geotek engineering & testing services, inc. 909 east 50th
TRANSCRIPT
GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50th Street North Sioux Falls, South Dakota 57104 Phone 605-335-5512 Fax 605-335-0773
March 15, 2021 Banner Associates, Inc. 409 22nd Avenue South Brookings, South Dakota 57006 Attn: Pat Carey, PE Subj: Geotechnical Exploration Proposed Street & Utility Improvements Lake Preston, South Dakota
GeoTek #21-046 This correspondence presents our written report of the geotechnical exploration program for the referenced project. Our work was performed in accordance with your authorization. We are transmitting an electronic copy of our report for your use. We thank you for the opportunity of providing our services on this project and look forward to continued participation during the design and construction phases. If you have any questions regarding this report, please contact our office at (605) 335-5512. Respectfully Submitted, GeoTek Engineering & Testing Services, Inc. Jared Haskins Jared Haskins, PE Geotechnical Manager
Proposed Street & Utility Improvements Page 2 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
TABLE OF CONTENTS
INTRODUCTION......................................................................................................................... 4
PROJECT INFORMATION ............................................................................................................... 4 SCOPE OF SERVICES ..................................................................................................................... 4
SITE & SUBSURFACE CONDITIONS ..................................................................................... 5
SITE LOCATIONS & DESCRIPTIONS .............................................................................................. 5 GROUND SURFACE ELEVATIONS & TEST BORING LOCATIONS .................................................... 5 EXISTING ASPHALT PAVEMENT, GRAVEL BASE & GRAVEL SURFACING THICKNESSES ............... 5 SUBSURFACE CONDITIONS ........................................................................................................... 7 WATER LEVELS ........................................................................................................................... 8
ENGINEERING REVIEW & RECOMMENDATIONS .......................................................... 8
PROJECT DESIGN DATA ............................................................................................................... 8 UTILITY IMPROVEMENTS ............................................................................................................. 9
Subgrade Soils ........................................................................................................................ 9 Water Control.......................................................................................................................... 9 OSHA Requirements .............................................................................................................. 9 Trench Backfill ..................................................................................................................... 10 Trenchless Installation Method ............................................................................................. 12
STREET IMPROVEMENTS ............................................................................................................ 12 Subgrade Conditions ............................................................................................................. 12 Stripping & Removals........................................................................................................... 14 Filling .................................................................................................................................... 14 Subgrade Preparation Option 1 – Scarification & Recompaction ........................................ 14 Unstable Subgrade with Subgrade Preparation Option 1 ..................................................... 15 Subgrade Preparation Option 2 – Subgrade Reinforcement ................................................. 15 Subgrade Preparation Option 3 – Cement Stabilization ....................................................... 16 Pavement Section Thicknesses ............................................................................................. 16 Unpaved Section Thickness .................................................................................................. 17 Asphalt Pavement, Aggregate Base Course Material & Gravel Surfacing .......................... 17 Existing Asphalt Pavement, Gravel Base & Gravel Surfacing ............................................. 18
CORROSIVE POTENTIAL ............................................................................................................. 18
CONSTRUCTION CONSIDERATIONS ................................................................................ 19
GROUNDWATER & SURFACE WATER ......................................................................................... 19 DISTURBANCE OF SOILS ............................................................................................................. 19 COLD WEATHER PRECAUTIONS ................................................................................................. 19 EXCAVATION SIDESLOPES.......................................................................................................... 20 OBSERVATIONS & TESTING ....................................................................................................... 20
Excavation............................................................................................................................. 20 Testing................................................................................................................................... 21
SUBSURFACE EXPLORATION PROCEDURES ................................................................ 21
TEST BORINGS ........................................................................................................................... 21
Proposed Street & Utility Improvements Page 3 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
SOIL CLASSIFICATION ................................................................................................................ 22 WATER LEVEL MEASUREMENTS ................................................................................................ 22 LABORATORY TESTS .................................................................................................................. 22
LIMITATIONS ........................................................................................................................... 23
STANDARD OF CARE ............................................................................................................. 23
APPENDIX A FIGURE 1 – SITE MAP BORING LOGS SOIL CLASSIFICATION SHEET
SYMBOLS & DESCRIPTIVE TERMINOLOGY PROCTOR DATA SHEETS
Proposed Street & Utility Improvements Page 4 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
GEOTECHNICAL EXPLORATION PROPOSED STREET & UTILITY IMPROVEMENTS
LAKE PRESTON, SOUTH DAKOTA GEOTEK #21-046
INTRODUCTION
Project Information
This report presents the results of the recent geotechnical exploration program for the proposed
street and utility improvements on various streets in Lake Preston, South Dakota.
Scope of Services
Our work was performed in accordance with the authorization of Pat Carey with Banner
Associates, Inc. The scope of work as presented in this report is limited to the following:
1. To perform 25 standard penetration test (SPT) borings to gather data on the subsurface conditions at the project sites.
2. To perform laboratory tests that include moisture content, dry density, standard Proctor,
resistivity, pH, sulfate content and chloride content. We did not perform laboratory tests on any frozen soils.
3. To prepare an engineering report that includes the results of the field and laboratory tests
as well as our geotechnical engineering opinions and recommendations regarding the following:
• Existing pavement section or gravel surfacing; • Subsurface conditions; • Underground utility excavation and backfilling; • Subgrade strength and potential corrective measures; • Pavement section thicknesses; • Unpaved section thickness; • Corrosive potential of the soils; • Special geotechnical conditions that may impact the constructability and final
performance of the project; • Quality control observation and testing.
Proposed Street & Utility Improvements Page 5 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
The scope of our work was intended for geotechnical purposes only. This scope of work did not
include determining the presence or extent of environmental contamination at the project sites or
to characterize the project sites relative to wetlands status.
SITE & SUBSURFACE CONDITIONS
Site Locations & Descriptions
The project sites are located on various streets in Lake Preston, South Dakota. The streets are
asphalt surfaced or gravel surfaced. The streets included in this project consist of the following:
7th Street NW/NE, 6th Street NW, 5th Street NW/NE, 4th Street NW/NE, 3rd Street NE, 2nd Street
NW, Preston Avenue N, Minden Avenue N, Main Avenue N, Lake Avenue N, Fremont Avenue
N, Spring Avenue N, Park Avenue N and Walters Avenue N.
Ground Surface Elevations & Test Boring Locations
We did not determine the ground surface elevations at the test boring locations. A site map
(Figure 1) is attached showing the relative location of the test borings.
Existing Asphalt Pavement, Gravel Base & Gravel Surfacing Thicknesses
Table 1 summarizes the thicknesses of the existing asphalt pavement and gravel base
encountered at the respective test boring locations. Asphalt was not encountered at test borings 3,
4, 6, 8, 9, 10 and 22. Table 2 summarizes the thicknesses of the existing gravel surfacing
encountered at the respective test boring locations. Also, see Tables 3 and 4 that show the
average asphalt pavement, gravel base and gravel surfacing thicknesses for the roads.
Table 1. Thicknesses of the Existing Asphalt Pavement & Gravel Base Test
Boring Street Asphalt Thickness, in Gravel Base, in
1 7th Street NW 4 5 2 7th Street NW 4 5 5 Main Avenue N 4 4 7 5th Street NW 4 3 ½ 11 4th Street NW 5 19
Proposed Street & Utility Improvements Page 6 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
Table 1 (Continued). Thicknesses of the Existing Asphalt Pavement & Gravel Base Test
Boring Street Asphalt Thickness, in Gravel Base, in
12 Minden Avenue N 5 6 13 2nd Street NW 5 4 14 Lake Avenue N 3 ½ 3 15 Lake Avenue N 3 ½ 3 16 4th Street NE 4 5 17 4th Street NE 5 ½ 5 ½ 18 Fremont Avenue N 4 3 19 Fremont Avenue N 4 4 20 Spring Avenue N 4 7 21 Spring Avenue N 3 4 23 Park Avenue N 4 6 24 Park Avenue N 4 3 25 3rd Street NE 4 3
Table 2. Thicknesses of the Existing Gravel Surfacing Test
Boring Street Gravel Surfacing, in
3 7th Street NE 8 4 Minden Avenue N 5 6 Lake Avenue N 5 ½ 8 5th Street NE 6 ½ 9 Preston Avenue N 7 10 Preston Avenue N 24 22 Park Avenue N 6
Table 3. Average Asphalt Pavement & Gravel Base Thicknesses
Road Average Asphalt Pavement Thickness, in
Average Gravel Base Thickness, in
All Asphalt Surfaced Roads 4.1 5.2* Note: *Includes a gravel base thickness of 19 at test boring 5 (4th Street NW).
Table 4. Average Gravel Surfacing Thickness
Road Average Gravel Surfacing Thickness, in
All Gravel Surfaced Roads 8.9* Note: *Includes a gravel surfacing thickness of 24 inches at test boring 10 (Preston Avenue N).
Proposed Street & Utility Improvements Page 7 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
Subsurface Conditions
The test borings were performed on January 21, January 22 and January 23, 2021. The
subsurface conditions encountered at the test boring locations are illustrated by means of the
boring logs included in Appendix A.
At the test boring locations, the subgrade soils consisted of the following soil types: existing fill
materials, topsoil materials, fine alluvium soils, mixed alluvium soils, coarse alluvium soils and
glacial till soils. The existing fill materials were encountered at the majority of the test borings
(not at test borings 3, 10 and 11) and extended to depths varying from 2 feet to 10 feet. The
topsoil materials were only encountered at test boring 22. The fine alluvium soils were
encountered at the majority of the test borings (not at test borings 19, 20, 23, 24 and 25). The
mixed alluvium soils were only encountered at test borings 2, 4, 11, 12 and 14. The coarse
alluvium soils were only encountered at test borings 3 and 6. The glacial till soils were
encountered at the majority of the test borings (not at test borings 2, 13, 20 and 21). The test
borings indicated that frozen soils extended to a depth of 2 feet.
The existing fill materials consisted of lean clay (CL) and lean clay with sand (CL). The topsoil
materials consisted of lean clay (CL). The fine alluvium soils consisted of lean clay (CL), fat
clay (CH) and lean clay with sand (CL). The mixed alluvium soils consisted of sandy lean clay
(CL) and clayey sand (SC). The coarse alluvium soils consisted of sand with silt (SP-SM). The
glacial till soils consisted of lean clay with sand (CL), fat clay with sand (CH) and sandy lean
clay (CL).
The consistency or relative density of the soils is indicated by the standard penetration resistance
(“N”) values as shown on the boring logs. A description of the soil consistency or relative
density based on the “N” values can be found on the attached Soil Boring Symbols and
Descriptive Terminology data sheet.
We wish to point out that the subsurface conditions at other times and locations at the project
sites may differ from those found at our test boring locations. If different conditions are
encountered during construction, then it is important that you contact us so that our
recommendations can be reviewed.
Proposed Street & Utility Improvements Page 8 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
Water Levels
Measurements to record the groundwater levels were made at the test boring locations. The time
and level of the groundwater readings are recorded on the boring logs. Groundwater was
measured at depths of 12 feet (test boring 5), 11 feet (test boring 7), 12 feet (test boring 10), 7 ½
feet (test boring 11), 12 feet (test boring 12) and 8 ½ feet (test boring 13). Groundwater did not
enter the boreholes at the other test borings at the time of our measurements.
The water levels indicated on the boring logs may or may not be an accurate indication of the
depth or lack of subsurface groundwater. The limited length of observation restricts the accuracy
of the measurements. Long term groundwater monitoring was not included in our scope of work.
ENGINEERING REVIEW & RECOMMENDATIONS
Project Design Data
We understand that the project will consist of street and utility improvements on various streets
in Lake Preston, South Dakota. The majority of the street improvements will consist of a new
asphalt pavement section. Several of the streets will remain gravel surfaced. The utility
improvements will likely consist of new water main and sanitary sewer. We understand that the
sanitary sewer will have a maximum depth of about 12 feet. We understand that open-cut
methods will be used for the majority of the installation. Trenchless methods (directional
drilling) will likely be used for the installation of the utilities beneath the existing railroad tracks.
Minimum grade changes are expected for the project.
The information/assumptions detailed in the project design data section are important factors in
our review and recommendations. If there are any corrections or additions to the information
detailed in this section, then it is important that you contact us so that we can review our
recommendations with regards to the revised plans.
Proposed Street & Utility Improvements Page 9 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
Utility Improvements
Subgrade Soils
The subgrade soils anticipated at the invert depths for the underground utilities will consist of
clay soils and sand soils, but mostly clay soils. Where soils having moderate moisture and
density values are encountered at the bottom of the trench excavations, it is our opinion that the
soils are considered suitable for support of the proposed utilities, provided they are adequately
dewatered and are not disturbed by construction traffic. Localized areas of wet or soft soils may
be encountered at the bottom of the trench excavations. These areas will require subexcavation
and trench stabilization methods and materials. Appropriate bedding materials should be used for
the utility pipes.
Water Control
Water may enter the trench excavations as a result of subsurface water, precipitation or surface
run off. Dewatering procedures may be required in order to control and remove water entering
the trench excavations. Where clay soils are encountered, it will likely be possible to remove and
control water entering the excavations using normal sump pumping techniques. However, if
waterbearing sand soils are encountered, then extensive dewatering techniques will likely be
required due to the potentially large volumes of water. The contractor should provide appropriate
dewatering methods and equipment. Again, groundwater was measured at depths varying from 7
½ feet to 12 feet at test borings 5, 7, 10, 11, 12 and 13. Therefore, some dewatering should be
expected for the project, likely for the deeper utilities. Any water that accumulates at the bottom
of the excavations should be immediately removed and surface drainage away from the
excavations should be provided during construction.
OSHA Requirements
All excavations must comply with the requirements of OSHA 29 CFR, Part 1926, Subpart P,
“Excavations and Trenches”. This document states that the excavation safety is the responsibility
of the contractor. Reference to this OSHA requirement should be included in the project
specifications.
Proposed Street & Utility Improvements Page 10 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
Trench Backfill
The trench backfill should be placed in lifts of up to 6 inches in thickness and compacted to the
levels outlined in Table 5. Due to the depth of the sanitary sewer, it is our opinion that a higher
compaction specification (for excavations greater than 6 feet in depth) will be necessary to limit
(but not eliminate) the amount of settlement within the trench backfill. The compaction
specifications in Table 5 are based on a material’s maximum dry density value, as determined by
a standard Proctor (ASTM: D698) test.
Table 5. Recommended Compaction Levels Placement Location/Depth Compaction Specification
Backfill within 6 feet of the finished subgrade level 95% Backfill more than 6 feet below the finished subgrade level 97%
Below agriculture land and grass only areas 95%
Generally, it will be easier to achieve the compaction specification if the moisture content of the
trench backfill soils is adjusted to within plus or minus 2 percent of the optimum moisture
content as determined by standard Proctor (ASTM:D698). However, in order to achieve the 97
percent compaction specification, it may be necessary to adjust the moisture content of the trench
backfill soils to within plus or minus 1 percent of the optimum moisture content as determined
by standard Proctor (ASTM:D698). In order to provide increased stability in the trench backfill
areas that are within 2 feet of the finished subgrade level, we recommend that the moisture
content of the soils be within a range of 1 percent to 4 percent below the optimum moisture
content.
We performed 5 standard Proctor tests for the project (3 on the fine alluvium soils at test borings
10, 13 and 15 and 2 on the glacial till soils at test borings 17 and 23). The results of the standard
Proctor tests are shown in Table 6.
Table 6. Standard Proctor Test Results Test
Boring Depth (ft) Soil Type OMC (%)
Maximum Dry Density (pcf)
10 2 to 4 ½ Lean Clay (FA) 21.1 101.1 13 6 to 10 Lean Clay (FA) 19.4 103.9 15 4 ½ to 9 ½ Lean Clay (FA) 19.4 102.5
Proposed Street & Utility Improvements Page 11 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
Table 6 (Continued). Standard Proctor Test Results Test
Boring Depth (ft) Soil Type OMC (%)
Maximum Dry Density (pcf)
17 7 to 12 Lean Clay w/ Sand (GT) 19.6 104.0 23 3 to 8 Fat Clay w/ Sand (GT) 21.1 102.4
Note: FA – fine alluvium soils and GT – glacial till soils.
Based on the results of the moisture content and standard Proctor tests, it is our general opinion
that the majority of the existing fill materials, mixed alluvium soils and glacial till soils and
portions of the fine alluvium soils have in-situ moisture content levels that range from slightly
below to 4 percent above the optimum moisture content, while the majority of the fine alluvium
soils and a small portion of the existing fill materials and glacial till soils have in-situ moisture
content levels that range from 6 percent above to 15 percent above the optimum moisture
content. The wet fine alluvium soils were encountered at test borings 1, 2, 7, 10, 13, 15 and 16.
The wet existing fill materials were encountered at test borings 13 and 16. The wet glacial till
soils were encountered at test borings 4 and 10. In general, soils with moisture content levels
above 25 percent are considered “wet”. We also highlighted the wet existing fill materials, fine
alluvium soils and glacial till soils on the boring logs.
In our opinion, the majority of the existing fill materials, mixed alluvium soils, coarse alluvium
soils and glacial till soils and portions of the fine alluvium soils can likely be reused as trench
backfill, while the wet existing fill materials, wet fine alluvium soils and wet glacial till soils are
not suitable or ideal for use as trench backfill. Again, the wet existing fill materials, wet fine
alluvium soils and wet glacial till soils were encountered at the test borings discussed in the
paragraph above. Also, the topsoil materials should not be used as trench backfill. Our opinions
are based on our observations of the collected samples, the results of the laboratory tests and the
difficulties that the contractor will likely have trying to dry the wet soils within the project limits.
