Mt. Everest Biogas Project Garry C Porter July 23, 2014 MtEverestBiogasProject.org

Upload: sustainable-summits-initiative

Post on 14-Apr-2017

116 views

Category:

Environment


0 download

TRANSCRIPT

Page 1: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas Project

Garry C PorterJuly 23, 2014MtEverestBiogasProject.org

Page 2: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas Project

• The Problem

• Who are we?

• Accomplishments

• Implementation Plan

• Summary

Agenda

Page 3: Garry Porter - Mt. Everest Biogas Project
Page 4: Garry Porter - Mt. Everest Biogas Project
Page 5: Garry Porter - Mt. Everest Biogas Project
Page 6: Garry Porter - Mt. Everest Biogas Project
Page 7: Garry Porter - Mt. Everest Biogas Project
Page 8: Garry Porter - Mt. Everest Biogas Project
Page 9: Garry Porter - Mt. Everest Biogas Project
Page 10: Garry Porter - Mt. Everest Biogas Project
Page 11: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas ProjectThe Problem

Page 12: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas ProjectWho are we?

• Can existing biogas digester design/technology be implemented at Gorak Shep?

• If implemented, is it sustainable?

• If successful, can it be replicated?

• April 2010 meeting with Dan Mazur

Page 13: Garry Porter - Mt. Everest Biogas Project
Page 14: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas ProjectIf digester implemented at Gorak Shep

Page 15: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas ProjectValue of biogas at Gorak Shep

Page 16: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas ProjectWho are we?

• All volunteer engineering team from the Seattle, Washington area

• Key affiliations/partnerships with:

• Engineers Without Borders (EWB-Seattle)• Architects Without Borders (AWB-Seattle)• Department of Engineering

• University of Washington• Seattle University

• Living Earth Institute (LEI-Seattle)• Center for Urban Waters (University of Washington)• Biogas Support Programme (BSP-Nepal)• Mt. Everest Foundation for Sustainable Development (MEFSD-Nepal)• Sagarmatha Pollution Control Committee (SPCC)

• Not a Business Entity• Transparency of design

Page 17: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas ProjectAccomplishments

• Will a biogas digester function using human waste as input media?• What are critical performance parameters?

• Internal temperature (20-30 C)• Digester retention time

• What is atmospheric environment of Gorak Shep?• TMY2 data acquired for Gorak Shep

• What is the heat loss of a digester at Gorak Shep?• Biogas digester modeled• Heat loss model developed

• How to replace heat loss using:• Off the shelf components• Available in Kathmandu• Can be transported to Gorak Shep by yak or porter• Long term sustainable

Page 18: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas ProjectAccomplishments

• Water quality testing conducted under NSF and AAC grant

• Gorak Shep, Luboche, Everest base camp and camp 2• E-coli and total coliforms were 2 to 20 times the USEPA drinking standards• Follow up tests with U. of W. Urban Water studies in 2013 and 2014

• Site Survey in May 2013• Gorak Shep community meetings• Sagarmatha Pollution Control Committee briefing• Biogas Sector Programme briefings• Potential Nepal hardware suppliers

• Rough Order of Magnitude (ROM) Cost Estimates Developed

Page 19: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas ProjectDesign Conclusions

• Shelter required over the digester • Effluent disposed in underground drain field• Three feasibility designs evaluated under worst case

assumptions

• Passive Solar shelter will not provide sufficient heat• PV solar panel array with heated water coils in digester floor• PV solar panel and battery array with immersion coil in digester

• Design Documented in Basis of Design (BOD)

• Technical peer review being conducted in July 2014

Page 20: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas ProjectFeasibility Designs

Heating solution must replace system heat lossHeating solution must heat daily slurry to 30C

200 watts for digester150 watts for heating slurry to 30C

PV solar array with heated coils in floor of digester24 PV solar panelsInsulated water storage deviceImmersion coil in water storageCirculation pump with battery back up

PV solar and Battery array30 PV Solar panels24-2Volt battery pack

Page 21: Garry Porter - Mt. Everest Biogas Project
Page 22: Garry Porter - Mt. Everest Biogas Project
Page 23: Garry Porter - Mt. Everest Biogas Project
Page 24: Garry Porter - Mt. Everest Biogas Project
Page 25: Garry Porter - Mt. Everest Biogas Project
Page 26: Garry Porter - Mt. Everest Biogas Project

Must demonstrate economic and environmental benefits for Gorak Shep community

Phase 1: Construction of pilot biogas system• Hire and train 2 system operators at Gorak Shep• Operate system with water for 1 year• Funded and managed by Seattle based team in concert with EWB-Seattle, AWB-Seattle and BSP-Nepal• Requires approval by SPCC and Gorak Shep community

Phase 2: Long term sustainability and operations • Ownership of biogas system by SPCC or tea house owners• Provide technical/operational support with: Seattle, EWB, SPCC and BSP team• Operations and Maintenance funding provided by additional climber fees

Mt. Everest Biogas Project2 Phase Implementation Plan

Page 27: Garry Porter - Mt. Everest Biogas Project

Mt. Everest Biogas ProjectSummary

• Technically the biogas digester will work at Gorak Shep

• Implementation is the challenge

• Team is committed thru construction and initial operation

• Fund raising for biogas system at Gorak Shep starts in 2014

• Construction starts in 2015

• Initial contact with climbing community is positive

• Need financial support and implementation advice

Thank you