GreaterLosAngelesCountyRegion Attachment4
WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐1
GreaterLosAngelesCountyRegionIRWMImplementationGrantProposal
WorkSummaryAttachment4consistsofthefollowingitems:
Work Summary.Attachment 4 contains information regarding the tasks that have been and will be performed for eachprojectconstitutingtheproposal.
ThisWorkSummary containsbrief summariesof theanticipated tasksnecessary tocompleteeachproject in theproposal.Eachprojectworksummaryisorganizedbythefourbudgetcategories,asapplicable:(a)DirectProjectAdministration,(b)Land Purchase/Easement, (c) Planning/Design/Engineering/Environmental Documentation, and (d)Construction/Implementation.Eachprojectworksummaryalsoidentifiesdeliverablesforeachtaskandthecurrentstatusofeach task. The Work Summary tasks are also consistent with the major tasks and sub‐tasks identified in the Budget(Attachment5)andSchedule(Attachment6)ofthisproposal.
LosAngeles‐BurbankGroundwaterSystemInterconnectionProjectTheLosAngeles‐BurbankGroundwaterSystemInterconnectionProject(Project)WorkSummaryTablecontainsdescriptivesummariesofthetasksnecessarytocompletetheProject,discussesthedeliverablesthatwillbeprovided,anddiscussesthecurrentstatusoftheProject,includingworkalreadycompleted.Task DescriptionofWorkCompleted,InProgress,orToBe
CompletedforTask(listedas%Complete)Deliverables Status
Category(a):DirectProjectAdministrationTask1:Administration
Administrationofgrantfundingapplication. (0%)PrepareandfinalizeaMOUbetweenCitiesofLosAngelesandBurbankforwaterexchangeandconstruction.(25%)HavemonthlymeetingswithBWPtodiscussProjectprogress.Grantapplicationpreparationbyconsultant.(85%)
Invoicesforreimbursement,MOUbetweenLAandBurbank,andcompletionofgrantapplicationandotherdocumentsasnecessary.
Inprogress
Task2:LaborComplianceProgram
TheCityofLosAngeleshasaLCPinplace. (100%)
LCPdocuments Completed
Task3:Reporting Submitreportingdocumentsasrequiredforgrantfunding. (0%) QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/EasementTask4:LandAcquisition
NolandacquisitionisrequiredforthisProject. Notapplicable.
Notapplicable Notapplicable
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
IterativeHydraulicModelingwillassess that the proposedinterconnectionisfeasibleandwillstillalloweachagencytoprovidewateratacceptablepressurestoneighboringserviceconnections.ThePressureDataRecordingswillbeusedasinputsforhydraulicmodels.(50%)
HydraulicModelsforeachdistributionsystem,andpressuredatarecords
Inprogress
Task6:FinalDesign
Completionofprojectplansandspecifications forthe30%,60%,90%,and100%design.(0%)UpdateProjectConstructionSchedule(0%)
30%,60%,90%,and100%DesignPlansConstructionSchedule
Notyetbegun
4Attachment
GreaterLosAngelesCountyRegion Attachment4
LosAngeles‐BurbankGroundwaterSystemInterconnectProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐2
Task DescriptionofWorkCompleted,InProgress,orToBeCompletedforTask(listedas%Complete)
Deliverables Status
Task7:EnvironmentalDocumentation
ProjectiscategoricallyexemptfromCEQA. (0%)
CEQANoticeofExemption
Notyetbegun
Task8:Permitting
Obtainallnecessarypermits.Allpermitsarependingandwillbeobtainedpriortoconstruction.(0%)
LABOEU‐Permitforexcavation,LABOEPeakHourExemptionTrafficVariancePermit,LACDPHNewWaterSourcePermit,LABSSStreetServicesPermit,LADOTApprovedTrafficControlPlan
Notyetbegun
Category(d):Construction/ImplementationTask9:ConstructionContracting
Constructionwillbeperformedbyin‐houseresources. (0%) Connectiondrawings(pipe,meters,andvalves)
Notyetbegun
Task10:Construction
Subtask10.1:MobilizationandSitePreparation
Procurematerialsandequipment, mobilizetosite,andimplementtrafficcontrol.(0%)
Materialdeliverytickets
Not yetbegun
Subtask10.2:ProjectConstruction
Projectconstructionincludesgroundexcavation;pipe,valve,andmeterinstallation;andrestorationoftheground.(0%)
Inspectionreports,surveyconstructionmethodology,designdrawings,andprojectcompletioncertificate
Notyetbegun
Subtask10.3:PerformanceTestingandDemobilization
Performancetestingincludesmeteringvolumes,measuringwaterflow,andrecordingpressurereadings.AfinalwalkthroughwillbeconductedofthesiteforProjectacceptance.AmonitoringplanwillbedevelopedfortheProject.(0%)
Pressuretestresults,disinfectionverificationlabresults,andProjectPerformanceMonitoringPlan
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
Nomitigationorenhancement is required forthisProject. Notapplicable Notapplicable
Task12:ConstructionAdministration
ConstructionManagementtaskswillbehandledbyLADWPandBWP.(0%)
Informationsubmittals Inspectionreports Submittals As‐builtdrawings
Notyetbegun
Notes:BWP–BurbankWaterandPower LCP–LaborComplianceProgramCEQA–CaliforniaEnvironmentalQualityAct MOU–MemorandumofUnderstandingLABOE–LosAngelesBureauofEngineering LABSS–LosAngelesBureauofStreetServicesLACDPH–LosAngelesCountyDepartmentofPublicHealth LACFCD–LosAngelesCountyFloodControlDistrictLADOT–LosAngelesDepartmentofTransportation LADWP–LosAngelesDepartmentofWaterandPowerEIR–EnvironmentalImpactReport NEPA‐NationalEnvironmentalPolicyAct
GreaterLosAngelesCountyRegion Attachment4
MissionWellsImprovementProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐3
MissionWellsImprovementProjectThe Mission Wells Improvement Project (Project) Work Summary Table contains descriptive summaries of the tasksnecessary to complete theProject,discusses thedeliverables thatwill beprovided, anddiscusses the current statusof theProject,includingpermittingactivities.Task DescriptionofWorkCompleted,In
Progress,orToBeCompletedforTask(listedas%Complete)
Deliverables Status
Category(a):DirectProjectAdministrationTask1:Administration EnterintoMOUwithLACFCD(80%)
PossibleMOUwithMetropolitanWaterDistrict(MWD)(0%)
Grantapplicationpreparationbyconsultant(85%)
Administrationofgrantandassociatedreportingrequirements(0%)
MOUbetweenLADWPandLACFCD,PossibleMOUwithMWD,Completegrantapplicationandotherdocumentsasnecessary,PreparationofInvoices
Inprogress
Task2:LaborComplianceProgram
TheCityofLosAngeleshasaLCP inplace.(100%)
CityofLosAngelesLCP Completed
Task3:Reporting Submitreportingdocumentsasrequiredforgrantfunding.(0%)
QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/EasementTask4:LandAcquisition
Landpurchase/easementisnotrequiredfortheproductionandmonitoringwellsandcollectorline.Theproductionwells,collectorline,andpumpstationupgradewillbebuiltinLADWPproperty.Uptofivemonitoringwellswillbebuiltinthepublicright‐of‐wayanddonotrequirelandpurchase/easement.
Notapplicable Notapplicable
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
FinalScopeofWorkDocumentforMissionWellsImprovementProject(100%)
UpperLosAngelesRiverArea(ULARA)SylmarBasinSafeYield(100%)
FinalPlanning(80%)
ScopeofWork
TechnicalStudy–preparedbyULARAfortheSylmarBasin
UpdateProjectscheduleandbudgetandcoordinationtoinitiateconstruction.
Inprogress
Task6:FinalDesign MonitoringWellsSpecifications(100%)
ProductionWellsSpecifications(95%)
CollectorLineDesign(100%)
MonitoringWellsSpecifications,ProductionWellsSpecifications,CollectorLineDesign
Inprogress
Task7:EnvironmentalDocumentation
FileNoticeofExemption‐ FiledonMay9,2014(100%)
NoticeofExemption Completed
Task8:Permitting ThecollectorlinewillbeconstructedinLADWPpropertyandpermitsarenotrequired.
ProductionwellswillbeconstructedinLADWPpropertyandpermitswillbeobtainedpriortoconstruction(90%).
Allpermitsforthefirstmonitoringwellhavebeenobtained.Permitsforthe
LACountyPublicHealthWellDrillingPermits;LADOTTrafficControlPlans,LABOEExcavationPermits,LosAngelesPoliceDepartment(LAPD)NoiseVariance,LABSSPermits,NationalPollutantDischargeEliminationSystem(NPDES)Permits,and
Inprogress
GreaterLosAngelesCountyRegion Attachment4
MissionWellsImprovementProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐4
Task DescriptionofWorkCompleted,InProgress,orToBeCompletedforTask(listedas%Complete)
Deliverables Status
remainingmonitoringwells(2‐5)willbeobtainedifmonitoringwellsareinstalled,dependingonthefieldfindingsfromthefirstmonitoringwellinstallation(100%).
IndustrialWasteDischargePermits
Category(d):Construction/ImplementationTask9:ConstructionContracting
Monitoringwellswillbeinstalledunderanexistingcontractviaachangeorder.(100%)
Productionwellswillbeinstalledunderanexistingcontractviaanamendment.(50%)Kickoffmeetingwithexistingcontractor(100%)
TheinstallationofthecollectorlineandpumpstationupgradewillbeperformedbyLADWPin‐housecrewsandthereforenoconstructioncontractingisnecessary.
