![Page 1: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/1.jpg)
GROUND IMPROVEMENT
BY
STONE COLUMNS
Prof. A.K.Choudhary
Professor & Ex Head
Department of Civil Engineering,
NIT, Jamshedpur
![Page 2: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/2.jpg)
INTRODUCTION
Soil improvement technique have been
developed rapidly in the past several yrs.
because on various occasions it is noted that
the local soil by nature, unable to bear the
proposed structure. Use of stone column is one
of such technique.
![Page 3: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/3.jpg)
HISTORICAL BACKGROUND
first stone column was used in ancient Egypt in 2600 BC.
In experimental approach, Hughes and Withers
(1974) carried out series of model tests in normally consolidated clay. The test results indicated that ultimate capacity of stone column was governed primarily by the maximum radial reaction of the soil against the bulging and the extend of vertical movement in the stone column was limited to about 4 times the diameter
![Page 4: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/4.jpg)
PRINCIPLE AND MECHANISM
Crushed stone is laterally compacted against
surrounding soil
Dense stone , aid in further transmitting
vibrational energy into the soil causing
densification
Stone column in situ soil form an integrated
system having low compressibility & high shear
strength.
Stone column act as vertical drains ,excess pore
water can rapidly dissipate.
![Page 5: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/5.jpg)
![Page 6: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/6.jpg)
TEST BEFORE STONE CLOUMN
Standard Penetration Testing (SPT)
Cone Penetrometer Testing (CPT)
Dilatometer Testing (DMT)
Load Testing
Shear Wave Velocity Profiling
![Page 7: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/7.jpg)
EQUIPMENTS & MATERIALS
crawler crane
vibrating probe
Rammer
Bailer and casing
Hooper
Crushed coarse aggregates.
Water
![Page 8: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/8.jpg)
![Page 9: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/9.jpg)
![Page 10: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/10.jpg)
CONSTRUCTION TECHNIQUE
TWO METHODS:-
Vibratory Technique using vibrofloat
• Wet top feed method
• Dry bottom feed method.
Rammed Stone Column Technique
![Page 11: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/11.jpg)
STEPS INVOLVED
![Page 12: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/12.jpg)
WET, TOP FEED METHOD (REPLACEMENT AND
DISPLACEMENT)
Jetting water is used to remove soft material, stabilize the probe hole, and ensure that the stone backfill reaches the tip of the vibrator.
This is the most commonly used and most cost-efficient of the deep vibratory methods.
However, handling of the spoil generated by the process may make this method more difficult to use on confined sites or in environmentally sensitive areas.
![Page 13: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/13.jpg)
WET TOP-FEED METHOD PROCESS
![Page 14: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/14.jpg)
DRY, BOTTOM FEED METHOD (DISPLACEMENT)
This technique uses the same vibrator probes as standard Vibro-Replacement Stone Columns, but with the addition of a hopper and supply tube to feed the stone backfill directly to the tip of the vibrator.
Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator remains in the ground during the construction process.
The elimination of flushing water in turn eliminates the generation of spoil, extending the range of sites that can be treated.
Treatment is possible up to a depth of 80 feet and is not inhibited by the presence of groundwater.
![Page 15: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/15.jpg)
DRY BOTTOM-FEED METHOD PROCESS
![Page 16: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/16.jpg)
2. RAMMED STONE COLUMN TECHNIQUE :-
In this technique the granular fill is introduced into a
pre-bored hole and compacted by a heavy rammer.
The hole is made by using normal bored piling rig
with winch bailer and casing.
Sometimes mixtures of stone aggregate and sand
generally in the proportion of 2:1 are used as
backfill material.
Gravel backfill of aggregate size 75 mm to 2 mm is
generally recommended.
![Page 17: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/17.jpg)
![Page 18: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/18.jpg)
SPECIFICATION
Diameter of stone column ranges from 0.5 to
0.75 m
Spacing depends upon(1.5 to 3m)
Characteristic Of untreated ground
soundness of stone column
settlement tolerence.
Weight of rammer varies from 2 – 3 tonnes
falling from height 1- 1.5m
![Page 19: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/19.jpg)
MONITORING
Ramming –
compaction should be done at 1.5-2.0m of
column
settlement should be < 17mm for 10
blows,each imparting 20j
![Page 20: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/20.jpg)
INSTALLATION
![Page 21: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/21.jpg)
BEHAVIOUR OF STONE COLUMN
![Page 22: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/22.jpg)
CRITICAL LENGTH OF STONE COLUMN
qu = NΦ ( σr +4Cu)
Where
qu = ultimate strength
N Φ =tan2(θ) =tan2(45 +Φ/2)
σr = effective radial stress.
K =effective earth pressure coefficient.
= effective vertical stress generally taken 4times the dia. Of stone columns.
C u = undrained cohension of immediate surrounding soil.
![Page 23: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/23.jpg)
REPRESENTATION OF SETLLEMENT
REDUCTION:
![Page 24: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/24.jpg)
BENEFITS:
Increases in bearing capacity
Increase in shear strength
Reduction in foundation settlement.
Mitigation of liquifaction.
Cost and time savings over other conventional
systems
It can be applied close to existing structure.
![Page 25: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/25.jpg)
APPLICATIONS
To improve soils prior to construction of foundations and slabs for commercial, industrial and residential buildings.
To reduce settlement in areas of landfill.
To reduce the risk of liquefaction under roadways,
airport runways, embankments, bridges and tunnels.
As an alternative support system to deep
foundations (piling).
![Page 26: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/26.jpg)
PROBLEMS ENCOUNTERED:-
If the soil is cohesive , the disturbance reduces
the strength of the surrounding soil, resulting in
no densification due to formation of cavity.
Sensitive clays do not adequately regain shear
strength, due to high sensitivity after stone
column.
![Page 27: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/27.jpg)
CASE STUDY
Vibro Stone Columns to support high reinforced soil walls for a highway project
![Page 28: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/28.jpg)
![Page 29: GROUND IMPROVEMENT BY STONE COLUMNSnitjsr.ac.in/course_assignment/6_ Strengthening by Stone Column.pdf · Bottom Feed Vibro-Replacement is a completely dry operation where the vibrator](https://reader033.vdocuments.us/reader033/viewer/2022050522/5fa5a6a09530cf26ac0a2f6d/html5/thumbnails/29.jpg)
THANK YOU!!!!!!!