griha good site practices manual 3

87
GRIHA Good Site Practices Manual Guide to adopting construction practices during construction for compliance with GRIHA Ministry of New and Renewable Energy, Government of India

Upload: abhishektheone

Post on 30-Apr-2017

227 views

Category:

Documents


6 download

TRANSCRIPT

G R I H A

G o o d S i t e P r a c t i c e s M a n u a l

G u i d e t o a d o p t i n g c o n s t r u c t i o n p r a c t i c e s d u r i n g

c o n s t r u c t i o n f o r c o m p l i a n c e w i t h G R I H A

Ministry of New and Renewable Energy, Government of India

GRIHA as a green building rating system examines

buildings on various parameters in order to evaluate

their “Green-ness” and appraise the projects

accordingly. GRIHA recommends certain practices to

be followed on site during construction in order to

reduce the overall environmental impact of

construction. These practices need to be adopted and

followed on site from the beginning till the end of

construction. Some of these represent mandatory

conditions of GRIHA. Therefore, compliance with them

becomes necessary in order to comply with GRIHA.

This short manual has been created to share some of

the images from various GRIHA registered projects

which demonstrate good as well as bad practices.

The various GRIHA criteria which need to be addressed

during construction are as follows

Criterion 2

Preserve and protect landscape during

construction/compensatory depository forestation.

Criterion 3

Soil conservation (post construction)

Criterion 8

Provide minimum level of sanitation/safety facilities for

construction workers

Criterion 9

Reduce air pollution during construction

Criterion 12

Efficient water use during construction

Criterion 22

Reduction in waste during construction

Criterion 2: Preserve and protect landscape during

construction/compensatory depository forestation.

• Do not excavate during the rainy season. A site in its

natural form is stable and covered with natural wild

vegetation, shrubs etc. which hold on to the soil.

Digging on site loosens the soil. If the digging happens

during rains, the rainwater will lead to soil erosion.

Hence it is recommended to avoid excavation during

rains.

• Stage construction on site. Disturb only that part of the

site where construction is supposed to happen

immediately. This ensures that the entire site is not

disturbed at one go and left. Staging construction also

helps in better site management since small areas need

to be managed at any given time.

• Provide for soil erosion channels on site. During

construction flowing water will try to erode soil as it

flows through the site. Erosion channels help

channel the flowing water effectively through the site

in a manner which minimizes the erosion and also

limits the spread of flowing water over the site.

• Water flowing across the site has the potential to

erode and carry soil off the site. In order to prevent

this, soil erosion channels should be coupled with

sedimentation tanks. Water flowing across the site

can be allowed to collect in a sedimentation tank

where it can be made to stand for a day. The mud

will settle at the bottom and the clearer water can be

either reused on site or discharged from site.

• Protect trees on site. In order to preserve a tree, one

must identify the drip-line around the tree and

provide a protective barricading around the tree so

that the construction activities do not damage the

tree in any manner.

Bad Examples

Figure 1

No erosion

control

measures

taken, site

prone to soil

erosion

Figure 2

No barricading provided around trees to protect them during

construction

Figure 3

Top soil and sub-soil mixed together and dumped on site

Good Examples

Figure 4

Staging on site, only part of the site has been disturbed,

remaining has been barricaded

Figure 5

Natural drains

on site can be

used for soil

erosion control

Figure 6

Mulching to be

done on stored top

soil for its

preservation

Figure 7

Staging carried

out on site,

green geotextile

fabric boundary

divides the

disturbed part

of site from the

undisturbed

Figure 8

Soil erosion control around stored top soil with drains lined with

aggregate to control soil erosion

Figure 9

Soil erosion

control around

stored top soil

with drains

lined with

aggregate to

control soil

erosion

Figure 10

Sedimentation tank prepared with find and coarse aggregate lining for

water percolation

Figure 11

Sedimentation tank lined with bricks to help separate soil from water and soft

base of sedimentation tank to allow for water percolation. Notice the

segregation between the disturbed and undisturbed areas on site

Figure 12

Tree

preservation

done, area

around tree

barricaded

Figure 13

Tree preservation done, area around tree barricaded

Criterion 3: Soil conservation (post construction)

• Store the top soil safely on site. Stabilize the soil so that

it does not get eroded. This can be done through various

strategies like mulching, creating a sturdy small

boundary around the stored top soil etc.

