getting heard in the madhouse: a citizen's guide to the cdm
TRANSCRIPT
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
1/29
Getting Heard in theMadhouse:
A CITIZENS GUIDE TO THE CDMPatrick McCully
Rivers for Life 3
Temacapauln, Jalisco, Mexico
October 2010
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
2/29
Climate change Global warming is a major threat to
communities in developing countries Wet areas getting wetter; dry areas getting drier;
extremes getting more extreme
Many sources of greenhouse gases: biggest
contribution is from burning fossil fuels
US & China are biggest polluters
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
3/29
Origins of the CDM The Kyoto Protocol (1997) to the UN Framework Convention on Climate Change
(UNFCCC)
Sets targets for industrializedcountries to reduce emissionsby an average of 5% below1990 levels in the period
2008-2012
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
4/29
Purpose of the CDM Under Kyoto, the Clean Development Mechanism is supposed to reduce emissions
and promote sustainable development by: allowing project developers in developing countries to gain revenue by selling carbon
credits for projects that reduce greenhouse gas emissions and
allowing offset buyers (industrialized
country companies and governments)
to use credits to comply with Kyoto-
mandated emissions reductions
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
5/29
The CDMsCurrency: CERs
Carbon Emission Reduction
= 1 tonne of CO2-equivalent not emitted to the atmosphere
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
6/29
Current CDM Pipeline:5513
PROJECTS
Adapted from UNEP Risoe
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
7/29
Expected CERs by 2012
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
8/29
Key Problems with the CDM
1. Lack of additionality
2. Inefficient & ineffective
3. Perverse incentives
4. Climatologically insufficient
5. Inequitable
6. Lack of sustainable
development
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
9/29
Lack of Additionality What does additional mean?
- CDM credits must represent real emission reductions that only happened because of
CDM revenue/recognition Non-additional projects allow emissions in industrialized countries to increase without
reducing emissions in a developing country.
Estimates of non-additional projects range from 40% to most. Actual number is
unknowable
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
10/29
Additionality Testing Most projects prove additionality with the following tests:
- Investment analysis shows whether project is profitable without CDM income
- Barrier analysis show where there are barriers that prevent project implementation without theCDM (e.g. project is located in a remote area, project ran into financial difficulties, etc.)
- Common practice demonstrates whether the project type is common in the relevant sector and
region.
THESE TESTS ARE HIGHLY SUBJECTIVE
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
11/29
Inefficient & Ineffective Inefficient
- emission reductions could be achieved cheaper in other ways Ineffective- CDM revenues too low and too unpredictable to support emerging technologies
- Process extremely opaque, complex & bureaucratic
- Unsuitable for small projects
- Supports cheapest, least best solutions (e.g. natural gas) rather than
transformative solutions (e.g. solar)
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
12/29
Perverse Incentives The CDM is increasing production of the refrigerant HCFC-22 in order to
produce more waste gas (HFC23) for more CDM credits
Discourages climate friendly policies
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
13/29
Insufficient To stay below 2C, we need reductions in both industrialized and
developing countries
No climate benefit from Southern emission reduction opportunities if
these delay climate action in the North
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
14/29
Inequitable Increases future costs of developing countries own reductions
Levy on CDM revenue for adaptation fund
=> developing countries pay costs of adaptation
Most funds go as extra profits to corporations & developers in China and other
middle-income countries
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
15/29
Sustainable Development Little or no sustainable development benefit
Host country defines sustainable development Lack of safeguards for stakeholder consultations
Some projects cause social and environmental damage:
- Dams
- Industrial projects
- Gas-fired power plants
- Coal?
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
16/29
Hydro in the CDM Majority of CDM hydro projects in China (then Brazil, India and Vietnam)
As of 4 Sept 2010:
1525 hydro projects seeking registration
749 (56,771 MW) large hydro ( > 15MW)
71% of large hydros in China
16m CERs issued from 177 big hydro projects
All big hydros in pipeline would produce 166m CERS/year
[Mexico fossil fuel emissions 2007 = 129m tonnes]
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
17/29
Big dams in the CDM:NON-
ADDITIONALITY
More than a third of the hydros approved already completed at the time of registration
Almost all already under construction
No substantial increase in the number of large hydros under construction
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
18/29
Big hydro in China Worlds largest installed hydro capacity
Hydropower technology at mature stage
Project development mostly carried out by a small number of state-owned or state-
controlled actors
Loans from banks for 75% or more of capital costs
No need for subsidies
Plans to double installed capacity to
225 GW by 2020
Almost 2/3 Chinese large hydro projects
applied for CDM in 2007
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
19/29
CDM Project Lifecycle1. Validation
2. Registration
3. Verification & Certification
4. Issuance
Stakeholder Input in yellowboxes
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
20/29
ValidationProject Design Document (PDD)
written by the developer or a hired consultant
Host country approval of CDM Project
by countrys Designated National Authority (DNA)
PDD undergoes validation
by certified CDM auditing company, called a
Designated operational Entity (DOE)
30-Day Public
Comment Period
Project can be withdrawn
Developer must consult
you on the design of the
project.