Therefore, the wet existing fill materials, wet fine alluvium soils, wet glacial till soils and topsoil
materials should be replaced with an off-site borrow material or with suitable material available
at other areas of the project.
The off-site borrow material should consist of either a granular or clay material. If a granular
material is used, then it should consist of a pit-run or processed sand or gravel having a
maximum particle size of 1 inch. The granular material can be placed in lifts of up to 1 foot in
Proposed Street & Utility Improvements Page 12 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
thickness. If a clay material is selected, then it should consist of a non-organic clay having a
liquid limit less than 45. Scrutiny on the clay material’s moisture content should be made prior to
the acceptance and use. If granular materials are used, then the upper 2 feet to 3 feet of the trench
backfill should consist of a clay material in order to provide a consistent subgrade condition
beneath the pavement section.
Trenchless Installation Method
As previously stated, directional drilling will likely be used for the installation of the utilities
beneath the existing railroad tracks. Fine alluvium soils and glacial till soils will likely be
encountered during the direction drilling. In our opinion, the fine alluvium soils have low
strength levels and the glacial till soils have moderately high strength levels. We estimate that the
fine alluvium soils have unconfined compressive strength values between 0.5 tons per square foot
(tsf) and 1.0 tsf. Also, we estimate that the glacial till soils have unconfined compressive strength
values between 1.5 tons per square foot (tsf) and 2.5 tsf. The contractor may experience difficulties
if coarse gravel or cobbles are encountered during the installation process.
If water or saturated soils are encountered within the bore pits, then it would be beneficial to
place a layer (6 inches to 12 inches) of drainage rock at the bottom of the bore pits to provide a
stable base during construction. Also, some dewatering may be needed within the bore pits. The
drainage rock should be crushed, washed and meet the gradation specifications shown in Table 7.
Table 7. Drainage Rock Gradation Specifications Sieve Size Percent Passing 1 ½-inch 100 1-inch 70 – 90
3/4-inch 25 – 50 3/8-inch 0 – 5
Street Improvements
Subgrade Conditions
In general, existing fill materials, fine alluvium soils and glacial till soils are expected to be
encountered as subgrade soils. The existing fill materials, fine alluvium soils and glacial till soils
Proposed Street & Utility Improvements Page 13 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
have Unified Soils Classification System symbols of CL and CH and AASHTO classifications of
A-6 and A-7.
As previously stated, frozen soils extended to a depth of 2 feet. Therefore, the moisture content
and density levels of the subgrade soils within 2 feet of the surface are unknown. Based on our
observations of the collected samples, the majority of the subgrade soils within 2 feet of the
surface consisted of existing fill materials that are dark in color (dark brown, very dark brown or
black). In our opinion, the majority of the existing fill materials within 2 feet of the surface have
low strength characteristics and are prone to instability during freeze-thaw cycles. In addition,
the majority of the existing fill materials within 2 feet of the surface are prone to instability from
normal construction traffic.
In general, we estimate California Bearing Ratio (CBR) values of 1.5 to 2.0 for the existing fill
materials that are dark in color and CBR values of 2.5 to 3.5 for the other existing fill materials,
fine alluvium soils and glacial till soils. CBR values of 1.5 to 2.0 are considered low CBR
values. The CBR value is a measure of the supporting value of the subgrade soils. The value can
be determined from a soaked test or a unsoaked test. The value from a soaked test is used to
simulate the worst conditions (wet periods of the year and the spring thaw), while the value from
an unsoaked test is used to simulate normal field conditions (summer and fall). Values from
soaked tests are much lower than values from unsoaked tests. The values discussed above
represent values from soaked tests. With all this said, we would consider the subgrade condition
to be a poor to fair subgrade condition.
In our opinion, normal subgrade preparation (option 1) could be used for the project. The normal
subgrade preparation would consist of scarification and recompaction. However, it should be
understood that additional corrections would likely be needed in some areas in order to provide a
stable subgrade condition. For option 1 to be successful, there may need to be an extended period
of dry weather during construction. Two (2) other subgrade preparation options could be
considered for the project. The other subgrade preparation options would consist of subgrade
reinforcement (option 2) and cement stabilization (option 3). Options 2 and 3 would likely
provide a stable subgrade condition in areas where poor subgrade conditions are encountered.
Proposed Street & Utility Improvements Page 14 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
Options 2 and 3 would also extend the life of the pavement. In addition, the cement stabilization
would provide an “all weather” subgrade during construction.
Stripping & Removals
We recommend removing any vegetation/organic materials and the existing pavement section
(where applicable) in order to achieve the design subgrade elevations. Low-ground-pressure
construction equipment or excavators with smooth-edged buckets should be used for the
stripping and removals in areas where soft/wet soils are present. We recommend limiting the
amount of heavy wheeled construction traffic on the subgrade.
Filling
If filling is required to achieve the design subgrade elevations, then the fill materials should
consist of non-organic lean clay or sandy lean clay soils having a liquid limit less than 50 and a
plasticity index between 15 and 35. The moisture content of the fill soils should be 1 percent to 4
percent below the optimum moisture content. The fill soils should be placed in compacted lifts
having a maximum thickness of 6 inches. We recommend a minimum compaction specification
of 95 percent of standard Proctor (ASTM:D698) for the fill soils. Alternatively, granular
materials could also be used as subgrade fill.
Subgrade Preparation Option 1 – Scarification & Recompaction
For subgrade preparation option 1, the upper 8 inches of the subgrade should be scarified,
moisture conditioned and recompacted. The soils should be moisture conditioned to a moisture
level that is 1 percent to 4 percent below the optimum moisture content as determined by
standard Proctor (ASTM:D698). The scarification should be performed by a disc harrow and not
a road grader with teeth. Following the subgrade preparation (scarification and recompaction)
and prior to the placement of the aggregate base course material, we recommend that a proof roll
be performed on the exposed subgrade with a truck weighing 20 tons to 30 tons. During the
proof roll, unstable areas in the subgrade should be delineated from stable areas. An unstable
area would be considered a location with at least 1 inch of rutting or deflection. Unstable areas
will need additional corrections in order to provide a uniform and stable subgrade condition. See
Proposed Street & Utility Improvements Page 15 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
the section entitled Unstable Subgrade with Subgrade Preparation Option 1 for detailed
information regarding the additional corrections.
Unstable Subgrade with Subgrade Preparation Option 1
Areas of unstable subgrade may be encountered during construction with subgrade preparation
option 1. The soils within the unstable area should be removed, and either moisture-conditioned
and recompacted, or replaced with suitable subgrade soils. If the unstable area will not stabilize
using this method, then alternative stabilization methods may be used such as a modified cross-
section involving a geotextile fabric. With the geotextile fabric, a thicker aggregate base course
section will likely be needed (thickness would be based on field conditions). For very poor
subgrade conditions, granular subbase will likely be needed with the geotextile fabric. The
granular subbase should consist of crushed quartzite, recycled concrete or a crushed pit-run
material meeting the gradation specifications shown in Table 8.
Table 8. Granular Subbase Gradation Specifications Sieve Size Percent Passing
4-inch 100 3-inch 70 – 90 2-inch 60 – 80 1-inch 40 – 70
#4 10 – 50 #40 5 – 20 #200 0 – 8
Regarding the geotextile fabric, we recommend using Mirafi HP 370, Propex Geotex 3x3 HF,
Huesker Comtrac P 45/45 or an approved alternative. The granular subbase should be compacted
to a minimum of 97 percent of standard Proctor density (ASTM:D698). It should be noted that
compaction testing may not be practical for the granular subbase due to the large aggregate.
Subgrade Preparation Option 2 – Subgrade Reinforcement
Subgrade preparation option 2 would consist of subgrade preparation option 1 with the addition
of a geotextile fabric beneath the aggregate base course material.
Proposed Street & Utility Improvements Page 16 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
Subgrade Preparation Option 3 – Cement Stabilization
The cement stabilization should consist of blending the subgrade soils with cement to a
minimum depth of 12 inches. The percentage of cement used typically ranges from 5 percent to 7
percent and should be based on a site specific mix design. For bidding purposes, the percentage
of cement used should be 6 percent (example: if the in-place dry density equals 100 pounds per
cubic foot (pcf), then 6.0 pounds of cement should be applied to the subgrade, per square foot).
We recommend that the percentage of cement used during the blending process be determined by
a mix design that should be performed when the subgrade soils are exposed during construction.
The mix design typically takes about 2 weeks to complete.
