ADVANCE POLYELECTRIC SYSTEMS, INC.25-B Bayani St., Brgy. San Isidro, Galas, Quezon City
Tel. No. 413-3806 / Telefax No. 731-5238______________________________________________________________________
REF: QPE10-124
September 18, 2010
FRONTIER POWER TECHNOLOGIESAguilar Compound, 683 Magsaysay Road,Bgy. San Antonio,San Pedro, Laguna
Attention : MIKE KAQUILALASubject : INSTALLATION OF 1500KW PRIME GENSET AND
CONSTRUCTION OF GENSET HOUSEProject : FORT BONI
Dear Sir:
We are pleased to submit our quote for the above stated subject as follows:Supply of labor and materials with technical supervision and use of tools for the following scope of works:
Fort Boni PS New 1500KW GENSET Schedule of Quantities
ITEM
NO. DESCRIPTION UNIT QTY UNIT PRICE TOTAL
A GENERAL ITEMS
1. Mobilization/Demobilization Lot 1 50,000.00 50,000.00
2 Implementation of construction Health and SafetyProgram
Lot 1 30,000.00 30,000.00
3 Permits Lot 1 100,000.00 100,000.00
Sub-total 180,000.00
B ELECTRO-MEECHANICAL-CIVIL WORKS (Design,Supply, Construction and Installation)
1 Design, supply and construction of genset houserated for 1500 KW
Lot 1 1,260,000.00 1,260,000.00
2 Genset house soundproofing ( 50mm thk Rockwool
type, 2-hours fire rated)
Lot 1 700,000.00 700,000.00
3 Supply and installation of main feeder breaker(3200At) rated for genset to be located at existingMCC (GCB)
Lot 1 375,000.00 375,000.00
4 Re-routing / tapping of existing tapping point of1135KW genset (existing) to other side of MCCbusbar
Lot 1 150,000.00 150,000.00
5 Supply and installation of mechanical and electricalinterlocking device system for Meralco and gensetpower switching
Lot 1 250,000.00 250,000.00
6 Fuel Tank, Transfer pump and Fuel piping Lot 1 400,000.00 400,000.00
-
8/8/2019 Frontier Fort Bonil 124[1]
2/2
7 Exhaust muffler Lot 1 300,000.00 300,000.00
8 Radiator duct Lot 1 80,000.00 80,000.00
9 3,200AT, ACB, ATS Lot 1 950,000.00 950,000.00
10 Supply and installation of 8 sets:3x250mm THHNfrom genset to GCB
Lot 1 795,000.00 795,000.00
11 Supply and installation of 8 sets:3x250mm THHNfrom GCB to MTS
Lot 1 4,257,000.00 4,257,000.00
12 Supply and installation of 8 sets:3x250mm THHNfrom MTS to existing MDP
Lot 1 1,175,000.00 1,175,000.00
13 Testing and commissioning (ASSIST) Lot 1 50,000.00 50,000.00
Sub-total 10,742,000.00
Grand-total 10,922,000.00
TERMS AND CONDITIONS:
A. Payment : 30% Downpayment balance thru progress billingB. Completion : Within 90 days from receipt of PO, downpayment
and approval of shopdrawings whichever comes latest.
C. Warranty : One (1) year on materials against force majeure
D. Validity : One (1) month from receipt of this quote.
Thank you very much for giving us the opportunity to quote. We look forward to have a good workingrelationship with you.
Truly yours,
MANOLITO M. GAMBOAGeneral Manager