Set up instructions on the GateKeeper 1935.

TRANSCRIPT

Page 1: Gate keeper 1935 series

Gatekeeper 1935 Series

Page 2: Gate keeper 1935 series

a. Site Evaluation / Preparation

• FOD search (Foreign Objects or Debris)• Possible obstructions/hazards- i.e. trees, power

lines, underground plumbing, etc.• Terrain type- i.e. grass, sand, gravel, concrete,

asphalt, etc.• Anchoring needs vary depending on terrain

• Shelter configuration• Repeat weather

Page 3: Gate keeper 1935 series

b. Equipment Positioning

– Layout cases/bags in kit form• Stage close to set up location• Do not stage within

designated set up location• Case=kit form• No cases? Bags=kit form

– Organize equipment accordingly

Page 4: Gate keeper 1935 series

c. Frame

1. Layout Mainframe Assy

2. Stand up one of the two mainframes and remove the bottom strap

3. Using 3 people, expand the mainframe with the key flange facing the center where the structure will be located

Page 5: Gate keeper 1935 series

c. Frame Continued…

4. Extend roof truss assemblies

5. Connect Eave Bars (Velcro OUT)• Caution! Pinch Point• Keep Eave Bars parallel to the

ground for easier installation

6. Repeat (2-5) with other mainframe until all Eave Bars are installed

Page 6: Gate keeper 1935 series

c. Frame Continued…7. Position both mainframes together so

all Eave Bars are connected• Importance of mainframe

connection before center section installation

8. Install Center Section frame at Key Flanges• Only use 2 people for ease of

installation• Do not force the fit

Page 7: Gate keeper 1935 series

c. Frame Continued…

9. Connect Center Section Roof Trusses to Eave Bars• Compress button, position

lower bracket over button, and squeeze Eave Bars together to release button

Page 8: Gate keeper 1935 series

c. Frame Continued…

10. Lock the Center Section Assembly into place• Demonstrate the weakness

without the buttons locked• Lift Center Section Assembly

from the middle until all four buttons have locked

• Demonstrate the strength with the buttons locked

Page 9: Gate keeper 1935 series

c. Frame Continued…

**Note: Some accessories can be pre-attached to the roof truss at this point. (Divider Walls, Plenum, Lights, Exhaust fans, and CO/smoke detectors)

11. Lower leg assemblies• Squeeze two bars together about

1 foot up the Eave Bar and pull pin out, lower the leg slowly

Page 10: Gate keeper 1935 series

d. Roof Fabric

1. Place the folded Insulation Roof Panel on top of the center of the frame assembly

2. Partially unfold the fabric onto the frame assembly, leaving room to gain access to the top of the center of the frame assembly to later attach the vent cap

Page 11: Gate keeper 1935 series

d. Roof Fabric Continued…

3. Place Vinyl Roof Panel on top of the center of the frame assembly

4. Partially unfold the fabric onto the frame assembly, leaving room to gain access to the top of the center of the frame assembly to later attach the vent cap

Page 12: Gate keeper 1935 series

d. Roof Fabric Continued…

6. Locate the Vinyl Roof Panel Cones over the Key Flanges

5. Remove the protective pieces of fabric and place them into the corresponding storage bag

Page 13: Gate keeper 1935 series

d. Roof Fabric Continued…

7. Install Vent Cap(s)• Locate Vent Cap hole• Pull pin and connect to Vent Cap

hole• Clear out all fabric between Key

Flange and Cones• Assure that the Vent Cap is

securely attached

Page 14: Gate keeper 1935 series

e. Raising the Shelter Frame

1. 4 people lift one side of shelter• Caution! Always make first lift facing INTO the wind• Position each person at the 4 legs• Lift until legs are fully extended• Caution! Pinch Point

• Rest frame on 4 extended legs and install pins into top most outside hole on the frame

Wind

Page 15: Gate keeper 1935 series

e. Raising the Shelter Frame Continued…

2. Repeat on opposing side of shelter

3. Finish by lifting the two ends and installing the pins into the top most outside hole

4. When leg is lifted, it drops into it’s natural place

Page 16: Gate keeper 1935 series

f. Insulation Roof Panel

1. Locate the center seam on the Insulation Roof Panel

2. Locate the center mark on the Eave Bars (metal screw)

3. Ensure center seam of Insulation Panel matches with the center of the Eave Bar• Vertically center the two strips

of Velcro

Page 17: Gate keeper 1935 series

f. Insulation Roof Panel Continued…

4. Start at the center and work out towards the legs

5. Do not attach Vinyl Roof Panel at this time

Vinyl Roof

Page 18: Gate keeper 1935 series

g. Flooring Installation

1. Place Floor Fabric in the center of the shelter

2. Unfold the Floor Fabric completely

Page 19: Gate keeper 1935 series

g. Flooring Installation Continued…

3. Place Legs onto Floor Fabric• Lift each Leg and place on the 2’’ welded strip

located on the floor• Pull both the Floor Fabric and Leg until the Leg is

vertically square and the floor is tight

2’’ Welded Strip

Page 20: Gate keeper 1935 series

g. Flooring Installation Continued…

4. Install all Base Bars• Caution! Pinch Point• Keep Base Bars parallel to the

ground for easier installation

**Note: If it is determined that a vestibule is to be installed and one shelter is already standing, now is the recommended time to start the installation.

Page 21: Gate keeper 1935 series

h. Door Installation

1. Decide Door location(s)• Discuss various options

2. Peel back the Insulation Roof Panel at the Door location only

3. Remove the Door from the bag

Page 22: Gate keeper 1935 series

h. Door Installation Continued…

4. Leaving the Door folded, install over the Eave Bar• Align the center hinge of the Door

along with the center of the Eave Bar (metal screw)

5. Unfold Door while guiding the Door frame over the Eave Bar

Page 23: Gate keeper 1935 series

h. Door Installation Continued…

6. From the inside, use the center mark on the Eave Bar to ensure the Door is centered

7. Lift the Door and guide it over the Base Bar

8. Ensure that the Door is securely in place and centered

9. Reattach ONLY the Insulation Roof Panel over the Door

Page 24: Gate keeper 1935 series

h. Door Installation Continued…

10. Insert Door Ramp directly after installing the Door• Open doors fully• Insert Door Ramp slots into door

gussets

Page 25: Gate keeper 1935 series

i. Insulation Wall Panels

1. Review label on inside of Insulation Wall (“Left of Door” and “Right of Door”)

2. Align Velcro along the Door hinge

3. Attach completely along the Door before continuing onto the rest of the shelter

Page 26: Gate keeper 1935 series

i. Insulation Wall Panels Continued…

4. Unroll and place loosely on the Insulation Roof Panel Velcro

5. Go around the shelter for a second time and attach the Wall Panel to the Roof, stretching as tightly as possible

6. Repeat with remaining Insulation Wall Panels

Page 27: Gate keeper 1935 series

i. Insulation Wall Panels Continued…

**Note: It may be necessary to stretch the Insulation Wall Panels a second time to achieve a complete connection. Expansion Strips can be used if the Fabric does not connect.

7. Connect Insulation Wall Panels• Use the left hand on the inside and the right hand on

the outside to stretch and attach the two panels

Page 28: Gate keeper 1935 series

j. Vinyl Wall Panels

1. Review label on the Vinyl Wall Panel. If folded correctly, the label will be on the outside of the Wall Panel (“Left of Door” and “Right of Door”)

2. Align Velcro along the Door hinge

3. Attach completely down the side of the Door before continuing along the Insulation Wall Panel

Page 29: Gate keeper 1935 series

j. Vinyl Wall Panels Continued…

4. Unroll and place loosely on the Insulation Roof Panel Velcro

5. Go around the shelter for a second time and attach the Wall Panel to the Roof, stretching as tightly as possible

6. Repeat with remaining Vinyl Wall Panels

Page 30: Gate keeper 1935 series

j. Vinyl Wall Panels Continued…

**Note: It may be necessary to stretch the Insulation Wall Panels a second time to achieve a complete connection. Expansion Strips can be used if the Fabric does not connect.

7. Connect the Vinyl Wall Panels• Use the left hand on the inside and the right hand on the

outside to stretch and attach the two panels together• It is very important to ensure no blue Velcro is showing, and

if there is, go back a third time and stretch again until no blue Velcro is showing.

Page 31: Gate keeper 1935 series

k. Attach Vinyl Roof Panel

1. Align the middle welded seam on the Vinyl Roof Panel with the Roof Bar

2. In a star pattern, stretch one corner then move to the opposing corner and stretch it to the Vinyl Wall Panel Velcro. Do this on all corners before attaching the Vinyl between the corners.• Tip: Use thumbs as leverage and

rotate wrists backward to stretch over the corner

3. DO NOT pull too much!

Page 32: Gate keeper 1935 series

k. Attach Vinyl Roof Panel Continued…

4. Attach remaining Roof Panel to Wall Panels by starting in the center of each section and working out toward the corners• Tip: Use thumbs as leverage and rotate wrists

backward to stretch over the corner

Center Thumbs

Page 33: Gate keeper 1935 series

l. Wall to Floor Connection1. Connect Wall Straps• Disconnect buckle from Wall Panel• Feed the strap under the Base Bar• Reconnect the buckle to the Wall

Panel• Slightly tighten by pulling the

adjustment strap• DO NOT over tighten!

• Do this throughout the entire shelter

Page 34: Gate keeper 1935 series

l. Wall to Floor Connection Continued…

2. Door Strap• Feed strap from Vinyl Wall Panel

under the Base Bar• Feed the strap through the double

D’rings and pull through to create tension

Page 35: Gate keeper 1935 series

l. Wall to Floor Connection Continued…

3. Create the Berm• From the outside, lift the skirt to

expose the floor beneath• Detach the black Velcro strap from

the Floor Panel• Fold the left side (with the D-Ring)

toward the black Velcro Strap• Ensure the Floor fabric is folded

inward toward the interior of the tent

• Weave the black Velcro strap through the D-Rings and tighten• DO NOT over tighten

• Reattach black Velcro strap to Floor

Page 36: Gate keeper 1935 series

l. Wall to Floor Connection Continued…

4. Create the Berm by the Door• Fold the Floor next to the Door

Ramp upward• Tuck the floor upward under the

Door Ramp• Reconnect the Wall Panel along the

Door hinge• Connect the Wall Panel Velcro to

the Floor Velcro• Ensure the Wall skirt is covering the

newly created Berm

Page 37: Gate keeper 1935 series

l. Wall to Floor Connection Continued…

5. Velcro Connection• Lift outside skirt to expose Velcro

flap• Pull Vinyl Floor snugly and attach

the Velcro to the Wall Panel• Pull Vinyl Wall skirt over the

connection• Continue around entire shelter

Page 38: Gate keeper 1935 series

m. Accessory Set Up

1. Interior• Wiring Harness• Lights• Plenum• Desk Sets• Thermostats• CO / Smoke Alarm

2. Exterior• Stake Kit• Generator / Electrical Distribution• Climate Control

Page 39: Gate keeper 1935 series

n. Complete Shelter Overview

1. Interior• Floor Buckles• Floor Velcro• Door to Wall Connection• Lighting

2. Exterior• Roof Connection• Skirting placement• Anchoring• Electrical cables• Vestibules

Page 40: Gate keeper 1935 series

o. Accessory Strike

1. Interior• Wiring Harness• Lights• Plenum• Desk Sets• Thermostats• CO / Smoke Alarm

2. Exterior• Stake Kit• Generator / Electrical

Distribution• Climate Control

Page 41: Gate keeper 1935 series

p. Accessory Inventory

1. Importance of Inventory• Match label with equipment• Assure correct quantity

Page 42: Gate keeper 1935 series

q. Accessory Repackaging

1. The Importance of Cleaning• Clean with a mild cleansing

solution• Dry completely• Fold or package as directed• Set aside for further packaging

Page 43: Gate keeper 1935 series

Shelter Strike, Folding, and Repacking

Page 44: Gate keeper 1935 series

a. Vinyl Walls

1. Disconnect buckles from floor to wall connection

2. Close all window and duct openings

3. Peel back Roof Fabric and remove walls in individual pieces

4. Lay walls flat on clean surface (preferably shelter floor) with the outer side of the fabric facing upwards

Page 45: Gate keeper 1935 series

a. Vinyl Walls Continued…

5. Clean the Wall Panels with a mild solution and let dry completely

6. Fold the BOTTOM edge 1/3 of the way toward the top edge

7. Fold again from the BOTTOM the rest of the way to the top

1/3

Page 46: Gate keeper 1935 series

a. Vinyl Walls Continued…

8. Roll TOWARDS the end with the Wall Panel label• If rolled correctly, the Vinyl Wall

label will be on the top of the roll

9. Roll tightly as to fit the Wall Panel back in the bag

10. Put immediately into the corresponding bag

Page 47: Gate keeper 1935 series

b. Insulation Walls

1. Remove walls in individual pieces

2. Lay the Insulation Walls on a clean surface (preferrably the shelter floor) with the inside (WHITE) of the fabric facing up