Once the percentage of cement is determined, the cement should be placed uniformly over the
subgrade surface at the specified percentage with a truck-mounted cement spreader. In addition
to the cement being placed uniformly, the truck-mounted spreader will help control the spread of
cement dust. Then, a self-propelled pulvimixer/reclaimer should be used to reclaim the upper 12
inches of the subgrade along with the cement. Within 30 minutes, the reclaimed mixture of soil
and cement should be initially compacted with a large (60-inch to 72-inch diameter) vibratory
sheepsfoot roller to a minimum of 95 percent of the maximum dry density as determined by
Moisture-Density Relations of Soil-Cement Mixtures (ASTM:D558). The moisture content of
the material should be adjusted to a moisture level that is within 3 percent below to 3 percent
above the optimum moisture content determined by Moisture-Density Relations of Soil-Cement
Mixtures (ASTM:D558). After initial compaction, the subgrade should be graded to design
elevations, rolled with a pneumatic tire roller and watered with a commercial water truck.
Construction traffic should not be allowed on the subgrade for 48 hours after the final watering.
This delay allows for the cement to properly hydrate without being disturbed. If at any time
during or after the cement stabilization process it is determined that the subgrade is not
performing as expected, then the problem should be assessed to determine the best course of
action. This may include an additional application of cement.
Pavement Section Thicknesses
We were not provided traffic volumes for the streets, but we assume low traffic volumes. We
assume that the vehicle traffic will consist of automobiles and some trucks. Most of the trucks
Proposed Street & Utility Improvements Page 17 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
will be on the truck routes – Minden Avenue N from 2nd Street NW to 4th Street NW, 4th Street
NW from Minden Avenue N to Main Avenue N and Park Avenue N from US Highway 14 to the
entrance to the grain facility. The pavement surfacing will be asphalt. Table 9 summarizes the
recommended pavement section thicknesses for the project.
Table 9. Recommended Asphalt Pavement Section Thicknesses
Area Asphalt
Pavement Thickness, in
Aggregate Base Course Thickness, in
Granular Subbase
Thickness, in
Subgrade Reinforcement
Cement Stabilization
Light Duty (1) 4 12* ** ** - Light Duty (2) 4 12* *** Geotextile Fabric† Light Duty (3) 4 8 - - Yes**** Heavy Duty (1) 5 12* ** ** - Heavy Duty (2) 5 12* *** Geotextile Fabric† Heavy Duty (3) 5 8 - - Yes****
Notes: The options are (1) scarification and recompaction, (2) subgrade reinforcement and (3) cement stabilization. The heavy duty sections should be used on the truck routes. *The thickness of the aggregate base course may need to be increased with options 1 and 2. **Subgrade reinforcement and granular subbase may be needed with option 1. ***Granular subbase may be needed with option 2 if very poor subgrade conditions are encountered. ****The percentage of cement may need to be increased if very poor subgrade conditions are encountered. †See page 15 for the approved products.
We recommend that routine maintenance such as crack filling, localized patching and seal
coating be performed. The design sections could be reduced if the owner is willing to assume
additional maintenance costs or potentially shorter pavement life.
Unpaved Section Thickness
As previously stated, several of the streets will remain gravel surfaced. We recommend that 4
inches of gravel surfacing over 8 inches of aggregate base course material be used for the
unpaved section thickness. We also recommend installing a geotextile fabric beneath the gravel
surfacing and aggregate base course material. Some maintenance should be expected in the
gravel surfaced areas. We also recommend that the gravel surfaced areas be crowned or sloped to
help shed surface water.
Asphalt Pavement, Aggregate Base Course Material & Gravel Surfacing
The asphalt pavement should meet the requirements of sections 320 and 321 for Class G. We
recommend that the aggregate base course materials and gravel surfacing meet the requirements
Proposed Street & Utility Improvements Page 18 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
of Sections 260 and 882 of the SDDOT Standard Specifications. The aggregate base course
materials and gravel surfacing should be compacted to a minimum of 97 percent of standard
Proctor (ASTM:D698).
Existing Asphalt Pavement, Gravel Base & Gravel Surfacing
Reclaiming of the existing asphalt pavement, gravel base and gravel surfacing for use as
aggregate base course material or gravel surfacing could be considered for the project. Samples
of the reclaimed material should be collected for analysis during construction in order to approve
the material for use as aggregate base course material or gravel surfacing. In our opinion, the
lower 4 inches of the aggregate base course material for the asphalt pavement sections could
consist of recycled material. Also, the aggregate base course material (lower 8 inches) for the
unpaved section could consist of recycle material.
Corrosive Potential
Soil samples were collected from test borings 4, 13 and 19 and were submitted for resistivity,
pH, chloride content and sulfate content testing. The results of the laboratory tests are shown in
Table 10.
Table 10. Laboratory Test Results
Boring Depth (ft) Soil Type Resistivity (ohm-cm)
(as-received)
Resistivity (ohm-cm)
(saturated) pH Chloride
(mg/kg) Sulfate (mg/kg)
4 2 to 7 Lean Clay (FA) 804 737 8.2 17 788
13 2 to 6 Lean Clay w/ Sand (F) 630 583 8.0 22 614
19 7 to 12 Fat Clay w/ Sand (GT) 563 496 7.8 25 2,445
Note: F – existing fill materials, FA – fine alluvium soils and GT – glacial till soils.
The saturated resistivity values ranged from 496 ohm-cm to 737 ohm-cm. Resistivity values
below 1,000 ohm-cm are considered extremely corrosive to metals. The pH levels ranged from
7.8 to 8.2. PH levels below 8.0 can be corrosive to steel and ductile iron. The chloride content
levels ranged from 17 mg/kg to 25 mg/kg. Chloride content levels below 250 mg/kg are
considered mildly corrosive. The sulfate content levels ranged from 614 mg/kg to 2,445 mg/kg.
Proposed Street & Utility Improvements Page 19 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
In general, the sulfate attack on concrete is considered mild if the sulfate content level is below
150 mg/kg, moderate if the sulfate content level is between 150 mg/kg and 1,500 mg/kg and
severe if the sulfate content level is above 1,500 mg/kg. Based on the test results, the potential
sulfate attack on concrete will be moderate to severe. With that said, we recommend using Type
II cement for moderate sulfate attack and Type V cement for severe sulfate attack. It should be
known that high sulfate levels can also accelerate corrosion of metals in direct contact with soil.
With all this said, protective measures should be taken for the project. This discussion should
also apply to the water tower site.
CONSTRUCTION CONSIDERATIONS
Groundwater & Surface Water
Water may enter the excavations due to subsurface water, precipitation or surface run off. Any
water that accumulates in the bottom of the excavations should be immediately removed and
surface drainage away from the excavations should be provided during construction.
Disturbance of Soils
The soils encountered at the test boring locations are susceptible to disturbance and can
experience strength loss caused by construction traffic and/or additional moisture. Precautions
will be required during earthwork activities in order to reduce the risk of soil disturbance. Where
soft/wet soils are encountered, the excavations should be performed with low-ground-pressure
construction equipment or an excavator (backhoe) having a smooth cutting edge on the bucket.
Cold Weather Precautions
If site preparation and construction is anticipated during cold weather, then we recommend all
subgrades, slabs and other improvements that may be affected by frost movements be insulated
from frost penetration during freezing temperatures. If filling is performed during freezing
temperatures, then all frozen soils, snow and ice should be removed from the areas to be filled
prior to placing the new fill. The new fill should not be allowed to freeze during transit,
placement and compaction. Concrete and asphalt should not be placed on frozen subgrades. If
Proposed Street & Utility Improvements Page 20 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
subgrades freeze, then we recommend that the frozen soils be removed and replaced, or
completely thawed. The subgrade soils will likely require reworking and recompacting due to the
loss of density caused by the freeze/thaw process.
Excavation Sideslopes
All excavations must comply with the requirements of OSHA 29 CFR, Part 1926, Subpart P,
“Excavations and Trenches”. This document states that the excavation safety is the responsibility
of the contractor. Reference to this OSHA requirement should be included in the project
specifications.
Observations & Testing
This report was prepared using a limited amount of information for the project and a number of
assumptions were necessary to help us develop our conclusions and recommendations. It is
recommended that our firm be retained to review the geotechnical aspects of the final design
plans and specifications to check that our recommendations have been properly incorporated into
the design documents.
The recommendations submitted in this report have been made based on the subsurface
conditions encountered at the test boring locations. It is possible that there are subsurface
conditions at the site that are different from those represented by the test borings. As a result, on-
site observation during construction is considered integral to the successful implementation of
the recommendations. We believe that qualified field personnel need to be on-site at the
following times to observe the site conditions and effectiveness of the construction.
Excavation
We recommend that a geotechnical engineer or geotechnical engineering technician working
under the direct supervision of a geotechnical engineer observe all excavations for utilities, slabs
and pavements. These observations are recommended to determine if the exposed soils are
similar to those encountered at the test boring locations, if unsuitable soils have been adequately
removed and if the exposed soils are suitable for support of the proposed construction.
