global construction 8 critical ways the new jct · pdf fileglobal construction 8 critical ways...
TRANSCRIPT
GLOBAL CONSTRUCTION
8 CRITICAL WAYS THE NEWJCT 2016 WILL CHANGECONSTRUCTION CONTRACTS New simplified payment provisions, insurance amendments and other updated provisions are welcome additions.
THE JCT 2016 UPDATE
Each update to JCT (Joint Contracts Tribunal) brings significant changes to standard
contract terms and the 2016 edition is no different. Now that the dust has settled on the
newly published 2016 suite of contracts, it is worth reflecting on the changes that these
standard contracts will bring about for employers and contractors alike.
A reminder of the contract families included in the JCT 2016 editions:
1. Intermediate Building Contract family released on 7 December 2016
2. Collateral Warranties (CWa/F, CWa/P&T, SCWa/F, SCWa/P&T, SCWa/E) released on
21 November 2016
3. Standard Building Contract family on 4 November 2016
4. Design and Build Contract family on 23 September 2016
5. Minor Works Building Contract family on 24 June 2016
Some key changes compared to the JCT 2011 edition - which are to be welcomed - are
revamped insurance amendments and simplified payment provisions intended to make
the notice requirements under the Housing Grants, Construction & Regeneration Act 1996
more understandable.
I will be referring mainly to the new JCT Design & Build, (arguably the most widely used
in the JCT contract family) in this article which will outline the most significant updates.
2
I. CHANGES FOR PAYMENTThe new JCT Design & Build 2016 payment provisions
have been simplified to ensure that the contract payment
mechanism is more easily understood. Section 4 for the
Payment provisions have now been separated into the
following eight sub-sections;
1. Contract Sum and Adjustments under clause 4.1
to 4.3
2. Taxes under clause 4.4 to 4.5
3. Payments and Notices - general provisions under
clause 4.6 to 4.11
4. Interim Payments - calculation of sums due under
clause 4.12 to 4.14
5. Listed Items under clause 4.15
6. Retention under clause 4.16 to 4.18
7. Loss and Expense under clause 4.19 to 4.23
8. Final Statement and Final Payment under clause 4.24
I.I PAYMENTS AND NOTICES - GENERAL PROVISIONS UNDER CLAUSE 4.6 TO 4.11There have been significant policy developments
in payment terms since the 2011 edition of JCT. The
Government has set an ambitious target for the
construction industry to adhere to 30-day payment terms
and zero retentions by 2025 - part of the Fair Payment
Campaign1. In addition, the Construction Leadership
Council has updated the Construction Supply Chain
Payment Charter2. The new JCT 2016 contracts reflect
this, via the introduction of Interim Valuation Dates to give
more certainty to a defined payment date.
The Interim Valuation Dates are to be defined within the
Contract Particulars under 4.7.2 in which the “first Interim
Valuation Date is,” to be inserted and subsequent Interim
Valuation Dates are “thereafter the same day in each
month or the nearest Business Day in that month.”
1. Fair Payment Campaign
2. https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/306906/construction-supply-chain-payment-charter.pdf
3
However, if no date is included within the Contract
Particulars then the first Interim Valuation Date will be one
month after the Date of Possession.
The section for Payments and Notices - general provisions
now contains a revised payment mechanism which, if left
unamended by the parties’, states that;
1. Under clause 4.7.2 the monthly due dates will be
“7 days after the relevant Interim Valuation Date.”
2. However, under clause 4.7.3, if the Interim Payment
Application from the Contractor is received after
the due date, will be “7 days after the date of
receipt by the Employer.”
3. Under clause 4.9.1, the final date for payment of
each Interim Payment and the final payment is 14
days from its due date.
The JCT Design & Build 2016 requires that the parties
take account of Business Days (any day other than
Saturdays, Sundays and Bank Holidays) within the above
quotation from clause 4.7.2 of the Contract Particulars.
Caution should be taken, as the Interim Valuation Date
is worded under clause 4.7.2 of the Contract Particulars
as the “nearest Business Day,” which during the Easter
Bank Holidays and the Christmas period, could bring the
Interim Valuation Date forward whereas if the Contract
Particulars are amended from “nearest,” with replaced
with “next,” this could overcome this problem and adjust
the Interim Valuation Date after the retrospective Bank
Holiday. It also requires that the parties re-evaluate due
dates and Payment Notice timescales in the event of an
Interim Payment Application being received after the
Interim Valuation Date.
Parties need to ensure that timescales for notices
and payments are adhered to avoid parties being
able to implement ‘smash and grab adjudication’, the
results of which saw an epidemic of cases throughout
2014 and 2015.3 Although JCT Design & Build 2016
makes this no more of a requirement than the
previous 2011 edition.
