geothermal project timelinestheargeo.org/presentations/newtechnologies... · geothermal project...

18
6th African Rift Geothermal Conference | ARGeo-C6 Short Course 1 | Project Management for Geothermal Development Geothermal Project Timelines Yngvi Guðmundsson

Upload: others

Post on 26-Aug-2020

80 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

6th African Rift Geothermal Conference | ARGeo-C6 Short Course 1 | Project Management for Geothermal Development

Geothermal Project Timelines

Yngvi Guðmundsson

Page 2: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project phases

• Resource identification • Potential areas, Defining concession and Allocating concessions

• Exploration • Surface exploration and Exploration drilling

• Plant construction • Production drilling

• Steam gathering, turbine generation system, power lines

Page 3: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project milestones

• Each phase ends or starts with a major milestones

• Can be very difficult to reach these milestone

• Usually problem with funding/financing

Page 4: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project duration guidelines (Example, ESMAP Geothermal handbook)

• Most guidelines or literature assume 5-7 Years for project

Activity/Phase Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7

Preliminary survey

Exploration

Test drilling

Project review and planning

Field development

Construction

Start-up and commissioing

Page 5: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project duration/timeline

• Has significant influence on project feasibility

• Often pressure from government to show progress

• Are Seven years reasonable?

Page 6: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Examples of projects for comparison

- From Iceland: Krafla, Svartsengi, Nesjavellir, Reykjanes, Hellisheidi and Þeistareykir.

- Key dates generally accessible on company websites, news articles or through literature

- From Kenya: Olkaria and Menengai. - Key dates generally accessible through UNU-GTP articles or news articles

Page 7: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project duration

Krafla

Krafla Installed capacity: 60 MWe Surface exploration: 1973 Exploration drilling: 1974 Construction start: 1975 Completion of first unit: 1978

Page 8: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project duration

Svartsengi and Nesjavellir

Nesjavellir Installed capacity: 60 MWe, 200 MWth Resource identification and surface exploration:1946 Exploration drilling: 1986 Construction start: 1989 Completion of first unit: 1990 (only heating)

Page 9: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Reykjanes

Svartsengi Installed capacity: 75 MWe, 150 MWth Resource identification and surface exploration: Unclear Exploration drilling: 1971 Construction start: 1975 Completion of first unit: 1976 (only heating)

Page 10: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project duration

Reykjanes

Reykjanes Installed capacity: 100 MWe Resource identification and surface exploration:1953 Exploration drilling: 1997 Construction start: 2004 Completion of first unit: 2006 (50 MWe)

Page 11: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project duration

Hellisheiði

Hellisheiði Installed capacity: 303 MWe, 133 MWth Resource identification and surface exploration: Unclear Exploration drilling: 2001 Construction start: 2005 Completion of first unit: 2007

Page 12: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project duration

Theistareykir

Þeistareykir Installed capacity: 45 MWe (in 2017) Resource identification and surface exploration: Unclear Exploration drilling: 2002 Construction start: 2015 Completion of first unit: - in Construction

Page 13: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project duration

Olkaria

Olkaria Resource identification and surface exploration: Unclear Exploration drilling: 1973 Construction start: 1979 Completion of first unit: 1981

Page 14: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project duration

Olkaria

Olkaria Estimated total installed capacity: Olkaria I: 45 MWe Olkaria II: 105 MWe Olkaria III: 139 MWe Olkaria IV: 140 MWe Olkaria IAU: 140 MWe Cumulated capacity from multiple well head generators: ~60 MWe

Page 15: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Geothermal project duration

Menengai

Menengai Installed capacity: 105 MWe (Planned) Start of exploration: 2004 First exploration drilling: 2011 Construction start: 2013 Completion of first unit: in Construction

Page 16: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Results

• First phase (Resource indentification and surface exploration) does not have a clear start or duration

• New projects take more than seven year if everything is considered

• Shorter by developing small units, simple or direct use units as a first unit

Page 17: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

New Projects (greenfield) timeline

• 10 years is more realistic if everything is considered

• 5-7 years is reasonable from start of exploration drilling

Activity/Phase Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

Resource identification

Surface exploration

Exploration drilling

Field development

Power plant construction

Project Planning

Page 18: Geothermal Project Timelinestheargeo.org/presentations/newtechnologies... · Geothermal project duration guidelines (Example, ESMAP Geothermal handbook) •Most guidelines or literature

ARGeo-C6 Short Course 1 | Geothermal Project Management Addis Ababa, Ethiopia | 31 Oct – 1 Nov, 2016

Conclusions

• If additional time is realized in the early phases of the project it can be considered to reduce risk in the project going forward

• If a project fast tracks through the first phases of the project, it should be considered to have higher risk of delay in the later stages.

• Additional time in the first phases allows more time for better project planning