Proposed Street & Utility Improvements Page 21 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
Testing
After the subgrade is observed by a geotechnical engineer/technician and approved, we
recommend a representative number of compaction tests be taken during the placement of the
backfill placed below slabs and pavements. The tests should be performed to determine if the
required compaction has been achieved. As a general guideline, we recommend at least 1 test be
taken for every 10,000 square feet of embankment fill placed, at least 1 test for every 500 feet in
trench fill, and for every 2-foot thickness of fill or backfill placed. The actual number of tests
should be left to the discretion of the geotechnical engineer. Samples of proposed fill and backfill
materials should be submitted to our laboratory for testing to determine their compliance with
our recommendations and project specifications.
SUBSURFACE EXPLORATION PROCEDURES
Test Borings
We performed 25 SPT borings on January 21, January 22 and January 23, 2021 with a truck rig
equipped with hollow-stem auger. Soil sampling was performed in accordance with the
procedures described in ASTM:D1586. Using this procedure, a 2-inch O.D. split barrel sampler
is driven into the soil by a 140-pound weight falling 30 inches. After an initial set of 6 inches, the
number of blows required to drive the sampler an additional 12 inches is known as the
penetration resistance, or “N” value. The “N” value is an index of the relative density of
cohesionless soils and the consistency of cohesive soils. In addition, thin walled tube samples
were obtained according to ASTM:D1587, where indicated by the appropriate symbol on the
boring logs.
The test borings were backfilled with on-site materials and some settlement of these materials
can be expected to occur. Final closure of the holes is the responsibility of the client or property
owner.
The soil samples collected from the test boring locations will be retained in our office for a
period of 1 month after the date of this report and will then be discarded unless we are notified
otherwise.
Proposed Street & Utility Improvements Page 22 of 23 Lake Preston, South Dakota GeoTek #21-046
GeoTek Engineering & Testing Services, Inc.
Soil Classification
As the samples were obtained in the field, they were visually and manually classified by the crew
chief according to ASTM:D2488. Representative portions of all samples were then sealed and
returned to the laboratory for further examination and for verification of the field classification.
In addition, select samples were then submitted to a program of laboratory tests. Where
laboratory classification tests (sieve analysis and Atterberg limits) have been performed,
classifications according to ASTM:D2487 are possible. Logs of the test borings indicating the
depth and identification of the various strata, the “N” value, the laboratory test data, water level
information and pertinent information regarding the method of maintaining and advancing the
drill holes are also attached in Appendix A. Charts illustrating the soil classification procedures,
the descriptive terminology and the symbols used on the boring logs are also attached in
Appendix A.
Water Level Measurements
Subsurface groundwater levels should be expected to fluctuate seasonally and yearly from the
groundwater readings recorded at the test boring locations. Fluctuations occur due to varying
seasonal and yearly rainfall amounts and snowmelt, as well as other factors. It is possible that the
subsurface groundwater levels during or after construction could be significantly different than
the time the test borings were performed.
Laboratory Tests
We performed laboratory tests on select samples to aid in determining the index properties of the
soils. The tests consisted of moisture content, dry density, standard Proctor, resistivity, pH,
sulfate content and chloride content. The laboratory tests were performed in accordance with the
appropriate ASTM procedures. The results of the laboratory tests are shown on the boring logs
opposite the samples upon which the tests were performed or on the attached data sheets.
Lake Preston Survey Request
2000 ft
N
➤➤
N© 2020 Google
© 2020 Google
© 2020 Google
1 2 3
4 5 6
9 7 810
11
12
13
15
14
16 17 2223
18 2025
19 21 24
1
2
3
4
5
6
29
21
22
24
24
89
HSA
SPT
SPT
SPT
SPT
SPT
7
17
16
15
15
0.3
0.8
2½
4½
9½
13½
EXISTINGGRAVEL
BASEFILL
FINEALLUVIUM
GLACIALTILL
GLACIALTILL
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 5" thickFILL, MOSTLY LEAN CLAY: a little gravel,dark grayish brown, frozen to 2' then moist
LEAN CLAY: brown and gray, moist, firm,(CL)
LEAN CLAY WITH SAND: a little gravel,brown and gray, moist, very stiff, (CL)
FAT CLAY WITH SAND: a little gravel,brown and dark gray, moist, stiff, (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 1 (1 of 1)
1-21-21------
8:44 am------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-21-21 8:44 amSTART 1-21-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Mike Wagner
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
-wet soils
1
2
3
4
5
6
19
12
15
36
32
HSA
SPT
SPT
SPT
SPT
SPT
9
15
16
9
8
0.3
0.8
3½
9½
13½
EXISTINGGRAVEL
BASEFILL
MIXEDALLUVIUM
FINEALLUVIUM
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 5" thickFILL, MOSTLY LEAN CLAY: a little gravel,dark brown and black, frozen to 2' then moist
SANDY LEAN CLAY: a trace of gravel,brown and gray, moist, stiff to very stiff, (CL)
LEAN CLAY: brown and gray, moist, firm tostiff, (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 2 (1 of 1)
1-21-21------
9:23 am------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-21-21 9:22 amSTART 1-21-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Mike Wagner
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
-wet soils
1
2
3
4
5
6
10
9
23
24
23
HSA
SPT
SPT
SPT
SPT
SPT
11
13
11
14
15
0.7
2½
7
8½
13½
EXISTINGGRAVEL
SURFACINGFINE
ALLUVIUM
COARSEALLUVIUM
GLACIALTILL
GLACIALTILL
FILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 8" thickLEAN CLAY WITH SAND: dark brown tovery dark brown, frozen to 2' then moist, (CL)
SAND WITH SILT: medium grained, darkbrown, moist, medium dense, (SP-SM)
LEAN CLAY WITH SAND: a little gravel,grayish brown, moist, stiff, (CL)
FAT CLAY WITH SAND: a little gravel,brown and gray, moist, stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 3 (1 of 1)
1-21-21------
10:05 am------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-21-21 10:05 amSTART 1-21-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Mike Wagner
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
21
23
19
30
23
100
FA
SPT
SPT
SPT
SPT
SPT
7
8
11
7
10
0.4
2
7
9½
13½
EXISTINGGRAVEL
SURFACINGFILL
FINEALLUVIUM
MIXEDALLUVIUM
GLACIALTILL
FILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 5" thickFILL, MOSTLY LEAN CLAY: a trace ofgravel, black, frozen
LEAN CLAY: grayish brown, moist, firm,(CL)
SANDY LEAN CLAY: brown and gray,moist, stiff, (CL)
LEAN CLAY WITH SAND: a little gravel,brown, moist, firm to stiff, (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 4 (1 of 1)
1-21-21------
3:35 pm------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-21-21 3:35 pmSTART 1-21-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
-wet soils
1
2
3
4
5
6
22
22
24
23
24
99
FA
SPT
SPT
SPT
SPT
SPT
7
10
10
12
11
0.3
0.7
2
4½
13½
EXISTINGGRAVEL
BASEFILL
FINEALLUVIUM
GLACIALTILL
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 4" thickFILL, MOSTLY LEAN CLAY: a trace ofgravel, black, frozenLEAN CLAY: grayish brown, moist, firm,(CL)
FAT CLAY WITH SAND: a little gravel,grayish brown, moist, stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 5 (1 of 1)
1-21-21------
4:15 pm------
12------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-21-21 4:15 pmSTART 1-21-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
19
13
23
23
23
105
HSA
SPT
SPT
SPT
SPT
SPT
8
12
10
11
11
0½
2
4½
6
13½
EXISTINGGRAVEL
SURFACINGFILL
FINEALLUVIUM
