fynsværket, fv07 · 2018. 3. 22. · future earnings of fynsværket blok 7, based on a client’s...

75
No. of characters w/ spacing: 59,294 Space occupied by figures and tables: 9 pp. Fynsværket, FV07 Modelling potential future earnings at Fynsværket Semester project - Energy Technology, ET-EKO-U2, 2. Semester, Southern University of Denmark, May 29 th 2015 Supervisor: Christian T. Veje Written by: Mathias C. Gjøl (16-12-1992) Kristoffer Christensen (03-03-1995) Jonathan M.R.-Hemmingsen (07-04-1993) Mads Odsgaard Olesen (13-10-1992) Jonas Korsgaard (27-09-1993) Karl Meyer (10-04-1993)

Upload: others

Post on 30-Jan-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • No. of characters w/ spacing: 59,294

    Space occupied by figures and tables: 9 pp.

    This report may be published

    Fynsværket, FV07 Modelling potential future earnings at Fynsværket

    Semester project - Energy Technology, ET-EKO-U2, 2. Semester,

    Southern University of Denmark, May 29th 2015

    Supervisor:

    Christian T. Veje

    Written by:

    Mathias C. Gjøl (16-12-1992) Kristoffer Christensen (03-03-1995)

    Jonathan M.R.-Hemmingsen (07-04-1993) Mads Odsgaard Olesen (13-10-1992)

    Jonas Korsgaard (27-09-1993) Karl Meyer (10-04-1993)

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 2 / 75

    1 Abstract

    The focus of this project has been producing a mathematical model that is able to calculate

    future earnings of Fynsværket Blok 7, based on a client’s own expectations of electricity and

    fuel prices. FV07 is as CHP-plant and the only large power plant on Fyn. In this report, FV07 is

    described and hereafter analysed from a political and economic point of view. A

    thermodynamic assessment of the plant is made and, as the project outline states, a

    mathematical model is established, in order to give a potential buyer a better overview of the

    plant and its related costs and revenues.

    Furthermore, the optimal electricity production is estimated alongside with the total revenue

    of sales, total costs and in the end the optimal annual profit of FV07.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 3 / 75

    2 Table of contents

    1 Abstract ...................................................................................................................................... 2

    2 Table of contents ........................................................................................................................ 3

    3 Introduction................................................................................................................................ 4

    4 Price regulations ......................................................................................................................... 6

    4.1 Regulations of the energy prices ......................................................................................... 6

    4.2 Marginal cost ....................................................................................................................... 6

    4.3 Net electricity price ............................................................................................................. 7

    4.4 Financial challenges associated with running a CHP ........................................................... 7

    4.5 Interconnections of European electricity ............................................................................ 9

    5 Political regulations .................................................................................................................. 10

    5.1 Cooling water .................................................................................................................... 10

    5.2 Air pollution ....................................................................................................................... 10

    5.3 Security of supply .............................................................................................................. 11

    5.4 Economy ............................................................................................................................ 12

    6 Optimising the electric efficiency ............................................................................................. 13

    6.1 The Rankine cycle .............................................................................................................. 13

    6.2 Thermal efficiency ............................................................................................................. 13

    6.3 The Rankine cycle at FV07 ................................................................................................. 14

    6.4 Assumptions ...................................................................................................................... 15

    6.5 Electric efficiency .............................................................................................................. 16

    6.6 Conclusion ......................................................................................................................... 18

    7 Fuel input calculation ............................................................................................................... 19

    8 Model development ................................................................................................................. 21

    8.1 Model assessment ............................................................................................................. 23

    9 Simulations ............................................................................................................................... 25

    9.1 Simulation 1....................................................................................................................... 25

    9.2 Simulation 2....................................................................................................................... 26

    9.3 Simulation 3....................................................................................................................... 28

    10 Discussion ............................................................................................................................... 31

    11 Conclusion .............................................................................................................................. 33

    12 References .............................................................................................................................. 35

    13 Appendix list ........................................................................................................................... 37

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 4 / 75

    3 Introduction

    Fynsværket (FV) is a combined heat and power plant (CHP) located, as the only central plant, in

    Odense, Fyn. It consists of two operating blocks, block 7 and 8. Block 8 is a biomass-fired unit

    that is able to run on both straw and wood pellets, producing exclusively district heat, whilst

    block 7 is coal fired.

    Fynsværket Blok 7 (FV07) is the main production unit at FV and the subject of the research of

    this report. In full condensing mode FV07 can produce as much as 416 MW and has a lower

    capacity limit of 74 MW. When producing district heat the lower limit reaches 62.2 MW with a

    district heat capacity of up to 582 MJ/s. For electricity production, FV07 utilises five steam

    turbines, two one-sided and three two-sided symmetric turbines connected to a generator.

    The produced electricity is then supplied to the main transmission network at 400 kV. Some of

    the discharge from the second medium pressure turbine is used to produce district heat in a

    heat exchanger; this amount can be regulated at will. For a full schematic of the plant, please

    see Appendix 8.

    Considering the Danish 2050 emission targets, coal fired power plants such as FV are to be

    scuttled by the year 2050. Due to financial doubts concerning the future feasibility of FV,

    Vattenfall put it up for sale in 2010. This report aids a potential buyer in the evaluation of

    whether purchasing FV is still an attractive investment, by both analytically and

    mathematically, investigating the issues and advantages of operating FV.

    The report outlines the production and verification of a mathematical model, which calculates

    the future earnings of FV07 based on data supplied by Vattenfall. It contains a description of

    how the cooling water temperature influences the electrical efficiency of a Rankine cycle. An

    outline of the method used to calculate the fuel input to the boiler from measurements of the

    flue-gas composition and knowledge of the fuel-composition. In addition, an assessment of

    said method’s accuracy, as well as a description of the political and economic factors that

    govern the production of electricity and district heat at a CHP-plant. The stem data used in this

    report is depicted in Figure 3-1.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 5 / 75

    Figure 3-1: Measured electricity and district heat production in 2010 at FV07.

    To make the report easy to read, FV is described with the most significant information in the

    introduction. Every section starts with its own introduction to each subject, followed by the

    main text with references highlighted in brackets for easy access to literature and a numerated

    structure for each paragraph and figure. The main results of each paragraph are summed up in

    a partial conclusion that leads up to a discussion and final conclusion.

    -100

    0

    100

    200

    300

    400

    500

    600

    700

    Electricity production [MW] District heat production [MJ/s]

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 6 / 75

    4 Price regulations

    The energy market, NordPool, is the exchange where energy prices are determined. It is

    elaborated further in this chapter, both how the market price for electricity is determined and

    how the marginal cost (MC) of a power plant is established. Some of the tariffs and taxes on

    electricity are discussed and the net price for the consumer is determined.

    4.1 Regulations of the energy prices

    On the exchange the different production reports are sorted by their MC, cheapest first. The

    energy consumption determines which and how many of the energy producing plants that

    have to produce and deliver electricity. Then the plant with the highest MC of the producing

    plants sets the overall market price, as the price will be equal to the highest MC of the

    producing plants. The price of electricity is found where demand meets production in Figure 4-

    1, and the MC of the last plant that produces the energy that the demand requires, will then

    be the electricity price. In the case of Figure 4-2, a coal condensation power plant will set the

    market price.

    If a large fraction of the demand is covered by e.g. wind energy because of good conditions,

    producers with higher MC cannot cover their costs through the market price and so, cannot

    compete given that the electricity price will now be lower than the power plant’s MC.

    Figure 4-1: Determination of market prices, found from the demand curve.

    4.2 Marginal cost

    The marginal production cost is found from an equation where the following basic information

    about the plant is needed:

    o Fuel prices (FP)

    o Fuel consumption (FC)

    o Variable operation cost (VC)

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 7 / 75

    o CO2 price (CO2P)

    o CO2 emission (CO2E)

    With these costs, the marginal cost is found from this equation [1]:

    𝑀𝐶 = 𝐹𝑃 ∙ 𝐹𝐶 + 𝑉𝐶 + 𝐶𝑂2𝑃 ∙ 𝐶𝑂2𝐸

    4.3 Net electricity price

    Consumers of electricity are imposed some taxes and tariffs when using the electricity grid.

    Appendix 9 shows taxes and tariffs for households, small companies and large companies.

