Bank of Jamaica - Re-roofing GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 CANOPY ROOF 4 TOWER ROOF 6 Contingency Sum Include the Provisional Sum of $750,000.00 for Contingencies to be used as directed by the Architect/Contract Administrator or deducted in whole or in part if not required 750,000.00 *$ *Any sum(s) added to or deducted from this total will be treated as a percentage on or off the prices in this Bill of Quantities (excluding Preliminary Items, Prime Cost and Provisional Sums) and the rates to any variation will be based on rates arrived at after being subjected to such percentage adjustments $ TOTAL VALUE OF WORKS $ GS 1

Upload: vuongkhanh

Post on 03-Aug-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL SUMMARY

PAGE NO.

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES P15

CONCOURSE ROOF 2

CANOPY ROOF 4

TOWER ROOF 6

Contingency Sum

Include the Provisional Sum of $750,000.00 for

Contingencies to be used as directed by the

Architect/Contract Administrator or deducted in whole or in

part if not required 750,000.00

*$

*Any sum(s) added to or deducted from this total will be

treated as a percentage on or off the prices in this Bill of

Quantities (excluding Preliminary Items, Prime Cost and

Provisional Sums) and the rates to any variation will be

based on rates arrived at after being subjected to such

percentage adjustments $

TOTAL VALUE OF WORKS $

GS 1

Page 2: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES

A Location and Description of the Works

B Prices

C Method of Measurement

Carried to Collection

The site of the Works is Bank of Jamaica, Nethersole Place,

Kingston CSO.

The Works consists of the removal of old waterproofing

membrane to the concourse level, canopy level and the tower

roof; repairs to the concrete surface (where necessary) and the

re-roofing of approximately 2,536 m² of concrete roof.

The existing roof has various mechanical equipment supported

on concrete or steel plinths, as well as cables, refrigerant and

other pipes and the re-roofing work will have to be carried out

around and without damage to these items. Where equipment,

etc. needs to be moved to facilitate the re-roofing, the Employer

will arrange for this to be done and the Contractor is expected

to re-schedule his work to accommodate the moving of such

equipment, pipes, etc.

The Contract Sum shall be understood to be the total price for

all the works described in the Conditions of Contract,

Preliminaries and Bill of Quantities. Where no price is inserted

beside an item, the cost of that item shall be deemed to be

included in the price of other items in these documents

The Contract quantities have been measured in accordance with

the Jamaican Standard Method of Measurement of Building

Works (Third Edition) published by the Jamaican Institute of

Quantity Surveyors

P1

Page 3: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A Definitions

B Delegation

Carried to Collection

The term "Work" of the Contractor or Sub-Contractor includes

labour or material or both.

All time limits stated in the Contract Documents are of the

essence of the Contract.

The law of the place of building shall govern the construction of

this Contract.

Either the Architect/Contract Administrator or the Quantity

Surveyor or both of them may, from time to time, delegate to

a person or persons nominated in writing to the Contractor,

such of the powers, discretions or authority vested in the

Architect/Contract Administrator or the Quantity Surveyor by

the Contract Document as the Architect/Contract Administrator

or the Quantity Surveyor may think fit and the Contractor shall

recognize such person or persons as lawfully exercising, for the

purpose of this Contract, such powers, discretion and authorities.

The Contract Documents consist of the Agreement, Conditions of

Contract and Preliminaries, Drawings, Bills of Quantities and

Specifications, including all modifications thereof incorporated in

the documents before their execution

The Employer, the Contractor, the Architect/Contract

Administrator and the Quantity Surveyor are those mentioned

as such in the Agreement. They are treated throughout the

Contract Document as if each were of the singular number and

masculine gender

The term "Sub-Contractor" as employed herein, includes only

those having a direct contract with the Contractor and it includes

one who furnishes materials worked to a special design

according to the Plans or Specifications of this Work, but does

not include one who merely furnishes material not so worked.

Written notice shall be deemed to have been duly served if

delivered in person to the individual or to a member of the firm

or to an officer of the corporation for whom it is intended, or if

delivered at or sent by registered mail to the last business

address known to him who gives the notice.

P2

Page 4: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A Examine Drawings and Visit Site

B Conditions of Contract

C 1 - Contractor's Obligations

D 2 - Architect's/Contract Administrator's Instructions

E 3 - Contract Documents

F 4 - Statutory Obligation Notice Fees and Charges

G 5 - Levels and Setting Out of the Works

Amend Clause 5 by adding the following:

H 6 - Materials, Goods and Workmanship to conform to

Description, Testing and Inspection

Carried to Collection

(i) Allow for the setting out of the Works and for assisting the

Architect/Contract Administrator in checking, including providing

all instruments

(ii) Figured and calculated dimensions are always to be

followed in preference to scaled dimensions. The attention of the

Architect/Contract Administrator must be drawn to any

discrepancy between figured or calculated dimensions and

scaled dimensions before any work is executed

The Contractor is deemed to have examined the Drawings,

visited the Site and satisfied himself as to local conditions,

accessibility of the Site, full extent and character of the site,

availability of labour, materials and the like and of any general

conditions which may affect his tender, as no claim due to the

lack of knowledge, insufficient information, or misunderstanding

in these respects will be allowed.

THE ARTICLES OF AGREEMENT AND CONDITIONS OF

CONTRACT SHALL BE THOSE PROVIDED IN THE STANDARD

FORM OF BUILDING CONTRACT PRIVATE EDITION WITH

QUANTITIES, 2007 REVISION, ISSUED BY THE CONSTRUCTION

INDUSTRY COUNCIL FOR THE BUILDING AND CONSTRUCTION

INDUSTRY IN JAMAICA AND THE CONTRACTOR IS TO ALLOW

FOR COMPLYING THEREWITH AND WITH ANY AMENDMENTS

AND AMPLIFYING CLAUSES. BELOW IS A LIST OF THE CLAUSE

HEADINGS AND AMENDMENTS:

P3

Page 5: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A 7 - Royalties and Patent Rights

Amend Clause 7 by adding the following:

B 8 - Contractor's Supervision

Amend Clause 8 to add the following as sub-clause (4):

C 9 - Access for Architect/Contract Administrator

D 10 - Clerk of Works

E 11 - Variations, Provisional and Prime Cost Sums

Amend Clause 11 (4) (d) by adding the following:

Amend Clause 11 (3) by adding the following:

Amend Clause 11 to add the following as sub-clause (7):

Carried to Collection

The Contractor shall constantly keep upon the Works a

competent Supervisor/Foreman and instructions given to him by

the Architect/Contract Administrator shall be deemed to have

been issued to the Contractor.

Daywork will not be allowed without the prior written approval

of the Architect/Contract Administrator.

The Architect/Contract Administrator and Surveyor shall be

afforded all reasonable assistance in measuring variations and

checking labour, materials and the like. To afford them sufficient

time to take proper measurements, they shall be given at least

three clear days notice by the Contractor before any work is

covered up and in the event of the Contractor failing to provide

such notice, he is to uncover and reinstate as required at his own

expense.

Where the Contractor has information that a specified process

or product of a particular manufacturer is an infringement of a

patent, he shall be responsible for paying all resulting claims

and costs unless he promptly gives such information to the

Architect/Contract Administrator or Employer.

No compensation will be made to the Contractor as a result of

the omission of any or all Provisional Sums

P4

Page 6: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A 12 - Contract Bills

Amend Clause 12 to add the following as sub-clause (3):

B 13 - Contract Sum

Amend Clause 13 by adding the following:

C 14 - Materials and Goods unfixed or off-site

D 15 - Practical Completion and Defects Liability

E 16 - Partial Possession by Employer

F 17 - Assignment or Sub-Letting

G 18 - Injury to Persons and Property and Employer's

Indemnity

H 19 - Insurance against injury to Person and Property

J 20 - Insurance of the Works against fire, etc.

Clause 20C is the applicable option

Carried to Collection

(iii) Materials shall be ordered in accordance with the Drawings

and Specifications and NOT from these Bills of Quantities.

(i) The Contractor shall not alter the text of these Bill of

Quantities, unless otherwise instructed by the Architect/Contract

Administrator or the Quantity Surveyor

(ii) All Provisional Quantities and Sums will be omitted in the

Final Account, and any work represented by such quantities or

sums and authorized by the Architect /Contract Administrator

will be measured on completion and entered in lieu.