COARSEALLUVIUM
GLACIALTILL
FILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 5 1/2" thickFILL, MOSTLY LEAN CLAY: a trace ofgravel, very dark gray, frozen
LEAN CLAY: brown, frozen to 2.5' thenmoist, firm, (CL)
SAND WITH SILT: a trace of gravel, fine tomedium grained, brown, dry, medium dense,(SP-SM)
LEAN CLAY WITH SAND: a little gravel,brown, moist, stiff, (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 6 (1 of 1)
1-21-21------
1:40 pm------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-21-21 1:40 pmSTART 1-21-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
25
26
26
36
24
99
FA
SPT
SPT
SPT
SPT
SPT
7
6
7
9
10
0.30.6
2
3½
11
13½
EXISTINGGRAVEL
BASEFILL
FINEALLUVIUM
FINEALLUVIUM
GLACIALTILL
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 3 1/2" thickFILL, MOSTLY LEAN CLAY: a trace ofgravel, brown and black, frozenFAT CLAY: very dark grayish brown, moist,firm, (CH)
LEAN CLAY: brown and gray, moist, firm, afew lenses of sand between 8' and 11' (CL)
LEAN CLAY WITH SAND: a little gravel,grayish brown, moist, stiff, (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 7 (1 of 1)
1-21-21------
2:55 pm------
11------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-21-21 2:55 pmSTART 1-21-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
-wet soils
1
2
3
4
5
6
21
18
22
21
22
104
HSA
SPT
SPT
SPT
SPT
SPT
7
6
7
10
11
0½
2
4½
7
13½
EXISTINGGRAVEL
SURFACINGFILL
FINEALLUVIUM
GLACIALTILL
GLACIALTILL
FILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 6 1/2" thickFILL, MOSTLY LEAN CLAY: a trace ofgravel, dark gray, frozen
LEAN CLAY: brown, moist, firm, (CL)
SANDY LEAN CLAY: a trace of gravel,brown and gray, moist, firm, (CL)
LEAN CLAY WITH SAND: a little gravel,brown, moist, firm to stiff, (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 8 (1 of 1)
1-21-21------
2:15 pm------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-21-21 2:15 pmSTART 1-21-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
22
23
24
23
23
98
FA
SPT
SPT
SPT
SPT
SPT
7
10
10
12
15
0.6
2
4½
7
9½
13½
EXISTINGGRAVEL
SURFACINGFILL
FINEALLUVIUM
GLACIALTILL
GLACIALTILL
GLACIALTILL
FILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 7" thickFILL, MOSTLY LEAN CLAY: a trace ofgravel, brown and black, frozen
LEAN CLAY: brown, moist, firm, (CL)
LEAN CLAY WITH SAND: a little gravel,grayish brown, moist, stiff, (CL)
FAT CLAY WITH SAND: a little gravel,grayish brown, moist, stiff, (CH)
FAT CLAY WITH SAND: a little gravel, darkgrayish brown, moist, stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 9 (1 of 1)
1-22-21------
9:25 am------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-22-21 9:25 amSTART 1-22-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
7
25
29
34
28
23
98
FA
SPT
BAG
SPT
SPT
SPT
SPT
8
3
7
8
12
2
4½
9½
11
13½
EXISTINGGRAVEL
SURFACING
FINEALLUVIUM
FINEALLUVIUM
GLACIALTILL
GLACIALTILL
FILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 24" thick
LEAN CLAY: very dark gray to black, moist,firm, (CL)
LEAN CLAY: brown, moist to wet, soft tofirm, (CL)
LEAN CLAY WITH SAND: a little gravel,brown, moist, firm, (CL)
FAT CLAY WITH SAND: a little gravel,brown and dark gray, moist, stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 10 (1 of 1)
1-22-21------
10:10 am------
12------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-22-21 10:10 amSTART 1-22-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
-wet soils
1
2
3
4
5
6
7
21
15
18
17
23
102
FA
SPT
SPT
BAG
SPT
SPT
SPT
9
9
10
8
12
0.4
2
4½
12
13½
EXISTINGGRAVEL
BASE
FINEALLUVIUM
MIXEDALLUVIUM
GLACIALTILL
ASPHALT: 5" thick
FILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 19" thick
LEAN CLAY: grayish brown, moist, stiff,(CL)
CLAYEY SAND: fine to medium grained,brown, moist to wet, loose to medium dense,(SC)
LEAN CLAY WITH SAND: a little gravel,brown, moist, stiff, (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 11 (1 of 1)
1-22-21------
11:14 am------
7.5------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-22-21 11:14 amSTART 1-22-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
20
9
10
12
24
101
FA
SPT
SPT
SPT
SPT
SPT
9
11
10
6
8
0.4
0.9
2
4½
12
13½
EXISTINGGRAVEL
BASEFILL
FINEALLUVIUM
MIXEDALLUVIUM
GLACIALTILL
ASPHALT: 5" thick
FILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 6" thickFILL, MOSTLY LEAN CLAY: a little gravel,dark brown and black, frozenLEAN CLAY: grayish brown, moist, stiff, afew lenses of sand (CL)
CLAYEY SAND: a little gravel, fine tomedium grained, brown and dark brown,moist to wet, loose to medium dense, (SC)
FAT CLAY WITH SAND: a little gravel,brown, moist, firm, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 12 (1 of 1)
1-22-21------
11:55 am------
12------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-22-21 11:55 amSTART 1-22-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
7
26
21
34
36
33
95
FA
SPT
SPT
BAG
SPT
SPT
SPT
6
6
8
7
7
0.4
0.8
2
6
13½
EXISTINGGRAVEL
BASEFILL
FILL
FINEALLUVIUM
ASPHALT: 5" thick
FILL, MOSTLY CLAYEY SAND: a trace of,fine to medium grained, brown, frozen, 4"thickFILL, MOSTLY LEAN CLAY: very darkbrown and black, frozenFILL, MOSTLY LEAN CLAY WITH SAND: alittle gravel, brown and gray, moist
LEAN CLAY: brown and gray, moist to wet,firm, a few lenses of sand at 11' (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 13 (1 of 1)
1-22-21------
12:40 pm------
8.5------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-22-21 12:40 pmSTART 1-22-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
-wet soils
1
2
3
4
5
6
19
14
21
23
22
104
FA
SPT
SPT
SPT
SPT
SPT
7
13
12
11
16
0.30½
2
4½
6
8½
12
13½
EXISTINGGRAVEL
BASEFILL
FILL
MIXEDALLUVIUM
FINEALLUVIUM
GLACIALTILL
GLACIALTILL
ASPHALT: 3 1/2" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 3" thickFILL, MOSTLY LEAN CLAY: a little gravel,dark brown and black, frozenFILL, MOSTLY LEAN CLAY: brown andgray, moist
SANDY LEAN CLAY: brown and gray,moist, stiff, (CL)
LEAN CLAY: brown and gray, moist, stiff,(CL)
LEAN CLAY WITH SAND: a little gravel,grayish brown and gray, moist, stiff, (CL)
FAT CLAY WITH SAND: a little gravel, darkgrayish brown, moist, very stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 14 (1 of 1)
1-22-21------
2:10 pm------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-22-21 2:10 pmSTART 1-22-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
7
21
26
34
24
23
103
FA
SPT
SPT
BAG
SPT
SPT
SPT
7
7
8
11
13
0.30½
2
4½
9½
13½
EXISTINGGRAVEL
BASEFILL
FINEALLUVIUM
FINEALLUVIUM
GLACIALTILL
ASPHALT: 3 1/2" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 3" thickFILL, MOSTLY LEAN CLAY: a little gravel,dark brown and black, frozenLEAN CLAY: brown, moist, firm, (CL)
LEAN CLAY: brown and gray, moist, firm,(CL)
FAT CLAY WITH SAND: a little gravel,brown and gray, moist, stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 15 (1 of 1)
1-22-21------
1:35 pm------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-22-21 1:35 pmSTART 1-22-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
-wet soils
1
2
3
4
5
6
26
25
32
23
24
93
FA
SPT
SPT
SPT
SPT
SPT
6
7
7
10
14
0.3
0.8
4½
7
9½
13½
EXISTINGGRAVEL
BASEFILL
FINEALLUVIUM
FINEALLUVIUM
GLACIALTILL
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 5" thickFILL, MOSTLY LEAN CLAY: a trace ofgravel, grayish brown and black, frozen to 2'then moist
LEAN CLAY: brown, moist, firm, (CL)
LEAN CLAY: brown and gray, moist, firm,(CL)
LEAN CLAY WITH SAND: a little gravel,grayish brown, moist, stiff, (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 16 (1 of 1)
1-22-21------
2:51 pm------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-22-21 2:51 pmSTART 1-22-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
-wet soils
1
2
3
4
5
6
7
21
25
25
22
23
99
FA
SPT
SPT
SPT
BAG
SPT
SPT
6
6
8
10
15
0½
0.9
4½
7
12
13½
EXISTINGGRAVEL
BASEFILL
FINEALLUVIUM
GLACIALTILL
GLACIALTILL
ASPHALT: 5 1/2" thick
FILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 5 1/2" thickFILL, MOSTLY LEAN CLAY: a trace ofgravel, very dark brown and black, frozen to2' then moist
