getting heard in the madhouse: a citizen's guide to the cdm

Upload: international-rivers

Post on 10-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    1/29

    Getting Heard in theMadhouse:

    A CITIZENS GUIDE TO THE CDMPatrick McCully

    Rivers for Life 3

    Temacapauln, Jalisco, Mexico

    October 2010

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    2/29

    Climate change Global warming is a major threat to

    communities in developing countries Wet areas getting wetter; dry areas getting drier;

    extremes getting more extreme

    Many sources of greenhouse gases: biggest

    contribution is from burning fossil fuels

    US & China are biggest polluters

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    3/29

    Origins of the CDM The Kyoto Protocol (1997) to the UN Framework Convention on Climate Change

    (UNFCCC)

    Sets targets for industrializedcountries to reduce emissionsby an average of 5% below1990 levels in the period

    2008-2012

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    4/29

    Purpose of the CDM Under Kyoto, the Clean Development Mechanism is supposed to reduce emissions

    and promote sustainable development by: allowing project developers in developing countries to gain revenue by selling carbon

    credits for projects that reduce greenhouse gas emissions and

    allowing offset buyers (industrialized

    country companies and governments)

    to use credits to comply with Kyoto-

    mandated emissions reductions

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    5/29

    The CDMsCurrency: CERs

    Carbon Emission Reduction

    = 1 tonne of CO2-equivalent not emitted to the atmosphere

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    6/29

    Current CDM Pipeline:5513

    PROJECTS

    Adapted from UNEP Risoe

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    7/29

    Expected CERs by 2012

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    8/29

    Key Problems with the CDM

    1. Lack of additionality

    2. Inefficient & ineffective

    3. Perverse incentives

    4. Climatologically insufficient

    5. Inequitable

    6. Lack of sustainable

    development

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    9/29

    Lack of Additionality What does additional mean?

    - CDM credits must represent real emission reductions that only happened because of

    CDM revenue/recognition Non-additional projects allow emissions in industrialized countries to increase without

    reducing emissions in a developing country.

    Estimates of non-additional projects range from 40% to most. Actual number is

    unknowable

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    10/29

    Additionality Testing Most projects prove additionality with the following tests:

    - Investment analysis shows whether project is profitable without CDM income

    - Barrier analysis show where there are barriers that prevent project implementation without theCDM (e.g. project is located in a remote area, project ran into financial difficulties, etc.)

    - Common practice demonstrates whether the project type is common in the relevant sector and

    region.

    THESE TESTS ARE HIGHLY SUBJECTIVE

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    11/29

    Inefficient & Ineffective Inefficient

    - emission reductions could be achieved cheaper in other ways Ineffective- CDM revenues too low and too unpredictable to support emerging technologies

    - Process extremely opaque, complex & bureaucratic

    - Unsuitable for small projects

    - Supports cheapest, least best solutions (e.g. natural gas) rather than

    transformative solutions (e.g. solar)

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    12/29

    Perverse Incentives The CDM is increasing production of the refrigerant HCFC-22 in order to

    produce more waste gas (HFC23) for more CDM credits

    Discourages climate friendly policies

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    13/29

    Insufficient To stay below 2C, we need reductions in both industrialized and

    developing countries

    No climate benefit from Southern emission reduction opportunities if

    these delay climate action in the North

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    14/29

    Inequitable Increases future costs of developing countries own reductions

    Levy on CDM revenue for adaptation fund

    => developing countries pay costs of adaptation

    Most funds go as extra profits to corporations & developers in China and other

    middle-income countries

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    15/29

    Sustainable Development Little or no sustainable development benefit

    Host country defines sustainable development Lack of safeguards for stakeholder consultations

    Some projects cause social and environmental damage:

    - Dams

    - Industrial projects

    - Gas-fired power plants

    - Coal?

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    16/29

    Hydro in the CDM Majority of CDM hydro projects in China (then Brazil, India and Vietnam)

    As of 4 Sept 2010:

    1525 hydro projects seeking registration

    749 (56,771 MW) large hydro ( > 15MW)

    71% of large hydros in China

    16m CERs issued from 177 big hydro projects

    All big hydros in pipeline would produce 166m CERS/year

    [Mexico fossil fuel emissions 2007 = 129m tonnes]

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    17/29

    Big dams in the CDM:NON-

    ADDITIONALITY

    More than a third of the hydros approved already completed at the time of registration

    Almost all already under construction

    No substantial increase in the number of large hydros under construction

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    18/29

    Big hydro in China Worlds largest installed hydro capacity

    Hydropower technology at mature stage

    Project development mostly carried out by a small number of state-owned or state-

    controlled actors

    Loans from banks for 75% or more of capital costs

    No need for subsidies

    Plans to double installed capacity to

    225 GW by 2020

    Almost 2/3 Chinese large hydro projects

    applied for CDM in 2007

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    19/29

    CDM Project Lifecycle1. Validation

    2. Registration

    3. Verification & Certification

    4. Issuance

    Stakeholder Input in yellowboxes

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    20/29

    ValidationProject Design Document (PDD)

    written by the developer or a hired consultant

    Host country approval of CDM Project

    by countrys Designated National Authority (DNA)

    PDD undergoes validation

    by certified CDM auditing company, called a

    Designated operational Entity (DOE)

    30-Day Public

    Comment Period

    Project can be withdrawn

    Developer must consult

    you on the design of the

    project.

