frffz li't~r~£$!1llh'}~q '~z.tmitlr.~j...

336
A SURVEY OF LOCALIZED CRACKING IN STEEL BRIDGES by John W. Fisher Umur Yuceoglu fRffZ This document is disseminated under the sponsorship of the Department of Transportation in the interest of information exchange. The United States Government assumes no liability for the contents or use thereof. Fritz Engineering Laboratory Lehigh University Bethlehem, Pa. 18015 Fritz Engineering Laboratory Report 448-2(81)

Upload: dangkiet

Post on 19-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

A SURVEY OF LOCALIZED

CRACKING IN STEEL BRIDGES

by

John W. Fisher

Umur Yuceoglu

fRffZ li't~R~£$!1llh'}~Q

'~Z.tmitlr.~J ~'il!

This document is disseminated under the sponsorship of the Department of Transportation in the interest of information exchange. The United States Government assumes no liability for the contents or use thereof.

Fritz Engineering Laboratory

Lehigh University

Bethlehem, Pa. 18015

Fritz Engineering Laboratory Report 448-2(81)

Page 2: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

1. R .. porr No. 2. Governme-nr Accession No.

4. Tit!., end Subtitle·

A SURVEY OF LOCALIZED

CRACKING IN STEEL BRIDGES

9. Performing Orgoni:otion Nome and Address

Fritz Engineering Laboratory, #13 Lehigh University Bethlehem, Pennsylvania 18015

~------------------------------~--------------------------~ 12. Sponsoring Agency Nome end Address

Office of Research U. S. Department of Transportation Federal Highway Administration Washin~ton D.C. 20590

15. Supplementary Notes

16. Ab.stroct

Technical Report Documentation Pcge

3. R.,cipient" • Cot clog No.

5. Report Dcr.,

6. Performing Orgcni xcticn Code

Fritz Lab. No. 448-2(81)

10. Work Unit No. (TRAIS)

35F2-132 II. Contract or Grant No.

DOT-FH-11-9506 13. Type of Report ond Period Covered

Interim Report September 1978- June 1981

14. Sponsoring Agency Code

This report summarizes the tc fatigue and/or fracture 142 bridges was obtained. types of details.

results of a survey of localized failures due in bridge members. Altogether, information on The cracking observed was classified into 28

A representative sample of fifteen of the bridges was selected for a detailed review, and a summary was prepared describing.the bridge structure, the cracking, its cause, and the repair, retorfit, and cost. These case studies are a part of this report.

17. KeyWords

Bridges, Fatigue, Fracture, Life expectancy, Fatigue Damage, Truck weight, Welded details

18. Di stribvtion Statement

19. s~curity Clossil. {0 1 rhio report) 20. Security Clossil. (ol thi• pcs•l

Unclassified Unclass.ified

Fc:.rr.1 DOT F 1700.7 CS-721 Reproduction of co,.,plcte::! poge Ol.'t!,oriz.ed

21. He. ol Pages

334

22. Price

Page 3: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

1. Introduction

1.1 Summary Tables

1.2 Selected References

2. Eyebars and Pin Plates

2.1 Silver Bridge (I.D. 2)

2.2 Illinois 157 over St. Clair Avenue (I.D. 36)

3. Coverplated Beams and Flange Gussets

3.1 Yellow Mill Pond (I.D. 3)

4. Web Lateral Connection Plates

4.1 Lafayette Street Bridge (I. D.

5. Transverse Groove Welds

5.1 Aquas a bon River Bridge (I. D.

5.2 Qumnipiac River Bridge (I. D.

5.3 Illinois 51 at Peru (I. D. 70)

6. Web Penetrations

6.1 Dan Ryan Elevated (I.D. 7)

7. Welded Holes

6)

5)

4)

7.1 Illinois 57 at Farina (I.D. 54)

8. Cantilever Floorbeam Brackets

9.

10.

8.1 Lehigh Canal Bridge (I.D. 14)

8.2 Allegheny River Bridge (I.D. 16)

Transverse Stiffener Web Gaps

9.1 I90 over Conrail Tracks (I. D. 41)

9.2 I90 over Cuyahoga River Valley (I. D.

Floorbeam Connection Plates

10.1 Poplar Street Bridge (I. D. 13)

10.2 Des Moines Polk County Bridge (I. D.

..,_i-

42)

58)

Page 4: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

1. INTRODUCTION

As part of this study, a survey of localized failures due to fatigue

and brittle fracture of domestic and foreign bridge structures was carried

out. Detailed information was not readily available from most foreign

sources. Some information was made available but for the most part the in­

formation was not extensive.

A mail solicitation was made of several states in order to obtain

supplemental information on cases of cracking that were known to exist and

where further i~formation was needed in order to summarize the cracking.

In addition, visits were made to several states in order to obtain

additional information on known cases of cracking and to acquire new infor­

mation. The states visited included: California, Illinois, Iowa,

Louisiana, Minnesota, Oregon, Texas, Washington and Wisconsin.

Altogether information was a~quired on 142 bridge sites. An effort

to group cracking problems into categories required use of more than 30

terms to represent the various types of cracking problems. Often a bridge

site contained more than one kind of bridge structure and several types of

cracking problems were observed. Table 1 summarizes the design details

where cracks developed and for which information was acquired. It also

shows the number of bridge sites where the various kinds of cracks were de­

tected.

A representative sample of these bridges was selected for a detailed

review and summaries were prepared which describe the bridge structure, the

cracking and its causes, the repair or retrofit and the cost. These

-1-

Page 5: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

summaries form the basis for this report.

Table 2 provides a list of most bridge sites, the state they are

located in, and a brief description of the detail or condition that led

to cracking.

Each summary has its own reference list and sequence of figures.

References cited in the individual introductory sections are listed at

the end of report.

-2-

Page 6: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

TABLE 1: SUMMARY OF TYPES OF DETAILS EXPERIENCING CRACKING

Detail.

1. Eyebars

2. Pin Plates

3. Coverplated -Beams

4. Flange Gussets

5. Flange or Web Groove

6. Coverplate Groove

7. Electroslag Welds

8. Longitudinal Stiff­eners

9. Web Gusset

10. Flanges & Brackets through Web

11. Welded Holes

12. Cantilever Brackets

13. Lamellar Tearing

14. Transverse Stiffeners

15. Floorbeam Connection Plates

16. Diaphragm Connection Plates

17. Diaphragm & Floorbeam Connection Plates at Piers

18. Tied Arch Floor Beams

19. Tied Arch Floor Beam Connections

20. Coped Members

21. Welded Web Inserts

22. Plug Welds

Initial Defect Number

of or Condition Bridges

Stress corrosion 1 Forge laps, un-

known defects 12

Frozen pins 1 Other 1

Normal weld toe 3 Fabrication cracks 1

Weld toe 5

Lack of fusion 6

Lack of fusion 4

Various flaws 6

Lack of fusion, poor weld 4

Intersecting welds 5 Gap between stiff-

ener & gusset 2

Flange tip crack 3

Lack of fusion 3

Tack welds 1 Riveted Connection 2

Restraint 1

Shipping & handling 4

Web gaps 26

Web gaps 9

Web gaps

Web gaps

Weld root

Notch

Lack of fusion

Crack

-3-

4

8

2

13

1

1

Fatigue Catagory

Initial crack

Out-of-plane D

E' <E'

E or E'

Large initial crack

Large initial crack

Large initial crack

<E'

Out-of-plane

<E'

Large initial cracks

Out-of-plane Out-of-plane

Out-of-plane

Out-of-plane

Out-of-plane

Restraint

Out-of-plane

Restraint

Restraint

Large initial crack

Page 7: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

TABLE 1: ·SUMMARY OF TYPES OF DETAILS EXPERIENCING CRACKING (CONT'D)

Detail

23. Gusset Plates

24. Box Girder Corner Welds

25. Stringer-Floorbeam Brackets

26. Stringer End Con­nections

27. Hangers (Truss & Arches)

28. Welded Repair

Initial Defect Number

of or Condition Bridges

Lateral bracing vi-bration 3

Transverse weld cold cracks 3

Web gap 4

Restraint 3

Vibration-Wind 4

Lack of fusion, 2 weld termination

-4-

Fatigue Catagory

Out-of-Plane

Large initial crack

Out-of-plane

Weld termination

Aeroelastic Instability

<E

Page 8: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

TABLE 2: SUMMARY OF BRIDGES

Bridge I.D. No.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

Name

Kings Bridge

Silver Bridge

Yellow Mill Pond

Quinnipiac River

Aquasabon River

Lafayette Street

Dan Ryan Elevated

I79 Back Channel

I79 Tied Arch

Brady Street

Meadville

I78

Poplar Street

Lehigh Canal

Chester-Bridgeport

Allegheny River

South Bridge

Ohiopyle Truss

Point Marion

Country Club

Ft. Duquesne Bent

St. Anne, Ottawa River

I24 Bridge at Paducah

Des Plaines River

13.9 Mile Grimsby

5.09 Mile Edmonton

Walt Whitman

Mackinac

Milford-Montague

C.P.R. Subway

Founders Bridge

Location

Melbourne

West Va.

Conn.

Conn.

Ontario

Minn.

Illinois

Pa.

Pa.

Pa.

Pa.

N.J.

Illinois

Pa.

Pa.

Pa.

Pa.

Pa.

Pa.

Pa.

Pa.

Ontario

Ill. - Ky.

Ill.

Alberta

Alberta

Pa.

Mich.

Pa.

Ontario

Conn.

-5-

'rype Cracking

End coverplates

Eyebar head

End coverplates

Longit. stiffener groove weld

Web insert groove weld

Lateral gusset-web

Flange piercing web

Electroslag welds

Electroslag welds

Electroslag welds

Electroslag welds

Longit. stiffener groove welds

Floorbeam web gaps

Cantilever bracket plates

Verticals-wind vibration

Cantilever bracket plates

Cantilever bracket plates & rivets

Corrosion

Impact damaged .hanger

Corrosion & fatigue

Lamellar tearing

Welded patch plates

Thrust brackets, groove welds and box corner welds

Web gaps

Diaphragm web gaps

Diaphragm web gaps

Floorbeam truss-stringer brackets

Floorbeam truss-stringer brackets

Welded gusset

Longit. stiffener groove

Lateral connection plates

Page 9: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

TABLE 2: SUMMARY OF BRIDGES (CONT'D)

Bridge I.D. No.

32

33

34

35

36

3Z

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57

58

59

Name

Se)~our at Mill Pond

Cromwell

Wainwright

Location

Conn.

Conn.

Virginia

Alberta

Ill. 157- St. Clair Ave. Illinois

C. P. Bridge, Dutch Creek Canada

Belle Vernon Pa.

Dekorra Bridge Wise.

Girard P-oint Pier Caps Pa.

I90 over Conrail Tracks Ohio

I90 over Cuyahoga River Valley Ohio

Bartow County (L&N) Ga.

Route 21 Ramp N.J.

Chamberlain South Dakota

Belle Fourche South Dakota

Tilford

L&N Bridgeport

Silver Memorial

Southwest Miramichi

35.2 Dublin Santa Fe

412.1 Santa Fe

Route 17

I57 Farina Overpass

Burned River Bridge

Praire du Chien

Lehigh-Webster County

Des Moines (1061 )

Iowa City (7659)

South Dakota

Alabama

West Va.

Canada

Texas

Oklahoma

Va.

Ill.

Ontario

Wise.

Iowa

Iowa

Iowa

-6-

Type Cracking

Welded stringer connections

Lateral connection plate web gaps

Pin plates

Cross frame connections

Cracked hangers

Stringer copes

Stringer angle connection rivets

Web crack; gusset cracks; flange crack

Flange penetrations

Transverse stiffener web gaps

Transverse stiffener web gaps

Electroslag welds

Coverplate end

Cross-frame diaphragm web gaps

Cross-frame diaphragm web gaps

Coverplate groove weld splice

Eye bar

Groove welds

Diaphragm web gap

Eyebar head

Web gaps

Welded bolt holes

Plug welds

Web gaps, restraint, corner weld

Welded pelt holes

Floorbeam-girder web gap

Floorbeam-girdet web gap

Page 10: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj, 448-2

TABLE 2: SUM}~Y OF BRIDGES (CONT'D)

Bridge I.D. No,

60

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

79

80

81

82

83

84

85

86

87

88

89

Name Location

B37-30, Big Eau Pleine Hisconsin

Dresbach Wisconsin

I229 Big Sioux River South Dakota

Napier Ave. - St. Joseph Michigan River

Lenhardtsville I78 Pa.

Fremont Oregon

Vermilion River Ill.

Gulf Outlet La,

Eel River Calif,

Mascoutah Ill.

US 51 @ Peru Ill.

Old Cairo Ill,

Meredosia Ill.

I70 Fayette County Ill.

Little Vermilion River Ill.

Crooked River Canyon Oregon

Milwaukee Harbor Wise.

Cornell B-9-87 Wise.

Toutle River Wash.

Satsop River Wash.

Stillaquamish River Wash.

Hwy 27 over !94 Minn.

Quinebaug Conn.

New England Mills Calif.

Merced River Calif.

Bryte Bend Calif.

US 61 (657) Iowa

Decatur (3567) Iowa

Bear Creek (3958) Iowa

I80 (3758) Iowa

-7-

Type Cracking

Lateral connection plate

Floorbeam-girder web gap

Lateral_ connection web gap

Riveted diaphragms

Welded insert;

Gusset welded to flange angle

Box corner welds

Crack at cope

Coverplate groove welds

Coverplate groove welds

Corrosion; fatigue @ stringer supports

Corrosion and copes

Diaphragm web gaps

Gusset plate cracks

Stringer end conn. & floor-beam bracket

Electroslag welds

Tied arch floorbeam conn.

Tied arch floorbeam conn,

Tied arch floorbeam conn.

Tied arch floorbeam conn.

Weld repair of web

Groove weld

Coped girder web

Stringer brackets-web

Flange gussets

Diaphragm web gap

Lateral (gusset) connection plate-web

Diaphragm web gap

Helded bolt holes

Page 11: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

TABLE 2: SUMMARY OF BRIDGES (CONT'D)

Bridge I.D. No.

90

91

92

93

94

95

96

97

98

99

100

101

102

103

104

105

106

107

108

109

110

111

112

113

114

115

Name

Marshaltown (2640)

Yaquina Bay Bridge

Siuslaw River Bridge

Coos Bay

Santiam River Bridge

Thruway-Buffalo

Clarion River Bridge

Canoe Creek Bridge

Fayette County (359)

Red Rock Reservoir (613A)

Cedar River I80 (8859)

Moshannon Creek

Ramp C Viaduct I83-I695

I470 Ohio River

BN Sandpoint

Metro Pier Caps

Shitoku-Ohashi Tied Arch

Mukaijima-Ohashi

Location

Iowa

Oregon

Oregon

Oregon

Oregon

N.Y.

Pa.

Pa.

Iowa

Iowa

Iowa

Pa.

Md.

W~Rt Va.

Idaho

Wash., D.C.

Japan

Tied Arch . Japan

Maoroshi Tied Arch Japan

Dallas Elevated Texas

Green Bayou Bridge Texas

Red River Bridge Texas

Port Allen Intracoastal La.

Sunshine Bridge La.

I90 over Train Ave. Ohio

Third St. Via., Columbus Ohio

-8-

Type Cracking

Groove welded blast plates

Floorbeam end restraint

Cracked Stringer webs-Basqule

Floorbeam web above end conn.

Coped stringers

Longit. stiffener groove

Floorbeam web gap

Floorbeam web gap

Bearing stiffener web gap

Bearing stiffener web gap

Bearing stiffener web gap

Coped stringers

Box girder web gaps

Hanger cable fatigue

Weld repair-flange plate

Web penetration

Steel pipe diagonals-wind ·vibration

Hv·shaped hangers-wind vib.

H shaped hangers-wind vib.

Intersecting welds, end restraint

Lateral brace welded to flange

Coped flange at joint

Coped finger joint seat

· Coped sidewalk bracket

Transverse stiffener web gap

Lateral connection plate

Page 12: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

LIST OF REFERENCES

1. Nishimura, T. and Miki, c. FRACTURE OF STEEL BRIDGES CAUSED BY TENSILE STRESS Journal of Japanese Society of Civil Engineers, November 1975 (In Japanese)

2. Fisher, J. W. BRIDGE FATIGUE GUIDE - DESIGN AND DETAILS AISC Booklet Tll2-ll/77, 1977

3. ENR CRACKED GIRDER CLOSES I79 BRIDGE Engineering News Record, February 10, 1979, p.ll

4. FID.J'A Notice N5040. 23 Electroslag Welding, March 1977

5. Nozawa, T. and Yamada, Y. EXISTING STATES OF SHINKAUSEN BRIDGES (Tokaido-Shinkausen, Tokyo -Osaka) Civil Engineering of Railways, May 1977 (In Japanese)

6. Nishimura, T. FRACTURE IN WELDED BRIDGES Journal of Welding Society of Japan, Vol. 10, No. 10, 1978 (In Japanese)

7. ENR HIGH WIND BREAKS HANGERS IN NEH TIED-ARCH STEEL BRIDGE Engineering News Record, Vol. 103, October 17, 1929

8. ENR VIBRATING CABLES HALT WORK Engineering News Record, September 10, 1981, p.l6

9. Tanabe, M.; Shioi, Y.; Matsui, T. and Shiraki, K. VIBRATION CAUSED BY WIND ON BRIDGE ME}ffiERS COMPOSED OF STEEL PIPES AND ITS COUNTER MEMBERS Bridges and Foundations, Vol. 2, No. 8, 9 and 10, 1968 (In Japanese)

Note: This list of references is cited in the introduction and in the introductory articles provided for each type of cracking discussed. Each example has its own list of references.

-9-

Page 13: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

2. EYEBARS AND PIN PLATES

The failure of the Point Pleasant or Silver Bridge (I.D. 2) in

1967 as a result of the fracture of an eyebar is well known and a summary

of this failure is provided hereafter.

Several other eyebars have cracked in bridge structures although

none resulted in a collapse. At least two railroad bridges in the U. s.

developed fatigue cracks in eyebar heads that resulted in fracture

(I.D. 52, I.D. 48). One such failure that occurred in a Santa Fe Bridge

in Oklahoma (I.D. 52) was found to be caused by forge laps in the eyebar

head that happened to be oriented normal to the axis of the pin. This

served as an initial crack that resulted in fatigue crack growth and even-

tual fracture.

Five Japanese railway bridges built between 1900 and 1913 have de-

veloped fatigue cracks at the eyebar head normal to the axis of the pin.

A description of the Fujigawa Bridge is given in Ref. 1. About 820,000

train crossings have occurred over most of these structures.

Two bridge structures have experienced cracking in pin plates which

supported suspended spans. One such crack formed on the net section at '

the pin hole, much like an eyebar failure (I.D. 34). However, in the

second structure (I.D. 36) several pin plates failed in the gross section

as a result of corrosion product that "welded" the pin plate heads to the

girders. This caused bending stresses to be developed in the pin plates

and the fixity at the ends resulted in cracking at the corroded area.

Bending stresses were observed in the pin plates of two bridges that were

-10-

Page 14: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448-2

instrumented during the summer of 1981. Friction and corrosion product

provided fixity at the pins and caused rigid link behavior and bending.

A summary of the structure with cracked pin plates is provided in

this section on the Illinois 157 bridge,(I.D. 36).

-11-

Page 15: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

2.1 FATIGUE/FRACTURE ANALYSIS

of

POINT PLEASANT (SILVER) BRIDGE OVER OHIO RIVER

-- A Brief Summary --

I.D. No.

Town/City/etc.

Railway/Highway/Avenue

State

Owner

2

Pcir.t Pleasant, W.V. and Kanauga, Ohio

us. 35

West Virginia

West Virginia-DOT

-12-

Page 16: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 1

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief Description of Structure

The Point Pleasant Bridge which carried U.S. 35 highway over the Ohio

River was located between Point Pleasant, West Virginia and Kanauga, Ohio.

The bridge was also known as the "Silver Bridge" because it was one of the

major structures to be painted with aluminum paint (Ref. 1). It was one of

two nearly identical and unique eyebar chain suspension bridges in the U.S.

The other bridge, also spanning the Ohio River was at St. Mary's, West

Virginia until it was dismantled.

This bridge was an important link between major cities on both sides of

the Ohio River. It was also an important local artery for industrial plants

in Point Pleasant and the Gallipolis areas of Ohio.

The Point Pleasant Bridge was an eyebar chain suspension bridge with its

axis in an east-west direction over the Ohio River. It had a 700 ft. center

or main span and two 380 ft. side spans as shown in Fig. 1 (Ref. 1). In addi­

tion,. there were two approach spans on each side of the bridge. They were plate

girder spans 75.25 ft. and 71.50 ft. in length supported on concrete piers~

The two suspension bridge towers extended 130 ft-10.25 in. above the tops

of the two main piers. The total length of the bridge was 1, 753 ft. (Ref. 1).

The roadway of the suspended span as originally built in 1928, consisted

of a timber deck and sidewalks. In 1941, the timber deck was replaced with a

3-inch deep steel grid floor filled with concrete. The new roadway was 21

feet wide for two lanes of traffic with a 5 ft-8 inch sidewalk. The new deck

caused no significant change in the dead load of the structure.

-13-

Page 17: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 2

The bridge superstructure was unique in that the stiffening trusses of

both the center span and the two side spans were framed into the eyebar chain

to make up the top chord of about half of the length of the stiffening trusses

{Ref. 1) . Most of the eyebars were between 45 and 55 feet in length of

varying thickness (1.5 to 2.2 in) depending on the truss panel_inwhich they were

located. The shank width of eyebars was 12.0 in. They were made of heat treated

rolled carbon steel bars with forged heads designed to break at ultimate

loading in the shank. Each joint was composed of 4 eyebar heads and a con­

necting pin or pin rod, and was secured by double nuts on each end of the pin

rod as shown in Figs. 3, 4 and 5. A view of the stiffening truss and joint de­

tails are given in Figs. 4 and 6, 7, 8.

Brief History of Structure and Cracking

Construction began on the Point Pleasant Bridge on May 1, 1926 and the

Bridge was opened to traffic on May 19, 1928. The brdige originally was

built and owned by the W. Virginia-Ohio River Bridge Corporation. On

December 24, 1941, the State of W. Virginia purchased the Point Pleasant

Bridge and continued to operate the bridge under the authority of the State

Highway Commission as a toll bridge until January 1952, when it became toll

free (Ref. 1)

For almost 40 years, it carried an increasing number of vehicles across

the Ohio River (Ref. 1). On December 15, 196 7 the Point Pleasant Bridge col­

lapsed suddenly without any warning about 5:00 PM with the loss of 46 lives and

37 vehicles of all types (.Kef. 1). The three suspended .. sections fell within 60

seconds. The collapse was immediately preceded by several loud "cracking"

sounds on the Ohio side span superstructure. According to eyewitness

accounts, the bridge started to fall, hesitated, and then collapsed

-14-

Page 18: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 3

completely with a "roaring" sound that lasted during the collapse (Ref. 1).

0 The temperature at the time of collapse was recorded as 30 F (Ref. 1).

It has been clearly established by the investigation (Ref. 1) following

the failure that the nominal static stresses in all eyebar elements at the

time of collapse did not exceed those provided for in the original design.

The main cause of collapse (Refs. 2,3,4) was traced back to the unstable

extension or brittle fracture of two corrosion cracks located at the pinhole

of one of the four eyebars (Eyebar 330) of joint Cl3 north (see also Figs. 1,

2 and 6). The design of the chain was unique in that only two eyebars were

used in each chain segment and the chain also formed a portion of the top

chord of the stiffening trusses. Thus, failure of any one eyebar in the

bridge would cause the complete collapse of the structure (see Fig~ 9).

-15-

Page 19: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

2. FAILURE MODES AND FAILURE ANALYSIS

Location of Fracture, Failure Modes and Stages

Model test results (Ref. 3) on an eyebar and joint assembly made up

from the structural elements recovered from the wreckage similar to those

of joint Cl3N indicate that the separation of joint Cl3N was the key event

in the sequence of collapse of the Point Pleasant Bridge. Several possi­

bilities for separation of Cl3N were considered and tested which imitated

the cyclic and static load conditions at the time of failure. Physical

evidence on the .components of the joint by the induced brittle fracture

through the lower limb of eyebar 330, as shown in Fig. 8, was essentially

identical to that of the model prototype. Also the opening of the eye of

the eyebar due to plastic strain as well as the appearance of this second

fracture in the upper limb of this same eye are essentially similar.

Branching of the model test opposite limb of the eyebar introduced a

slightly different appearance after the midwidth of the section (Ref. 3).

Also, it was observed during the model test that there was an unexpectedly

long time interval between the instant of brittle fracture in the lower

limb of eyebar 330 and the subsequent complete separation of the joint.

This indicated that some time interval would likely be present during col­

lapse of the bridge structure.

4

Other studies (Ref. 4) corroborated the mechanism of stable crack ex­

tension responsible for the crack which triggered the collapse. It was con­

cluded that fatigue was probably not the cause of the crack extension (Ref.

4). The low live load stress range in the eyebar would not be large enough

to cause appreciable fatigue crack propagation.

-16-

Page 20: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

The two corrosion-fatigue cracks from which the fracture of the eyebar

initiated are shown in Fig. 11. Figure 12 shows a sketch of the flaws and

their dimensions (Ref. 2). Also shown in Fig. 12, are the results of a

hardness survey through the thickness of the eyebar. Due to heat treat­

ment of the eyebar a harder layer existed at a depth of 0.1-0.4 in. from

the surface. This also decreased the toughness of the material. Since

5

the two flaws lie in the area of highest hardness, the local fracture tough­

ness was less than the average value shown in Fig. 13 (Ref. 2).

Examination of the flaws and the crack surface revealed considerable

corrosion and corrosion product. At the location of the flaws, contami­

nated water could be trapped in a crevice area of high stress and high

local hardness. Hence, stress corrosion appears to have been the oominant

mechanism for the creation of the two initial flaws or cracks. These

flaws coupled with the low toughness at the time of collapse caused the

sudden brittle fracture phase in the lower limb of the eye of the eyebar

and consequently the catastrophic failure of the Point Pleasant Bridge.

Cyclic Loads and Cyclic Stresses (Known or Field Recorded)

A traffic survey conducted by Ohio-DOT in 1964 indicated that 6,640

vehicles (ADT) crossed the structure as a result of the two-way traffic.

There were 5,040 of the vehicles that were passenger cars, and the remain­

ing 1,600 were trucks.

The bridge was not posted for weight limits. However, an ''overload"

permit was required for all vehicles over 70,000 pounds. On December 7,

1967 a tractor trailer weighing 98,000 lbs. crossed the bridge without any

unusual occurrences.

-17- '

Page 21: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 6

A computer analysis of the bridge was conducted after the collapse,

and it was found that the unit stress at collapse was less than the 1927

design unit stress for all essential structural members in the bridge

(Ref. 1). Figure 15 summarizes the results for eyebars 11-13 (Ref. 4).

The mechanical characteristics of the bridge steel obtained from tests

after the failure are given in Fig. 16 a,b (Ref. 3).

Temperature and Environmental Effects

The atmosphere provided the necessary elements for the development

of stress corrosion cracking in the heat treated 1060 eyebar steel. Thus

the size of the corrosion induced cracks was increasing with passage of

time.

0 In addition, the recorded temperature at the time of collapse was 30 F

(Ref. 1). The fracture resistance was then low enough in comparison with

crack size so that onset of rapid brittle fracturing developed.

The measured static fracture toughness KIC of the specimens from the

eyebar material and the estimated dynamic toughness KID are plotted in

Fig. 12. Approximate values of KIC and KID corresponding to the tempera­

ture of 30-32° F at the time of collapse are indicated in Fig. 12.

Material "Mechanical, Chemical and Fracture Characteristics"

Analysis in the Failure Regions

Several specimens \·7ere tested from the shank portion of the eyebar

members of the collapsed Point Pleasant Bridge.

-18-

Page 22: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Chemical and metallurgical characteristics of the material were re-

ported and evaluated in Ref. 2. The tensile and fatigue characteristics

of the eyebar steel from the collapsed bridge was also investigated, and

the results are reported in Ref. 4.

The tensile strength values obtained from standard and special tension

specimens at room temperatures met the minimum strength requirements of the

original specifications, as can be seen in Tables 1 and 2. No major vari-

ation in the tensile properties of the eyebar steel is apparent.

· An analyti~al and experimental study of the fatigue characteristics of

the small specimens fabricated from the eyebars of the collapsed bridge

showed that the small stress range levels probable at eyebar Cl3N would be

too low to cause the imitation and extension of the flaws and cause failure

by fatigue (Refs. 4,5). The design live load stress in the shank of the

eyebar was 12.5 ksi. The dead load design stress was 36 ksi. At the time

of failure, the total shank stress was estimated to be 41 ksi. The stress

intensity estimate of the crack tip was about 50 ksi lrn. (Ref. 4).

The measured static toughness KIC and the estimated dynamic toughness ·

Kid of the eyebar material are shown in Fig. 12 (Ref. 5). A temperature

shift of 100° F was used to estimate the dynamic fracture toughness. At

the failure temperature of 30-32° F, the value of KIC is 41 ksi ;in. and

Kid is 26 ksi /In. (Ref. 5).

The initial flaws or cracks from which the fracture of the eyebar

initiated are shown in Figs. 10 and 11. Figure 11 also shows results of a

hardness survey through thickness of the eyebar. Due to heat treatment of

the original eyebar during manufacturing, the material in the center of

-19- '

7

Page 23: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 8

the plate is harder than the material on the surface. The flaws are

located in the area of maximum hardness (Ref. 5) which produces lower

fracture toughness. It seems probable that the two corrosion cracks

would have eventually coalesced and increased K substantially. Hence

fracture would likely have occurred with a higher toughness material as

well if it was stress corrosion sensitive.

Visual and Fractographic Analysis of Failure Surfaces

Examination of the flaw surfaces on the Cl3N eyebar, revealed con­

siderable quantities of corrosive products. Stress corrosion tests on

the material showed that it was corrosion sensitive. The fatigue tests

on specimens with machined surfaces indicated that eyebars of the structure

should have adequate fatigue resistance (Ref. 4).

-20-

Page 24: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

3. CONCLUSIONS A~~ RECOMMENDATIONS

Conclusions Regarding Fracture/Failure

The following conclusions can be made regarding the collapse of the

Point Pleasant (or Silver) Bridge (Refs. 4,5):

a) The tensile properties of the eyebars in the structure met the

minimum requirements of the original design.

b) The mechanism of crack extension of the initial flaws in Cl3N

eyebar to the critical size at failure was most likely caused

by stress corrosion. The eyebar material provided to be stress

corrosion sensitive. The location of the initial flaws in an

area of high local hardness in combination with stress corro­

sion sensitivity appears to have been the primary cause of

·failure.

Recommendations for Repair/Fracture Control

This is not applicable to the case of the Point Pleasant Bridge

failure. The structure collapsed suddenly before the flaws and stress

corrosion cracking was detected.

4. ACTUAL REPAIR/FRACTURE CONTROL EFFORTS

Not applicable to this case.

-21-

9

Page 25: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 10

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

Not applicable to this case.

6. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

Cost of Failure Investigation

This is not available. The failure of the Point Pleasant Bridge was

investigated by Federal Highway Administration, Washington, D.C. (see, for

instance, Reference List on this Summary).

Cost of Repair/Rehabilitation

Not applicable to this case.

Original (or Adjusted) Cost of Structure

This is not available.

