fy11 teaching station refresh plan
DESCRIPTION
This presentation provide two approaches to addressing the lifecycle refresh requirements for a colleges multi-mediated teaching stations. The approach demonstrate show to solve the issues when it is budgetary and there is a need for consistency in the technology.TRANSCRIPT
FY11 Teaching Station Refresh Plan
President’s CabinetDecember 9, 2009
Teaching Station
• Current Issues– Refresh Plan that is unsustainable– VHS technology– Document Camera use– Standard configuration
Cost of Standard SetupComponent Cost
Lectern $1,500Chair $ 500Projector $ 800Pole-Vault (Black Box) $ 3,100Standard PC and monitor $1,000DVD/VCR combo $ 200Document Camera (ELMO) $1,600Projection Screen (70” diag) $ 300Alarm $ 80TOTAL $9,100
InventoryLocation Classrooms and
Conference RoomsCosts
$9100/stationBEC 68 $ 618,800
EA 8 $ 72,800
WA 1 $ 9,100
HEC 21 $ 191,100
ESEC 10 $ 91,000
ECT 5 $ 45,500
MEC 17 $ 154,700
CF 12 $ 109,200
MEN 10 $ 91,000
RF 12 $ 109,200
NE 2 $ 18,200
TOTAL 166 $1,510,600
Refresh Options
• Technology Based – Refresh projectors every 4 years, show breakdown – Different Doc Camera (Wolfvision)– Doc Camera/Visual Presenter in designated rooms– Eliminate VHS/DVD devices
• Location Based• PC refresh every 4 years within normal PC
Lifecycle management plan
FIVE-YEAR CAPITAL BUDGET PLAN
Category Line Item 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014
I. Computer/ PC Refresh (4 year refresh cycle) $287,000 $287,000 $287,000 $287,000 $400,000
Instruct'l Technology PC Expansion $0 $0 $0 $0 $0
Server Refresh $0 $30,000 $210,000 $400,000 $200,000 File Server Expansion $0 $90,000 $0 $0 $100,000 Data Projectors (Multi-media Refresh) $372,500 $106,500 $106,500 $206,500 $200,000 Multi-Media Expansion $50,000 $150,000 $150,000 $0 $0 Network Refresh $267,500 $310,000 $390,000 $100,000 $173,000 Network Expansion $102,500 $94,000 $94,000 $94,000 $94,000 Software Refresh $395,000 $330,500 $330,500 $330,500 $330,500 Software Expansion $100,000 $40,000 $0 $0 $100,000 Printer Refresh $0 $0 $0 $0 $0 Equipment $82,500 $62,500 $62,500 $82,500 $62,500
Subtotal - Computer/Instructional Technology $1,657,000 $1,500,500 $1,630,500 $1,500,500 $1,660,000Subtotal - Capital Equipment $1,343,000 $1,499,500 $1,369,500 $1,499,500 $1,550,000Subtotal - Facilities Improvements $2,000,000 $2,000,000 $2,000,000 $2,000,000 $1,000,000Subtotal - Non-Facilities Improvements $275,000 $65,000 $0 $0 $0Subtotal - Property Acquisitions $0 $0 $0 $0 $0Subtotal - New Facilities $1,500,000 $0 $1,500,000 $0 $1,500,000TOTAL COSTS PER YEAR $6,775,000 $5,065,000 $6,500,000 $5,000,000 $5,710,000
Refresh by Technology4-Year Refresh ($377K/yr)
Component Cost Qty Extended Year 1 Year 2 Year 3 Year 4Lectern $ 1,500 166 $249,000
$249,000 Chair $ 500 166 $83,000
$ 83,000 Projector $ 800 166 $132,800
$132,800 Pole-Vault $ 3,100 166 $514,600
$514,600 PC and monitor $ 1,000 166 $166,000
$166,000 DVD/VCR combo $ 200 166 $33,200
$ - Document Camera $ 1,600 166 $265,600
$265,600 Projection Screen $ 300 166 $49,800
$ 49,800 Alarm $ 80 166 $13,280
$ 13,280 TOTAL $ 9,080 $1,507,280 $332,000 $361,880 $265,600 $514,600
Net (Carryover) $ 44,820 $ 59,760 $170,980 $ 33,200
Refresh by Location4-Year Refresh ($377K/yr)
Location UnitsUnit Cost (incl VCR) Extended Year 1 Year 2 Year 3 Year 4
BEC 68 $ 9,100 $ 618,800 $618,800 EA 8 $ 9,100 $ 72,800 $ 72,800 WA 1 $ 9,100 $ 9,100 $ 9,100 HEC 21 $ 9,100 $ 191,100 $191,100 ESEC 10 $ 9,100 $ 91,000 $ 91,000 ECT 5 $ 9,100 $ 45,500 $ 45,500 MEC 17 $ 9,100 $ 154,700 $154,700 CF 12 $ 9,100 $ 109,200 $109,200
MEN 10 $ 9,100 $ 91,000 $ 91,000 RF 12 $ 9,100 $ 109,200 $109,200 NE 2 $ 9,100 $ 18,200 $ 18,200
TOTAL 166 $ 1,510,600 $109,200 $637,000 $364,000 $400,400
Net (Carryover) $268,450 $ 9,100 $ 22,750 $ -
VHS
• VHS players are no longer manufactured as of December 31, 2008
• Unable to buy new combos units as of February 2009• Purchased a batch of 40 in May 2009 but had to switch
vendors as JVC was the last vendor to manufacturer them.• Current units should last until end of FY 2012• May be able to get used refurbished/off brand, but
unreliable • Curriculum and budget impact to discontinue or convert
to DVD format or online
VHS Usage
Jul 06 to Dec 06
Jan 07 to Jun 07
Jul 07 to Dec 07
Jan 08 to Jun 08
Jul 08 to Dec 08
Jan 09 to Jun 09
Community 0 0 1 1 2 0
Loan 39 31 5 24 10 3
Staff 596 933 328 798 290 606
Students 31 21 57 51 36 8
Total 666 985 391 874 338 617
NOTE 1: The total VHS check out does not distinguish for unique titlesNOTE 2: Total video assets 4,973 are cataloged in the Library system todayNOTE 3: The library has indicated they have not cataloged all videos that are used today by different departments.
Plan to decommission use of VHS
• Purchase additional 20 VCR/DVD combo units in Fiscal
Document Cameras
• Starting 2007, switched from Wolfvision to Elmo– Less expensive unit ($1600 vs. $2200)– Most commonly used brand in Education Industry– Requires more user intervention to adjust display
• Currently the Elmo is not meeting the needs of faculty that want to show 3D objects
Specialized Areas
• High end applications, AutoCAD• Larger/deeper classrooms• Mobile lab presentations• Microscopes• X-rays• Classroom parts - Automotive, Diesel, etc.