LEAN CLAY: brown and gray, moist, firm,(CL)
LEAN CLAY WITH SAND: a little gravel,grayish brown, moist, stiff, (CL)
FAT CLAY WITH SAND: brown and darkgray, moist, stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 17 (1 of 1)
1-22-21------
3:30 pm------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-22-21 3:30 pmSTART 1-22-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
24
21
22
22
23
101
FA
SPT
SPT
SPT
SPT
SPT
11
9
15
15
15
0.30.6
2
3½
7
12
13½
EXISTINGGRAVEL
BASEFILL
FINEALLUVIUM
FINEALLUVIUM
GLACIALTILL
GLACIALTILL
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 3" thickFILL, MOSTLY LEAN CLAY: a trace ofgravel, black and dark gray, frozenFAT CLAY: dark grayish brown, moist, stiff,(CH)
LEAN CLAY: brown and gray, moist, stiff,(CL)
LEAN CLAY WITH SAND: a little gravel,brown and gray, moist, stiff, (CL)
FAT CLAY WITH SAND: a little gravel,grayish brown, moist, stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 18 (1 of 1)
1-22-21------
4:05 pm------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD6" Flight Auger
DEPTHin
FEET
COMPLETE 1-22-21 4:05 pmSTART 1-22-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Roy Hanson
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
22
22
25
23
24
100
HSA
SPT
SPT
SPT
SPT
SPT
7
5
7
8
10
0.3
0.7
7
13½
EXISTINGGRAVEL
BASEFILL
GLACIALTILL
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 4" thickFILL, MOSTLY LEAN CLAY: brown, frozento 2' then moist
FAT CLAY WITH SAND: a little gravel,brown, moist, firm to stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 19 (1 of 1)
1-23-21------
8:48 am------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-23-21 8:48 amSTART 1-23-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Mike Wagner
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
22
25
19
HSA
SPT
SPT
SPT
7
3
9
0.3
0.9
10
EXISTINGGRAVEL
BASEFILL
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 7" thickFILL, MOSTLY LEAN CLAY: a trace ofgravel, brown, frozen to 2' then moist
Bottom of borehole at 10 feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
11------
CASINGDEPTH
CAVE-INDEPTH
10------
WATERLEVEL
BORING NO. 20 (1 of 1)
1-23-21------
9:54 am------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-23-21 9:54 amSTART 1-23-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Mike Wagner
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
22
23
22
21
29
95
HSA
SPT
SPT
SPT
SPT
SPT
7
6
9
10
8
0.30.6
2½
4½
7
13½
EXISTINGGRAVEL
BASEFILL
FINEALLUVIUM
FINEALLUVIUM
FINEALLUVIUM
ASPHALT: 3" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 4" thickFILL, MOSTLY LEAN CLAY: very darkbrown, frozen to 2' then moist
LEAN CLAY: very dark brown, moist, firm,(CL)
LEAN CLAY: light grayish brown, moist,firm, (CL)
LEAN CLAY: brown and gray, moist, firm tostiff, (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 21 (1 of 1)
1-23-21------
9:15 am------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-23-21 9:15 amSTART 1-23-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Mike Wagner
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
26
23
22
21
90
HSA
SPT
SPT
SPT
SPT
SPT
10
9
8
10
15
0½
2
4½
7
9½
12
13½
EXISTINGGRAVEL
SURFACINGFILL
TOPSOIL
FINEALLUVIUM
FINEALLUVIUM
GLACIALTILL
GLACIALTILL
FILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 6" thickFILL, MOSTLY LEAN CLAY: brown, frozen
LEAN CLAY: black, moist, stiff, (CL)
LEAN CLAY: dark grayish brown, moist,stiff, (CL)
LEAN CLAY: brown and gray, moist, firm,(CL)
LEAN CLAY WITH SAND: a little gravel,brown, moist, stiff, (CL)
FAT CLAY WITH SAND: a little gravel,brown, moist, stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 22 (1 of 1)
1-23-21------
10:28 am------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-23-21 10:28 amSTART 1-23-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Mike Wagner
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
7
24
23
22
22
24
100
HSA
SPT
BAG
SPT
SPT
SPT
SPT
10
9
9
12
14
0.3
0.8
2
13½
EXISTINGGRAVEL
BASEFILL
GLACIALTILL
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 6" thickFILL, MOSTLY LEAN CLAY WITH SAND: alittle gravel, brown, frozenFAT CLAY WITH SAND: a little gravel,brown and gray, moist, stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 23 (1 of 1)
1-23-21------
10:53 am------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-23-21 10:53 amSTART 1-23-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Mike Wagner
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
20
19
24
24
22
107
HSA
SPT
SPT
SPT
SPT
SPT
8
7
3
8
10
0.30.6
9½
13½
EXISTINGGRAVEL
BASEFILL
GLACIALTILL
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 3" thickFILL, MOSTLY LEAN CLAY: brown anddark brown, frozen to 2' then moist
LEAN CLAY WITH SAND: a little gravel,brown and gray, moist, firm to stiff, (CL)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 24 (1 of 1)
1-23-21------
11:24 am------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-23-21 11:24 amSTART 1-23-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Mike Wagner
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
1
2
3
4
5
6
17
19
13
23
24
HSA
SPT
SPT
SPT
SPT
SPT
11
11
14
12
15
0.30.6
3½
9½
13½
EXISTINGGRAVEL
BASEFILL
GLACIALTILL
GLACIALTILL
ASPHALT: 4" thickFILL, MOSTLY CLAYEY SAND: a littlegravel, fine to medium grained, brown,frozen, 3" thickFILL, MOSTLY LEAN CLAY WITH SAND: alittle gravel, brown, frozen to 2' then moist
SANDY LEAN CLAY: a little gravel, brownand gray, moist, stiff, (CL)
FAT CLAY WITH SAND: a little gravel,brown, moist, stiff, (CH)
Bottom of borehole at 13½ feet.
--------
LABORATORY TESTS
DATE TIME SAMPLEDDEPTH
GEOTECHNICAL TEST BORING LOG
13.5------
CASINGDEPTH
CAVE-INDEPTH
12------
WATERLEVEL
BORING NO. 25 (1 of 1)
1-23-21------
12:03 pm------
none------
PROJECT Proposed Street & Utility Improvements, Lake Preston, SD
NO. WC D PL QULLTYPEN
GE
OT
EC
HN
ICA
L T
ES
T B
OR
ING
21-
046
.GP
J G
EO
TE
KE
NG
.GD
T 1
/29/
21
GEOTEK # 21-046
WATER LEVEL MEASUREMENTS
METHOD3.25" ID Hollow Stem Auger
DEPTHin
FEET
COMPLETE 1-23-21 12:03 pmSTART 1-23-21
909 E 50th St NSioux Falls, South Dakota, 57104605-335-5512 [email protected]
GEOLOGICORIGIN
CREW CHIEF Mike Wagner
SAMPLE
GEOTEK ENGINEERING& TESTING SERVICES, INC.
DESCRIPTION OF MATERIALWL
SILTY GRAVELS, GRAVEL - SAND -SILT MIXTURES
ORGANIC CLAYS OF MEDIUM TO HIGHPLASTICITY, ORGANIC SILTS
PEAT, HUMUS, SWAMP SOILS WITHHIGH ORGANIC CONTENTS
LETTERGRAPHSYMBOLSMAJOR DIVISIONS
COARSEGRAINED
SOILS
TYPICALDESCRIPTIONS
GRAVELAND
GRAVELLYSOILS POORLY-GRADED GRAVELS, GRAVEL
- SAND MIXTURES, LITTLE OR NOFINES
FINEGRAINED
SOILS
CLEANGRAVELS
GRAVELS WITHFINES
CLEAN SANDS
(LITTLE OR NO FINES)
SANDS WITHFINES
LIQUID LIMITLESS THAN 50
LIQUID LIMITGREATER THAN 50
HIGHLY ORGANIC SOILS
WELL-GRADED GRAVELS, GRAVEL -SAND MIXTURES, LITTLE OR NO FINES
SILTSAND
CLAYS
CLAYEY GRAVELS, GRAVEL - SAND -CLAY MIXTURES
WELL-GRADED SANDS, GRAVELLYSANDS, LITTLE OR NO FINES
POORLY-GRADED SANDS, GRAVELLYSAND, LITTLE OR NO FINES
SILTY SANDS, SAND - SILT MIXTURES
CLAYEY SANDS, SAND - CLAYMIXTURES
INORGANIC SILTS AND VERY FINESANDS, ROCK FLOUR, SILTY ORCLAYEY FINE SANDS OR CLAYEYSILTS WITH SLIGHT PLASTICITY
INORGANIC CLAYS OF LOW TOMEDIUM PLASTICITY, GRAVELLYCLAYS, SANDY CLAYS, SILTY CLAYS,LEAN CLAYS
ORGANIC SILTS AND ORGANIC SILTYCLAYS OF LOW PLASTICITY
SILTSAND
CLAYS
INORGANIC CLAYS OF HIGHPLASTICITY
SANDAND
SANDYSOILS
MORE THAN 50%OF MATERIAL IS
LARGER THAN NO.200 SIEVE SIZE
MORE THAN 50%OF MATERIAL ISSMALLER THANNO. 200 SIEVE
SIZE
MORE THAN 50%OF COARSEFRACTION
PASSING ON NO. 4SIEVE
MORE THAN 50%OF COARSEFRACTION
RETAINED ON NO.4 SIEVE
SOIL CLASSIFICATION CHART
(APPRECIABLE AMOUNTOF FINES)
(APPRECIABLE AMOUNTOF FINES)
(LITTLE OR NO FINES)
INORGANIC SILTS, MICACEOUS ORDIATOMACEOUS FINE SAND OR SILTYSOILS
NOTE: DUAL SYMBOLS ARE USED TO INDICATE BORDERLINE SOIL CLASSIFICATIONS
GW
GP
GM
GC
SW
SP
SM
SC
ML
CL
OL
MH
CH
OH
PT
BORING LOG SYMBOLS AND DESCRIPTIVE TERMINOLOGY
GeoTek Engineering & Testing Services, Inc.