-22-

Page 26: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 11

7. REFERENCES

(1) National Transportation Safety Board COLLAPSE OF U.S. 3) HIGID~AY BRIDGE POINT PLEASANT, WEST VIRGINIA, DECEMBER 15, 1967, NTSB Highway Accident Report, U. S. Department of Transportation, Washington, D.C., October 4, 1968.

(2) Ballard, D. B. and Yakowitz, H . .. MECHANISMS LEADING TO THE FAILURE OF THE POINT PLEASANT, WEST VIRGINIA BRIDGE - PART 3, National Bureau of Standards Report No. 9981 to U. S. Bureau of Public Roads, September 1969.

(3) Scheffey, C. F. and Cayes, L. R. MODEL TESTS OF HODES OF FAILURE OF JOINT Cl3N OF EYEBAR CHAIN POINT PLEASANT BRIDGE I1~ESTIGATION, Federal Highway Administration Report No. FHWA-RD-74-19, U. S. Department of Transportation, Washington, D.C., January 1974.

(4) Nishanian, J. and Frank, K. H. FATIGUE CHARACTERISTICS OF STEEL USED IN THE EYEBARS OF TEE POINT PLEASANT BRIDGE, Final Report, Federal Highway Administration Report No. FHWA-RD 7 No. FHWA-RD-73-18, U. S. Department of Transportation, Washington, D.C., June 1972.

(5) Frank, K. H. and Galambos, C. F. APPLICATION OF FRACTURE MECHANICS TO ANALYSIS OF BRIDGE FAILURES Specialty Conference Safety and Reliability of of Hetal Structures of ASCE, Pittsburgh, Pennsylvania, Nov. 2-3, 1972, pp. 279-306.

-23-

Page 27: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

TJ;,.Bi.":' 1

TENSILE PROPERTIES fJF TEE P.~.7ERIAL AT Roo..! T:::M:PERATUP.E

SPECIMEN TENSILE YTl"T J) ELCNGATION :t.1JMBER STRENGTH STRE!iGTH m 2 INCHES

k.s.i. k.s.i. :2ercent

1 ll6.1 76.9 23.62

2 ll6.1 79.4 2l.50

lt ll5.1 79.45 20.90

5 ll4.95 77.3 20.50

7 ll9.15 81.45 20.90

8 1.22.15 83.15 21.29

10 ll3.2 76.3 21.89

ll ll3.55 79. 22.00

AVERAGE ll6 79. 21.58

TA3LE 2

TENSION TEST RESULTS TCGETE!:R ;;-rrH THE MliHY".JM STRENGTH

~UIREMEN'l'S OF ORIGINAL DESIGN SPECIFICATIONS

Yield Strength TensUe Strength lt.s.i. lt.s.i.

Average Results of Standard Specimens 79 ll6

Special Specimen 82 109

Values as Required* by Specification 75 100 to 105*

* Taken from original drawing pre:pa.re:i by J. E. Greiner Co.

-24-

Page 28: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

TP.BLE 3 COMPUTED STRESSES IN THE PROTOTYPE EYEBAR

WHICH w~RE REPRODUCED IN TF~ MODEL EYEBARS.

~URED .:EASt:RED DESIGN LOADS ACTUATOR LOADS TOTAL LOAD . IN STRESS IN !10DEL

IN POUNDS IN POUNDS EYEBARS 11-13 EYEBARS 11-13 IN POUNDS IN FSI

Dead Load 67,200 68,500 36,600.

Live Load 22,950 23,400 12,500

Temp. 2,380 2,430 1,300

Total 92,530 94,330 50,400

Yield 137,600 140,400 75,000 (Theoretical)

NOTE:

Total area of model eyebars 11-15 ~ere calculated as 2 x 2.4 x 0.39 • 1.872 1n2

-25-

Page 29: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I N (J"\

I

C13N (Far Side)~ Se• F ;gu" 2 "-,..

<

<o

Fig. 1

te Atl"f/t f?J"o.mfo IBn: a~·

Elevation View of Point Pleasant Bridge

(

>;

___ J~~!:.. ___ _

Page 30: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I IV -....J I

Ohio

I

l __ l5 _fqnejs at 25'- 4: 2 3/}g'-o• -l-- ----=28 Panels (J_l_f!..5'-g_"~-Z_QQ'~o:_ ELEVATION ___ _

Fig. 2 Location of Joints Cl3, U7, and Ul3

Page 31: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Typical eyebar cnain joint for portion& of the eyebar chain where the chain was not framed into truss members. Note hanger· strap and &trap plates in the center of photograph. The strap plate was connected to the top chord of truss members vertically below the eyeba r joint. This plate shows makeup of joint C 13 north.

Fig. 3 Details of Joint Cl3

-28-

Page 32: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Oetaikd dia~ram of construction of joint U7 of the north truss of the Ohio side span showing the joint pin, the two sets of eyebars, gusset plates attaching members of the north truss to the eyebar joint, retaining plate and the retaining pin which was inserted through a concentric hole in the joint pin and which was installed with two nuts :>neither end of the retaining pin. The makeup of the retaining pin, retainer plates and the use of double nuts on each end of the retaining pin were. common to all eye bar joints except at the tops of ~he two towers and at the connections of the eyebar chain with the. :hain bent post•.

------------------....,

Fig. 4 Details of Joint U7

-29-

Page 33: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

/: -l " 'c

' (

'

/: " 0 0 " ,. ' 0

"

0

' 0 0

Details of connection of Ohio end of lower chord of south truss of Ohio side span into south chain bent post on Ohio sid" of bridge. Note the square pin connected to vertical chain bent post. The lower chord of the side span truss ":'as permitted to move

L-------------------------longitudinally through provision of a slotted section around the

Fig. 5

square pin to equalize expansion and contraction of tht: bridge due to temperature changes and changes in live load. The detail shown was that used to connect th" lower chords of both trusses of the two side spans into the four chain bent posts in the bridge.

Details of Joint at Ohio End of the Point Pleasant Bridge (See Also Fig. 2)

-30-

Page 34: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 6 Point Pleasant Bridge (after collapse)

Fig. 7 One of the Eyebar Joints (after collapse)

-31-

Page 35: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

, -· .. . :.: .• ,...,.,_ .........

Fig. 8 Fractured Cl3N Eyebar

- .. !. ~:~?---- -.~ --:-~~, :-: , ---~. : . ·:. ,_.

Fig. 9 Fracture Surface of Cl3N Eyebar

-32-

Page 36: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 10 Initial Cracks in Pinhole of Reyebar Cl3N

-33-

Page 37: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

K

ksi

80

60

,rrn

40

20

Distance F::-on: Surface of Eyeba.r

in.

0. 8

0.6

0.4

0.2

0

I \ \ \

' ' ' ' ' ' ' ' Secondary '"- Cracking

' \ \ \

0.2 0.4 0.6

Distance from.Pin Hole

in.

I • • ••

1-• • I • \

... -·

~ ...

/.

\ •. • I •

"' 200 220 240 260

Vickers Hardness

Fig. 11 Location of Initial Eyebar Cracks and the Local Hardness of the Material

·8 -8

0

0 Measured Static

0 KID = 15.87 (CVN)~

~/-Static •rc

---------0

--------------~~-_.:-­---0

Dynamic KID

--

0-+----+---------~------~~-------+--------~--------4---------+-------~~ 0 40 80 120

TEMPERAT.URE - °F

Fig. 12 Fracture Toughness of Eyebar Steel

-34-

Page 38: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

2.2 FATIGUE/FRACTURE ANALYSIS

OF

ILLINOIS RT. 157 OVER ST. CLAIR AVENUE

-- A Brief Summary --

I.D. No. 36

Town/City/etc. French Village

Railway/Highway/Avenue: Illinois 157 over St. Clair Avenue

County St. Clair

State Illinois

Owner Illinois

-35-

Page 39: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 1

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief Description of Structure:

The Route 157 bridge located in St. Clair County, Illinois is a skewed

seven span continuous structure 474 ft.- 6 in. long over St. Clair Avenue.

It is composed of thirteen rolled WF beams spaced at 5 ft.- 6 in. and vary­

ing spans. Spans 2 and 6 are each 100 ft. long with 60 ft. suspended

segments supported by cantilevering the adjacent spans. The suspended

spans are supported by a rocker bearing on one end and by pin plate links

on the other end, as illustrated in Fig. 1. Figure 2 shows a view of

span 2. Spans 1 and 7 are 54 ft.-9 in. long and spans 3, 4 and 5 are

55 ft. - 0 in. long.

The original A7 steel rolled sections were W36X230 in spans 1, 3, 5

and 7. The suspended spans were W36Xl50 sections as was span 4. Welded

cover plates were attached to the bottom flange over the supports at piers

1, 2, 5 and 6. Two additional A36 steel beams were added in 1966 and were

W33X200 sections between pier 3 and the north abutment, W36Xl60 sections

between pier 4 and the south abutment. The structure was designed for

H20-44 loading. Figure 3 shows a schematic of suspended span 2.

The structure was built in 1945. In 1966 it was widened by adding

two beams to the west side of the structure. On October 23, 1978, the pin

links supporting the ends o.f beams (No. 8, 9, 10) in the passing lane of

span 2 were found to be fractured as illustrated in Fig. 4. The cracked

plates were discovered by a district employee driving beneath the structure.

The beams had dropped between 1/2 to 3/4 in. below the deck slab. Span 6,

which is identical to span 2, was found to be structurally sound with no

evidence of cracks in the hangers.

-36-

Page 40: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 2

2. FAILURE MODES AND FAILURE ANALYSIS

Location of Cracks, Failure Modes and Stages

Figure 3 shows the locations of the fractured hanger plates in span 2.

In addition to the hangers supporting beams 8, 9 and 10, seven additional

beams had plate hangers which were either bowed or partially cracked, and

these are also identified in Fig. 3.

The cause of the failures appears to be due to rust and other corro­

sion product which builds up between the beam web reinforcement and the

hanger plates. .Since the hangers were located beneath the expansion joint

finger plates, water, salt and other debris came in contact with the pin­

ned connections of the hanger plates. This resulted in a freezing_ of the

lower pins. Hence, rigid joints developed with passage of time.

The frozen joints subjected the hanger plates to large in-plane bend­

ing stress as a result of traffic and thermal expansion. Measurements on

other bridges with suspended span hangers have confirmed that the relative

end rotation that is assumed to occur results in large bending stresses

when frozen hanger plates exist. The repeated loading resulted in cracking

and eventual failure of the 3/4 in. x 7 in. pin plates.

Cyclic Loads or Stresses (Known or Field Recorded)

No measurements or design stresses were avilable for this structure.

The average daily truck traffic (ADTT) for 1980 was 300. The total

daily traffic for 1979 was 18,600. The average daily truck traffic results

in 110,000 cycles of random loading per year. Hence, about 3.5 million

cycles of repeated load were experienced by the structure.

-37-

Page 41: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 3

Temperature and Environmental Effects (Known or Field Recorded)

No temperature data was available. However, it seems likely that the

thermal expansion of the structure resulted in large bending stresses in

the hanger plates.

The slant fractures of the hangers do not suggest any evidence of

cleavage fracture. (see sketch in Fig. 3).

Material "Fracture, Mechanical and Chemical Properties"

in the Failure Regions

No tests were performed on the hangers.

Visual and Fractographic Examination of Failu~e Surfaces

Visual inspection of the cracked hangers revealed a 45° failure sur­

face, as shown schematically in Fig. 3. As can be Seen in Fig. 4, cor­

rosion product exists at the cracked area. No fractographic examination

was carried out.

Crack Growth (Initiation and Propagation)

and Probable Causes of Failure

The primary cause of failure was the development of frozen pin joints

as a result of corrosion product. The hanger and girder web reinforcement

became rigidly attached as a result of the water, salt and other debris to

which the hangers were exposed. This prevented the links from rotating

and accommodating the repeated loading from traffic and thermal expansion.

The cracks develoved in the gross section at the edge of the frozen joint.

-38-

Page 42: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 4

The corrosion product effectively welded the hanger to the web and prevented

the net section from becoming critical. The fracture surface of the hanger

from Beams 8 and 9 appeared to be "very old." The hangers on Beams 5, 6,

7 and 11 were all bowed.

-39-

Page 43: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 5

3. CONCLUSIONS/RECOMMENDATIONS

Conclusions Regarding Fracture/Failure

The cracked hangers in the Ill. 157 bridge appear to be repeated

load induced as a result of the frozen pin connection. The suspended span

end displacements subjected the hanger to high cyclic in-plane bending

stresses from traffic and thermal conditions. The resulting cumulative

damage caused cracks to form and propagate at the edge of the corrosion

"welded" region.

The highest thermal expansion and contraction stresses were probably

induced during the periods June-August and December-February. This cor­

responds to the highest and lowest temperature per'iods. Final failure may

have occurred during the winter period when the material toughness would

be at its lowest level.

Recommendations for Repair/Fracture Control

The northbound passing lane was closed, and Beams 8, 9 and 10 were

shored, as illustrated in Fig. 5 until the broken hangers were replaced.

Fourteen additional hangers were replaced during subsequent maintenance

operations. The hangers on the beams which were added in 1966, were

inspected and found to be satisfactory. No evidence of cracking was

observed.

-40-

Page 44: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 6

4. ACTUAL REPAIR/FRACTURE CONTROL EFFORTS

The cracked and defective hangers were replaced by Illinois Department

of Transportation. Beams 7, 8 and 9 were jacked back into place, and new

hangers and pins installed. All corrosion product was removed, and all of

the pins were freed up.

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

. No adverse effects are expected as a result of the repair procedures

which were carried out. Other cracks should be prevented from developing

as long as the hangers function as intended.

5. ACTUAL OR EST~ATED REPAIR/REHABI~ITA!ION COSTS

Cost of Investigation

No investigation was carried out.

Cost of Repair/Rehabilitation

The cost of repairing the cracked and defective hangers with Illinois

Department of Transportation personnel was $10,000, including traffic control.

Original (or Adjusted) Cost of the Bridge

The original cost of the structure was $120,836.96 in 1945. The cost

of widening the structure in 1965 was $208,199.20.

-41-

Page 45: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

TYPICPIL SECTION Fig. 1 Typical Hanger Section for Suspended Spans 2 and 6

---- ~ : ·:-... . ~.

.. -

Fig. 2 View Showing Suspended Span 2 over St. Clair Avenue

-42-

Page 46: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

<t Pier I

Fractures

I 2 Links 31411

X 7 !e.

I 3" Pins I

i

601

Cracked 2"

4' Median 7 {

Ill -(.) U)

' bound

bowed

bowed

bowed

bowed

OK

___ -.;;;.;~+--------__;;O..;.K;.._ rust @ crack I 1/2'~ intact.....,...

East Link--.1 Rust Condition

West Link__..-T Pin Condition

clean

rust

c ..Q -0 ~

0 Q. G>

Cf)

c::t ~

Fig. 3 Schematic of Suspended Span Showing Locations of Cracked Hangers

-4 3-

I-

-c G>

"C ·:; w Ill Ill G> ~ -..!!!

0 ~ (.J

G> 0 0 z

Page 47: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 4 View Showing One of the Cracked Hangers in Span 2.

Fig. 5 Steel Shapes Shoring up Cracked Beams in Span 2

-44-

Page 48: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

3. COVER-PLATED BEAMS ru~D FLANGE GUSSETS

The Yellow Hill Pond multibeam structures (I.D. 3) at Bridgeport,

Connecticut have developed extensive fatigue cracks at the ends of cover

plates. A summary of this cracking is provided hereafter. These cracks

resulted from the large volume of truck traffic and the unanticipated low

fatigue resistance of the large sized cover-plated beam members (Cat. E').

The King's Bridge in Austrailia (I .D. 1) is well known for its failure

as a result of fatigue cracking and fracture from very large weld toe

cracks that developed during fabrication in all four girders.

A third structure experienced cracking at the cover plate end of one

beam ir. New Jersey (I.D. 44).

In addition to welded cover plates, several other Category E or E'

details have experienced fatigue cracking at weld terminations. These

include gusset plates welded to the flange and the termination of longitudi­

nal stiffener welds at transverse stiffeners or connection plates. Three

structures have exhibited cracking at the end of flange gusset plates

(I.D. 39, I.D. 66, and I.D. 85).

The crack that formed in the Vermillion River Bridge, originated at

the end of a longitudinal fillet weld that was used to attach a 3 ft.

(.9 m) long lateral connection plate to the edge of a 8 x 8 x 1 in.

(20 x 20 x 3 em) flange angle. The gusset plate lapped over the flange

angle surface and was welded along both edges. An 18 in. (46 em) wide

cover plate was also welded to the flange angles.

-45-

Page 49: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Two structures have had cracking at the end of longitudinal stiff­

eners that intersect transverse welded plates (I.D. 65 and I.D. 109).

-46-

Page 50: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

3.1 FATIGUE/FRACTURE ANALYSIS

OF

YELLOW MILL POND BRIDGE

-- A Brief Summary --

I. D. No.

Town/City/etc.

Railway/Highway/Avenue/etc.

County

State/Province

Owner

-47-

3

City of Bridgeport

Interstate I-95

Fairfield County

Connecticut

Connecticut-DOT

Page 51: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 1

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief Description of Structure:

The Yellow Mill Pond Bridge carries Interstate I-95 (Connecticut Turn-

pike) over the Yellow.Mill Channel (an extension of Bridgeport Harbor on

Long Island Sound) is located in the City of Bridgeport, Connecticut.

The simple spans of the Yellow Mill Pond complex were designed con-

sidering composite action between the rolled cover-plated steel beams

and 7.25 in. (184 mm) reinforced concrete slab. In 1969 a 2 in. (51 mm)

bituminous concrete overlay was placed on the concrete deck.

The bridge complex consists of fourteen consecutive simple span

cover-plated steel and concrete composite beam bridges crossing the Yellow

Mill Pond Channel (fourteen bridges in each direction of traffic) (see

Fig. 1). Each bridge carries three lanes of traffic. The typical posi-

tion of the main beams and diaphragms of the structure a:r.e given in the

d · f lOU~) · F. 2 d 2 b plan an cross-sect1on o span . . . 1n 1gs. . a an . . The

external facia beam (M88) of the eastbound bridge is skewed as four lanes

of through traffic are being reduced to three lanes.

In order to accommodate the Yellow Mill Pond Bridge structure to

tidal shipping channel clearances, cover-plated beams were employed by

the designers in lieu of deeper built-up girders. In the span 10, all

beams are W36 A242 steel sections. The tension flanges of all beams

except (M86) interior facia beam of the eastbound roadway are fitted with

(*) This is the typical span at which field strain measurements were recorded and stress-range histograms developed (see also Ref. 1).

-48-

Page 52: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 2

multiple cover plates (primary and secondary). The compression flanges

have single cover plates. All cover plates are partial length with the

exception of the primary plates of the external facia tension flanges of

(H88) and (M83) which extends to full length. The cover plate ends are

square, and their corners are rounded to a 3 in. (76 mm) radius of curva­

ture (for the cover plate details, see Figs. 3 and 4).

Brief History of the Structure and Cracking:

The Yellow Mill Pond Bridge was constructed in 1956-1957. It was

opened to traffic in January 1958. In October-November 1970, the steel

superstructure of the Yellow Mill Pond Bridge were inspected following

the cleaning and repainting done by the contractor. On November 2, 1970,

during a routine inspection of the repainting workmanship, it was dis­

covered that a crack had developed in the eastbound roadway in span 11.

The crack started at the west end of the cover-plated beam and had pro­

pagated through the flange up to 16 in. (400 mm) into the web of one of

the main girders (girder No. 4, span 11). Figure 5 shows a photograph of

the beam as it appeared shortly after the fracture was discovered. The

crack originated at the toe of the transverse fillet weld connecting the

cover plate to the tension flanage of the beam (see also Figs. 6.a and 6.b).

Inspection of fifteen similar locations on different girders on the

same bridge revealed the possibility of incipient cracks of varying magni­

tude along eight of the cover-plate end welds. The two beams adjacent to

the fractured beam had fatigue cracks which extended halfway through

the tension flange at the end of cover plates. These were Beams 3 and 5

-49-

Page 53: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 3

in Span ll of the eastbound roadway. The cracks in Beams 3 and 5 were

inspected by ultrasonic testing and a crack depth of 0.625 in. (16 mm)

was measured.

In December 1970, following the detailed inspection, a section of

fractured girder was removed, and all three damaged girders were repaired

with bolted web and flange splices. In November 1973, the east end of

Beams 2 and 3 of the eastbound roadway of Span 10 were inspected again.

Fatigue cracks were observed in both girders at the toe of the primary

cover plate transverse fillet welds. A crack depth of 0.275 in. (10 mm)

was measured in Beam 2, and its presence was verified by the magnetic

crack definer.

In June 1976, the cover plate details in the eastbound and westbound

lanes of Span 10 were inspected for fatigue cracking by visual, dye pene­

trant and ultrasonic inspection techniq~es. Twenty-two out of forty

details were found to have cracks. The smallest visually observable

crack was 0.25 in. (6 mm) long. Ultrasonic inspection provided confirma­

tion of cracks about 0.5 in. (13 mm) long at the west end of the east­

bound lane in Beams 3 and 7 of Span 10. The results of the inspection

in terms of the crack depth and locations are given in Refs. 1 and 5.

-50-

Page 54: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

2. FAILURE MODES AND FAILURE ANALYSIS

Failure Modes, Stages and Location of Failure:

In November 1976, during a brief inspection of Span 13 with field

glasses from the ground level, four large cracks were observed. These

cracks were approximately 6- 10 in. (150- 250 mrn) long and about 0. 5 in.

4

(13 rnm) deep. They had broken the paint film at the weld toe (see Fig. 6a).

In September 1977, span 10 was inspected again. The secondary details

at Beam 5 of the westbound bridge, and the secondary details of Beams 5 and

6 of the eastbound bridge at the east end were inspected for the first time.

No cracks were observed. Small cracks were found at the west end of the

secondary details of Beams 4, 5 and 6 of the eastbound bridge. (These de­

tails were previously inspected in 1976, but no cracks were found at that

time). In addition, several cracks were found in details in Span 12. The

cracks were up to 15 in. (381 mm) long.

In November 1979, several details in Span 10 were inspected again by

visual and ultrasonic means. The ultrasonic inspection verified the crack

found during the 1977 inspection. The secondary detail on Beam 4 of the

eastbound bridge near the west end was cracked. The retrofitted details

were also inspected, and only one crack was detected, which was growing

from the root of the primary detail on the west end of Beam 2 of the east­

bound structure. The crack was 1. 25 in. (32 mm) on the surface, and ultra­

sonic inspection indicates 6 in. (152 rnm) length at the root. Small cracks

were found for the first time at the west end of the secondary detail on

Beam 2 of the eastbound bridge.

The history of inspection of span 10 and the location of the cracks

detected or found each time are summarized in Table 1. Figure 2a shows

the location of these details. -51-

Page 55: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 5

Cyclic Loads or Stresses (Known or Field Recorded)

The eastbound and westbound bridges of Span 10 were selected for two

major stress history studies. Both of these studies were conducted by the

State of Connecticut (CONN-DOT) and the Federal Highway Administration

(Fffi~A). The first study was conducted in July 1971 (2), and the second

between April 1973 and April 1974 (3).

In the July 1971 study two electrical resistance strain gages were

placed on the interior beams. One gage was placed midspan and the other

4 in. (102 mm) from the end of the primary cover plate (the gages were

either on the bottom flange or on primary cover plates). A typical stress

histogram for the gage on a girder under the eastbound lanes is shown in

Fig. 7. A typical stress histogram is given in Fig. 8 for the westbound

lanes. The truck distribution and its position in the lanes were also

concurrently recorded and the:ir weights were sampled (2).

It can be seen from stress-range histograms of the eastbound bridges

that 94-99% of the stress ranges occurring at the cover plate ends fell

within 0.60-1.95 ksi (4.137 -13.445 MPa) levels. Very few events were

found to have cyclic stresses in excess of 2.40 ksi (16.548 MPa). A

single event exceeded 3.3 ksi (22. 753 HPa). At the midspan gages, 97-99%

of all recorded stress ranges fell within the limits 0. 60- 2. 85 ksi

(4.137 -19.650 MPa). Thirty-five events exceeded 3.0 ksi (20.684 MPa).

The overwhelming majority of midspan stress ranges were below 3.6 ksi

(24.821 ~~a). A large event equal to 7.2 ksi (49.643 MPa) occurred in

only one case. The gross truck weights were fairly evenly distributed

between 10,000 and 70,000 lb. with the maximum weights recorded between

-52-

Page 56: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 6

90,000 and 100,000 lb. The distribution of truck traffic indicated that

approximately 55 percent of the trucks were in the outer lane and 45 per­

cent in the middle lane. Less than 1 percent were in the inner lane

The composition of the average daily truck traffic (ADTT ) at the Yellow

Mill Pond Bridge was about the same as the gross vehicle weight distribu­

tion developed from the 1970 FHWA nationwide Loadometer survey. The

one-way average daily traffic (ADT) and the average daily truck traffic

(ADTT) on span 10 is plotted in Fig. 9 for 1958 through 1975. From

January 1958 to June 1976 approximately 259 million vehicles have crossed

Span 10. Approximately 13.5% of this total traffic flow is truck traffic.

Therefore, approximately 35 million trucks crossed the eastbound and west­

gound bridges of Span No. 10 during the interval between 1958 and 1976

The output of a gage on the diaphragm produced some of the most sur­

prising results within 63 hours, the bottom flange at midspan of the dia­

phragm was stressed to 3.0 ksi or more 2400 times. This included 27 stress

cycles greater than 5.4 ksi. The only explanation for this phenomenon

must be related to the rotation of the main girders. Rotation of the

internal beams are restrained by the diaphram at their points of inter­

section with the girders unless some lateral movement of the latter is

permitted. This might explain the high incidence of bolt failures in these

connections.

During the second study, from April 1973 to April 1974, the stress

history of the eastbound bridge of span 10 was monitored by mechanical

strain recorders that were attached at midspan to Beams 3 and 4

-53-

Page 57: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 7

A comparison of the results with strains recorded at the midspan of Beams 3

and 4 during July 1971 indicates that slightly higher stress range events

occurred in 1973 as compared to the 1971 study.

Also, a limited strain history record was obtained for the eastbound

bridge of span 10 in June 1976.

The Miner and root-mean-square (RMS) effective stress ranges for the

July 1971 study do not differ as much as implied by the June 1976 study.

Temperature and Environmental Effects (Known or Field Recorded):

The material toughness for the Yellow Mill Pond Bridge girders satis­

fied the requirements for AASHTO temperature Zone 1. The transiti9n tem­

perature at 15 ft-lb. (20 joules) for the beam flange was 55° F (13° C)

as shown in Fig. 10. The transition temperature diagram is given in

Fig. 11 for the web. The web of the cracked beam showed evidence of some

cleavage fracture. This rapid crack growth may have occurred in September

1970 when a large overlaod is believed to have crossed the bridge

In spite of the lower temperatures [i.e. less than 0° F (-l8°C)] the

adjac~nt girders with sizeable fatigue cracks withstood these conditions.

-54-

Page 58: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Material "Chemical, Mechanical and Fracture Properties"

Anal vsis in Failure Regions:

In December 1970 after a detailed inspection, following the dis­

covery of cracks, a portion of the flange and web adjacent to the crack

was removed for testing.

The chemical analysis of the material from the web and flange of the

W36X300 rolled steel beam indicated that excessive manganese was present.

The chemistry check based on ASTM A.242 specifications yielded 1.69%

manganese which is above the limit value 1.45%. All other chemical ele­

ments appear to be satisfactory and within tolerance limits (4).

Mechanical tests of the flange and web material provided a 57.8 ksi

(398.519 }~a) yield point for the flange and a 95.1 ksi (655.695 MPa)

tensile strength. The web material had a yield point of 57.2 ksi

8

(394.383 MPa) and a tensile strength of 87.5 ksi (603.295 MPa). Both

flange and web exhibited satisfactory elongation characteristics (i.e. 28%).

The fracture characteristics of the web and flange material was

assessed using Charpy V-notch impact tests. These tests revealed an

interesting difference in transition temperature of the flange and web

material. The flange material provided a +55° F (13° C) transition tem­

perature at 15 ft-lbs. (20.337 joules), whereas the web provided -10° F

(-23° C) transition temperature. This is most likely due to the excess

manganese and increased thickness of the flange material. Transition

curves for both flange and web material are given in Figs. 10 and 11.

Compact tension tests were also carried out, and these provided 1 sec.

fracture toughness values of about 80 ksi ~. at -10° F.

-55-

Page 59: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Visual and Fractographic Examination of Failure Surfaces:

The crack surfaces in the web and flange were subjected to visual

examination in order to evaluate crack growth regions. Three dis-

9

tinct areas or regions were noted. The fracture surface examinations indi­

cated that fatigue crack growth started at the weld toe and grew completely

through the flange and into the web about 2 in. (50.8 mm). The crack path

changed when it encountered a lamination condition near the center of the

flange. The lamination retarded the advancement of the path.

Near the edges of the beam flange, the crack path moved into a second

crack growth region away from the weld toe. At this stage, tensile frac­

ture partially occurred as evidenced by some apparent necking. The frac­

ture surface in the web characteristically indicates that rapid crack growth

developed after a 2 in. (50.8 mm) fatigue crack had penetrated into the web.

The crack extended about 7 in. (177.8 mm) up the web and was finally ar­

rested near middepth. The fracture surface suggested a "brittle fracture"

mode in the web. There was also some evidence of shear lips at the surface

of the web plate. It is highly probable that the rapid crack extension

occurred in September 1970 when a large overload crossed the bridge.

A third region of apparent slow crack growth which likely occurred

after the large overload was also observed.

The fracture surface was coated with oxide and paint. This suggested

that the crack existed for several months prior to its discovery on

November 2, 1970

-56-

Page 60: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

3. CONCLUSIONS AND RECO:HHENDATIONS

Conclusions Regarding Fracture/Failure:

The field observations on cracking of the Yellow Mill Pond Bridge

yielded the following conclusions

10

a. Significant fatigue crack growth can occur at welded cover plate

ends when a few stress cycles in the variable stress spectrum

exceed the constant cycle fatigue limit and a large number of

stress cycles accumulate (~ 10 7).

b. It is possible that other comparable cover-plated beam bridges

(with the flange thickness tf > 0. 8 in. (.20 mm) will require

retrofitting in the future if subjected to high volume truck

traffic.

c. The observed field behavior at the Yellow Mill Pond Bridge is

compatible and corroborated by the results of laboratory tests

on full scale cover-plated beams.

-57-

Page 61: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 11

Recommendations for Repair/Fracture Control

Peening and gas tungsten arc remelting procedures were recommended

and used to retrofit the cover-plated beams in Span 10 of the Yellow Mill

Pond Bridge. THenty-five of the cover plate details in· Span 10 were

treated. Of these, fourteen were peened and eleven were gas tungsten arc

(GTA) remelted. Figure 12 shows a transverse fillet weld after the gas

tungsten retrofit at each original cover plate weld. All retrofitting was

carried out under normal traffic with the dead load in place. A peened

weld toe at Yellow Mill Pond is shown in Fig. 13. The depth of indenta­

tion due to peening was approximately 0.03 in. (0.8 mm)

All cracks that exceeded 1-1/2 in. length along the weld toe were

spliced with bolted butt splices. Holes were placed in the girder web

directly above the crack., Fi-p;ure 14 shows typical bolted joints used to

splice across the crack locations.

4. POSSIBLE ADVERSE EFFECTS OF REPAIR

No adverse effects of repair and retrofit are expected in the case of

Yellow Mill Pond Bridge. The end welds of the cover plates should be

checked periodically in order to insure the integrity of the cover-plated

girders.

