grab your partner and let’s dance · 1.3. notice of change (noc). upon concurrence of the...
TRANSCRIPT
9/11/2019
GRAB YOUR PARTNER AND LET’S DANCETxDOT and Contractor Partnership
9/11/2019
TxDOT and Contractor Partnership
TxDOT and contractor are joint co-permittees on projects for the Construction General Permit (CGP), TPDES General Permit TXR150000. For construction projects that are authorization under the CGP
– TxDOT is the Primary Operator with Control Over Construction Plans and Specifications including the ability to make modifications to those plans and specifications;
– The Contractor is the Primary Operator with Day-to-Day Operational Control of activities at the construction site that are necessary to ensure compliance with the Stormwater Pollution Prevention Plan (SWP3) for the site
Special Provision 007-004, Special Provision 506-004
2
9/11/2019
Communicating Environmental Requirements
Construction project plans
Environmental requirements are reviewed and communicated during the preconstruction for the construction project with the TxDOT District Environmental Quality Coordinator (DEQC), contractor, superintendent, and the Contractor Responsible Person Environmental (CRPE)
TxDOT: Construction Contract Administration Manual (CCAM), Chapter 3, Section 4
3
9/11/2019
Managing Environmental Requirements During Construction
Contract management process
Construction Project Inspections
– TxDOT performs SWP3 inspection, provides contractor report, documents necessary corrective action, and validates actions are completed within established priority time
– TxDOT and contractor responsible person environmental (CRPE) perform join inspections using the construction stage gate checklist
4
9/11/2019
Panel Discussion
Preconstruction Meeting
Managing ENV requirements during construction
5
9/11/2019
Pharr Example
6
9/11/2019
EMS COMMUNICATIONS 101 FOR U2Communicating EMS Best Practices
9/11/2019
EMS POLICY
8
9/11/2019
Communications
Both TxDOT and Contractor and subcontractor employees involved in soil disturbing activities are required to take the “Environmental Management System Awareness” training
The course communicates TxDOT’s commitment to the environment and the EMS policy
The EMS policy is posted on construction site boards and communicated in meetings
Special Provision 506-004
9
9/11/2019
Project Planning, Design, Construction, and Maintenance Summit
Districts conduct Summit meetings once per fiscal calendar year
Meetings are attended by individuals from district and or division from project planning, design, construction and maintenance
Summit meetings allow districts to have a discussion on construction projects, and identify best practices that can be incorporated in future projects
Identify need for procedural changes in the district or divisions that can be incorporated into future projects
10
9/11/2019
Panel Discussion
General environmental communications to employees
Summit Meetings
11
9/11/2019
San Antonio
12
9/11/2019 13
2018 Revisions To SWP3 Weekly Monitoring Form 2118 (Page 2)
9/11/2019
Storm Water “Working” Plans
14
SWP3 Working Plans: Installation and removal dates of BMP’s
9/11/2019 15
No. 5 (of Top Ten List) – Overall Housekeeping Issues - Scattered Waste Piles
9/11/2019
TxDOT districts
16
Dallam Sherman Hansford Ochiltree Lipscomb
Hartley Moore Roberts Hemphill
Oldham Potter Carson Gray Wheeler
Deaf Smith Randall Armstrong DonleyCollings-worth
Parmer Castro Swisher Briscoe Hall
Bailey Lamb Hale Floyd Motley
Dickens King KnoxHockleyLubbock
Crosby
GarzaLynnTerryYoakum
Gaines Dawson Borden Scurry Fisher Jones
Kent Stonewall HaskellThrock-morton
Baylor
Wilbarger Wichita
WICHITAFALLS
Clay
Archer
YoungJack
Howard Mitchell NolanTaylor Callahan Eastland
Glasscock Sterling Coke Runnels
ReaganIrion
Cooke Grayson Fannin
Lamar
Delta
Red RiverPARIS
Bowie
Wise Denton CollinHunt Hopkins
RainsWood Upshur
Marion
Cass
Titus
Mor
ris
Camp
ATLANTA
Harrison
Smith
VanZandt
Henderson TYLER
Rusk Panola
