 8/3/2019 Group 5 - Project Plan

    10/23

    Project Plan Or de lAcadie British Side

    3. Managerial Process Plans

    This section of the IM/IT Project Management Plan specifies the projectmanagement processes for the project. This section defines the plans for project

    start-up, risk management, project work, project tracking and project close-out.

    3.1 Start-up Plan

    3.1.1 Estimates

    The estimate of time required for each stage is based on the time given to

    complete the stage and on the description of the stage itself. The confidencelevel ranges from low-high and is high for completed documents simple updates.

    The total estimated time scheduled for the project is: 45 person-days.

    The re-estimation of effort will be done on the project milestones. This will be

    done based on project description and from an estimate given by the customer,

    as they will expect a certain task completed in a specific time frame.

    3.1.2 Staffing

    The project will require four staffed individuals, including the project manager.

    The skill level of each individual is equivalent, since the framework being used

    is unfamiliar to all staff at the moment. The personnel are required to be on handready to take on tasks from January 2, 2012 to March 29, 2012.

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 5

    Milestone/DeliverableEstimated Time

    (person-days)Confidence Level Planned Completion Date

    Project charter 2 High January 20, 2012

    Project plan, requirements document 5 High January 31, 2012

    Prototype 1: throwaway 5 Low February 14, 2012

    Design documents 4 Low February 28, 2012

    Prototype 2: implementation steel

    thread8 Low March 13, 2012

    Updated documents 3 High March 27, 2012

    User manual 4 Medium March 27, 2012

    Deployment guide 4 Medium March 27, 2012

    Demo 10 Low March 29, 2012

  • 8/3/2019 Group 5 - Project Plan

    11/23

    Project Plan Or de lAcadie British Side

    3.1.3 Resource Acquisition

    All personnel are already acquired as part of the Group Five Design team. There

    are no other projects currently on the go that require attention from any of the

    staff.

    Any software or hardware resources are available free of cost courtesy of the

    Dalhousie Computer Science Department. Personal computers will also be usedfor work from the home or at any time an employee is out of the office.

    Facilities to work on the project have been supplied by the customer Dr. Reillyand in conjunction with Dalhousie University.

    Software and hardware will not be required until the coding stage of the project

    and will involve the following:

    Eclipse IDE, Java SDK

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 6

    Milestone/DeliverableNumber of Staff

    RequiredPlanned Completion Date

    Project charter 2 January 20, 2012

    Project plan, requirements document 3 January 31, 2012

    Prototype 1: throwaway 4 February 14, 2012

    Design documents 3 February 28, 2012

    Prototype 2: implementation steel

    thread4 March 13, 2012

    Updated documents 2 March 27, 2012

    User manual 2 March 27, 2012

    Deployment guide 3 March 27, 2012

    Demo 4 March 29, 2012

  • 8/3/2019 Group 5 - Project Plan

    12/23

    Project Plan Or de lAcadie British Side

    Openwonderland Server

    OSX, Linux or Windows Operating System

    Computer with 3D graphics card and a minimum of 128MB of videomemory

    3.1.4 Project Staff TrainingEach staff member on the project (all four) will be required to go through theopenwonderland tutorials provided at openwonderland.org. This will be all the

    training necessary to ensure that the team is up to speed. Any specific problems

    that arise after this initial training will be looked at on a case-by-case basis. Thisapproach is being implemented since it is a very large framework to learn and

    only specific parts are necessary for the success of the project.

    The project manager will specify any training necessary well ahead of the

    required date to ensure ample time for completion.

    3.2 Work Plan

    3.2.1 Work Breakdown Structure

    The project charter requires group input and approval by the customer. This

    section has been completed and will be updated as the project moves forward.The resources necessary will be small, one-person hour every two weeks or

    when required.

    The project plan and requirement documents will identify the requirements and

    plan for the entire project. This milestone requires three staff and to have the

    fourth on standby for editing and consultation. This portion will be completed

    within a week and will provide the customer with insight into our view of theproject. The project plan builds off of the project charter.

    Design documents will describe the details of the build structure for the project;

    along will the resources and frameworks needed. This document should validate

    the SRS. This is one of the last steps before the project moves into the codingphase and is a chance to analyze the design to prevent delays in the future. This

    section requires seventy-five percent of the teams man-power and will require

    four-person days.

    The first prototype (Throwaway) will build off the requirements to create anoverall design for the project. This prototype will attempt to meet the

    requirements and will be delivered to the client to critique. This stage will

    require the full team resources and will take approximately 5 person-days to

    complete. Upon completion and receiving the customer review, the SRS will beupdated to match the new set of requirements if necessary.