3. Clean the Insulation Walls with a mild solution and let dry completely• DO NOT spray cleaner directly onto

the Insulation fabric as it could lead to mold/mildew

Page 48: Gate keeper 1935 series

b. Insulation Walls Continued…

4. Fold the BOTTOM edge 1/3 of the way toward the top edge

5. Fold again from the BOTTOM the rest of the way to the top

1/3

Page 49: Gate keeper 1935 series

b. Insulation Walls Continued…

6. Roll TOWARDS the end with the Wall Panel label• If rolled correctly, the Insulation

Wall label will be on the top of the roll

7. Roll tightly as to fit the Wall Panel back in the bag

8. Put immediately into the corresponding bag

Page 50: Gate keeper 1935 series

c. Doors

1. Reattach the door strap and close the window material

2. Lock the upper barrel bolt

3. Lift and remove the door completely and fold in half

4. Clean the Door and dry completely as needed

5. Put immediately in the corresponding bag

Page 51: Gate keeper 1935 series

d. Base Bars

1. Remove all Base Bars

2. Put immediately in corresponding bag or case

Page 52: Gate keeper 1935 series

e. Flooring

1. Unfasten the berm straps at each corner of the floor so it lays flat

2. Lift each leg of the shelter to remove the floor from underneath

3. Clean the floor panel with a mild solution and let dry completely

Page 53: Gate keeper 1935 series

e. Flooring Continued…

3x

6. Repeat on the other side

4. Fold each end of the floor toward the middle to make the floor a rectangle

5. Take one side and fold to the middle weld-line 3 times

Page 54: Gate keeper 1935 series

e. Flooring Continued…

7. Fold the two halves together

8. Take each end and fold to meet in the middle

9. Fold one end on top of the other

10. Place immediately in the corresponding bag or case

Page 55: Gate keeper 1935 series

f. Lowering the Shelter

1. Lift up and lock into place the 2 opposing sets of legs on the narrow ends of the shelter

2. Using 4 people, lift up the 4 legs on one side of the shelter and lower down slowly • Make sure not to lock into place!

3. Lift up remaining 4 legs on other side and lower shelter down slowly• Make sure not to lock into place!

Page 56: Gate keeper 1935 series

f. Lowering the Shelter Continued…

4. Peel back the Insulation and Vinyl material to gain access to the Vent Cap

5. Pull the pin on the Vent Cap and lift to remove

6. Put immediately in the corresponding bag or case

Page 57: Gate keeper 1935 series

f. Lowering the Shelter Continued…

7. Assure that the protective pieces of fabric for the cones are installed prior to folding

8. Clean the Roof Panel with a mild solution and let dry completely

Page 58: Gate keeper 1935 series

f. Fold and Repackage Roof Panels

1. Fold both ends upward and over the vent cap to form a rectangle

2. Fold the ends one more time (2 total folds)

Page 59: Gate keeper 1935 series

f. Fold and Repackage Roof Panels Continued…

3. Fold one side approximately 6 inches over the centerline of the Mainframe

4. Fold the other side up to meet with the first fold

Page 60: Gate keeper 1935 series

f. Fold and Repackage Roof Panels Continued…

5. Fold each side in half TWO more times

6. Fold the one side (that was NOT folded over the centerline) on top of the opposing side to rest on centerline of the Mainframe

Page 61: Gate keeper 1935 series

f. Fold and Repackage Roof Panels Continued…

7. Fold each end over the vent cap

8. Don’t forget to reinsert the protective piece of vinyl!

Page 62: Gate keeper 1935 series

f. Fold and Repackage Roof Panels Continued…

10. Finish by folding one end over the other

11. Place immediately in corresponding bag or case

9. Continue folding both ends to meet in the center of the Mainframe

Page 63: Gate keeper 1935 series

f. Fold and Repackage Roof Panels Continued…

12. Clean the Insulation Roof Panel with a mild solution and let dry completely

13. Fold the end over the Vent Cap a total of TWO times

14. Do this for each side to create a rectangle

Page 64: Gate keeper 1935 series

f. Fold and Repackage Roof Panels Continued…

15. Fold one side approximately 6 inches over the centerline of the Mainframe

16. Fold the other side up to meet with the first foldCenterline

Page 65: Gate keeper 1935 series

f. Fold and Repackage Roof Panels Continued…

17. Fold each side in half TWO more times

18. Fold the one side (that was NOT folded over the centerline) on top of the opposing side to rest on centerline of the Mainframe

Page 66: Gate keeper 1935 series

f. Fold and Repackage Roof Panels Continued…

19. Fold each end over the vent cap (Vinyl Roof illustrated here)

20.Continue folding both ends to meet in the center of the Mainframe

21.Finish by folding one end over the other

22.Place immediately in corresponding bag or case

Page 67: Gate keeper 1935 series

f. Repackaging the Frame

1. Lock remaining legs into storage position

2. Remove the Center Section Trusses from the Eave Bars

Page 68: Gate keeper 1935 series

f. Repackaging the Frame Continued…

3. Remove the Center Section Trusses from the Key Flanges

4. Bundle the Center Section and fasten the frame strap

5. Put immediately into the corresponding bag or case

Page 69: Gate keeper 1935 series

f. Repackaging the Frame Continued…

6. Remove all Eave Bars

7. Depress the button and slide the Roof Truss assembly into storage position on all legs

8. Bundle the frame and fasten the frame strap

9. Put all pieces immediately into the corresponding bag or case

Page 70: Gate keeper 1935 series

Shelter Inventory

a. Bags– Use bag labels to

inventory shelter components

b. Cases– Use case labels to

inventory shelter components