georgia #18, 2012
DESCRIPTION
Georgia #18, 2012TRANSCRIPT
By Cindy RileyCEG CORRESPONDENT
Major construction at South GeorgiaMedical Center (SGMC) promises signifi-cant change at the non-profit hospital. Crewsin Valdosta are putting in long hours, work-ing to complete projects ranging from apatient tower, a new parking deck, infusionroom and generator building. Drainageupgrades and nursing station renovationsalso are among the hospital’s recentimprovements and renovations.“We are working an average of 50 trades-
men right now,” explained Mark Fernung,senior project manager of general contractorRobins & Morton of Valdosta, Ga., which isoverseeing the patient tower project. “Weshould peak around 250.”The tower expansion and renovation
involves approximately 127,000 sq. ft.(11,798 sq m) of new construction with thefive-story patient tower construction and8,000 sq. ft. (743 sq m) of renovation.According to Fernung, working in the some-what confined space has been a challenge,along with keeping the existing areas func-tional and operating.Some of the equipment included as part of
the job are cath labs, ceiling booms andpatient lifts. The patient tower calls for 8,500cu. yds. (6,498 cu m) of concrete, 850 tons(771 t) of reinforcing steel, 48,000 sq. ft.(4,459 sq m) of precast concrete, 180 tons(163 t) of structural steel, 20,000 sq. ft.(1,858 sq m) of metal panels, 17,000 sq. ft.(1,579 sq m) of glass and six new elevators.Crews hope to complete work on the towerby next summer.Half a dozen locations were evaluated
before deciding on the current site for thepatient tower, which is next to the outpatientcenter. The main floor of the new construc-tion will house the Dasher Heart Centerdiagnostics and cath labs. The second floorof the tower is slated for the CardiacProgressive Unit. The third floor will housethe CICU, and the fourth floor will serve asthe M/S ICU. A specialized surgical unit willbe on the fifth floor. A bridge will connectthe existing hospital with the new patient
tower. Chuck Smith, owner of Cauthan
Construction Company Inc. said the SGMCCancer Center expansion/renovaton and thenew hospital parking deck both began inJune 2011. “Both projects are in the final stages of
construction with occupancy in approxi-mately 45 days. Some of the biggest chal-lenges or concerns on this project haveincluded infection control, noise, parkingand maintaining services to SGMC. Also,because we’re working through an existingbuilding to enclose a courtyard and buildingover an existing detention pond, weatherwas a concern and a variable every day.” Equipment used by Cauthan’s crews
included a tower crane, mobile cranes, boomtruck, concrete pumps, backhoes, bulldoz-ers, excavators, dump trucks, power bug-gies, demo equipment, concrete finishingequipment and pneumatic equipment.Materials have included structural fill,ready-mix concrete, masonry, metal studs,
EIFS, hollow metal wood, door, pre-castconcrete, aluminum storefront/curtain walland structural steel. The Cancer Center expansion includes 27
infusion bays and calls for fresh paint, floor-ing, cabinetry and new furniture as part ofthe renovation. The parking deck, mean-while, is expected to feature a walkway fromthe deck to the main cafeteria hallway. Smith added, “These two feature projects
are a successful reality due to the pre-plan-ning and the close working/team relation-ship with our client, our design team and our
many sub-contractors and suppliers.”Valdosta Mechanical Co. Inc. CEO
Jimmy Scruggs says coordination is crucialon a project of this magnitude.“We’re responsible for the
mechanical/HVAC work. We started on thebridge connector addition in March of 2012,and will start physical work on the patienttower in September. We are almost finishedwith the Cancer Center addition/renovationwhich started in late 2011, and have juststarted working in the new parking deck.”Valdosta Mechanical is working on the
new generator building, and has just com-pleted the air handling unit replacement,which is three projects combined into one,replacing air handling units for operatingrooms and adjacent spaces, lab area and theradiology area.“Access to the site and coordination with
other trades to make sure the owner hasaccess to all components involved formaintenance is one of the biggest chal-lenges. Hospitals have a lot more serv-ices than most buildings, but the allot-ted space never seems to increase pro-portionally. Chilled water piping,steam, heating water, supply duct,return duct, exhaust duct, fire protec-tion piping, medical gases, domesticwater, sanitary, and storm piping areall trying to fit into some very tightspaces. We are using building infor-mation modeling (BMI) to helpaccomplish this on the patient tower. “It’s even more challenging on the
renovation areas,” Scruggs explained.“There are existing spaces so tight wecan’t even remove the ceiling tiles.