    Prototype (Steel Thread) is a direct implementation of the design documents.

    This prototype is a means to validate each of the design choices made in the

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 7

  • 8/3/2019 Group 5 - Project Plan

    13/23

    Project Plan Or de lAcadie British Side

    previous step. This stage will ideally show the customer that the design processwe choose is correct and that the team is ready to move forward to completion.

    Test cases will in drawn up in conjunction with this prototype.

    Final documentation, presentation, and demo are the final deliverables for the

    project. This section is used to gather all the appropriate documents and topresent the final product to the customer. The requirements need to be traced

    through each of the design stages to see where they are implemented in the finalproduct. This will require the longest amount of time to create and will require

    the full team working at near capacity to ensure that this section is completed ontime. This stage will be the final gauge of if the project was successful or not.

    3.2.2 Schedule Allocation

    Each milestone must be completed before the project is able to continue to the

    next stage.

    Milestone/Deliverable Planned Completion Date

    Project charter January 20, 2012

    Project plan, requirements document January 31, 2012

    Prototype 1: throwaway February 14, 2012

    Design documents February 28, 2012

    Prototype 2: implementation steel thread March 13, 2012

    Updated documents March 27, 2012

    User manual March 27, 2012

    Deployment guide March 27, 2012

    Demo March 29, 2012

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 8

  • 8/3/2019 Group 5 - Project Plan

    14/23

    Project Plan Or de lAcadie British Side

    3.2.3 Resource Allocation

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 9

    Milestone/Deliverable

    Number of

    Staff

    Required

    Computer

    ResourcesOther Requirements

    Planned Completion

    Date

    Project charter 2 Microsoft Word Approval by Customer January 20, 2012

    Project plan,

    requirements

    document

    3 Microsoft Word Approval by Customer January 31, 2012

    Prototype 1:

    throwaway4 Microsoft Word Approval by Customer February 14, 2012

    Design documents 2 Microsoft Word Approval by Customer February 28, 2012

    Prototype 2:

    implementation steel

    thread

    4

    Eclipse

    Open wonderland

    Microsoft Word

    Simulation Facilities

    Administrative Support

    Approval by Customer

    March 13, 2012

    Updated documents 1 Microsoft Word Approval by Customer March 27, 2012User manual 2 Microsoft Word Approval by Customer March 27, 2012

    Deployment guide 2 Microsoft Word Approval by Customer March 27, 2012

    Demo 4

    Eclipse

    Open wonderland

    Microsoft PP

    Microsoft Word

    Simulation Facilities

    Administrative Support

    Approval by Customer

    March 29, 2012

  • 8/3/2019 Group 5 - Project Plan

    15/23

    Project Plan Or de lAcadie British Side

    3.3 Project Tracking Plan

    3.3.1 Requirements Management

    Requirements will be managed through the SRS (Software Requirements

    Specification) document. The changes to the requirements can be traced throughthe version control implemented on each document.

    Assessing the impact of requirement changes will be done on a case-by-case

    basis during development. Risk management will be applied at the start of the

    project to help identify any potentially high-risk changes that could occur.

    3.3.2 Schedule Control

    The schedule will be controlled by the progress that has been completed at eachmilestone. If the schedule is off at a particular milestone the customer will becontacted and a meeting will be called to discuss how to move the project

    forward.

    The calendar system will be set up to mark the days to the next milestone

    depending on the stage of the project. This will be compared to the person-dayson the milestone completed and those still remaining against the amount of time

    left to complete that section.

    3.3.3 Quality Control

    Quality control will be measured by the completion of the project with zerocritical errors. Minor bugs will be allowed but anything that causes a system

    failure will be studied and corrected. Portions of the requirements and designwill be reviewed by a third party and by the customer to ensure the best

    implementation.

    3.3.4 Reporting

    E-mail and two weekly meetings with the customer will be used to communicate

    any changes that will occur to the project. Any project critical communicationmay take on both forms of communication to get the issue resolved. Otherwise

    communication will be kept to the weekly meetings if possible. The detail of

    these communications will depend on the size and scope of the issue.

    3.3.5 Project Metrics

    Weekly group meetings will be used to track progress within the group on each

    individual task. These will be stored in the weekly minutes with concerns andideas about the project. Milestones will be used as a baseline for tracking the

    progress of the overall completion of the project. Discussion with other groups

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 10

  • 8/3/2019 Group 5 - Project Plan

    16/23

    Project Plan Or de lAcadie British Side

    working on similar projects will be used to roughly analyze our own progressdata to see where we stand. The customer throughout the project will validate

    the metrics.

    3.4 Risk Management Plan

    Risk management will be done at the start of the project and before major

    milestones. It will involve identifying, analyzing, management planning, andreviewing the risk.