    Three, and the highest of the tariffs, are the Grid-tariff, System-tariff and PSO-tariff. The Grid-

    and the System-tariff are used to maintain the grid. The PSO is used to fund the expansion of

    the Danish renewable energy sector. The Danish Climate- and Energy-ministry established the

    state owned company Energinet.dk in 2005 [2]. Energinet.dk manages the tariffs. Energinet.dk

    is the Transmission System Operator (TSO) and is responsible for the Danish transmission

    system and the security of supply. Due to the added taxes and tariffs, including System- and

    Grid-tariffs to Energinet.dk, the net electricity price is relatively high even with a low spot

    electricity price.

    As explained earlier, the spot price is determined from the demand. With a high demand the

    price will rise, as producers with higher MC will need to deliver electricity. The TSO manages

    the funds to maintain and extend the grid. Therefore, all the consumers give financial help to

    push the Danish grid towards a green revolution.

    4.4 Financial challenges associated with running a CHP

    In Figure 4-2, the production at FV07 is illustrated for a period of 36 hours, starting on

    December 10th. There is a close correlation between the production in Figure 4-2 and the DK1

    spot price vs. the marginal cost of FV07 depicted in Figure 4-3.

    Figure 4-2: Production at FV07 vs. Minimum production over a 36-hour period from 10/12-2010 11.00 pm to 12/12-2010 11.00 am.

    0

    100

    200

    300

    400

    23 1 3 5 7 9 11 13 15 17 19 21 23 1 3 5 7 9 11

    MWh

    Hours

    Electricity production min. electricity production

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 8 / 75

    Figure 4-3: Marginal cost vs. DK1 spot price over a period of 36 hours from 10/12-2010 11.00 pm to 12/12-2010 11.00 am.

    The decline of the price is caused by the large percentage of wind energy in the Danish energy

    system. Because electricity in Denmark is bought from the producers with the lowest short-

    term MC, as explained in section 4.1, CHP-plants running on coal, like FV, cannot compete with

    wind, as wind energy uses no fuel and emits no CO2, which is a large fraction of the MC of e.g.

    coal fired power plants.

    Since wind turbines have no expenses for fuel, very low maintenance cost and are by

    legislation ensured a minimum price per MWh, they report a MC to Nord Pool of 0 DKK/MW to

    be sure to sell all the electricity they produce.

    This poses a problem for power plants like FV as they are forced to stop production in periods

    with sufficient wind. This ads expenses because they have to start and stop, increasing fuel

    consumption for start-ups. This is visible in Figure 4-2 and 4-3. As the price declines in Figure 4-

    3 and goes below the MC line it can be seen from Figure 4-2 that the production falls below 74

    MW, which is the technical minimum production of electricity. Thus, it is assumed that

    production ceases completely. With more wind energy, this happens more frequently and

    lowers the amount of MWh’s produced. As a result, FV has fewer units to divide the overall

    cost by. This is the challenge FV is facing. As more sustainable production, favoured by the

    government, is connected to the grid, they risk having to shut down the plant.

    If some of the CHP-plants stop producing for good, because of their bad economy, it will lower

    the security of supply in the grid, due to the fact that the fluctuating wind production does not

    have a backup alternative to CHP plants, that can deliver sufficient regulatory capacity. To

    counteract this, unless alternative regulateable energy sources are found or large-scale energy

    storage becomes an option, the government will be forced to come up with a way of

    supporting the plants. Such a way could be a large power transmission-grid across Europe, so

    that electricity can be distributed to areas were it is needed, when production in other areas is

    higher than needed.

    Vattenfall applied for an approval to shut down FV07 by 2016 [3] because the cost of

    operation was too high compared to the revenue. The request was denied due to the risk of

    -200

    -100

    0

    100

    200

    300

    400

    500

    23 1 3 5 7 9 11 13 15 17 19 21 23 1 3 5 7 9 11

    kr/MWh

    Hours

    Maginal cost Spotprice DK1

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 9 / 75

    unbalancing the electricity supply on Fyn, as FV is the only major power plant on Fyn. To

    ensure that Denmark will have plants in the future to supply a fluctuation backup and peak

    load, some form of financial incentive for keeping the plants running is needed. Alternatively

    Denmark could experience blackouts or be forced to import the electricity at a very high price.

    4.5 Interconnections of European electricity

    When the production of wind energy in Denmark is low, the countries surrounding it, like

    Sweden and northern Germany, with a lot of wind energy, will also have a low wind energy

    production, making the electricity price rise. The large amount of hydro energy in Norway

    could be put into action, but as they will be connected to England and Holland, the demand

    will rise and so will the price. Denmark’s own connection to Holland through the Cobra cable

    can ensure a higher security of supply but still at a higher price as Holland also has a large

    number of connections to other countries, which would most likely be in need of electricity

    when Denmark is, as adjacent countries such as Germany have large amounts of wind energy

    as well. This demand will in itself raise the price of electricity. The reason for Holland having

    capacity to adjust the production if needed, is because of their many gas turbines, which have

    higher marginal costs than renewable energy systems and even coal fired power plants as

    FV07. Therefore, the price of electricity will rise as a function of these higher costs.

    The uncertainty of what the spot price will be set at is the price a country pays for not being

    energy-self-sufficient. That is why it is necessary to maintain the CHP-plants. If larger

    interconnections of European electricity are not completed, CHP-plants might be the cheapest

    alternative in the long term to keep the security of supply at an acceptable level, until a

    sufficient alternative has been found.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 10 / 75

    5 Political regulations

    To manage FV correctly, it is necessary to ensure that the political aspects are considered. In

    this section, the main political aspects for FV are mentioned and discussed. The main aspects

    are the cooling water emission, the air pollution, the security of supply and the economy.

    5.1 Cooling water

    The cooling water used in the condenser comes from Odense New Canal, and the discharged

    water goes into Odense Old Canal. The limit value for the temperature-rise of the water from

    intake to outlet of the cooling system is 8°C. The chosen value is set to protect the flora and

    fauna in the old canal. Even with the limit value, the temperature differences have a minor

    effect on the flora and fauna. Miljøstyrelsen is trying to find an alternative to the discharged

    cooling water, because of these effects [4].

    5.2 Air pollution

    Figure 5-1 shows the average emission of SO2, NOx and dust. The limit value of SO2 and NOx is

    200 mg/Nm3. For dust, the limit value is 30 mg/Nm3 in 2013. In 2015 the limit value for dust is

    20 mg/Nm3, and the limit value for SO2 and NOx is still 200 mg/Nm3 [5]. FYV7 has an average

    emission far below the limit values.

    Figure 5-1: Review of the limit values and the average emission of FV07 for 2013 [4]

    The different power and district heat producing companies, including FV, are imposed a CO2-

    quota law, as a part of the third package of liberalisation. This means that they have to pay for

    their CO2 emission by buying quotas as well as being obligated to report their GHG-emissions.

    The entire purpose of this law is to reduce the emissions by encouraging development of less

    polluting technologies through an increased running-cost for conventional technologies [6].

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 11 / 75

    Emission Unit 2009 2010 2011 2012 2013

    CO2 ton 1,956,875 1,996,064 1,329,548 1,636,993 1,659,811

    CO2 g/kWh 461 414 379 415 417

    SO2 g/kWh 0.11 0.09 0.08 0.06 0.07

    NOX g/kWh 0.17 0.16 0.14 0.11 0.10

    Dust g/kWh 0.03 0.02 0.02 0.03 0.01

    Table 5-1: Table of GHG emissions from FV [4].

    5.3 Security of supply

    As FV supplies electricity and district heat to the Danish energy sector, they are obligated to

    act in accordance with certain laws and regulatory statements put forth by the respective

    authorities and the Danish government.

    5.3.1 Law of electricity supply

    FV is assigned to the law of electricity supply [7] under chapter 3, §10. They are licenced to run

    an electricity producing plant with a capacity over 25 MW [8]. By signing the licence that

    allows them to produce electricity, they are assigned to fulfil the duties and conditions

    mentioned in the law of electricity supply, the law about advancing renewable energy [9] and

    the law of CO2 quotas [6]. Energistyrelsen can, with a one-year notice, order FV to deliver a

    minimum electricity capacity, according to §50 [7].

    The purpose of the law of electricity supply is, according to §1, to secure that the Danish

    electricity supply is organized in agreement with the security of supply. Its target is to deliver

    cheaper electricity to the consumers and advance the sustainability of the energy use.

    5.3.2 Law of heat supply

    The purpose of the law of heat supply [10] is expressed in §1 and is to advance the economic

    use of energy to heat indoor areas and supply them with hot water. The district heat supply

    should be in agreement with the purpose from §1 to advance the co-generation of electricity

    and district heat as much as possible. The municipalities are responsible for the approval of

    projects for collective heat supply. With the licence to sell electricity they have the duty to

    supply district heat to the plant’s district heat consumers, in accordance with §12 [7].

