global apqp matrix

Upload: hmp90

Post on 03-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Global APQP Matrix

    1/3

    Global Quality APQP Requirements MatrixActual" status symbol

    key:

    not

    Target Actual TargetPreliminary DFMEA created for supplier

    responsible components or supplier has

    reviewed DFMEA. High RPNs have

    action plans with timing

    DFMEA reviewed and signed for

    supplier responsible components

    supplier has reviewed , DFMEA.

    High RPNs have action plans wit

    timing that meets tool kick-off dat

    Initial design review complete with

    supplier and per AIAG A-2 or equivalent

    100% design concerns addressed. AIA

    A-2 checklist or equivalent complete a

    open issues resolved

    Agreement with ( ) on performance and

    functional validation plan; Identify key

    dimensional characteristics for layout on

    prototypes

    Prototype testing and measurement is

    100% complete.

    Major program elements are documented

    to meet the program deliverables.

    Major program elements are

    documented to meet the program

    deliverables.Tool lead time/maker concept

    gauge and fixture design concepts

    Capacity study complete

    Supplier manufacturing facility identified

    Tool maker and lead time fixed w/

    schedule

    Gauge plan complete and approved by

    ), Machine/fixture plan complete and

    approved

    Control plan contains DV test plan

    elements and prototype layout

    requirements

    Prototype build issues fed back into pre

    launch control plan.

    Prototype build requirements are

    documented and agreed with ( ) (quantity,

    dates, lead time)

    prototype parts delivered on time at

    quality level expected. Build issues ha

    been addressed.

    Surrogate test data submitted to ( )

    Engineering and QA if available

    DV failures were addressed in the

    DFMEA and corrective actions

    incorporated into the design.

    DVP&R includes requirements fo

    all ertinent s ecifications

    preliminary list of critical characteristicsidentified and agreed with ( )

    Surrogate capability data reviewed with ( )

    Engineering

    layout information complete, processcapability known and can meet drawing

    tolerances or actions in place to resolv

    CAD data reviewed for feasibility issues

    and submitted to ( ).

    Drawings and specifications released a

    verified against CAD data

    Drawings contain appropriate material

    and performance requirements

    Drawings contain critical and safety

    characteristics

    Team Feasibility Commitment has been

    reviewed by team and signed off as

    approved

    Signed off to current design level

    Initial process flow is complete; used to

    develop PFMEA and Control Plan. AIA

    checklist A-6 or equivalent initiated and

    Supplier Champion:

    phone/e-mail

    Program:

    Supplier Name:

    Part Number(s)Part Name:

    Comme

    ()Phase 1- date xx/yy/zz ()Phase 2- date xx

    8. Design Verification Testing

    9. Prototype Part Layout and

    CPK/ Ppk, APQP Elements

    6. Prototype Build Control Plan

    7. Prototype Builds

    12. Manufacturing Process Flow

    10. Drawings and Specifications11. Team Feasibility

    Commitment

    APQP Elements

    1. Design FMEA

    4. Master Timing Plan

    5. Facilities, Tool and Gauges

    2. Design Review)

    3. Design Verification Plan

  • 7/28/2019 Global APQP Matrix

    2/3

  • 7/28/2019 Global APQP Matrix

    3/3

    CVGSR

    Stage Target Actual

    1 2 3 4 5 6 7 8 9101112131415161718192021

    APQP Element

    Key to "Status" symbols: "O" = item meets target (Shift + letter o); "D" = item does not meet target; plans exist

    Gap Expla

    Program Name:

    Champion: