RMOTC Location
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C.
3
Geothermal Potential
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C.
17-WX-21Madison and Tensleep
Possibly 35 MBWPD flowing
57-WX-3Madison and Tensleep
Possibly 10 MBWPD flowing
TENSLEEP PRODUCING AREA
OTHER POSSIBLE TENSLEEP SOURCE WELLS AND DEEPENING
CANDIDATES
Precambrian granitic
basement structure
4
Water Treatment Pond
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
5
Water Treatment Ponds
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
6
Project Goals
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
The project is to validate the use of a binary geothermal power generation system that uses hot produced oilfield water to produce electricity.
Test the system for a minimum of 1 year
Provide a technical and economic analysis of the process
Testing partner: ORMAT Nevada, Inc.
7
Projected Generator Performance
Flow Rate: 40,000 bpd (6,358 m3/d)
Inlet Temperature: 170°F (77°C)
Outlet Temperature: 152°F (67°C)
Ambient Temperature: 50°F (10°C)
Generator Gross Power: 180 kW
Net Power Output: 132 kW
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
Unit designed and built by Ormat Systems Ltd, Yavne, Israel.
8
5000 Barrel Tank Moving
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
9
5000 Barrel Tank Moving
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
10
Setting of Vaporizer
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
11
Setting of 2nd Condenser
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
12
Cooling Fan Motor
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
13
Cooling Fans
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
14
Working Fluid Piping
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
15
Return Vapor Piping
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
16
Completed Unit
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
17
Operational Trends
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
18
Daily Power Fluctuation
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
19
Daily Ambient Temperature
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
20
Operational Summary
On Line Total, Total (Actual) days 161 (151)Inlet Brine Temperature °F 195-198
°C 90-92Inlet Brine Volume Barrels 3,047,370
m3 484,493
Net Power Produced kilowatt hour 586,574Overall
On line percentage % 91Average net power kilowatt 159
Overall w/o Field DowntimeOn line percentage % 97Average net power kilowatt 171
Avg. Net Power Jan-Feb 2009kilowatt 200
3rd B.C. Unconventional Gas Technical Forum, Victoria, B.C
21
Future Plans
Perform equipment checkout, maintenance and repair, to include:
• Change system control to a source control loop with an additional control valve, and
• Install vapor bypass line around turbine to ease unit starting, and
• Install a vibration monitoring system, and• Heat trace all oil lines to prevent oil thickening.
Continue testing of the unit until at lease September 2009