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 12 / 75

    5.4 Economy

    Energinet.dk has to perform the listed duties in §28 in the law of electricity supply. In §8 of the

    law of electricity supply, it is stated the consumers of electricity have to cover a part of the

    expenses, caused by Energinet.dk’s obligation to maintain the public duties listed in §8.

    Denmark has a goal to achieve a large reduction in CO2 emissions, and have made a political

    plan towards 2020 and 2050. To achieve the goals set by the plan Denmark has to make a big

    investment in renewable energy. The financial resources for the plan come from the PSO tariff.

    The PSO tariff is imposed on all electricity consumers, and finances all new renewable projects

    that apply for support.

    Figure 5-2: PSO with planned politics and alternatives without subsidies to power production. The left figure shows the renewable energy sector if the political plan proceed with their subsidies.

    The right figure shows if they do not proceed. [11]

    Figure 5-2 shows two different scenarios regarding the 2020 and 2050 plan. Negative aspects

    of the planned politics include that even if the electricity spot price declines, the net price for

    electricity rises because of the high PSO tariff, and the fact that wind turbines and farms are

    guaranteed a fixed price when selling their electricity for a fixed amount of time or produced

    energy, regardless of the spot price. The difference between the spot price and the guaranteed

    price is covered by the PSO tariff. This subsidisation puts other renewable technologies at risk

    of being without a financial incentive.

    The Danish goals for reducing CO2 emissions are more ambitious than the goals of the

    European Union (EU) as shown in Appendix 10. FV is licenced to produce electricity and is

    assigned to the law of electricity supply, the law of heat supply and different environmental

    laws. The environmental laws make it difficult for FV07, as a coal fired CHP, to survive in the

    future, because of the 2020 and 2050 plans for EU and Denmark. Until then FV is bound to

    deliver heat and electricity when needed.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 13 / 75

    6 Optimising the electric efficiency

    In this section, the Rankine cycle used at FV07 is reviewed. The relation between cooling water

    temperature used in the condenser and the overall electricity efficiency is examined with the

    purpose of optimising the net work output of FV07.

    At FV, the condenser uses cooling water from Odense New Canal and discharges the heated

    water into Odense Old Canal, joining Odense Stream and Odense Fjord. Since the canal has

    inconsistent water temperatures throughout the year, the temperature varies and therefore

    the overall net work output at FV07 varies. This relation is elaborated later on, however first

    an ideal Rankine cycle is reviewed.

    6.1 The Rankine cycle

    In the T-s diagram in Figure 6-1, an ideal Rankine cycle is illustrated. The cycle consists of four

    steps. Step 1 to 2 is an isentropic compression in the pump, step 2 to 3 is a constant pressure

    heat addition in the boiler, step 3 to 4 is an isentropic expansion in the turbine, and step 4 to 1

    is a constant pressure and heat rejection in the condenser. The grey area in the illustration

    represents the net work produced in the cycle.

    Figure 6-2: Illustration of an ideal Rankine cycle in a T-s diagram. The grey area represents the Wnet. [13]

    6.2 Thermal efficiency

    The thermal efficiency is determined using Equation 6-1 [12]. To obtain a higher efficiency, it is

    necessary to increase the net work output relatively more than the heat input, obtaining an

    efficiency as close to unity as possible.

    𝜂𝑡ℎ =

    𝑊𝑛𝑒𝑡𝑄𝑖𝑛

    (6 - 1)

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 14 / 75

    The optimal thermal efficiency of a Rankine cycle is approximately 15-20 %. Several factors

    affect the efficiency of the cycle and thus the actual power output. Both friction and heat loss

    in the various components of the power plant will cause the pressure to drop. To maintain the

    required net work output, more heat addition in the boiler is required causing the thermal

    efficiency to decrease. These factors are difficult to improve. One way to regulate the

    efficiency is to control the temperature of the cooling water used in the condenser.

    Considering Figure 6-2, the points 1’, 2’ and 4’ are introduced to the illustration of an ideal

    Rankine cycle. Reducing the temperature in the condenser will create point 4’ and therefore

    point 1’, since both the temperature and pressure are held constant in the ideal process in the

    condenser. Reducing the temperature in the condenser will increase the Wnet, being the grey

    area enclosed by the points 1, 4, 4’ and 1’ in Figure 6-2. The required heat input, Qin, is also

    increased but the change in heat addition is relatively small compared to the change in net

    work output and considering Equation 6-1, the thermal efficiency of the entire cycle is, by

    doing so, increased. The increase in required heat input is the red area enclosed by the points

    1, 1’, 2’ and 2 in Figure 6-2.

    Figure 6-3: Illustration of an ideal Rankine cycle in a T-s diagram. The grey area illustrates the increase of Wnet by lowering the temperature in the condenser and the red area illustrates the increase in Qinput. [13]

    There is a deviation from the ideal Rankine cycle and the actual cycle at FV07 due to

    irreversibilities in the various components throughout the cycle. The common reasons for

    irreversibilities occur in the piping due to heat loss and friction in the piping connecting the

    various components.

    6.3 The Rankine cycle at FV07

    In order to determine the thermal efficiency and how it fluctuates at FV07, the software

    Engineering Equation Solver (EES) is used. All the relevant information, such as temperature,

    pressure, mass flow etc., used in the thermodynamic model to determine the enthalpies and

    the work- and heat-output, is extracted from the data sheet Kopi af Billeder fra turabs til

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 15 / 75

    studerende 2012-04-10 [14]. The model and its specific results can be examined further in

    Appendix 11.

    In Figure 6-3, the P-h diagram of the Rankine cycle at FV07 is illustrated. In the diagram, the

    process 1 to 2 is the heat addition in the boiler. Process 2 through 8 is the turbine cycle. In a

    Rankine cycle, it is possible to reheat the steam by conducting it back through the boiler. By

    reheating the steam in the cycle, a higher optimal thermal efficiency than 15-20 % is achieved

    due to e.g. reducing moisture content in the steam and increased enthalpies.

    At FV07, the steam is reheated twice; from the high-pressure turbine to the first medium-

    pressure turbine and from the second medium-pressure turbine to the low-pressure turbines,

    causing the overall net work output to rise. The rise in enthalpy from the reheat is illustrated in

    the P-h diagram in Figure 6-3, from point 3 to 4 and from point 6 to 7.

    Figure 6-4: P-h diagram illustrating the Rankine cycle at FV07.

    The process from 8 to 9 is the heat extraction in the condenser, implying that point 8 is

    regulated by the cooling water temperature. The final process to complete the cycle from the

    pump, through the feedwater tank and the pre-heaters and into the boiler again is process 9

    through 1.

    6.4 Assumptions

    Some assumptions have been made in order to define the cycle and to determine the thermal

    efficiency at FV07. It is important to state that the thermodynamic model in this report

    assumes FV07 to produce no district heat. This assumption causes the thermal efficiency of the

    cycle to be calculated completely from electricity production; that is, the electric efficiency

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 16 / 75

    solely depends on the generator efficiency. The specific generator used at FV is unknown;

    however, due the scope of the production requirement at FV07, it is assumed that it is a highly

    productive and modern generator suggesting an efficiency of about 98% [15].

    The turbines have outlets to the pre-heaters, to Stobudako and to other parts of FV. These

    outlets have been neglected in the model due to a lack of information in the data sheet. By

    simplifying the model in such a way, the calculated enthalpies throughout the cycle will differ

    from the actual energy output making the model rather inaccurate. However, since the subject

    of inquiry in this section is the relation between the efficiency and the cooling water

    temperature, the actual energy output will only affect the outcome by resulting in a higher

    theoretical efficiency than the actual one at FV07 preserving the relation between rise in

    efficiency per degree Celsius, %

    °𝐶.

    When considering the relation between the inlet cooling water temperature and the inlet

    temperature of the steam into the condenser, a relation of 10°C is used. It has not been

    possible to determine the actual relation between the two streams and therefore this relation

    is considered a reasonable assumption.

    When calculating the thermal efficiency at FV07, the cycle is considered an ideally reversible

    process; that is, the thermal efficiency of the heat engine is considered equal to the reversible

    thermal efficiency [12].

    𝜂𝑇ℎ𝑒𝑟𝑚𝑎𝑙 = 𝜂𝑇ℎ𝑒𝑟𝑚𝑎𝑙,𝑟𝑒𝑣 (6 - 2)

    Since the heat engine at FV07 is considered reversible, the efficiency is determined as,

    𝜂𝑇ℎ𝑒𝑟𝑚𝑎𝑙 = 1 −

    𝑇𝐿𝑇𝐻

    (6 - 3)

    By doing so, the TL is regulated by the cooling water temperature in the condenser causing the

    overall thermal efficiency to fluctuate.