Changeorderapproval
Contractamendment
KickoffMeetingnotes
Inprogress
Task10:Construction Subtask10.1:MobilizationandSitePreparation
Procureandpreparematerials,equipmentandsite,contractormobilizestotheworksite,andimplementssiteandtrafficcontrols(10%)
Trafficcontrolplansandthefollowingsubmittals–schedule,drillingplan,welldevelopmentandmaterialslist
Inprogress
Subtask10.2:ProjectConstruction
Projectconstructionincludesdrilling,construction,anddevelopmentofmonitoringandproductionwells(0%)
Projectconstructionalsoincludesinstallationofproductionwellpumps,pumpstationupgrade,andinstallationofacollectorlinetoconnecttothedistributionsystem(0%)
Testing
Sitephotos
Inspectionreports
Notyetbegun
Subtask10.3:PerformanceTestingandDemobilization
Conductwaterqualitytesting,productionwelldevelopmenttesting,wellpumptesting,samplingpumptestingandverification,instrumentationtestingandcalibration,siterestoration,andimplementMonitoringPlan(0%)
Labresults,calibrationcertificates,testverificationsubmittals,wellcompletionreportandProjectPerformanceMonitoringPlan
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
Nomitigationorenhancement actionsarerequiredforthisProject.Notapplicable.
Notapplicable Notapplicable
Task12:ConstructionAdministration
ConstructionmanagementtaskswillbecompletedbyLADWP.LADWPiscollaboratingwithMWDonapossiblepartnership(0%)
Submittals‐ NoticetoProceed,ProjectCloseoutMemo,Projectmeetingswithcontractor
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
ManhattanWellsImprovementProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐5
ManhattanWellsImprovementProjectThe Manhattan Wells Improvement Project (Project) Work Summary Table contains descriptive summaries of the tasksnecessary to complete theProject,discusses thedeliverables thatwill beprovided, anddiscusses the current statusof theProject,includingworkalreadycompleted.
Task DescriptionofWorkCompleted,InProgressortobeCompletedforTask(listedas%Complete)
Deliverables Status
Category(a):DirectProjectAdministration
Task1:Administration EnterintoMOUwithWaterReplenishmentDistrict(WRD)forcontractadministration(100%)
EnterintoMOUwithLACFCDforgrantconsultantwork(80%)
GrantApplicationPreparationbyConsultant(85%)ConductprogressmeetingswithWRD(5%)
Administrationofgrantfundingapplication(0%)
MOUbetweenLADWPandWRD,MOUbetweenLADWPandLACFCD,Completegrantapplicationandotherdocumentsasnecessary,Meetingminutes,andinvoicesforreimbursement
Inprogress
Task2:LaborComplianceProgram
TheCityofLosAngeleshasaLCP inplaceandwillbeimplementedduringconstruction(100%)
LCP documents Completed
Task3:Reporting Submitreportingdocumentsasrequiredforgrantfunding(0%)
QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/Easement
Task4:LandAcquisition NolandacquisitionisnecessaryforthisProject. Notapplicable Notapplicable
Category(c):Planning/Design/Engineering/EnvironmentalDocumentation
Task5:AssessmentandEvaluation
FinalScopeofWorkDocumentforManhattanWellsImprovementProject(100%)
ScopeofWork Completed
Task6:FinalDesign Completionofprojectplansandspecificationsfor:
Wells(100%) CollectorLine/WellConnections(90%) Electrical/SupervisoryControlandData
Acquisition(SCADA)(0%)
100%plansandspecificationsforwells,collectorline/wellconnections,electrical/SCADA
Inprogress
Task7:EnvironmentalDocumentation
ApprovedandadoptedCEQA(100%) FileNoticeofExemption Completed
Task8:Permitting Obtainallnecessarypermits:
LABOEExcavationPermit(0%) LAPDNoiseVariance(0%) LosAngeles(LA)SewerDischargePermit
(100%) NPDESPermit(100%) LACountyPublicHealthWellDrillingPermit
(0%)
LABOEExcavationPermit
LAPDNoiseVariance
LASewerDischargePermit
NPDESPermit
LACountyPublicHealthWellDrillingPermit
Inprogress
Category(d):Construction/Implementation
Task9:ConstructionContracting
LADWPwillprepare,advertise,holdapre‐bidmeetingandwalkthrough,evaluatethebidsandpresenttheselectedcontractortotheLADWPBoardofDirectorsforconstructionprojectaward(0%)
LADWPwillreviewtherequiredconstructionmaterialsubmittals(0%)
Bidadvertisement,contractawardandthefollowingsubmittalsasrequired:
Bidform Bondverification SBECompliance Projectschedule Shopdrawings ScheduleofValues
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
ManhattanWellsImprovementProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐6
Task DescriptionofWorkCompleted,InProgressortobeCompletedforTask(listedas%Complete)
Deliverables Status
NoticetoProceedTask10:Construction
Subtask10.1:MobilizationandSitePreparation
Procureandpreparematerials,equipmentandsite(0%)Contractormobilizestotheworksite(0%)
Implementsiteandtrafficcontrols(0%)
Submittalsasrequired: Drillingandwellpermit Soundwalldesign
Notyetbegun
Subtasks10.2:ProjectConstruction
Projectconstructionincludesdrilling,construction,anddevelopmentofproductionwells.Projectconstructionalsoincludesinstallationofproductionwellpumpsandinstallationofdistributionpipinginfrastructure.
Drilling,constructionanddevelopmentofproductionwells(0%)
Pumpinstallation(0%) Wellheadconnectionandcollectorlines
(0%) Electricalservicesandcontrols(0%)
Sitephotosandthefollowingsubmittalsasrequired: Tradesmencertifications Materialdeliverytickets Offtheshelfmaterialdata Testresults Proposedconstructionmethodology
As‐BuiltDesigndrawings Chainofcustodies Surveyresultsanddata Inspectionreports
Notyetbegun
Subtasks10.3:PerformanceTestingandDemobilization
Conductwaterquality testing,productionwelldevelopmenttesting,wellpumptesting,samplingpumptestingandverification,instrumentationtestingandcalibration,siterestoration,finalwalkthroughandimplementMonitoringPlan(0%)Assessmentofpumptestingdatatoevaluateproductionwellperformanceandspecificcapacitytoinclude:
Videolog(0%) Welldevelopmenttesting(0%) Bacterialtesting(0%) Constantrateandstepdrawdowntesting
(specificyieldevaluation)(0%)
Labresults,calibrationcertificates,testverificationsubmittals,WaterQualityStudy,ProductionWellAssessmentandProjectPerformanceMonitoringPlan
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
Nomitigationorenhancement actionsarerequiredforthisProject.Notapplicable.
Notapplicable Notapplicable
Task12:ConstructionAdministration
ConstructionmanagementtaskswillbecompletedbyWRDandLADWP(0%)
RequestForInformationsubmittals,potentialchangeorders,meetingminutesandfinalnoticeofcompletionletter
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
TIWRPAdvancedWaterPurificationFacilityandDistributionSystemExpansionProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐7
TIWRPAdvancedWaterPurificationFacilityandDistributionSystemExpansionProjectThe Terminal Island Water Reclamation Plant (TIWRP) Advanced Water Purification Facility and Distribution SystemExpansion Project (Project)Work Summary Table contains descriptive summaries of the tasks necessary to complete theProject,discussesthedeliverables,anddiscussesthecurrentstatusoftheProject,includingworkalreadycompleted.Task DescriptionofWorkCompleted,InProgress,orTo
BeCompletedforTask(listedas%Complete)Deliverables Status
Category(a):DirectProjectAdministrationTask1:ProjectAdministration
TIWRPExpansionContractAdministration: DepartmentofPublicWorksBOEwilloverseethecontractfortheTIWRPportionoftheProjectonbehalfoftheBureauofSanitation(BOS).BOEUniformProjectReportingSystem(UPRS)reportswillbemonthly.(10%)
DistributionSystemExpansionContractAdministration:BOEwilloverseetheconstructioncontractfortheDistributionSystemportionoftheProjectonbehalfofLADWP.LADWPProjectReporterreportswillbeproducedmonthly.(0%)
Grantapplicationpreparationbyconsultant(85%)
BOEUPRSreports,LADWPProjectReporter,ContractorInvoices,BOEtoBOSQuarterlyTimeChargeReports,BOEtoLADWPInvoices,Completegrantapplication,invoicesforreimbursementandotherdocumentsasnecessary.