The monthly payment procedure also continues
after practical completion, during the Rectification
Period, as opposed to the JCT 2011 edition which
changed to payments at two month intervals after
practical completion.
3. Harding t/a MJ Harding Contractors v Paice and Springall [2014] EWHC 3824 (TCC); ISG Construction Ltd v Seevic College [2014] EWHC 4007 (TCC); Galliford Try Building v Estura Ltd [2015] EWHC 412 (TCC) and Caledonian Modular Ltd v Mar City Developments Ltd [2015] EWHC 1855 (TCC)
4
I.II CHANGES FOR PAYMENT OF LOSS AND EXPENSE UNDER CLAUSE 4.19 TO 4.23In my opinion, the most significant change is the updated
wording of the loss and expense provisions under the JCT
Design & Build 2016 which now incorporates a specific
timescale for the Employer to notify the Contractor of the
ascertained value of the loss and expense.
This has been incorporated to influence a prompt
assessment of loss and expense and again, is likely to
have been influenced by the Fair Payment Campaign.
The Contractor is required to provide their “initial
assessment,” after notification “as soon as reasonably
practicable,” under clause 4.20.1 and under clause 4.20.3
to provide an updated assessment at monthly intervals.
Under clause 4.20.4, the Employer has to ascertain the
loss and expense claim “within 28 days of receipt,” and
“14 days of each subsequent update,”. The amounts then
ascertained under clause 4.20, in accordance with clause
4.22 is “added to the Contract Sum.”
As seen within NEC3 the principals of undertaking an
initial assessment of the loss and expense which is then
developed and updated over time (as JCT 2016 states,
monthly) and once the full value is ascertained allows the
parties to progress with claims as and when they occur,
rather than the end of the project.
This is a different approach from the previous JCT
editions which seemed to delay the ascertainment of
loss and expense until it had been clearer whether the
Contractor had actually been delayed or disrupted
under the Relevant Matter and the final effect was
actually known.
It appears that the wording suggests that it is a condition
precedent to payment of loss and expense for the
Contractor to notify and provide monthly updates under
clause 4.20. However, I am sure, this will be later debated
as it is not clear from the accompanying JCT guidance
that the intention was to create a condition precedent.
Furthermore, there appears to be no sanction for not
complying with the specific timeframe and the wording
does not clarify whether the Employer can later contest or
adjust the ascertainment of loss and expense once awarded.
5
II. CHANGES TO THE INSURANCE SECTIONThe new JCT 2016 simplifies the insurance options and
has recognised that the insurance for a construction
contract may not fit into the JCT Options A, B and C as
seen within the 2011 edition.
Insurance Option C has been amended to include an
option for the parties to agree their own insurance
arrangements where works are being carried out within
an existing structure;
“6.3.3 Where Insurance Option C applies but a C.1
Replacement Schedule applies in lieu of paragraph C.1,
the Contractor ‘s liability and indemnity under clause 6.2
shall, in respect of loss, injury or damage to the Existing
Structures and their contents due to the causes specified
in that clause, be subject only to such limitations or
exclusions as are specified in that schedule.”
It is welcoming to see an option for the parties to agree
their own insurance arrangements where works are being
carried out in an existing structure. However, care still
needs to be taken to engage with insurance brokers early
on to ensure suitable insurance cover is obtained.
Summary of other notable changes
III. REMOVAL OF FLUCTUATIONS OPTIONSWithin the JCT 2016 edition there is updated Schedule 7
which removes Fluctuations Options B and C. However, as
confirmed within the Contract Particulars under footnote
13 for clause 4.2, 4.12 and 4.13;
“JCT Fluctuations Options B and C are no longer included
in JCT contract documents but continue to be available on
the JCT website www.jctltd.co.uk.” 4
There is also a new opportunity for the parties to agree
to a cost adjustment formula or an alternative bespoke
fluctuation calculation.
4. Can be accessed from http://www.jctltd.co.uk/docs/DB-2016-FluctuationsOptionsBC.pdf.
6
IV. CHANGES FOR PERFORMANCE BONDS AND PARENT COMPANY GUARANTEESThe new JCT allow the parties to agree the form for a
performance bond and parent company guarantee under
clause 7.3;
“The Contractor shall on the execution of this Contract
provide to the Employer whichever of the following the
Contract Particulars state as being required:
1. a performance bond or guarantee of the
Contractor’s due performance of the Contract
from a bank or other surety approved by the
Employer in an amount equal to the percentage of
the Contract Sum and for the period stated in the
Contract Particulars;
2. a guarantee by the Contractor’s parent company
identified in the Contract Particulars;
any such bond or guarantee, unless otherwise agreed
by the Employer, being substantially in the form of the
document identified by the Contract Particulars.”