-58-

Page 62: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 12.

5. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

Cost of Investigation:

This is not available as a separate item.

Cost of Repair Rehabilitation:

The cost of the retrofit for the Yellow Hill Pond Bridge is given

by CONN-DOT as $28,825.00 for the original bolted splices.

Original Cost of the Bridge:

The original cost was $4,944,333.00 in 1958.

6. REFERENCES

(1) Fisher, J. W., Slockbower, R. E., et al. LONG THfE OBSERVATION OF A FATIGUE DAMAGED BRIDGE, Proceedings of ASCE, Journals of the T~chnical Councils of ASCE, Vol .. 107, No. TCl, April 1981.

(2) Bowers, D. G. LOADING HISTORY SPAN NO. 10 Yellow }fill Pond Bridge I-95, BRIDGEPORT, CONNECTICUT, Bureau of Highways Report, Department of Transportation, State of Connecticut, May 1972.

(3) Dickey, R. L. and Severga, T. P. MECHANICAL STRAIN RECORDER ON A CONNECTICUT BRIDGE Report No. FCP 45 G1-222, 1974.

(4) Fisher, J. W. Personal communication to the Bureau of Highways, Connecticut Department of Transportation, dated March 22, 1971.

(5) Fisher, J. W., Hausammann, H., Sullivan, M. D. and Pense, A. W. DETECTION AND REPAIR OF FATIGUE DAMAGE IN \.JELDED HIGHWAY BRIDGES National Cooperative Highway Research Program Report 206, June 1979.

-59-

Page 63: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Table 1: Insnection Historv

(Span 10) .

E"as t bound

Detail Dec. Nov. June Nev. 1970 1973 . 1976 1976

lES

2EP

2ES

3EP

JES

4EP

4ES

5EP

5ES

6EP

6ES

7EP

3HP

3WS

4 '\.,11'

·4WS

6HP

6i·:'S

X

X

X

c X

c X

NC

X

X

X

X

X

X

X

c X

c X

c v .. X

X

X

f! - Beam l~o. ·

X

cv X

c X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

E - East end of bea~ W - West end of beam

c cv NC

cv NC

cv NC

NC

X

NC

X

NC

cv cv NC

cv CV

cv NC

c NC

NC

.NC

cv

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

? - Primary co~er plate detail S - Secondary cover plate detail

NA - Not applicable R - Root Crack

-60-

I·Jestbound

Sept. Nov. 1977 1979

June Sept. Nov. 1976 1977 1979

X

X

X

X

X

X

X

X

X

X

X

X

c X

X

~c

c X

c c X

X

!iC

c NC

X

c X

X

X

X

X

X

X

X

cv R

c cv c

NC

cv NC

X

X

X

cv

cv c

1\C

cv cv c

NC

NC

x· NC

NC

NA

cv c

NC

cv NC

c NC

cv X

X

cv 'NA

X - ~o inspection

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

c X

cv c X

cv X

cv X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

NC - No indication of cn.cking C - Visual indication

of cracking CV - Crack verified by

ultrasonic inspection

Page 64: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I 0' I-' I

... ~_C!..!I~h -~D~~-~±_._:J.!!.:!::t..:(,,.,, ... ,.,i._..,, O.,POrtrnr,.lc..f f<t1n~\.olil•lre'lf"'ftii(I'TJ't),