Inprogress
Task2:LaborComplianceProgram
LACityLCP:TheCityofLosAngeles’LCP iscertifiedunderCaliforniaCodeofRegulationsChapter8,Section16425.(100%)TIWRPExpansionUnionNotification:Title22NoticetoUnionsiscomplete.(100%)
CityofLosAngelesLCPdocuments,NotificationtoUnions
Completed
Task3:Reporting ComplianceReporting:DuringtheProject,quarterlyreportsandaprojectcompletionreportwillbepreparedasspecifiedinthegrantagreement.(0%)
QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/EasementTask4:LandAcquisition
TheTIWRPexpansionandAOPimplementationdoesnotrequireanylandacquisitionoreasementsasittakesplacewithinexistingTIWRPboundaries.(100%)
DistributionSystemExpansionEasements:Themajoritydoesnotrequirelandacquisitionaspipelinewillmainlybewithinpublicrightofway.Temporaryeasements,encroachmentpermits,andapermanentrailroadeasementmaybeneededforsomeportions.(20%)
CaltransEncroachmentPermit,Construction/TemporaryEasement,PropertyEasementAgreementbetweenPortofLAandLADWP
Inprogress
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
PlanningDocuments:TheLADWP‐BOSRecycledWaterMasterPlanandtheIntegrationofTwoSeparateRecycledWaterSystemsintheHarborAreaPlanningStudy.(100%)
TIWRPExpansionandDistributionSystemPredesign.(100%)
TIWRPExpansionAOPBenchScaleTesting.(100%)
TIWRPExpansionExtendedPilotTesting.(80%)
TIWRPExpansionPrequalification‐AOP.(80%)
DistributionSystemExpansionSiteandSubstructureInvestigations.(75%)
DistributionSystemExpansionGeotechnicalInvestigations.(10%)
DistributionSystemExpansionSoilEnvironmental
DWP‐BOSRecycledWaterMasterPlan,2013HarborRecycledWaterSystemAlternativesEvaluationTM,DominguezGapBarrierProjectConditionAssessment,TIWRPExpansionPredesign,DistributionSystemExpansionPredesign,AOPBenchScaleTestReport,PilotTestReport,AOPTrainingandMonitoringProcedures,TIWRPAWPFPrequalificationPackages,SelectionReports,SubstructureReport,GeotechnicalReport,EnvironmentalEvaluation
Inprogress
GreaterLosAngelesCountyRegion Attachment4
TIWRPAdvancedWaterPurificationFacilityandDistributionSystemExpansionProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐8
Task DescriptionofWorkCompleted,InProgress,orToBeCompletedforTask(listedas%Complete)
Deliverables Status
Evaluation.(25%)
Task6:FinalDesign
TIWRPExpansionBridgingDocuments.(100%)
DistributionSystemExpansionDesign.(60%)
TIWRPExpansionDesign70%Documents.(100%)
TIWRPExpansionDesign100%Documents(design‐build).(0%)
Bridgingdocuments,Specifications,Projectplansanddrawings,Specifications,TrafficControlPlans,FinalProjectPlans
Inprogress
Task7:EnvironmentalDocumentation
TIWRPExpansionCEQA.(100%)
DistributionSystemExpansionCEQA.(100%)
TIWRPExpansionEnvironmentalSurvey.(100%)
CEQACategoricalExemption,CEQAEIR(SCH2009081093),EnvironmentalSurvey(lead,asbestos)Report
Completed
Task8:Permitting
TIWRPExpansion‐PortofLA CoastalDevelopmentPermit(100%)
TIWRPExpansion‐100%FundingApprovalbyProjectReviewCommitteebasedonaClass“0”Estimate(100%)
RegulatoryApprovalofEngineeringReports.(50%)
TIWRPExpansion‐DepartmentofBuildingandSafety(LADBS)BuildingPermits.(0%)
As‐NeededPermitsfortheDistributionSystemExpansion.(0%)
No13‐9PermitbyPortofLA,ProjectReviewCommitteeapproval,EngineeringPermit,LADBSBuildingPermits(StructuralandElectrical),NPDESPermit,UndergroundClassificationPermitforJacking,BOEExcavationPermit,CaltransPermit,RailroadCrossingPermit
Inprogress
Category(d):Construction/ImplementationTask9:ConstructionContracting
TIWRPExpansionprequalification– Design‐BuildContractor(100%),TIWRPExpansionMF,RO,andVFDSystems–SoleSource(50%),TIWRPExpansionDesign‐BuildBidandAward(0%),DistributionSystemExp.–ConstructionContract.(0%)
TIWRP AWPFPrequalificationPackages,SelectionReports,MF,RO,andVFDSystemssole‐sourceprocurementdocuments,ContractAwards,Notice‐to‐Proceed,BidAdvertisements,BidDocuments
Inprogress
Task10:ConstructionSubtask10.1:MobilizationandSitePreparation
Procurematerialsandequipment,mobilizetosite,andimplementtrafficcontrol(0%)
Notyetbegun
Subtask10.2:ProjectConstruction
TIWRPExpansion.(0%)DistributionSystemExpansionConstruction.(0%)
Sitephotos,MonthlyandQuarterlyReports,Projectcompletioncertificate
Notyetbegun
Subtask10.3:PerformanceTestingandDemobilization
TIWRPExpansionPerformanceTesting(0%),DistributionSystemExpansionPost‐Construction(0%),RegulatoryPermitTesting(0%),PunchListItem(0%),BeneficialOccupancy(0%),developprojectmonitoringplan.(0%)
PerformanceTestingReport,RegulatoryPermittoOperate,PunchListItem,Certificateofbeneficialoccupancy,ProjectPerformanceParametersReport,ProjectPerformanceMonitoringPlan
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
AstheTIWRPExpansionreceivedaCategoricalExemption,allenvironmentalmitigationrequiredisfortheDistributionSystemExpansionportionoftheProject.(20%)
Environmentalmitigationmeasuresmustbeembeddedin:ProjectPlans,ContractSpecifications,FieldInspections
Inprogress
Task12:ConstructionAdministration
TIWRPExpansionConstructionManagement.(0%)DistributionSystemExpansionConstructionManagement.(0%)
ProjectCloseoutMemo,ProjectMeetingswithContractor
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
RecycledWaterTurnoutsProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐9
RecycledWaterTurnoutsProjectTheRecycledWaterTurnoutsProject(Project)WorkSummaryTablecontainsdescriptivesummariesofthetasksnecessarytocompletetheProject,discussesthedeliverablesthatwillbeprovided,anddiscussesthecurrentstatusoftheProject,includingworkalreadycompleted.Task DescriptionofWorkCompleted,InProgress
ortobeCompletedforTask(listedas%Complete)
Deliverables Status
Category(a):DirectProjectAdministrationTask1:Administration Theprojectmanagerwillberesponsiblefor
generatingprogressreportsandoverallprojectcoordinationwithstakeholders.Thedesignatedgrantmanagerwillmanagethegrantagreement,completefinancialreports,andscheduledinvoicing.(0%)Grantapplicationpreparationwillbeconductedbyaconsultantpriortograntaward.(85%)
Invoicesforreimbursementandcompletegrantapplicationandotherdocumentsasnecessarytoreceivegrantaward
Inprogress
Task2:LaborComplianceProgram
TheWRDapproved,adopted,andauthorizedimplementationofaLCPinaccordancewithLaborCodeSection1771.5.(100%)
LCP documents
Completed
Task3:Reporting Submitreportingdocumentsasrequiredforgrantfunding.(0%)
QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/EasementTask4:LandAcquisition WRDwillsecurenecessaryconstruction
easementstoperformtheplannedworkfromagencieshavingministerialapprovalauthority.(0%)
ConstructionEasements Notyetbegun
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
Assessalternativesforobtainingneworadditionalwatersourcesforgroundwaterreplenishment.(100%)
GRIPAlternativeAnalysisReport,GRIPAlternativeAnalysisUpdateReport,PreliminaryEngineeringReportGRIPRecycledWaterProjectFinal
Completed
Task6:FinalDesign Completionofprojectplansandspecificationsforthe10%and60%design.(100%)Completionofthe90%designplans.(25%)Completionofthe100%designplans.(0%)
10%,60%,90%,and100%DesignPlans
Inprogress
Task7:EnvironmentalDocumentation
CompleteCEQAenvironmentalcompliance.(100%)
InitialStudyandMND Completed
Task8:Permitting Obtainallnecessarypermitspriortothestartofconstructionandpriortothegrantawarddate.(50%)
Obtained:RWQCB401PermitandDFW1602PermitInProgress:U.S.ArmyCorpsofEngineers404/408PermitandLACDPWFloodPermit
Inprogress
Category(d):Construction/ImplementationTask9:ConstructionContracting
Advertisebid,pre‐bidcontractorsmeeting,evaluatebids,andawardcontract.NoticetoProceedwillbeissuedbyDecember2014onceallnecessaryconstructionpermitshavebeen
Advertisementforbids,pre‐bidcontractorsmeeting,evaluationofbids,awardcontract,and
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
RecycledWaterTurnoutsProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐10
acquired.(0%) NoticetoProceedTask10:ConstructionSubtask10.1:MobilizationandSitePreparation
Thecontractorwillmobilizeandestablishafieldofficeattheproposedprojectsite.(0%)
Sitephotos Notyetbegun
Subtasks10.2:ProjectConstruction
Projectconstructionwillincludeconstructionoftworeinforcedconcreteturn‐outstructurestobeconstructedontheexistingrecycledwaterpipelinethatextendsfromtheSanJoseCreekWaterReclamationPlant.Constructionactivitieswillinclude:groundexcavation,soilcompaction,groundpaving,fabricationofpipestools,andinstallationofelectricalwiringandinstrumentation.Excavateground,compactsoil,paveground,pre‐castlids;fabricatepipespools;installelectricalwiringandinstrumentation.(0%)
Constructionreports,designdrawings,andProjectcompletionreport
Notyetbegun
Subtasks10.3:PerformanceTestingandDemobilization
Uponcompletionofconstruction,thecontractorwillconductperformanceteststodemonstratethatthefacilitiesmetallperformancerequirements.ThecontractorwilldemobilizeafterWRDacceptstheresultsoftheperformancetests,andwilldevelopprojectmonitoringplan.(0%)
