general notes and - okladot.state.ok.us · general notes and pittsburg hensley defranco sh-71 over...
TRANSCRIPT
JOB PIECE NO.
Design
Detail
Check
SHEET NO.
REVISIONSREV. NO. DESCRIPTION DATE
Engr.:
Squad:
BRIDGE COUNTY
OKLAHOMASTATE OF DEPARTMENT OF TRANSPORTATION
(04)
N/A
26348
TEE
RAH
"A"
AB01
SUMMARY OF PAY QUANTITES (BRIDGE)
GENERAL NOTES AND
PITTSBURG
HENSLEY
DEFRANCO
SH-71 OVER AN UNNAMED CREEK
GENERAL NOTES
VERIFICATION OF EXISTING CONDITIONS:
SPECIFICATIONS:
PROVISIONS (SEE PROPOSAL FOR SPECIAL PROVISIONS).
SPECIAL AND PLANS THE BY MODIFIED WHERE EXCEPT CONSTRUCTION, HIGHWAY FOR SPECIFICATIONS
STANDARD OKLAHOMA 2009 THE WITH ACCORDANCE IN BE SHALL MATERIALS AND CONSTRUCTION ALL
CONTACT THE BRIDGE DESIGN DIVISION OF THE OKLAHOMA DEPARTMENT OF TRANSPORTATION.
ASSISTANCE FOR PROJECT. WPA UNKNOWN AN ARE BRIDGE EXISTING THE FOR PLANS CONSTRUCTION
SOLELY RESPONSIBLE FOR THE ACCURACY THEREOF.
BE SHALL AND SHOWN AS WORk THE COMPLETE TO NECESSARY DIMENSIONS ALL VERIFY SHALL CONTRACTOR
THE APPROXIMATE. ARE PLANS THE ON SHOWN COMPONENTS BRIDGE EXISTING THE OF DIMENSIONS ALL
ENGINEER.
THE OF SATISFACTION THE TO EXPENSE, CONTRACTOR'S THE AT REPAIRED BE SHALL NEGLIGENCE CONTRACTOR'S
THE TO DUE ROADWAY OR STRUCTURES BRIDGE NEW THE TO DAMAGE ANY ATTACHMENTS. OR STRUCTURE
BRIDGE NEW THE TO DAMAGE PREVENT TO PRECAUTIONS NECESSARY ALL TAKE SHALL AND PRACTICE
CONSTRUCTION GOOD WITH CONSISTENT METHODS ADOPT SHALL CONTRACTOR THE PERFORMED. BE WILL IT
WHICH UNDER CONDITIONS AND WORK THE OF NATURE THE OF THEMSELVES INFORM FULLY SHALL BIDDERS
CURTAINWALL INTO ROCK:
CURTAINWALL SHALL BE KEYED 6 INCHES INTO ROCK.
THE REACHED. BEEN HAS CURTAINWALL THE OF DEPTH TOTAL THE BEFORE ENCOUNTERED IS ROCK IF
TEMPORARY WORK ROAD:
ERODIBLE MATERIAL ACCEPTABLE TO THE ENGINEER.
NON OF MADE BE MUST ROAD WORK ACTIVITIES. CONSTRUCTION ALL OF COMPLETION THE AFTER CONDITION
AND FLOW NORMAL TO RETURNED BE TO BANKS STREAM AND CHANNEL CONSTRUCTION. OF END AT REMOVED
BE TO ROAD WORK TEMPORARY SHEET. ELEVATION" AND PLAN "GENERAL THE ON ROAD" WORK THRU SECTION
"TYPICAL THE IN SHOWN AS SPECIFICATION AND SIZE THE TO CONSTRUCTED BE SHALL ROADS WORK
TEMPORARY RETAINING STRUCTURES:
CONCRETE CURING:
ONCE CONCRETE HAS BEEN POURED, IT MUST CURE FOR A MINIMUM OF FOURTEEN (14) DAYS.
(1) UNCLASSIFIED EXCAVATION:
(2) STRUCTURAL EXCAVATION UNCLASSIFIED:
(3) REMOVAL OF EXISTING BRIDGE STRUCTURE:
EXCAVATION".