Please note that there is no published JCT 2016
edition forms for performance bonds and parent
company guarantees.
V. THIRD PARTY RIGHTS AND COLLATERAL WARRANTIESIn terms of Third Party Rights and Collateral Warranties,
the main changes are the deletion of Part 2 of the Contract
Particulars and the addition of sub-contractor third party
rights. This is reflected within the JCT standard sub-
contracts which aim to reduce the possibility of the third
party rights not being amalgamated into the sub-contracts.
VI. INCORPORATION OF BIMThe updated JCT 2016, requires the parties to agree to
implement a BIM Protocol, under clause 1.1 of the Contract
Particulars. This BIM Protocol requires the project team to
prepare and include the protocol within the contract.
As per the precedence of documents within clause 1.3, the
wording has been amended so that the articles of agreement
and conditions take precedence over any BIM protocol.
Clause 1.4.6 states that “where there is a BIM Protocol or other
protocol relating to the supply of documents or information,
be deemed to include information in a form or medium
conforming to that protocol.”
VII. INCORPORATION OF THE CONSTRUCTION DESIGN & MANAGEMENT (CDM) REGULATIONS 2015The new CDM regulations 2015 were previously
an amendment under the JCT 2011 edition with an
additional published sheet. This is now fully updated and
incorporated within the JCT 2016 edition under clause 3.16
to reflect updated CDM legislation.
7
VIII. ADDED PUBLIC SECTOR SUPPLEMENT 2011 AND PUBLIC CONTRACTS REGULATIONS 2015The contracts have been updated to include the new
Public Contract (PC) regulations as standard for use
by Local Authorities and Registered Providers of
Social Housing.
Clause 8.6, termination by the Employer, refers to
corruption regulation 73(1)(b) of the PC Regulations and
clause 8.11 headed, Termination by either Party, refers to
regulations 73(1)(a) and 73(1)(c) of the PC Regulations.
The incorporation of the requirements of the Public
Contract Regulations 2015 give “provisions enabling the
contracting authority to terminate the contract where”5
1. The “contract has been subject to a substantial
modification which would have required a new
procurement procedure.”6
2. Where the Contractor “at the time of contract
award,” should have been “excluded from the
procurement procedure.”7
3. Where the contract should not have been
awarded to the Contractor in “view of a serious
infringement of the obligations under the Treaties
and the Public Contracts Directive that has been
declared by the Court of Justice of the European
Union in a procedure under Article 258 of TFEU.”8
CONCLUSION
Given the significant changes brought in with JCT 2016,
including a new payment procedure and timescales for loss
and expense, it will take time for Employers and Contractors
to adapt. Some of the changes to the 2016 edition will be
welcomed however, in practice, we are also likely see a large
number of contract amendments being introduced to reflect the
bespoke requirements of individual parties. Parties also need to
be wary when completing the Contract Particulars, particularly
the Supplemental Provisions – Part 2 which automatically
‘applies’, unless the parties opt out.
Important Notice
The views expressed in this article are those of the authors and
do not necessarily represent the views of Navigant Consulting
Inc. or any of our clients.
5. The Public Contracts Regulations 2015 – 73 (1) http://www.legislation.gov.uk/uksi/2015/102/pdfs/uksi_20150102_en.pdf
6. The Public Contracts Regulations 2015 – 73 (1)(a)
7. The Public Contracts Regulations 2015 – 73 (1)(b)
8. The Public Contracts Regulations 2015 – 73 (1)(c)
©2017 Navigant Consulting, Inc. All rights reserved. 00006604
Navigant Consulting is not a certified public accounting firm and does not provide audit, attest, or public accounting services.
See navigant.com/Licensing for a complete listing of private investigator licenses.
twitter.com/navigant
linkedin.com/company/navigant
CONTACTS
MATTHEW FINNBSc, Hons, FdSc, LLM, FCIArb, MCInstCES ,FCIOB, FRICS Managing Consultant+44 (0)20 7398 3861
navigant.com
About Navigant
Navigant Consulting, Inc. (NYSE: NCI) is a specialized, global professional services
firm that helps clients take control of their future. Navigant’s professionals apply deep
industry knowledge, substantive technical expertise, and an enterprising approach
to help clients build, manage and/or protect their business interests. With a focus
on markets and clients facing transformational change and significant regulatory
or legal pressures, the Firm primarily serves clients in the healthcare, energy and
financial services industries. Across a range of advisory, consulting, outsourcing, and
technology/analytics services, Navigant’s practitioners bring sharp insight that pinpoints
opportunities and delivers powerful results. More information about Navigant can be
found at navigant.com.