  • 8/2/2019 GR Block Due to Incoming Certificate

    1/5

    GR block due to incoming certificate

    by Tanuj on Sun Aug 29, 2004 1:57 am

    Hi everyone,

    I have a question. I want the incoming inspection process to work so that GR cannot be done

    if the certificate is not received. So in customizing i created a control key z001 for cert

    required.

    In the material master, I set QM procurement active and entered the control key and a

    customized cert type. In this cert type, I have checked the following options in customizing.

    - Cert for each PO item is checked

    - Cert per GR item is checked

    - Cert check required is checked

    - In control without cert, I have given "With lot: error message, without lot: error message" ,

    because I want the GR not to happen if the cert is not received, with or without the

    inspection lot.

    Before GR, once the cert is received, then I create a cert record in QC51 for the purchase

    order, with Cert. status "Certificate filed and Inspected" and the appropriate Cert. receipt

    date.

    During GR, I set the Cert Received field to "Yes" under purchase order data. But it is still not

    allowing GR. It says "an insp. cert is required".

    When I checked the long text of this error, it said that u must create a record for the

    purchase order with status "cert recd and stored" ... but I already did that in QC51.

    Then why is the GR still being blocked. The requirement is to block the GR and not to confirm

    the receipt during UD. What must I do? Please help.

    Tanuj.

    Tanuj

    Posts: 859

    Joined: Fri Nov 14, 2003 10:22 pm

    T

    o

  • 8/2/2019 GR Block Due to Incoming Certificate

    2/5

    p

    by JPS on Mon Aug 30, 2004 9:32 am

    Hello Tanuj,

    To do so, you has to opt the same that NO GR processing if certificate doesnot come along

    with delivery in the PURCHASE ORDER.....

    That means, while creation of the Purchase order please mention the same.... see it would

    work that way !

    Enjoy your week...

    JPS

    Posts: 86

    Joined: Fri Dec 12, 2003 6:57 am

    Location: England,Germany

    T

    o

    p

    by Tanuj on Mon Aug 30, 2004 10:12 pm

    Hi JPS,

    Where do I have to make that setting, can you please elaborate? I have mentioned the

    customizing setting that I made, in my previous post. If there is anything beyond that, can

    you please tell me where I need to make that setting?

    Thanks,

    Tanuj.

    Tanuj

    Posts: 859

    Joined: Fri Nov 14, 2003 10:22 pm

    T

    o

    p

    by Guest on Tue Aug 31, 2004 2:38 am

    Good Morning,

    The setting has to be made, while creating the new Purchase order, if you go for creating new

    PO there you can find the same drop down list, I had used this while my last implementation

    on 4.6C

  • 8/2/2019 GR Block Due to Incoming Certificate

    3/5

    whatever u has made setting also required,

    Actually, presently, I am working on QNotification project and here I donot have access to

    PO... though I try to send you the screen short also....Enjoy your day !

    Guest

    T

    o

    p

    by Tanuj on Tue Aug 31, 2004 3:20 am

    Ok .. i found that in the PO. That is only the control key that is mentioned in the material

    master itself.

    Maybe I should elaborate my question. While reading SAP help it says that during GR, the MMpeople will write yes/no in the GR doc for cert. In both the cases, the GR will happen and the

    goods will move into inspection stock. In case it is a no, it will have to be confirmed during

    UD.

    Now what I wanted was a setting that in case it is a NO during GR, the GR should not happen

    and should be on hold. In case it is a yes, then it should allow the GR. Where can I make the

    relevant setting?

    Thanks,Tanuj.

    Tanuj

    Posts: 859

    Joined: Fri Nov 14, 2003 10:22 pm

    T

    o

    p

    by JPS on Tue Aug 31, 2004 4:10 am

    Hello Again,

    When I used this option, I made setting in PO that no GR creation if certificate not received,

    ....... and during execution there is a Drop down appeared in GR screen ( with yes or No ) and

    if during GR creation, we choose No, it does not allow to complete GR and this option is also

    available in QM customization, ( QM in procurement,define certificate type.... and under

    'control without certificate' )

  • 8/2/2019 GR Block Due to Incoming Certificate

    4/5

    So finally, one setting is reqd. in PO and other over above mentioned, path.... and this will

    finally, make this things happen.

    If possible, send me the screen short ofPO ( [email protected] ).... please......

    and update me, if u able to thu it.....

    Enjoy your rest of the day !

    JPS

    JPS

    Posts: 86

    Joined: Fri Dec 12, 2003 6:57 am

    Location: England,Germany

    T

    o

    p

    GR block due to incoming certificate

    by krishna_ranganath on Tue Aug 31, 2004 5:14 am

    JPS,

    Hi,

    Even I tried hard finding the answer to the query by Tanuj.The QM customisation part is clear

    & I could close that with the relevant setting in:-QM in procurement,define certificate

    type.... and under 'control without certificate' )

    as you have mentioned in your reply.But the setting reqd in the P O while P O creation is still

    UNCLEAR.

    Is this a setting at user level ie at transaction level??-which mean, every time, user need to do

    this setting while P O creation OR is this a customisation setting interface in MM component??

    to apply to all P O S' of a type??

    Pl. help clarify on this ASAP!!

    Thanks,

    Regards,

  • 8/2/2019 GR Block Due to Incoming Certificate

    5/5

    Krishna Ranganath

    31st Aug'04

    krishna_ranganath

    T

    op

    by Tanuj on Fri Sep 03, 2004 11:32 pm

    anyone?

    Tanuj

    Posts: 859

    Joined: Fri Nov 14, 2003 10:22 pm

    T

    o

    p

    by JPS on Tue Sep 07, 2004 2:20 am

    Good Morning,

    Sorry did not respond earlier, As I finding hard to test the same due to Authorization issues,

    Please give one more try with Info-Record..... Insp control...... may this time it works, and

    update in either case.