SYMBOLS FOR DRILLING AND SAMPLING
Symbol Definition Bag Bag sample CS Continuous split-spoon sampling DM Drilling mud FA Flight auger; number indicates outside diameter in inches HA Hand auger; number indicates outside diameter in inches HSA Hollow stem auger; number indicates inside diameter in inches LS Liner sample; number indicates outside diameter of liner sample N Standard penetration resistance (N-value) in blows per foot NMR No water level measurement recorded, primarily due to presence of drilling fluid
NSR No sample retrieved; classification is based on action of drilling equipment and/or material noted in drilling fluid or on sampling bit
SH Shelby tube sample; 3-inch outside diameter SPT Standard penetration test (N-value) using standard split-spoon sampler SS Split-spoon sample; 2-inch outside diameter unless otherwise noted WL Water level directly measured in boring ▼ Water level symbol
SYMBOLS FOR LABORATORY TESTS
Symbol Definition WC Water content, percent of dry weight; ASTM:D2216 D Dry density, pounds per cubic foot LL Liquid limit; ASTM:D4318 PL Plastic limit; ASTM:D4318 QU Unconfined compressive strength, pounds per square foot; ASTM:D2166
DENSITY/CONSISTENCY TERMINOLOGY
Density Consistency Term N-Value Term Very Loose 0-4 Soft Loose 5-8 Firm Medium Dense 9-15 Stiff Dense 16-30 Very Stiff Very Dense Over 30 Hard
DESCRIPTIVE TERMINOLOGY
Term Definition Dry Absence of moisture, powdery Frozen Frozen soil Moist Damp, below saturation Waterbearing Pervious soil below water Wet Saturated, above liquid limit Lamination Up to ½” thick stratum Layer ½” to 6” thick stratum Lens ½” to 6” discontinuous stratum
PARTICLE SIZES
Term Particle Size Boulder Over 12” Cobble 3” – 12” Gravel #4 – 3” Coarse Sand #10 – #4 Medium Sand #40 – #10 Fine Sand #200 – #40 Silt and Clay passes #200 sieve
GRAVEL PERCENTAGES
Term Range A trace of gravel 2-4% A little gravel 5-15% With gravel 16-50%
GEOTEK ENGINEERING& TESTING SERVICES, INC.909 East 50th Street NorthSioux Falls, SD 57104605-335-5512 Fax 605-335-0773www.geotekeng.com
REPORTED TO: PROJECT: 21-046 COPIES TO:
DATE REPORTED:
Sample No.: 1 Date Received:ASTM Test Method: D698B Manual Date Tested:
Soil Classification: Lean Clay, Very Dark Brown (CL)
Remarks:
Maximum Density, pcf:
Optimum Moisture, %:
Percent Passing, %:3/4":3/8":#4:#200:
Atterberg Limits (ASTM: D4318):Liquid Limit:Plastic Limit:Plasticity Index:
Nick Bierle, Staff Engineer
101.1
21.1
SAMPLE DATA
TEST DATA
MOISTURE - DENSITY TEST REPORT
1/25/2021
SB 10 (2' to 4 1/2')
1/29/2021
1/29/2021
10010010088
80
85
90
95
100
105
110
115
120
125
130
135
140
0 5 10 15 20 25 30 35 40
DR
Y D
ENSI
TY (
pcf)
MOISTURE CONTENT (%)
Curve for 100% saturation for specific gravity equal to 2.65
Proposed Street & Utility ImprovementsLake Preston, SD
Banner Associates, Inc. (Brookings)Pat Carey409 22nd Avenue SouthBrookings, SD 57006
GEOTEK ENGINEERING& TESTING SERVICES, INC.909 East 50th Street NorthSioux Falls, SD 57104605-335-5512 Fax 605-335-0773www.geotekeng.com
REPORTED TO: PROJECT: 21-046 COPIES TO:
DATE REPORTED:
Sample No.: 2 Date Received:ASTM Test Method: D698B Manual Date Tested:
Soil Classification: Lean Clay, Grayish Brown (CL)
Remarks:
Maximum Density, pcf:
Optimum Moisture, %:
Percent Passing, %:3/4":3/8":#4:#200:
Atterberg Limits (ASTM: D4318):Liquid Limit:Plastic Limit:Plasticity Index:
Nick Bierle, Staff Engineer
103.9
19.4
SAMPLE DATA
TEST DATA
MOISTURE - DENSITY TEST REPORT
1/25/2021
SB 13 (6' to 10')
1/29/2021
1/22/2021
10010010086
80
85
90
95
100
105
110
115
120
125
130
135
140
0 5 10 15 20 25 30 35 40
DR
Y D
ENSI
TY (
pcf)
MOISTURE CONTENT (%)
Curve for 100% saturation for specific gravity equal to 2.65
Proposed Street & Utility ImprovementsLake Preston, SD
Banner Associates, Inc. (Brookings)Pat Carey409 22nd Avenue SouthBrookings, SD 57006
GEOTEK ENGINEERING& TESTING SERVICES, INC.909 East 50th Street NorthSioux Falls, SD 57104605-335-5512 Fax 605-335-0773www.geotekeng.com
REPORTED TO: PROJECT: 21-046 COPIES TO:
DATE REPORTED:
Sample No.: 3 Date Received:ASTM Test Method: D698B Manual Date Tested:
Soil Classification: Lean Clay, Brown (CL)
Remarks:
Maximum Density, pcf:
Optimum Moisture, %:
Percent Passing, %:3/4":3/8":#4:#200:
Atterberg Limits (ASTM: D4318):Liquid Limit:Plastic Limit:Plasticity Index:
Nick Bierle, Staff Engineer
102.5
19.4
SAMPLE DATA
TEST DATA
MOISTURE - DENSITY TEST REPORT
1/26/2021
SB 15 (4 1/2' to 9 1/2')
1/29/2021
1/22/2021
10010010087
80
85
90
95
100
105
110
115
120
125
130
135
140
0 5 10 15 20 25 30 35 40
DR
Y D
ENSI
TY (
pcf)
MOISTURE CONTENT (%)
Curve for 100% saturation for specific gravity equal to 2.65
Proposed Street & Utility ImprovementsLake Preston, SD
Banner Associates, Inc. (Brookings)Pat Carey409 22nd Avenue SouthBrookings, SD 57006
GEOTEK ENGINEERING& TESTING SERVICES, INC.909 East 50th Street NorthSioux Falls, SD 57104605-335-5512 Fax 605-335-0773www.geotekeng.com
REPORTED TO: PROJECT: 21-046 COPIES TO:
DATE REPORTED:
Sample No.: 4 Date Received:ASTM Test Method: D698B Manual Date Tested:
Soil Classification: Lean Clay with Sand, Brown (CL)
Remarks:
Maximum Density, pcf:
Optimum Moisture, %:
Percent Passing, %:3/4":3/8":#4:#200:
Atterberg Limits (ASTM: D4318):Liquid Limit:Plastic Limit:Plasticity Index:
Nick Bierle, Staff Engineer
104.0
19.6
SAMPLE DATA
TEST DATA
MOISTURE - DENSITY TEST REPORT
1/27/2021
SB 17 (7' to 12')
1/29/2021
1/22/2021
10010010076
80
85
90
95
100
105
110
115
120
125
130
135
140
0 5 10 15 20 25 30 35 40
DR
Y D
ENSI
TY (
pcf)
MOISTURE CONTENT (%)
Curve for 100% saturation for specific gravity equal to 2.65
Proposed Street & Utility ImprovementsLake Preston, SD
Banner Associates, Inc. (Brookings)Pat Carey409 22nd Avenue SouthBrookings, SD 57006
GEOTEK ENGINEERING& TESTING SERVICES, INC.909 East 50th Street NorthSioux Falls, SD 57104605-335-5512 Fax 605-335-0773www.geotekeng.com
REPORTED TO: PROJECT: 21-046 COPIES TO:
DATE REPORTED:
Sample No.: 5 Date Received:ASTM Test Method: D698B Manual Date Tested:
Soil Classification: Fat Clay with Sand, Brown (CH)
Remarks:
Maximum Density, pcf:
Optimum Moisture, %:
Percent Passing, %:3/4":3/8":#4:#200:
Atterberg Limits (ASTM: D4318):Liquid Limit:Plastic Limit:Plasticity Index:
Nick Bierle, Staff Engineer
102.4
21.1
SAMPLE DATA
TEST DATA
MOISTURE - DENSITY TEST REPORT
1/26/2021
SB 23 (3' to 8')
1/29/2021
1/22/2021
10010010079
80
85
90
95
100
105
110
115
120
125
130
135
140
0 5 10 15 20 25 30 35 40
DR
Y D
ENSI
TY (
pcf)
MOISTURE CONTENT (%)
Curve for 100% saturation for specific gravity equal to 2.65
Proposed Street & Utility ImprovementsLake Preston, SD
Banner Associates, Inc. (Brookings)Pat Carey409 22nd Avenue SouthBrookings, SD 57006