AndersonCherokee
Freestone
DallasDALLAS
Rockwall
Palo Pinto
Parker Tarrant
Shelby
SabineHoustonLUFKIN
Angelina
TylerPolk
Trinity
Jasp
er
New
ton
SanJacinto
Walker
Leon
Navarro
Ellis
Hardin
FORTWORTH
Erath
Hood Johnson
Hill
BosqueMc
LennanHamilton
Coryell
Bell
Falls
WACO
RobertsonMadison
MilamBrazos
Grim
es
Burleson
BRYAN
WashingtonLee
Austin
FayetteHarris
Montgomery Liberty
BEAUMONTOrange
Jefferson
ChambersHOUSTON
FortBend
Brazoria
Matagorda
Wharton
Colorado
LavacaGonzales
Dewitt
YOAKUM
Jackson
Victoria
Calhoun
Goliad
Bee Refugio
Karnes
LiveOak
JimWells
SanPatricio
Nueces
CORPUSCHRISTI
Kleberg
Kenedy
Willacy
Hidalgo
BrooksJim
HoggZapata
Starr
PHARR
Duval
Webb
LAREDO
La SalleDimmit
Zavala Frio Atascosa
McMullen
Guadalupe
Wilson
Bexar
MedinaUvalde
Real Bandera
Kerr
Kendall
Gillespie Blanco
Kinney
SANANTONIO
Edwards
Sutton Kimble
Mason LlanoBurnet
Williamson
Travis
AUSTIN
BastropHays
CaldwellComal
Brown Comanche
BROWNWOOD
Coleman
Mills
McCulloch
San Saba Lampasas
Concho
Menard
SANANGELO
Schleicher
TomGreen
Andrews Martin
Midland
Pecos
Ector
CraneWard
WinklerLoving
Crockett
Val Verde
Upton
Terrell
ReevesCulberson
Jeff Davis
Brewster
Presidio
Hudspeth
El Paso
EL PASO
ODESSA
LUBBOCK
AMARILLO
ABILENE
Cottle Foard
CHILDRESS
Fran
klin
Cameron
9/11/2019
BACKUP SLIDES
9/11/2019
Communication Tools
18
Optional page
9/11/2019
Special Provision to Item 7, SP007-004
19
Section 7.7.2., “Texas Pollutant Discharge Elimination System (TPDES) Permits and Storm Water Pollution Prevention Plans (SWP3),” is voided and replaced by the following:
7.2. Texas Pollution Discharge Elimination System (TPDES) Permits and Storm Water Pollution Prevention Plans (SWP3).
7.2.1. Projects with less than one acre of soil disturbance including required associated project specific locations (PSL’s) per TPDES GP TXR 150000. No posting or filing will be required for soil disturbances within the right of way. Adhere to the requirements of the SWP3.
7.2.2. Projects with one acre but less than five acres of soil disturbance including required associated PSL’s per TPDES GP TXR 150000. The Department will be considered a primary operator for Operational Control Over Plans and Specifications as defined in TPDES GP TXR 150000 for construction activity in the right of way. The Department will post a small site notice along with other requirements as defined in TPDES GP TXR 150000 as the entity of having operational control over plans and specifications for work shown on the plans in the right of way.
The Contractor will be considered a Primary Operator for Day-to-Day Operational Control as defined in TPDES GP TXR 150000 for construction activity in the right of way. In addition to the Department’s actions, the Contractor will post a small site notice along with other requirements as defined in TPDES GP TXR 150000 as the entity of having day-to-day operational control of the work shown on the plans in the right of way. This is in addition to the Contractor being responsible for TPDES GP TXR 150000 requirements for on- right of way and off- right of way PSL’s. Adhere to all requirements of the SWP3 as shown on the plans. The Contractor will be responsible for Implement the SWP3 for the project site in accordance with the plans and specifications, TPDES General Permit TXR150000, and as directed.
9/11/2019
Special Provision to Item 7, SP007-004
20
7.2.3. Projects with 5 acres or more of soil disturbance including required associated PSL’s per TPDES GP TXR 150000.
The Department will be considered a primary operator for Operational Control Over Plans and Specifications as defined in TPDES GP TXR 150000 for construction activities in the right of way. The Department will post a large site notice, file a notice of intent (NOI), notice of change (NOC), if applicable, and a notice of termination (NOT) along with other requirements per TPDES GP TXR 150000 as the entity having operational control over plans and specifications for work shown on the plans in the right of way.