• Strategies like temporary grassing; planting shrubs etc.

can be done on the stored top soil. This is to ensure that

the stored top soil maintains its fertility and can be

effectively reused post construction for landscape.

Bad Examples

Figure 15

No segregation between top soil and sub-surface soil, soil

stabilization measures not adequate

Figure 16

No segregation between top soil and sub-surface soil, soil

stabilization measures not adequate

Good Examples

Figure 16

Top soil stored and stacked properly. Tree saplings planted to

maintain fertility as well as to stabilize the soil

Figure 17

Top soil stored and stacked properly. Temporary grassing carried

out to maintain fertility as well as to stabilize the soil

Figure 18

Top soil stored and stacked properly. Tree saplings planted to

maintain fertility. Cement bags filled with loose earth used to

stabilize the stored top soil

Figure 19

Top soil stored and stacked properly. Tree saplings planted to

maintain fertility and to stabilize the top soil

Figure 20

Top soil stored and stacked properly. Tree saplings planted to

maintain fertility and to stabilize the top soil

Criterion 8: Provide minimum level of

sanitation/safety facilities for construction workers

• Provide sufficient safety equipment to construction

workers. Minimum requirement is a hard hat, safety

boots and high-visibility jacket for all.

• Additionally, provide all necessary safety equipment as

specified in the National Building Code 2005 like

safety nets if working at heights, safety harness,

gloves and goggles for welding etc.

• Provide clean drinking water to all construction

workers.

• Provide clean and hygienic accommodation to all

construction workers. The accommodation should

adhere to the sample as described in the CPWD

manual. The colony should be clean; the bathing

areas should be covered. The accommodation

should have ventilation and some daylight.

• The colony should have trash bins for the families to

use, clean drinking water and cooking areas such

that smoke from cooking does not harm.

• Provide for clean and hygienic toilets for all

construction workers. The toilets for both males and

females should be sufficient in number.

Bad Examples

Figure 21

No labour safety on site, construction workers working on site

without any safety gear

Figure 22

Dysfunctional toilet for an entire colony of construction

workers, insufficient in hygiene levels as well as number

Figure 23

The accommodation for construction workers not satisfactory,

alleyways not maintained properly and accommodation lacks

access to daylight as well as ventilation

Figure 24

Unhygienic conditions in which the families of workers have to

live. No access to clean bathing facilities or washing areas,

unmaintained patches like this can lead to spread of diseases

Figure 25

Child labour on site, not a GRIHA recommended practice

Good Examples

Figure 26

All construction workers on site

have been provided with safety

gear like helmets, high-visibility

jackets and safety boots,

workers working on upper

levels have safety harnesses

and nets. The tank in the front

stored drinking water.

Figure 27

Even on smaller sites, workers with all safety gear

Figure 27

Workers working with stones or other such activities which involve a lot

of dust, are to be given face masks as depicted here

Figure 28

All workers provided with safety helmets and high-visibility jackets

Figure 29

Safety nets provided at regular intervals on the buildings to prevent any

mishap

Figure 30

Workers should

be provided

with clean

drinking water

Figure 31

Workers should

be provided

with clean

drinking water

Figure 32

The toilets to be provided to the construction workers should be clean

and hygienic. These should be cleaned regularly

Figure 33

The toilets should be constructed properly in case of large workforce

with adequate sewage management systems

Figure 34

And even in case of smaller sites and temporary toilets, toilets should

be maintained properly and clean

Figure 35

Mobile toilets can be maintained on site for workers. They must be

cleaned regularly.

Figure 36

The accommodation facility for workers should be clean and preferably

pucca

Figure 37

The accommodation facility for workers should be clean and preferably

pucca. Notice the clean floor and windows for ventilation and light.

Figure 38

The

accommod

ation facility

for workers

should be

clean and

preferably

pucca.