    Looking at the weak areas of the project will identify the risks and what is critical tomake the project successful. An analysis will give a detailed list of the weak areas

    and critical success elements. Management planning will look at the specific ways to

    minimize the impact if any of the defined risks occur. This process will be reviewedthroughout the project to ensure the progression of the project. Staff members will be

    responsible for alerting the group of any risk factors that may be occurring or have

    not mentioned.

    Each milestone might bring with it a different set of risks and upon completion thoserisks may no longer be relevant to the project. Each weekly meeting the group willrun through the risks, make additions and changes as necessary. Emergency issues

    can be brought to the attention of the project manager at any point.

    Some of the major risks of the project revolve around the technology and time

    constraints that have been put of the project. The fact that unfamiliar software is

    being used by each of the staff member increases the chance of an extendeddevelopment time. Since the project is on a strict timeline this could cause

    unsatisfactory deliverables. Since the complexity of the tasks is unknown there could

    bring a change to the scope of the project at a later date.

    3.5 Project Closeout Plan

    Upon completion of the project, hard copies of all communications and projectdocuments will be handed over to the customer, Dr. Reilly. They may also be stored

    electronically on each of the staff members personal computers for use in their

    portfolios. Each staff member is required to provide a post-mortem analysis of the

    project and their experiences. The staff members do not need to be reassigned to afuture project, as there is none currently in the works. The customer will do analysis

    of the completion of project objectives.

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 11

  • 8/3/2019 Group 5 - Project Plan

    17/23

    Project Plan Or de lAcadie British Side

    4. Technical Process Plans

    4.1 Process Model

    The customer will dictate information and work products whenever a section of theproject is due. This is outlined in the project timeline on the basis of milestones.

    Information within the group will be shared via e-mail and weekly meetings.

    The major milestones are project plan and requirements, design documents,

    prototyping, final product documents, and a live demonstration of completed British

    enhancements. These will all be in the form of deliverables to the customer who willapprove them based on their set of defined criteria for success.

    Minor reviews will be conducted weekly to ensure up to date information in

    documents. A major review will take place before starting to work on the final demo

    product and after completion of all milestones. The standard by which we reviewwill be based on the expectation and criteria set out by the customer.

    Project initiation occurred when Dr. Reilly awarded us a contract to develop asection of Or de lAcadie. This process will terminate upon successful completion of

    the project, or at the end of the timeline for the project, whichever comes first.

    4.2 Methods, Tools, and Techniques

    Development will be done using Java in the IDE Eclipse. This will be integrated with

    subversion software to track and document changes to the deliverable. The coding

    will be broken down to allow each member of the team the ability to work onsections most suited to their strengths. Group input through all steps will keep the

    ideas flowing so no one person gets stuck on a specific implementation.

    4.3 Infrastructure

    Eclipse, Java, and openwonderland are compatible with all operating systems and

    network setups. Testing will be done across OSX, Linux and Windows operatingsystems to ensure this assumption holds. Dalhousies computer science department is

    equipped with hardware that implements all of these operating systems. Dalhousie

    also has a free to access network that openwonderland can be tested on during the

    verification stages. Each staff member is responsible for there own working area ifthey do not wish to use that provided by Dalhousie University.

    4.4 Product Acceptance

    The customer will receive the final deliverables on March 29, 2012. They will bereviewed by the customer and critiqued on the following basis as defined by the

    customer in the project details:

    Completeness

    Consistency

    Correctness

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 12

  • 8/3/2019 Group 5 - Project Plan

    18/23

    Project Plan Or de lAcadie British Side

    Level of specificity

    Clarity

    Organization

    Format, spelling, grammar

    Use of diagrams

    These criteria will be used along with meeting of critical success factors outlined inthe project charter.

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 13

  • 8/3/2019 Group 5 - Project Plan

    19/23

    Project Plan Or de lAcadie British Side

    5. Supporting Process Plans

    5.1 Configuration Management

    Any changes to internal documentation will be met with a signature, time stamp, andcomments on why the changes were made. This requires approval of the customer.

    Progress will be tracked weekly at the groups meeting and will be built into theminutes for each meeting. Any changes required to the project will be communicated

    via e-mail or in person to the customer whenever the need arises.

    5.2 Verification and Validation

    Analyzing the finished product against the scope stated in the project character will

    be the verification for the project. Creating a more realized gameplay experience inthe opinion of the players will validate the process. Demoing the final product will

    be a part of the validation.