The Contractor will be considered a primary operator for Day-to-Day Operational Control as defined in TPDES GP TXR 150000 for construction activities in the right of way. In addition to the Department’s actions, the Contractor shall file a NOI, NOC, if applicable, and NOT and post a large site notice along with other requirements as the entity of having day-to-day operational control of the work shown on the plans in the right of way. This is in addition to the Contractor being responsible for TPDES GP TXR 150000 requirements for on- right of way and off- right of way PSL’s. Adhere to all requirements of the SWP3 as shown on the plans.
9/11/2019
Special Provision to Item 506, SP506-004
21
Item 506, “Temporary Erosion, Sedimentation, and Environmental Controls,” of the Standard Specifications is amended with respect to the clauses cited below. No other clauses or requirements of this Item are waived or changed.
Article 506.1., “Description.” The second paragraph is voided and replaced by the following.
Contractor is considered primary operator to have day-to-day operational control as defined in TPDES GP TXR150000.
1.1. For projects with soil disturbance of less than 1 acre, no submittal to TCEQ will be required but Contractor will follow SWP3. For projects with soil disturbance of 1 acre to less than 5 acres a small site notice will be posted at the site. For projects with soil disturbance of 5 acres or more a notice of intent (NOI) is required and a large site notice posted at site. Postings will be in accordance with TPDES GP TXR150000. Postings not associated with project specific locations will be in same location as Department’s postings.
1.2. Notice of Intent (NOI). Submit a NOI, if applicable, with the TCEQ under the TPDES GP TXR150000 at least 7 days prior to commencement of construction activities at the project site. Provide a signed copy to the Engineer and any other MS4 operators at the time of submittal. The Department will submit their NOI prior to contractor submission and will provide a copy for Contractor’s use in completing the Contractor’s NOI form. 1.3. Notice of Change (NOC). Upon concurrence of the Engineer, submit a NOC, if applicable, to the TCEQ within 14 days of discovery of a change or revision to the NOI as required by the TPDES GP TXR150000. Provide a signed copy of the NOC to the Engineer and any other MS4 operators at the time of submittal.
1.4. Notice of Termination (NOT). Upon concurrence of the Engineer, submit a NOT, if applicable, to the TCEQ within 30 days of the Engineer’s approval that 70% native background vegetative cover is met or equivalent permanent stabilization have been employed in accordance with the TPDES GP TXR 150000. Provide a signed copy of the NOT to the Engineer and any other MS4 operators at the time of submittal.
9/11/2019
Special Provision to Item 506, SP506-004
22
Section 506.3.3., “Training,” is supplemented by the following:
Training is provided by the Department at no cost to the Contractor and is valid for 3 yr. from the date of completion. The Engineer may require the following training at a frequency less than 3 yr. based on environmental needs:
� “Environmental Management System: Awareness Training for the Contractor” (English and Spanish) (Approximate running time 20 min.), and � “Storm Water: Environmental Requirements During Construction” (English and Spanish) (Approximate running time 20 min.).
The contractor responsible person environmental (CRPE), alternate CRPE designated for emergencies, Contractor’s superintendent, Contractor, and subcontractor lead personnel involved in soil disturbing or SWP3 activities must enroll in and complete the training listed below and provide the certificate of completion to the Engineer before performing soil disturbing or SWP3 activities on the project. Training is provided by a third party and is valid for 3 years from the date shown on the Certificate of Completion. Coordinate enrollment as prescribed by the Department and pay associated fees for the following training:
� “Revegetation During Construction” “Construction General Permit Compliance,” and Construction Stage Gate Checklist (CSGC).”
Training and associated fee will not be measured or paid for directly but are subsidiary to this Item.
9/11/2019
District Communication
Communicating EMS Information Best Practices throughout TxDOT, district, and contractor
Project Planning, Design, Construction, and Maintenance Summit Meetings
TxDOT: Environmental Management System Manual, Chapter 3, Section 10
23