Good Practice of Training Course Provided by
Vendor Company
I. Introduction of Haiyang Nuclear Power
Project
II. Introduction of Training Courses
Provided by the NI Supplier
III. Good Practice
Shandong Nuclear Power Company (SDNPC) , a holding subsidiary company of
China Power Investment Corporation (CPI), was founded in September of 2004.
As the owner of Haiyang Nuclear Power Project, SDNPC is fully responsible for
the preparation, construction, operation and nuclear safety management of the
Project.
Introduction of Haiyang Nuclear Power Project
Organization of SDNPC
Pla
nn
ing &
Project
Con
trol D
ep
t.
Safety &
Qu
alit
y
Assu
ran
ce D
ep
t.
Desig
n M
an
agem
en
t
Dep
t.
Con
stru
ctio
n
Man
agem
en
t D
ep
t.
Com
mercia
l &
Con
tract D
ep
t.
Procu
rem
en
t D
ep
t.
Com
mis
sio
nin
g &
Start-u
p M
an
agem
en
t
Dep
t.
Prod
uctio
n P
lan
nin
g
Dep
t.
En
gin
eerin
g D
ep
t.
Logis
tic
s D
ep
t.
Gen
eral
Ad
min
istratio
n D
ep
t.
( L
egal A
ffair
es D
ep
t.)
Hu
man
Resou
rces
Dep
t.
(S
ocia
l In
su
ran
ce
Cen
ter)
Fin
an
cia
l Dep
t.
Au
dit
Dep
t.
Corp
orate C
ult
ure
Dep
t.
Executives
SDNPC
Train
ing D
ep
t.
Main
ten
an
ce D
ep
t.
Healt
h P
hysic
s D
ep
t.
D
iscip
line I
nvestig
atio
n
an
d S
up
ervis
ion
Dep
t.
Op
eratio
n D
ep
t.
22 departments currently.
It is planned to build 6 PWR units with a capacity of 1000MW each, and has
reserved space for another 2 units.
Haiyang Phase Ⅰ Project is planned to build 2 AP1000 units, with a capacity of
1250MW each. The first concrete of Unit 1 Nuclear Island was poured in Sep.
2009.
SDNPC was permitted to start the project preparation of Unit 3 and 4 in Mar. 2009.
Fundamental Conditions of the Project
Site Preparation
1983 2002 2008-7-29 2005-11
CPI commenced
preliminary work
……
2006-12
Unit 1& 2 approved
2009-9-23 2009-9-24 2014-6
EPT of Unit 1
AP1000 technology
determined
FCD of Unit 1
NI excavation
Finish Site
leveling
Site survey
There are 84 milestones for Phase I project. 44 of them have been completed.
The erection work of major NI systems have fully progressed. Key equipments of Unit
1 NI such as Reactor Vessel, Steam Generators, Reactor Vessel Internals, Polar Crane,
etc. have been delivered to site, and are erected or preparing for erection. RCL started
installation on 2013-2-3. Containment Vessel Top Head(CVTH) was set on 2013-3-29.
The erection work of CI systems has started. Generator Stator has been set in place.
Unit 1 is planned to begin commercial operation by end of 2014.
The civil structural construction of Unit 2 NI is in process, and CI structural
construction work has been completed. Unit 2 is planned to begin commercial
operation in March of 2016.
Current Progress
CI Design Process
The civil structure design of TB is all completed, and the construction drawings are
all issued.
Now the process system design is fixed, and drawings are almost finished.
Design progress
NI CFC drawings, except for part of I&C tubing and piping drawing, are finalized
and submitted;
CFC drawings for annex building, radwaste building and diesel generator building
are completed.
NI Design Process
Procurement and Equipment Fabrication progress
2012-7-13 Unit 1 SG A Arrived
2011-12-11 Unit 1 RV Arrived
2012-6-3 Unit 1 PRZ Arrived
2012-3-21 Unit 1 RCL Arrived 2011-11-10 Unit 1 Condenser Arrived
2012-5-21 Unit 1 Generator Arrived
Unit1 NI
CVTH has been set.
The shield wall has been constructed to
12th layer.
Construction of 135’ platform has been
finished.
Main system installation is on-going.
Construction progress
Building structure construction
is finished.
Building sealing is almost
finished.
Generator stator and rotor are set.
Condenser installation and
welding are finished.
LP Outer Casing assembly are
finished.
Installation of MT, UAT and
RAT are almost finished.
Unit 1 CI
All CV Rings set.
107’ platform of CV internal structure is on
going.
The 2th-4th layer of shield wall construction
is ongoing.
90% of Auxiliary 82’6”floor is finished.
In 1,2&3 areas of Annex building, main
structure below 135’ is finished.
Unit 2 NI
Unit 2 CI
Turbine building structure is
finished.
Turbine base concrete placement
is completed.
Turbine Building Main Crane is
available.
Achieve the following construction goal of 2013.
Goals for Unit 1: NI major equipments and CVTH installation; Shielding wall
and dome construction complete; Main Control Room available; RCS turnover to
commissioning; CI construction and erection complete.