    6.5 Electric efficiency

    To examine how the inconsistent water temperatures in the cooling water flow affects the

    lowest temperature in point 4’ in Figure 6-2, the turbine cycle at FV07 is divided into two parts,

    part A and part B, to make sure that the reheat process from the high-pressure turbine to the

    medium-pressure turbine is taken into account. Part A covers the high-pressure turbine and

    part B covers the rest of the turbines combined. The reheat process before the low-pressure

    turbines is neglected in this model because the change in enthalpy in this process is relatively

    small and because otherwise the complexity of the model exceeds the scope of this report.

    At a cooling water temperature of 1°C, the model results in the following thermal efficiency.

    𝜂𝑇ℎ𝑒𝑟𝑚𝑎𝑙, 𝑨 = 1 −

    341.4°𝐶 + 273.15

    541.1°𝐶 + 273.15= 0.2453 (6 - 4)

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 17 / 75

    𝜂𝑇ℎ𝑒𝑟𝑚𝑎𝑙, 𝑩 = 1 −

    (1 + 10)°𝐶 + 273.15

    509.1°𝐶 + 273.15= 0.6368 (6 - 5)

    Thus, the overall thermal efficiency at FV07 is determined to be:

    𝜂𝑇ℎ𝑒𝑟𝑚𝑎𝑙 =

    𝜂𝑇ℎ𝑒𝑟𝑚𝑎𝑙, 𝑨 + 𝜂𝑇ℎ𝑒𝑟𝑚𝑎𝑙, 𝑩2

    = 0.441 (6 - 6)

    This thermal efficiency is to be multiplied with the efficiency of the generator used at FV07,

    which is set to be 98 %, to determine the electricity efficiency of FV07:

    𝜂𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐𝑖𝑡𝑦 = 𝜂𝑇ℎ𝑒𝑟𝑚𝑎𝑙 ∙ 𝜂𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑜𝑟 (6 - 7)

    𝜂𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐𝑖𝑡𝑦, (1°𝐶) = 0.441 ∙ 0.98 = 0.4322 = 43.22 % (6 - 8)

    By using the model in EES, the fluctuating efficiencies according to the respective cooling water

    temperatures are calculated. The model shows that the average rise in efficiency per decrease

    in cooling water temperature is 0.0625 %

    °𝐶. In Figure 6-4, the relation between temperature and

    efficiency is illustrated. The outlet cooling water temperature at FV07 is also illustrated.

    Figure 6-4: The relation between cooling water temperature and electricity efficiency.

    By using EES to create a T-s diagram, the difference in net work output is illustrated. In Figure

    6-5 the temperatures and entropies of the Rankine cycle at FV07 are inserted. The difference

    between point 9a and 9b represents the change in net work output. The point 9a represents a

    cooling water temperature of 1°C and 9b represents 25°C.

    41

    41.5

    42

    42.5

    43

    43.5

    0 5 10 15 20 25 30 35 40

    Elec

    tric

    ity

    effi

    cien

    cy [

    %]

    Cooling water temperature [°C]

    Inlet temperature

    Outlet temperature

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 18 / 75

    Figure 6-5: T-s diagram of the Rankine cycle at FV07. 9a represents a cooling water temperature of 1°C and 9b represents a temperature of 25°C.

    6.6 Conclusion

    The theoretical electricity efficiency calculated is estimated to be higher than the actual

    efficiency at FV07, due to the isolated enthalpy system throughout the Rankine cycle as

    elaborated in section 6.3. The assumption that the turbine cycle at FV07 is considered a

    reversible heat engine will also result in a higher theoretical efficiency than the actual.

    However, the relation between temperature and electricity efficiency is considered

    unaffected. For every degree the temperature rises, the efficiency will decrease 0.0625

    percentage points leading to the conclusion that the electricity efficiency at FV07 will be at its

    highest during the winter, when the temperature in Odense New Canal is at its lowest.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 19 / 75

    7 Fuel input calculation

    The fuel input is calculated from the composition of the flue gas and knowledge of the fuel

    composition via an oxygen balance calculation [16]. The data used for a comparison of the

    results is a direct measurement of the hourly average fuel input to the boiler for 24 hours from

    the 10th of February 2011 to the 11th of February 2011.

    C 63.40 % 0.6340 kg/kg

    H 3.55 % 0.0355 kg/kg

    S 0.60 % 0.0060 kg/kg

    O2 8.16 % 0.0816 kg/kg

    N 1.39 % 0.0139 kg/kg

    H2O 10.40 % 0.1040 kg/kg

    Ashes 12.50 % 0.1250 kg/kg

    Table 7-1: Table of the composition of coal on a mass basis.

    When the coal is burned, the water evaporates and is therefore negligible. The composition of

    the ash is not known and it is therefore impossible to do any calculations on this part of the

    fuel, hence, it is not included in the calculations. Assuming a complete combustion of the fuel

    due to an oxygen surplus, the following six reactions occur:

    𝐶 + 2𝑂 → 𝐶𝑂2 𝑆 + 2𝑂 → 𝑆𝑂2

    𝑁 + 𝑂 → 𝑁𝑂 𝑁 + 2𝑂 → 𝑁𝑂2

    𝑁 + 3𝑂 → 𝑁𝑂3 2𝐻2 + 2𝑂 → 2𝐻2𝑂

    Now the molar composition and the oxygen required for full combustion is calculated from the

    respective molar masses of the elements and the stoichiometric coefficients of the reactions:

    Molar composition Required O2

    C 0.05278495 kmol/kg 0.052784947 kmol

    H 0.03522035 kmol/kg 0.008805088 kmol

    S 0.00018712 kmol/kg 0.000187120 kmol

    O2 0.00510319 kmol/kg -0.002551595 kmol

    N 0.00099238 kmol/kg 0.001240478 kmol

    Table 7-2 Molar composition and amount of O2 required for a full combustion.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 20 / 75

    The oxygen is negative because it is already present in the coal and it must therefore be

    subtracted from the oxygen input to the combustion. The oxygen required for the nitrogen

    combustion is calculated based on an assumption of an equal distribution of NO, NO2 and NO3.

    The oxygen factors are now summarised to achieve a factor of how much oxygen is needed to

    fully combust 1 kg of the coal-type used in this case: 0.060466038 kmol O2/kg coal.

    Assuming a dry-air-basis the air-input-flow is now converted to oxygen input flow in kmol/s

    using the density of air at 20°C, an assumed air composition of 79 % N and 21 % O2, and the

    molar mass of dry-air. The oxygen content of the flue gas is now subtracted from the input

    flow in order to calculate the amount of oxygen used in the combustion in kmol/s. This is then

    divided by the amount of oxygen needed to fully combust 1 kg of coal found earlier, to give a

    fuel input in kg/s. Multiplying this with the energy content of the coal-type used at the plant

    and converting to the correct unit yields an estimate of the energy supplied to the boiler and

    can now be compared to the measured value supplied by Vattenfall. The estimated deviation

    from the actual supplied value is now calculated for all 24 hours and averaged; this yields an

    average deviation of 5.09 %, which, considering the assumptions made earlier can be deemed

    a satisfactory result and the method can therefore be assessed to be accurate. For a full

    schematic of the calculations, refer to Appendix 12.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 21 / 75

    8 Model development

    The mathematical model simulates an optimal operation of FV07 and ensures that power

    production is always above the lowest possible electricity production capacity, while fulfilling

    the requirements for minimum district heat production. The model also ensures that FV07 only

    produces power where the marginal cost is lower than the electricity price.

    The model is constructed in MatLab [17] [18], so that a potential buyer of FV07 can simulate

    an optimal operation. Given other expectations of electricity and fuel prices, the vectors Coal

    which is the price of coal in 2010, ElectricityPrice which is the DK1 spot price in 2010 and

    Oil_Price_pr_tonne, which will be the price for a tonne of oil in 2010, can be changed at will, to

    simulate other scenarios. Furthermore, all other costs, as well as expectations for electricity

    and district heat production, are replaceable. The model can therefore be used to simulate any

    outcome based on any given assumption of costs, prices and so on.

    First, all the expenditures of FV07 are estimated, in order to make an estimate of the marginal

    cost of FV07.

