gas mitigation program residents out of homes 406 days1 year, 1 month, 9 days september 12, 2013
DESCRIPTION
Respec Dual-Phase Vapor Extraction (DPVE) Pilot Test Pilot test ran for a total of 219 hours. DPVE test was shut down at 14:00 on September 6, Total methane removed = 6.9 pounds per hour methane or ~4,000 scfd Bubbles started to reappear at NSDBS-026 within 90 minutes of shut down.TRANSCRIPT
![Page 1: Gas Mitigation Program Residents out of homes 406 days1 year, 1 month, 9 days September 12, 2013](https://reader033.vdocuments.us/reader033/viewer/2022052709/5a4d1b677f8b9ab0599b135c/html5/thumbnails/1.jpg)
Gas Mitigation ProgramResidents out of homes
406 days—1 year, 1 month, 9 days
September 12, 2013
![Page 2: Gas Mitigation Program Residents out of homes 406 days1 year, 1 month, 9 days September 12, 2013](https://reader033.vdocuments.us/reader033/viewer/2022052709/5a4d1b677f8b9ab0599b135c/html5/thumbnails/2.jpg)
Gas Mitigation Program1. Control shallow gas above the
MRAA with dual-phase vapor extraction
2. Remove gas from MRAA using similar gas/water extraction
![Page 3: Gas Mitigation Program Residents out of homes 406 days1 year, 1 month, 9 days September 12, 2013](https://reader033.vdocuments.us/reader033/viewer/2022052709/5a4d1b677f8b9ab0599b135c/html5/thumbnails/3.jpg)
Respec Dual-Phase Vapor Extraction (DPVE) Pilot Test
•Pilot test ran for a total of 219 hours.•DPVE test was shut down at 14:00 on September 6, 2013.•Total methane removed = 6.9 pounds per hour methane or ~4,000 scfd•Bubbles started to reappear at NSDBS-026 within 90 minutes of shut down.
![Page 4: Gas Mitigation Program Residents out of homes 406 days1 year, 1 month, 9 days September 12, 2013](https://reader033.vdocuments.us/reader033/viewer/2022052709/5a4d1b677f8b9ab0599b135c/html5/thumbnails/4.jpg)
Dual Phase Vapor Extraction Pilot Test
September 612:45
1 hour prior to shut down
Wednesday August 28, 201307:30 AM
3 hours prior to startup
PRIOR TO START UP
September 10, 20134 days after shutdown
Compressor Forty horsepower oil-sealed dual phase liquid ring pump
Very successful test conducted by Respec!
![Page 5: Gas Mitigation Program Residents out of homes 406 days1 year, 1 month, 9 days September 12, 2013](https://reader033.vdocuments.us/reader033/viewer/2022052709/5a4d1b677f8b9ab0599b135c/html5/thumbnails/5.jpg)
MRAA Aquifer
Dual-Phase Vapor Extraction System
Clay AquitardGas
Slab-on-grade Crawl space
DPVE System
Fine-grained sand
![Page 6: Gas Mitigation Program Residents out of homes 406 days1 year, 1 month, 9 days September 12, 2013](https://reader033.vdocuments.us/reader033/viewer/2022052709/5a4d1b677f8b9ab0599b135c/html5/thumbnails/6.jpg)
Trailer Mounted DPVE Unit
![Page 7: Gas Mitigation Program Residents out of homes 406 days1 year, 1 month, 9 days September 12, 2013](https://reader033.vdocuments.us/reader033/viewer/2022052709/5a4d1b677f8b9ab0599b135c/html5/thumbnails/7.jpg)
![Page 8: Gas Mitigation Program Residents out of homes 406 days1 year, 1 month, 9 days September 12, 2013](https://reader033.vdocuments.us/reader033/viewer/2022052709/5a4d1b677f8b9ab0599b135c/html5/thumbnails/8.jpg)