Criterion 9: Reduce air pollution during

construction

• Provide at least a 3 meter high barricading all

around the site or around the area where immediate

construction is happening.

• Sprinkle water on dust roads inside the site. This is

to ensure that the dust does not become air-borne.

• Minimize the distance traveled by vehicles inside the

site. This will ensure that vehicles cause disturbance

over the least possible area on site.

• Provide for wheel washing for vehicles exiting the

site. Alternatively, provide a water trough at the

entrance/exit of the site to ensure that all vehicles

pass through it as they go.

• Ensure that all loose sand etc. and other fine

construction material on site is covered.

• Ensure that Diesel gensets on site do not throw

smoke on to the construction workers. A certain

stack height should be maintained.

Bad Examples

Figure 39

Sand stored on site without any covering and will lead to dust. The site

has no barricading and dust from site will affect the workers on site as

well people living in the surrounding villages

Figure 40

Sand stored on site without any covering and will lead to dust.

Figure 41

DG genset on site without any chimney for the exhaust. This will only

throw smoke on the workers and site professionals working on site,

leading to respiratory problems.

Good Examples

Figure 42

A 3-metre high barricading should be installed all round the site to

curtail air pollution

Figure 43

The barricade should be capable of stopping dust transfer. Even

recycled materials can be used to made the barricade like the waste

cement bags being used in this case.

Figure 44

The barricade should be continuous around the site/construction zone.

Figure 45

The loose dirt

tracks on the site

can be watered to

prevent dust

Figure 46

The loose dirt tracks on the site can be watered to prevent dust

Figure 47

Water trough created at the site entrance for wheel washing of all

vehicles entering and exiting the site. This helps in cleaning the wheels

and remove any mud from leaving the site

Figure 48

Water trough created at the site entrance for wheel washing of all

vehicles entering and exiting the site. This helps in cleaning the wheels

and remove any mud from leaving the site

Figure 49

If possible, certain tracks on site commonly used by heavy vehicles can

be covered made hard to prevent dust pollution due to vehicle

movement

Figure 50

Loose earth and/or sand stored on site should be covered to prevent

dust pollution

Criterion 12: Efficient water use during

construction

• Use of strategies like ponding for curing of slabs and

use of jute bags for curing columns and beams help

in reducing the amount of potable water needed.

• Standing water from sedimentation tanks can be

used for cleaning construction equipment or for the

last stages of curing.

• Chemical admixtures can be used for quick drying to

ensure that concrete curing requires lesser amount

of water.

Good Examples

Figure 51

Jute bags being used on plinth beams for curing in order to save the

amount of water required for curing

Figure 52

Jute bags being used on columns for curing in order to save the

amount of water required for curing

Figure 53

Jute bags being used on slabs for curing, towards the last stages of

curing, in order to save the amount of water required for curing

Criterion 22: Reduction in waste during

construction

• Segregate construction waste on site. The inert

wastes like sample concrete testing blocks, waste

steel scrap, waste wood, broken bricks etc. should

be stored separately from chemical wastes like

shuttering oil, paints, adhesives, oils etc.

• Construction waste should be either reused on site

or should be disposed off safely to recyclers/scrap

dealers.

• Waste bins should be provided on site for managing

the waste thrown by construction workers.

• The project should ensure that construction waste is

managed well on site.

• Training should be given to construction workers so

that they use trash bins on site and do not throw

waste all over the site.

Bad Examples

Figure 54

Construction

waste not

managed

properly on site.

All waste

material mixed

up on site, no

segregation of

waste

Figure 55

Material stored on site, especially chemicals, should be away from

drinking water facilities

Figure 56

Chemical waste being leached onto the site

Good Examples

Figure 57

All construction material on site well managed and stored in

designated areas.

Figure 58

Segregation between hazardous waste (stored in the bin) and inert

waste (stored next to the barricading).

Figure 59

Different kinds of metal scrap stored separately and barricaded to

demarcate waste from fresh metal bars

Figure 60

Different bins created for storage of inert and hazardous waste

For more information:

Email: [email protected]

Or

Visit: www.grihaindia.org