Goals for Unit 2: Reactor Vessel, SG fabrication complete; Containment Building
internal structural construction complete; Auxiliary Building structure roof
sealing; Bulk materials erection complete 50%; CI civil construction complete
and erection work complete 50%.
Goal for 2013
Unit 1 NI
Dome
construction
complete
Main equipments
installed
Shielding
Wall
construction
complete
Main Control Room available;
RCS turnover to commissioning;
Shielding
Wall
construct to
14th Layer
Containment Building internal structural
construction complete; Bulk materials erection
work complete 50%;
Unit 2 NI
Prospect by the end of 2013
Unit 1 CI
Turbine
ready for
Gas Inlet
turbine
bucking-
cylinder
CI construction and erection complete CI building complete; erection complete
50%
Generator
arrived
Unit 2 CI
From June 2011 to now, the NI supplier conducted 8 groups of classroom training on
Haiyang site. 219 trainees participated in the training.
Training Programs on Haiyang Site
Group Title of Training Time Duration
(Day) Number of
trainees
1
RO/SRO AP1000 System Classroom Training 2011.6-2011.10 90 43
RO/SRO Simulator Training 2013.7-2013.10 80 36
Shift Technical Advisor (STA) Training TBD 8 12
2 RO/SRO AP1000 System Classroom Training 2011.11-2012.3 90 36
RO/SRO Simulator Training 2013.10-2014.2 80 36
3 Instrumentation and Control (I&C) Technicians Classroom Training 2012.3-2012.7 85 20
4 Mechanical and Electrical Maintenance Technicians Classroom Training
2012.3-2012.4 30 30
5 Chemistry Technicians Classroom Training 2012.3 15 20
6 Station Nuclear Engineers Classroom Training 2012.7-2012.9 55 10
7
AP1000 Operation Supervision staff Classroom Training, including QA/QC staff, Performance Reliability Engineers, Safety Assessment Engineer, Regulatory Compliance Engineer, Radiation protection and health physics staff
2012.5-2012-6 30 30
8
AP1000 Operation and Maintenance Support Staff Classroom Training, including System /Component / Maintenance Engineers, Scheduling Engineers, Program Engineers, Design/Engineering Engineers
2012.3-2012.4 40 30
Two batches of technical elites from SDNPC, 59 persons in total, took part in the Job
Shadow Training held in the US operating nuclear power stations as listed in the
table below.
Job Shadow Training in US Nuclear Power Stations
Group Places of Training Time of
Training
Duration
(Week)
Number
of
Trainees
Jobs for Shadow Training
A
Westinghouse,
V.C.Summer Nuclear
Station,
Seabrook Nuclear
Station,
McGuire Nuclear
Station
2010.9-
2010.11 10 29
Plant Manager(1), RO/SRO(11), I&C(4), Electrical
Maintenance(3), Mechanical Maintenance(4),
Chemistry(1), Training Management(1),
System/Equipment/Maintenance(1), QA/QC(1),
Station Nuclear Engineer(1), Safety Assessment(1).
B
Westinghouse,
V.C.Summer Nuclear
Station,
Alvin W. Vogtle
Nuclear Station
2011.1-
2011.3 10 30
Plant Manager(1), RO/SRO(12), I&C(4) ,
Electrical Maintenance(3), Mechanical
Maintenance(4), Radiation Protection and Health
Physics(1), Program Management(1), Performance
Reliability (1), Scheduling (1), Training
Management(1), Design/Engineering(1).
From May 2010 to now, 55 persons from SDNPC participated in 15 equipment
training activities held in the Vendor Factories, amounting for 37 man·months.
Equipment Vendor Factory Training
No. Title of Training Place of Training/
Equipment Vendor
Time of
Training
Duration
(Week)
Number of
Trainees
1 Variable Frequency Drive
Maintenance
Siemens Energy & Automation
Inc. 2010.5 2 2
2
Reactor Coolant Pump Switchgear
Maintenance and Reactor Trip
Breaker Maintenance
Eaton Corporation &
Westinghouse Repair,
Replacement and Automation
System(RRAS)
2010.6 4 2
3 Pressurizer Spray Valve Maintenance Fisher Controls International
LLC 2010.7 2 2
4 Main Steam Relief Valve
Maintenance Control Components, Inc.(CCI) 2010.8 2 2
5 Pressurizer Safety Valve and Main
Steam Safety Valve Maintenance Tyco Valves & Controls 2010. 9 4 2
6 Main Feedwater Isolation and Main
Steam Isolation Valve Maintenance Flowserve: Raleigh, NR 2010.10 4 2
7 Main Feedwater Control Valve
Maintenance Control Components, Inc.(CCI) 2011.1 2 2
Equipment Vendor Factory Training
No. Title of Training Place of Training/
Equipment Vendor
Time of
Training
Duration
(Week)
Number of
Trainees
8 Supplier's Ovation and Advant
Training (session 1) Westinghouse, Pittsburgh, PA 2011.3 2 9
9 Ovation on-the-job Training Westinghouse, Pittsburgh, PA 2011.4 4 5
10 Common Q On-the-Job Training Westinghouse, Pittsburgh, PA 2011.5 4 5
11 Supplier's Ovation and Advant
Training (session 2) Westinghouse, Pittsburgh, PA 2011.11 2 9
12 Squib Valve Maintenance Training SPX: McKean, PA 2012.1 2 2
13 SMS equipment manufacturer's
factories on-the-job training
Westinghouse's training
Facility in New Stanton,
Pittsburgh, PA 2012.2 2 4
14 DAS equipment manufacturer's
factories on-the-job training WISCO's training facility,
Pittsburgh, PA 2012.2 2 4
15 Reactor Coolant Pump Maintenance
and Operation EMD: Cheswick, PA 2012.3 4 3
16 Refueling Equipment Training PaR; Westinghouse TBD 4 8
3.1 Full Preparation
Organization Preparation
SDNPC establishes a complete training system. The NI supplier delivers training
in its scope; the manager of SDNPC Training Department takes responsibility for
these training according to the NI Supply Contract and assigns a program
manager responsible for the interface management and coordination on the side
of SDNPC.