Contractor's arithmetical or pricing errors discovered before

signing the Contract shall be corrected in accordance with the

Instructions to Tenderers.

The Limits of Liability under Clause 19(i)(a) shall be

$10,000,000,00 for any one incident. The number of incidents

shall be unlimited.

P5

Page 7: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A 21 - Possession, Completion and Postponement

Amend Clause 21 to add the following as sub-clause (4):

B 22 - Damages for non-completion

C 23 - Extension of Time

D 24 - Loss and Expense caused by Disturbance of Regular

Progress of the Works

E 25 - Determination by Employer

F 26 - Determination by Contractor

G 27 - Nominated Sub-Contractors

Amend Clause 27 to add the following as sub-clause (h):

(a) The cost involved in preparing approved contracts for

signing with the various Nominated Sub-Contractors.

(b) Provision of any facilities necessary for Sub-

Contractors to carry out their work concurrently with

the main Contractors.

(c) Unloading, getting in, storing, hoisting and distributing

materials and plant to all areas and levels of the

building. However, where this exercise necessitates

the use of equipment that would not otherwise be

required by the main Contractor, he shall be

compensated

Carried to Collection

(i) The sums included for work to be executed by Nominated

Sub-Contractors are nett without allowance for any discount but

inclusive of Customs Duties and Import Taxes

Allow for all overtime, night work and additional labour and

plant, etc. required to ensure the Contract is completed by the

Date for Completion

(ii) The term "Allow for Attendance" where used in these Bills of

Quantities shall be deemed to include for the following:

P6

Page 8: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

27 - Nominated Sub-Contractors (Cont'd)

(d) Provision of adequate working space and safe and

dry storage accommodation for materials and plant

(e) Provision of water and electric light and power

necessary to execute and test the work

(f) Free use of all fixed scaffolding, plant and covered

storage available and the erection of any scaffolding

or staging not otherwise required for the Main

Contractor's own use.

(g) Obtaining and/or supplying dimensions for setting

out and all directions and templates, etc. including

the coordination of all specialist contractors and all

trades.

(h) Protecting the finished work.

(i) Provision of unskilled labour for general attendance

A 28 - Nominated Suppliers

Amend Clause 28 to add the following as sub-clause (d):

(i) Unloading at site, getting in, unpacking, storing, hoisting

distributing, assembling and fixing as particularly

described, including returning empty cases carriage paid

(ii) Provision of safe and dry storage accommodation

(iii) Provision of all water, electric light and power and sca-

ffolding

(iv) Protecting the finished work

(v) Prime Cost Sums for imported goods are deemed to be

C.I.F. Kingston docks, unless otherwise described and

in connection therewith the term "Take delivery at dry

Dock" where used in these Bills of Quantities shall be

deemed to include the following in addition to the above:

Carried to Collection

The term "FIX ONLY" where used in these Bills of Quantities shall

unless otherwise stated, be deemed to include the following:

P7

Page 9: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

28 - Nominated Suppliers (Cont'd)

(a) Payment of all bank charges in connection with

ordering.

(b) Payment of charges for landing dues, demurrage,

storage, wharfage and brokerage except where

occasioned through circumstances beyond the

Contractor's control

(c) Clearing through Custom (excluding Customs

Duties and Import Taxes)

(d) Loading and transporting to Site including insuring

in transit.

A 29 - Artists and Tradesmen

B 30 - Certificates and Payments

Amend Clause 30 by adding the following after the second

paragraph:

Amend Paragraph 3 of Clause 30 to read as follows:

Carried to Collection

If within 28 days of delivery of the Contractor's statement the

Employer has not received the Architect's / Contract

Administrator's Payment Certificate, the Employer shall pay to

the Contractor the amount shown in the Contractor's statement,

less retention at the rate stated in the Appendix to these

Conditions, less the total of previous payments and less any

amount for which the Employer / Architect / Contract

Administrator has specified their reasons for disagreement. The

Employer / Architect / Contract Administrator shall not be

bound by any sum previously considered by him to be due to

the Contractor.