"UNCLASSIFIED OF YARD CUBIC PER BID PRICE THE IN INCLUDED BE SHALL ABOVE DESCRIBED AS WORK
THE COMPLETE TO NECESSARY INCIDENTALS AND EQUIPMENT, LABOR, MATERIALS, INCLUDING COSTS ALL
APPROVED BY THE ENGINEER.
MANNER A IN OF DISPOSED AND CONTRACTOR THE OF PROPERTY THE BECOME SHALL EXCAVATION UNCLASSIFIED
REMAINING ANY ENGINEER. THE BY DIRECTED AS AND STANDARD SBI-4-2 THE IN SHOWN AS COMPLETED
BE SHALL PLACEMENT R.C.B. THE OF CONSTRUCTION THE FOR EXCAVATION" "UNCLASSIFIED ITEM PAY THE
EXCAVATION UNCLASSIFIED".
"STRUCTURAL OF YARD CUBIC PER BID PRICE THE IN INCLUDED BE SHALL ABOVE DESCRIBED AS WORK
THE COMPLETE TO NECESSARY INCIDENTALS AND EQUIPMENT, LABOR, MATERIALS, INCLUDING COSTS ALL
PLACEMENT SHALL BE COMPLETED AS SHOWN IN THE SBI-4-2 STANDARD AND AS DIRECTED BY THE ENGINEER.
R.C.B. THE OF CONSTRUCTION THE FOR UNCLASSIFIED" EXCAVATION "STRUCTURAL ITEM PAY THE
ENVIRONMENTAL MITIGATION NOTES
AMERICAN BURYING BEETLE:
ARCHEOLOGICAL AVOIDANCE:
T8N-R18E: SECTION 15 SW1/4 SW1/4 SW1/4
EQUIPMENT STAGING, HAUL ROADS, SPOIL DUMPS OR ANY OFF-SITE PROJECT-RELATED ACTIVITY.
BORROW, FOR UTILIZED BE NOT MUST AREA FOLLOWING THE IN AREA PROJECT THE OUTSIDE LOCATIONS
(Typ.)
#4Bars
E3 or E4
(Typ.)
BARS #4
E2or E1
Phase IPhase II
Min.
Proj.
2'-6"
AT PHASE JOINT
DETAIL OF LAP LENGTH
Construction Joint
! of Phase
PAY QUANTITIES
PAY QUANTITIES
PAY QUANTITIES
MARK NO. SIZE FORM LENGTH VARIANCE
ITEM DESCRIPTION UNIT QUANTITY
ITEM DESCRIPTION UNIT QUANTITY
ITEM DESCRIPTION UNIT QUANTITY
0200 BRIDGE "A"
UNCLASSIFIED EXCAVATION1301
501(A) 1306
E3
E4
E1
E2
STR.
STR.
#4
#4
#4
#4
152
72
152
72
65'-8"
1
STR.
1
1
450.00
758.70
117,410.00
32'-4"
202(A)
STRUCTURAL EXCAVATION UNCLASSIFIED
CLASS AA CONCRETE C.Y.(BR-1)
(BR-1)
0640 CONSTRUCTION
LSUM 1.00
LSUM 1.00CONSTRUCTION STAKING LEVEL II (S-1)
(BR-1)
0600 STAKING
(1)
(2)
(3)
32'-4"
65'-8"
MARK NO. SIZE FORM LENGTH VARIANCE
STR.
C.Y.
C.Y.
LB.
1326509(A)
LSUM1397619(D) REMOVAL OF EXISTING BRIDGE STRUCTURE
THE BAR LIST SHOWN SUPPLEMENTS THAT FOUND IN STANDARD RCB-C2-16(2-8)01E
LENGTH INCLUDES ONE 2'-4" PHASED LAP LENGTH.
0096642(B)
1.00
2,825.00
PAY ITEMS NOTES
EARTHWORK PAY ITEMS.