    The model uses the input to perform various calculations. First, calculating the extra start-up-

    fuel consumption of oil in the hours where FV07 has been taken out of production. If FV07

    stands still for one to five hours, the start-up fuel consumption is categorized as a warm-start

    and will consume 800 GJ of fuel oil, and if the number of hours of standstill exceeds five hours,

    the oil consumption will be a cold-start and consume 1500 GJ fuel oil.

    The total fuel consumption, not including oil, is calculated on the basis of the fuel consumption

    model supplied by Vattenfall:

    𝐹𝑢𝑒𝑙 𝑐𝑜𝑛𝑠𝑢𝑚𝑝𝑡𝑖𝑜𝑛 (𝑝, 𝑞) = 𝑎2 ∙ 𝑝2 + 𝑎1 ∙ 𝑝 + 𝑏2 ∙ 𝑞

    2 + 𝑏1 ∙ 𝑞2 + 𝑐

    The inputs of this model include different coefficients, where a-coefficients are coefficients of

    the electricity production vector P, b-coefficients are coefficients of district heat production

    vector Q and the coefficient c is a baseline consumption coefficient. The coefficient values are:

    a2 0.00291999985879979

    a1 1.86501347204465∙10-4

    b2 6.429118241647

    b1 1.04197700742527

    c 426.593857573076

    Table 8-1: Coefficients to the fuel consumption formula

    Hereafter fuel and CO2-emission costs are found on the basis of both coal and fuel-oil prices, as

    the two fuels have different prices, heating-values and CO2-emissions pr. unit. The cost of fuel

    oil for start-ups is calculated on the basis of the consumption found above, the price of oil in

    2010 and heating-value of the oil. Similarly the cost of coal-based consumption is calculated

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 22 / 75

    from the heating-value of coal and price of coal in 2010 and the fuel-consumption model

    supplied by Vattenfall.

    In a similar manner, the cost of CO2 emissions is found based on different coefficients of

    emission for both oil and coal and the fuel-consumption of each type of fuel calculated above.

    Now additional production cost such as cost of chalk, water, catalysers, operating and

    maintenance cost, filter bags and disposal of waste products are summed up. Also, fixed costs

    such as cost of staff, handling of fuel oil, annual handling of coal, transport, harbour cost and

    annual investment of the plant are summed-up to give the total annual cost of the plant. The

    sum of these costs is now corrected for inflation, as the data is from 1993.

    Now the extra effect, and in relation to this the extra oil-consumption in times of peak-

    productions is calculated and added to the total fuel consumption. The cost is divided by the

    total fuel-consumption, to give the cost per fuel.

    The marginal fuel consumption is now found by differentiating the fuel-consumption model

    supplied by Vattenfall expressed in terms of electricity-production with respect to P.

    This marginal fuel-consumption is now multiplied with the cost per fuel to give the MC of

    electricity production for FV07 as a function of P.

    When the marginal cost has been derived, the optimization loop itself simulates an optimal

    operation of FV07 by ensuring that no electricity is produced when the marginal cost MC is

    higher than the electricity price by setting the values of district heat production in these points

    as zero. In these points no electricity production will be simulated either, as power production

    in the model is a function of district heating production Q, Cm and Cv-values.

    The estimated electricity-production is calculated from a Cv-value, which indicates how much

    electricity production is lost due to additional district heating production, and a starting value

    equal to the maximum possible electricity production of 416.225 MW. The minimum required

    electricity productions are found as the Cm-values: Cm1 and Cm2, with starting values found

    by choosing end values, supplied by Vattenfall, of the Cm1 and Cm2 lines and estimating the

    point where the line intersects with the second axis in the area of possible production. These

    two lines intersect each other at the minimum possible electricity production of 74 MW, which

    is included in the loop. The loop ensures that electricity production on these lines beneath 74

    MW is not incorporated in the calculations. Therefore production outside the area of possible

    production is not incorporated in order to yield a more accurate result. The total minimum

    production will be the sum of minimum required electricity production and minimum required

    electricity production2, as minimum electricity will be calculated from the Cm2 value until

    district heat production exceeds 110 MJ/s. Hereafter the minimum electricity production will

    be calculated from the Cm-value. If these values are added, they will yield the total minimum

    electricity production. A plot of the Cv, Cm1 and Cm2 functions is created to illustrate the area

    of possible production. The plot can be seen in Figure 8-1.

    The model also ensures that the production of electricity is higher than the lowest possible

    production of 74 MW, again by setting the district heating production Q to zero in points

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 23 / 75

    where the measured electricity production values supplied by Vattenfall are beneath 74 MW.

    Also, if district heat values, Q, and condensing mode values, C, are beneath zero, the electricity

    production will be set to zero. When all criteria above is fulfilled, the model will simulate an

    optimal operation of FV07.

    Figure 8-1: Cv, Cm1 and Cm2 curves as a function of electricity production and district heat production, showing the area of possible production.

    8.1 Model assessment

    The estimated fuel consumption is calculated on the basis of the model supplied by Vattenfall

    and estimates the measured fuel consumption with a percentile difference of 1.37 %. Reasons

    for the small differences include that the values of P and Q are hourly measurements of FV07´s

    electricity and district heat production. FV07 can alter the production of electricity and district

    heat rather quickly and since the measurements are hourly averages, this will be a reason for

    discrepancies as some data is lost by averaging.

    Estimated fuel consumption 21,208,700 GJ

    Measured fuel consumption 20,921,700 GJ

    Percentile differences in fuel consumption 1.37142 %

    Maximum Electricity Production 1,740,100 MWh

    Exact Electricity production 2,241,970 MWh

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 24 / 75

    Surplus Power -501,873 MWh

    Percentile difference in Electricity production 22.3853 %

    Minimum required Electricity production 752,011 MWh

    Minimum required Electricity production2 143,089 MWh

    Minimum required district heat 1,269,360 MJh

    Table 8-2: Mathematical model, operation of FV07, results.

    Some measured values supplied by Vattenfall are negative, which will also be a reason for

    discrepancies between measured fuel consumption and the estimated fuel consumption.

    Negative hourly values of electricity and district heat will yield a negative hourly, estimated

    fuel consumption. It is impossible to have negative values for fuel consumption leading to

    further discrepancies in the model.

    The potential buyer of FV07 can with confidence use the mathematical model as a guideline

    for the fuel consumption of FV07 in future years because of the small percentile difference

    from the simulation to the actual production. The model can also be used to calculate costs

    related to the operation of FV07, as seen in simulation 3, where the potential buyer can use

    own expected values for e.g. electricity and fuel prices.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 25 / 75

    9 Simulations

    The mathematical model simulating optimal operation of FV07 is tested in three different

    simulations each estimating different aspects of operation such as production, cost and profit

    from selling electricity.

    The first simulation estimates the electricity production of FV07 hour by hour in 2010. The

    second simulation estimates an annual deficit of inefficient production when FV07 is forced to

    produce electricity in times where the marginal cost exceeds the DK1 spot price for electricity,

    due to district heat requirements. The third simulation optimises the operation of FV07 and

    calculates the annual profit when producing and selling electricity only. That is when district

    heat productions and requirements are neglected.

    9.1 Simulation 1

    Simulation 1 simulates the production and operation of FV07 in the year 2010 hour by hour

    and compares the calculated electricity production, with the actual electricity production at

    FV07. Any discrepancies are explained. Until the point of deriving the MC, simulation 1 is

    identical to the overall model explained above.

    The simulation loop itself, ensures that electricity production values of P, lower than the

    minimum possible electricity production capacity of 74 MW are disregarded so that there in

    these hours is no electricity production, as such a production would be impossible in actual

    operation. Actual operation is approximated further as the model ensures that to electricity-

    production takes place when the values of district heat Q and operation in condensing mode C,

    are below zero, as no electricity production can take place if there is neither district heat

    production, nor condensing mode production.

    In simulation 1, the total minimum production will be the sum of minimum required electricity

    production and minimum required electricity production 2, as explained in the overall model.

    Table 9-1 contain the results from simulation 1.

    Maximum Electricity Production 2,396,010 MWh

    Exact Electricity production 2,241,970 MWh

    Surplus Electricity 154,041 MWh

    Percentage Error in Percent 6.87077 %

    Table 9-1: Simulation 1, operation of FV07 in 2010

    9.1.1 Assessment of simulation 1

    Reasons for discrepancies between the actual operation and simulation 1 include negative

    values of P in the actual measured values of FV07 in 2010. Such negative values are not

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 26 / 75

    technologically possible, and are therefore not included in simulation 1, which will be a reason

    why electricity production will be higher.