1 ,, "' . ·~ <", ,_.I \'1 ,~ ''"" t l, 1<'!::~:~ .. -_::1'!.'.\ll\ .. ~~~' J'.J.·: ~'•l•ldnr,J ~>ecdfo.;d\i..,• ~" lli01h-tt etO.~••

~~~ ~: ~~~:2 :. ~-·.~ :!· .... ~.~·"·:.~ !:;.~:; :"; .~~c.i:~:;,',i~~.r::.::r ~~ ~~~~~~::~i~" """'"' u.,,,.,,,·,llt'lc.."'t

~'..!..!.!!!!::...l:!'.l.!..l" .. '''".:.~?i - ...... '"' ,,, ~A';;> I"" "see n •l:1,00op ... i.

L._•:·:.'-'..=..~2 u•.r•'··\" ~i~J~ \;;~~-~'r'::\;;,\:, -~...:;,;.:,'~ ~:;7e~'::~~~~.-~:1~ <off~": 1:~~.-f.o~;.'~~~~;,•

't:olr.• ~'' I ,,.; .. t, <;_,.,,.,,.,. -en!>u'.lcntf s;t • .;.o C.hto'"'''~ l"'l·.-·. n• ,..,.,,,1,,_. l•r H ... ~"..-c;.,, Prooo<t.!Ot>S. lh~ .-,.1.,.. 0 ( kot fo•l!'ll for\A ....,.., of

l..,,.,f <"••11.,.. -,f.,,c.l .. rn\ a."-d :-I ..roll "'nlc.h ftloe Or...,Qr(Hol"f"\1, '":,.\ 1rll('lard )• .... j ... • •·'"' ~Jo). ~.roG. (t·,, ........ ).

.J.!.: j~L!,J!~• .:::1 :::• ,,. : ... ,,. • ., rti,.,,.,...,.,ooo~ f'tl~ 'J>W'Io Ito l~'!o lhf\n HW~ .,..c.iho<ll 1 ~··•· ...... .,,.,,,,..,, ~n.,,t ... <o,hoil b~ ass'""•rl In L..o r. ... ros.

~~.t~.;i! .. !.,i;:r~:;;~~1·r.:~~;;;,:S:.~~~~~-;;·;::~·~-~ .. ~·~;;~·.'.~.~~~~,,;;;:~: ,.,.,,, . ._ t,,,.., ot tt ... ~'''"· ,.,,.._ 11\,. fonnl tnt-ol (&oor.ntoly .. ,u bot delcrrnllol"..d ,-i,,,,,,, • ~ ... ~ •. t\o•• cot ,,,.. "'""'' otc I

~~;;:;!ii:!/f;r:-7. :-~;~;~·-r~.-.;;~-;-r 1:~';.~J~~ :·~ ... ~~!~~~~rd.~~·;:~!~::...": .,,,..,,.~1 ,.,,,..,, l'h• {on...,l lotnl .._..,C1f'lil-t .. 111 he.,....,,~, ..-olo •• d dur;•'") ,. •• ., ........ ,.tll,.,. ..... ,.,,,,,,,

t:.::::r .. -J.~:; ·~ ~:-r;"=:;;!~~ .. :.';: -~ ~ ~~-;';~~~·~~··~~~.:. .~~;.;;~·~7~!.:~:·;,",~ ::;:,~: .; ~:~;, ~-:::...: ·~:ir;:: :;-~·:~ ::;:.~;··~··;~ · :;::·r :.·~.:.~~:~:::~.:~·~~:~.,':..

~·· ?" !",..,,.,..,, ln.r,to,-.., .. ,..,....,,<'It•..! nn 11'-'t pl"'n' otl.-i ,.,;n,,...,t~ W tn"-c.na\ ltvotoon"-1'',..•• Q hnlh:cl.i!>f>IW:c '"' n·-ucd.

[L[VIITION --;;;:;;r.sor-

UMn 1--,---c--;-:--;.;-;--7.":-;:-------j-~

t),,ll.-d ~.,hc_,.(i.>roi"Q' 1<••.-r f"lnt<r\ i". -~~l~-:,-~ • .-~i;:;(~N-;~.~c:-;;, 1':,0.J1el -- r;:­(tw-"7.:~::--·------------- £A.'

-~:·<::·.r._ s.·''': .~

.!.~.,,.,-~ ~:-.•:._~~· """'•:::·'''--''-'-"'-L..::.:C:._..J

Fig. 1 Plan and Elevation of the Yellow Mill Pond Bridges

CONNECTICl r•£PARTM£"Jf OF TRANSP(

fJfliDG<:,>(Jij

INftRS1'ATE ROt•

Page 65: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I 0> ...., I

o Not Inspected + No Crack o Crock Not

Verified· By U.T x Crock Verified

<f> Small Crack N Verified by U.T

ot

(1977) .

W.B.<:=

Be a m7

iG

Cover plate 5

Beam 4

3

Cracks 2

~ ~ -.l M83 M84

I - <I NB4

I " : I N84 ,~

~I N84

I " I .. , I NB~

-

I _1 "J 1.486

N84

I I

~ :1 NB-4 ,~ :t N84

I" ~I N84

I r I M8<4

I~ s91 I 992

Secondary Det01

il I U I N88 ., t-- Br . Pier.

I I 1_1 "I I I I I I I I I:

"' I I I: 1 I ,. l I' I I - -

I I L J I I I . l : I I I I ,.

I 'I I I [ I I I I : I.

' I ,. " r I I

. Faacla Line <t Brg. Pier

Fig. 2a Plans of Inspected Details in Span No. 10, Yellow Mill Pond

-62-

Be om I

2

3

4

5

6

E. B . =>

Page 66: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

/ I ' /

2 ~--- 12 ---1---- 12 ------1---- 12 vor ies

' , 1---+--------t-5 spa. at 8 0- 3/4--1---------+--+-

• ~ 6 • •• ~ • . . . · ...

Intermediate diaphragms shown End diaphragms shown at pier

: r.

Fig. 2b Typical Expressway Cross-Section (Eastbound)

-63-

Page 67: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

SYMM. ABOUT 'f. BEAM

<t_ BEARING -J 1------- 56' s" ---------:I 1----- 32' 6"---{

36 WF 230

b

I R-I e.

rdl: STRAIN r------

GAGE

\

SEAM 3 WESTBOUND (M84)

Fig. 3 Details of Beam and Strain Gage Location

-64-

Page 68: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Rolled Flange

Web

(a) Primary Detail

Rolled F Ionge

Web

(b) Secondary Detail

Fig. 4 Cover Plate Detail at Yellow Mill Pond

-65-

Page 69: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 5 Cracked Girder 4 in Span 11 Eastbound of Yellow Mill Pond

-66-

Page 70: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

ll'vV4-E

Fig. 6a Typical Large Crack at Weld Toe at End of Cover Plate

Fig. 6b Smaller Crack at Weld Toe of Co~er Plate

-67-

Page 71: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I 0' co I

Front

Detail 3WP

Front

Detail 7WP

Full Scale

Fig. 6.c Crack Shape for Beams 3 and 7, 1976 (Eastbound Span 10)

Page 72: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

(/) 70

f-z w >

60 w (/) 50 (/)

w a:

40 f-(/)

..J 30 <t f-0 f- 20 l.L 0

~ 10 0

0 0.6 (4. I)

80 -(/) 70 -f-z w 60 -> 2 w (/) 50 f-(/)

w I a: f- 40 f-(/)

..J <t 30 '-f-0 f-

l.L 20 -0

~ 10 -0

0 I

0.6 (4.1)

1.05 (7.2)

1.50 (10.3)

1.95 (13.4)

2.40 (16.5)

2.85 (19.7)

Stress Range Off Primary Cover Plate,

3.30 3.75 (22.8) (25.9)

ksi (MPa)

4.20 (29.0)

Fig. 7 Stress Range Histogram, 1971 Eastbound Span 10 ·

3

5

.

I

1.2 (8.3)

I ~ 1.8

(12.4)

J 2.4

(16.5)

CBEJI On Primary Plate, Off Secondary c:=:J On Flange, Off Primary Plate

3.0 (20.7)

v --. CD 0 oo -: C> ooooo I ooooo

1 oooooo

1oooooo

1

3.6 (24.8)

4.2 (29.0)

4.8 (33. I)

5.4 (37.2)

Stress Range At Various End Of Cover Plate Locations, ksi (MPa)

Fig. 8 Stress Range Histogra::-,, 1971 ;,'estbound Span 10

-69-

Page 73: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

50 -

(/) • ADT "0 c 0 0 ADTT (/)

::J 40 0 ..c -0

z <t 30 (L (f)

I z --..! 0 0 I ._

20 0 <t

>-<{

3: .I

w 10 z 0

I I I I I I I I 58 60 62 64 66 68 70 72 74 76

YEAR Fig. 9 One-Way ADT and ADTT on Span 10, 1958-1975

Page 74: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

.&J

--'0

" .Q ... 0 ..

.Q 0

>-00 ... " c: w

.&J

'0 41

.Q ... 0

"' .&J 0

>-0' ... 41 c:

UJ

(

100

90

80

70

60

50

40

30

20

10

0 -150

80

70

60

50

40

30

20

10

0 -150

A-24 Materi I

This erles wa removed v from the flan e

I I

I 1/

xj I Vx

/ v 8

-100 -50 0 50 100 150 200 250 300 350

Test temperature, °F

Fig. 10 Charpy V-Notch Test Data for Beam Flange

A-242 Material

This se ries was removed

from 1 he web v /

I v X

I

I 1/:

:; ...-----. v A

r-

-100 -50 0 50 100 150 200 250 300

Test temperature, °F

Fig. ll Charpy V-No tch .1es t Data for Beam Flange

-71-

Page 75: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

• >. -~ .... .: :.... ..

. . ~-·- ... ,.

~-:~,: ... - .....

../

Fig. 12 Gas Tungsten Arc Remelted Weld Toe

Fig. 13 Peened Weld Toe

-72-

Page 76: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I --..)

w I

1 J

-~ --- " -- - ~ - - -----

~PL I( [ PLAT[

'5cnl< of"·•'<f Z'·J'

n s,...e r.·~z'·l·

£1_[V .. l10N ~colr tf•t'O"'

- - - -

If, ~~i ; li111'1o.Js.lh~!.

~I~~--~~ '0 . r I ···-+- -<r 1 r Vorle• V\ ..; -- fl\--~1-l'--"fl--fl-4'--fl-

r!L L PLATE --Seol•tf,ff"'

BOLHO ::PUC[ 5 roR W~6-l( Zf\0 GIRDERS

'::J((OUDAfH (IJVlR PLAT[

!

I I

I

FILL PL'\% 5cot. ,[.,~

[L[ V .. liON ~coW 1f•l'd

~PLI(r PL .. Tr 'Sc.al~ t[·I"'•

5(Cl.ION [-[ ~le3'r1'.o-

BOLltO SPLICES fOR W36XZ•~ GIRDERS

PRIUAR'f' COVER PLAT'=

I FOr Mat.• .... !!muc.turt '!titwpt ..ao.s CONNECTICUT

DtPARTM!NT OF TRANSPORTATION ORIOGE_PORT

INTERSTATE ROUTE 95 0 V[R

YELLOW MILL POND

SUPERSTRUCTURE REPAI~

BOLTED SPLICE DETAILS I

IMI rtrJ,_.UIOtl, •tt\10111( Ul!.UfD OUIIIfiTIU Of' fNQrN[[It Bridqe Oe!L1qn u.ut WQII SHOW• Otl lM11f Sllf(IS IS IA"JD Otl l1•11ID 111TIS

DtSIO't£1'1 w.r-:c. (lfii.VT$MAN F.T.R Jott~t[lt H\rt<-f!C:.t.IIOIS I>' hi( tilT( lolllto IS 1t1 tiO _.AT WUUitiiO It IIIOfCAit TMI UU( tt'liltNUntr' 0t1 -tl\lit OVUIITIU 01 NO D'IT( O£SCMtTION Al"f""'\'fO '-""-(.;)

\...._ _____ OAT[ ; ,, ..

Ollti11U110'1 w ouuutlts " won •una. nt I(

I -· I ltfOI.MI(O. AEVISION!Ii ST'"-'CTUM. NO. 15·1Z.1..,")1)1151\ "' .. e

Fig. 14 Retrofit Details of Bolted Splices

Page 77: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

4. WEB CONNECTION PLATES

Cracks that have developed in the web at lateral connection plates

have generally occurred as a result of intersecting welds. One of the

first bridge structures to exhibit this cracking was the Lafayette Street

Bridge over the Mississippi River at St. Paul, Minnesota. A summary of

the crack development is provided hereafter (I.D. 6). The primary problem

was the large defect in the weld attaching the lateral connection plate to

the transverse stiffener. Since this weld was perpendicular to the cyclic

stresses, and the weld intersected with the vertical welds attaching the

stiffener to the web and the longitudinal welds of the connection plate,

a path was provided into the girder web.

Similar cracks formed in at least five other bridge structures with

similar intersecting welds (I.D. 39, 51, 61, 87). In two of these cases

the cracks were discovered before the girder flange was cracked in two.

Cracking was also observed in two other bridges where the lateral

connection plates were installed on each side of the transverse stiffeners.

(I.D. 33 and 63). This often provided an intersecting weld condition

between the transverse stiffener welds and the longitudinal welds attach­

ing the connection plates to the girder web. Since no connection was

provided between the lateral connection plate and the transverse stiff­

eners, out-of-plane movement occurred in the web gap or at the intersect­

ing welds. Tne resulting high cyclic stress conditions in the web caused

vertical cracks to form in the web. This mode of cracking is shown in

Fig. 58 of Ref. 2.

-74-

Page 78: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

4.1 FATIGUE/FRACTURE ANALYSIS

OF

LAFAYETTE STREET .BRIDGE

-- A Brief Summary --

I. D. No.

Town/City/etc.

Railway/Highway/Avenue/etc.

State/Province

Owner

-75-

6

St. Paul

Lafayette Street

Minnesota

Minnesota DOT

Page 79: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 1

1. DESCRIPTION AND HISTORY OF THE BRIDGE

. Brief Description of Structure:

The Lafayette Street Bridge spans the Mississippi River in St. Paul,

Minnesota. The main channel crossing consists of two parallel structures

composed of two main girders extending three spans over the Mississippi

River with the central main span (Span 10) of 362 ft. (110 m) and side

spans of 270 ft. (82 m) and 250 ft.-6 in. (76 m) (see Fig. 1) correspond­

ing to Spans 9 and 11, respectively. These continuous main girders extend

beyond piers 8 and 11 as 40 ft. (12 m) cantilevers. The transverse cross­

section consists of two main girders connected by transverse floor beams

and by transverse bracing, as shown in Fig. 2. The transverse floor beams

support two stringers.

The web and flanges of the main girders were fabricated from ASTM A441

steel.

Brief History of Structure and Cracking:

The Lafayette Street Bridge was opened to traffic on November 13,

1968. The southbound lanes were closed between May 20, 1974 and

Octobe~ 25, 1974 for repairs to the deck and overlays.

On May 7, 1975 a crack was discovered in the east main girder of the

southbound structure in Span 10 (see Fig. 2). Figures 3, 4 and 5 show the

crack developed in the main girder web and the lateral bracing gusset

plates.

-76-

Page 80: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 2

2. FAILURE MODES AND FAILURE ANALYSIS

. Location of Fracture Failure Mode(s) and Stages: ·

The crack occurred in the "east" girder of the southbound lane in

Span 10, 118 ft.-8 in. (36m) from pier 10. The web crack had propagated

to within 7.5 in. (19 em) of the top flange when it was discovered on

May 7, 1975. The entire bottom flange was fractured (see Figs. 3 and 7).

A d '1 d d (l' 2) d . 1 . . f f d . eta1. e stu y · an v1.sua exam1.nat1.on o racture port1.ons

of the girder web, flange and the gusset plate of transverse bracing indi-

cated that fatigue crack growth originated in the weld between the gusset

plate and the transverse stiffener as a consequence of a large lack of

fusion discontinuity in this location (see Figs. 3, 5, 6 and 8). The

fracture surface of the web shows that a brittle or cleavage fracture

occurred after the fatigue crack propagated into the web through the

gusset-stiffener weld. As can be seen in Fig. 7, the cleavage fracture of

web continued and also extended down into the bottom flange, and conse-

quently _the entire bottom flange was broken (see also Fig. 8) .

. Cyclic Loads and Stresses (Known or Field Recorded):

The estimated average daily truck traffic (ADTT) crossing the bridge

was 1500 vehicles during the period November 1968- May 1975. Thus,

approximately 3,300,000 trucks crossed the bridge prior to the time the

crack was discovered.

Stress range histograms for the main girders and other structural

members are not available. However, the root-mean s·quare stress range was

-77-

Page 81: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 3

approximated from the gross vehicle weight distribution in Ref. 1. A

standard HS20 truck is used to generate a moment range in the main girder

which varied from +3.814 ft-kips (+5.172 kNm) to -1.622 ft-kips (-2.199 KNm).

This results in a stress range of 4.68 ksi (32 MPa) in the girder flange

and 4.13 ksi (28 MPa) at the gusset-web connection. A few strain measure­

ments were acquired on the main girders near the fracture during passage

of an HS 20 type truck and resulted in a stress range of about 2 ksi

(14 MPa).

Temperature and Environmental Effects (Known or Field Recorded):

During the winter prior to May 7, 1975 the temperature at St. Paul,

Minnesota was recorded at -8° F (-22° C) on March 13, 1975 and on

February 9, 1975 the temperature in St. Paul reached -22° F (-30° C).

Material "Fracture, Mechanical and Chemical Properties"

in the Failure Regions:

Four pieces (i.e. from I to IV, as shown in Fig. 3) of material from

the flange, web and gusset plate were removed and tested (see Refs. 1,2).

Charpy V-notch tests, tensile tests and chemical analysis were performed.

The results are given in Fig. 9 and Tables 1 and 2. In addition, a few

compact tension tests (KQ) were conducted on the web plate.

The web plate was ·observed to satisfy the fracture toughness require­

ments of the 1974 AASHTO Specifications for Temperature Zone 2 [15 ft-lbs.

(20 Nm) was reached @ 15° F (-9° C) for the web material]. The flange and

the gusset plates, however, met the requirements of Temperature Zone 1.

-78-

Page 82: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 4

The flange and web plate show correspondence with the requirements of

A441 and the gusset plate with A36 steel.

• Visual and Fractographic Examination of Failure Surfaces:

The fracture surfaces of part of the web, flange, and gusset plate are

given in Fig. 5, 6 and 7. From these photographs, it can be seen that

the transverse and longitudinal single bevel groove welds that connect the

gusset plate to the transverse stiffener and web did not penetrate to the

backup bar on the root of the weld preparation. This resulted in a signi­

ficant lack of fusion.

Further visual examination of the fracture surface indicated that

fatigue crack growth initiated in the weld between the gusset plate and the

transverse stiffener as a consequence of the fusion discontinuity mentioned

above. The fracture surface of the weld indicates that mainly a cleavage

or brittle fracture occurred in the web after the crack had propagated into

the web through the gusset-stiffener weld. This cleavage or brittle frac­

ture extended down the web and into the flange (Refs. 1,2).

Fractographic examination of failure_surfaces at several locations by

the transmission electron microscope eorroborated the conclusions of the

visual examinations (Ref. 1,2).

• Crack Growth (initiation and propagation) and Probable Causes of

Fracture/Failure:

The primary cause of failure (Ref. 1,2) is the large lack of fusion

discontinuity in the weld between the gus~et plate and the transverse stiff­

ener near the backup bars. This resulted in a fatigue crack initiation

-79-

Page 83: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 5

in the web at the point of the gusset-stiffener-web intersection which

later created essentially brittle fracture in part of the web and the whole

cross section of bottom flange of the "east" girder. Probably, the brittle

fracture of the web occurred during either one of the recorded cold days

on March 13, 1975 and February 9, 1975. Thus, both fatigue and brittle

fracture cracks were observed. The crack surfaces showed several stages of

crack growth (see also Ref. 1,2).

Final fracture of the web occurred as further fatigue crack growth

and yielding of the gusset plate occurred which permitted the crack to open.

This eventually led to the final girder fracture.

3. CONCLUSIONS/RECOMMENDATIONS

• Conclusions Regarding Fracture/Failure:

The fracture of the "east" main girder of the southbound lane of the

Lafayette Street Bridge was due to the formation of a fatigue crack in the

lateral bracing gusset plate to transverse stiffener weld. This fatigue

crack originated from a significant lack of fusion region near the back-up

bars. At the failure gusset. this groove weld intersected the transverse

stiffener-web weld and thus provided a direct path for the fatigue crack

which penetrated the web. Subsequently this fatigue crack precipitated a

brittle fracture of part of web and all of the tension flange (see Ref. 1,2~

• Procedure u~ed for Repair/Fracture Control:

If other fatigue cracks are removed or properly·arrested, the material

used in this structure will provide adequate resistance to brittle fracture.

It is very probable that other discontinuities due to lack of fusion exist in

-80-

Page 84: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

other similar transverse stiffener-gusset plate welds in the two bridges.

Therefore, all gussets located in the regions of cyclic stress range and

tensile stress should be properly treated to prevent (and to detect) any

fatigue crack growth into the girder web(l, 2),

The scheme used to retrofit the structure is given in Fig. 10. Two

vertical holes 1.25 in. (32 mrn) were cut into the gusset plate and ground

smooth at the corners of the gusst-transverse stiffener-web interface.

Additionally, two smaller vertical holes were drilled through the gusset

plate and ground smooth at the tips of groove welds which join the gusset

plate to the transverse stiffener. In the first set of holes [1.25 in.

(32 mm)], the web surface and the gusset should be carefully inspected by

6

a dye penetrant after the material is removed. If no crack indication is

observed, then the detail can be regarded as adequate. Otherwise, additional

holes were to be cut into the girder web with a 1.25 in. (32 mm) hole saw

on the two diagonal lines from opposite sides of the web surface, as shown

in Fig. 10. After these plugs are removed, the holes should be ground

smooth and the exposed web surface checked with dye penetrant to insure

that the web crack does not extend beyond the holes. The holes should be

ground smooth before the area is painted.

A suggested redesign for the type of the "gusset-transverse stiffener­

web" connection is given for future use in Refs. 1 and 2.

4. POSSIBLE ADVERSE EFFECTS OF REPAIR

No adverse behavior of importance is expected. Some cracking may

develop in the isolated transverse welds between the holes in the gusset

-81-

Page 85: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 7

After the repairs there was a slight sag_observed in the south facia

girder at the location of the original fracture (Ref. 3). According to

the Minnesota-DOT the repair did not have any significant effect on the

load-carrying capacity of the structure (Ref. 3).

5. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

Cost of Investigation of Fracture:

The cost of investigation of the brittle fracture developed in the

girders of the Lafayette Street Bridge is estimated by Minnesota-DOT as

$14,620.00 (Ref. 3).

Cost of Repair/Rehabilitation:

The total cost of repair/rehabilitation, excluding the costs for

investigation, is given as $161,120.17 (Ref. 3).

Original or Adjusted Cost of the Bridge:

The original cost of the bridge was approximately $4,750,000.00

according to the Minnesota-DOT (Ref. 3).

6. REFERENCES

(1) Fisher, J. W. Pense, A. W. and Roberts, R. "Evaluation of Fracture of Lafayette Street Bridge," Proceedings, ASCE, Jour. of Struct. Div. Vol. 103, No. ST7, July 1977, pp. 1339-1357.

(2) Fisher, J. W., Pense, A. W. and Roberts, R. "Investigation and Analysis of the Fractured Girder in Bridge No. 9800, T.H. No. 56 Over Mississippi River in St. Paul, Minn.," Minnesota Department of Highways (Materials, Research and Standards), October 1975.

(3) Personal Communication from K. V. Benthin, Bridge Engineer, Minnesota-DOT to J. W. Fisher, Lehigh University, dated March 11, 1980.

-82-

Page 86: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

TABLE 1.-Physicel Properties

------------ ··--Property ... -·=c· Fl~nge (A441) Web (A441) lGusse~A36j.-

(1) (2) (3) (4) ----------~--------------

{a) Mechanical ------·-------------- ----Thickness. in inches {milli- 2-1/2 1/:! 1/2

lllctcrs) {M) ( 13) {13)

Yield stress. in kips per 46.0 53.7 37.') square inches {meganew- {317) {370) {2(>1)

tons per square 111ctcr) Tensile strength. in kips per 7n.2 X 1.8 f.7.0

square inch (meganewtons {52.~) (51'.4) (462)

per square meter) Elongation. as a percentage 32.1! ~0.0 36.4 Reduction in area, as a per-

cent age 65.8 68.0 67.1

{h) Chemical

c 0.19 0.23 0.25 Mn I. 18 1.17 0.!!7 p 0.046 0.024 0.()31!

s 0.030 0.044 0.03R Si 0.23 0.14 0.06 Cu 0.25 0.18 ILOif. Va 0.046 0.032 O.IX14

TABLE 2.-K 1c Fracture Tests

====;;====·==r==~-===;===;:==-==-=--= .. :..-=-=== .. :o..;.-=.~c=·; Test Crack

Speci- temperature, depth, u;. Failure K v• in kips per square men in degrees in inches load P0 . in inch ymch (rnega-num- Fahrenheit (milli- pounds newtons per square ber (Celsius) meters) a/"' (newtons) meter per meter 3/2) (1) (2) (3) (4) (5) (6)

------~----------~-------+---~-+---------!----------------1 o• <-IX·> 1.20 0.480 s.X75

(30.5) (26,133) 2 -25" (-32") 1.20 0.4RO 6,850

(30.5) 00.470) 3 -120° ( -84°) 1.23 0.491 4,300

()1.2) (19,127) 4 - 150" (- I 0 I") 1.24 0.496 4.850

(31.5) (21.574)

-83-

61!.0 (74.K)

79.3 (87 .2)

51.3 (56.4) 58.6

(64.5)

Page 87: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I OJ

Fig. 1

ELEVATION

The Lafayette Street Bridge (three main spans and neighboring spans)

Page 88: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

A

r e-r------n n

j__ 210' _j ____ _2.6_2_' ____ ---J_, __ 2_5_o_'-_s_"----~1 Pier 8 Pier 9 Pier 10

--W21 x62

Fig. 2 Schematic of Span and Cross-S·ection

I v

1

i I I ! I v

/' i

I \

\ \ \ \

I \ I

I

~ I i ,,, . \: ;.\

'Nee, ~:::;:;! : ~ '·: ·~, 1

1 G~.:s!a:- ::::g : """".... , :

~::{/ ---.; ... ·. •,'

I

~ 1 I

' ,/

/',

/'

-'

; :;·' r. 2 ':,- .J

Fig. 3 Schematic of Girder Showing Crack and Sections ~emoved for Examination

-SS-

Pier II

Page 89: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I co c' I

Fig. 4 Cracked ~irder of Lafayette Street Bridge

.' .

I.

----------------------------

Fig. 5 Fracture Surface of Gusset-web Showing Lack of Fusion - Piece II

Page 90: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

~ ·-: .;. · ... -~~ -· /'. .. ~.,;~· ,.r-;

.,

Fig. 6 fracture Surface of Gusset to Stiffener Weld and Adjacent Web- Piece

Fig. 7 Fracture Surace of Web-Flange Boundary

-87-

Page 91: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

"

Stage :2:: Brittle

of Remaining Web

Stags I!Z: Fati~ue Crock Growth

1 in Web and Gwsset

Stoge II: Fatigue/\ Crock Growth j \

I I

Stege I: Initial --J

Cr::Jck

Stege m: Brittle Fracture of Lower Web ond Flange

Fig. 8 Schematic of S.tages of Crack Growth in Gusset, Web, and Flange

-88-

Page 92: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

II ll J ......... , ....... ----, -·-- ---- , .. -· -···-----.- .. --···· --,-- -. --·-··r·--

Ull IIYF..fl[ Sl _(l!llnr:r. >< ~ J(l )( --· .. -·-- -· .. -· -- -·-. )(

,,, Sl rfllll. IIINN ' on

I I·Jf.l1 lo.. ){)

,. J f,f) 1.11 Ill fV ~j(l ( _) r I) fll ·10 (I_

>­c..'J

J(J

l:i ?0

10 / )(

~i')(

IIJO

91J

rn -' no

I 1-

''- 70

Cl GO I.LJ UJ o-: :;o CJ U)

-If) !'lJ n: >- 30 u 0:::

20 LLJ 2 lLJ

10

- ···-··-·--,--- --,-- -···---~-·-·--- -, ---·. --- I

'"nr.~rt:!JE:_ ~L nJl_l m;£: __

S T l'n111_ Ill NN

n.nNcc

)(

){----

If /---- ------.

If

I .. .,

0 - --~=~-:j~H --~_J ________ L. _____ _I _______ I ____ L ____ . _____ _ 0 __ ____t_ __ __L ____ t ______ _l _____ .I ____ ----- I __ ------·--'------·-·

· ltJO - :!11 fl :!0 I 00 . I :Jr J ?00 7.:;0 -50 0 50 I flO I :10 2110 250 Jllll ToO

ru-~1 n:r·wnm rum:: 1 on; F 1 lEST lHIFFJ~nT UHF r DFG F l (a) Flange (b) Web

00 )(

(TJ ST rnt.n_ I liNN __ J

I 70 GUS5F.:I 1--

;;-- ----·-------·--···------···--!(

)( " lo_

r;o r:l ld :;o OJ n:: u

-10 U) 1:0 cr:

JO >-u o::: ?.0 )(

lLJ 7 LLJ to

)(

0 ------'----'---·-'---1.----· L---- --'------'--··--·--·---5(1 IJ 50 I 00 I :JO 200 2:JO .100 J:ifl

TEST TEMPEF:nllJRE ( fJ[G F l (c) Gusset

Fig. 9 Charpy ~-Notch Test Results

Page 93: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I ! ! /Grind Smooth

cr===f ====::=: Section 8 - 8 Section A- A

/ ' . '.~ ., ..

' , ' ,.;,;;1..._"-.. --v

~~,!·!·!·~·I·!·I·I·!·~CC·~·l_C:··:.~/~/~-~~:(,~~ .,

L~h" c,t I "4 in Hcles / s-1 I through Web N . when ar1y disc~ntinuity tj is detected in Web tj

~ ~ N,

Fig. 10 Preferred Procedure for Corrective Action

-90-

Page 94: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

5. TRANSVERSE GROOVE WELDS

}~ny groove welds placed into bridge structures were not well executed

and inspected during the initial applications to welded structures in the

late 1940's and 1950's. This lack of quality control resulted in large

lack of fusion defects, slag, and other discontinuities which have led to

fatigue crack growth and fracture.

At least four different types of groove weld details have experienced

crack propagation. One such condition was found to occur in the Aquasabon

River Bridge in Ontario (I.D. 5), where a rolled section was haunched by

welding in an insert plate. This resulted in a short .length of vertical

groove weld perpendicular to the stress field. An embedded discontinuity

and the poor quality of the detail resulted in crack propagation.

Cracks have been found in the flange and web splices at groove welds

in at least four bridges (I.D. 23, 49, 65, 82). The flange groove weld

cracks detected in the Quinebaug Bridge appear comparable to those

observed in the Aquasabon River Bridge. Fatigue crack growth developed

from large unfused region of the weldment.

In two of the structures, cracks were found in the groove welded

splices of A514 steel tension members (I.D. 23, 49). In both cases,

part of the cracking was traced to weld repairs. Other cracks were found

to be related to cold cr~cking which was apparently not detected at the

time of fabrication. These structures were fabricated during the period

1969- 1973. Only the cracks found in the 124 Bridge (I.D. 23) were found

to have experienced fatigue crack growth. No evidence of fatigue crack

-91-

Page 95: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

extension was detected in the Silver Memorial Bridge (1.D. 49) nor the

Fremont Bridge (1.D. 65).

Comparable cracks have been observed in the weld of groove welded

cover plates. These welds were used to splice two different thickness

plates which were then attached by fillet welds to either rolled sections

or to riveted built-up girders. Four different bridges are known to have

developed cracks at such details (1.D. 47, 69, 70, 90). A review and

summary will be given of the cracking that developed in the 111.51

Bridge at Peru (I.D. 70).

A third kind of groove welded detail that has experienced cracking

occurs at splices in continuous longitudinal stiffeners. These attachments

were considered secondary components, and no weld quality control was

imposed on the groove weld splice. The first such structure to experience

cracking at this detail was the Quinnipiac River Bridge near New Haven,

Conneticut (I.D. 4). A summary and review of this structure is provided

hereafter. At least three other bridges have developed cracks at such

splices (I.D. 12, 30, 95). One of these structures developed a crack

during a cold winter prior to being placed into service. In every instance

of cracking, no weld quality control was imposed on the longitudinal

stiffener splices. Some of these were in tension zones. As a result,

cyclic stresses resulted in crack propagation from large defects, and

these eventually resulted in fracture~

The fourth groove weld detail that has resulted in cracking is the

electroslag weld. The fracture of an 179 bridge flange at Neville Island in

1977( 3) has resulted in detection of significant flaws in at least five

-92-

Page 96: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

other bridge structures. Except for the 179 structure, all discontinu­

ities in the electroslag welded bridges were detected and retrofitted

before significant crack propagation developed. The electroslag welds

were found to have a lower level of fracture toughness than implied from

qualification tests. Furthermore, detection of the fabrication discon­

tinuities was found to be difficult and not reliable. As a result of the

179 failure and these other experiences, electroslag welds are not per­

mitted in tension components of bridge structures(4).

-93-

Page 97: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

5.1 FATIGUE/FRACTURE ANALYSIS

OF

I.D. No.

Town/City/etc.

AQUASABON RIVER BRIDGE

-- A Brief Summary --

5

Railway/Highway/Avenue: Highway 17 (Trans-Canada Highway)

State/Province . Ontario, Canada

Owner Ontario Department of Highways

-94-

Page 98: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

FATIGUE/FRACTURE ANALYSIS

OF AQUASABON RIVER BRIDGE

-- A Brief Surr~ary --

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief Description of Structure

-1

The Aquasabon River Bridge is located on the north shore of Lake

Superior on Highway 17 (Trans-Canada Highway) 130 miles (210 km) east of

Thunder Bay, Ontario. The structure was completed in 1948. The three­

span continuous beam structure has a composite steel beam-reinforced con­

crete slab. It was designed by the Ontario Department of Highways to

accommodate an H20 truck load.

The 200 ft. (61 m) structure has three spans of 52 ft. 5 in. (16 m)

80 ft. (24.40 rri) and 51 ft. 2 in. (15.60 m)as shown on Fig. 1. The super­

structure consists of four longitudinal 33 in. (84 em) WF girders con­

nected to 15 in. (384 mm) transverse floor beam stringers. The steel

structure supports a 7 in. (178 mm) reinforced concrete deck. The main

girders are haunched at both piers and abutments. These haunches •-vere fab­

ricated by cutting the bottom flange from the web fillet and welding a

parabolic insert plate into the web which resulted in a 51.25 in. (1.30 m)

deep section at the piers and abutments (see Fig. 2).

The main girders were field spliced at two points in the center span

22 ft. (67 m) from each pier as shown in Fig. 2. The splice points were

placed at the points of dead load contraflexure. The riveted splice con­

sisted of 5/8 in. (16 nun) flange plates on interior and 1/2 in. (12. 7 mm)

-95-

Page 99: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

plates on the exterior girders. All had two 3/8 in. (10 mm) web plates

for shear splice.

The reinforced concrete floor slab was connected to the girders by

channel-type shear connectors of 11 in. x 3 in. (275 mm x 75 mm) welded

at 1 ft. 6 in. (0.457 m) intervals as shown in Fig. 2.

Brief History of Structure and Cracking:

The Aquasabon River Bridge was completed in 1948. In 1963, cracks

were discovered at the vertical butt weld detail in three of the six

haunch inserts of the north interior main girder as shown in Fig. 2b.

(Ref. 1). One of these cracks extended 44 in. (1.12 m) into the girder

web along a diagonal line starting from the vertical butt weld detail.

-2

In 1973, the structure was subjected to rigorous testing to determine

its safe load-carrying capacity. Prior to the 1973 tests, dye-penetrant

and magnetic-particle inspection techniques were used on the repaired and

other 21 remaining original welds. As a result, four other weld cracks

were discovered. The location of individual cracks are marked on Fig. 1.

One of these cracks is shown in Fig. 3.

-96-

Page 100: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

-3

2. FAILURE MODES AND FAILURE ANALYSIS

Location of Fracture, Failure Modes and Stages:

The fatigue cracks that developed were in the main WF girders and are

identified in Figs. 1 and 3 (Ref. 1). These cracks propagated from large

initial weld imperfections or inclusions in the short transverse groove

welds at the ends of the parabolic haunch inserts in the main girders (see

Figs. 3, 4, 6 and 7). Of 24 welded details, seven failed. By 1963, three

of the six haunch inserts in the north interior girder had developed

cracks. These were repaired by welding cover plates over the cracks.

By 1973 four more welded details developed cracks. One of the cracks pene-

trated 7 in. (178 rnm) up the web beyond the 2.5 in: (64 rnrn) transverse

weld and had cracked about 65% of the bottom flange (Ref. 3). With large

imperfections residing near the bottom of the web, crack growth developed

in the web and then into the flange as a part circular crack, as sho~m in

Fig. 4. The enlargement of this crack extended it into the flange and up

the web. After the crack penetrated through the flange, most of the

fatigue resistance was exhausted. All cracks were discovered before the

flanges fractured, because the details were located near the contraflexure

points where the dead load stress was small. The stages of crack growth

are indicated in Fig. 4.

Cyclic Loads and Stresses (Kno~~ or Field Recorded)

A rigorous field testing of the Aquasabon River.Bridge was conducted

in 1973. Two fully loaded vehicles each \-lith the gross vehicle weight

GVW = 197,000 lb. (89,360 kg) distributed on five axles carrying the minimum

payload of 153,000 lb. (69,400 kg) were used. The payload can be placed

'i'Jm7 JZM•~_J\\1~~ -97- · SIMOiv\i<i-1'11 i.i~

Page 101: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 -4

on the semitrailer to produce any tandem axle weight up to 110,000 lb.

(49,900 kg). These loads were applied in four increments, while stresses

in critical areas were monitored. Pier settlements were also measured.

Dynamic strains were recorded with the test vehicle loaded to a gross

weight of 91,000 lb. (41,280 kg). The vehicle crossed the bridge at vary-

ing speeds between 30 to 40 mph (48 to 80 km/h). Based on the dynamic

strain measurements and traffic conditions, a representative stress range

histogram (S ) was determined (see Fig. 5). r

The Stress Range Histogram was used to estimate the effective root-

mean-square stress range SrF~s· If all stress range conditions above

0. 85 ksi (5. 9 MPa) are considered, this results in S rRMS = 1. 92 ksi

(13.2 MPa). The effective stress range using Miner's rule was equal to

SrHiner = 1. 85 ksi (12. 76 MPa).

A sample of vehicles crossing the bridge indicated that each vehicle

produced from six to seven stress cycles.

Temperature and Environmental Effects (Known or Field Recorded)

It appears that temperature and environmental effects were not signi-

ficant factors in the development of cracks in the short transverse groove

welds of the Aquasabon River Bridge. The examination of the crack surface

and the weld detail indicated that the cracks were stable fatigue cracks.

This is reasonable considering the low dead load at the inflection

points. As a result, the maximum stress was small, and this permitted the

development of large fatigue cracks without brittle fracture

-98-

Page 102: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Haterial "Chemical, Hechanical a:1d Fracture Characteristics"

Analysis on the Failure Regions:

-5

Web cutouts, taken from the weld failure zones as shown in Fig. 6 and 7.

were analyzed to determine their chemical composition. The material used

in the bridge is A7 steel base material. The chemistry checks provided

0.24% C, 0.74% Hn, 0.09% Si, 0.01% P and 0.03% S. The fracture toughness

characteristics of the base material was not determined.

Visual and Fractographic Analysis of Failure Surfaces:

Visual examination of failure surfaces indicated that stable fatigue

crack growth developed from imperfections in the transverse groove weld

(see Fig. 6). The surfaces examined were coated with oxides suggesting

that the crack surfaces were exposed for a considerable period of time.

No fractographic examination was carried o~t with the electron microscope.

Crack Growth (Initiation and Propagation) and Probable Causes

of Failure:

An examination of fracture surfaces indicated that the cracks in the

Aquasabon River Bridge were stable fatigue cracks. There was no

evidence of brittle fracture (Ref. 2). The fatigue cracks originated at

large weld imperfections in the short transverse groove welds at the end

of the haunch inserts in the main girders as shown in Figs. 2, 3, 4 and 6.

The crack growth (Ref. 2) developed in two stages as shown schemati­

cally in Fig. 4. The first stage corresponds to the growth from the large

inclusions in the transverse groove welds. The fatigue crack continued

-99-

Page 103: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 -6

to grow and propagated into the flange and up the web. During the second

stage, the crack grew as penny-shaped circular crack through the flange.

The crack eventually developed into a through crack in the flange.

For the crack sho\vn in Fig. 6 it was estimated that the effective

stress range was SrRMS = 1.92 ksi (13.2 MPa) which occurred about

1,340,000 cycles each year. Approximately 3.5 years would be required

before the crack penetrated into the bottom· flange during the first stage

of growth. An addition twenty years would be required before the crack

propaged through the thickness of the flange. The results of the analysis

are in good agreement with the actual field behavior of these details.

The first cracked details were detected in 1963 after fifteen years of

service and in all probability had a more severe initial discontinuity

than the detail analyzed (Ref. 1).

-100-

Page 104: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

3. CONCLUSIONS/RECO~~ENDATIONS

Conclusions Regarding Fracture/Failure:

The cracking that developed resulted from large imperfections that

were fabricated in the short transverse groove welds. These welds were

insufficient length to produce sound welds.

-7

The welded connection which caused the problem was difficult to fab­

ricate. In 1948, equipment for nondestructive inspection was not avail­

able. Thus, the weld quality was poor and permitted fatigue crack propa­

gation to develop under the normal stress spectrum that the bridge was

subjected to.

This structure demonstrates the necessity to provide sound groove

welds perpendicular to the cyclic stress. It also suggests that short

transverse groove welds are difficult to produce with sound welds and

should be avoided.

Recommendations Regarding Repair/Fracture Control:

Fatigue cracks in weld details originating at extremely large

initial weld imperfections and inclusions were retrofitted as explained

in the following section (see also Ref. 1).

-101-

Page 105: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 -8

4. ACTUAL REPAIR/FRACTURE CONTROL EFFORTS

The fatigue cracks discovered in 1963 in the transverse (or vertical)

weld detail in the three of the six haunch inserts of the north interior

girder were repaired (Ref. 1). The repairs were made by welding cover

plates or insert plates (see Fig. 3). Prior to the load tests in 1973

a through inspection of the repairs and remaining transverse weld details

revealed four other weld cracks. The transverse weld area was cut out in

a circular shape, and an insert was welded in its place. Where the crack

penetrated the bottom flange, it was gouged out and filled with weld mate­

rial at a slow rate of deposit, by using low hydrogen-coated electrodes.

All repaired surfaces were subsequently ground smooth .and flush· to elimi­

nate any stress concentrations.

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

The probable adverse effects of the original repairs might be the

possibility of new imperfections or inclusions fabricated into -the repair

welds. Installation of bolted flange splices were later applied, as cracks

were also observed in the groove welds that connected the flange to the

web plate insert. Figure 8 shows the flange splice detail.

This subsequent retrofit should offset and prevent any significant

distress from developing in the structure.

-102-

Page 106: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

6. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

Cost of Investigation:

According to the Ontario Department of Highways' estimate, the

inspection and investigation of the cracking in the Aquasabon River

Bridge is $8,200.00 in 1979.

Cost of Repair:

The cost of repair and retrofit of the bridge in 1979 was given as

$92,141.00.

Original Cost or Adjusted Cost of Structure:

This is given as $74,616.00 in 1947 by the Ontario Department of

Highways.

7. REFERENCES

(1) King, J. P. C., Csagoly, P. F. and Fisher, J. W. FIELD TESTING OF AQUASABON RIVER BRIDGE IN ONTARIO, Transportation Research Record No. 579, 1976, pp. 48-60. (Also presented at the Transportation Research Board Annual Meeting, January 1975, Washington, D.C.)

(2) Fisher, J. W. Personal Communication to P. Csagoly, Engineering Research and Development, Department of Highways, Downsview, 'Ontario, Canada, dated November 21, 1973.

(3) Csagoly, P. F.

-9

Personal Communication to J. W. Fisher, dated November 29, 1973.

-103-

Page 107: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Table 1 Expected Maximum Live Load Stresses (Loading= two 177,000 lb. vehicles)

L oca :irJ:1 - y Ex;sc~ed Stresses, tsi

::-ef. East Brg. Live I Dead I To":al

2!_;. I !~azimu:n :Snd Span -20.1 I - 9.0 I -29.1

I I 44 1 - 2:::::.. ::au::ch · .. :elci

I Detail -15.8 I .,. 2.5 -13.3

I 60' East Pier +17. 4 "-14.1 i +31.5 -

I I I

30' - Splice Zone -13. a - 2.0 I -15.9 / i

I

l 100' Ce!:ter 2;::3.:--. -2C.6 I -10.5 -3l.1 I I

i L_ ______ --- i

- ive = Tensile Stress

+ ive = Co~pressive Stress

Table 2 Summary of Estimated Life with Crack Growth Stages (Aquasabon Bridge)

Stage 1: Crack Growth Through web

Initial Crack Size, a1 , in.

0.25

0.30

0.32

Stress Cycles srRHS = 1. 92 ksi

25,360,000

8,175,000

4,500,000

Stage 2: Crack Growth Through Flange

b.i tial Crack ~adius, in.

1.40

1 L.:: -.. ./ l. 50

31,700,000

26,200,000

I 21 ' 4CO ' 000

-104-

Years to Achieve

18.9

6.1

3.4.

-a , .L,..,. 0

::..6.0 I I i

Page 108: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I ...... 0 \.)I I

Fig. 1

WEST ABVT.

Plan and Elevation of Aquasabon Bridge (Crack Locations are indicated with mark X)

Page 109: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I t---' 0 Cl' I

r-11~"_ -•j ~~ ___ 1'--:_G"- __ 3£11"a~"f1LLET WELDS

!;;;.w d ~~~ ::=.ill EliCit SIDE

lr <!3''J~G·;u•LUGS ~ 1~ _,@t'~s··c::~.~ ~ \~_j

SLAB CONNECTION LUGS ON TOP FLANGES WITHIN LIMITS AS SHOWN

GIRDERS

IILL STntNGERS ---- · io'~o· c1s. ~

i4'..:s· -~-

Strur.turAI Strol- medium pracht.

n;, ... 718" tfJ. All sliding hrar 1,0, Jrround 5mooth one facr.. Girrlr.rs placr.d convftM ~ide uv to counter dr.rlrctiou.

o.., nol paint tops of all girders Pnd hearn~

All splicn to develop 50% of ~trr.ngth of heavier ~ctioo.

Coocrf!ll! conuactor to lettve 4"' Jlt 4'" )( 12 .. oprn holes

for anchors.

~--~{ SYM

:n• WF GIRDER

."--._ WELD FIIILURE ZONE

SECTION AT PIER

Fig. 2a Main Girder Haunch Detail, Field Shear Splice and Connector Detail -- Aquasabon Bridge

Page 110: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

·.: :·.·. :' ......... : .• : 6.". •. ,. '·.

Fig. 2b Location of Weld Failure in Main Girder (see Fig. 3 for a detailed photograph of circled area)

r--~·

~ .

;

Fig. 3 Typical Crack at Vertical Butt Weld Detail (Terminal Point of Haunch Insert Detail)

-107~

Page 111: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I.

INCLUSION

Fig. 4a Details of Weld Inclusion

STAGE I

BOTTOM FLANGE

Fig. 4b Assumed Stages of Crack Growth

STAGE 2

' I / -" ,/at / BOTTOM -....... -/ FLANGE --

(Outer Edge of Weld Inclusion is shown as dark line)

-108-

Page 112: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

400

2 a: <: 300 ..., >-a: ..., c.. Vl~

"-0 200 c:: ..., Cl ::!: ::::> z

100 z

0

~9S

NOTE' I

i8 - OSSERVATION PO: RICO • 32.5 HRS

1:< - 286 VEHICL.::S w;TH £r > 20~ lN./IN . IU

<;z -AN ESTIMATED SO,OOO VEHICLES/YEAR ...-:~ <ta: 011- w:TH Sr > 0.6 KS!

133

5

.22 .67 1.12 1.56 2.01 2.46 2.90 :3.35 3.80 424 Sr (KSI)

CLASS MARKS

Fig. 5 Stress Range Histogram (Smoothed) -- Aquasabon Bridge

-109-

Page 113: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I f-4 f-4 0 I

Inclusion

Fig. 6 Crack Surface at Weld Detail (Inclusion area is the dark

area in the photograph)

··~ ______ ._ __ .. ·········--------.... ~--. -- --------· --- ------. -

Fig. 7 Circular Cut-Out Section at Haunch Tip Weld Detail

Page 114: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I I-' I-' I-' I

-J

:-.. ., I_

.... .:I

1 "''"- 1..110 •,T & "'IT .A.aur.

···--·- '---~

~c

:1-- ___ , ... '·'11

I .I I

I

•' I I' II

·---~~------------------------·-------T'~~:---------------------y~:+: __ ,..J 6o'·o· ':J.: t:.o'-o· ~-:-_:--:-:;

·-----.. 1110 .. q, \..1 :\1. .... ,

PLAN OF GIRDERS TO ,.,C: at8U'4POA.CaD

I'· 0!1'-o ___ _Jr-·--~~r . • I I' I

···I-• . --- -----~'"!.:.2.. ________ -~ ... .-·. 8~1 . ... . . r-r. ·1·-llE•N•o•u:e .eo:.ri __ . ______ ..;,!::! ____ . __ ,69'.-.o.' ______ L~.

ELEVATION OF TYPICAL GIRDER I • IS -0

~-------------------------LL~·--·-----

I, '-AHir'l T'ut: \.11\:LO a.T TF rJo1t"IAt._ r·("llt~T •,111 tnTu

t")N l'lf'IT., .O•DF ~ f)r UEP!o Tr., 5'r.n014 TED"" r()•'IT .

fl. Dql\.l 1"4- UC"tLI! AT 'lli.LO IIJTr- tt-.r· 1 Tt11""4\.

_~- ;~::r:~- ,\:'r;;~!~"~~·;,~l~~' :.;~ ;:;.l,~~'\'~~;:;~··~~:. TO q_c;p1(Y"'"- ""lL I:!,.Ar.r-1: f'l r: oc;...F~.

4. Rlit1()\'Ci r'QI;.Vt0U' Q_EINIII"QQ(IIIPqT AU£) f"'\.-'r:C NP\.f RI'!IU~ It'' .&!If) TOQ<:liJI! Q!')\.T~ ..... ~ 1\~F.r.t~tP.O .

l ,.A tNT tl.'"' 1rct•JC TVD'AL ~T£[ 1... Jr>(I'"J)n l"tlllr;.

Hrr_ FO"M ''t.~(l\.

NOTES,

MltTA\. "00 .. A.(.@\ ~tol(..t UILL r.(J•~~ IPI (.t:)qT ... Cf' ~!"'._.

ONE -'"Ol~i.Q.• \t-tALt. t.-I')T P\E f"'.-._II~T""t) 1\tJT c;""'"l.L ~- 8\...A.CT C.L~A..NIID :»~ QTwEctHI~' '\•JIT,a.I'ILY Ptt&rA..QF.O u• "'- ~.-..·~•18Q. Ar!-~0\.'lioO nv Tt4C0 C'"l'-'"''"'!Jl. CONTiii' .... C.TQI:t TO fiA.TC'"' •1~1-1 P\0\.T WOLP.!o t~ ... lA"~'E.f LltTW TH&. ~Ji'IC.T•ttr,. 1'\r)l'T Hf)Lf::'\.

IJ T Q.IJC. T U ~A L II; T E I! L TO 1\ E C. o; A. G "0 '1.1 - '5o'".

:.J\b /4. -''PI }'aht. 41,"\..01-Jf; .._.,,.._. ,.li:N,•Lf \T•.C.ttC.r~

ftOLf'- \.IIT\.t W...._l:lO'-NED \.oi._~H!;ct'\ A....,.O ""UT"

1-tOLCi(. TO ftt 1i;4"+·

TORqtJJ;" e.oLT~ ,.0 54ft f::T '-"""·

evH~IIIrA,c.i...L rl!X.I\T

1«e. c;ttl[)~t:t \.1\~.141 ""'"0\IT" l Ofl ~11q

==========/~====~!]

I • J. ---···------· __ , _________ -------~~-=-~-----

t-"r:\.1 TQf"O Q:EI..,~. n_ \f•~'/,•1.0.\

·[111~11

C. "RDER.I.I\\•141

Fig. 8

!;:L!;.VATION OF l'IEINFORCIN~ PLAT!;:{,

PLAN OF "lEW BOTTOM REINI'OQC.ING. 'PLATE ------·-------------------·-------------------· DETAIL OF TYPICAL REINFORCED biRDER

AT PIER. ( ~IHI~T AI'IUTH~ I • 1-0

Retrofit Detail (Top and bottom reinforcing plates along the haunch and the hole drilled at the terminal point)

I

Page 115: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

5.2 FATIGUE/FRACTURE ANALYSIS

OF

QUINNIPIAC RIVER BRIDGE

-- A Brief Summary --

I.D. No.

Town/City/etc.

Railway/Highway/Avenue

State/Province

Owner

-112-

4

North Haven

Interstate Route 91

Connecticut

Connecticut DOT

Page 116: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 1

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief Description of Structure

The Quinnipiac River Bridge on Interstate 91 near New Haven,

Connecticut (see Fig. 1 a,b) is a four span structure over the Quinnipiac

River. Span 1 is of composite construction with \\1F beams and welded

girders. Spans 2, 3 and 4 are noncomposite welded girders of cantilever

type with a suspended center span. The suspended part of the structure in

Span 3 is 165 ft. (50.3 m) long between the hinges which connect it to the

anchor spans (Spans 2 and 4, see Fig. 1). The span lengths are

62 ft.- 12 in., 112 ft., 220 ft. and 111 ft. -1 in. for the Spans 1, 2, 3

and 4, respectively. The entire structure is on a skew, as shoWn in

Fig. 1. _The cross-sections of Spans 2, 3 and 4 are composed of nine paral­

lel welded girders supporting each roadway in between metal team-type

guard rails separating the traffic. The main girders have transverse

X-type bracing and longitudinal stiffeners.

Th~ roadway is a 7-3/4 in. thick reinforced concrete deck. This con­

crete deck forms a composite system with WF beams in Span 1.

Brief History of Structure and Cracking

The structure was opened to traffic in 1964. In November 1973 a

large crack was discovered in the south facia girder of the suspended span

in the center portion of the bridge. The bridge had experienced approxi­

mately nine years of service life at the time the crack was discovered.

The exact loaction of the crack in the south facia girder of the sus­

pended span is shmm in Fig. 1.

-113-

Page 117: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

2. FAILURE MODES AND FAILURE ANALYSIS

Location of Crack, Failure Modes and Stages

As shown in Fig. lb and Fig. 2, the crack developed in the south

facia girder web. The crack propagated approximately to the mid-depth of

the girder, as shownin Fig. 2b, and had penetrated the bottom flange of

the girder at the time it was discovered. The location of the crack is

shown on the schematic profile of the bridge in Fig. 1. It is approxi­

mately 59 ft. - 6 in. from the left support of the noncomposite suspended

span.

2

A detailed study (Ref. 1) of the fracture surfaces indicated that the

fracture had initiated at the unfused butt weld .in the longitudinal stiff­

ener. The portions of the fracture surfaces in the vicinity of the butt

weld were severely corroded from exposure to the enivornmental effects.

The crack surface indicated that some crack extension probably developed

from the unfused section of the butt weld across the thickness of the

stiffener during transport and erection.

Examination of the crack surface in the web adjacent to the longi­

tudinal stiffener showed that a "brittle fracture" had occurred following

the penetration of the web thickness by fatigue crack growth. Study of

the fracture surfaces shown in Figs. 4, 5 and 6 revealed that the cleavage

fracture propagated throughout the depth of the fractured web and pene~

trated some distance into the flange before it had arrested. Several

stages of crack growth and the failure modes starting from the unfused

butt weld on the longitudinal stiffener-girder web interface are indicated

in a schematic manner in Fig. 9.

-ll4-

Page 118: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 3

Cvclic Loads or Stresses (Kno~~ or Field Recorded)

The stress range histograms for the girders were obtained in 1981. At

the critical section of girder, three load cases exist: (1) stress a11

due to the "live load,_" (2) stress a dl due to "dead load," and (3) residual

stress a due to welding. rs

The equivalent stress range for live load are approximated from

Miner's rule using gross vehicle distribution given in Ref. 2. This is

approximately S M' ~ 1.95 ksi (13.4 MPa) in the flange where the design r ~ner

stress range S D . r es~gn 4.35 ksi (30.0 MPa). The corresponding stresses

at the longitudinal stiffener areS M' ~ 1.17 ksi (8.1 MPa). The maxi-r ~ner ·

mum live load stress at the longitudinal stiffener is estimated to.be

2 ksi (13. 8 MPa). (See Ref. 1 for details.)

The average daily truck traffic (ADTT = 4300) crossing the bridge

was estimated to produce 1.600.000 random cycles per year corresponding

to the S M' ~ 1.17 ksi (8.1 MPa). r ~ner

The stress adl due to dead weight was 4.95 (34.1 MPa) at the critical

cross-section (see Ref. 1 for details).

Temperature and Environmental Effects (Known or Field Recorded)

As shown in Fig. 9, Stage III of crack growth was the brittle frac-

ture of the ~.;reb probably during a time of low temperatures. Comparison of

the fracture surfaces from the three point bend tests indicated that the

web had fractured when the temperature was between 10° F (-18° C) and -10° F

(-25° C). Brittle fracture initiated in a zone of high residual tensile

-115-

Page 119: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 4

stresses. Once the crack became unstable, it propagated through the web

and was eventually arrested in the girder flange. It is highly probable

that the brittle fracture occurred during the period of December 1972 -

March 1973, when the material toughness of the web would be decreased by

low temperatures to a minimum level (Ref. 4).

Material "Fracture, Mechanical and Chemical Properties"

in the Failure Regions

Several pieces of the web and flange material at the cracked area

(see also Fig. 4) were removed. Standard ASTM Type A Charpy V-Notch (CVN)

tests, and tensile tests were conducted on the web and flange material

(Ref. 1).

The tensile tests provided a yield strength of 36.8 ksi (254 MPa) and

an ultimate strength of 60.9 ksi (420 MPa). The results of the CVN tests

are summarized in Fig. 10. Both flange and web material satisfied the

toughness requirements for Group 2 of the 1974 Interim AASHTO specifica-

tions. The average CVN impact value for the web was 20 ft-lb. (27 J) at

40° F (4° C). The flange provided 37ft-lb. (47 J at 40° F (4° C).

Several three-point bend specimens were al~o fabricated from the

web material. A notch with a 45° chevron front was machined at the center

of the specimen to initiate fatigue crack growth.

The specimens were tested at temperatures of -40° F (-40° C), -20° F

(-20° C), and a 0° F (-18° C). From a comparison of the fracture surface

of the web crack with the fractures of the K test specimens an estimate c

of the temperature at which brittle fracture occurred was made. On this

-116-

Page 120: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 5

basis, it is believed that the fracture occurred at temperatures between

~10° F (-25° C) and 10° F (-14° C) (see also Fig. 11). It is apparent from

Fig. 10, that CVN energy absorbtion and consequently the dynamic toughness

of the girder material decreased significantly at 0° F (-18° C). The esti­

mated fracture toughness of the web steel from the J-lntegral Analysis are

plotted in Fig. 11. These tests indicated that the fracture toughness of

the web material was betweenlOO ksi and 150 ksi at the time of the fracture.

Visual and Fractographic Examination of Failure Surfaces

The fracture surfaces of flange-web longitudinal stiffener-web inter­

section (at which the crack originated), and the ends .of the longitudinal

stiffener are given in Figs. 4, 5 and 6 respectively.

Visual examination of the fracture surfaces (see Figs. 4, 5 and 6)

indicated that the failure had initiated at the web-stiffener intersection

due to an unfused butt weld in the longitudinal stiffener. The web frac­

ture's surface indicated that brittle (cleavage) fracture occurred follow­

ing the' penetration of the web thickness by a fatigue crack.

Replicas of the web-longitudinal stiffener intersection (Fig. 7) and

near the flange-web intersection (Fig. 8) were made and examined with the

transmission electron microscope. The examination of web-stiffener inter­

section confirmed that fatigue crack growth had· occurred (see Fig. 7) in

that region. The brittle (cleavage) fracture extended into the flange

(see Fig. ~t·

-117-

Page 121: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Crack Growth (Initiation and Propagation)

and Probable Causes of Failure

6

The primary cause of failure was the inadequate butt weld made across

the width of the long~tudinal stiffener. It is probable that some crack

extension from the unfused section occurred during transport and erection

of the girder. Several stages of crack growth based on the visual and

fractographic examination of the fracture surface of the web .are shown

in Fig. 9 (see also Ref. 1).

Stage III in Fig. 9 was the brittle fracture of the web after the

initial fatigue crack became unstable and propagated rapidly down the web

and arrested in the flange. This stage likely occurred during low tempera­

ture in the period of December 1972 - March 1973.

-118-

Page 122: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 7

3. CONCLUSIONS/RECOH:HENDATIONS

Conclusions Regarding Fracture/Failure

During its nine years of service life, the fractured girder is esti­

mated to have sustained 14.5 million cycles of random truck loading. The

final brittle fracture and failure of the girder resulted from an initial

crack which started from an unfused butt weld in the longitudinal

stiffener-girder web interface which enlarge in fatigue. The final

failure occurred at the end of several stages and modes of cracking as

shown in Fig. 9, probably during the period of December 1972- March 1973,

when the material toughness of the web would be decreased considerably by

low temperatures.

Recommendations for Repair/Fracture Control:

Reference 1 analyzes in detail the cracking and subsequent brittle

fracture and failure of Quinnipiac River Bridge. However, no recommenda­

tions w~re presented in Ref. 1 as to the repair and rehabilitation of the

structure.

The information file on the bridge indicates that the fractured south

facia girder was repaired by Conn-DOT with spliced bolted plates following

removal and grinding smooth of the poor quality butt weld in the longi­

tudinal stiffener-web interface which initiated the Stage I in Fig. 9.

Figure 12 shows the bolted splice detail used i~ repairing the

cracked girder. In addition, several other inadequate groove welds were

detected, and holes were drilled in the web in order to isolate the crack

which was propagating into the girder web.

-119-

Page 123: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

4. ACTUAL REPAIR/FRACTURE CONTROL EFFECTS

The fractured south facia girder of the Quinnipiac River Bridge was

repaired by the Connecticut-DOT personnel, as schematically shown in

Fig. 12. After necessary grinding of flame cut surfaces in the web and

flange, bolted splice plates were installed to restore the integrity of

the structure (3). Holes were drilled in the web to isolate a second

crack near midspan.

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

8

Not expected in this case (3) provided all the inadequate goove welds

similar to the one which caused the fracture of the south facia girder

were taken care of as recommended in the previous section.

6. ACTUAL OR EST~~TED REPAIR/REHABILITATION COSTS

Cost of Investigation

This was not available (probably not documented as a separate item by

the Connecticut-DOT).

Cost of Repair/Rehabilitation

The repair cost of the fractured girder according to a Connecticut­

DOT estimate was $7,960.00.

Original (or Adjusted) Cost of the Bridge

The original cost of the structure was given as $2,236,912.00 by the

Connecticut-DOT.

-120-

Page 124: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

7. REFERENCES

(1) Fisher, J. W., Pense, A. W., Hausammann, H. and Irwin, G. R. "Analysis of Cracking in Quinnipiac River Bridge" Fritz Engineering Laboratory Report No. 386, 1979. (also published in the ASCE Journal of the Structural Division, Vol. 106, No. ST4, April 1980, pp. 773-789).

(2) Fisher, J. W. "Bridge Fatigue Guide, Design and Details" American Institute of Steel Construction, New York, 1977.

(3) Personal Communication from J. W. Fisher toR. A. Norton of Connecticut-DOT, dated December 12, 1973.

-121-

9

Page 125: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I 1-' lv f-.) I

L_A

112'- o" 220' -o" Ill' - 4 15/16 II

Ill I -Rte 91

L

Section A- A

Fig. 1 Side View and Typical Cross Section of Quinnipiac River Bridge

Page 126: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

···~e·

··::-·-:-= . .;:~·-+ .. · L ·<·.:i(·: ·., :·:·::;.:r •.

. ::<-~- ~: .... ·· ·--_ .... : ... . .. .

-~-!"'-::~. ~: \ · .. :·: ·~ ... ~-: ·:· .:·:-: ···.':··~-· ~--.. :~-=·!··· . . -~- ;';._ .~(~-.~·~.- :.. .

; :~. :~~;j~~:-~; :-.

-?f ' ) . .. !:

~

;'

- . J "

Fig. 2a Profile of Quinnipiac River Bridge

"" :.••to:-: • >9: :J'""" .".1.:-.'"l't:a:: ;_:,.e:- • !r.- ... O,C-93 -f''lf'"t. ·; •• " o!" ?:-.-l(e- :..OO.::nt'So:-!.1: at .. 01-l~ fucia ~.-::. •: :..J../U7)

Fig. 2b Crack in Web of Fascia Girder

-123-

Page 127: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

~======~============J ,, ,, 1: If If • :1--s x 1/2 St1ffener 1: ~ Inside Face :1 ( 203mm x 13mm) ,r

'' I 11 L 4 lf211 x 3Ja"

:: L on g. S t i f f. ( 114mm x IOmm)

Left ;r Stiffener ~~ Piece 1

1 ,, 41/2 "x 3fa

11 :'

(114mmxl0mm)ll ,, ,,

I I I I • I I I I I I I I I

I {-...-"""' I

Web Piece 1I

t1 Crack~. !

II I

Web -Piece I

T 21.6

11

(549mm)

9'-2~411

:

(2813mm!

I I ,, I' l~~l_

Flange l 31e11

x 22 11

Flange .(559mmx 35mm)

Fig. 3 Schematic of Girder showing Sections Removed for Examination at Crack

-124-

Page 128: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 4 Fracture Surface at Flange-Web Junction

-125-

Page 129: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 5 Fracture Surface of Web Near Longitudinal Stiffener

Fig. 6 Ends of Longitudinal Stiffener at Crack

-126~

I I I I I

.j I I

i

Page 130: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 7 Crack Growth Striations 4912SX

Fig. 8 Cleavage in Flange Near Bottom Surface - 4300X

-127-

Page 131: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

,.-Stage I

Initial Crock (Unfused Weld)

Fatigue Crock Growth

Through Fused Port

Stage: .II

Fatigue Crock Growth

Through Web

Stage m

Brittle Fracture in Web

Arrested in Flange

Stage TIL

Fatigue Crack Growth

in Flange

Fig. 9 Schematic of Crack Growth Stages

-122-

Page 132: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

80 (/)

..0

I -- 60 ->-<.!) 0::: w z w a w CD 0::: 0 en CD <l

-40

80 (/)

..0

I --.. >-<.!) 0::: w z w a w CD cr: 0 en CD <l

TEMPERATURE, oc

Flange e L T o LS

0 40 80 TEMPERATURE, Of

TEMPERATURE I °C -20 0 20

Web ( LT)

TEMPERATURE l °F

Fig. 10 Charpy Results for Web and Flange Adj3cent to Crack

100 Co) -• ::::J

.Q. 80 ->-

<.!)

60 0::: w z w

40 a w CD 0:::

20 0 (f) CD <J:

120

100 cu ::~· 0

80 ....... ..

>-<.!) c: 60 w z w

40 a - w

CD 0:::

20 0 en CD <

120

Page 133: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

l:; en ~ .. (/) (/) w :z I 80 (9

I ::::> f--' w 0 C> I I-

w 0:: ::::> I-(.) <( 0:: LJ...

Ts -I

I

KcR /O.Isec I

I

o Kj (0.1 sec)

• K ( CVN , dynamic)

I I I I

I lo I I •

I I • .;· I I o 0 • I v /

//1 sec / v· / /

/ / / _.,..,

Temp. at ,..,., ~

Fracture

-100 0 100 TEMPERATURE Of • •

Fig. 11 Fracture Toughness of hleb estimated from Charpy V-Notch Tests and from Three-Point Bend Specimens

Page 134: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I f--' w f--' I

L <·/I

Fig. 12

- Wr.t> 51,/•cll/'lnl•t 11,','1} !6JI·> /',m•lt J}•l•c• ~·•co'u ~ 11!1 tb• ,_.

!ola:tst.,,.:- . .;-'" ll•J- r,'••;lEf.,,,., A""' ~,.u,

··~.u~A:O/rl AHO/f,,,,, Pin, . ., "''~'tJ ,,,.,..,,;" •>'·•ff

·· lr .•• J ;,,tj""/'"9 ~•at 1Jt:<J

•.11.}

v7Z. ..:. :•?_

,.,,,,, -'"-"'t"'ll-•

3/Z (o,.e- /'/_,,-.., "'<>!{rr

J!j)~, •

.. :..,··~:~~~~~~;;,;:~:-.'~~i: :;,':;'"/;:·_,:r; ,··:~:~r..~'f~.:.r:, .. ; .. :8;,1~~ ~-~.:.~/.~~::,:~fit, v••tlrr ,,,JI '-r:t<l!' -,.,.J tJ f'_,;,.. """or;.t', ~··fl,., -,v~J- Nulr o,/

1• ~}.,,•! :)Ill ;;.~,,..,.c/

•AI/ holllt J4.orifll tlr> 1 rr/ 'l•' ·All ,plu:r ,,Ia_-, .. rita I/ c:orofo,:'" fo ASI A·'' '""' ,4.,1/ j, ,..,OIOJIA om/ r,..,, f,o"?

C:.I'J •O•(•J > ::t:-'J"I ' :;::·i~.:J·d:!~.; ·l;:::':· ~::·:~; :~:·:.~l~'E:::;\:::J;~ ~::·:,::7.::.::~:, .. ,.

tvppl••i 6)' IJ,,.,~, Co:p~,.. # ,.-..,,..,,r, 'JI rovnrl''' "''"•..,, :U,r lloJ• ·•&ri :,_......, .,... tJ•r"·"'''''' -~;~,, ('.;.·v l!o~ lr.-.~ Jr . .J,c ... /;"1. ,.....,.,.~,J J/t.utll>,. ,,.,.Jolf~d ' /

·b.•'~:~.~;."~;;,:i-.~.' .. t>,;::;:~:·.~~~c~-;:·.~·,• ;'l~;; ~;~:·c~'~.:;;··~ Olfl ""' ~ c/ ',l/1 ltro~! tr, • ·/~,,~ Col~ ! ' -. 11 t fl '" .,1"1. ~~ . .fr•'N ho t:'.Jffu•f, ..,.,, ~ ., ., '"' ~ ~~ 3( 'I' ~~~~

~·r JT:~· ~~r ,

Bolted Splice Plates in Web and Bottom Flange

Page 135: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

5.3 FATIGUE/FRACTURE ANALYSIS

OF U.S. 51 OVER

ILLINOIS RIVER AT PERU

I.D. No. 70

Town/City/etc. Peru

Railway/Highway/Avenue U.S. 51

County · LaSalle

State/Province Illinois

Owner Illinois

-132-

Page 136: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

1

1. DESCRIPTION AND HISTORY OF BRIDGE

Brief Description of Structures

The U.S. 51 Bridge over the Illinois River at Peru is a 2292 ft.

(765 m) thirteen span structure with the three main truss spans consisting

of a cantilever truss 1077 ft. (360 m) long. The suspended center span of

the truss is 477 ft. (160m), and the two side spans are 265ft. (90 m).

The approach spans consist of two 75 ft. (25 m) single span units, one two

span and two three span units, all with spans of ± 137.5 ft. (± 46 m).

Except for Spans 1, 2 and 3, each span is constructed with four riveted

plate girders spaced 10 ft. - 3 in. (310 em) apart. Span 1 has six girders,

and Spans 2 and 3 have five girders. Figure 1 shows the plan and elevation

of a typical 137.5 ft. (46 m) span with five girders. Welded cover plates

were attached to the riveted plate giiders at the piers and at midspans,

as illustrated in Fig. 2.

The girder webs were fabricated from A7 steel. The flange angles and

cover plates were furnished A373 steel.

The bridge is one of the few early girder bridges that combined

riveted girders and welded cover plates.

Brief History of Structure and Cracking

The structure was built in 1958. On July 22, 1980, painters reported

a cracked cover plate at a transition weld, as shown_ in Fig. 3. As of

January 30, 1981 district maintenance personnel had located thirteen

transverse cracks in the bottom cover plate groove welds, including two

-133-

Page 137: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 2

locations in the negative moment region adjacent to Pier 2. Cover plates

were cracked in two at two locations, one including the outside leg of a

flange angle, as shown in Fig. 4. Eight girder cover plates were cracked

between 2 and 4 in. (5 and 10 em) from each edge of the cover plate. At

three locations, grinding revealed full width subsurface cracking, as

illustrated in Fig. 5. Four out of six girders were cracked near the

quarter point of the north approach span.

-134-

Page 138: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 3

2. FAILURE MODES AND FAILURE ANALYSIS

Location of Fracture, Failure Modes and Stages

Of the thirteen transverse cracks detected in the cover plate groove

welds, two were in the compression flange of the negative moment regions

adjacent to pier 2. The cover plates were cracked completely at two loca­

tions. The cracks all appeared to be fatigue cracks, which had propagated

from large internal flaws in the cover plate groove welds.

Ultrasonic testing of suspected weld defects in Spans 11, 12 and 13

(corresponding to the riveted plate girders in Spans 1, 2 and 3, respec­

tively) was also carried out. These tests revealed a 3/4 in. x 7/16 in.

(2 em x 1 em) crack in the outstanding leg of an 8 in. x 6 in. x 7/8 in.

(20 em x 15 em x 2.25 em) bottom flange angle near pier 12. All cover

plate butt welds were ground smooth and tested with liquid penetrant in

order to locate subsurface cracks.

_Cyclic Loads and Stresses (Known or Field Recorded)

The 1979 estimated annual daily traffic crossing the bridge was

10,700 vehicles per day. The 1980 estimated annual daily truck traffic

was 1950 ffiulti-unit vehicles per day, including occasional 120,000 lb.

(54,400 kg) permit loads.

The design stress range in Span 1 was found to equal 10 ksi (68.95 MPa)

at the groove weld near the 0.26 point from the north approach for HS20

loading. T~e stress ranges in Span 2 were found to equal 8.5 (58.6) and

11:4 ksi (78.6 MPa) at the groove welds in the positive moment region near

-135-

Page 139: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 4

the 0.23 and 0.55 points where cracks had been detected. The stress range

adjacent to pier 2 in the compression flange was 4.4 ksi (30 MPa).

The net section properties were used to estimate stresses in the ten­

sion flanges of the positive moment areas and the gross section was used

for the compression flange in the negative moment regions.

Temperature and Enviornmental Effects (Known or Field Recorded)

There was nothing available.

Material "Fracture, Mechanical and Chemical Properties"

in the Failure Regions

There was nothing available.

Visual and Fractographic Examination of Failure Surfaces

There was nothing available.

Crack Growth (Initiatio~ and Propagation)

and Probable Cause of Failure

The primary cause of failure was the poor quality of the groove welds

at the thickness transitions of the cover plates. This was due to incor­

rect procedures used during fabrication and resulted in poor weld quality.

Large cracks appear to be fabricated into the members as a result.

-136-

Page 140: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

3. CONCLUSIONS/RECOMMENDATIONS

Concl~sions Regarding Fracture/Failure

The groove weld transitions at all cover plate splices were ground

to expose subsurface cracks.

Butt welds that had surface cracks less than 1/16 in .. deep were

ground smooth, and the crack removed. The .joints were also liquid pene­

trant tested to insure that no evidence of cracking remained.

Recommendations for Repair/Fracture Control

All groove welds which were found or suspected to be defective were

retrofitted with bolted splice plates. A typical splice is shown ln

Fig. 6. The repair work was carried out by Illinois DOT day labor crews.

Those groove welds that were found to be acceptable by nondestructive

inspection were ground smooth and left as constructed.

·Actual Repair/Fracture Control Efforts

5

All defective butt welds were ground down a maximum of 1/4 in. (6 mm).

Contact surfaces between the splice plates and existing cover plates were

ground smooth to ensure proper fitting.

Bent cover plates were used to splice across the defective butt welds

in Spans 2 and 13.

Additional bolts were added to compensate for the forces induced by

the sloped bearing face. Figure 6 shows the general splice detail used

throughout the structure.

-137-

Page 141: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Possible Adverse Effects of Repair

No adverse effects are expected as a result of the repair procedures

that were carried out.

Actual or Estimated Repair/Rehabilitation Costs

Cost of Investigation

This was not available.

Cost of Repair/Rehabilitation

The repair cost for retrofitting the cracked cover plates was

$32,035.64 (day labor costs 1980).

Original (or Adjusted) Cost of the Bridge

The original cost of the structure in 1958 was $2,539,737.88.

-138-

6

Page 142: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I t-' w ~ I

... v ... ..,,

·i . >.J'I-

~ > ~ l ... ' l:: ' -.. ~

---- _ . .?.~.:.: ,_~ .!!__l!_lll..:.l.:..----

. ' '- , ·'·' '·/ ~· J 1fl-'···'-' _.,,..~ ... ..- -v.-, .. ~

A'\~A<..:'*'-.11 r.:S ~ :.C T.I>J~Ot..'ONVV':__ .1

__ ,- / ~.a <-1. AT ~A-:'''osr

~--

I I

. ··OI '""" d ~~- J"'' 9-.

~::JIAPA/~AGM . -···--·--- ... ···

.o.J•

I • 't 'It. I

' : I I

\ .0/..v'..VRA o/V "

"''.4/'(,V.-4'.411. .~A' A I ·· ..

LAYOUT PLAN JC~<Ll ,,.·;,,,

II • .l. D " (iRADl

't-... ~ : ________ _

Fig. 1 Pl~n ~nrl rlPv~tinn nf Sn~ns 1 ~nd 2

Page 143: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

II

~+

~ ~ -~

I

..-·~. ..-·.· ~I'UlTC:JI~ IN~

.,AI. l?lr~ ~ ""'TC* • 6-

~--·· 6 s~· a~s;,: Z'·4 •• I

rl44~ r ... L f.!.::..ti: ~1

r-- r-

t - ~ ~~ ~ ~ ~ I~

,_

~ ~

,....

~ , ... f+

~ ' . . ~ ~ ~ ;~ ~ ~ ;q:

:~.o ~ ~ -. " ' ~ ~

~ ~

,

I. jr l I. ,.;,· J ~ /4'z·· y « r I I ) [ I I [ r- ~-- ... '7 f I [ l L - ---" . ....,. f ' I r' H£ D&T,!!tl. N' CO•I l I

Pl.llo rr ·llf!LD • r., Slf*l T I'·'. 7'·(1' I 'l'·o· 1TJ t. 81u;,. Pt£R •z

' -- 1~ ·.c· -

De TAIL OF COVER R. BUTTW£LD SC,AL£ · 6' :I H

,:g,·-~· [.Q. t ~~!i. er~~t ·z .SLOPE

-.....:::=====:::::J .J ,,. 2.'·o· :"f __ __,::....::., __ _

Fig. 2 Typical Welded Cover Plate Detail

-140-

I

l I

i ' ' , I I I

""".:! --~

II •I II I.

I' i!

'I 1!1' ld

..

Page 144: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 3 Cracked Groove Weld in Cover Plate

Fig. 4 Crack Extending into Flange Angle

-141-

Page 145: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

"

..

••

Fig. 5

-· _::····---~·--:-fl~~-~; ·~'

. , . ,.1 ' . : ·.r. .. ·'.

(' ..

. .. ·,

.. ~- .·· ·.::::..· ......

Ground Groove Weld Showing Crack

-142-

Page 146: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

'•

~ .(.-':1 IP ~,. .. ~

.. •f ·. ·. .. ~l...1 " ' I< .-

I I r- 1 ~1

f WfLO

IJ- --- ' . ·-·-·-··-·-:-~1~~-- ~-' ·--= = -----·------~--------==~- ~

H--· --- ------~------

. I I E-~-..,s+~ ~~~ ¥ f- 1- ' . - -

COVC!.,r {l I -.

I' " j . I•

N . __,..,.

I

J_l~a 1· I

0 - ----

l\ ~,

I

3----~ •'•t ,-:-\(· •v- .. --

... . ' . " r. . . I'' I 1.. l . . I I

I ·~_il-.l±~.l!ALL.rf.il'~ (~ J I.

I .t ~ * J._ ""t_._ SPM . .c.t-iz--.. 1· ~IJ.Y.Il~J~....rAc.tJ __ =t_! +-~ .;, .') ,, -: 'i ,, ~-· 3 'l. I I (. h . =I I- :1. II ' . ; I , - 'I I

1- - - - - - - -- - - - - - -- - - - - - - - - - ---+ t· + -+ t + t t J,_ -4- ·+ + --+ --<V .. -<P-- -~-

:

I

_q;_ -~- + -'' -~- -t- --4-- -+-$- -4t- ....... ~ -+- -+- -+-- ·-·+-...

- - - - - --- - - - - - - --r- - - - - - ·- - - - --., ,l I -· I

~---~ .. ·------ ........ ..

PlAN

I _) ., .

. ------·· ~;. --, I[; .... .

Vl f l D ___ G R I N DIN G DE TB I L

I -0 n

Fig. 6 Typical Repair Splice and Removal· of Fillet Weld

·-

- --' -- - -II 1! I' I ...

. I I

1: ;: "

I

iJ

Page 147: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

6. WEB PENETRATIONS

The cracking of the rigid frame bents of the Dan Ryan elevated transit

structure in Chicago in 1978, resulted in an examination of other struc­

tures with comparable details. In the Dan Ryan structures, longitudinal

girders framing into the steel box bents had their bottom compression

flanges pass through slots in the box girder web. A detailed description

of this cracking is given in the summary that follows (I.D. 7).

In the Dan Ryan structures, the flange plates that passed through the

web slots were groove welded to the web. However, large lack of fusion

defects were found to exist in the web at the tips of the flange plates.

Two other bridge structures have experienced cracking at similar lack

of fusion conditions (I.D. 40 and I.D. 105). In both instances the.details

were retrofitted before significant damage developed by isolating the

detail with holes similar to the condition described for the Dan Ryan. In

the Girard Point pier caps (I.D. 40) the flange plates were connected to

the web slots by exterior fillet welds only. In the Metro pier cap

(I. D. 105) vertical reaction brackets were passed through the web. These

brackets were welded to the web using backup bars and the resulting crack­

like condition and lack of fusion adjacent to the flange resulted in

significant crack growth.

-144-

Page 148: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

6.1 FATIGUE/FRACTURE ANALYSIS

of

DAN RYAN RAPID TRANSIT STEEL BOX BENTS

-- A Brief Summary --

I. D. No.

Town/City/etc.

Railway/Highway/Avenue

County

State/Province

Owner

-145-

7

Chicago

Dan Ryan Rapid Transit

Cook

Illinois

Chicago Transit Authority

Page 149: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 1

1. DESCRIPTION AND HISTORY OF THE STRUCTURE

Brief Description of the Structure

The Chicago Transit Authority's (CTA) Lake- Dan Ryan Rapid Transit

Line provides direct service between· the city center and the south and

west sectors of the city. The tracks ascend from the median onto a via­

duct which carries them through a curve of 400 ft. or 120m radius to a

smaller junction curve which joins them with the old North-South Elevated

structure at 17th and State Streets. The side view and underview of the

structure are shown in Figs. la and b.

General features of the viaduct at the location of cracked bends Nos.

24, 25, 26 are shown in Figs. 2a and 2b. The superstructure consists of

four continuous plate girders which carry a cast-in-place concrete· deck and

two tracks. The rails of the two tracks are on wooden ties resting on bal­

last. The bents supporting the four continuous I-beam plate girders have a

box-shaped cross-section consisting of two column legs and a horizontal box

member as shown in Fig. 2b. The stringer bottom flanges plass through

flame-cut slots near the bottom of the side plates or webs of the box

girders. The stringer flange was inserted through these slots and then

connected to the supporting box girder web by groove welds all around the

flange surface.

The stringers at the location of failure have a track curvature of

400 ft. or 120 m in the horizontal plane, and they intersect the boxes at

different angles (approximately 45°). With the exception of bent No. 35,

the bents were fabricated with portions of the superstructure girders or

stringers welded integrally within the boxes. The girder stubs project 3 to

4 feet from the sides of the boxes and are connected with the continuous .

girders by a pinned link or bolted connection (see also Fig. la).

-146-

Page 150: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Brief History of the Structure and Cracking

The entire structure was designed in 1967 in accordance with the

criteria and procedures established by the American Railway Engineering

Association (AREA), the American Welding Society Specifications, and the

2

CTA design policy for elevated railways. The construction of the Dan Ryan

Line started in April 1968 and was complete and opened to traffic in

September 1969. On an average day, 46 7 tra,ins (in both directions) pass

over this viaduct. The trains vary in length from eight cars during the

rush hours to two cars during the nighttime(1 •2 •3).

On January 4, 1978, a crack was discovered in one of the steel box

girders in bents (or frames) near 18th and Clark Streets. Subsequent

inspection of the structure verified the existence of this crack fn bent

No. 24 and also revealed that bents Nos. 25 and 26 were cracked as well.

A typical crack is shown in Figs. 3a and 3b. The most recent inspection

prior to the discovery of the cracks was conducted in July 1976, and no

significant cracks were found at that time.

Initial examination of fractures in bents Nos. 24, 25, and 26

indicated that they originated from fatigue cracks at or near the welded

junctions where the bottom flanges of stringers intersect the steel box

bent side plates (see Figs. 3 and 4a, b, and c).

Prior to the discovery of the fractures, temperatures in the Chicago

area were extremely low on several occasions. There were five occasions

when the temperatures dropped below 0° F, and the coldest trnperature

recorded at Hidway Airport was -7° Fin December 1977.

-147-

Page 151: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 3

2. FAILURE MODES AND FAILURE ANALYSIS

Location of Crack(s), Failure Modes and Stages

The field examination and measurements indicated the location shape

and pattern of the crack, as shown in Figs. 4a, b, c. The common feature

of the cracks in bents Nos. 24, 25 and 26 was their close proximity to the

vertical edge of the bottom flange of the stringers(1 • 2 •3). The cracks

completely separated the box girder bottom flange plate and both side

plates or webs in all three bents Nos. 24, 25 and 26. Openings at the bot­

torn flange of about 3/4 in. (20 mm) were measured. They were arrested at

the edge of, or with only very little penetration into the top flange plate

of the box girder of the bents. In bent No. 24, the crack extended into

the web of the plate girder (see Fig. 4a).

The initial field examination of fractures in bents Nos. 24, 25 and 26

indicated that they initiated at the welded junction of a plate girder or

stringer bottom flange tip to the supporting box girder side plate. Chevron

markings were observed on the fracture surfaces pointing toward the welded

junction. The fracture surfaces on bents Nos. 25 and 26 appeared to be lightly

rusted, while the fracture surfaces on bent No. 24 was more heavily rusted.

The trajectory of the crack in the box girder of each bent was

influenced by the dominance of tension, shear, and flexural stresses

(see, for instance, Figs. 4a, 4b and 4c).

The examination of the fracture surfaces in each bent showed that a

brittle fracture occurred after fatigue cracks developed from the unfused

welds at the edges of the bottom flange of stringers (or I-bearns) inter­

secting horizontal box girder of bents( 3). In the fractured bents, the

intersections were connected by partial penetration welds on the outside

-14o-'

Page 152: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 4

and little or no weld inside. Typical stages of crack growth in one of the

box girders are presented in Fig'. 5.

Cyclic Loads or Stresses (Known or Field-Recorded)

Following the discovery of cracking in the bents of the Dan Ryan Rapid

Transit, a reanalysis of the bents based on the finite element method was

performed. The stress analysis indicated that the computed stresses were

generally less than the values allowed by the governing specifications of

the American Railway Engineering Association. The maximum design shear

stress in the web plate in the east side of bent No. 24 near stringer

girder No. Gl27 was 17.27 ksi (119 MPa) which exceeded the value of

12.5 ksi (86 MPa) ~urrently allowed by these specifications(l, 2). ·

The normal design cyclic stress range during passage of a train was

estimated to be about 3.2 ksi (22 MPa) at the edge of the stringer flange.

With variable amounts of impact and multiple presence of two trains on

occasion, it was estimated that an effective stress range of 1.4 ksi (10 MPa)

was reasonable. for the trains that had crossed the structure. About 7 million

.variable stress cycles had occurred before rapid crack extension.

Temperature and Environmental Effects (Known or Field-Recorded)

The temperatures in the Chicago area were known to be extremely low

prior to the discovery of the fractures. There were five occasions when

the temperatures dropped below 0° F (18° C), and the coldest temperature was

recorded at the Midway Airport on December 1977 of -7° F (22 C). Low tempera-

tures were again experienced in Chicago on January 3, 1978 at the time the

crack in the box girders of the viaduct d . d(l,2) V.'aS lSCOVere .

Page 153: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Material Fracture, Mechanical and Chemical Properties

on the Failure Regions

5

Several sample pieces were recovered from the fractured box

girders(l, 2). From this material specimens were fabricated. Tensile

tests, chemical analysis, Charpy V-notch tests (CVN), Compact Tension

Fracture tests (CT) and metallographic and fractographic examinations were

conducted on these samples(1 • 2•3).

The tensile tests provided a yield strength (0.2% offset) of 33.7 ksi

(235 MPa) and an ultimate strength 69.6 ksi (480 MPa). Machining and test-

ing was done according to ASTM Designation E8.

The chemical analysis performed on the specimens was done according

to ASTM Designation E350.

Both tensile and chemical tests indicated that the material used in

the structure conformed to the ASTM requirements for A36 steel (1 • 2 •3).

Charpy V-notch tests (CVN) .were performed on the specimens in accord­

ance with ASTM Designation E23. The results are presented in Fig.· 6. The

results ·indicated that all plates satisfied the impact requirements of the

AASHTO specifications [15 'ft-lb. (20 joules) at 40° F (4° C)] for a mini­

mum service temperature of -29° F (-34° C) for Zone 2. The transition

temperature behavior for the material in the range between +40° F (4° C)

and +70° F (+21° C), as shown in Fig. 6( 2)

Compact tension fracture (CT) specimens were tested at a one second

loading rate between -30° F (-34° C) and +30° F (-1° C) in general accord

with ASTM Designation E399. The results did not fulfill the requirements

of AS~}f E399, and therefore the stress intensity factor Kic had to be

obtained by a J-Integral approximation.

-150-'

Page 154: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 6

The results are summarized in Fig. 7. It is apparent from Fig. 7

that a significant increase in toughness developed about 10° F (-12° C)(l).

Visual and Fractographic Examination of the Failure Surface

Visual examination of fracture surfaces indicate that the stringer

bottom flange tip was partially welded to the box girder side plate.

Paint was also noted in gas holes and other. unfused portions of the

fracture surfaces in bent Nos. 24 and 26. Slag, blowholes and paint on

unfused regions were observed in the welded junctions(l, 2).

A detailed microscopic examination was carried out on the fracture

surfaces of bent No. 26 (see Fig. 5) and to a limited extent on bent

Nos. 24 and 25. The examinations were made by both the transmission elec-

tron microscope and the scanning electron microscope. The microscopic

examination showed that the major portion of the fracture surface below

and above the welded juction is coarse grained and contains chevron

markings, typical of brittle fracture(1 •2•3).

The examination of a piece removed from bent No. 24 indicated that

crack growth initiated near the inside flame cut surface and also at the

exterior weld surface and extended toward the outside. Similar observa-

tions were made for bent No. 25.

The microscopic examination established that fatigue cracking (see

Fig. 8) in the welded junctions had preceded the subsequent brittle frac-

tures. The estimated length of flaws in bent Nos. 24, 25 and 26

-151-

Page 155: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 7

(vertical height of the flame-cut region) plus additional height of fatigue

cracking was 3 in. (8 ern), 3 in. (8 em) and 2 in. (5 em), respectively.

The metallographic examination did not reveal any defects in the

steel. The appearance of the grain structure near the surface was con-

sidered to confirm both fatigue and fracture modes of crack propagation.

Crack Growth (Initiation and Propagation)

and Probable Causes of Fracture Failure

The field examinations of the fractures in bent Nos. 24, 25 and 26

indicated that the fatigue cracks originated at the partially welded

junction ~f an I-beam plate girder (or stringer) bottom flange tip to the

side plate of the box bent( 2•3). Numerous weld deficiencies were apparent

such as slag, blowholes, etc. Subsequent microscopic analysis of the

failure surfaces confirmed the above observation (see Fig. 8).

The laboratory testing verified that the combination of stress con­

centration at the point of origin, fatigue cracking and cold temperatures

was sufficient to cause the brittle fracture of box girder bents.

It can be concluded that the severe stress concentration and the lack

of fusion in.the welds at the junction of the stringer bottom flange and

side plate of the box girder (or bent) is the primary cause of the cracks

which occurred in the bents of the Dan Ryan Rapid Transit struct~re( 2 • 3 • 4 ).

-152-

Page 156: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 8

3. CONCLUSIONS/RECOMMENDATIONS

Conclusions Regarding Fracture/Failure

A detailed examination of the fracture surfaces from the cracked

steel pier bents of Dan Ryan Elevated structure has shown that these frac­

tures were all caused by fatigue cracks( 2 •3). These cracks originated from

poor quality welds at the edges of stringer bottom flanges where they inter­

sect box bents (see Fig. Sb).

During fabrication slots for the stringers flanges were flame cut into

box girders. Subsequently stringers were inserted through these slots and

connected to the box bent girder web by welding. This kind of connection

created the high stress concentration at the weld adjacent to the stringer

flange. Thus, the joint was very sensitive to fatigue crack propagation

at very low levels of stress range(1 •2 •3).

The fatigue cracks developed at welds adjacent to the stringer flange

edge in box bent girders reached a critical condition at the low tempera­

tures that occurred in Chicago in late December, 1977 and early January,

1978. Thus, fatigue cracks, poor quality welds, high stress concentrations

and low temperatures occurring simultanously caused the brittle fractures

of box girders which were discovered in early January, 1978(l, 2).

-153-

Page 157: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Recommendations for Repair/Fracture Control

A detailed repair and fracture control plan for the bents of the Dan

Ryan Rapid Transit is given in Refs. 2 and 4. Specifically for locations

where flanges pass through the web, any retrofit must reduce the severe

9

stress concentrations at the intersection of the stringer·bottom flange and

box girder webs (or side plates) and also reduce high residual stresses

from weld shrinkage.

For this purpose, "dumbbell" type retrofit holes and saw cuts were

installed on side plates of the box bents near the tips of all stringer

bottom flanges as shown in Fig. 9. In addition, 1 in. diameter holes at

the tip of the cracks in the fractured bents were .used to arrest the

cracks(2 •4 ). The cracked side plates and bottom plate of the horizontal box

member of each bent are to be repaired with bolted splice plates. Also,

the depth of the horizontal box member cf each bent is to be increased by

addition of a "U" shaped section which will be bolted to the underside of

the existing box as shown in Fig. 10.

Prior to retrofitting the structures and after one week of lack of

service, temporary support cribbing was erected under each cracked bent to

provide support to the cracked members. These cribs have remained in

place pending the final repair( 2).

-154-

Page 158: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

4. ACTUAL REPAIR/FRACTURE CONTROL EFFORTS

Immediately following the discovery of cracks in box girder side

plates (or webs) on January 3, 1981, Department of Public Works of the

City of Chicago started the construction of temporary support structures

under the box girders at Bent Nos. 21 through 26( 2).

Each temporary steel support structure consisted of jacking beams

10

placed on both sides of the box girder and supporting the existing longi-

tudinal plate girders. Jacking beams were supported by a steel falsework

tower with bracing resting on timber mudsill and crushed stone( 2). The

temporary support structures were to carry the weight of the tracks and

. '1 h . d f' d . ( 2) tra1ns untl t e permanent repa1r an retro lt recommen atlons were

implemented.

Holes were placed at the flange tip of all details.as shown in Fig. 9.

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

In the case of Dan Ryan Rapid Transit Structure no adverse effects of

repair are expected. However, the field inspection of the structure at

critical details in intervals to preclude the possibility of fatigue crack

growth ·should be continued.

-155-

Page 159: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

6. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

Cost of Investigation

This is not available.

Cost of Repair/Rehabilitation

The cost of repair/rehabilitation is not available.

Original or Adjusted Cost of the Structure

The original cost of the structure is not available.

7. REFERENCES

(1) Wiss, Janney, Elstner and Associates, Inc. "Inspection of Junctions of Girder Flanges and Pier Side Plates on Pier Nos. 21 through 26 on the Dan Ryan," Wiss, Janney, Elstner and Associates, Inc., Consulting Engineer, Northbrook, Illinois, 1978.

(2) The Technical Committee Final Report on Causes of Fracture in Bent Nos. 24, 25, 26 of Dan Ryan Rapid Transit, Chicago, Illinois, January 1979.

11

(3) Fisher, J. W. and Pense, A. W., Hausammann, H. and Osborn, A. E. N. "Elevation of Fractures of Steel Box Pier Bents of Dan Ryan Elevated- Chicago Transit Authority," April 3, 1978.

(4) Fisher, J. W., Hanson, J. M., "Fracture and Retrofit of Dan Ryari Rapid Transit Structure," Final Repor·t, 11th Congress, IABSE, August 31- September 5, 1980, Vienna.

-156-

Page 160: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. l.a General View of Dan Ryan Rapid Transit Structure

I ·I I I

I I

I

Fig. l.b View of Cracked Bents Looking.West from Clark Street (Arrows Are Pointing to Locations of Fracture).

-157-

Page 161: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I ,__. lll 00 I

~ct_ PI '-R 20

I A .

¢. PI!;.R 1.7.

(, I.IIHG'-'1~

t H. O. TRAC¥-

~ ct ~1Hg.~7 -?. C.R.I.ARR.Ri

SE.CTION A-A (HPANOE.D SC~t.E.)

• .... H

DAN RYAN RAPID TRANSIT ELEVATED STRUCTURE INVESTIGATION

PIER LOCATION PUN

DE LEUW, C_ATHJ;:R & COMrlRY • COIISULTIR.8 £118111££U AIIO PLAIIIIUS

CHICAGO • IlliNOIS

«t_ 5.t>.TRACil

<l PI~ 'Z7"'J__.

. ct,l.liNG'-ttiJ-­

¢,f.UNG'- F-1 J__.

~ PI'A 2&-J--

Fig. 2.a Schematic Plan and Locations of Cracked Bents (Bent Nos. 24, 25, 26)

ST R'-I:T

Page 162: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I I~

Ut cc I

l '

Fig. 2.b

ttt CCI.. puq Pll!&J

2 r- and Crack Locations Bent No. u

~-...

.....

,-1-=- y -::a.,.~"'fu

ff~ lt.'-•"•11W'•r-olllllii•

lltl!O!I 1!-!1

IOl!QI! fLMH bu PIJM,

::-JI. ........... .-c~ ..... , ...... ........ ..... .... r:-=:~·-"'~~~=·""•'"'

~

II:PAitf:~ ~ ~~~ WCMtlll .._,ltf~ OP hMIMIIIttwt

DAN RYAN RAPID TRAHIIT COM HUCf ., •• t

ll(VATlD IJftUCnntl • l4fH Ullffl TO I ClAitll: lfllllll

. rot R DllAill

'"'" .. MAI..I: ~~·.:.. f·4MW •I _;:......_ ....

Page 163: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I t-' 0"' 0 I

·~ .... . .

·J~ •. t".

Box Girder

(a) Location of Fracture (Bent No. 26) (b) Close-up View of Cracked Box Girder Web

Fig. 3 Fracture of the Box Girder (Bent No. 26)

Page 164: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

of outside pl.atc girder under south-bound ~<t

~------,Jt~v-~~: ~-~-4·-~----~A~ cracks -1

Elevation of east •ide plate

r-T,~ 7.41''2

I, > IY'4 1

Section II-A

"''I'' -2. t;." r--~-~1·

.. V,c;,

c f:'\EA~VR~D WIOTI( OF c. R,lo.. c."'-

Elevation of west side plate

Section B-B

Fig. 9-.-- Cr.tck pr<>fllc on 1\cnt No. 21,

Fig. 4.a Crack Profile on Bent No. 24

-161-

Page 165: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

, 1-- 4. of outside plate-­L __ 40_:_1," _ J~ '2J H __ j girder under south-/ ; . UounJ tracks

I I -i' r--Ye." . ~ I

c ~

I vi)"

(_ rv!EoA'S\IRE-0 .,.Jit:>TI-\ oF uu\c.~;:.

Elevation of c~st •ide plate Elevation of west side plate

Section C-C

F . 4 b Crack Profile on Bent No. 25 l.g. .

-162-

c J_J

Page 166: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

ELEVATION OF WEST SIDE PLATE

I • 132

I • 1 'a • \_MEASURED

3116 WIDTH OF CRACK

EAST SID

SECTION D·D

F . 4 Crack Profile on Bent No. 2b l.g. .c

-163-

Page 167: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I r' (j\ .t~

I

Inside I Outside .... ... of Box Girder

--f--- Brittle Fracture

Fatigue ---1_ 1\

Crack ,.......,....., ___ Fatigue Crock From

Outside Surface

Painted ----r\\' Surface

Study Region

--+---Brittle Fracture

(a) Stages Fatigue Crack Growth (b) Fracture Surface of Box Girder Web

Fig. 5 Schematic of Fracture Surface at Bent No. 26·

Page 168: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

80

"' 60 .D ...l I

20

----• 13ent No. -- --• Otnt No. ----"' 11entNo. · • • • • • 0 Dent No.

24} 25 26 25

3/4" web plate

Ji" flange plate

) I 0

I ·; .... I . / . /

/ /

/

Bottom Flange

.I~ 0 .. ····;

~All test~; meet cut rent

Well Platt'

1-----------------;;~rL---1/ AASHTO requlrem .. nt for 15 Zor.e 2 cf I 5 ft-lbp@ 40'?F •

.. ··~· . . . . .Temperature, °F •

Fig. 6 Comparison.of CVN Test Results

-165-

Page 169: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

400

300 _,...,.

·= . ·-1

~ 200 ::::::

1 00

0

-SO

-8---§ 0

-30 -10 10

o_ Test Temperature J:

30

Fig. 7 KIC vs. Test Temperature

-166-

50

Page 170: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 8 Fatigue Crack Growth Striations in Region 3 on Box Girder Web Surface at Bent No. 2b (X17000)

-167-

Page 171: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I I-' 0'\ m I

....

\\fi ~li<DER

SECTION A-A

[

.1 •. .

.. '

. .... . .·

I I I\_ WHI PLAT£ OF BENT

l

E, • ,t:, r· 2~!.p SAW DRILLED /-/OLE (TYP.)

~: l ~ ±~ ts•fSA\W CUT(TY.O.)jA I -~.,_·.::....."· ~~~- - -l-

ELEVATION

(a) Schematic Showing Retrofit

... -·

. , .··:·""'·· ..

i' ··---........ ...

(b) Photograph of Retrofitted Box Side Plate (or Web)

Fig. 9 Typical Retrofit Detail at Bent No. 26 (same as No. 21, 22, 24, 25)

Page 172: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I I-' (J\

1.0 I

A .. l CR/\CK IN WEBS B FLANGES

t==b~ ... ~~=,=-.

D

1- -1

DUMB-BELL TYPE RETROFIT (SEE FIG. 9)

SPLICE PL/\TES TO BE BOLTED TO EXISTING BOX SECTION

LONGITUDINAL GIRDERS

"u" SHAPED SECTION TO BE ADDEO TO UNDERSIDE OF EXISTING BOX SECTION

0

G- EXISTING BENT 1] SECTION A-A

Fig. 10 Recommended Repair and Structural Modif~cations (Bent Nos. 24, 25, and 26)

Page 173: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

7. WELDED HOLES

Several bridges have developed cracks as a result of misplaced holes

that were subsequently filled with weid. This has resulted in lack of

fusion and other cracklike defects at each welded hole that eventually

experienced significant crack growth and fracture.

At least three multibeam bridges developed major cracks in one or more

girders as a result of welding-up misplaced holes. The Ill. 57 overpass

at Farina (I.D. 54) is reviewed and summarized hereafter. Welded-up mis­

placed holes in rolled sections resulted in the cracking of one of the

beams. Similar conditions were found in two structur~s in Iowa (I.D. 57

and I.D. 89).

In every instance cracks were observed to originate at several holes.

These often linked and resulted in fracture of the section. Only the

Illinois structure experienced a crack that turned and traveled down the

~ength of the beam.

A similar condition was found to exist in a cover-plated plug welded

chord of the Burned River Truss Bridge in Ontario (I.D. 55). The cover

plate was attached to a rolled section with plug-welded holes. This

created- a lack of fusion and defect condition that was similar to the weld

filled holes. The crack eventually caused the chord to fracture.

-170-

Page 174: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

7.1 FATIGUE/FRACTURE ANALYSIS

OF

COUNTY HIGHWAY 28 BRIDGE OVER I-57

-- A Brief Summary --

I.D. No. 54

Town/City/etc. near Farina, Illinois

Railway/Highway/Avenue: County Highway 28 over I-57

County Fayette County, Illinois

State Illinois

Owner Iiiinois-DOT

-171-

Page 175: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 1

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief Description of Structure:

The county Highway 28 bridge over Interstate I-57 is located north of

Farina, Illinois in Fayette County. The structure is a skewed four-span

composite-reinforced-concrete-slab steel-beam bridge. It was completed

and opened to traffic in 1968. The bridge primarily carrieslocal traffic

over Interstate I-57.

The general plan and elevation of the structure is given in Fig. 1. A

typical cross-section is shown in Fig. 2. The bridge has a 32 ft. wide 7 in.

thick reinforced concrete deck supported by five continuous W36Xl50 steel

beams of ASTif A36-67 steel. It has two 95 ft.- 5 in. midn spans. and two.

55 ft. - 8-1/2 in. side spans. The concrete slab is connnected to the main

girders with shear studs with different spacings depending on the location

along the span.

The entire structure was constructred in accordance with the "AASHO

Standard Specifications for Road and Bridge Construction,''January 2, 1958;

the supplemental specifications, dated January 3, 1966; and the current

specifications of Illinois-DOT.

Brief History of Cracking:

On March 8, 1977 a large crack in the south side of the first interior

girder (Girder No. 2) of the second span was discovered by a construction

technician while driving under the birdge (1). The fracture in the stringer

originated at one of the four horizontal rivet holes which were mispunched

and later improperly repaired and filled with weldments.

During the winter of 1976-77 very low temperatures of -20° F (-29° C)

were experienced in the area where the bridge was located (1).

-172-

Page 176: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

2. FAILURE MODES AND FAILURE ANALYSIS

Location of Fracture, Failure Modes and Stages:

The location of the fracture in the south interior beam is shown in

Fig. 3, and a detailed schematic drawing is given in Fig. 4 (1).

2

There were two seperate fractures which started from two holes filled

with weldment immediately under the clip angle supporting the diaphragm

(1,2). Both cracks were initiated from weld filled holes with large slag

inclusions. Both fractures propagated down through the flange of interior

beam 2B2 at a common termination point. These cracks also extended up and

turned longitudinally along the web at about middepth. One crack extended

about 1 ft. (0.305 m) while the other curved upward and extended hori­

zontally approximately 15 ft. (4.57 m), reaching the next diaphragm as

illustrated in Fig. 4. Photographs showing the cracks and the plug holes

are given in Figs. 3 and 5.

Several pieces, including the crack surface, were removed by flame

cutting at locations shown in Fig. 7.

The results of mechanical and fracture tests of the material and

visual examination of the fracture surfaces shown in Fig. 5 and 6 indi­

cated that the failure was primarily a brittle fracture along the entire

length of the cracks.

There was very little ductility in the fracture. ·The brittle fracture

probably occurred during the extremely low temperatures recorded in the

area during the winter of 1976-77. Close examination of the plug welds

show the existence of the herring bone patterns near the slag and voids in

-173-

Page 177: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 3

welds (1,2). Thus, the fracture likely initiated from fatigue sharpened

cracks originating from slag and voids in the plug welds. During low tem­

peratures, the brittle fracture resistance was decreased. The small crack

from plug weld 4 (probably occurred at about the same time as the cracks

from plug weld 3) propagated, as shown in Fig. 4.b, in brittle failure mode

down toward the bottom flange and intersected the crack from plug weld 3.

Cyclic Loads and Stresses (Known or Field-Recorded):

The normal traffic using county Highway 28 bridge over I-57 is com­

posed mainly of automobile and light farm equipment (1). There are no

truck traffic counts available. Illinois-DOT estimated the ADT.to be 400

vehicles in 1976 (3). The computed design stress in the bottom flange

adjacent to the origins of fracture is 15.2 ksi (104.8 MPa) based on the

HS 20 truck loading (3).

A series of field live-load tests with loaded trucks were conducted

on the bridge following the repair of the fractured beam. During these

tests a dump truck was loaded with gravel to a gross vehicle weight of

44,700 lb. (98,500 kg). This truck was driven across the bridge in order

to determine the live load response of the structure.

A series of strain gages were installed on the replacement beam 2B2

at several locations including the fracture initiation point (for strain

gage locations, see the schematic figure included in Table 1). This gage

was used to estimate the maximum live-load stresses (1). Results of thes

field tests are summarized in Table 1. The measured stress ranges in

Beam 2B2 were all quite low with the maxi~um stress range being 3.46 ksi

-174-

Page 178: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 4

(23.9 MPa). The ASTM A36-37 steel used in the beam has a yield point of

43.5 ksi (300 MPa). Therefore, live-load tensile stresses observed in the

beam even with the addition of the dead-load stresses are well below the

yield point of the steel. Welding residual stresses from the weld filled

holes would introduce stresses near the yield point at each hole.

Temperature and Environmental Effects (Known or Field Recorded):

The time the fractures of the south side interior girder in the bridge

over I-57 were discovered, temperatures in the locality during the 1976-77 ·

winter were as low as -20° F (-29° C). Aside from the low service tempera­

ture, no other significant enironmental effects were apparent.

Material "Fracture, Hechanical and Chemical Properties"

Analysis in Failure Regions:

The lower portion of the beam 2B2 in the shape of a tee-section was

removed from the bridge by flame cutting between two bolted splices.

Specimens fabricated from this portion of the beam 2B2 were used for ten­

sile tests, Charpy V-Notch tests, fracture toughness tests and for the

chemical analysis (1).

The results of chemical analysis_indicated that the chemical composi­

tion of the steel was well within the chemical requirements specified for

A36 steel (1).

-175-

Page 179: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Tensile tests were also conducted on specimens fabricated from beam

2B2. The test results indicated that the web material had an average

yield point of 43.5 ksi (300.0 MFA) and an ultimate strength of 71.3 ksi

(491.6 MPa). Similar results were obtained for the flange. The tensile

properties of the steel satisfied the specification requirements for

ASTM A709 Grade -36 steel (A36 steel).

5

Charpy V-Notch tests were carried out in accordance with ASTM

standard A370. Four sets of standard size specimens were cut from the web

and flange of the fractured girder.

The test results are summarized in Fig. 8. Both longitudinal and

transverse specimens were tested from the beam web. All of the specimens

tested at 40° F (4° C) exceeded the 15 ft-lb. (20 J) requirement of the

AASHTO specifications for A36 steel:

Web specimens "WL" with their lengths parallel to the

direction of rolling of the beam (the notch being perpen­

-dicular to the direction of rolling)

Web specimens "WT" with their lengths transverse to the direction

of rolling (the notch being parallel to the direction of rolling).

Two sets of flange specimens were cut with their lengths parallel to the

direction or rolling of the beam and their notches parallel to the surface

of the flange, and

Flange specimens "FT" was located at the top of the flange,

Flange specimens "FM" was located at the middepth of the flange

-176-

Page 180: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

In addition to the Charpy V-Notch tests, fracture toughness tests

were conducted· on bend specimens in order to establish the toughness of

the steel. Since A-36 steel was used in the beam, valid Kic tests were

not possible. Static fracture toughness values, KQ, for the steel were

estimated from the maximum load. No load-deflection data was acquired,

6

hence a more accurate determination using the J-integral was not possible.

These tests provided KQ values of about 49 ksi /irl. (53. 9 MPa ;; ) at -20° F

(-29° C). A single test at -40° F (-40° C) yielded 50 ksi lin. (55 MPa /;).

These results were compatible with the estimated K values provided by the c

Barsom-Rolfe correlation equation and the intermediate rate temperature

shift.

In addition to the Charpy V-Notch and KQ tests, a series of tensile

tescs were conducted on rectangular specimens containing plug welds (1).

The test specimens were approximately 3 in. (76.2 mm) wide. The speci-

mens were machined such. that the plug weld was centered on the width of

the specimen. Three tests were carried out at -20° F (-29° C) and one

at -L:0° F (-40° C). The results are summarized in Table 2.

All of these tests failed at nominal stresses on the gross section

that were well in excess of the yield. Obviously, none of the plug welds

in these specimens had initial flaws that were· as large as those at· the

failure section. Failure occurred at stresses about midway between the

yield point and tensile strength of the base plate.

-177-

Page 181: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Visual and Fractographic Analysis of Failure Surface:

Visual observations indicated that the plug welds initiated the

fracture of Beam 2B2.

7

Photographs of one of the fracture surfaces are shown in Figs. 5 and

6. These indicated that a small shear lip is visible along the outer

edges over most of the length. Figure 3a demonstrates a similar condition.

No spalled paint exists at the plug weld and for a distance of about 1 in.

(25 rnrn) each side of the plug welds. Therefore, the mill scale is spalled

off and confirms the plastic behavior associated with the shear lips. The

herringbone surface patterns and the fine texture of the surface near the

plugs in Fig. 5 also show the brittle fracture characteristic which caused

the sudden unstable crack propagation at a low nominal stress level (1).

The slag and the voids which initiated the unstable crack growth are also

visible in Fig. S. The herringbone patterns in Fig. 6 point towards the

plug welds.

-173-

Page 182: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

3. CONCLUSIONS AND RECOMMENDATIONS

Conclusions Regarding Fracture/Failure:

The investigation of the fracture of a rolled beam in Fayette County

Highway 28 Bridge indicated the following:

The maximum live load stresses in the cracked beam was measured

to be 3.46 ksi (23.86 MPa) which was far below the AASHTO allow­

able stresses for such a member (1).

The chemical and mechanical properties of the steel were well

within ASTM-A36 specifications (1).

8

The steel met the Charpy V-Notch requirements for service tempera­

tures down to -30° F (-34° C) which was lower than the tempera­

tures experienced by the fractured beam (1).

Fatigue cracks and subsequent brittle fracture resulted from

the prescence of plug welded holes. These welded holes resulted

in large cracklike discontinuities that were susceptible to

crack propagation. The fracture surfaces shown in Figs. 5 and 6

show the cracks that formed at the welds. Radiographs of other

weld filled holes showed plug welds with slag inclusions and voids.

-179-

Page 183: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Recommendations Regarding Repair/Fracture Control:

It can be expected that cracking will develop in other mispunched

holes that are filled with weldment. The problem can be avoided by leav­

ing the holes and installing high strength bolts rather than welding.

9

Existing weld filled holes should be removed by drilling or coring 2n

order to remove the discontinuities and prevent any further undesirable

cracking.

4. ACTUAL REPAIR/FRACTURE CONTROL EFFORTS

The repair of county highway 28 bridge over I-57 was carried out as

follows:

The fractured section of Beam 2B2 was removed by flame cutting the

lower portion of the beam in the form of a tee-section about 10 in.

(254 mm) below the top flange for the entire length between splices.

A new tee-section that matched the section removed was field-welded

horizontally to the remaining section of the web and then bolted to the

adjacent beam segments using the existing splice plates. The repaired

portion of the beam is shown in Fig. 7. The tee-section removed from

the structure was used to fabricate test specimens in order to establish

the chemical, ·physical; and fracture toughness characteristics of the

steel (1,2). Fractographic studies were also carried out on the original

crack surfaces on these specimens.

-180~

Page 184: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 10

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

No adverse behavior is anticipated from the repaired member. Non­

destructive tests were carried out on the longitudinal field weld.

Furthermore, it is located near the neutral axis, so no appreciable cyclic

stress is likely to ever occur at that level.

6. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

Cost of Investigation:

No direct investigative costs were accounted for. All costs were

included in the cost of retrofit/repair. The University of Illinois

studies were carried out as part of their ongoing work.

Cost of Repair:

Available records (3) indicate that the cost of the repair was

$13,150.00 in 1977.

Original or Adjusted Cost of the Structure:

The county highway 28 bridge crossing over Interstate of I-57 was

awarded at a cost of $164,607.85 in 1958 (3).

-181-

Page 185: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

7. REFERENCES

(1) Handel, W. and Munse, W. H. I~~ESTIGATION OF INTERSTATE I-57 BRIDGE BEAM BRITTLE FRACTURE, University of Illinois, Structural Research, Series No. 477, March 1980.

(2) Illinois Department of Transportation Memo from T. R. Bright to H. L. Wear, dated March 29, 1977.

(3) Illinois Department of Transportation Personal communication from J. B. 'Nolan to J. W. Fisher, dated March 23, 1981.

-182-

11

Page 186: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

TABLE 1: ~1E..<\SURED STRAINS AND COHPUTED STRESSES

Truck Run

1. Crawl --

(Centered on Beam

line 2, SOuthbound

2. Crawl -­

(Right wheels over

Beam Line 2, Southbound

3. 30 mph -

(Centered on Beam

1 ine 2, Southbound

Gage Location

44

34

44

34

44

34

Spl•ct I

{ I

IN BEAM 2B2 UNDER TEST TRUCK

Tension Stress

ksi (MPa)

2.56 (17.65)

2.21 (15.24)

2.28 (15.72)

1.98 (13.65)

2.84 (19.58)

2.47 (17.03)

I. Si.ew

t

Compression Stress

ksi (HPa)

0.34 (2.34)

0.28 (1. 9 3)

0.34 (2.34)

0.28 (1.93)

0.62 (4.28)

0.56 (3.86)

17'-11\f:!'

SpiiCI 2

I I t

·-- ~--­! j

... ... -I I ''

~""-r.;;;~!

Replocement Boom 292

Norl" ~-

Stchon C ··:.

-183-

• Stro•r~ Goo•• + Boll rtolet

Stress Range

ksi (HPa)

2.90 (19.99)

2.69 (17. 77)

2.62 (18.06)

2.26 (15.58)

3.46 (23.86)

3.03 (20.89)

Page 187: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

TABLE 2: TENSILE TEST OF SPECINENS WITH PLUG WELDS

Specimen Tensile Stress on Spec. Gross Area Test Temp. Strength Gross Area No. • 2 (mm 2

) OF (oC) kips (kN) ksi (MPa) ~n.

lOa 1. 842 (1188) -20 (-29) 100.97 (449.1) 54.82 (378. 0)

lOb 1. 822 (117 5) -20 (-29) 1'05.13 (467.6) 57.70 (397.8)

lOc 1.815 (1171) -20 (-29) 114.9 (511.1) 63.31 (436.5)

lOd 1.807 (1166) -40 (-40) 99.6 (443.0) 55.12 (380.0)

-184-

Page 188: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

f-' co Vt I

-=~~~~-~-r~~~~~-~~;;:1-~~~~~,-=--~~--~:~~t:.:-.t. ----+ ~--------------,----