PerformancetestsandProjectPerformanceMonitoringPlan
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
MitigationmeasureswillbeimplementedaccordingtotheMitigationMonitoringandReportingProgramoutlinedintheenvironmentaldocumentsfortheProject.(0%)
MitigationMonitoringPlanComplianceReport
Notyetbegun
Task12:ConstructionAdministration
AconstructionmanagerandfieldinspectorwillbecontractedforthisProject.Theconstructionmanagerwillberesponsibleforallconstructionmanagementandthepreparationofallconstructiondocuments.Thefieldinspectorwillberesponsibleforoverseeingtheconstructionsite,workingwithinspectorsandofficialsonsite,andworkingwiththeconstructionmanageronallotheraspectsoftheconstructionproject.(0%)
Constructioncontractoragreementandfieldinspectoragreement
Notyetbegun
Notes:DFW–CaliforniaDepartmentofFishandWildlifeGRIP–GroundwaterReliabilityImprovementProgramLACDPW–LosAngelesCountyDepartmentofPublicWorksMMRP–MitigationMonitoringandReportingProgramMND–MitigatedNegativeDeclarationWRD–WaterReclamationDistrictRWQCB–RegionalWaterQualityControlBoard
GreaterLosAngelesCountyRegion Attachment4
GoldsworthyDesalterExpansionProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐11
GoldsworthyDesalterExpansionProjectThe Goldsworthy Desalter Expansion Project (Project)Work Summary Table contains descriptive summaries of the tasksnecessary to complete theProject,discusses thedeliverables thatwill beprovided, anddiscusses the current statusof theProject,includingworkalreadycompleted.Task DescriptionofWorkCompleted,In Progress,orToBe
CompletedforTask(listedas%Complete)Deliverables Status
Category(a):DirectProjectAdministration Task1:Administration
EnterintoMOUwithWRDfortheoperationandpurchaseofwaterfromtheGoldsworthyDesalter(100%)MOUtoestablishrolesforreportingprogressandsubmittinginvoicesforreimbursement(10%)Administrationofgrantfundingapplication(0%)Grantapplicationpreparationwillbeconductedbyaconsultantpriortograntaward.(85%)
MOUs,Invoicesforreimbursement,andcompletegrantapplicationandotherdocuments
Inprogress
Task2:LaborComplianceProgram
TheCityofTorrancehasaLCP inplace.(100%) LCP documents Completed
Task3:Reporting Submitreportingdocumentsasrequiredforgrantfunding.(0%)
QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/Easement Task4:LandAcquisition
Notapplicable Notapplicable Notapplicable
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
EvaluatethefeasibilityofexpandingtheGoldsworthyDesalter.(100%)
FeasibilityStudy Completed
Task6:FinalDesign
Completionofprojectplansandspecificationsforthe90%design.(100%)Completionofthe100%designplansandspecifications.(80%)
90%DesignPlans,Final(100%)DesignPlans
Inprogress
Task7:EnvironmentalDocumentation
CompleteCEQAenvironmentaldocumentation.(100%)
InitialStudyandMND
Completed
Task8:Permitting
Obtainallnecessarypermits.(0%)
Permits:RWQCBNPDES,Cal/OSHAConstruction,LACDPHDrinkingWaterProgramWellPermit,LACSDSewerDischarge,CityofTorranceEncroachment
Inprogress
Category(d):Construction/Implementation Task9:ConstructionContracting
Advertiseconstructionmanagementandconstructionbidding,pre‐bidcontractorsmeeting,evaluatebids,andawardcontractinaccordancewithpubliccontractcodes.(0%)
Advertisementforbids,pre‐bidcontractorsmeeting,evaluationofbids,awardcontract,andNoticetoProceed
Notyetbegun
Task10:Construction
GreaterLosAngelesCountyRegion Attachment4
GoldsworthyDesalterExpansionProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐12
Task DescriptionofWorkCompleted,In Progress,orToBeCompletedforTask(listedas%Complete)
Deliverables Status
Subtask10.1:MobilizationandSitePreparation
Mobilizationincludescivilsiteworkconductedatwellsitesandalongthepipelineroutewithsiteclean‐upandpreparation.(0%)
Sitephotos Notyetbegun
Subtasks10.2:ProjectConstruction
Constructwellpumphouses;welldrillingatDelthorneParkandPoliceStation;installnewenergy‐efficientequipmenttoupgradeROTrainNo.1;constructROTrainNo.2todoubletreatmentcapacity;constructtwonewgroundwaterwellheadfacilities;constructtransmissionmainsfromwellstoDesalter;chemicalfeedimprovements;start‐uptesting;operationstraining;conducton‐siteinspections.(0%)
Testresults,inspectionreports,fieldreports,andProjectcompletioncertificate
Notyetbegun
Subtasks10.3:PerformanceTestingandDemobilization
WRDwilloverseethetestingofthewellperformance,welloutput,desalinationtreatment,waterqualityandpipelineintegrityattheendoftheconstructionphase.WRDwilloverseeallclean‐upanddemobilizationofconstruction.Astheoperatorofthefacility,theCityofTorrancewillassumeday‐to‐dayresponsibilityforpost‐constructionprojectmonitoring.(0%)
PerformancetestsandProjectPerformanceMonitoringPlan
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
Conductenhancementactivitiesformitigationmeasuresandbestmanagementpractices.Mitigationmeasuresincludepracticestoreduceairpollutionandminimizeconstructionimpactstowaterquality.TheWRDandtheCityofTorrancewillensuresafehandlingofanymineralorarcheologicalobjectsshouldtheybeuncoveredonthewellconstructionsitesorpipelinepathways.Traffic‐abatementmeasureswillbeimplementedtoallowfortheinstallationofpipelineunderneaththeasphaltroadway.(0%)
MitigationMonitoringPlanComplianceReport
Notyetbegun
Task12:ConstructionAdministration
WRDwilloverseetheconstructionadministrationoftheprojectviaacontractconstructionmanager.ProgressmeetingswithConstructionManager/Foreman,CityofTorrance,andprojectengineers.TheCityofTorrancewilloverseedatacollectionandreportingfromthetwonewwellsandtheoutputoftheDesalterasrequiredbygrantcontract.(0%)
Constructioncontractoragreement
Notyetbegun
Notes:Cal/OSHA–CaliforniaDivisionofOccupationalSafetyandHealthLACSD–LosAngelesCountySanitationDistrictRO–ReverseOsmosis
GreaterLosAngelesCountyRegion Attachment4
BeaWaterSaverConservationProgramProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐13
BeaWaterSaverConservationProgramProjectTheBeaWaterSaverConservationProgramProject (Project)WorkSummaryTablecontainsdescriptivesummariesof thetasksnecessarytocompletetheProject,discussesthedeliverablesthatwillbeprovided,anddiscussesthecurrentstatusoftheProject,includingworkalreadycompleted.Task DescriptionofWorkCompleted,In
Progress,orToBeCompletedforTask(listedas%Complete)
Deliverables Status
Category(a):DirectProjectAdministration Task1:Administration Implementand/orupdateagreementswith
consultantsandwithMWDtoofferthevariousconservationrebateprograms.(0%)AmendestablishedagreementswithMWDandconsultantstoincludeproposedconservationactivities.(25%)MWDwillhandleadministrativetasksassociatedwithrebates.(0%)Approvedistributionofrebatefunds.(0%)Administrationofgrantfundingapplication.(0%)Grantapplicationpreparationbyconsultant.(85%)
AgreementswithconsultantsandMWDforconservationactivities,amendedcontractagreementswithconsultantandMWDforrebateprograms,Invoicesforreimbursement,andcompletionofgrantapplicationandotherdocumentsasnecessary.
Inprogress
Task2:LaborComplianceProgram
Notapplicable Notapplicable Notapplicable
Task3:Reporting Submitreportingdocumentsasrequiredforgrantfunding.(0%)
QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/Easement Task4:LandAcquisition Notapplicable Notapplicable NotapplicableCategory(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
Assessmentofsustainablewatersuppliesbyevaluatingconservationprograms(100%)
TechnicalMemo
Completed
Task6:FinalDesign Notapplicable Notapplicable NotapplicableTask7:EnvironmentalDocumentation
Notapplicable Notapplicable Notapplicable
Task8:Permitting Notapplicable Notapplicable NotapplicableCategory(d):Construction/Implementation Task9:ImplementationContracting
CompetitivebiddingprocessforHomeWaterprogram.(0%)AwardproposalforHomeWaterprogram.(0%)ConsultantagreementfortheHomeWaterReportsandCustomerWebPortalProgram.(0%)Contractagreementsforinformationallandscapeclassesandwebsitedevelopment.(100%)
Solicitproposal,awardcontract,consultantagreement,andcontractagreements
Inprogress
Task10:Construction/Implementation
Subtask10.1:MobilizationandSitePreparation
Notapplicable Notapplicable Notapplicable
Subtask10.2:ProjectImplementation
IssuerebatesforHighEfficiency toilets,turfremoval,andrainbarrels(0%)Replaceturfwithacceptablenativeplants
Distributerebates,turfremovalandreplacement,
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
BeaWaterSaverConservationProgramProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐14
Task DescriptionofWorkCompleted,InProgress,orToBeCompletedforTask(listedas%Complete)
Deliverables Status
andpermeablesurfaces(0%)ImplementHomeWaterPortal(0%)ImplementWaterWiseWebsitefortheeducationalprogramandworkshops(0%)Implementlandscapingclasses(0%)
customerwebportalandinformationalwebsite,landscapingplanwebsite,andeducationalworkshops.
Subtask10.3:PerformanceTestingandDemobilization
Projectmonitoring(0%)Evaluatewatersavingsforproposedconservationmeasures(0%)Trackthequantityofrebatescompleted(0%)Customersatisfactionsurvey(0%)
ProjectPerformanceMonitoringPlan,Post‐installationinspectionreports,annualwatersavingsdata,quarterlyparticipationdata,andcustomersatisfactionresults
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
Notapplicable Notapplicable Notapplicable
Task12:ConstructionAdministration
ImplementationmanagementtaskswillbecompletedbytheCityofBurbankandWRD(0%)
Implementationmanagement
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
On‐SiteRecycledWaterRetrofitsProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐15
On‐SiteRecycledWaterRetrofitsProjectThe On‐Site RecycledWater Retrofits Project (Project)Work Summary Table contains descriptive summaries of the tasksnecessary to complete theProject,discusses thedeliverables thatwill beprovided, anddiscusses the current statusof theProject,includingworkalreadycompleted.Task DescriptionofWorkCompleted,InProgressortobeCompleted
forTask(listedas%Complete)Deliverables Status
Category(a):DirectProjectAdministrationTask1:Administration
Grantapplicationpreparationbytheconsultant.(85%)TheWestBasinMunicipalWaterDistrict(WBMWD)ProjectManager(PM)willcoordinatemeetings,managecontracts,maintaintheProjectschedule,andcollectalldata.ThePMwilloverseetheProject’sconceptualproposal,implementation,andgrantreporting.ThePMwillprovideinput,data,reviewdocumentsanddesignplans,coordinatetasksthroughoutallphasesofProjectandberesponsibleforcommunicationwiththeProjectpartnersduringimplementation.(0%)
Completegrantapplicationandotherdocumentsasnecessarytoreceivegrantaward,invoicesforreimbursement,Projectschedule,andcustomeragreements
Inprogress
Task2:LaborComplianceProgram
TheLCPwillberequestedbyWBMWDtobemaintainedandimplementedbythecontractor.WBMWD’sConstructionManagerwillreviewlaborcompliancereportspreparedbythecontractor.WBMWDwillrequirethatthecontractormeettheprevailingwagerequirements.(0%)
LCPdocuments Notyetbegun
Task3:Reporting
SubmitquarterlyandfinalReporttotheStateperProposition84requirements.(0%)
QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/EasementTask4:LandAcquisition
AcquireeasementtoconstructlateralsinpublicstreetsfortheManhattanVillageHomeOwnersAssociation(HOA).(0%)Nolandacquisitionisnecessary.
ProofofEasement Notyetbegun
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
TheProjectwasidentifiedforitsfeasibilityinthe2009CapitalImplementationMasterPlan.(100%)OtherworktobecompletedincludesSiteInvestigationandAssessmentsfortheeightProjectsites:AnimoCharterMiddleSchool(0%),JeffersonMiddleSchool(0%),DominguezTechCenter(20%),AndersonPark(0%),St.JamesSchool(0%),VircoManufacturingCorp.(0%),ManhattanVillageHOA(20%),andCalTrans–105andWesternAve.(0%)
2009CapitalImplementationMasterPlan,andSiteInvestigationandAssessmentReports
Inprogress
Task6:FinalDesign
CompleteProjectplansandspecificationsforthe60%,90%,and100%Designfor:AnimoCharterMiddleSchool(0%),JeffersonMiddleSchool(0%),DominguezTechCenter(0%),AndersonPark(0%),St.JamesSchool(0%),VircoManufacturingCorp.(0%),ManhattanVillageHOA(0%),andCalTrans–105andWesternAve.(0%)
60%,90%,and100%Designplansandspecs
Notyetbegun
Task7:EnvironmentalDocumentation
AProgrammaticEnvironmentalImpactReport(EIR)wascompletedin2003forlateralsthatwillfeedseveralofthesitesforthisProject.TwoadditionalSupplementalEnvironmentalAssessments(EAs)werecompletedin2007and2009forotherlateralsrelatedtotheProject.(100%)Theconnectionstothesitesthemselvesdonotrequireadditionalenvironmentalstudiesbecausetheywilltakeplaceonprivateproperty.IftheManhattanVillageHOAhasspecificrequirements,thesewillbeimplemented.
Harbor/SouthBayWaterRecyclingProjectEnvironmentalAssessment/InitialStudy(2003),andSupplementalEnvironmentalAssessment/SubsequentMitigatedNegativeDeclaration(2007&2009)
Completed
GreaterLosAngelesCountyRegion Attachment4
On‐SiteRecycledWaterRetrofitsProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐16
Task DescriptionofWorkCompleted,InProgressortobeCompletedforTask(listedas%Complete)
Deliverables Status
Task8:Permitting
Obtainthefollowingpermits: Encroachmentpermitsfromeachoftheeightcitieswhen
workrequiredoutsideprivateproperty(0%) LetterstoandfromDepartmentofPublicHealth(DPH)
regardingtheProject’scompliancewithpotableandrecycledwaterseparationcriteria(0%)
NPDESpermitforDischargeofhydrostatictestingwater(ManhattanVillageHOA,DominguezTechCenter,Virco,andAnimoCharterMiddleSchool)(0%)
CaltranswilldeterminetheirinvolvementinpermittingwithintheirProjectsiteconnection(0%)
Encroachmentpermits,DPHoverallpermitandProjectsiteletters,andNPDESpermit
Notyetbegun
Category(d):Construction/ImplementationTask9:ConstructionContracting
WBMWDwillprepareandadvertisethebidandpresenttheselectedcontractortotheWBMWDBoardofDirectorsforconstructionProjectaward.(0%)Theselectedcontractorwillhavetosubmitinsurance,bonds,signedcontract,etc.(0%)WBMWDwillissueNoticetoProceed(NTP).(0%)
Biddocuments,contractaward,andNTP
Notyetbegun
Task10:Construction
Subtask10.1:MobilizationandSitePreparation
ProcureDIGAlertforutilitymarkings,surveying,potholing,materialsubmittal,shopdrawingsubmittals,contractorpermits,constructiontemporalre‐striping,attendanceofmeetings,materialandequipmentprocurement,bestmanagementpractices(BMPs),andstorageareasetup.(0%)
Surveyresults,shopdrawingsubmittals,contractorpermits,andconstructionBMPsandNPDESpermitrequirementsimplementation
Notyetbegun
Subtasks10.2:ProjectConstruction
Projectconstructionincludestrafficcontrol,sawcutting,trenching,pipeinstallation,pavement,restorationofstripping,andBMPs.(0%)
Sitephotos Notyetbegun
Subtasks10.3:PerformanceTestingandDemobilization
Conductpressuretest,cleanupProjectsiteandstoragearea,conductafinalwalkthroughofthesiteforProjectacceptance,demobilizesite,anddevelopaMonitoringPlan.(0%)
Performancetestingresults,andProjectPerformanceMonitoringPlan
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
Throughouttheconstruction,dust,noise,applicationofconstructionBMPsandenvironmentalassessmentrecommendationswillbemonitored.DisposalofpressuretestwaterwillbeconductedperNPDESpermitrequirements.ThesesubmittalswillbeprovidedaspartofSubtask10.1asMobilizationandSitePreparationrequirements.NoenhancementormitigationactionshavebeenidentifiedforthisProjectatthispoint.(0%)
ThissubmittalwillbeprovidedunderSubtask10.1(asMobilizationandSitePreparationrequirements)
Notyetbegun
Task12:ConstructionAdministration
AconstructionmanagementcompanywillbehiredtoassistthePMtoperforminspections,compileconstructionreports,conductfieldverifications,participateinnegotiations,andmaintainbookingoflogreportsandsubmittals.DesignEngineeringwilloccurthroughoutconstruction.AconstructionoutreachfirmwillbehiredtooperatetheProjectconstructionhotlineanddistributeconstructionnotices.Atconstructioncompletionafinalnoticeofcompletionletterwillbeissued.(0%)
ConstructionReports,fieldverifications,logreports,constructionnotices,andfinalnoticeofcompletionletter
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
WestCoastBasinBarrierProjectUnit12InjectionandObservationWellsProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐17
UpperSanGabrielValleyMunicipalWaterDistrict(USGVMWD)RecycledWaterProgramExpansionProjectTheUSGVMWDRecycledWaterProgramExpansionProject(Project)WorkSummaryTablecontainsdescriptivesummariesofthetasksnecessarytocompletetheProject,discussesthedeliverablesthatwillbeprovided,anddiscussesthecurrentstatusoftheProject,includingpermittingactivities.Task DescriptionofWorkCompleted,InProgressortobe
CompletedforTask(listedas%Complete)Deliverables Status
Category(a):DirectProjectAdministrationTask1:Administration
Grantapplicationpreparationwillbeconductedbyaconsultantpriortograntaward.(85%)USGVMWDwillexecuteMOUsandagreementswiththeappropriatepartnerandactasgrantadministratortoseethatallgrantrequirementsaremet.USGVMWDwillcoordinatewithpartneragenciesandorganizationstoobtaintheinvoicesandpackageforsubmittalforreimbursementofProjectexpenditures.(0%)
Completegrantapplication,MOUs,andinvoicesforreimbursement
InProgress
Task2:LaborComplianceProgram
AconsultantwillbehiredtopreparetheLCP.(0%) LCPdocuments Notyetbegun
Task3:Reporting
Necessarywaterusagedatawillbecompiledforpreparationofthequarterlyreportsandthefinalreportasspecifiedinthegrantagreement.(0%)
QuarterlyandFinalReports
Notyetbegun
Category(b):LandPurchase/EasementTask4:LandAcquisition
TheproposedProjectdoesnotanticipateanylandacquisition. NotApplicable NotApplicable
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