    Another similar reason for discrepancies would be that measured values of district heating

    production, at times, are negative. Such values are avoided by the optimization values of

    simulation 1, and as electricity production is a function of district heating, the summed up

    electricity production will as a result become higher for the simulation.

    Yet another reason for the difference in electricity production between simulation 1 and the

    actual operation of FV07, would be the hourly measurements of the electricity and district

    heat production of the actual operation of FV07. By averaging the output hourly, data is lost

    due to the large regulatory capacity of FV07. Had the measurements been available by minutes

    or even seconds, the discrepancies would lessen. It can be concluded that the simulation is

    somewhat accurate and can be used to simulate production at FV07 for a potential buyer of

    the plant.

    9.2 Simulation 2

    If FV07 is forced by the district heat requirement to have any electricity production to cover

    the requirement, even when the production is economically inefficient, the deficit in DKK must

    be estimated and paid by the district heat company in order to be fair.

    Until the point of deriving the MC, simulation 2 is identical to the overall model explained

    above.

    Figure 9-1: Electricity-price vs. marginal cost at FV07 in 2010

    -400.00

    -200.00

    0.00

    200.00

    400.00

    600.00

    800.00

    1000.00

    1200.00

    [kr/

    MW

    h]

    Electricity-price [kr/MWh] Marginal cost [kr/MWh]

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 27 / 75

    Figure 9-1 is an illustration of why simulation 2 is relevant. The marginal cost is a limitation of

    when production renders any profit. The simulation finds all the production hours where the

    spot price is below the marginal cost. For each of these hours, it determines the difference

    between price and cost and sums it up giving the deficit from producing electricity in the

    periods with unattractive prices. Using the MC-function, production with a negative surplus

    occurs 2,136 hours in 2010. Yet because of the law of heat supply, FV07 is forced to produce

    electricity. This is because the plant has a minimum required production of electricity of 74

    MW for it to keep running and produce district heat. The district heat company is required to

    cover the increased expenses associated with the ineffective production, paying FV the

    calculated extra price/GJ produced district heat in the hours of unattractive electricity prices.

    The optimization loop of simulation 2 ensures that FV07 never produces electricity below the

    minimum electricity production capacity. The model also ensures that FV07 only produces

    power in times, where there is district heat and full condensation-mode production and

    therefore these values of Q and C, are above zero. Given these limitations, the electricity

    productions are calculated, as in simulation 1.

    The point of this simulation is to simulate a non-optimal operation of FV07, where electricity is

    produced even though marginal cost is higher than the price of electricity.

    The efficient electricity production from the mathematical model is now subtracted from the

    maximum electricity production in order to find the inefficient production, which is found as

    production deficit in Table 9-2.

    Hereafter the deficit in DKK is calculated in a loop that ensures that every time the marginal

    cost of production is higher than electricity production, the deficit of that hour is calculated as

    the marginal cost subtracted from the price of electricity. The sum of these deficits is

    multiplied with the production deficit in MWh to yield the total deficit of inefficient production

    in DKK from Table 9-2. The sum is also divided with 3.6 in order to convert the deficit from

    DKK/MWh into DKK/GJ, and hereby estimating the extra cost of producing inefficient power in

    order to fulfil district heating requirements in DKK per produced district heating unit.

    Maximum Electricity Production, simulation 2 2,396,010 MWh

    Efficient Electricity production 1,740,010 MWh

    Production Deficit 655,914 MWh

    Minimum required District Heating 1,913,650 MJh

    Total deficit of inefficient production -22,206,500 DKK

    Suggested compensation 9.40438 DKK/GJ

    Table 9-2: Results from simulation 2

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 28 / 75

    9.2.1 Assessment of simulation 2

    The production deficit and therefore the inefficient electricity production of simulation 2 yields

    655,914 MWh, which is the production forced by district heat, when marginal cost of

    production is higher than the price of electricity. Such a production is inefficient and should be

    avoided if possible. Yet it is unavoidable given the laws concerning a required amount of

    district heat deliverance from FV07.

    The inefficient production will cause a deficit in DKK which should be paid by the district heat

    company, as their demand for district heat causes the inefficient production at FV07. The price

    of district heat varies from technology to technology. A general rule is that it lies between 20

    DKK/GJ and 80 DKK/GJ [19]. An extra payment of the estimated deficit of 9.40 DKK/GJ is rather

    realistic.

    9.3 Simulation 3

    In this simulation the mathematical model is tested by calculating the total profit of FV07,

    assuming that FV07 runs exclusively in condensing mode and therefore only produces

    electricity.

    The potential buyer can simulate the total profit of FV07, when producing electricity only,

    based on any fuel and electricity prices by simply replacing the Coal, which is the price of Coal

    in 2010, ElectricityPrice which are DK1 spot prices in 2010 and Oil_Price_pr_tonne, which is the

    price for a tonne of oil in 2010. Generally all values in simulation 3 are replaceable with own

    expectations of future prices and costs.

    Until the point after calculating the marginal cost of the operation of FV07, simulation 3 is the

    same as simulation 1 and 2, with the only difference being that the fuel-consumption in

    simulation 3 is expressed only in terms of electricity production P. Naturally this affects the

    cost of operation of FV07, as both CO2-emission cost, Fuel-cost (both oil and coal), cost of

    docking and transportation costs are functions of the fuel consumption. Therefore, the MC-

    function in simulation 3 will be different from the other simulations.

    With the marginal cost of FV07, all data needed to simulate an optimal operation are in place.

    The optimisation loop now ensures that FV07 does not produce electricity when the MC is

    higher than the price and that the production of electricity is never lower than the minimum

    capacity of 74 MW in order to ensure that cold and warm start fuel consumption and thereby

    additional fuel cost can be avoided. The optimal electricity production is found and

    consequently the fuel-consumption will change as the model supplied by Vattenfall is a

    function of the electricity production, P. The new, optimal P is substituted into the model,

    which yields lower fuel consumption and hence lowers cost, which gives a higher total profit.

    As seen from Figure 9-2 though, some hours of the year FV07 will have to shut down due to

    MC being higher than the price of electricity, the model has accounted for the fuel

    consumption during these hours.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 29 / 75

    Figure 9-2: Optimal production of FV07 in 2010

    The optimal power production P is now summarised to yield the optimal power production of

    the plant for 2010. On the basis of the hourly production of this optimal production, the total

    sales are calculated by multiplying the optimal production with the hourly price of electricity.

    Total revenue in an optimal operation of FV07 is now calculated by subtracting the total cost

    from the electricity sales.

    Optimal Electricity Production 1,830,130 MWh

    Total revenue of electricity sale 694,729,000 DKK

    Total Cost 576,048,000 DKK

    Total Profit 118,681,000 DKK

    Table 9-3: Simulation 3 results

    9.3.1 Assessment of simulation 3

    As seen from the results listed in table 9-3 the power production in this simulation 3 does not

    come close to the actual measured power production of FV07 in 2010. The main reason for the

    difference would be that the simulation takes its point of departure of estimating the optimal

    power production, only when such a production is economically feasible. Another reason for

    the inaccuracy could be the assumption that FV07 only produces electricity and no district heat

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 30 / 75

    and is therefore not forced to produce inefficient electricity along with the minimum required

    district heat, even though MC is higher than the spot price. In other words, in simulation 3,

    FV07 produces the electricity that yields the largest profit, which is not necessarily the case for

    the actual operation.

    The revenue of 694,729,000 DKK in simulation 3 is made from selling the simulated power

    production for each hour of the year 2010 at the spot price at that given hour. The cost

    fluctuates with the power production, as e.g. fuel cost and CO2-emission cost are functions of

    the power and heat production, due to the fuel-consumption model being a function of these

    productions.

    Reasons for the profit being as high as it is, includes the fuel-consumption and CO2-emission

    cost saved, due to the fact that FV07 only produces electricity in simulation 3 and hence does

    not incorporate additional cost for district heat production. Additional costs and negative

    revenues are avoided further in simulation 3 as power is only produced when the spot price is

    higher than the MC and therefore no non-optimal electricity is produced due to the minimum

    district heat requirements mentioned above, which lowers the cost and therefore maximises

    the total profit.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 31 / 75

    10 Discussion

    There are multiple things that need to be discussed, they can be divided into two categories;

    internal- and external factors.

    First the external factors that influence FV will be discussed. The largest influence on the plant

    comes from the political decisions of the government. Their 2020-plan for throttling back a

    large part of the coal fired power production and replace it with energy from wind turbines will

    harm the revenue for the CHP-plants, especially in the long run, as the Danish goal for 2050 is

    to have a 100 % green energy production [20]. Yet more than half of energy engineers believe

    that it is not achievable [21]. A positive thing is that FV also produces district heat; the risk of

    the investment is therefore spread, as there is no alternative that can cover an equal amount

    of district heat production. In addition, the plant is guaranteed a compensation for the hours

    they produce ineffectively, because of the district heat requirement as shown in simulation 2.