The Contractor's valuation shall, if in order, be approved by the

Architect / Contract Administrator within 14 days and an interim

Certificate of Payment issued by the Architect / Contract

Administrator to the Employer stating the amount due. Such a

certificate shall be calculated as the total amount of the

approved valuation, less the percentage of Certified Value

Retained as noted in the Appendix to these Conditions, less the

total of previous certificates issued by the Architect / Contract

Administrator.

P8

Page 10: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A 31 - A, B, C - Fluctuations

Amend Clause 31A to add the following as sub-clause (f):

B 32 - Outbreaks of Hostilities

C 33 - War Damage

D 34 - Antiquities

E 35 - Notices

F 36 - Site Meeting

G 37 - Appointment of Adjudicator

H 38 - Arbitration

J Warranties

K Provision by Employer

Carried to Collection

Prior to Practical Completion the Contractor shall deliver to the

Architect/Contract Administrator all Warranties and guarantees

including information on the commencement date of each.

As a condition for payment, the Contractor shall submit along

with his claims, the original of all invoices for materials

purchased, as well as proof of payments made to or in respect

of workpeople engaged in connection with the Works. All

original invoices, etc. shall be returned to the Contractor after

inspection by the Quantity Surveyor

(End of Clause Headings and Amendments)

Where goods, services, equipment, etc. are to be provided

direct by the Employer for use in the work and are so identified

in the Contract Documents, the Contractor shall not be entitled to

receive any percentage addition or remuneration in respect of

profit on such items.

P9

Page 11: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A General Requirement

B Programme and Progress Reports

C Site Diary and Other Records

D Identification Cards

Carried to Collection

The Contractor shall prepare a programme (using Microsoft

Projects or Primavera) showing all activities to be carried out to

complete the works and clearly identifying all activities on the

critical path and shall submit it to the Architect/Contract

Administrator before taking possession of the site. The

Contractor shall within a further one (1) month elaborate this

programme to show the co-ordination of all major sub-contracts

and identifying critical dates when owner-supplied materials will

be required and again submit it to the Architect/Contract

Administrator. After approval the Contractor shall keep a

copy of the programme on the site and record current progress

thereon and submit a copy to the Architect/Contract

Administrator upon application for monthly payments together

with a progress report for the Employer.

The use and/ or distribution of illegal drugs, smoking, the

consumption of alcoholic beverages and the bearing of arms is

strictly prohibited on the site. Anyone found violating this

condition will immediately be removed and banned from the

site.

The Contractor must issue each site worker/ personnel with a

picture identification and this must be prominently displayed on

the worker's person at all times. A list of all workers and

personnel (including those employed by Nominated Sub-

Contractors) must be given to the Contract Administrator and this

list must be updated from time to time as necessary

The Contractor shall maintain a proper site diary with daily

records of activities being carried out, workforce broken down

by category, plant, equipment, materials delivered or removed

and weather conditions.

P10

Page 12: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A Site Enclosure and General Protection

B Site Security

E Damage to Adjoining Property and Works

D Contractor's Storage Shed & Mess Room

E Latrines

F Water, Lighting and Power for the Works

Carried to Collection

Water, lighting and power will be made available to the

Contractor

Unless he receives written authorization from the Architect

/Contract Administrator, the Contractor must not allow any

advertisements to be displayed on the hoarding, except for his

firm's name board.

Washroom and latrine facilities are available on site and will

be made available for use by the Contractor and his workers.

If required, storage facilities and mess room for the workmen

will be provide by the Bank of Jamaica. The Contractor must

allow for maintaining in a clean condition.

Should any loss, damage or injury occur to roads, drains, power

lines, pipes, surrounding properties or any part of the works, the

Contractors shall make good the same at his own cost to the

satisfaction of the Architect/Contract Administrator.

Allow for providing all means necessary, other than watching

and lighting, to preserve the Site, Works, unfixed materials and

plant, etc. from trespass, damage or theft and to protect all

persons from injury or inconvenience due to the operation of this

Contract including temporary fences, screens, etc., all to be in

accordance with the requirements of statutory or other

regulations.

Site security will be provided by the Bank of Jamaica

P11

Page 13: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A Scaffolding, Plant and Small Tools

B Holiday, Bonus, Special Pay, etc.

