general foundation conditions conditions faced during ... · pdf fileproject description the...
TRANSCRIPT
Project DescriptionThe Panama Canal Expansion Project included the construction of four dams that will allow navigation access to the new Pacific Post-Panamax Locks. Borinquen Dams 1W, 2W & 2E are part of the design-build contract for the Third Set of Locks.
Challenges Faced During Construction: » Variable Geology » High Seismic Hazards » Challenging Foundation Conditions » Construction in Tropical Climate » Use of Tropical Residual Soils » Filters Optimization
Faults treatment » Four Major Fault Treatments Were
Implemented - Miraflores Fault - Dam 1W
- Miraflores Fault - Dam 2E
- Unnamed Fault (Dam 2W)
- Shear Zone at Sta. 0+590 (Dam 2W)
» Treatment Implemented - Seepage Cutoff Wall
- Upstream Clay Blanket
- Downstream Filter Blanket
Use of Tropical Residual Soils as Clay Core Materials » Two Main Sources of Materials
(Sucre and Cocolí Hill) » High Natural Moisture Content (30 to 45 %) » Natural Moisture Content +5 to +12 % above OMC. » Exhibits “Dry” Behavior at Optimum Moisture
Content » Materials Sensitive to Testing Procedures and Oven
Temperatures » Rainfall Precludes Drying of Borrow Areas
and Stockpiles » Remedial Actions:
- Special Placement and Compaction Controls Were Developed
- Extensive Laboratory Testing and Field Trials
- Acceptance Criteria Based on Degree of Saturation (S) in addition to MDD and OMC
- MDD and OMC Were Specified with Degree of Saturation to Prevent Compacting Materials Excessively Wet of optimum
Filters Optimization » Owner’s Conceptual Design Required Four
Different Filters Placed in Six Separate Zones » An Effort was Made by Designer to Reduce the
Numbers of Filter/Transition Zones Due to Material Availability and Construction Issues
» Final Filter Design in Accordance with U.S. Bureau of Reclamation Guidelines (USBR, 2007)
» As a Result One Broadly-graded Sand Filter/Transition Zone and a Graded Rockfill (i.e., “Buffer”) Adjacent to the Filters/Transitions were Implemented
» The Dams Included One Broadly-graded, Gravelly Sand Chimney Filter/Transition (Type 3a) at Both the Inboard and Outboard Sides of the Core and Cobble “Buffer” Material
Construction in Tropical Climate » High Temperatures and
Humidity » Abundant rainfall » Frequent Thunderstorms » Placement and Compaction
during Rainy Season » Remedial Actions
Implemented: - Flexibility in Construction Sequence
- Execution of Construction Joints Perpendicular to the Dam Axis
- Advanced Construction of Rock Fill Shells placed on the Inboard and Outboard Toe of the Dam
- Core Geometry was Revised From Conceptual Design to Reduce the Quantity of Clay Materials and Excavations
Wonnie Kim, PE – MWH Gabriel Martinez – MWH Carlos Zambrano, PE – MWHwww.mwhglobal.com
General Foundation Conditions Conditions Faced During ConstructionThree Different
Geological Formations » Basalt Formation » La Boca Formation » Pedro Miguel Formation
Presence of Active Faults » Pedro Miguel Fault » Miraflores Fault » Unnamed Fault
Seepage Control » Double Grout Curtain
Seismic Considerations (Owner’s Requirement)
» Horizontal Displacements Up to 3.0 m » Vertical Displacements Up to 0.50 m » Two Design Earthquakes (1000 & 2500
return periods) » Peak Ground Accelerations 0.72g & 0.97g
DAM FEATURES
Dam Type Zoned rockfill dam with central clay core
Crest Elevation (without camber) El. 32 m PLD
Top of Core Elevation (without camber) El. 29 m PLD
Crest Width 30 m
Max. Dam Height (above foundation) 35 m
Dam Length 0.6 km (1W), 0.9 km (2W), 1.4 km (2E)
Dam Fill Volume 7 million m3 (approx.)
Dam/Core Freeboard (above NMOP) 4.87 m / 1.87 m
Inboard Slopes 2.87H:1V
Outboard Slopes 2.5H:1V (1W & 2W), 2.5H:1V to 3H:1V (2E)
Design-Build Construction of the Panama Canal Borinquen Dams 1W, 2W and 2E
Typical Foundation Treatment Implemented in Major Faults/Sheared Zones Borrow Source
Compaction Requirements Shear Strength RequirementMoisture Content Density / Saturation Level
Sucre Hill
+1% to +4% OMC 98% of MDD (avg.) 96% of MDD (min.) n/a
+4 to +10% OMCDensity equivalent to
87% (min.) and 90% (avg.) saturation
70 kPa (shear vane)
Cocoli Hill
+1% to +4% OMC 98% of MDD (average) 96% of MDD (minimum) n/a
+4 to +8% OMC Density equivalent to 90% (min.) saturation 120 kPa (shear vane)
Borinquen Dams 1W, 2W & 2E Typical Cross Section
Panama Canal Expansion Project Pacific Site - Borinquen Dams 1W, 2W & 2E Panama Canal Expansion Project Pacific Site – General Geological Conditions
Borinquen Dam 1W – Basalt FormationTypical Foundation Conditions
Borinquen Dam 2W – La Boca FormationTypical Foundation Conditions
Typical Material Condition at Moisture Content +3% above OMC
Filter and Buffer Material Placement
Sucre Hill and Cocolí Hill End-Production Compaction Specifications
Panama Canal Expansion Project General Layout