RELATED FOR BID PRICE THE IN INCLUDED BE SHALL DESCRIBED AS WORK THE COMPLETE TO NECESSARY
INCIDENTALS AND SERVICES PROFESSIONAL MATERIALS, EQUIPMENT, LABOR, INCLUDING STRUCTURES RETAINING
TEMPORARY FOR COSTS THE PAYMENT. FOR MEASURED BE NOT WILL STRUCTURES RETAINING TEMPORARY
WORK ON THE RETAINING STRUCTURES.
STARTING BEFORE ENGINEER THE BY APPROVED AND SUBMITTED BE SHALL STRUCTURES RETAINING TEMPORARY
THE FOR DRAWINGS AND CALCULATIONS OKLAHOMA. OF STATE THE IN REGISTERED ENGINEER PROFESSIONAL
A BY DESIGNED STRUCTURES RETAINING TEMPORARY THE HAVE WILL CONTRACTOR THE NECESSARY,
BE STRUCTURES RETAINING TEMPORARY SHOULD SLOPES. FLATTER OR 2:1 MAINTAIN TO NECESSARY BE
MAY STRUCTURES RETAINING TEMPORARY ALLOWED. BE NOT WILL 2:1 THAN STEEPER SLOPES TEMPORARY
1/16
5/15
BID PER LUMP SUM OF "REMOVAL OF EXISTING BRIDGE STRUCTURE".
PRICE THE IN INCLUDED BE SHALL INCIDENTALS AND EQUIPMENT, LABOR, INCLUDING ENGINEER THE BY DIRECTED
AS AND ABOVE DESCRIBED AS STRUCTURE EXISTING THE OF REMOVAL THE WITH ASSOCIATED COSTS ALL
THE ENGINEER.
BY APPROVED MANNER A IN OF DISPOSED BE AND CONTRACTOR THE OF PROPERTY THE BECOME SHALL REMOVED
MATERIALS AND STRUCTURE ALL STANDARD SPECIFICATIONS AND IN A MANNER APPROVED BY THE ENGINEER.
THE OF 619.04B(2) SECTION WITH ACCORDANCE IN 189+57 STA. CENTERLINE APPROXIMATE AT SPAN SLAB 9'X10'X9'
A OF DISPOSAL AND REMOVAL OF CONSISTS STRUCTURE" BRIDGE EXISTING OF "REMOVAL ITEM PAY THE
(BR-1)
511(B) 6010 EPOXY COATED REINFORCING STEEL
(EPOXY COATED REINFORCING) (PHASE 1)
BARREL BAR LIST
(EPOXY COATED REINFORCING) (PHASE 2)
* BARREL BAR LIST
EPOXY COATED REINFORCING STEEL:
OF STUB THRU DRAINAGE STRUCTURES OR PHASING JOINTS.
USE THE TO DUE COATED EPOXY BE SHALL RCB NEW THE OF CONSTRUCTION THE IN USED REINFORCING ALL
*
(BR-1):
SPECIFICATION.
STANDARD THE OF 109.01B SECTION SEE ONLY. QUANTITIES PLAN ON BASED BE WILL ITEM THIS FOR PAYMENT
(BR-2):
(S-1):
CONSTRUCTION FEATURES AS DETERMINED BY THE ENGINEER
EARTHWORK OTHER ALL AND ROADWAY THE FOR REPORTS/COMPUTATIONS VOLUME WITH SECTIONS
CROSS FINAL AND ORIGINAL, BENCHMARKS, DETOUR, OF CENTERLINE AND SURVEY, OF CENTERLINE RIGHT-OF-WAY,
NEW AND PRESENT OF STAKING INCLUDES CONTROL VERTICAL AND HORIZONTAL OF ESTABLISHMENT
(BR-1) (BR-2)
STEEL TO CONSTRUCT ALL COMPONENTS OF THE RCB.
REINFORCING "BLACK" OF USE STANDARD THE SUPERSEDE WILL STEEL REINFORCING COATED EPOXY OF USE
Ø
Ø ADD PAY ITEM 4/18/2016
MOBILIZATION LSUM 1.001399641
220 2800 SWPPP DOCUMENTATION AND MANAGEMENT
TEMPORARY RIGHT-OF-WAY THROUGHOUT PROJECT ACTIVITIES.