C Statutory Payments

D Permits and Taxes

E Contractor's Levy

Carried to Collection

The Contractor's attention is drawn to the fact that not-

withstanding anything to the contrary contained in these

Conditions, the Employer shall, pursuant to the 'Contractor's Levy

Act - 1985', deduct from the gross amount of the Contract Sum

a levy equal to 2% of any amount due. Similarly, the Contractor

shall be required to make the same deduction from payments to

his sub-contractors.

Allow for obtaining permits and paying all fees connected

therewith and for paying all taxes of whatever description and

character incidental to the performance of the Contract.

Allow for all costs in connection N.I.S., H.E.A.R.T., Education Tax

and N.H.T.

The Contractor's price will be deemed to be inclusive of suitable

and sufficient labour including holiday-with-pay and public

holiday schemes, all materials, transport, haulage, workshops,

bonus and incentive schemes, height pay, depth pay, working in

water pay, over water pay, sick leave pay or severance pay,

travelling time, expenses and subsistence and welfare measures.

The Contractor shall provide and maintain all necessary

scaffolding, hoists, mechanical equipment, shoring, plant, and

small tools for the proper execution of the work (other than

plant, scaffolding and small tools properly provided by

specialist sub-contractor) and shall clear away on completion

P12

Page 14: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A Bonds

B Safety and Welfare Measures

B Samples

Carried to Collection

Allow for affording full safety precautions at both site and

workshops. This shall include, but shall not be limited to: first aid

kits, safety equipment, safety and protective gear, danger and

caution signs, safety instruction signs and directional signs.

The Contractor shall provide and install all fall protection

systems including railings, screens, mesh, safety nets, body belts,

harnesses, lifelines, etc.

The Contractor will not be required to submit Performance and/

Mobilization bonds. The Employer is prepared to advance a

payment to the Contractor for use in purchasing roofing

materials on the condition that such materials are delivered

directly to the site and will immediately become the property of

the Bank of Jamaica.

The Contractor shall in respect of all persons employed by him

(whether in the execution of the Contract or otherwise in every

factory, workshop or place occupied or used for the execution

of the Contract) comply with the general conditions required by

these Conditions and the current Factories Law

Allow for obtaining and submitting samples of materials as

required by the Architect/Contract Administrator before use or

application in the Works. Any samples rejected are to be

replaced and all materials subsequently used in the work are to

be equal to the approved samples in all respects.

All manufactured articles, materials and equipment shall be

applied, installed, connected, erected, used, cleaned and

conditioned in strict accordance with the manufacturer's printed

instructions, unless herein specified to the contrary. Where

reference is made to manufacturer's directions, the Contractor

shall submit copies of such direction to the Architect/Contract

Administrator. If the Contractor is in doubt of any such instruction

he shall not proceed but shall refer the decision to the

Architect/Contract Administrator for approval

P13

Page 15: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

A Cover Up and Protect

B Testing

C Remove Rubbish and Debris

Carried to Collection

(i) Allow for covering up and protecting the Works from

damage resulting from weather or other causes and for making

good any damage which may be so caused save as covered by

insurance hitherto described.

(ii) Allow for protecting from trespass, loss or damages arising

from the operation of this Contract, all existing property

including: buildings, temporary fences, walls, trees, grass,

vegetation, roads, paths, drains, sewers, water, electric and gas

pipes and mains and the like, whether public or private and

both inside and outside the Site and for making good any

damage occasioned through the operation of this Contract and

pay all charges in connection. The Contractor shall not interfere

with any of the foregoing without the consent of the Public

Authority or private owner concerned.

(iii) The Contractor will be required where possible to leave all

existing trees, plants and shrubs and shall include for all

protection and any inconvenience caused.

Allow for keeping the Works reasonably clean during the

progress of the Contract, clearing away all rubbish and debris

as it accumulates and finally cleaning glass both sides, scrubbing

or otherwise, cleaning all floors, pavings, and steps, cleaning out

cisterns and gutters, cleaning sanitary fittings and other fittings,

cutting all grass and weeds and leave the Site and premises

clean and ready for occupation at completion to the

satisfaction of the Architect/Contract Administrator

Allow for testing materials as and when called upon to do so by

the Architect/Contract Administrator. Any material or work

found to be defective or not complying with the tests shall be

immediately removed from the Site or cut out and made good

at the Contractor's own expense.

