GENERAL DESCRIPTION ON DEMOLITION
PEMBINAAN C W YAP SDN BHD (202393-U)
EARTHWORKS, CIVIL & DEMOLITION CONTRACTOR
-
8/6/2019 General Description on Demolition
2/12
General Preparations Prior to
Physical Demolition
Proposed Demolition Sequence and MethodsProposed demolition Sequence and Methods are based on existing building conditions,Demolition Contractors knowledge and experience put into practice along with the necessary
calculations and advise from our Civil & Structural Consultants.
Inspection on Existing Building and Layout DesignAlthough the building is meant for demolition, an inspection on the health of the building is of
utmost importance. Efforts should be made to acquire the structural plans from the owners or
consultants or the archives from local authorities.A site visit/inspection will also be carried outby our team and affiliated professionals.
Safety PrecautionsSafety precautions has to be extensively planned and monitored any kind demolition especially
along the demolition perimeters. Extra precautions has to be taken to ensure that no debris will
be accidently ejected outside of the site into the neighboring tenants boundary as well as into
the public road. The demolition team, consisting of project managers, supervisors, operators,safety officers, etc.. Shall go through an extensive planning hand in hand.
Soft Stripping/Internal StrippingSoft Stripping will be carried out on the existing building to remove and dispose hazardous and
combustible material, ie: glass windows, doors, wooden fittings, roofing, steel members, steel
structures, carpet and etc. This will also control and minimize projectiles from being ejected
during demolition works.
-
8/6/2019 General Description on Demolition
3/12
Preliminary Safety Precautions
Perimeter Hoarding
Perimeter Hoarding of3.6m in height as per DBKL requirement
Additional Hood/Platform to be added due to heavy pedestrian
traffic
Debris Catch Fence
Make shift Debris Catch Fence with 1 layer of
industrial netting and 1 layer of Heavy Duty
Netting at critical zones
-
8/6/2019 General Description on Demolition
4/12
Preliminary Safety Precautions
External Scaffolding
1) 1 layer of Industrial Netting
2) 1 layer of Tarpaulin
3) 1 layer of Heavy Duty Industrial Netting
External A-Frame scaffoldings with 3 layers of
protection to be constructed around structure
-
8/6/2019 General Description on Demolition
5/12
Preliminary Safety Precautions for
High Rise Structures
CRAB60 Propping
Our Professional Engineer(P.E.) will carry out the slab load calculation to cater
to the movement and vibration from the machineries and subsequently to
design the propping and bracing required to back prop the suspended slab. This
will maximize the safety factor and to avoid from any unintended collapse on
any part of the structure during the course of demolition works
-
8/6/2019 General Description on Demolition
6/12
Demolition Sequence
Hoisting of Machineries
The Demolition team and its affiliated professionals, P.E, etc, shall carry out
necessary calculations and survey of site conditions prior to the hoisting of
machineries to the roof of structure .
-
8/6/2019 General Description on Demolition
7/12
Demolition Sequence
Top-Down Demolition
Physical hacking works will be carried out on floor by floor
basis starting with the slab, beam and lastly the columns.
Excavators will be lowered down to the lower floor using a
steel ramp customized to the structures floor height as
shown in the diagram on the right.
-
8/6/2019 General Description on Demolition
8/12
Demolition Sequence
External Demolition
Higher capacity excavators, i.e: EX300 onwards to be utilised for external
demolition.Excavators are usually fitted with either hydraulic breakers or
hydraulic crushers.
-
8/6/2019 General Description on Demolition
9/12
Demolition Sequence
External Demolition & Ground Works
Once the structure is brought down to a safe level using top down demolition,
higher capacity excavators will be mobilized to speed up the demolition process
Upon the complete demolition of the structure, hacking works will be done on
the ground/basement slab, and subsequently the pile caps.
-
8/6/2019 General Description on Demolition
10/12
Debris & Traffic Management
Debris will be transported away from site on a progressive basis.
Warning Signages & Barricades will be placed around perimeter of site.
Traffic management team to be stationed on site to manage traffic
whenever necessary.
-
8/6/2019 General Description on Demolition
11/12
Safety, Health & Environment
Temporary Perimeter Hoarding External Scaffold with 3 layers of protective materials
(Industrial Netting, Tarpaulin & Heavy Duty safety netting)
Safety Toolbox meeting to be
carried out daily.
Water Pump & Hose Jet will be use to contain and
minimize dust derived from demolition works
-
8/6/2019 General Description on Demolition
12/12
THE END
Prepared by,
Andy Yap