Government of the Republic of SerbiaMinistry of Construction, Transport and

Infrastructure

Single project pipeline- tool for concentrated economic development -

Pristina 25/03/2015

Page 2: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

Why Single Project Pipeline

To avoid ad hoc approach to planning preparation and implementation of infrastructure projects

To meet the necessity for strong project prioritization (developed set of criteria reflecting EU and national strategy and policy goals focusing on economic development)

To enable systematic and timely planning of resources To provide reliable basis for defining proper sequencing of

the actions To help linking investments planning and program budgeting

2

Page 3: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

Adopted by the Government (as an annex to the document National Priorities for international assistance to the Republic of Serbia for the period 2014 to 2017 with the projections up to 2020) Basis for the Single Project Pipeline. Covers energy, transport, environment and business related infrastructure. Based on two basic pillars:

• Strategic relevance of the project

• Project readiness/maturity for implementation

3

Page 4: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

Methodology development process

Comprehensive consultative process involving all relevant stakeholders (line ministries, public utility companies and public and civil society organizations etc.)

Supportive approach by and active participation of the Delegation of the European union in Serbia and the European Commission (DG NEAR)

Consultations with the International Financial Institutions and bilateral donors

Sector Working Groups (SWGs) coordinated by Serbian European Integration Office (SEIO) as a main mechanism for consultations

4

Page 5: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

1. 1. Collect existing infrastructure project ideas/proposals

2. Identify broad list of projects by completion of Project Identification Forms

3. Strategic Relevance Assessment (filtering step)

4. Short list of strategically relevant projects

5. Gap Assessment Analysis of strategically relevant projects

6. Final list of prioritized projects (to be included in ISDACON)

Project identification form (PIF)

Strategic Relevance Assessment criteria (based on PIF)

Gap Assessment Questionnaire /Gap Assessment Report

5

Page 6: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

Scoring of transport sector projects

Two phases:1.Scoring (which is not final) based on Strategic relevance criteria:•Consistency with EU, national, transport policies/strategies•Demand/supply and origin/destination factors•Relation with other transport corridor/routes•Traffic safety and security of transport•Economy systems and sectors affected by the project

6

Page 7: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

Scoring of transport sector projects

2. Final scoring based on GAP report; projects divided into 4 groups according to their degree of maturity:

Group 1 – Ready for tendering and investment realization:• Group 1a – projects with technical documentation prepared, ready

for tender preparation or tendering • Group 1b – projects with preparation of technical documentation

ongoing, and ready for tendering when it is finished Group 2 - Ready for preparation of technical documentation:• Group 2a – projects with spatial planning documentation completed

with preconditions for land acquisition in place • Group 2b – projects with gaps in spatial planning documentation with

preconditions for land acquisition still pending

7

Page 8: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

Single Project Pipelines of sectors

Transport Sector Projects (26 projects) € 5,512.50m

Waste Water Subsector Projects (17 projects) € 438.45m

Energy Sector Projects ( 39 projects) € 4,487.70m

Solid Waste Projects (15 projects) € 399.90m

Business related infrastructure projects (12 projects) € 57.95m

TOTAL € 10,896.50m

8

Page 9: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

Project Passport

Project Passports are prepared for all the projects from the single project pipelines on the basis of the inputs from the Gap Assessment Reports.

Project Passport is an overview of all the steps which should be done in the course of project preparation and implementation, projects’ tentative costs and the responsible institution.

Project passport ensures that all the steps are considered in a realistic time perspective.

9

Page 10: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

Project Passport example

10

Highway Belgrade – South Adriatic (E-763) Beograd-Boljare-Podgorica-Bar Comments Institution

responsible

Year 1 Year 2 Year 3 Year 4 Year 5 Indicative cost

estimation (EUR)Indicative source of

financingQ1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Beograd - Obrenovac Length of the route 17.6 km. Under negotiation with concessionaire Ministry of Transport,

Roads of Serbia 170.000.000 Concession

Obrenovac - Preljina Length of the route 103.07 km. Under construction Koridori of Serbia 700.000.000 Republic of Serbia, Republic of

China, Republic of AzerbaijanPreljina - Pozega Length of the route 30.96 km Under negotiation with concessionaire Ministry of Transport,