Allow for the preparation and testing of concrete cubes

including all transportation and delivery thereof to the Testing

Laboratory

P14

Page 16: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - Re-roofing

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES (Cont'd)

COLLECTION

From Page No. P1

From Page No. P2

From Page No. P3

From Page No. P4

From Page No. P5

From Page No. P6

From Page No. P7

From Page No. P8

From Page No. P9

From Page No. P10

From Page No. P11

From Page No. P12

From Page No. P13

From Page No. P14

GENERAL CONDITIONS OF CONTRACT AND

PRELIMINARIES

Carried to General Summary on Page No. GS1

P15

Page 17: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - re-roofing

CONCOURSE ROOF

General Notes

The Contractor must visit the site in order to assess for himself

the existing Conditions and the extent of the Work to be

removed, altered, etc. so as to supplement the descriptions

contained in these Bills as the prices inserted will be

understood to include for all items necessary to carry out and

complete the works to the satisfaction of the Architect/Contract

Administrator

The Contractor shall provide all necessary scaffolding, plant,

tarpaulins, dust sheets, etc. required for the demolition, etc.

and support and maintain such protection and remove and

clear away and make good on completion

The Contractor shall take all responsibility for the stability and

upholding of the existing structures during the progress of the

works and must provide all necessary shoring, etc. even

though not specifically referred herein

All making good or 'patching' rendering or screeding must be

cut out to a rectangular shape so as to form a dovetailed key

and finished flush with the surrounding surfaces

The Contractor is to allow for the covering up and protection of

the existing structures, etc. during the progress of the Works

so as to prevent the ingress of water inside the building and for

clearing away on completion, disposing of all debris and

making good all damages at his own expense

Allowance is to be made for disconnection of any water supply

and waste pipes and sealing off ends, etc. and disconnection

of electrical services, where necessary

(End of General Notes)

A Remove membrane waterproofing and dispose off site 2,055 m²

B Remove old cement mortar or caulking from reglet and prepare

for new skirting (measured separately) 122 m

C Include the Provisional Sum of $350,000.00 for additional

repairs to Concourse Roof, to be expended in whole or in

part, or deducted in full if not required, all as directed by the

Contract Administrator Sum 350,000.00

Carried to Collection

1

Page 18: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - re-roofing

CONCOURSE ROOF (CONT'D)

A 4 mm Thick modified bitumen waterproofing membrane with

granular finish (as Novaglass grade 'A' supplied locally by

Spectrum Systems Ltd.) fixed to roof, bases and upstands,

in accordance the manufacturer's specifications 2,030 m²

B Ditto as skirting 150 mm girth, including tucking in edge of

membrane into existing reglet and make good with cement

mortar or an approved caulking compound 122 m

C Dress membrane into or around roof drains (PROVISIONAL) 23 nr

Carried to Collection

COLLECTION

From Page No. 1

From Page No. 2

CONCOURSE ROOF

Carried to General Summary on Page No. GS1

2

Page 19: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - re-roofing

WESTERN CANOPY ROOF

General Notes

The Contractor must visit the site in order to assess for himself

the existing Conditions and the extent of the Work to be

removed, altered, etc. so as to supplement the descriptions

contained in these Bills as the prices inserted will be

understood to include for all items necessary to carry out and

complete the works to the satisfaction of the Architect/Contract

Administrator

The Contractor shall provide all necessary scaffolding, plant,

tarpaulins, dust sheets, etc. required for the demolition, etc.

and support and maintain such protection and remove and

clear away and make good on completion

The Contractor shall take all responsibility for the stability and

upholding of the existing structures during the progress of the

works and must provide all necessary shoring, etc. even

though not specifically referred herein

All making good or 'patching' rendering or screeding must be

cut out to a rectangular shape so as to form a dovetailed key

and finished flush with the surrounding surfaces

The Contractor is to allow for the covering up and protection of

the existing structures, etc. during the progress of the Works

so as to prevent the ingress of water inside the building and for

clearing away on completion, disposing of all debris and

making good all damages at his own expense

Allowance is to be made for disconnection of any water supply

and waste pipes and sealing off ends, etc. and disconnection

of electrical services, where necessary

(End of General Notes)