    Peer reviews will be done to ensure the requirements and project details are complete

    and outline all the parts necessary to have a successful project. The customer will bereviewing each milestone and giving the group feedback based on a numerical score.This along with comments will verify any choices we made and allow us to change

    them if necessary before reaching any critical points. There will be multiple

    implementations in the form of a throwaway model and a steel thread model. Eachdocument created will be reviewed as part of a milestone to ensure they are correct

    and up to date.

    Automated tools such as SVN, wiki, and Dropbox give version control and will give

    each group member, as well as the customer, access to the latest version.

    5.3 Documentation

    Documentation is will be generated as part of the milestones, reviews, and during the

    weekly meetings. Generating and reviewing the project documents is theresponsibility of all the members of the group. The reviews for a specific week will

    be designated at the beginning of that week and are to be completed by the same

    time the following week. The customer has the responsibility to give input into the

    project documentation and provide guidance in areas that are incorrect.

    The following table contains information about all the documents that will bepresented at the end of the project.

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 14

  • 8/3/2019 Group 5 - Project Plan

    20/23

    Project Plan Or de lAcadie British Side

    5.4 Quality Assurance

    The product must in its final form implement at least one of the features stated in thescope of the project. This implementation must have a workable demonstration that

    can be repeated on multiple occasions. During the course of the project the

    milestones must be completed by the date that they are due.

    The customer may decide to deem the project a success or a failure depending on his

    or her own criteria even if the project does not match the scope initially stated. Aneffort will be made to communicate with the customer to ensure quality is

    maintained. Constant review of the documentation and project plan and design will

    ensure the project is in the green zone each step of the way.

    5.5 Reviews and Audits

    Reviews will be performed after the deliverables have been handed in at eachmilestone stated in section 2.1 of the project charter. The customer can retain the

    right to review and make changes, as he or she seems fit during any point of the

    process.

    In house reviews will be done in respect to the documentation processes highlightedin section 4.3 of this document.

    5.6 Problem Resolution

    Emergency meetings can be called in the event of a major problem that needs to beresolved. These will be done in conjunction with communication to and from the

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 15

    Document Creation Date Review DatePerson(s)

    Responsible

    Project charter January 20, 2012 January 27, 2012 Stu Penner

    Project plan, requirements document January 27, 2012 February 7, 2012Ryan MacLeod

    Travis Russell

    Design Sketches and Evaluation

    NotesFebruary 28, 2012 TBD Stu Penner

    System Design & Detailed Design

    DocsFebruary 28, 2012 TBD TBD

    Documented Code Base March 27, 2012 March 29, 2012 All Group Members

    Test Plan March 12, 2012 March 29, 2012 All Group Members

    Test Reports March 27, 2012 March 29, 2012 TBD

    User Manual March 27, 2012 March 29, 2012 TBD

    Deployment Guide March 27, 2012 March 29, 2012 TBD

    Meeting Minutes March 27, 2012 March 29, 2012 Ryan MacLeod

    All Reviews TBD March 29, 2012 All Group Members

  • 8/3/2019 Group 5 - Project Plan

    21/23

    Project Plan Or de lAcadie British Side

    customer. The project manager will be in charge of contacting the customer andfinding an appropriate time for the team to meet.

    Problems will be tracked during the weekly meetings and stored in the minutes.

    These can be reviewed and analyzed at a later point and time. More effort should be

    placed on solving the problems rather than on the reporting of them.

    5.7 Process Improvement

    The project will be assessed at each milestone. This will allow the group to decide if

    the method in which they handled the last section was appropriate. Since the group issmall, implementation of process improvement will require little upfront planning.

    In the case of a problem, a processed improvement assessment will occur to

    minimize the chance of the same problem reoccurring during the project. In the case

    of uneven workload distribution the project manager must decide how to divide the

    work more evenly.

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 16

  • 8/3/2019 Group 5 - Project Plan

    22/23

    Project Plan Or de lAcadie British Side

    6. Additional Plans

    No additional plans are required to fulfil contractual obligations.

    OrganisationGroup Five Design

    Project PlanOr de lAcadie British Side

    Number1.0

    Owner - RM Approved by Date - January 31, 2012 Version Page 17

  • 8/3/2019 Group 5 - Project Plan

    23/23

    Project Plan Or de lAcadie British Side

    7. Project Evolution

    7.1 Project support and maintenance

    Openwonderland has an assortment of online resources that can be used totroubleshoot and debug any future issues with the software. This can be found at

    openwonderland.org. Java also has an online help center that can be found online at

    www.java.com.

    7.2 Follow-up projects

    There will be no follow-up projects that will use this project. The customer however

    may decide to overwrite this project with an implementation of his or her own.

    OrganisationG Fi D i

    Project PlanO d lA di B iti h Sid

    Number1 0

    http://www.java.com/http://www.java.com/