Glina WWTP – May 2015

CONTENT:

General Information

Performance Results

Ongoing Projects & New Projects

General Info

History of the first project

1978 1982

• Research

• Studies

1982 1985

• Design

• Start of Construction

1986 1989

• Construction/Unfinished Achievement

1991 1995

• Restart of Works

1995 1996

• Technological Tests

• Pollution Events

1996 2007

• Minimal Preservation

Contract Data

BUCHAREST WWTP REHABILITATION – STAGE 1

ISPA Contract 2004/RO/16/P/PE/003-03

IMPLEMENTATION PERIOD OF THE PROJECT: 2007 - 2009

Financing Agencies: European Union, EBRD, EIB& Self-financing by

Municipality of Bucharest

Total Contract Value: 108 millions EURO

Employer: The Municipality of Bucharest

Engineer: J/V Jacobs – Fichtner – Plancenter

Contractor: J/V Aktor SA – Athena SA

Key data of the rehabilitation project

2003 2011

• Financing approval

• Design and Construction of Stage 1 Project

Dec 2010 May 2011

• Training the operation and maintenance first team in South Pest WWTP

Jun 2011

• Training & Testing by the Contractor

Jul 2011

• Tacking over the plant

Jul Oct 2011

• Trial Operation with FCsM/Aquiris and VWST

Jul 2012

• End of Defect Notification Period

General Layout

1.22 Mil. EI

10 m3/s partial treatment

5 m3/s complete treatment

Process Flow

Performance Results

Flow Distribution

Flow ( m3/s ) Project Average 2012 Average 2013 Average 2014 Average Apr 2015

Primary treatment 10 6.27 7.04 8.30 8.35

Biological treatment 5 4.04 4.94 4.95 5.33

Biological Effluent Conformity

Combined Effluent Conformity

Pollutants Removed

Self Sufficiency

Ongoing Projects &

New Projects

Digesters Behavior

STAR Pro Control® - Biological Treatment

Optimization

STAR - Advantages

An increased N capacity in the biological stage by 15-25%

A well tested advanced control system to ensure a stable operation of Glina WWTP during variable process conditions.

Reduced operational costs for energy and metal salt addition.

A robust control, so the risk for operational errors is reduced

A plug and play solution, which requires a minimum of mechanical and PLC/SCADA modifications

The possibility for future extension

New Projects

• 110 kV Main Power Plant rehabilitation

• Grit trap

• Common SCADA control room

• 3th storm basin rehabilitation

• Gas line conformity

• By-pass pipes of PST's lines

• New automatic road truck scale