We’ve also had issues dealing with some ofthe existing systems old enough that no oneknows where or what many of the compo-nents are. We’ve tracked and found dampersclosed, blocking air to different areas, foundin-line pumps no one knew the purpose of,found piping that had eroded bad enough tostop up the HW system, etc. These are issuestypical in an aging facility that can’t be pre-dicted. SGMC has been good about workingwith us on these issues, but it takes a lot of
SGMC Undergoes Extensive Renovations, Improvements
GEORGIA STATE EDITION A Supplement to:
Your Georgia Connection: Rich Olivier, Atlanta, GA • 1-800-409-1479
“The Nation’s Best Read Construction Newspaper… Founded in 1957.”Bainbridge
Macon
Albany
Athens
Atlanta
Augusta
Columbus
Rome
Savannah
ValdostaThomasville
Moul- trie
Tifton
Blakely
Cuthbert
CordeleMcRae
Douglas
La Grange
Ameri- cus
Milledgeville
DublinOak Park
Lyons
Dorchester
Waycross Bruns- wickPearson
Statesboro
Swainsboro
Griffin
Madison
Cornella75
75
75
16
16
20
20
85
59
185
95
85
27
19
441
441
441
441
19
19
27
82
27
82
82
341
341
1301
301
84
8484319
82
1129
1
Photo courtesy of Aero PhotoWorking in the somewhat confinedspace has been a challenge, along withkeeping the existing areas functionaland operating.
see SGMC page 6
September 52012
Vol. XIV • No. 18
Core drilling for the new patient tower keptcrews busy as they worked on one of SGMC’shighest profile projects.
Page 2 • September 5, 2012 • www.constructionequipmentguide.com • Georgia State Supplement • Construction Equipment Guide
REALACall or stop by today for a FREE demo to see why Bobcat is the industr
REALCall or stop by today for a FREE demo to see why Bobcat is the industr
HASCall or stop by today for a FREE demo to see why Bobcat is the industr
NOHASCall or stop by today for a FREE demo to see why Bobcat is the industr
y leaderCall or stop by today for a FREE demo to see why Bobcat is the industr
.y leader
Construction Equipment Guide • Georgia State Supplement • www.constructionequipmentguide.com • September 5, 2012 • Page 3
We didn’t reinvent the wheeljust the skid steerThe revolutionary full range of JCB skid steers
Redesigned from the inside out here in Georgia
LO C AT I O N S
JOIN THE SKID STEER REVOLUTIONwww.jcbamericas.com/ss3
Service: Industry-l
eading access
to various service point
s Comfort: Up to 46% more cab space,
quietest cab in the industry
Visibility:270° of total visibility60% better than the competition
Safety: First and only skid steerwith a side door making it the world’s safest
World’s most fuel
DWUSA 3197
Headquarters1008 E Hwy 80
Pooler, GA 31322(888) 809-3612
Kennesaw2679 Barrett Lakes Blvd
Kennesaw, GA 30144(678) 594-5400
Augusta4008 Mike Padgett Hwy
Augusta, GA 30906(706) 798-6115www.jcbofgeorgia.com
Page 4 • September 5, 2012 • www.constructionequipmentguide.com • Georgia State Supplement • Construction Equipment Guide Construction Equipment Guide • Georgia State Supplement • www.constructionequipmentguide.com • September 5, 2012 • Page 5
For more information please contact your Yancey Machine Sales Representative today. (800) 282-1562 www.YanceyBros.com
Page 4 • September 5, 2012 • www.constructionequipmentguide.com • Georgia State Supplement • Construction Equipment Guide Construction Equipment Guide • Georgia State Supplement • www.constructionequipmentguide.com • September 5, 2012 • Page 5
For more information please contact your Yancey Machine Sales Representative today. (800) 282-1562 www.YanceyBros.com
Page 6 • September 5, 2012 • www.constructionequipmentguide.com • Georgia State Supplement • Construction Equipment Guide
time to resolve.“The patient tower is the largest
project,” Scruggs went on. “It’sfive stories with a new heart centeron the first floor, and patient roomson the upper four floors. We areinstalling five custom air handlingunits with fan walls totaling140,000 cfm, two in the basementand three in penthouses to servethe building, three new boilerstotaling 350 hp for heating water,chilled water piping connecting tothe existing plant to provide 560tons of cooling, nine individualcomputer room units totaling 45tons, steam connecting to the exist-ing plant for humidification, and244 VAV boxes along with inter-connecting supply, return, andexhaust duct.“The air handling unit project