    The reason why coal fired power plants are still needed is that there are simply no alternatives

    when it comes to supplying a steady base load that can be regulated easily depending on the

    fluctuations of the wind production. A possible way to achieve 100% independence from fossil

    fuels is by storing the energy from wind turbines; however, there are no units with a capacity

    large enough to store sufficient amounts of energy.

    Moving away from CHP-plants will jeopardise the security of supply as discussed in section 4.4,

    and therefore the government will have to support them until an alternative can be found. To

    safeguard the plant against the transition to a more green energy system, the production can

    be converted to run on biomass as the primary fuel, as has been partially done with block 8.

    This can be cause for further discussion as even though there is a large portion of biomass in

    the Danish system, further utilisation will take up land that could be used for food production,

    so there is an ethical question here and it will alter the balance between nature and human

    territory. Also, if a large part of the coal production should be substituted with biomass, import

    of said fuel will be necessary [22]. All these are factors that will cause an increase in the price

    per unit compared to coal, which will further decrease a plants competitiveness.

    The internal factors that need to be discussed, regard the model. The first and most striking

    cause of uncertainties is the fact, that the model is based on financial data for FV07 from 1993,

    when the block was commissioned. A lot of the data, such as expenses for staff and waste

    management will most likely have changed more than just the inflation, which is already taken

    into account. This gives a distorted picture on the actual expenses of running the plant and can

    be the cause of a skewed result.

    Another factor that can alter the accuracy of the calculations is the fact that the data given for

    the power production in MW, which is the base of the calculations, is a measured average

    value within the production hour. FV07 has substantial regulatory capacity, meaning that it can

    change its production on very short notice and by a large amount. These fluctuations in

    production are not reflected in the average value and have an influence of the accuracy of the

    model.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 32 / 75

    Since the data that is the base of the model is from 2010, changes have occurred to the

    composition of how the producers share the deliverance to the grid. Especially as Anholt wind

    farm with a capacity of 400 MW was connected to the grid in 2013. Yet this will be reflected in

    the spot price, because a larger production of wind energy with more fluctuation will yield

    lower prices in some periods and higher in others. Therefore, future calculations using the

    model will incorporate this change as production can be set up to only occur when the spot

    price is favourable.

    The relation between cooling water temperature and electricity efficiency of FV07 can be used

    as a point of departure to evaluate whether or not it is feasible to speculate in artificially

    lowering the cooling water temperature as much as possible throughout the year or if using

    the water from Odense New Canal to regulate the efficiency, optimises the performance

    enough. These calculations are not considered in the report. However, comparing the costs of

    the current process and a process, where cooling towers are used to lower the temperature

    instead, might be interesting when optimising the energy output in accordance with a feasible

    economy.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 33 / 75

    11 Conclusion

    The electricity spot price is set as the MC of the last and most expensive unit that delivers

    electricity to the grid. However, it is a lesser part of the price that the consumers pay for

    electricity, due to tariffs and taxes such as Grid-tariff, System-tariff and PSO-tariff, which make

    up the largest fraction of the electricity bill. The PSO tariff subsidises the renewable

    development of the Danish energy sector, and pays e.g. the gap between a guaranteed

    electricity sales price of an offshore wind farm, and the spot price in the electricity market.

    Financial challenges for coal fired power plants such as FV07 include the production cost of

    such plants compared to e.g. production units such as wind turbines, that deliver electricity to

    the grid at a very low MC due to no costs for fuel and CO2 emission quotas. Another financial

    challenge for coal fired power plants is that renewable systems such as wind turbines are

    subsidised heavily by the PSO tariff, despite the fact that e.g. large-scale offshore wind farms

    are not yet financially compatible with e.g. coal fired power plants such as FV07, which creates

    a financial challenge in the future for CHP-plants even though they are more compatible with

    the electricity grid of today.

    The Danish law of electricity supply regulates power plants such as FV, as the unit is above 25

    MW and therefore assigned to fulfil the duties and conditions mentioned in the law. The

    purpose of units above 25 MW being regulated by the law of electricity supply is to secure

    Danish security of supply in the most economical and environmentally friendly way while

    protecting the customer. The responsibility of ensuring Danish security of supply is the TSO of

    Denmark, Energinet.dk, who´s responsibilities are mentioned in §28 in the law of electricity

    supply. Part of the additional price for electricity, which the consumer has to pay, is the system

    tariff paid to Energinet.dk, which is a tariff paid to ensure the security of supply.

    FV is also regulated by the law of heat supply as the FV is a cogeneration plant and is therefore

    obligated to deliver district heat while producing electricity, in accordance with §1, which

    states that cogeneration of district heat and power should be utilized as much as possible.

    The electrical efficiency of FV07 is calculated to be 43.22 % at a cooling water temperature of

    1°C under ideal conditions and the assumption that the generation process at FV07 resembles

    an ideal reheating Rankine cycle and therefore a reversible heat engine. The calculations show

    that the electrical efficiency increases as a result of decreasing cooling water temperatures, as

    the extra heat extracted in the condenser causes the net work output to increase, as the

    cooling water temperature decreases. Even though the increase in efficiency per degree drop

    in cooling water temperature is 0.0625 %

    °𝐶, it should be taken into account when producing,

    because of the difference in water temperature with changing seasons.

    The mathematical model of FV07 simulates an actual operation of electricity and district heat

    production on the basis that production only occurs when the MC is lower than the spot price,

    when the electricity production is above the minimum and when district heat requirements

    are fulfilled. The model also estimates the fuel consumption of FV07 in 2010, as 21,208,700 GJ

    with a percentile difference from the measured fuel consumption of 1.37 %. Also, the

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 34 / 75

    electricity production is estimated as 2,289,050 MWh which yields a percentile difference from

    the measured electricity output of 2.1 %.

    Simulation 1 simulates the operation of FV07 in the year 2010 hour by hour and compares the

    calculated electricity production, with the actual electricity production at FV07. The electricity

    production is estimated to 2,396,010 MWh with a percentile difference of 6.87 % to the actual

    electricity production in 2010.

    Simulation 2 simulates a scenario where FV07 is forced by district heating requirements to

    have some inefficient production, when the marginal cost is higher than the spot price. The

    deficit of the inefficient production is found, and an amount of loss per unit heat produced,

    which should be paid by the district heat company, in order to compensate for financial losses,

    is calculated. The electricity production of 2010, including inefficient production is estimated

    as 2,396,010 MWh compared to an efficient production in 2010 of 1,740,100 MWh. The

    difference is 655,914 MWh. The total deficit of inefficient production in DKK, found as the sum

    of hourly marginal cost – the hourly spot electricity price times the inefficient production, is -

    22,065,000 DKK and the deficit per unit of produced district heating, which should be paid by

    the district heat company, is 9.40 DKK/GJ.

    In simulation 3 the mathematical model is tested by calculating the total profit of FV07,

    assuming that FV07 runs exclusively in condensing mode and therefore only produces

    electricity.

    The optimal electricity production is estimated to be 1,830,130 MWh, the total revenue of

    sales is estimated as 694,729,000 DKK, total costs 576,048,000 DKK and thus a total profit of

    118,681,000 DKK.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 35 / 75

    12 References

    1. Material from ELVA course.

    2. Wikipedia, 09/01/2015. Energinet.dk. [Website] Available from:

    http://da.wikipedia.org/wiki/Energinet.dk [05/14/2015]

    3. Wittrup, S., 11/17/2014. Vattenfall får nej til at skrotte Fynsværket i 2016. [Website

    (Ingeniøren)] Available from: http://ing.dk/artikel/vattenfall-faar-nej-til-skrotte-

    fynsvaerket-i-2016-172352 [05/21/2015]

    4. Vattenfall, 2013. Fynsværket- Grønt regnskab 2013.

    5. The ministry of environment, 02/16/2015. Bekendtgørelse om begrænsning af visse

    luftforurenende emissioner fra store fyringsanlæg. [Website (schulz lovportaler)]

    Available from: http://miljoe-

    offentlig.lovportaler.dk/ShowDoc.aspx?activesolution=http%3a%2f%2fwww.lovportale

    r.dk&q=grænseværdier&t=%2fV1%2fNavigation%2fKoncept+kommune%2fKoncept+Te

    knik%2fLT+Miljoe+offentlig%2fEmneindgang%2fLuft%2f&docId=bek20150162-full

    [05/14/2015]

    6. Ministry of Climate, Energy & Building, 11/29/2012. Lov om CO2 kvoter. [Website]

    Available from: https://www.retsinformation.dk/Forms/R0710.aspx?id=144102

    [05/14/2015]

    7. Ministry of Climate, Energy & Building, 01/01/2013. Lovbekendtgørelse 2013-11-25 nr.

    1329 om elforsyning.

