![Page 1: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/1.jpg)
Future Improvements of
Bayview Street Bridge and US 1
Bridge over I-295
Preliminary Public Meeting
Yarmouth Town Office
February 5, 2018
![Page 2: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/2.jpg)
2
Presentation Outline
• Introduction and Meeting Goals
• US Route 1 Bridge followed by Bayview Street
Bridge
o About the bridges (age, condition, widths)
o Programmed scope of work at each bridge
o Concepts for maintaining traffic during construction
• Schedule for Bridge Projects
• Public Input, Questions, Answers
![Page 3: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/3.jpg)
3
Introduction and Goals
Joel Kittredge – MaineDOT Project Manager
Steve Hodgdon – Hoyle, Tanner Project Manager
o Make Public Aware of the Project Early in Design
o Share Project Information, Development Process and
Preliminary Schedule
o Listen to Concerns and Gather Public Input Prior to
Design
o Answer Questions
![Page 4: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/4.jpg)
4
Presented to:
Presented by:
US Route 1 Bridge over I-295
CUMBERLAND
YARMOUTH
Graphic Source:
Bing Maps
![Page 5: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/5.jpg)
5
About the US 1 Bridge over I-295
• Constructed 1958 (age 60 years). 242’ long.
• Past Rehabilitation Work includes:
o 1991 – new bridge railing, new pavement, deck joints,
steel painting, concrete repairs. Roadway width
increased 16” (to 41.3’).
o 2013 – exit 15 NB off-ramp relocated under southern
span. Top layer of bridge pavement replaced for new
pavement markings.
• Deck, abutments, and piers are in “fair” condition.
The steel beams are in “satisfactory” condition.
![Page 6: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/6.jpg)
6
DECK
PIER
COLUM
DECK
JOINT
![Page 7: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/7.jpg)
7
Looking northerly along US 1 bridge
![Page 8: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/8.jpg)
8
Deck Replacement
Increase roadway 2’ ± for wider shoulders
43’ ± curb-to-curb
New, wider deck
New bridge railing not shown
![Page 9: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/9.jpg)
9
Maintain 2 lanes of two-way traffic
New bridge railing not shown
Work Area
Work Area
Work Area
Stage 1
Stage 2
Stage 3
![Page 10: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/10.jpg)
10
Presented to:
Presented by:
Bayview Street Bridge over I-295
Exit 17
Graphic Source:
Bing Maps
![Page 11: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/11.jpg)
11
About Bayview Street Bridge over I-295
• Constructed 1962 (age 56 years). 227’ long.
• Past Rehabilitation Work includes:
o Routine preservation and maintenance activities
o No substantial rehabilitation work
• Deck is in “fair” condition, steel beams are in “good”
condition, and abutments and piers are in
“satisfactory” condition.
![Page 12: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/12.jpg)
12
DECK
PIER
COLUM
DECK
JOINT
![Page 13: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/13.jpg)
13
Looking westerly along Bayview Street
![Page 14: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/14.jpg)
14
Deck Replacement with new Sidewalk
New bridge railing not shown
24’5’
sidewalk curb-to-curb
Looking westerly
New, wider deck
![Page 15: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/15.jpg)
15
Maintain 1 lane of reversible two-way traffic
New bridge railing not shown
Work Area
Work Area
Work Area
Work Area – Stage 4
Sidewalk construction
trafficpedestrians
Stage 1
Stage 2
Stage 3
![Page 16: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/16.jpg)
16
Est. Project Schedule (Both Bridges)
• Preliminary Design – now to September 2018
• Informational Meeting – late Spring 2018
• Formal Public Meeting – July/August 2018
• Final Design and Permitting – 2019
• Construction – 2020/2021 (may change depending on
conflicts with other capital, maintenance, and
preservation projects scheduled in the next 3 years)
![Page 17: Future Improvements of Bayview Street Bridge and US 1 ...27541806... · 5 About the US 1 Bridge over I-295 • Constructed 1958 (age 60 years). 242’ long. • Past Rehabilitation](https://reader036.vdocuments.us/reader036/viewer/2022071004/5fc1056c02df703e622b5d9d/html5/thumbnails/17.jpg)
17
Public Input & Questions
• Ground Rules:
o Use the Microphone if available
o Introduce Yourself for the
Public Record
Joel Kittredge,
MaineDOT Project Manger
Phone: (207) 624-3550