gas & power the algerian experience in contracted onshore non- recourse financing francois...

10
Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006 NOT AN OFFICIAL UNCTAD RECORD

Upload: hillary-farmer

Post on 17-Dec-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006

Gas & PowerThe Algerian Experience in Contracted Onshore non-

Recourse Financing

Francois LabartheCorporate Bank Head

Citigroup, Algeria

April 4, 2006

NOT AN OFFICIAL UNCTAD RECORD

Page 2: Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006

Overview Background Traditional vs. Project Financing African Precedent Transactions Algerian Experience Way Forward

1

Page 3: Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006

Power Project Financing During 2000/04, banks lent $212bn to power projects globally

Only 0.6% went to Africa

$89bn

NorthAmerica

$35.5bn

Europe

$25.8bn

LatinAmerica

$1.3bn

Africa

$15.3bn

MiddleEast

$27.5bn

Asia

$17.7bn

Australasia

Source: Dealogic

3

Page 4: Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006

African GDP Figures Low African GDP figures are one reason behind small

investment in gas & power infrastructure projects

Source: The Economist Intelligence Unit

2

2005 Africa GDP

S Africa $238bn

Egypt $93bn

Nigeria $97bn

Algeria $91bn

Morocco $55bn

Libya $37bn

Others $268bn

Page 5: Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006

Traditional vs. Project FinancingTraditional Procurement Model Project Finance Model

Payment for Inputs

Overruns

ConstructionDevelopment

Operating Costs

Overruns

DelayCosts

Extension

0 3 10 15

Time (years)

Pay

me

nts

ConstructionNo Payments

0 3 10 15

Time (years)

Pay

me

nts

Operational PeriodOutput Payments

Payment Against Delivery

Shorter development time Contractor vs. Operator Interface issues Short-term view Limited (LD’s) risk

Operator & Contractor “Project Finance” discipline Long-term view High (Equity) risk Longer development time

4

Page 6: Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006

Key Success Factors Successful contracted projects rely on:

“Creditworthy” offtaker

Affordable tariff

Long-term stability

5

Page 7: Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006

African Precedents (sample)

Hamma Water Desalination

Algeria $235mm Sonatrach as offtaker

West Africa Gas Pipeline

Nigeria, Benin, Togo & Ghana

$560mm WB guarantees offtakers’ obligations

AES Power Barge Nigeria $120mm Credit enhancement of NEPA’s obligations

Kwale IPP Nigeria $450mm NNPC backstops NEPA’s obligations

Mozambique-SA Gas Pipeline

Mozambique & South Africa

$1.2bn Sasol as offtaker

Port Said Power Plant

Egypt $382mm Central Bank guarantees EEA’s obligations

Project Country Amount Key Feature

6

Page 8: Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006

Algerian Experience HWD was the first onshore contracted project to raise financing

in Algeria

Sonatrach offtaker made the project financeable This template has been followed in 2 water projects since One power project with Sonelgaz offtaker is about to reach

financial close using the HWD template

7

Page 9: Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006

Pipeline of Projects PFI lists a pipeline of power projects worth $30bn for Africa

The majority of these deals involve “creditworthy” offtakers

8

Source: Project Finance International

Project Pipeline

Algeria $2.95bn

Botswana $4.50bn

Namibia $4.23bn

Nigeria $2.78bnZambia

$2.53bn

Morocco US$2.40bn

Others $10.30bn

Page 10: Gas & Power The Algerian Experience in Contracted Onshore non- Recourse Financing Francois Labarthe Corporate Bank Head Citigroup, Algeria April 4, 2006

Way Forward Algerian Lessons

Leverage country’s highest creditworthy entity

Leverage local liquidity and international know-how Other African Lessons

Multilateral backstop of offtakers’ obligations

Other credit enhancements

“Stapled” projects Other Potential Sources

Pooled PPA

9