consists of removing and replacingfour each air custom handling unitswith fan walls totaling 96,600 cfm,while the spaces being served areoccupied, three new glycol sub-cooling chillers, and a new steamfed heating water system. We hadabout five days from shut down togetting each space back under fullcontrol. This required a lot of prepwork, planning, and coordinationwith each department. The operat-ing room systems were done one ata time, so the hospital always hadat least half their eight rooms in useat any one time. During that time,we also installed new operatingroom pressure and status monitor-ing and connected them to thefacility automation system. Whenfinished, the units deliver 37-degree Farenheit air and maintainthe rooms as low as 62 degreesFarenheit at 42 percent relativehumidity and can raise or lower thespace temperature 10 degreesFarenheit in each individual oper-ating room in about 11 minutes.We had to install a 20,000 cfmtemporary unit connected to facili-ty utilities for the radiology unit tokeep it in service and the machin-ery cool while we were replacingthe main unit and used spot coolersto maintain temperature in the labwhile that unit was being changedout.”According to Scruggs, the
Cancer Center addition and reno-vations involved installing a new9,000 cfm custom rooftop unitwith fan walls, 21 each VAV termi-nal units, HW and CHW piping to
connect the equipment to the exist-ing facility utilities, and associatedduct work and distribution pumps.The parking deck and bridge
connector involve installing multi-ple fan coil units and associatedHW and CHW piping to connectthe new equipment to the existingfacility utilities. The power plantproject involves a new fuel systemand associated tanks and piping,including a new 30,000 gal. UGtank, three new 400 gal. day tanks,and temporarily relocating theexisting 10,000 gal. tank, and pro-viding 25 tons of cooling for thenew generator building.The air handling units are all
made by Temptrol. Pumps are allB&G. Computer room units are allLiebert. VAV boxes are all JCI.Crews will be using 200,000 lbs.(90,718 kg) of sheet metal, 23,000ft. (7,010 m) of piping, 23,000 ft.of piping insulation and 170,000sq. ft. (15,793 sq m) of duct insula-tion.“Weather has not impacted us so
far but has impacted the project asa whole while the basement iscoming out of the ground. With allof these projects going on at thesame time, logistics are a night-mare. We are involved on all ofthem, but each one has a differentprime contractor. We were theprime contractor on the air han-dling unit project. Coordinatingwhat is happening and when oneach project to be able to controlgetting materials in and out wherewe need them has been tough, buteveryone has worked togetherbetween the different projects verywell. “We are prefabricating and
using our warehouse as much aspossible, delivering material andequipment to the site only as need-ed to minimize any lay down spaceand protect the materials to main-tain the quality and cleanlinessrequired in a medical facility.When all of these projects are fin-ished, SGMC and the communityas a whole will have one of the topmedical centers in the region.” Ashley Paulk, president of
Valdosta Electrical, predicts hiscrews will go through roughly amillion ft. (304,800 m) of wire andapproximately 250,000 ft. (76,200m) of pipe as they continue workon the patient tower.“We’re using scissor lifts, Gehl
loaders to move dirt, John Deere
backhoes, John Deere mini exca-vators and a John Deere 330 exca-vator,” Paulk said, “We needed thelarger one because we’re as deepas 23 feet to get down to the base-ment.”“In addition to the tower, we’re
actually doing the central energyplant that feeds the entire project.Our work here has involved a lot ofcoordination and planning.Anytime you’re adding on to abuilding, it’s a different environ-ment. And in a hospital environ-
ment, you must be extra cautiousin doing any kind of shutdown.You have to be careful not to turnoff any critical service that couldput someone’s life at risk.”Hogan Pullin, CEO of Erickson