~~~~,---0-,,­·"' ~ .. .:'& r ---+-::!

::I ,.,

-------------------------~

Fig. 1

. v ntl/1 -:; ~

1')"

'· --~---- N

(

' '

' P+.min (I

"~ _____ J.D.~.::..O.:...AJ<LB.t.._.AA.d.mon.ta. _____________ _

Plan and Elevation of the County Highway 28 Bridge

''-------0 o-----• -.. .. Ot

"',l.i

Page 189: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

South Splice North Splice

I (a l East Elevation

95'-s" 95'-s" ss'-eY2"

Skew 42"-35'-15"

\

North ~

X' Pier3

r ""-I-57-SW \

(a) Framing Plan and Location of Beam 2B2

NEAR PIER NEAR AIIOSPAN

CROSS SECTION

(b) Cross-Section

Fig. 2 Framing Plc~ and Cross-Section

-l8G-

Page 190: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

+

! 2 • •

Ca)

... ~~ ~ ~ ...... ... -· ............. .

(b)

Fig. 3 Schematic and Photograph of Crack at the Welded Bolt Holes 3 and 4

-187-

~Bolt Holes for Diaphragm: connection

• Holes filled with Weldrnent

Page 191: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

North Splice

I,,,

\ 1/

2

. 2

Holes

~ _/1,\

'

(a)

' \ \ ·~

Beam 2B2 and Crack

Plug Weld 3

Plu; Weld 4

/

I /

/<_ 2nc1 /

Crock

( Flon;el

Oolite! Line lndieotu Croci Po1it ion Arrowa Oil Dolled Li,. lr>d,cott D11•ction of Crock

(b) Crack Initiation and Propagation from Plug Welds

Fig. 4 Location of Fracture and Crack Initiation and Propagation -lSS-

l 2

2

South sPlice

Page 192: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

,~

w 1.0 I

(a)

... -----·- ·------··-···· ....

Photograph from Direction·"a" (b) Photograph from Direction "b"

Fig. 5 Fracture Surfaces (see also Fig. 3.a for the direction in which photographs were taken)

Page 193: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I I-' \D 0 I

(a) Photograph from Direction "c" (b) Photograph from Direction "d"

Fig. 6 Fracture Surface (see also Fig. 3.a for the direction in which photographs are taken)

Page 194: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I I-' 1.0 I-' I

t/OTl: IW horix. cltmt!n.51~.,U tJr'! along ~ lx~ts.

Fig. 7 Retrofit Detail (Replacement to Beam 2B2)

I.~·, •

, ..

: \;.