A Remove membrane waterproofing and dispose off site 137 m²

B Remove old cement mortar or caulking from reglet and prepare

for new skirting (measured separately) 26 m

C 4 mm Thick modified bitumen waterproofing membrane with

granular finish (as Novaglass grade 'A' supplied locally by

Spectrum Systems Ltd.) fixed to roof, bases and upstands,

in accordance the manufacturer's specifications 132 m²

Carried to Collection

3

Page 20: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - re-roofing

WESTERN CANOPY ROOF (CONT'D)

A Ditto as skirting 150 mm girth, including tucking in edge of

membrane into existing reglet and make good with cement

mortar or an approved caulking compound 26 m

B Dress membrane into or around roof drains (PROVISIONAL) 3 nr

Carried to Collection

COLLECTION

From Page No. 3

From Page No. 4

WESTERN CANOPY ROOF

Carried to General Summary on Page No. GS1

4

Page 21: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - re-roofing

TOWER ROOF

General Notes

The Contractor must visit the site in order to assess for himself

the existing Conditions and the extent of the Work to be

removed, altered, etc. so as to supplement the descriptions

contained in these Bills as the prices inserted will be

understood to include for all items necessary to carry out and

complete the works to the satisfaction of the Architect/Contract

Administrator

The Contractor shall provide all necessary scaffolding, plant,

tarpaulins, dust sheets, etc. required for the demolition, etc.

and support and maintain such protection and remove and

clear away and make good on completion

The Contractor shall take all responsibility for the stability and

upholding of the existing structures during the progress of the

works and must provide all necessary shoring, etc. even

though not specifically referred herein

All making good or 'patching' rendering or screeding must be

cut out to a rectangular shape so as to form a dovetailed key

and finished flush with the surrounding surfaces

The Contractor is to allow for the covering up and protection of

the existing structures, etc. during the progress of the Works

so as to prevent the ingress of water inside the building and for

clearing away on completion, disposing of all debris and

making good all damages at his own expense

Allowance is to be made for disconnection of any water supply

and waste pipes and sealing off ends, etc. and disconnection

of electrical services, where necessary

(End of General Notes)

A Remove membrane waterproofing and dispose off site 383 m²

B Remove old cement mortar or caulking from reglet and prepare

for new skirting (measured separately) 40 m

C Hack and remove concrete to form 1200 x 150 x 150 mm

deep channel leading to roof drain and dress interior of

channel to slope with cement and sand (1:3) finished with a

steel float item

Carried to Collection

5

Page 22: GENERAL SUMMARY - Bank of Jamaica · GENERAL SUMMARY PAGE NO. GENERAL CONDITIONS OF CONTRACT AND PRELIMINARIES P15 CONCOURSE ROOF 2 ... B 22 - Damages for non-completion C 23 - Extension

Bank of Jamaica - re-roofing

TOWER ROOF (CONT'D)

A Hack and prepare concrete surfaces to receive screed

(PROVISIONAL) 40 m²

B Prepare and apply Bondcrete to prepared roof (prior to screed-

ing) in strict accordance with the manufacturer's specifications

(PROVISIONAL) 40 m²

C 50 mm Average thick cement and sand (1:3) screed laid to

falls and crossfalls on roof and finished with a wood float

(PROVISIONAL) 40 m²

D 4 mm Thick modified bitumen waterproofing membrane with

granular finish (as Novaglass grade 'A' supplied locally by

Spectrum Systems Ltd.) fixed to roof, bases and upstands,

in accordance the manufacturer's specifications 374 m²

E Ditto as skirting 150 mm girth, including tucking in edge of

membrane into existing reglet and make good with cement

mortar or an approved caulking compound 40 m

F Dress membrane into or around roof drains (PROVISIONAL) 3 nr

Carried to Collection

COLLECTION

From Page No. 5

From Page No. 6

TOWER ROOF

Carried to General Summary on Page No. GS1

6