The NI Supplier assigns a program manager responsible for the interface
management, organizing and managing the training activities according to the NI
Supply Contract.
3.1 Full Preparation
Organization Preparation
President of SDNPC
Manager of
Training Dept.
VP in charge of
Training
Simulator
Division
Teaching
Division
Training
Management
Division
Instructors
Training
Management
Engineers
Training
Implementation
Training
Evaluation
The NI
Supplier
Feedback
Support
3.1 Full Preparation
Personnel Preparation
SDNPC Trainees Preparation
English familiarization and improvement
Pre-study related materials and documents
Domestic experts delivered lectures on the topics related to the training
subjects
Instructor Preparation
The NI Supplier qualified and assigned 33 instructors for the 8 groups of
classroom training conducted on Haiyang site.
SDNPC reviewed the resumes of all instructors before training according to
the qualification requirements listed in the NI Supply Contract.
3.1 Full Preparation
Training Materials Preparation
The Supplier developed training materials and submitted all developed training
materials to the Purchaser for two cycles of review and comment in the
sequence as: the Supplier developing Training Materials → SDNPC
Reviewing→the Supplier revising→SDNPC Reviewing again→the Supplier
revising and finalizing the materials.
3.1 Full Preparation
Procedures Preparation
The supplier develops 4 training management procedures.
Title of Procedures
1 AP1000 Job And Task Analysis Procedure
2 AP1000 Training Material Design & Development Procedure
3 AP1000 Conduct of China Written Examinations
4 AP1000 China Training Implementation Quality Plan
SDNPC develops 38 training management procedures.
SDNPC developed training program management plans for the 8 groups of
classroom training on Haiyang site and the 2 batches of job shadow training in
the US nuclear power stations, which specified the organization, responsibilities
and management requirements for training programs
3.1 Full Preparation
Documents and Training Facilities Preparation
The supplier printed training material for the class, while SDNPC printed other
related documents such as drawings, etc.
When the 8 groups of classroom training were conducted on Haiyang site, the
training center and facilities hadn’t been ready for use yet, however, SDNPC
overcame difficulties and made great efforts to prepare four classrooms (each
room seats 40 persons) with required training equipment and appliances special
for the eight groups of training in advance.
SDNPC provided offices for instructors.
3.2 Thorough Communication
Quarterly Video-conference/face-to-face meeting at management level before
training
June 2008 – April 2010, quarterly video-conferences were held between
SDNPC and the NI supplier to coordinate training programs.
June 2008 – July 2010, face-to-face coordination meetings were held both in
China and the US.
3.2 Thorough Communication
Communication among training management, instructors and students during
training
Good communication between instructors and students
SDNPC training management always kept communication with instructors and
students to know more about their needs and feedback.
Good communication among students
3.2 Thorough Communication
Observation
SDNPC senior management, manager of Training Department and other
training management personnel observed the training and filled classroom
training observation/feedback form of the supplier.
SDNPC training management personnel exchanged with instructors and
students in a timely manner about the feedbacks and recommendations based on
the observation forms to improve the training effect.
3.2 Thorough Communication
Analysis of students examination results
Instructor of the supplier analyzed students’ examination results after each exam
based on its training management procedures. The analysis covers pass rate of
the exam, trends of students’ examination results, the extent of students
mastering knowledge, etc.
SDNPC training management personnel communicated with instructors and the
struggling students about the existing problems, weakness and improvement
measures.
As for students who failed three times successively, instructors and SDNPC
training management held special academic review meeting to discuss and
analyze the causes of students’ failure and measure to be taken to help students.
3.3 Feedback, Evaluation and Improvement
Collected feedback about training effect from instructors and students.
Developed monthly report and final report for each training program. Every student
wrote a summary report upon the completion of the training.
SDNPC specified the good practice and weakness in the report, and put forward
improvement recommendations as well.
Keep improvement to continuously perfect training effect.
Trainees of the above-mentioned training programs provided by the
NI supplier were satisfied with the training. Meanwhile, the training
management from both SDNPC and the NI supplier established a good
communication system, which formed a foundation for future further
cooperation.