Page 195: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

"' .c

--

,.. 0 ... • c

I.AJ

• 62 2 14 0

12 0

100

80

60

40

20

~0

. 17 7 44 26 7 48 9 71 I 115 5

I WT • WL 0 FM 0 FT A -~ p..----~;....-

~~., /

/ c ·"' /

i.f

~ ;:;:---- ,D

I .. v I

~/ l I v R /q w~---~ -

".~ ,....-

A' ./ ~ ~ /"' I

c ~ t).t!/ ~~ ~

-40 0 40 eo 120 160 200 240

Temp. {°F)

Fig. 8 Charpy V-Notch Impact Tests and Transition Temperature

-192-

1378 89.8 I

I 62.7

I 35.6

I oe.~

{ J)

81.3

:14.2

2

0 280

7.1

Page 196: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

8. CANTILEVER FLOOR BEAM BRACKETS

One of the earlier types of cracking that was found to develop in

highway bridges was fatigue cracks that were discovered in the tie plates

connecting transverse floor beams and cantilever brackets across the main

girders

The first such cracking was found in the Allegheny River Bridge

(I.D. 16) and was observed to originate from the rivet holes used to

attach the plate to the main longitudinal giders. Shortly thereafter,

cracks were observed in the Lehigh River and Canal Bridges (I.D. 14).

These particular cracks were found to originate from tack welds used to

connect the tie plate to the bracket prior to shop installation of the

rivets.

A summary and review of the Lehigh Canal Bridge is provided hereafter

(I.D. 14). Detailed measurements and an assessment of the crack develop­

ment was made on the Lehigh Canal Bridge. This study demonstrated that

unforeseen in-plane displacements of the tie plate, as a result of rota­

tion of the longitudinal girders at a cross-section was the reason such

cracks developed.

One other bridge experienced distress at the girder-bracket joint.

The South Bridge (I.D. 17) was found to have a number of rivet heads

cracked off. The in-plane movement of the connection plate distorted the

rivets and caused prying of the rivet heads which resulted in separation.

-193-

Page 197: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

8.1 FATIGUE/FRACTURE ANALYSIS

of

LEHIGH C~~AL BRIDGE

-- A Brief Summary --

I. D. No.

Town/City

Railway/Highway/Avenue

County

State/Province

Owner

-194-

14

Allentown, PA

U.S. 22 in Pennsylvania

Lehigh

Pennsylvania

Penn-DOT

Page 198: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

1

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief Description of the Structure:

The Lehigh Canal and River Bridges consist of two adjacent twin struc­

tures which carry the eastbound and westbound lanes of U.S. Route 22 over

the Lehigh Canal and River near Bethlehem, Pennsylvania. Each bridge is a

two girder continuous structure extending over three spans with small

haunches at the interior piers. The schematic plan and elevation is shown

in Figs. 1. a and 1. b. A side view photograph of the b·ridge is given in

Fig. l.c. The typical cross-section and tie plate details are shown in

Figs; 2.a and b, respectively.

Brief History of Structure and Cracking:

The twin bridges (one for the westbound lane and one for the east­

bound lane) were constructed in 1951-1953 and were opened to traffic in

November 1953.

During the spring of 1972, inspection by PennDOT personnel revealed

several 'fatigue cracks in the tie plates connecting the transverse floor

beams and cantilever brackets across the main girders (Refs. 1,2) as

shown in Fig. A. A more detailed description and the location of these

fatigue cracks in the tie plates is given in Refs. 1 and 3. The cracks

started at the edges of the tie plates at a tack weld which connected the

tie plates to the outrigger brackets during fabrication.

The cracks were discovered after the twin bridges were subjected to

nineteen years of traffic. U.S. Route 22 on which the bridge is ·located

carries substantial amounts of heavy truck traffic.

Page 199: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

2

2. FAILURE MODES AND FAILURE ANALYSIS

. Location of Crack, Failure Modes and Stages:

The approximate location and length of the fatigue cracks and stresses

in the tie plates of one side span are shown in Figs. 3.a and b. Through­

out the length of the Lehigh Canal and River Bridges, most of the tie plate

cracks were at or near the outside edge of longitudinal or main girders

(Ref. 1). Several of the plates had cracked across their entire widths.

All observed cracks appeared to be through the thicknesses of the tie

plates as shown in Figs. 3 and 4. All fatigue cracks initiated from the

edge of tie plates where a tack weld was used to connect the plates to the

outrigger or cantilever bracket during fabrication (Refs. 1,2). See, for

instance, Fig. 4.

A detailed study of the actual traffic conditions and the stress his­

tory measurements (Refs. 1,2,3) indicatated that the fatigue cracks

developed and propagated slowly from the ends of the tack welds, due to

out-of-plane displacements at the top flange of the main girders. These

displacements are shown schematically in Fig. 5. Corresponding strain

measurements are illustrated in Fig. 6 •

. Cyclic Loads and Stresses:

The stress range histograms for two tie plates and one of the main

girders are given in Fig. 7. The Gross Vehicle Weight distribution of

trucks crossing the structure in 1972 is given in Fig. 8.

The total number of trucks that have traveled over the bridge during

the nineteen year period bet\veen 1953 and 1972 was estimated from PennDOT

traffic count data. The AQTT is plotted in Fig. 9. This ranged from

-196-

Page 200: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

2,038 trucks per day (in 1953) to 3,709 (in 1972). The total volume from

1953 to 1972 was estimated to be 18.9 million trucks (Refs. 2,3).

The measured stress range occurrences at the gages on the tie plates

3

were used to determine an effective stress range using Miner's Rule and the

RMS* methods. These were then adjusted to the plate edges·where the crack

growth originated.

The S n~rs and S M' stress range values at the plate edge and the r~· r 1ner

fatigue cycles corresponding to the truck traffic of 18.9 million are plotted

in Fig. 10. The data from the Lehigh Canal Bridge is seen to lie somewhat

above the lower confidence limit for AASHTO Category D as shown in Fig. 10

(Refs. 2,3). The tie plates that plotted above thts limit would be ex-

oected to exhibit visible fatigue cracking.

The stress range values plotted in Fig. 10 demonstrate that Miner's Rule

and the RMS method both provide a reasonable correlation between observed

tie plate behavior and laboratory results.

The· Live Load stresses in the main longitudinal girders were similar to

those observed in longitudinal members of other bridges (the ~faximum Live Load

stress range was 55 MPa or 8 ksi). The live load stresses in the tie plates

connecting the outrigger brackets and floor beams were much higher than those

observed in the longitudinal member tthis is mainly due to the out-of-plane

displacements of the main girders (Refs. 1,2)].

Temperature and Environmental Effects (Known or field Recorded):

In this particular case there were no known temperature or other en-

vironmental effects that played a role in the cracking of the tie plates.

*Root-Mean-Square -197-.

Page 201: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Material "Fracture, Mechanical and Chemical Properties" Analyses in Failure Regions:

Since the tie plate cracks were fatigue cracks resulting from cyclic

loads and no sudden unstable crack propagation was observed, the tie plate

fracture properties were not obtained.

Visual and Fractographic Analysis of Failure Surfaces:

4

The only fractographic studies of failure surfaces were visual and low

magnification examination of the crack surfaces at the bridge site.

3. CONCLUSIONS AND RECOMMENDATIONS

The fatigue cracks that formed in the tie plates originated at tack weld

ends where high stress ranges were introduced as a result of out-of-plane

displacements. Tne cantilever load for which the bracket and tie plate were

designed did not result in a significant stress from traffic. The connection

of the plate to the longitudinal girders resulted in a secondary unaccounted

for cyclic stress that resulted in fatigue cracks. Stress measurements in-

dicated that the most severely stressed plates were near the reactions and

that those particular plates had likely cracked after a few years of service.

Cracking of the tie plates did not seriously impair the performance of

the structure as the web connection of the bracket was able to resist the

applied loads.

It was recommended that the structure be retrofitted by removing the

existing cracked and uncracked tie plates and replacing them with new plates

that were not attached to the longitudinal girders .

. -198-

Page 202: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

5

4. ACTUAL REPAIR AND FRACTURE CONTROL EFFORTS

The tie plates on the Lehigh Canal and River Bridges were replaced

with new tie plates during the bridge deck replacement that was undertaken

during 1977 and 1978. This involved removal of all existing cracked and

uncracked plates and replacing them with the plate shown in Fig. 11.

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

In the new tie plate configuration as shown in Fig. 11, the bolts

connecting the tie plates to the main girders are eliminated. Thus, the

out-of-plane displacements of main girders under Live Loads will not influ­

ence the tie plate behavior. Therefore, no adverse effects due to replace­

ment of tie plates are expected.

6. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

Cost of Investigation:

The total cost of investigations of causes of cracking producing both

the laboratory and field investigations is not available. However, the

field investigation only was estimated to cost $4,000.00 by PennDOT.

Cost of Repair/Rehabilitation:

It was estimated that $29,787.00 was required to make the necessary

retrofitting and corrective action during the time period in which the

reinforced bridge deck was also completely replaced.·

Original or Adjusted Cost of Structure:

The .initial cost of the structure is not available, as it was built

as part of a large section of Route 22 and only the total cost of the con­

struction is available.

-199-

Page 203: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

7. REFERENCES

1. Fisher, J. W., Yen, B. T. and Daniels, J. H. "Fatigue Damage in the Lehigh Canal Bridge from Displacement Induced Secondary Stresses" Fritz Engineering Laboratory Report No. 386.5, Lehigh University, Bethlehem, PA 18015, 1976.

2. Fisher, J. W. "Fatigue Cracking in Bridges from Out-of-Plane Displacements" Canadian Journal of Civil Engineering, Vol. 5, No. 4, 1978, pp. 542-556.

3. Fisher, J. W. and Daniels, J. H. "Field Evaluation of Tie-Plate Geometry" Fritz Engineering Laboratory Report No. 386.4, Lehigh University, Bethlehem, PA 18015, November 1974.

-200-

6

Page 204: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

<l; Q' ~~ ii ·rr !'Y, Q' Q; Q'

0: " ~ ~~ :..VVt.\'lt S truc.l• rr !! E'o.sl s I fVC~!!!!---~ ).· <t&, ,; -J ~i{ 97';; _IQJ{g"

...;ft} It I

~d :./v:_.,!d~r ~ PMfJiil: ___ -r~f-o· 106'·0" ll.6'0- IJ7'·0" '/'0" ... .'· ''''") ...; I lsL -~--{&upper~cing]

I I !AsrAN e I srAN < ~r-~Ql (':II') ~fY~~ 9 15f'/I.'V ,., SrAN. I srAN 21 SPAN J SPAN 4 ' SPAN 6 SPAN 7

r:~ ··r: P.~-- . "'r"'"l"" ;r ,.; __ / I\..: i! 1{

l r il ;; I! i: :~ -~ . I' ; :'!ii : , '0

'• I: !' " I I I ,. ~9~ I H;; II (j- =I

" \·:·.\ II 1/ I'' i!,b--0 H I I

il I I 1 i.: !! I 'I I~ I• :~ :LlJ1ij~ ! ! I : I' ll I I'

II I' .._,_._, 0. ' j. : xi•,t f),ff Hr:•

,-m~ 1 '11. ( (.f'·•v'l,

' II [r:11l /IJII t\·u-;,

'r. '·•'l•l•n

l f? 1 ,.,,..,in ' 111 'lt h.llrl ,l·nf

~/;~· r;lc.Ju.•

I 60' , __ _

11i <;f:HtPTI(]fJ

Fig. l.a Plan and Elevation of Lehigh Canal and River Bridge

Page 205: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Diagonal Bra ces

T s(Q)s'-6" =27'-6"

(5<PJI676.4_l = 8382)

\ \

\Y X

I \ Ll

\ \

\

Floor B / eam

7

~I \ I y X I\ 7 \

Long.

trmgers \. 1\ Girders s .

• \ I \ 7 \7 \ y y y \

1\. 1'\ 7\ \

3'-3" ( 991) j_

t 21'-o" cc Girders ( 64 0 I) _i

,_ ' ~--'-___ 8_P_an_e_ls_...::.@_.....::l8_' _= _14_4_'-.....::o_" ___ ...., .. ~l3'-3" ( 9 91) . (5486) (43891)

Measured } ksi Sr- HS20 Test Truck Mpo

"

21.3

147

13

90

PLAN VI.EW

(Deck Not Shown)

I 14

98

11.4

79

8.4 19.3 22.3 26.5

5s· 133 154 183

~~~~~~~~~~~~~l

Abutment C · so'-o" ( 15240)

ELEVATION VIEW

Pier lA

Fig. l.b Plan and Eleyation of the Side Span

-202-

1 s·-o~"' (2 4 51)

Page 206: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Fig· 1.C

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Page 207: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I

I ~~J 3-94

(1149)

14'-o"l (1219)

li-o" (3658)

W27x94 Tie£

(640 I) (1753}'

Fig. 2.a Cross-Section of Lehigh Canal and River Bridge

Floor Beam

Tie If. ((254 x 12.7)

11 1 1 Longitudinal IO x 2 Girder

(686). (991)

Section A-A

Flange of Brocket

I

Fig. 2.b Tie Plate Detail at Floor Beam Bracket Connection to Girder

-204-

Page 208: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Girder EN ~irder ES ~ i

1::::·.1-·::::J l::::·.j.·::::l I I

lA ~·- ·1 : .. : ·1 Pier.~:±_·-------? ~ · · . · .. .. . lA ~ · + ·=::::::::::::J

c 7 I" .. {. I' .... "I I

. . . . . . . . . . . . . . . . . . . . ... I

C6 I : : : :'. -1-- : : : : I C5 I : : : : .. i .. : : : : I

I : : : : · .j.-' : : : : I I

I : : : : · .j.-': : : : I C4 ..........

C3 . . . . . . ....

C2

Cl

East Bound

. . . . . . . ... Lanes .

1

. \Tie Plates

1::::· .. \:::1 . I

..... Location 2

C +·· ·;-!·-· · · ·1 · --tl.,;c"oiiOn 1~£3-~·. '."" ••• •. _ •••• ·.·~·.:....!.,_

ABUTMENT C

Fig. 3.a Schematic Showing Typical Cracks in the Tie Plates of the West End

of the Eastbound Span

-205-

Page 209: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

lA

C7

C6

C5

C4

C3

C2

Cl

co

Fig.

Girder EN

t I . . . . .,

• • • I t

10.8 ksi , (74.5 MPa) .... ... . . . . . I . . . . . . . . .....

. . ... . . ...

. . ... . . .

. . ... . . ...

. .. . .... I t t t t . . ... . . ...

. ..

East

Girder ES

t I . . . . . I • . ... . . . . . . . ..

. t .. . . ~ .. . . . . ...

. . ... Abutment C

3.b Schematic Showing the Tie Plates of

Stresses the West

of the Eastbound Span

-206-

in End

Page 210: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

.. .:..--·· ... .J_/;;7_- .~ _:::::~:~-·

~:~~~~-·-·:~2~,~~~-~·;;r_!_~._~· .. ·~;~~

~~~3.~~:~;;:i~::~~<r~~~ --;:--.. ··

Fig. 4

... '-

\

Crack in r· ~e Plate 0 riginating

-207-

at Tack \..Jeld

Page 211: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

j r-.6 r------f ~=====:= b-.==·====

A fr-f~;::=::==:t A

Girder ~---NA --

Girder -~---

Stringers

A-A

Bending Stresses in the Plate

Fig. 5 Longitudinal Displacement at Top Flange of Girder and Horizontal Bending of Tie Plate

-2os.:.

Page 212: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

<t End Span

~~rain - ~ 0

Slope

1- 4681

(142646).

( Approximately 5.3 S at 60 mph 96.6 km/h)

Strain Near Interior Support

I I 0

Slope

A ~ :::::::::=-A

I~ 468 I 142646)

6s

Fig. 6 Comparison of Measured Strain History in Tie Plates with Influence Lines for Girder Slope

.-209-

• I

6s

• I

Page 213: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

18

16

14

12

10

8

6

4

:t

18

16

14 Tie Plate C6N Gage 9

12 78.65%:0.9-3.0 ksi

6.2-20.7 MPa 10

o/o 8

6

4

2

0 3.0 4.5 6.0 7.S 9.0 10.5 12.0 13.5 13.5 ( k s i)

20.7 31.0 41.4 51.7 62.072.482.7 93.1 93.1 ( MPc) ·

err

18 ~

Girder EN 16 Tie Plate C4S Gage 5

r-Gage 15

r- 34.37 °/o: 1.5 -I .95 ksi 14 3.4 MPa

!""'",....

r-

1.9:'oZ.Z:!Z.!>:!2..tl!> :2.102..'-0VO z.e:. II! !Jill

10.3-1

( kso 1

1:3.415.517.!>19.7 (M?c) 11..5 16.518.6 19.7

12

10 o;o

8

6

4

2

0 3.3

59.67%: 1.5-3.3 ksi 10.3-22.8 MPo

-

,........ 5.1 s.s e.7

"'·' 6.0 7.8 9.6 9.6 ( ks i)

I . I I I I I 1

c.c..e :.~.z 47.6 6o.o 66.2 ( MPo)

29.0 <ll.4 ~3.s ss.c.

Fig. 7 Stress Histograms

-2:10-

Page 214: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

13

!2

I I

10

4t-

2t-

r-, I I

I

I

Li I I t

L-, I I

--- 1970 FHWA Nationwide Survey

- 1972 PennDOT Loodometer Survey

-..,

-I I I I L,__

o~~~· ~I ~I~~~~~~~~~~~~~~-~~ 20 28 36 45 55 65 75 85 95 105 >110 .

24 32 40 50. 60 70 80 90 100 I !0 (kipS)

89.0 !24.5 160.2 200.3 244.8 2e9.3 333.8 378.3 422.8 467.3 > 489.5 ( KN) 106.8 142.4 17a.o 222.s 267.0 311.5 356.0 400.5 445.0 4e9.5

GROSS VEHICLE WEIGHT

Fig. 8 Gross Vehicle Weight Distribution

Page 215: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

(4.5%) "- •- ......... .. ':v .... -

ADTT (in 1000)

-(1.5%)" .......... -~ _.---------

-· ·-· ·--

1953 55 60 65 . 70 72 YEAR

Fig. 9 Estimated ADTT at the Lehigh Canal and River Bridge Site

Sr 5

( k 5 i) .

.......... -...

......._ /-95% Confidence - Limits

-. ....... ....... .........

........ ....... .......

L.:y '0 " -- --AASHTO .......

..........

RMS Miner Cracked • • .&.

No Crack o !::.

10

N · ( x 106 cycles)

-... f ~ss-- ....... --1 -C6S

-....;:;CIN

~ -c:;s -0 -C6N

20 30

Fig. 10 Comparison of Est-imated Equivalent Stress Range with Laboratory Test Data

-212-

150

100

50

Sr (MPa)

10

Page 216: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

!.......:• 1-' l·)

I

,e·- •

~· 'P 4· 1>-

___ J

1

____ ,e~o·

~ j~r~!

TIE PLATE DETAIL AT PIERS 3.4./A cf 2::l_ONLY Scull! I e'-1'·0"

NOTES: I. [,-lsring tu: phtes,fillt.r p!alu,onrl COtfOcd/Dn ri~els eho/1 be.

rrmo•·t'rl.

Z. Bolt roifcrn shall b-> os sho•-n, Contractor Y>oll verify spacin9 in the fii:lcl to insc1re proper march wit!} exist in<] hc*s m hrot:ht?t ( floor beam.

1 ro,~ w~ldin9 along tfl< edqes of the tie pbte" will no1 be

1_ 1ez· ___ J, __ --:;19,_.,..· .-----J----"'-'---1 I= ------"':§:___ __ ------1

pt!rmi' fe.d. ·

4. The. ""V lift. p/nht. artt// cl~ttr 1/w. mffds o/ fllf. 'lt:W fi:ta~th in fJtc._ 9;,.r(i',S. f'ill~r p/nln. lW'f. rw'luirttl D~r lht r:trs p"t/ tJI IM. qc/.tfN.c.td floorhtam3 1'7~- /l'lrf,.r:alt'.r:/. AdcJ,I,{,,.,a/ (.1/r.r plalt.':!J eholl b~ fl)rn:~hc.cl iF ~nc/..,.~ rt.1o:rt.<l lut~ch,f! ... ·c.lt~rll~~ ollht lh/r~ {tJiklh, tJtw/lillh lloorhr.on1 from rneh t.nd bt.or/ng.

Fig. 11

5.F-n0r to placti'g lh! nt.r,• lit! pl",/z-)1 'h~ ,.;,.,{~ wlu'ch ,..,,.,..,. rr"'"~-'~d

fto,.., IJ, moin 9irdr.r.! oh?l! L• rt:,PI•::u·~...,· wilh lt. S. holi~ 7nd lhP.. lira~ of !/Jr. holl.11 lhr Joi,l OrYO en lllr 1,,", . .1_/"!1 r.:&-'~J qird~r."'J on?' lh~ und~reir:le. of I~ nrw ~;,. plai~:J "!>hrY/1 be, r;/~r,nv.d ond p,;..,reo' ,;., accort:l?ncv. wdh lhe Sp::ci-:71 Proy;zic:n~.

Retrofit Detail for Lehigh Canal and River Bridge (Note the change in Tie Plate Detail and Configuration)

Page 217: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

8.2 FATIGUE/FRACTURE ANALYSIS

OF

ALLEGHENY RIVER BRIDGE

-- A Brief Summary --

I.D. No. 16

Town/City near Pittsburgh, Pennsylvania

Railway/Highway/Avenue: Pennsylvania Turnpike

County

State

Owner

Pennsylvania

Pennsylvania Turnpike Commission

.-21~-

Page 218: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

1. DESCRIPTION A~~ HISTORY OF THE BRIDGE

Brief Description of Structure:

The Allegheny River Bridge is a four-span continuous beam-girder

bridge and a five-span truss bridge over the Allegheny River outside

Pittsburgh, Pennsylvania on the Pennsylvania Turnpike. The bridge deck

carries both eastbound and westbound traffic. The top view and side view

of the bridge is shown in Figs. 1.

1

The plan and elevation of the end span and the second span of the

four-span continuous girder bridge is shown in Fig. 2. A typical cross­

section and the original tie-plate details for the floor beam bracket

connection are shown in Fig. 3. The end span is 104 ft.- 4 in" (3~.822 m),

and the second span is 130 ft.- 5 in. (39. 777 m) long. The end span con­

tains a hinge 78 ft.- 3 in. (23.866 m) from the west abutment, as shown in

Fig. 2. The longitudinal girders are 7 ft. - 0. 5 in. (2 .148 m) deep with a

haunch at the piers of 9 ft.- 1.5 in. (2. 783 m).

The reinforced concrete slab in the end span is supported by twelve

longitudinal Wl2X62 stringers resting on the floor beams and outrigger

brackets. The floor beams are composed of built-up I-beams (web:

66in. x 3/8 in. (168 em x .10 em), flanges: 6 in. x 6 in. x 0.5 in.

(15 em. x 15 em. x 1 em) angles with outrigger brackets (see Fig. 3).

Ihe second span has a similar load-carrying system.

The original tie plate detail [14 in. x 0.5 in. x 4 ft. - 8 in.

(35.5 em x 1.27 em x 1421 em)] which connected the floor beam top

flange to the outrigger bracket flange is shown in Fig. 3.b.

-215.-

Page 219: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 2

Brief History of Structure and Cracking:

The Allegheny River Bridge was constructed in 1952. During the fall

of 1971, preliminary inspections by the Pennsylvania Turnpike Commission

personnel revealed several fatigue cracks in the tie plates (1). In

January 1972 all tie plates were again checked for fatigue cracks. The

approximate locations and length of cracks in the end and second spans is

given in Fig. 4. It was also observed that some of the rivets connecting

the tie plates to the first inboard or to the first outboard stringer

failed. These rivets are indicated by darkened circles in Fig. 4 (1).

A typical cracked tie-plate is shown in Fig. 5.

In the spring of 1972, the original_ cracked tie plates were repaired

with groove welds and reinforcement tie plates were added as well.

_-216-

Page 220: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 3

2. FAILURE MODES AND FAILUE ANALYSIS

Location of Fracture, Failure Modes and Stages:

The location and approximate lengths of the fatigue cracks in the tie

plates in the end and second spans are shown in Figs. 4.a and 5. Most of the

cracks were at or near the piers and abutments, i.e. near the supports.

All cracks originated from rivet holes in the region where the tie plates

were connected to the main longitudinal girders (see Fig. 4.a).

A detailed study (1) of the traffic conditions and stress history

measurements indicated that the fatigue cracks initiated and developed

from the tie plate rivet holes due to horizontal in-plane bending of the

tie plates. This horizontal bending was induced by the longitudin?l dis­

placement of top flange of the main girder under traffic loads. Similar

cracks due to out-of-plane displacements were also observed in the Lehigh

Canal and River Bridge on U.S. 22, near Allentown, Pennsylvania (2).

As shown in Figs. 4 •. a and 5, some of the tie plate rivets (indicated

by the filled circles in Fig. 4.a) became ineffective or failed completely.

Cvclic Loads and Stresses (Known or Field-Recorded):

A strain gage recording of the strains in the tie plates of the

Allegheny River Bridge was undertaken from November 10, 1972 to November 17,

1972 (1). The position of strain gages are shown in Fig. 4.b. From these

recordings several stress range histograms were developed. A typical

stress range histogram for the tie plate (gage 18) is shown in Figs. 6.a

and b (1). All tie plates provided stress ranges in the order of 12 to

18 ksi ($3 to 124 HPa).

-217-

Page 221: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 4

Stress distributions in the tie plates in~icate that the cracked

plates were subjected to high bending stresses in a horizontal plane, as

shown in Fig. 7. The measured stresses suggested that the horizontal

bending was induced by a relative movement between the girder and the ends

of the tie plate. The stress range distribution caused by a truck at each

of the gaged tie plates is shown in Fig. 8. Bending stresses in tie plates

were higher near the abutment and pier. This agreed well with the cracked

tie plate pattern shown in Figs. 4.a and 5.

Very low live load stresses were observed in the main .girders and the

floor beams. The main girder stresses as a result of an HS20-44 truck in

one lane of the bridge provided a maximum live load stress of 2.4 ksi

(16.54 MPa) and a stress range of 4.65 ksi (32.04 MPa). Both of these

measurements were well below the calculated design live load stress

9.6 ksi (66.19 MPa) (1).

Traffic counts were also taken during the in-service testing in 1972.

The results are given in the histogram of traffic flow in Fig. 9 and also

in Fig. 10. The survey was comparable to the 1970 FHWA Nationwide sur-

vey (1). The total volume of truck traffic that crossed the bridge durtng

the twenty years of service between 1952 and 1972 was 20.7 million vehicles.

This corresponds to at least 20.7 million cycles of loading for each tie

plate. The number of cycles for the truncated (SRM) root-mean-square

stress ranges when stresses below the crack threshold are neglected are

tabulateo in Table 1. The estimated number of RMS stress range cycles for

several tie plates are also plotted in Fig. 11 (1).

-218-

Page 222: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

~Tien all stress cycles were considered, the effective stress ranges

decreased and are also plotted in Fig. 10 at 20.7 x 10 6 cycles.

5

The (~1S) and Miner effective stress range procedure was used to cor­

relate the tie plate behavior with available test data. Table 1 and

Fig. 11 both indicate that reasonable correlation was obtained between

the observed behavior and the measured stress range spectra. Both the RMS

and Miner effective stress ranges and the cumulative stress cycles sug­

gested that fatigue distress should develop in the tie plates.

Temperature and Environmental Effects (Known or Field-Recorded):

In the case of the Allegheny River Bridge, there were no suspected

or recorded temperature or other environnental effects that influenced

cracking of the tie plates.

Haterial "Fracture, Mechanical and Chemical Properties"·

Analysis in Failure Regions:

The tie plate cracks and failed rivets were all fatigue induced due

to horizontal bending of tie plates. No sudden, unstable crack propaga­

tion was observed. The fracture toughness of the tie plate material was

no.t determined.

-219-

Page 223: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Visual and Fractographic Examination of Failure Surfaces:

The failure surfaces were only examined visually. The crack surface

showed clear evidence of fatigue crack growth.

Crack Growth (Initiation and Propagation) and

Probable Causes of Fracture/Failure:

The fatigue cracks initiated and grew from the rivet holes in tie

plates. Some of the rivets in the tie plates were cracked ~s a result

of horizontal bending in the tie plates. The stress distribution pattern

in tie plates indicated that horizontal bending of. tie plates was induced

by the relative longitudinal displacement of top flange of the main girder

and the floor beam under cyclic live load as shown in Fig. 7 (1). The

locations of cracked tie-plates are indicated in Fig. 4.a, and a typical

tie plate with cracks initiated from rivet holes is presented in Fig. 5.

-220-

6

Page 224: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 7

3. CONCLUSIONS AND RECO}lliENDATIONS

Conclusions Regarding Fracture/Failure:

All fatigue cracks found in the tie plates of the Allegheny River

Bridge originated from ri~et holes; most of the cracks were located near

the piers or supports and were formed where tie plates, connecting the

brackets and floor beams, were riveted to the main longitudinal girders.

The fatigue cracks developed due to the out-of-plane displacements which

introduced high horizontal bending stresses in the tie plates (1). The

connection of the plate to longitudinal main girders resulted in secondary

cyclic stresses causing the fatigue cracks in the rivet holes.

Stress relief in tie plates was accomplished naturally under service

conditions through the shearing of some of the rivets as well as by the

fatigue fracture of the tie plates (1,2). Fatigue cracks in tie plates

have occurred in other birdges under similar circumstances*.

4. ACTUAL REPAIR/FRACTURE CONTROL EFFORTS

During the spring of.l972, reinforcement tie plates

[17 in. x 0.5 in. x 4 ft.- 7.94 in. (431.8 mm x 12.7 mm x 1420.9 mm)] were

added to the structure. The original cracked tie plates were first groove

weld repaired at the crack locations, and the rei~forcement plates were

·placed over them. The bolt holes in the reinforcement plates were matched

to those of original tie plates for ease of installment. The reinforcement

plates were high strength bolted to the original tie plates, girders,

floor beams, outrigger brackets, and the neighboring stringers as sho~~ in·

Fig. 12. Also, the lock nuts are tack welded .

.;, see FATIGUE/FRACTURE OF LEHIGH CA~AL A:\D RIVER BRIDGE -- A Brief Summary Lehigh University, Fritz Engineering Laboratory Report 448, 1981.

-221-.

Page 225: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

From the approximate analytical and field measurements given in

Ref. 1, it can be concluded that increasing the width of the tie plates

will cause the horizontal bending moment in the tie plate to increase due

to the elongating and shortening of the girder. Also, depositing tack

welds at the lock nuts decreased the fatigue resistance.

Since the cause of longitudinal displacement at the tie plates has

not been eliminated, horizontal bending stresses will continue to be

developed at the edge of reinforcement plates. Tack welds are expected

to initiate fatigue cracks. Similar cracks developed from tack welds and

were observed in the Lehigh Canal and River Bridges (2,3).

6 .. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

At the time this "Brief Summary" was being prepared no estimates

regarding the cost of investigation of cracking, costs of retrofit and

the original cost of the bridge were available.

:-222-

8

Page 226: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

7. REFERENCES

(1) Marchica, N. V. STRESS HISTORY STUDY OF THE.ALLEGHEh~ RIVER BRIDGE­PEh~S1~VANIA TURNPIKE, M.S. Thesis, submitted to Lehigh University, Bethlehem, Pa., May 1974.

(2) Fisher, J. W. FATIGUE CRACKING IN BRIDGES FROM OUT-OF-PLANE DISPLACEMENTS, Canadian Journal of Civil Engineering, Vol. 5, No. 4, 1978, pp. 542-556.

