general presentation nl agency orio infrastructure for development
TRANSCRIPT
![Page 1: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/1.jpg)
General presentation
NL AgencyORIO
ORIOInfrastructure forDevelopment
![Page 2: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/2.jpg)
>> Focus on international business and cooperation
The Facility for Infrastructure Development (ORIO)
Reliable infrastructure is of vital importance for human development and private sector development, which in turn are expected to promote sustainable growth and improve the position of the poor.
The ORIO grant facility enables the Dutch government to contribute to the development, construction/expansion, operation and maintenance of public infrastructure in developing countries.
ORIO is funded by the Dutch Ministry of Foreign Affairs and implemented by NL Agency.
![Page 3: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/3.jpg)
The objectives of ORIO
• To stimulate human development in developing countries.
• To stimulate private sector development in developing countries.
• To stimulate the involvement of international business in the development and implementation of projects in order to benefit from the private sector’s expertise.
![Page 4: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/4.jpg)
Examples of selected projects
• Treatment and distribution of drinking water in rural areas (DRC, Ghana, Kenya, Vietnam)• Waste water collection and treatment (Bosnia and Herzegovina, Serbia, Vietnam)• Flood control and irrigation (Mozambique)• Road construction and rehabilitation (Bhutan, Ghana, Moldova)• Expansion of lake transport infrastructure (Ethiopia)• Rural electrification (Senegal, Tanzania, Uganda)• Urban waste treatment (Burundi)• Maternal and child health care (Ethiopia, Ghana, Macedonia, Malawi, Palestinian Territories, Peru, Tanzania)• Accelerating tuberculosis case detection (Ghana)
![Page 5: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/5.jpg)
61 projects in 25 countries
![Page 6: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/6.jpg)
Sectors
projects per sector11
3
1
16
30
Transport
Energy
Environment
Social Services
Water
![Page 7: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/7.jpg)
Results of the 7 calls for proposals
Calls for proposals (year-Call)
2009-I 2009-II 2010-I 2010-II 2011-I 2011-II 2012 Total
Applications 90 127 54 66 41 45 47 470
Selected projects 9 10 8 9 9 11 10 66
Budget (in mln. Euro) 101 79 88 101 56 137 178 740
![Page 8: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/8.jpg)
7 ORIO Calls for proposals (2009-2012)470 applications
179 fully assessedEUR 5,400 mln. total project costs
EUR 2,225 mln. grant applied
66 selectedEUR 2,100 mln. total project costs
EUR 740 mln. grant applied
![Page 9: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/9.jpg)
>> Focus on international business and cooperation
ORIO characteristics (1/2)•ORIO funds public, commercially non-viable infrastructure, relating
to drinking water, irrigation, wastewater, environment, (renewable) energy, transport, health, education, etc.
•Contributes to the development and implementation of projects, and the operation and maintenance of infrastructure
•Approximately 50 countries on the country list
•Maximum project budget EUR 60 million, minimum EUR 2 million
•Various grant percentages
![Page 10: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/10.jpg)
>> Focus on international business and cooperation
ORIO characteristics (2/2)•Untied aid
•A central government authority in recipient country is applicant
•Government authority in recipient country is owner of the project
•Private parties may initiate project proposals
•Call for proposals to submit grant applications, selection on a ‘first-come, first-served’ basis
![Page 11: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/11.jpg)
>> Focus on international business and cooperation
ORIO project cycle
Development phase Implementation phase Operation & maintenance phase
ACORIO ACORIO
Assessment I
First grant arrangement Second grant arrangement
Application
Assessment II
status selected projects number
rejected or withdrawn 5
selected, no signing of grant arrangement 12
development phase 42
implementation phase 7
total 66
![Page 12: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/12.jpg)
Evaluation procedure for applications Grant applications: - A central government authority submits an application - Applications dealt with on ‘first-come, first-served’ basis - Assessment against ORIO requirements and criteria - Selection until the available budget is exhausted (assessment I)
Development phase:- Preparation of project plan- Assessment of project plan (assessment II) Grant arrangement for the development phase
Implementation phase:- Procurement and project implementation One grant arrangement for both the implementation and the operation &
maintenance phases
Operation & maintenance phase:- Max. 10 years
![Page 13: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/13.jpg)
Formal requirements• The applicant is a central government authority in a country on the ORIO country list• Applications only during application period• Between EUR 2 million and EUR 60 million• All phases of the project cycle are covered: development, implementation, operation & maintenance• In English, using the most recent version of the application form• Complete, clear and concise• Commercially non-viable • Complies with the definition of a project • Procurement complies with the legislation of the recipient country and with the OECD’s Good Procurement Practices
![Page 14: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/14.jpg)
Criteria
RelevanceEfficiencyEffectivenessImpactSustainability (social and environmental factors, financial viability, capacity of parties involved, consistency with policy, end-user involvement, technology)
![Page 15: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/15.jpg)
Project budget
Inputs Activities Outputs Outcomes Impacts
Develop infrastructure
Construct infrastructure
Operate infrastructure
Maintain infrastructure
Well-functioning
public infrastructure
Private sector: improved access
and use of infrastructure
Households: improved access
and use of infrastructure
Private sector development
Human development
• No, or mitigated, negative social and environmental consequences
• Financial viability
• Parties involved have the capability and capacity to carry out the project
• Suitable technology
• Consistent with national/regional development policy
• Institutional, economic and legal factors have been taken into account
• End users are involved
ORIO Project Result Chain and Evaluation Criteria
Efficiency Effectiveness Impact
ProblemCauses of the problem
Relevance
Sustainability
![Page 16: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/16.jpg)
>> Focus on international business and cooperation
Calls for proposals
• Deadlines published at www.orio.nl
• All information, including application form, available at www.orio.nl
• Intake form available at www.orio.nl for discussing project ideas with project consultant
• Contact: [email protected] or tel. +31 88 602 80 60
![Page 17: General presentation NL Agency ORIO Infrastructure for Development](https://reader036.vdocuments.us/reader036/viewer/2022062422/56649efd5503460f94c10f42/html5/thumbnails/17.jpg)
Thank you for your attention