Threetechnicalevaluations/studieshavebeencompletedpriortothegrantawarddateincluding:
LaPuenteValleyCountyWaterDistrict(LPVCWD)RecycledWaterFeasibilityStudyReportandsupplementalLaPuenteValleyCountyWaterDistrictRecycledWaterProjectTechnicalMemorandum(100%)
FeasibilityStudyfortheProposedSouthElMonteWaterSystem(100%)
LetterReportonRoseHillsMemorialParkandCemeteryRecycledWaterEvaluationforPhase2andRoseHillsMemorialParkandCemeterySupplementalMemorandum(100%)
LPVCWDRecycledWaterFeasibilityStudyReport,DraftFeasibilityStudyfortheProposedSouthElMonteWaterSystem,andLetterReportonRoseHillsMemorialParkandCemeteryRecycledWaterEvaluationforPhase2
Complete
Task6:FinalDesign
Designoftherecycledwaterpipelinesandretrofitsofcustomers’irrigationsystem.Surveyingandgeotechnicalinvestigationwillbeconductedandsubmittalswillincludepreliminarydesignreport,60%,90%,and100%forplansandspecificationsincludingCivil,Structural,andElectrical,andTrafficControl.(0%)
PreliminaryDesignReport,60%Design,90%Design,and100%Designplansandspecifications
Notyetbegun
Task7:EnvironmentalDocumentation
AnInitialStudyandenvironmentalcompliancedocumentswhichwillresultintheadoptionofaNegativeDeclarationwillbecompletedpriortothegrantawarddatetosatisfytheCEQArequirements.(25%)
ApprovedandadoptedCEQAdocumentation(InitialStudy,NegativeDeclaration)
Inprogress
Task8:Permitting
Obtainnecessarypermitsincluding: EncroachmentPermitfromtheCity(0%) NPDESDischargePermitfromRegionalWaterQuality
ControlBoard(RWQCB)(0%) RecycledwaterconversionapprovalfromCDPH(0%)
NoticeofIntents,CityEncroachmentPermits,NPDESDischargePermit,andRecycledWaterConversionPermit
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
WestCoastBasinBarrierProjectUnit12InjectionandObservationWellsProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐18
Task DescriptionofWorkCompleted,InProgressortobeCompletedforTask(listedas%Complete)
Deliverables Status
Category(d):Construction/ImplementationTask9:ConstructionContracting
Projectbiddocumentswillbeprepared,apre‐proposalmeetingwillbescheduledtogooverthescopeoftheProjectwithbidders,andresponsestoanyRequestsforInformation(RFIs)duringthebidperiodwillbeprepared.Thesuccessfulbidderwillbeawardedthecontract,andNoticetoProceed(NTP)willbeissued.(0%)
Advertisementforbids,pre‐proposalmeeting,responsestoRFIs,bidevaluations,contractaward
Notyetbegun
Task10:ConstructionSubtask10.1:MobilizationandSitePreparation
Contractorwillmobilizethesiteandprovideadetailedconstructionschedule,andmeetwithappropriateCitystaff,implementingagenciesandUSGVMWDrepresentativestogoovertheirproposedworkplantogetconcurrenceifconstructionactivitiesweretotakeplaceinpublicstreets(i.e.pipelines).Contractorwillalsodocumentthepre‐constructionsiteconditionswithphotosandvideos.(0%)
Projectschedules,contractormeetingminutes,andsitephotos/videos
Notyetbegun
Subtasks10.2:ProjectConstruction
Forconstructionofrecycledwaterpipelinesinpublicstreets,thecontractorwillpotholeforutilitiesalongthepipelinealignmentandsetuptrafficcontrolpertheCityapprovedTrafficControlPlan.Constructionactivitieswillincludedemolitionofexistingpavement,installationofpipelineandvalves.Forrecycledwaterretrofits,constructionactivitieswillincludeinstallationofrecycledwaterpipes,newrecycledwatermeter,backflowpreventiondevice,anddisconnectionoftheirrigationsystemfrompotablewaterline.Allrecycledwaterequipmentwillbeappropriatelytagged.(0%)
Dailyconstructionreportincludingphotos,constructionsignage,andtrafficcontrol
Notyetbegun
Subtasks10.3:PerformanceTestingandDemobilization
Contractorwillperformhydrostaticpressuretestsonallinstalledpipelineperspecificationstocheckforleakage.Afinalshut‐downtestwillbeconductedwithCDPHstaffpriortoreceivingsign‐offontherecycledwaterretrofitstoverifythephysicalseparationoftheirrigationsystemfrompotablewaterandverifyitisconnectedtotherecycledwatersupply.Followingcompletionoftestsandconstruction,thesitewillbedemobilized,andaMonitoringPlanwillbedeveloped.(0%)
Projectcompletioncertificate,post‐constructionphotos/videos,testingcertifications,andMonitoringPlan
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
CEQArequirementswillbecompletedpriortothegrantawarddateandarenotanticipatedtorequireanymitigationmeasures.(0%)
Noneexpected Notyetbegun
Task12:ConstructionAdministration
Constructionadministrationwillincludeconstructionmanagementsuchasinspections,accounting,regulatoryagencycompliance,andhandlingofconstructionissuesthatwillinvolvetheImplementingAgencies.(0%)
Billinginvoices,issuesdocumentation,andinspectionreports
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
WestCoastBasinBarrierProjectUnit12InjectionandObservationWellsProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐19
WestCoastBasinBarrierProjectUnit12InjectionandObservationWellsProjectTheWestCoastBasinBarrierProjectUnit12InjectionandObservationWellsProject(Project)WorkSummaryTablecontainsdescriptive summariesof the tasksnecessary tocomplete theProject,discusses thedeliverables thatwillbeprovided,anddiscussesthecurrentstatusoftheProject,includingpermittingactivities.Task DescriptionofWorkCompleted,InProgressortobe
CompletedforTask(listedas%Complete)Deliverables Status
Category(a):DirectProjectAdministrationTask1:Administration
Grantapplicationpreparationwillbeconductedbyaconsultantpriortograntaward.(85%)Uponawardofthegrant,LACFCDwillprocessthenecessaryagreementsandpaperworktoacceptandabidebythegrantrequirements.Reimbursementrequestswillbesentasoutlinedinthegrantagreementwithallthenecessarysupportingdocumentation.(0%)
Completegrantapplicationandotherdocumentsasnecessarytoreceivegrantaward,andinvoicesforreimbursement
Inprogress
Task2:LaborComplianceProgram
LACFCDcurrentlyhasaLaborComplianceProgram(LCPID:2011.01022)whichhasbeenapprovedbytheStateforProp84grants.(100%)
LCPdocuments Completed
Task3:Reporting LACFCDstaffwillprepareandprovidethenecessaryquarterlyandFinalReportsasspecifiedinthegrantagreementandguidelines.(0%)
QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/EasementTask4:LandAcquisition
Nonerequired.TheProjectisconstructedcompletelywithinpublicrightofway.
Notapplicable Notapplicable
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
AProjectDesignConceptwaspreparedandfinalizedon10/20/10.(100%)
ProjectDesignConcept
Completed
Task6:FinalDesign
60%,90%,and100%designplans,specifications,andestimatewerecompletedon7/3/12.(100%)
60%,90%,and100%designplans,specificationsandestimate
Completed
Task7:EnvironmentalDocumentation
TheProjectiscategoricallyexemptfromtheprovisionsofCEQA.ThecategoricalexemptionwillbeadoptedwhentheProjectisadvertisedinNovember2014.(95%)Thisisnotafederalaidproject,andNEPAisnotrequired.
AdoptedCategoricalExemption
Inprogress
Task8:Permitting LACFCDwillobtainanengineeringpermitfrom theCityofRedondoBeachinJuly.(0%)
CityofRedondoBeachEngineeringPermit
Inprogress
Category(d):Construction/ImplementationTask9:ConstructionContracting
AdvertiseProjectandsolicitbids(0%)AwardContract(0%)ExecuteAgreementwithContractor(0%)IssueNoticetoProceed(NTP)1formobilization(0%)IssueNTP2forconstruction(0%)
Bidsolicitationpackage,contractaward,agreementwithcontractor,NTP1,andNTP2
Notyetbegun
Task10:ConstructionSubtask10.1:MobilizationandSitePreparation
Contractorwillmobilizetotheworksite,establishafieldoffice,produceaprojectscheduleandprovidethenecessarysubmittals.(0%)LACFCDreviewsandapprovessubmittals.(0%)
Projectschedule,andothercontractorsubmittals
Notyetbegun
Subtasks10.2:ProjectConstruction
Constructionactivitieswillincludedrillingtheinjectionandobservationwells,installingwellcasing,filterpack,andseal,pumpingthewellfordevelopment,andtreatingthewaterfordischarge.(0%)
Sitephotos Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
WestCoastBasinBarrierProjectUnit12InjectionandObservationWellsProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐20
Task DescriptionofWorkCompleted,InProgressortobeCompletedforTask(listedas%Complete)
Deliverables Status
Subtasks10.3:PerformanceTestingandDemobilization
Afterthecompletingtheconstructionofalltheinjectionandobservationwells,thecontractorwilldemobilizefromthesite.(0%)AMonitoringPlanwillbedevelopedandimplementedusingthenewobservationwells.(0%)
ProjectPerformanceMonitoringPlan
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
NomitigationorenhancementisrequiredforthisProject. Notapplicable Notapplicable
Task12:ConstructionAdministration
LACFCDwillhaveofficestaffandfieldinspectorsassignedtotheProjecttoensurethecontractormeetsProjectdesignandspecificationcriteria.Fieldinspectorswillkeepnotesonhoursworked,equipmentused,andmaterialsinstalled.(0%)OfficestaffwillutilizethefieldnotestoauthorizeprogresspaymentsandProjectcloseoutdocuments.(0%)