Your DNA must approve the
project and you should
have input in this decision.
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
21/29
RegistrationRequest for registration
The PDD and validation report are submitted to the CDM
Secretariat
Review by UNFCCC Registration and
Issuance Team
CDM Executive Board (EB) approval
Project is registered
Project may be
held from
validation
Project may be rejected
Project may require
correctionsCan lobby government to
request a review, orconvince 3 members of
CDM Executive Board to
request review.
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
22/29
Verification & Certification
Monitoring
The project developer must monitor all the data
required by the PDD monitoring plan to calculate the
number of credits to be generated
Monitoring Report
written by the developer or a hired consultant;
developer decides how often
Verification & certification of monitoring
report
by the DOE
DOE may interviewyou during
verification.
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
23/29
IssuanceRequest for Issuance
Monitoring and Verification & Certification reports are
submitted to the CDM Secretariat
Review by the UNFCCC Registration and
Issuance Team
CDM Executive Board approvalCERs are issued
Last chance to influence
process by lobbying your
government to request a
review, or convincing three
members of CDM Executive
Board to request review.
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
24/29
Summary of opportunities for input in the
CDM project cycle
Consultation by developer on the design of theproject
During the preparation of aproject
Public commenting periodEnvironmental ImpactAssessment
Input whether the project contributes tosustainable development
Host country approval
15-day public comment periodNew baseline and/or
monitoring methodology
30-day public comment period.At validation
Trigger a request for reviewWhen requesting registration
Contact with DOE is possible anytimeDuring verification and
monitoring period
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
25/29
Need more opportunities to intervene
OBLIGATORY meeting to be conducted by anindependent non-governmental panel
Report of the panel in public domain
During the preparation of a
project
NGO representatives must be included in DNAdecisionsHost country approval
Penalties if comments are not taken into account
Recommendations to be mandatory
Translations of PDDs into local languages
Public commenting periods
SECOND official public commenting period
Involvement of civil society and local governmentsin the process
Verification
If poject is violating agreed plans it must bedisqualified from CDMMonitoring
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
26/29
More transparency needed
Dates of receipts of the project applications, agenda notesand minutes of the CDM board meetings
Clearance letters and reasons when a project is rejected
Local governments(DNA)
Access to ALL stakeholder meetings
Minutes of closed meetings
Alert emails for commenting period
Executive Board
Tranlations of PDDs in locallanguages
DOEs / project
developers Information about CERs purchased
from which projectCER Buyers
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
27/29
Writing a CommentAddress the following questions:
1. Will this project go ahead anyway (is it already built, under construction, normal practice)?
2. Is the emissions baseline an accurate estimate of what will happen if the project were notregistered as a CDM project?
3. Has the DNA approved this project?
4. Does the project contribute to sustainable development?
5. Were local people consulted?
6. Is the social & environmental assessment adequate?
Back up arguments with written evidence and provide links.
Ask International Rivers, CDMWatch for help
For examples of comment letters, see:
http://www.internationalrivers.org/en/node/1741
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
28/29
Useful Links for Stakeholder
Input Contact info for your host countrys DNA: http://cdm.unfccc.int/DNA
30-day public comment period on PDDs:http://cdm.unfccc.int/Projects/Validation/index.html
15-day public comment period for experts on new methodologies:
https://cdm.unfccc.int/public_inputs/index.html
Procedure for contacting the CDM Executive Board for unsolicited comments:
http://cdm.unfccc.int/Reference/Procedures/eb_proc01_v02.pdf
-
8/8/2019 Getting Heard in the Madhouse: A Citizen's Guide to the CDM
29/29
Contact:Eva Maria Filzmoser
CDM WatchBonn, Germany
www.cdm-watch.org
Payal ParekhInternational RiversBerkeley/Bern
US/Switzerland
www.internationalrivers.org/climate