Plumbing of Valdosta, Ga., statedthat his company was responsiblefor plumbing and medical gas,beginning in December 2011.“Accurate coordination and
placement of nearly 1,000 sleevesfor pipes penetrating the concretefloors is the greatest challenge on a
project of this nature,” Pullin said.“Doing so requires a great amountof effort to locate every sleeve onthe plywood forms before the con-crete is poured, so each pipe, fix-ture and drain is in its correct loca-tion.” Pullin also said that prefabricat-
ing as much practical in-walldomestic water and medical gas,and as much overhead sanitarypiping as practical, was key. “This is done to maximize pro-
duction while building the pipingsections and minimize the fieldlabor needed in installing the pip-ing.”Kohler plumbing fixtures were
used, along with Amico medicalgas equipment. Fulton condensingboilers equipped for natural gas asthe primary fuel source and fuel oilbackup provided domestic hotwater. A Flo-Pak domestic waterbooster pump also was utilized,along with Chem-Aqua water sof-tener.Materials used include under
slab sanitary and storm PVC. Thedomestic water piping is copper.Above slab sanitary and storm pip-ing is no-hub cast iron. Medicalgas piping is copper. Plumbing fix-tures, drains and major equipmentare worth about $700,000.Said Pullin, “A great deal of
coordination between the trades, aswell as with the owner-furnishedequipment, is always a major fac-tor in a health care project of thismagnitude. Our company has beeninstalling the types of systemsrequired for this project in hospi-tals for more than 50 years and oursuperintendent has been doing sofor nearly 30 years. When it comesto understanding and planninghow all of the components of thesystems should fit within the over-all construction, our experience inthis field is an invaluableresource.”Since SGMC’s founding in
1955, the full-service acute carefacility has grown from a smallcommunity hospital into a regionalreferral center serving roughly350,000 residents in north Floridaand south Georgia. The hospital isnoted for its Pearlman CancerCenter, The Birthplace and theDasher Memorial Heart Center.
(This story also can be foundon Construction EquipmentGuide’s Web site at www.con-structionequipmentguide.com.)CEG
Multi-Faceted Job Requires Coordination of Many Trades
The main floor of the new construction will house the DasherHeart Center diagnostics and cath labs. The second floor of thetower is slated for the Cardiac Progressive Unit. Here crewshave been working on the heart tower pit.
SGMC from page 1
The new hospital parking deck is nearing completion and willserve visitors, patients and hospital staff.
Construction Equipment Guide • Georgia State Supplement • www.constructionequipmentguide.com • September 5, 2012 • Page 7
www.reynoldswarren.comE-Mail: [email protected]
1-800-875-5659 or 404-361-15931945 Forest ParkwayLake City, GA 30260
Georgia’s One Stop Shop For Everything Asphalt
YES...We Rent What We Sell!
Roadbuilding SolutionsLeeBoy’s Rosco brand roadbuilding solutions are designed and built for themost demanding applications. From asphalt distributors and brooms to pothole patchers and chip spreaders, count on LeeBoy products for valuethat delivers bottom-line results.
Durability, productivity, ease of operation and value have made LeeBoy anindustry leader.
MAXIMIZER 3 ASPHALT DISTRIBUTOR
Maximizer 3 Asphalt Distributor Features:
• 8 to 16 Foot Extendible Spraybar
• Automatic In-Cab Controls
• 400 GPM Viking Asphalt Pump
• Enviro-Flush Clean-Out System
• Internal Spraybar Valves
Contact your Rosco Dealer
VT LeeBoy, Inc. • 500 Lincoln County Parkway Ext. • Lincolnton, NC 28092 • Call (704)966-3300 • www.leeboy.com
3 Asphalt Pavers (Sizes range from 10,000 - 33,000 lbs)
3 Asphalt Rollers
3 Motor Graders
3 Pot Hole Patchers
3 Brooms
3 Asphalt Distributors
3 Concrete Curber
3 Conveyor Belt Loaders
Every Solution for Your Paving Needs
VT LeeBoy, Inc. • 500 Lincoln County Parkway Ext. • Lincolnton, NC 28092 • Call (704)966-3300 • www.leeboy.com
Tru-Pac 915 CSH Chip Spreader RA-400 Spray Patcher
Page 8 • September 5, 2012 • www.constructionequipmentguide.com • Georgia State Supplement • Construction Equipment Guide