AND PERMANENT THE FROM REMOVED BE SHALL TRASH FOOD ALL AND CARCASSES CONSTRUCTION. DURING USED
BE SHALL LIGHTING ARTIFICIAL NO IMPACTS, ADVERSE AVOID TO ORDER IN ACT. SPECIES ENDANGERED THE UNDER
ENDANGERED AS LISTED IS THAT BEETLE BURYING CARRION LARGE A IS BEETLE BURYING AMERICAN THE
MIGRATORY BIRD NOTES:
NETTING MUST BE PRE-APPROVED BY THE ODOT BIOLOGIST.
THAN OTHER METHODS COMPLETE. IS SEASON NESTING THE UNTIL DELAYED WORK THE OR 1 APRIL TO PRIOR
NETTED BE MAY BRIDGE THE BIRDS, NESTING ANY HARM WILL WORK PROPOSED THE IF AUTHORIZED. IS STRUCTURE
THE NEAR WORK BEFORE BIRDS NESTING ANY TO DISRUPTION POSE WOULD WORK PROPOSED THE WHETHER
CONCLUDE AND METHODS WORK PROPOSED CONTRACTOR'S THE EVALUATE WILL ENGINEER RESIDENT THE
IN THE FUTURE NESTING SEASONS.
STRUCTURES THESE OCCUPY MAY BIRDS MIGRATORY SURVEY. INITIAL THE DURING OBSERVED NOT WAS CULVERTS
AND BRIDGES REMAINING THE OF USE BIRD MIGRATORY 2016. IN STUDIES BIOLOGICAL THE OF PART AS CONDUCTED
SURVEY INITIAL THE DURING OBSERVED BEEN HAS 07102 NO. NBI BRIDGE OF USE BIRD MIGRATORY
THE MIGRATORY BIRD TREATY ACT.
VIOLATE WOULD BIRDS OR EGGS HARM OR NESTS ACTIVE DESTROY WOULD WHICH ACTIVITIES ANY 31. AUGUST TO
1 APRIL FROM RUNS BIRDS THE FOR SEASON NESTING THE NESTING. FOR CULVERTS AND BRIDGES USE COMMONLY
BIRDS THESE ACT. TREATY BIRD MIGRATORY FEDERAL THE BY PROTECTED ARE BIRDS MIGRATORY
BAT BRIDGE REMOVAL MODIFICATION NOTE:
RIPARIAN VEGETATION REMOVAL RESTRICTION NOTE:
CONSTRUCTION (TOE OF SLOPE/TOP OF CUT).
OF LIMITS ACTUAL THE WITHIN AREAS TO RESTRICTED BE SHALL SHRUBS AND TREES OF REMOVAL THE
BAT’S MATERNITY ROOSTING SEASON. ANY DELAY DUE TO THIS WILL NOT BE COMPENSATED.
THE OF DURATION THE OF PART OR ALL FOR PROHIBITED BE MAY AND RESTRICTED BE WILL BRIDGE THE ON WORK
SERVICE. WILDLIFE AND FISH US WITH CONSULT WILL PROGRAM RESOURCES BIOLOGICAL ODOT THE DETECTED,
ARE SPECIES BAT LISTED IF 15. AUGUST AND 15 MAY BETWEEN ONLY CONDUCTED BE CAN SURVEY THE
ODOT BIOLOGIST AT 405-521-2515 TO CONDUCT A BAT SURVEY.
THE CONTACT SHALL ENGINEER RESIDENT THE 15, NOVEMBER AND 1 APRIL BETWEEN OCCUR TO IS MODIFICATION
OR REMOVAL BRIDGE THE IF SITES. ROOSTING SUMMER AS BRIDGES USE CAN SPECIES THESE ACT. SPECIES
ENDANGERED THE BY PROTECTED BAT EATING INSECT MIGRATORY, A IS BATS LONG-EARED NORTHERN THE
5/10/2016Ù REVISE ENVIRO. NOTES
Ù
Ù
Ù
Ù