Fieldnotesonconstructionactivities,paymentauthorizations,andProjectcloseoutdocuments
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
RockhavenWellProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐21
RockhavenWellProjectThe Rockhaven Well Project (Project) Work Summary Table contains descriptive summaries of the tasks necessary tocompletetheProject,discussesthedeliverablesthatwillbeprovided,anddiscussesthecurrentstatusoftheProject,includingworkalreadycompleted.Task DescriptionofWorkCompleted,InProgressortobe
CompletedforTask(listedas%Complete)Deliverables Status
Category(a):DirectProjectAdministrationTask1:Administration a. ReimbursementinvoicingwithDepartmentofWater
Resources(DWR)(0%)b. AdministrationofCrescentaValleyWaterDistrict
(CVWD)andGlendaleWaterandPower(GWP)agreementfortheuseofthesiteandcostofwater.(40%)
c. Administrationofcontractswithconsultants,contractors,andvendors.(0%)
d. Grantapplicationpreparationbyconsultant(85%)
a. Invoicesforreimbursement
b. CVWD/GWPAgreement
c. VendorAgreements
d. Completegrantapplication(pendingconditionalacceptance)
Notyetbegun
Task2:LaborComplianceProgram
CVWD’sLCPwillbeincludedintheProjectspecificationsandismanagedbyContractorComplianceandMonitoringInc.(20%)
LCPdocuments Inprogress
Task3:Reporting Submitreportingdocumentsasrequiredforgrantfunding.(0%)
QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/EasementTask4:LandAcquisition TheRockhavenWellsiteisownedbyGWPandCVWDwill
enterintoaleaseagreementtooperatethewellonbehalfofCVWDandGWP.(40%)
CVWD/GWPleaseAgreement
Inprogress
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
a. Subsurfaceinvestigationtotestproductionwellviability.(100%)
b. Exploratorybidpackageforwelldrilling,wellcasingdesign,mechanicaldevelopmentanddischarge,pumptesting,andwaterqualitytesting.(100%)
c. Analysisofpumptestandwaterqualitydatatodemonstrateviabilityasapotablewatersource(100%)
a. RockhavenNo.1PitHoleandWellMemorandum
b. RockhavenExploratoryBidPackage
c. RockhavenExploratoryLetterreport
Inprogress
Task6:FinalDesign a. Preparepreliminarydesigntoidentifymajorelementsforfinaldesign(0%)
b. Wellsitedesignbyconsultant(0%)c. PipelinedesignbyCVWD(0%)d. Incorporatedesignplansintooneconstructionbid
package.(0%)
PreliminaryDesignReport;Plansandspecifications
Inprogress
Task7:EnvironmentalDocumentation
CEQANegativeDeclarationpreparedandNoticeofDeterminationwascompletedonJune17,2014.(100%)
NoticeofDetermination
Inprogress
Task8:Permitting CVWDwillobtainallnecessarypermitsforconstructionincluding:a. ExcavationPermit‐CityofGlendale(0%)b. NPDESPermit‐RegionalWaterQualityControlBoard
(0%)c. StormDrainPermit‐LosAngelesCounty,Department
ofPublicWorks(0%)
Excavation,NPDES,StormDrain,andElectricalpermits
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
RockhavenWellProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐22
Task DescriptionofWorkCompleted,InProgressortobeCompletedforTask(listedas%Complete)
Deliverables Status
d. ElectricalPermit‐ GlendaleWaterandPower(0%)Category(d):Construction/ImplementationTask9:ConstructionContracting
a. Advertisebid(0%)b. Pre‐bidmeetingandwalkthrough(0%)c. Evaluatebids(0%)d. Awardcontract(0%)
Advertisementforbids,Contractaward,Agreement,InsuranceCertificates
Notyetbegun
Task10:ConstructionSubtask10.1:MobilizationandSitePreparation
a. Ordermaterial–CVWD(0%)b. Mobilization(0%)c. Sitepreparation(0%)
Notyetbegun
Subtasks10.2:ProjectConstruction
a. Pre‐Constructionmeeting(0%)b. Shopdrawingreview(0%)c. Installon‐sitepiping&electricalconduits(0%)d. Installoff‐sitestormdrain(0%)e. Installsiteimprovementsforbuilding(0%)f. Installbuilding(0%)g. Installpump&motor(0%)h. Installmotorcontrolcenter,wiring&conduits(0%)i. Installelectricalservice(0%)j. InstallSCADA/telemetry(0%)k. Finalon‐siteimprovements(0%)l. Finalpunchlist(0%)m. Install8‐inchwatermain(0%)n. Completeconstruction(0%)
SitephotosConstructionreports
Notyetbegun
Subtasks10.3:PerformanceTestingandDemobilization
a. Developperformancemonitoringplanb. Pumpstartupandperformancetesting(0%)c. Waterqualitytesting(0%)d. Demobilization(0%)
ProjectPerformanceMonitoringPlanandperformancetestingresults
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
Notapplicable Notapplicable Notapplicable
Task12:ConstructionAdministration
a. ConstructionmanagementserviceswillbeperformedbyCVWD'sinspector(0%)
b. Soilstestingbysubcontractor(0%)c. Concretetestingbysubcontractor(0%)d. Electricalinspectionbysubcontractor(0%)
As‐BuiltDrawings;TelemetryPipingandInstrumentationDrawings;ManufacturerWarranty;Manuals;Projectcompletioncertificate
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
WaterBudgetBasedRateImplementationProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐23
WaterBudgetBasedRateImplementationProjectTheWaterBudgetBasedRateImplementationProject(Project)WorkSummaryTablecontainsdescriptivesummariesofthetasksnecessarytocompletetheProject,discussesthedeliverablesthatwillbeprovided,anddiscussesthecurrentstatusoftheProject,includingworkalreadycompleted.Task DescriptionofWorkCompleted,InProgress or
ToBeCompletedforTask(%Complete)
Deliverables Status
Category(a):DirectProjectAdministrationTask1:Administration
Grantadministration:application(85%) andinvoicing(0%).Grantapplicationpreparationbyconsultant(85%)
Completegrantapplication(pendingconditionalacceptance)andotherdocumentsasnecessary,Invoices
Inprogress
Task2:LaborComplianceProgram
AddlanguageinthePBWABidSpecificationsnotifyingthebiddersthatbidsmustcomplywithCaliforniaLaborCodeSection1771.5(b).(0%)
CertifiedpayrollprovidedbytheContractor
Notyetbegun
Task3:Reporting Grantreporting(0%) Quarterly ProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/EasementTask4:LandAcquisition
Notapplicable Notapplicable Notapplicable
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
(a) WaterBudgetBasedRatesImplementation–CostEffectivenessAnalysis,includingAppendix:LVMWDMemorandum‐Post‐DroughtWaterDemand;April2012(100%)
(a) WhitePaperwithAppendedMemorandum
Completed
Task6:FinalDesign Notapplicable Notapplicable Notapplicable
Task7:EnvironmentalDocumentation
Notapplicable Notapplicable Notapplicable
Task8:Permitting Notapplicable Notapplicable Notapplicable
Category(d):Construction/ImplementationTask9:ImplementationContracting
Developscopeofworkandrequestforproposals;advertiseforbids;evaluationofbids;andawardcontractsforvariousvendors:(a) Budgetbasedratesconsultant(100%)(b) AerialImageryacquisition(100%)(c) Financialrateconsultantforcostofservice
andratestructure(0%)(d) Temporarystaffforcustomerdata
development(0%)(e) Evapotranspirationdatavendor(0%)(f) Billingsystemsoftwareupgrade(0%)
Scopeofwork,requestforproposalsandcontractsawarded.
Inprogress
Task10:ImplementationSubtask10.1:MobilizationandSitePreparation
Notapplicable Notapplicable Notapplicable
Subtask10.2:ProjectConstruction/Implementation
(a) Aerialimageryandirrigatedlandscapedelineationproductionandverification(5%)
(b) Analyzeexistingdatatoestimateactualindooruseandsummarizepriorstudiesof
(a) GISandExceldataofirrigatedareaforeachcustomerparcel
(b) IndoorUseStaffReport(c) EvapotranspirationData
Inprogress
GreaterLosAngelesCountyRegion Attachment4
WaterBudgetBasedRateImplementationProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐24
Task DescriptionofWorkCompleted,InProgress orToBeCompletedforTask(%Complete)
Deliverables Status
actualandefficientindooruseforastaffreportandrecommendationontheindooruseallocation.(0%)
(c) Prepareevapotranspirationdata(0%)(d) Completecostofserviceanalysisanddesign
ratesinawaterbudgetframework(0%)(e) ModifyCustomerInformation/BillingSystem
toaccommodatewater‐budgetbasedratestructurecalculatingacustomer’sbillbasedonirrigatedarea,indoorusage,actualevapotranspirationandotherusage(throughvariances).Theupgradewillprovideamonthlybillingstructure.(0%)
(f) DevelopanimplementationplantofurtherAutomaticMeterReading/Infrastructure(AMR/AMI)installationandoperationtodetermineaccuratemonthlycustomerbilling(0%)
(g) ConductadditionalmanualmeterreadingsuntilAMR/AMIsystemissufficientlydevelopedsuchthatmonthlymeterreadingcanbeaccomplishedin‐house.(0%)
(h) IdentifyrevisionsneededinLVMWDCodetoaccommodatebudgetbasedrates(0%)
(i) UpdateandimplementdraftPublicOutreachPlanfortheProject(0%)
(d) CostofServiceReportandBudgetbasedratestructureforallcustomerclasses
(e) CustomerInformation/BillingSystemcapableofimplementingbudgetbasedbilling
(f) AMR/AMIimplementationplan
(g) Monthlymeterreads(h) LasVirgenesCodeRevision
Memorandum(i) PublicOutreachPlan
Prop.218notice Prop.218hearing Webpages Surveymailerfor
customerdata Workshops Newsrelease
