gitman zutter student ch10

2
The Drillago Company Calculation of the NPV, IRR, and the Payback Period Facts of case: maturity (n 10 years cost-of-cap 13% Initial out ### Excel function ### Estimated Trial and error 0.14763097 Cash NPV Technique IRR Technique Year Outflows/In PV PV Payback Technique 0 ### ### ### 1 600,000 530973.45 522816.14 ### 2 1,000,000 783146.68 759268.67 ### 3 1,000,000 693050.16 661596.53 ### 4 2,000,000 1226637.46 1152977.82 ### 5 3,000,000 1628279.81 1506988.54 ### 6 3,500,000 1681114.85 1531984.87 ### 7 4,000,000 1700242.57 1525612.24 $100,000 0.03 8 6,000,000 2256959.17 1994036.77 ### 9 8,000,000 2663078.67 2316699.14 ### 10 ### 3535060.18 3028019.27 ### ### (0.03) 6.03 Recap: NPV ### Accept the project as th IRR 14.76% Approximately as it equa Accept the project as the IRR (14.7 Payback 6.03 years approximately

Upload: tahir-hussain

Post on 23-Nov-2015

17 views

Category:

Documents


4 download

DESCRIPTION

Corporate finance

TRANSCRIPT

NPV IRR PBP formulasThe Drillago CompanyCalculation of the NPV, IRR, and the Payback PeriodFacts of case:maturity (n)10yearscost-of-capital (k)13%Initial outlay (pv)$15,000,000Excel function14.7630974%EstimatedTrial and error0.14763097CashNPV TechniqueIRR TechniqueYearOutflows/InflowsPVPVPayback Technique0$(15,000,000)-15000000.00-15000000.001600,000530973.45522816.14$(14,400,000)21,000,000783146.68759268.67$(13,400,000)31,000,000693050.16661596.53$(12,400,000)42,000,0001226637.461152977.82$(10,400,000)53,000,0001628279.811506988.54$(7,400,000)63,500,0001681114.851531984.87$(3,900,000)74,000,0001700242.571525612.24$100,0000.0386,000,0002256959.171994036.77$6,100,00098,000,0002663078.672316699.14$14,100,0001012,000,0003535060.183028019.27$26,100,0001,698,543.00(0.03)6.03yearsRecap:NPV$1,698,543Accept the project as the NPV > 0.IRR14.76%Approximately as it equates the NPV to Zero.Accept the project as the IRR (14.76%) > Cost of Capital (13%)Payback6.03years approximately