    8. The Energy Agency, 04/01/2015. Bevilling til elproduktion til Fjernvarme Fyn

    Fynsværket A/S. Climate, Energy- and Buildingministry.

    9. The ministry of Climate, Energy and Building, 04/16/2015. Bekendtgørelse af lov om

    fremme af vedvarende energi. [PDF] [05/21/2015]

    10. Ministry of Climate, Energy & Building, 02/02/2015. Bekendtgørelse af lov om

    varmeforsyning.

    11. The Econmic counsel, 02/03/2014. Økonomi og Miljø 2014: Kapitel I -Omkostninger

    ved støtte til vedvarende energi. [PDF] Available from:

    http://www.dors.dk/files/media/rapporter/2014/m14/m14_kapitel_1.pdf

    [05/18/2015]

    12. Çengel, Y. A. & Boles, M. A., 2015. Thermodynamics: an engineering approach. 8th ed.

    in SI units ed. NewYork: McGraw-Hill Education.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 36 / 75

    13. Rankine Cycle. [Website] Available from:

    http://home.iitk.ac.in/~suller/lectures/lec29.htm [05/12/2015]

    14. Data supplied with the task specification.

    15. Electropaedia, 2005. Energy Effiency. [Website] Available from:

    http://www.mpoweruk.com/energy_efficiency.htm [05/20/2015]

    16. Felder, R. M. & Rousseau, R. W., 2005. Elementary Principles Of Chemical Processes.

    3rd ed., 2005 ed. with integrated media and study tools. ed. Hoboken, NJ: Wiley.

    17. Griffiths, D. F., October 2012. An Introduction to Matlab. [PDF] 3rd edition ed.

    Scotland, UK: University of dundee.

    18. Kreyszig, E., 2006. Advanced Engineering Mathematics. 9th ed. ed. Hoboken, NJ: John

    Wiley.

    19. Ea Energianalyse, 04/08/2014. Elproduktionsomkostninger -Samfundsøkonomiske

    langsigtede marginalomkostninger for udvalgte teknologier. [PDF] Available From:

    http://www.ea-energianalyse.dk/reports/1410_elproduktionsomkostninger.pdf

    [05/21/2015]

    20. The energy agency, Dansk klima- og energipolitik. [Website] Available from:

    http://www.ens.dk/politik/dansk-klima-energipolitik [05/21/2015]

    21. Wessel, L., Ingeniøren, 03/28/2012. Ingeniører tvivler på fossilfrit Danmark i 2050.

    [Website] Available from: http://ing.dk/artikel/ingeniorer-tvivler-pa-fossilfrit-danmark-

    i-2050-128001 [05/21/2015]

    22. The energy agency, Biomasseressourcer. [Website] Available from:

    http://www.ens.dk/undergrund-forsyning/vedvarende-

    energi/bioenergi/biomasseressourcer [05/21/2015]

    23. Christensen, N. B. & Poulsen, A., 2005. Mikroøkonomi. [PDF] bookboon.com. Available

    From: bookboon.com

    24. The Energy Agency, Varme forsyning. [Website] Available from:

    http://www.ens.dk/info/lovstof/gaeldende-love/varmeforsyning [05/14/2015]

    25. Vanek, F. M., Albright, L. D. & Angenent, L. T., 2012. Energy Systems Engineering:

    evaluation and implementation /. 2nd ed. ed. New York: McGraw-Hill.

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 37 / 75

    13 Appendix list

    Appendix 1 - The group process .................................................................................................. 38

    Appendix 2 - Methods ................................................................................................................. 39

    Appendix 3 - Time schedule ........................................................................................................ 40

    Appendix 4 - Brainstorms ............................................................................................................ 41

    Appendix 5 - Supervisor contract ................................................................................................ 42

    Appendix 6 - Group contract ....................................................................................................... 43

    Appendix 7 - Belbin profiles ........................................................................................................ 44

    Appendix 8 - Fynsværket illustration .......................................................................................... 46

    Appendix 9 - Composition of electricity prices ........................................................................... 47

    Appendix 10 - Energy and climate goals ..................................................................................... 48

    Appendix 11 - EES model and results .......................................................................................... 49

    Appendix 12 - Fuel consumption calculations ............................................................................ 53

    Appendix 13 - The overall model ................................................................................................ 55

    Appendix 14 - Simulation 1 ......................................................................................................... 60

    Appendix 15 - Simulation 2 ......................................................................................................... 65

    Appendix 16 - Simulation 3 ......................................................................................................... 70

    Appendix 17 - Symbol list ............................................................................................................ 75

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 38 / 75

    Appendix 1 - The group process

    The 6-phase model is composed of six isolated stages. The model is a work model that attempts

    to ensure, that a subject is thoroughly examined and that the problems are solved optimally.

    Problem analysis During the first phase, the Problem Analysis, the overall project outline and its demands were

    analysed piece by piece with the purpose of establishing various sub tasks and an time schedule

    as shown in Appendix 3 In this first phase, we also analysed these different sub tasks individually

    by brainstorming which topics we should consider in detail.

    Idea phase After considering all sub tasks, we could move on to the next phase, the Idea Phase. We took

    notes of every part of the assignment and discussed how to solve them. We brainstormed the

    various outlines and noted our ideas on how to solve them. Regarding our model we went

    through the project outline and noted our ideas on how to solve them in the best way,

    concerning both structure and complexity.

    Planning phase In the next phase, the Planning Phase, we formed a detailed time schedule based on the general

    time schedule and the specified sub tasks. This detailed time schedule is attached as Appendix

    3. We discussed how we wanted to work with the individual tasks and concluded that we were

    to choose between two options. The first option was to split the tasks up between us so that

    each group member singlehandedly had responsibility of their respective tasks. By doing so, the

    other group member’s understanding of a certain topic would depend completely on that one

    person’s written product, which might lead to misinterpretations and misunderstandings within

    the report. This could be avoided if the group worked on the topics in plenum. We chose a

    middle way between the two options, which was that groups of 2 and three group members

    worked on individual subtask in order to supplement each others knowledge, while at the same

    time keeping every group member busy, and therefore getting sufficient amounts of work done,

    in less time than working everything through in plenum. We choose to begin every topic by

    harmonizing our understandings and expectations in plenum, where after we divided the tasks

    between us regarding research for data, theory discussion and so on. This middle way of

    working in plenum, and working individually ensured both a large amount of work being done in

    little time, while ensuring an organized product in terms of every member having an idea, of

    what the other members where doing, at all times.

    Problem-solving phase The fourth phase, the Problem-solving phase, was the most time consuming phase since it was

    here the report itself had to be worked out. The sub tasks were treated as described above and

    in accordance with the detailed time schedule. Due to our well-organized work schedule, this

    phase was carried out without complications, mainly because we at all times had an idea of how

    far in the process we were and where we were headed in terms of how we wanted the product

    to shape up. As mentioned in our Group contract, we agreed to meet at least one day a week to

    focus on the project and to assure that we kept up with our time schedule. During the rest of

    the week, we worked on our respective assignments and made sure to keep in touch with the

    rest of the group. To do this we established an online Dropbox folder, in which we had a system

  • Fynsværket, FV07 Semester project, Energy Technology May 29th 2015 Southern University of Denmark

    Page 39 / 75

    to store every single part of written material. This was done both to ensure a back-up of our

    work but also so that every group member at all times was kept up to date with what was going

    on during the entire process.

    Conclusion phase In this phase we summed up our results and discussed how we could have done things

    differently and what results we might have come up with then. We defined the most important

    results with regards to the model and the simulations and tried to validate them as much as

    possible.

    Product phase In this last phase we produced most of the written material and formulated all the sections

    required by the project outline and guidelines. We made sure everything was written to address

    the target group outlined in the project outline and formulated in a proper manner. The end of

    the product phase was marked by a period of proofreading all the written material and making

    sure the layout was set-up according to the guidelines as well as making sure all the references

    were correct.

    Appendix 2 - Methods The data has been analysed with a mixture of qualitative and quantitative methods. The

    quality of the gi