Gas Regional Initiative North-WestTransmission Transparency
Transmission Transparency Project
GRI North-West Operators‘ Group
Stakeholder Group Meeting
London, 14 November 2008
Contact:Oliver AltenhoffE.ON Gastransport GmbHOliver.altenhoff@eon-gastransport.comwww.eon-gastransport.com
Page 2
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Agenda
Introduction
Transmission transparency project
Monitoring
Next steps in the project
Transparency workstream outlook
Page 3
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Introduction
Market request
Wish list
Ofgem-Workshop
Project- Plan
Implementationat TSO
Progress-Report
Page 4
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Participating TSO
Page 5
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Project Overview
Objective of the transmission transparency project:
Improve the publication of capacity and flow data
Provide clarity over published data
Steps:
Enlist participating operators
Develop anticipated time schedule
Establish individual TSO implementation plans
Monitor improvements
Page 6
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Information to be published
Capacity Information(C1) Max technical capacity of the transmission system
(C2) Level of interruption probability
(C3) Daily commercial firm and interruptible capacity
Flow Information(F1) Daily flow and interruptions
(F2) Daily prompt allocation information to each shipper
(F3) Daily aggregate day-ahead nominations
(F4) Historic gas flow information database
Gas Regional Initiative North-WestTransmission Transparency
Examples of the project
Page 8
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Daily flow
Page 9
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Daily aggregate day-ahead nominations
Page 10
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Daily Nominations and Allocations
Page 11
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Capacity Information
Page 12
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Level of Interruption
Page 13
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Progress: January to October 2008
11
14
15
16
5
6
11
13
9
1313
16
4
9 9
14
13
14
16 16
2
3
4
10
7
11
12
15
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Max technicalcapacity
Interruption Daily commercialfirm and interruptible
capacity
Dailyflow/aggregated
allocation
Daily promptallocation information
Daily aggregate day-ahead nominations
Historic gas flowinformation database
Jan 08
Apr 08
Oct 08
Dec 08 (expected)
Page 14
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Next Steps
Jan. 2009: Implementation monitoring
Jan. 2009: review the results
of the project
Feb. 2009: lessons learned
Feb. 2009: Any improvements left?
Page 15
Stakeholder Group Meeting; London 14 November
Gas Regional Initiative North-WestTransmission Transparency
Agenda:
Intro-duction
Project
Moni-toring
Next steps
Outlook
Outlook
Road map - work plan 2009:
Discussion on further requirements with stakeholders
Less than 3 rule applicable
TSOs´ websites harmonized
Further Information
Project schedule
Deliverables