    Your DNA must approve the

    project and you should

    have input in this decision.

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    21/29

    RegistrationRequest for registration

    The PDD and validation report are submitted to the CDM

    Secretariat

    Review by UNFCCC Registration and

    Issuance Team

    CDM Executive Board (EB) approval

    Project is registered

    Project may be

    held from

    validation

    Project may be rejected

    Project may require

    correctionsCan lobby government to

    request a review, orconvince 3 members of

    CDM Executive Board to

    request review.

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    22/29

    Verification & Certification

    Monitoring

    The project developer must monitor all the data

    required by the PDD monitoring plan to calculate the

    number of credits to be generated

    Monitoring Report

    written by the developer or a hired consultant;

    developer decides how often

    Verification & certification of monitoring

    report

    by the DOE

    DOE may interviewyou during

    verification.

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    23/29

    IssuanceRequest for Issuance

    Monitoring and Verification & Certification reports are

    submitted to the CDM Secretariat

    Review by the UNFCCC Registration and

    Issuance Team

    CDM Executive Board approvalCERs are issued

    Last chance to influence

    process by lobbying your

    government to request a

    review, or convincing three

    members of CDM Executive

    Board to request review.

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    24/29

    Summary of opportunities for input in the

    CDM project cycle

    Consultation by developer on the design of theproject

    During the preparation of aproject

    Public commenting periodEnvironmental ImpactAssessment

    Input whether the project contributes tosustainable development

    Host country approval

    15-day public comment periodNew baseline and/or

    monitoring methodology

    30-day public comment period.At validation

    Trigger a request for reviewWhen requesting registration

    Contact with DOE is possible anytimeDuring verification and

    monitoring period

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    25/29

    Need more opportunities to intervene

    OBLIGATORY meeting to be conducted by anindependent non-governmental panel

    Report of the panel in public domain

    During the preparation of a

    project

    NGO representatives must be included in DNAdecisionsHost country approval

    Penalties if comments are not taken into account

    Recommendations to be mandatory

    Translations of PDDs into local languages

    Public commenting periods

    SECOND official public commenting period

    Involvement of civil society and local governmentsin the process

    Verification

    If poject is violating agreed plans it must bedisqualified from CDMMonitoring

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    26/29

    More transparency needed

    Dates of receipts of the project applications, agenda notesand minutes of the CDM board meetings

    Clearance letters and reasons when a project is rejected

    Local governments(DNA)

    Access to ALL stakeholder meetings

    Minutes of closed meetings

    Alert emails for commenting period

    Executive Board

    Tranlations of PDDs in locallanguages

    DOEs / project

    developers Information about CERs purchased

    from which projectCER Buyers

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    27/29

    Writing a CommentAddress the following questions:

    1. Will this project go ahead anyway (is it already built, under construction, normal practice)?

    2. Is the emissions baseline an accurate estimate of what will happen if the project were notregistered as a CDM project?

    3. Has the DNA approved this project?

    4. Does the project contribute to sustainable development?

    5. Were local people consulted?

    6. Is the social & environmental assessment adequate?

    Back up arguments with written evidence and provide links.

    Ask International Rivers, CDMWatch for help

    For examples of comment letters, see:

    http://www.internationalrivers.org/en/node/1741

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    28/29

    Useful Links for Stakeholder

    Input Contact info for your host countrys DNA: http://cdm.unfccc.int/DNA

    30-day public comment period on PDDs:http://cdm.unfccc.int/Projects/Validation/index.html

    15-day public comment period for experts on new methodologies:

    https://cdm.unfccc.int/public_inputs/index.html

    Procedure for contacting the CDM Executive Board for unsolicited comments:

    http://cdm.unfccc.int/Reference/Procedures/eb_proc01_v02.pdf

  • 8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM

    29/29

    Contact:Eva Maria Filzmoser

    CDM WatchBonn, Germany

    [email protected]

    www.cdm-watch.org

    Payal ParekhInternational RiversBerkeley/Bern

    US/Switzerland

    [email protected]

    www.internationalrivers.org/climate