Roads of Serbia 286.000.000 Concession

Pozega - Boljare Length of the route 107 km

1.830.857.578

Preparation of Spatial Planning documentation Infrastructure Corridor Special-Purpose Spatial Plan Infrastructure Corridor Special-Purpose Spatial Plan

Pozega-Boljare. Decision for provision approved (Official Gazette of RS, No. 3/11). Under preparation

Government of Serbia

9.150.000

Ministry of Transport, Roads of Serbia

Municipal spatial plan As the Infrastructure Corridor Special-Purpose Spatial Plan will be used for issuance of Location requirements it is not conditional to update Municipal Spatial Plans, General Urban Plans and General Regulation Plans for implementation of this project, although these plans has to be justified with higher level spatial plans.

General urban plan

General regulation plan

B Not necessary Urban design Not required Elaborate on Expropriation for locations needed Elaborate should be prepeared PE Roads of Serbia Decision on Public Interest Request for Public interest declaration to be submitted Government of Serbia Land acquisition Not started Government of Serbia PE Roads of SerbiaTOTAL Preparation of technical documentation

Preparation of pre-feasibility study Pre-feasibility Study for highway E-763 Belgrade-South Adriatic Area, Section III Pozega-Montenegrin border

PE Roads of Serbia

General designGeneral Design for highway E-763 Belgrade-South Adriatic Area, Section III Pozega-Montenegrin border

PE Roads of Serbia

Review of the General Design & Prefeasibility study State Revision Committee Site investigation PE Roads of Serbia Feasibility study (with CBA according to the EU requirements) PE Roads of Serbia 10.000.000IPA Preliminary design PE Roads of Serbia 45.000.000IPAReview of the preliminary Design & Feasibility study State Revision Committee Desin for Construction permit and technical control Technical control has to be independent PE Roads of Serbia 30.000.000IPA Environmental and Social Impact Assessment study Full EIA is compulsory per EIA legislation IPA

Scope and content application to be sent to the MinistryMinistry for Energy, development and environemntal protection

Preparation PE Roads of Serbia 5.000.000IPA

Approval approval issued by the MinistryMinistry for Energy, development and environmental protection

Permits Location requirements

Ministry of Construction, Transport and Infrastructure

Construction permit

Ministry of Construction, Transport and Infrastructure

Preparation of tender documentation and tendering procedure

This is the case if the contract is "design and build" PE Roads of Serbia

200.000IPATOTAL 90.200.000 Institutional Establishment of PIU MoT, PE Roads of Serbia TOTAL TOTAL PROJECT PREPARATION

90.200.000IPA TOTAL INVESTMENT REALISATION* 1.830.857.578 Concession SUPERVISION Supervision will lastduring project implementation/construction MoT, PE Roads of Serbia 82.300.000IPA O & M COSTS/year This is estimated cost per year MoT, PE Roads of Serbia 2.142.000 Boljare - Podgorica - Bar Length of the route 183 / 167 km.

Republic of Montenegro Government of Montenegro

1.950.000.000 Podgorica - Granica sa Albanijom Length of the route 000 km.

Republic of Montenegro Government of Montenegro

Page 11: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

National Investment Committee

Provides political support to operationalisation of the single project pipeline

Its recommendations and actions are based on the Single Project Pipeline.

Represents key platform for the discussion on critical issues and steps related to the specific projects from the single project pipeline.

Enables synergy between various sources of financing (budget, loans, and grant funds) with the aim to achieve substantial leverage effect.

11

Page 12: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

National Investment Committee (NIC)

12

EC , IFIs, bilateral partners

SEIO is a technical

secretariat of NIC

Sector Working Groups

Page 13: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

Key considerations ahead:

Single project pipelines are updated annually

Joint Assistance to Member States and Candidate countries provided by European Commission/EIB/EBRD (JASPERS) and Project preparation facility (PPF) assistance is essential for quality project preparation and mirroring/practicing EU-ESI funds principles

Synergy between EU funds (IPA national, IPA regional-Western Balkans Investment Framework), International Financial Institutions and budget resources coordinated by NIPAC

Promotion of PPP as a modality of financing of infrastructure projects

Proper reflection of the Single project pipeline methodology in the Budget System Law

13

Page 14: Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure Single project pipeline - tool for concentrated economic development

Thank you!