Subtask10.3:PerformanceTestingandDemobilization
Notapplicable Notapplicable Notapplicable
Task11:EnvironmentalCompliance/Mitigation/Enhancement
Notapplicable Notapplicable Notapplicable
Task12:ConstructionAdministration
Notapplicable Notapplicable Notapplicable
GreaterLosAngelesCountyRegion Attachment4
WellNo.2RehabilitationProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐25
WellNo.2RehabilitationProjectTheCityofInglewood(City)WellNo.2RehabilitationProject(Project)WorkSummaryTablecontainsdescriptivesummariesof the tasks necessary to complete the Project, discusses the deliverables thatwill be provided, and discusses the currentstatusoftheProject,includingworkalreadycompleted.Task DescriptionofWorkCompleted,InProgressor
ToBeCompletedforTask(listedas%Complete)Deliverables Status
Category(a):DirectProjectAdministration Task1:Administration Administrationofreimbursementinvoices(0%)
Grantapplicationpreparationbyconsultant.(85%)Invoicesforreimbursementandcompletegrantapplicationandotherdocumentsasnecessary
Inprogress
Task2:LaborComplianceProgram
AddlanguageintheBidSpecificationsnotifyingthebiddersthatbidsmustcomplywithCaliforniaLaborCodeSection1771.5(b).(0%)
CertifiedpayrollprovidedbytheContractor
Notyetbegun
Task3:Reporting Submitreportingdocumentsasrequired forgrantfunding.(0%)
QuarterlyProgressandFinalReports
Notyetbegun
Category(b):LandPurchase/Easement Task4:LandAcquisition Nolandwillneedtobeacquiredorleasedforthis
Project.Notapplicable.Notapplicable Notapplicable
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
PreliminaryEvaluationofDownwellConditionMunicipal‐SupplyWaterWellNo.2CityofInglewood:providesrecommendationsforrehabilitation,preparedbyRichardC.SladeAssociateson3/21/2014.(100%)
TechnicalMemorandum Completed
Task6:FinalDesign Sincethisisanexistingwellrehabilitation,theCitywillPreparetheBidPackageusingas‐builtplans,driller’slogs,existingpump/motordata,andProjectspecifications.(0%)
BidPackage Completed
Task7:EnvironmentalDocumentation
CEQA/NationalEnvironmentalPolicyAct(NEPA):CategoryExemptionwillbefiledwithLosAngelesCountyClerkOfficeduringthebiddingprocess.(0%)
ApprovedandadoptedCEQA/NEPAdocumentation
Notyetbegun
Task8:Permitting ProjectwilluseexistingNPDESPermit#CAG994005forgroundwaterdischargeduringconstruction(100%)
NPDESPermit
Completed
Category(d):Construction/Implementation Task9:ConstructionContracting
Advertiseforbids(0%)Holdpre‐bidcontractorsmeeting(0%)Evaluatebids(0%)Awardcontract(0%)
Advertisementforbidsandcontractaward
Notyetbegun
Task10:Construction Subtask10.1:MobilizationandSitePreparation
Mobilization(0%)SitePreparation(0%)
Notyetbegun
Subtasks10.2:ProjectConstruction
1)Removingexistingpump/motorassemblies(0%)2)Videoinspectionoftheexistingwell(0%)3)Wire‐brushing(0%)4)Jetting(0%)5)Bailing(0%)6)Chemicaltreatment(0%)
Sitephotos Notyetbegun
Subtasks10.3:PerformanceTestingandDemobilization
1)InstallationofTestPump(0%)2)InstallationofDischargeManifold(0%)3)Wellproductiontest(0%)
PerformancetestingresultsandProjectPerformanceMonitoring
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
WellNo.2RehabilitationProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐26
Task DescriptionofWorkCompleted,InProgressorToBeCompletedforTask(listedas%Complete)
Deliverables Status
4)Re‐installationofpump/motorassemblies(0%) Plan
Task11:EnvironmentalCompliance/Mitigation/Enhancement
Noadditionalenvironmentalmitigationsarerequiredbeyondexistingpermitcompliance.
Notapplicable Notapplicable
Task12:ConstructionAdministration
ConstructionadministrationandinspectionwillbedonebyCity.(0%)PrepareProjectinspectionReport.(0%)
ProjectinspectionreportandProjectcompletioncertificate
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
PomonaBasinRegionalGroundwaterProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐27
PomonaBasinRegionalGroundwaterProjectThePomonaBasinRegionalGroundwaterProject(Project)WorkSummaryTablecontainsdescriptivesummariesofthetasksnecessary to complete theProject,discusses thedeliverables thatwill beprovided, anddiscusses the current statusof theProject,includingworkalreadycompleted.Task DescriptionofWorkCompleted,InProgressorTo
BeCompletedforTask(listedas%Complete)Deliverables Status
Category(a):DirectProjectAdministrationTask1:Administration InternalProjectadministrationincludingholding
meetingsandprogressreporting(0%)ReimbursementinvoicingwithDWR(0%)Grantapplicationpreparationbyconsultant(85%)
ProgressReports,Invoices,Completegrantapplicationandotherdocumentsasnecessary
Inprogress
Task2:LaborComplianceProgram
AddlanguageinthePBWABidSpecificationsnotifyingthebiddersthatbidsmustcomplywithCaliforniaLaborCodeSection1771.5(b).(20%)
LCPDocuments Inprogress
Task3:Reporting QuarterlyandFinalReportsasrequiredbyDWR(0%) QuarterlyProgress andFinalReports
Notyetbegun
Category(b):LandPurchase/EasementTask4:LandAcquisition PropertyleaseagreementwiththeCityofLaVernefor
theOldBaldywellsite(90%)PropertyleaseagreementwithGoldenStateWaterCompanyfortheDurwardwellsite(50%)
FullyExecutedleaseagreements
Inprogress
Category(c):Planning/Design/Engineering/EnvironmentalDocumentationTask5:AssessmentandEvaluation
a. PomonaBasinRegionalGroundwaterProjectAlternativesEvaluation–Nov15,2012.(100%)
b. PomonaBasinRegionalGroundwaterProjectFinalEngineeringReport–Feb7,2014(100%)
c. SixBasinsGroundwaterProjectHydraulicAnalysis(100%)
a. TechnicalMemorandum
b. EngineeringReportc. Hydraulic
EngineeringReport
Completed
Task6:FinalDesign a. PerformSiteInvestigation(25%)b. PreparethefollowingBidPackages:
BidPackage#1:PWRJointWaterLineImprovements(20%)
BidPackage#3:DurwardWellequippingandconnectiontothePWRLine(0%)
BidPackage#4:ConnectionofOldBaldytothePWRline(0%)
c. PrepareBidPackage#2fordesignandconstructionofDurwardWelltobeperformedbywelldrillingcontractor.(0%)
a. TopographicSurvey,GeotechnicalEvaluation,Electrical&Structuralcriteria
b. EachBidPackage: 50%Submittal 90%Submittal 100%
Submittalc. WellDesignBid
Package
Inprogress
Task7:EnvironmentalDocumentation
CEQA‐FileCategoricalExemptionwiththeCaliforniaStateClearingHouse(0%)
ApprovedandadoptedCEQA/NEPAdocumentation
Notyetbegun
Task8:Permitting Determinationofandpreparationofnecessarypermits(0%)
EncroachmentPermit,NPDESDischargePermit,Railroadcrossingpermit
Notyetbegun
Category(d):Construction/ImplementationTask9:ConstructionContracting
ThefollowingactivitiesmusttakeplaceforBidPackages1,2,3,and4:Bidopening(0%),Holdpre‐bidmeeting(0%),Evaluate
Advertisementforbids,Pre‐bidmeeting,ContractAward
Notyetbegun
GreaterLosAngelesCountyRegion Attachment4
PomonaBasinRegionalGroundwaterProject WorkSummary
IRWMImplementationGrantProposal July2014Proposition84,Round3DroughtSolicitation 4‐28
Task DescriptionofWorkCompleted,InProgressorToBeCompletedforTask(listedas%Complete)
Deliverables Status
bids(0%),Awardcontract(0%)Task10:Construction Subtask10.1:MobilizationandSitePreparation
ThefollowingactivitiesmusttakeplaceforBidPackages1,2,3,and4:Mobilization(0%)SitePreparation(0%)
Notyetbegun
Subtasks10.2:ProjectConstruction
BidPackage#1‐PWRJointWaterLineImprovements:a. Fabricationandprocurementofmaterials.(0%)b. Installation/implementationofthefollowing:
OldBaldysiteexcavationandshoring(0%) Install60”valve(0%) Install8”bypasspiping,flowcontrolvalve,
flowmeter,andvault(0%) Durwardsiteexcavationandshoring(0%) Install54”valve(0%) Install18”bypasspiping,flowcontrolvalve
andflowmeter(0%)BidPackage#2‐DurwardWellInstallationc. Installnewwell,pump,andmotor(0%)BidPackage#3‐DurwardWellEquippingandConnection:d. Constructwellhousestructure(0%)e. MechanicalworkincludingInstalldisinfection
system(0%)f. Electricalworkincludinginstallationofpowerand
controlfacilitates(0%)g. Paving(0%)BidPackage#4‐OldBaldyWellConnection:h. Fabricationandprocurementofmaterials.(0%)i. Installation/implementationofthefollowing:
Installyardpipingimprovements(0%) Install2,400feetof24”pipelineto
DurwardWellSite(0%) Completeinstallationofpowerandcontrol
facilitates(0%)
Notyetbegun
Subtasks10.3:PerformanceTestingandDemobilization
DevelopMonitoringPlan(0%)ThefollowingactivitiesmusttakeplaceforBidPackages1,2,3,and4:PerformanceTesting(0%),Demobilization(0%)
ProjectPerformanceMonitoringPlanandperformancetestingresults
Notyetbegun
Task11:EnvironmentalCompliance/Mitigation/Enhancement
Notapplicable Notapplicable Notapplicable
Task12:ConstructionAdministration
ProvidedbyPBWAand/oritsconsultant:ConstructionManagement(0%),Constructionprogressreporting(0%),HoldProgressMeetings(0%)ReviewShopDrawings(0%),Invoicing(0%)ProduceAs‐BuiltRecordDrawings(0%)
Invoices,shopdrawings,asbuiltrecorddrawings,sitephotos,As‐BuildRecordDrawingscompletioncertificate
Notyetbegun