(3) Daniels, J. H. and Fisher, J. W. · FIELD EVALUATION OF TIE-PLATE GEOMETRY, Lehigh University, Fritz Engineering Laboratory Report No. 386.4, November 1974.

-225-

9

Page 227: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

TABLE l RMS AND MINER STRESS RANGE AND CYCLE DATA

FOR TIE PLATES

Adjusted Adjusted Number SrRMS SrMINER Cumulative of

Stress at at Frequency Cycles Rivet Hole Rivet Hole (% above Plate Gage ksi (MPa) ksi (MPa) Threshold) X 10 6

ABUT 3 6.4 (44.1) 7.3 (50. 3) 61.20 20.7

ABUT LT ll 6.5 (44.8) 8.6 (59.3) 26.72 20.7

3A RT 15 5.7 (39.3) 6.6 (45.5) 55.00 20.7

. 5 RT 18 7.1 (49. 0) 8.4 (57.9) 49.86 20.7

-224-

Page 228: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

' I !

Fig. 1 Side View of Allegheny River Bridge

. -225-

Page 229: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I N N 0'> I

0 2 3 3A 4 5 6 7 8 9

-

F -==

1- - I-- I-- I-- - - -= f--f.-- =- - - f- ~- -==--=

--

l< ·----~ ·_@ ___ '?JL:J~~-------------*----- -----~-~-~~~:e --->t lk<~------JQ'f! __ -:- 4-'' ----->k·--------- 1'30'- 5 1

' ' ----'-·--·---------------------------···--->l

' --------------

Fig. 2 Plan and Elevation of Allegheny River Bridge - Test Spans

Page 230: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

56'-o"

· 4'-o" I -- _---=:1-l..t=. -----

Fig. 3.a Bridge Cross Section

't Brocket

~ '32.5" +3f.s" 1

Fig. 3.b Original Tie-Plate Detail

.-227-

Page 231: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I()

"t I

N h . .l <1 ())

I<) I

r<l

C\J

0

Fig. 4.a

0 0 0 0 0 0 c 0

--00 o-o-o--r:· 0

I 0 o.

0 -j __ ___9 Q __g~ __ c·: ~ 00 00 0 0 '1. 00

oq .g:>-H--{~r~ 0

0 0

Cracked Tie Plates and Loose Rivets in Test Spans

v

<1 r<l r<l

0

~-:-z-6--~~~ (\( (> 00

0

Fig. 4.b Strain Location and Identification

Page 232: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

.•.

~··

Fig. 5 A Typical Cracked Tie-:-Plate of Allegheny River Bridge

-229-

Page 233: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I tv I_,)

0 I

9t-

8t-

7t-

6t-

5t-

0/o

4 t-

3t-

2t-

It-

GAGE 18 0.9-3.9 ksi: 77.99% 3.9-14.4 ksi: 22.01%

1---

1--

0 3.9 5.4 6.9 8.4 9.9 11.4 12.9 14.4

or ksi

Fig. 6.a Stress Histogram for Gage 18 (Tie Plate RT-5)

8

o;l 6

5

4

3

2

GAGE 15 0.9-3.3 ksi: 74.37% 3.3-11.7 ksi: 25.62%

0 3.3 4.5 5.7 6.9 8.1 9.310.5 11.7

err ksi

Fig. 6.b Stress Histogram for Gage 15 (Tie-Plate RT-JA)

Page 234: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I lv l..J

/ I

Fig. 7

-11.4

,/+0.6

I I I

+ 10. '2

I

I /

'··,~> ... . / ..... .,· ...

ORIGINAL TIE PLATE.

Stress Distribution in Tie-Plate R-5

I

I •

~!f__:__ ·~ !__;_ ~-~- __ o o 1-~

0( ·!~.~--­·o £--: 0 r 0 0

~ .. ·:-'-;-----::1-'

-1:!:-----::.::-0

I I -- ·- ~. - 0 o_ -- ,. -

~<'---.~

·o•,.. ,.•·o~ .

- I - ,_;·--_,,----=,.,..,----o ~~-Ci£r ~-:1 -----1~-:--- •: "i:b;.I:D - • -t- L_.;.:_ __ ;:_ ___ .--"'-'1

/

Fig. 8 Instantaneous Stress Pattern in Gaged Tie Plates

Page 235: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

r---

-

~ 'lO 2.0

~ "' >-v

I X w

N :;) 15 LJ cr ,,_,. I w

a:: u. I

,. \) z IU IS ::> 0 lU

"' .....

I

10 10

5

0 1-----.. 0 1.-. 30 100 >IOO 30 '+5 80

~l\05S VOllCLE WEtC.HT > Klf5

(Eastbound Lanes) (Westbound Lanes)

Fig. 9 Histogram of Traffic Flow of Allegheny River Bridge During Test Period

Page 236: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I 1'-' w L.J I

10. 0

9.0

8.0

7.0

;f.

>­u6.0 z w ::> 0 w5-0 0: "-.

4.0

3.0

2.0

1.0

r-

r-

.--

,......

..---

1-

1-...-- ...--.__

1--

'

1-

t-

n-, 0 20 28 36 45 55 65 75 65 95 05

24 32 40 50 60 70 80 90 100 I IIO>UO

..- _ ~RO~~ V_EHICL~ WEJGHT,Kips

(Loadometer Survey 1972 PennDOT, 20 Stations)

4.01-

3.0 f-

~ >-u z w ::> o2.0 w 0: LL.

1.0

25 35 45 55 65 75 85 95 0 20 30 40 50 60 70 80 90 100

. GROSS VEHICLE WEIGHT, Kips

(Loadometer Survey - 1970 FHWA, Nationwide)

Fig~ 10 Results of Loadometer Survey

Page 237: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Ill ....:

w (!) z <( 0::

(I) (I)

w 0:: .... (I)

I z N 0 w .... .c-. 0 I w

(I)

I-w z

• 0 +0 If! If! 0 0

"------ + + ' 0 • 0

x ~.1'3"' •otto + ._ • + 0 oo •::;' • o 0o' ~ *+0 lh "\ 0 •• •• 0 ~ 00

jl 0

0

• Category 0_/--....... -.._+ ~-AASHTO # 0~'kLl+ t+ • • + 0

ob/cr (bearing ratio)

{ .

Normal o Clamping :

1.37 • } . 1.83 cjJ 2 _74 + Reduced Clamping

2.36 + x 3.8 (exceeds limit of 1.5 <Tu P) 6 Full Scale Tests (failure)

+ Full Scale Tests (small crocks)

5

CYCLES TO FAILURE .

• -

Fig. 11 Tie-Plate Response and Laboratory Fatigue, Test Results

o­-

Page 238: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 12 Reinforcement and Original Tie-Plates (Bottom View)

·-235-

Page 239: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

9. TRANSVERSE STIFFENER WEB GAPS

Cracks were found during construction at the ends of transverse

stiffeners on several plate girder bridges. A detailed summary of two

Cuyahoga County bridges (I.D. 41 and I.D. 42) is given hereafter.

The results of the investigation of this cracking showed that the

primary cause was out-of-plane movement of the short web gap at the end of

the stiffeners and the flange.

Similar cracking at the ends of transverse stiffeners was detected

in other bridges (I.D. 114). In this case the cracks were found to have

formed in the fabricating shop, while the girders were handled (I.D. 114).

Cracking of a similar nature was found in web gaps of intersecting

vertical and transverse stiffeners. These cracks occurred as the large

web plate was moved and turned in the shop (I.D. 53).

In all of these cases handling resulted in high cyclic stresses in

the girder webs at the short gap regions. These cyclic stresses either

occurred as the girders we-re handled in the shop or developed as the

girders were shipped. The swaying motion of the girders supported on

rail cars created high repeated stresses at the weld terminations in the

web gaps.

-236-

Page 240: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

9.1 FATIGUE/FRACTURE ANALYSIS

of

CUYAHOGA COUNTY BRIDGES (CUY-90-1365L)

-- A Brief Summary --

I.D. No.

Town/City/etc.

Railway/Highway/Avenue

County

State

Owner

41

Cleveland, Ohio

Interstate I-90 over Conrail Tracks

Cuyahoga

Ohio

Ohio-DOT

-237-

Page 241: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief Description of the Structure

The Cuhahoga County Bridge (CUY-90-1365) carries Interstate I-90 traf­

fic over the Penn Central Railroad yard tracks in Cleveland, Ohio (Fig. la).

The superstructure in each traffic direction is composed of nine continuous,

built-up steel girders with an 8-1/2 in. (215 mm) reinforced concrete slab

extending over several spans. The eastbound and the westbound traffic is

separated by a concrete guard wall placed along the centerline of the roadway.

The structure has three main spans with lengths of 135 ft. (41 m),

140 ft. (43 m) and 93 ft. (28 m). The two side spans are 88 ft. (27 m)

and 62 ft. (19 m) long. The plan of the structure and the elevation is

given in Figs. la and lb. The main girder arrangements, the transverse

and lateral bracing, and the cross-sections are given in Figs. 2, 3 and 4.

The structure was designed in accord with the 1965 AASHO Specifications

including Ohio-DOT Supplements. The design loading was the HS 20-44 truck

and the_Interstate Alternate Loading. The mainline ADT in 1970 was 50,738.

The structural steel is ASTM A36.

Brief History of Structure and Cracking

On May 1-3, 1972, during the erection of steel girders on the east­

bound portion of the Cuyahoga County Bridge (CUY-90-1365) an inspection by

Ohio-DOT personnel revealed cracks on some of the erected girder webs on

the eastbound bridge near the abutments. All of the· steel superstructure

for the eastbound structure and the first span of th_e westbound bridge

were erected. Erection of the remaining steel was stopped so that a

-238-

Page 242: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

thorough inspection and rechecking of all girders by MPI (Magnetic Particle

Inspection) and by dye penetrant could be made. The cracks were of two

kinds as shown in Figs. 7 and 8.

A sample plug was removed from Girder 138Gl at stiffener 13. This

sample plug contained both types of cracks. Figure 9 shows one side of the

web prior to the removal of the sample core. The crack which formed in the

girder web at the end of the weld toe can be seen in Fig. 10. Figure 11

shows a. cut through the core sample with a polishe4 and etched surface of

the half section. Both types of cracks are visible in the photograph. The

cracks tend to turn and move up the web as they increase in siz~.

The field examination of other girders with. cracked details exhibited

similar characteristics.

All evidence from the field inspection and subsequent laboratory

studies on the sample core removed from Girder 138Gl indicated ~hat the

cause of cracking was cyclic loading. The cracks were fatigue cracks. No

brittle behavior or cleavage fracture was observed. Relatively large out­

of-plane cyclic web bending stresses were introduced into the girders dur­

ing rail transportation on a flat car _(see Fig. 12) from Columbus, Ohio,

to the bridge site. The cyclic displacement resulted in high stress ·range

excursions in the web gap of stiffeners adjacent or at the support points.

Cyclic Loads and Stresses (Known or Field-Recorded)

The cracked girders were shipped after fabrication from Columbus,

Ohio, to the Cuyahoga County Bridge site by rail and truck transportation.

The girders shipped by rail were arranged together as shown schematically

--239-

Page 243: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

in Fig. 12. Host girders were supported at two locations using wooden

blocks and tie down rods.

The cracks were only observed in the girders which were shipped to the

construction site by rail. There were no detectable cracks on the girders

shipped by truck. No defects were found when the web gap at the stiffener

opening was near the top flange. The cracks on the rail transported

girders all occurred at stiffener locations. approximately 25-30 ft.

(8-9 m) from the center of the girder. This placed the cracks at stiffeners

adjacent to the wooden supports on which the girders rested during trans­

port on the gondola car.

The crack locations are indicated in Figs. 5 and 6 (3).

Several core type specimens were removed from cracked regions-. Rec­

tangular specimens were removed from the web near the abutments in order

to determine the fracture properties of the steel. These specimens were

shipped to Lehigh Universitj for testing and evaluation (4).

2 FAILURE MODES AND FAILU.RE ANALYSIS

Location of Fracture, Failure Modes and Stages

The cracks were only observed in positive moment regions at the end of

stiffeners cut short of the bottom flange. ~~en cracks occurred in stiff­

ener details cut short of the bottom flange, they were always observed to

be near the girder support points during the rail tr?nsportation. The

stiffeners were attached to both sides of the web which resulted in cracks

on both sides. ~vo types of cracks were found.

-240-

Page 244: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

1. Cracks at the end of the stiffener weld wrapping around the

weld toe and extending parallel to the longitudinal axis of

the girder as shown in Fig. 7.

2. Cracks at the end of the stiffener in the weld which sometimes

extended into the web as illustrated in Fig. 8.

Since only vertical tie down rods were used to support the girders,

they offered little restraint to lateral movement of the girder sections.

Consequently, local twisitng of the girder flanges at the girder supports

would result in relatively high out-of-plane web bending strains in the

web gap at the cut-short stiffeners near the support points (4). This

cyclic out-of-plane movement of the web and the resulting cyclic stresses

caused the development of fatigue cracks at the stiffener ends near the

wooden blocks. The out-of-plane movement of the web is shown schemati­

cally in Fig. 13.

Temperature and Environmental Effects (Known or Field-Recorded)

In the case of the Cuyahoga County Bridges, the temperature and the

environmental effect did not contribute to the cracking of the girder webs

at the end of transverse stiffeners.

Material "Mechanical, Chemical and Fracture Properties" Analysis

in the Failure Region

The material used in the girder webs of the Cuyahoga County Bridges is

the ASTif A36 steel. Mill reports indicated that the steel met the mechani­

cal requirements of the ASTI1 standards .

. -241-

Page 245: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

The fracture toughness of a typical girder web was determined by mak­

ing transverse Charpy V-notch (CVN) tests. The small section removed from

Girder 172Gl was used to fabricate CVN specimens which are summarized in

Fig. 14. At 40° F (4° C), the average absorbed energy was 16.8 ft-lb. (23 Nm)

The results indicated a good toughness in the girder web material (4).

Fatigue crack formation in the girder webs without evidence of rapid

fracture was compatible with the measured toughness of the girder web

steel (4).

Visual and Fractographic Examination of Failure Surfaces

The fracture surface topography from the sample plug shown in Fig. 10

was examined under the electron microscope. Figure 15 shows the fatigue

striations that were detected in the web at the weld toe of the far side

stiffener (4). The fatigue crack had propagated 0.2 in. ( .5 mm) into the

web at the weld toe. The striation spacing varied between 5-15 micro-inGhes

(0.1-0.4 micro-meters).

The fatigue crack surface in the weld on the near side stiffener had

numerous oxides and other impurities due to the atmospheric influences

which prevented detection of fatigue striations (4).

The striation spacing observed in the base metal near the surface of

the web indicates relatively high web bending stresses of variable ampli­

tude. After the cracks 'propagated a few hundredths of an inch, the crack

surface exhibited the characteristics of high stress. fatigue. The stri­

ation spacing suggested that between 1000-10,000 cycles would be needed to

propagate the cracks detected at Stif:ener 13 on Girder 138Gl (4).

-242-

Page 246: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

3. CONCLUSIONS AND RECO~lliE~~ATIONS

Conclusions Regarding Fracture/Failure

The cracks found at the ends of transverse stiffeners cut short of the

tension flange on continuous plate girders for the Cuyahoga County Bridges

(CUY-90-1365-L&R) were fatigue cracks. No rapid fractures were observed.

All cracks were caused by large cyclic web bending stresses in the short

length of the girder web, the stiffener end, and the flange-to-web fillet

weld.

The cracks were only found in the positive moment regions of the

girders. All cracking was confined to the stiffeners located near the

wooden blocks used to support the girders during rail transit to the bridge

site. Relatively small out-of-plane movement of girders during transit

introduced large bending strains at the end of the cut-short stiffeners

in the girder web near the wooden supports, resulting in the fatigue cracks.

The cracks were all parallel to the bending stresses that would occur

in the webs.

Recommendations for Repair/Fracture Control

The following repair procedures were used in order to prevent future

crack growth during the serv~ce life of the Cuyahoga County Bridges (4):

1. Cracks in Stiffener Welds Only

Cracks that propagat~d into the weld metal near the stiffener

end were repaired by grinding out the crack and the weld metal

around it. The ground out region was checked by nondestructive

testing in order to insure the complete removal of crack tips.

-243-

Page 247: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

2. Cracks Propagated into the Web Plate

These cracks either initiated from the weld toe termination at

the end of the stiffener or propagated through the weld into the web.

They were retrofitted by drilling 7/16 in. (11 mm) holes at the end

of each crack and grinding the cylindrical surface of the hole

smooth as shown schematically in Fig. 16.

The sample core holes that were cut into the girders were ground and

any crack tip that extended beyond the core hole was removed as well.

4. ACTUAL REPAIR/FRACTURE CONTROL EFFORTS

The cracks were removed in the field according to the recommendations

given above. The holes at the ends of the cracks were filled with high

strength bolts which were tightened to a high preload.

-244-

Page 248: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

None of the cracks observed were detrimental to the safety of the

bridge during construction. The cracks were all parallel to the stresses

caused by dead and live loads. Repairs were made during construction and

should insure that further crack growth does not develop during the service

life of the structure. No adverse effects are expected from repairs.

6. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

The bid price of the Cuyahoga County Bridges was $2,203,883.10. The

bid price for the structural steel, excluding field painting was $924,056.

The investigation of the fracture including the repair of the cracked

girder webs was $12,335.67 in 1973. No costs are available on the repairs.

-245-

Page 249: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

REFERENCES

1. Ohio-DOT Internal Memo dated May 7, 1973 from J. D. Jones Shop Supervisory Eng. to R. B. Pfeifer Engineer of Bridges.

2. Ohio-DOT Inter-Office Communication dated May 11, 1973 from R. Van Horn, Structural Steel Engineer to R. B. Pfeifer, Engineer of Bridges.

3. Fort Pitt Bridge Co. Canonsburg, Pa ~1emo dated 6/13/73 from R. Osmond to W. H. Wallhausser (on Field Inspection of Open Ended Stiffeners)

4. Fisher, J.W. and Pense, A.W. "Report on Cracked Stiffener Details on Girders for Cuyahoga County Project Bridge No. CUY-90-1365 L&R." (Prepared for the C. E. Morris Co. and Fort Pitt Bridge Works Co.) Fisher, Fang and Associates, Engineering Consultants, Bethlehem, Pa. 18015; June 1973.

-246-

Page 250: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I N .c-. '--1 I

)_ \

Fig. la General Plan and Side View of Cuyahoga <;:ounty Bridge (CUY-90-1365 L)

! .J"VC

FCI'f 1? ,., Jl

.J•

-~-:~ AC·:·s,

Page 251: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I r·.J I> (n

I

Fig. lb

·~· -----#'-

Elevation of Cuyahoga County Bridge (CUY-90-1365 L)

Page 252: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

--------

I 1--· 1.­\(1

\

0

FRAMING PLAN <t>-'

DEl All A DEl All 8

Fig. 2 Framing Plan and Diaphragm Detail of Cuyahoga County Bridge (CUY-90-1365 L)

Page 253: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

GIRDER ELEVATION

GIRDER • U • ELEVATION

GIRDER ·v· ELEVATION --~~-~--~--~-----

(.

..... t1~}H4A. :.r:~~/'.1~~ .:'>-'"....a:::/N,.... /~~ ~.....,,.o"! t'/'l(~r rn--o tV.7i..~ ·.f€ o 4 -.!! .t:' • ...,._.e.r"t': . .....:.r:::.. f!l~rH ""'~~/r. 4-/.JA-.:.-A··;.r<JT")_..•.\C' ~­,;f~UT. ...., _ _, -~ .t"'/..Co.':'¥."-<~ ·u~ r,.,:.<v·~/:

Fig. 3 Typical Girders and Stiffeners of Cuyahoga County Bridge (CUY-90-1365 L)

Page 254: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

10 V1

·~ I

TRANSVERSE SECTION A INEST60UNO tlfNE.T

,. TP.ANSVERSE SEGION 8

Typical Cross-Sections of Cuyahoga County Bridge (CUY-90-1365 L)

Page 255: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

: r .~.~ "'! (r ,- ''·

c;\ __ -

01) --

1/;) ~ .o

(jj .r:. ~

" " C0-

® N

.)

~· (;/)

(~)

(/)

,.

Fig. 5

.. '

N

t

flfl"""!' -A.· /• •. • ... • a.~i.l-./o /!!" ·-.•• I'' .,,...,.. :.• · · .• ~; !·: nf~ s .. .t,.li

Location of Cracked Stiffeners in Eastbound Bridge (Small circles indicate cracked Stiffeners)

Page 256: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

(·.)

'.._; ~

w I

0-­(5) --

CD

.. ,

.. -,

7· ,I;'JJo (l ~~.~.s :• f"·i.VOo.S(K(T/ J·''\ '· ·•I , .

N

t fi~K - R ,.,,.,__ 2c.:-/ V<I!!E..~ Y

..-:> ./"" -~ /!'.C k ,.;. Z> ,5 T/~ ,..,.."",.Jr. A:"::) _k/ /_ L_'.C3-, (__ ~

Fig. 6 Location of Cracked Stiffeners on Westbound Bridge (Small Circles Indicate Cracked Stiffeners)

Page 257: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I

'--- l '--'

\..J v \..J v v

:-lv v Stiff. ~ \..1 " Web 'v

'-' v \_, ...__.

.......... v . \_, v

v \....., Web v

v '-' ~ v v

'-' \...,

'-' \...I

s·titt. '-' \....1 Stiff. v

..) v ...... _1. Crock

-)))))))J)JJ

Flange .

Flange

Cross Section Ele~otion

-Fig. 7 Schematic of Crack Growth at End of Stiffener Welds

_j,

' '- ~'-"'

\.....-;v'

( \..J

\.....- \...1 Stiff. v '-'

u v Web \..,

~ v \..., v

J! v ........ v

Stiff.

rock ....... , ....

~ Crock

)_)))))))))_) I

Flange ~~ Flange

Cross Section Elevation

Fig. 8 Schematic of Crack Growth at End of Stiffener into ~eld (and ~eb)

-25..'.-

.......

4-

~

\

\

' '

c

I

j

Page 258: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

.J

-

•.

Fig. 9 Photograph of Stiffener 13 on Girder 138 Gl Prior to Removing Sample Plug

Fig. 10 Sample Plug from ·Girder 138 Gl Shm,ring Crack in Held at End of Stiffener Near Side

-255-

Page 259: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 11 Macro-etched Section of Sawcut Showing Cracks into Web and Weld

-256-

Page 260: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

.. \Wooden Beam

[: ~

llo::ll 1"1QJ. [12Si fl'~

'&'I I~ ·'~ ·~ r· / / / / / / / / / '

Bed of Cor

Space r

... :I

1---

'I /

Steel Rods

Case I. Tension Flange on Bottom

.1. .... l: :j

"'" -~ 100 IOj

_..., _.., -""' ...... I I

////// / / / / / / / /

Bed of Cor

Case 2, Tension Flange on Top

AA

A I L-

\Girders\

n n n 1~

Flat Cor

A _j

Fig. 12 Tie Down Arrangement for Hoderate Size Girders During Rail Shipment

-257-

Page 261: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

m _j

I I-LL

D w CD 0::::: LJ U) m a:

>-u et: w z w

72"

![111

I I I I I I I ~ I I I I I I

Relative Movement of Top Flange

Support

Stiff.

'-' 1 lv ~t-----§lv

\..- 1 lv \...-I lv \.... 1Web lv 0 1 I Stiff. \.., v 0 lv \._.., 'v

Flange

Fig. 13 Schematic of Deformation of Girder Web at Support Block when Cut Short Stiffeners are Adjacent to Block

40 C . f_ • MORR I 5 RSTH R 36 TRR~JSVERSE

JUNE 1. 1973 X

30

X X

X ?n <...U

X X

10

c ~--------~----------L-________ _L ________ ~L_--------~

-1CC -SC 0

T 'c. ~-~ T T ~=· M p c- R' c T i I,..., :..· ...._, !......I,· L· I .__Jr. __ r DF.C F l

Fig. 14 Transverse Charpy.V-~otch Data for Web Plate of Girder 172 Gl

-25S-

JCG 1 so

Page 262: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

- ~ =--·~-~~ ';'· -· ---·-··--·

)

Fig. 15 Fatigue Crack Striations in Web Plate @ 7500X

-259-

Page 263: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

'-..../

Stiff. \..- v Stiff. v Web Web .......... v v

"-' ......... \........ .......... '-"".

v \.../

)j_)J)JJ ) ) . J .) ) J ) )

Flange Flange

Fig. 16 Retrofit Detail for Two Types of Cracks at the Bottom End of Stiffeners

-260-

\

Page 264: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

9.2 FATIGUE/FRACTURE ANALYSIS

of

CUYAHOGA RIVER BRIDGE (No. CL~-80-1843)

-- A Brief Summary --

I. D. No.

Town/City/etc.

Railway/Highway/Avenue

County

State/Province

Owner

-261-

42

near Independence, Ohio

I.480

Cuyahoga

Ohio

Ohio-DOT

Page 265: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 l

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief Description of the Structure

The Cuhahoga River Bridges are twin structures on Interstate I-480

carrying east and westbound traffic on separate roadways over the Cuyahoga

River, the Ohio Canal, the B & 0 Railroad and abandoned Penn Central Rail­

road tracks. The twin bridges are located near Independence, Ohio. The

total length of each bridge is 4150 ft. (1266 m), and the width is 71 ft.

(22 m) over 15 spans. The spans adjacent to the west and east abutments

are 220 ft. (67 m) and 180 ft. (55 m), respectively. Eleven inner spans

are 300 ft. (92 m) long, and the two remaining spans are each 225 ft.

(69 m) long. The overall view of the bridges is given in Fig. 1.

Each roadway is supported by four continuous main girders with two

stringers resting on a transverse beam between girders .. The main girders

are about 10 ft. (3 m) high and shop-wdded with field assembled bol teli

splices. The main girders are hauriched at the supports between west abut­

ment and the pier 11. The schematic plan and profile of the twin bridges

are given in Fig. 2. The typical main girders and the bridge cross­

sections are shown in Figs. 3a and 3b, respectively.

The structure was designed to satisfy the 1965 AASHO Specifications in­

cluding 1966-1967 Interim Specifications and the Ohio "Supplement" to these

specifications. The design loading is HS-20-44 and Inters tate Alternate Loading.

Brief History of Structure and Cracking

In April 1972, while erection of structural steel was progressing from

west to east, the inspection of a v.'ind damaged girder revealed a crack in the

-262-

Page 266: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 2

web at the open end of an intermediate stiffener. This resulted in examination

of other girders on the ground and piers resulting in the discovery of several

cracks near the bottom and of stiffeners cut short of tension flange (1).

All cracks were found to be fatigue related (2). They were caused by

the relative out-of-plane movements and bending of the short length of web

between the stiffener and the web-to:...flange fillet weld (2;3). The rela­

tive movement is believed to be caused by the cyclic swaying motion of the

girders while in transit to the construction site and/or wind induced

motion during storage on the ground. A typical crack is shown in Fig. 4.

2. FAILURE MODES AND FAILURE ANALYSIS

Location of Fracture, Failure Hodes and Stages

Several girders with the cracked stiffener details were examined on

April 17, 1973 at the Cuyahoga River Bridge site (2,3). The results of the

examination of a typical girder is surnmuarized in Fig. 5. The location of a

sample plug taken out of Girders 1204CL is also shown in Fig. 5 with a small

circle at the end of the stiffener. The field examination of other girders

showed that the cracks indicated in Fig. 5 are typical for all the cracked

girders (2).

The field examination and detailed evaluation of the sample taken from

the main girder plugs indicated that all cracks were fatigue cracks. They

were grouped into four categories as follows (2,3).

(1) Cracks between the Stiffener \.Jeld and Web: This type is shown

schematically in Fig. 6. The plug removed from Girder 1204CL is-shown in

Figs. 5, and Figs. 7 and 8 exhibit this kind of crack. Cyclically applied

loads caused fatigue cracking which peeled the weld away from the web surface.

-263-

Page 267: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 3

(2) Cracks across the Weld: These cracks were observed at the ends of

many stiffeners and, in some cases, did not propagate into the web. This type

of crack is shown schematically in Fig. 9 and is also visible· in the sample

plug in Fig. 7. The polished and etched surface shown in Fig. 10 indicates the

crack was started in the heat affected zone.

In several instances, the cracks in the weld at the end of the stiffener

extended completely across the weld and penetrated into the web as shown

schematically in Fig. 9. All cracks exhibited characteristic of fatigue

crack propagation.

(3) Cracks at Fillet Weld Toes: These cracks formed at the weld toes

at the end of stiffeners adjacent to the tension. flange (see Fig. 5). This

type of crack is shown schematically in Fig. 11. The sample plugs indicated

that the crack had propagated into the web at the end of the fillet weld and

turned and moved up the web after a short distance into the web as shown in

Fig. 12.

(4) Cracks in Web Surface Opposite Stiffener: Several surface cracks

were observed in the web opposite the stiffener. The sample plug removed from

Girder 2406AR contained this type of crack. This crack was initiated on the

net sur.face and did not join the crack propagating into the web from the end

of transverse stiffener detail. Crack initiation from the web surf~ce opposite

the stiffener indicates the presence of large cyclic strains on the web surface.

Eighty to ninety percent of the cracks observed in the main girders of

the Cuyahoga River Bridge were type 1. The remaining cracks were distributed

among other types described. The cracks detected in ~he girder at the

stiffener details were a new phenomena at the time they were observed. This

type of cracking had not been detected prior to their occurrence in Ohio.

-264-

Page 268: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 4

All macroscopic visual evidence from the field inspection and subsequent

laboratory examination of the crack surfaces of the sample cores removed from

the girders indicated that the cause of crack formation and propagation was

cyclic loading.

Cyclic Loads and· Stresses (known or field-recorded)

It is known that the main girders of the Cuyahoga River Bridge were

shipped from Chicago to the bridge site by rail transportation (2,3).

Because of their size a single girder was transported on three flatbed cars

as shown in Fig. 13. All girders were supported at two locations using the

tie-dow'!l arrangement given by section A-A in Fig. ],3 .. The two supports were

either located on the first and third flat cars or both supports -were placed

on the center flat car over the axles. One inch steel rods were used to

provide longitudinal restraint to moveme~t. This restraint system permitted

relative movement between the top and bottom flange during rail shipment. The

relative movement was caused by swaying of the girder and resulted in large

cyclic out-of-plane bending stresses in the short length of web between the end

of the stiffener and the flange-to-web fillet welds. Similar cyclic stresses

could have occurred due to wind induced swaying motion during storage. The

cyclic motion of the girder cross section is shown schematically in Fig. 14.

Thus a condition was created which resulted in large cyclic strains and

fatigue crack propagation.

Temperature and Environmental Effects (known or field~recorded)

Temperature effects, if any, did not contribute to the fatigue cracks

in the stiffener details.

-265-.

Page 269: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 5

The cyclic out-of-plane movements of girder webs in the narrow gap

between the end of the stiffener and the bottom flange would also have been

caused by wind induced vibrations during storage.

Material "Fractu-re, Physical and Chemical Properties Analysis" in Failure Regions

The web plates were fabricated from ASTil A588 steel. Mill test reports

indicated that the steel met the physical and chemical requirements (3,4).

Longitudinal Charpy V-notch (CVN) tests at 40~ F (4° C) were reported

for information from the heaviest gage plate in a lot. The_ mill reports

show absorbed energy that varied from a low of 24 ft-lbs. (33 Nm) to a high-

of 130 ft-lbs. (176 Nm) (3). Since the web plates were 123 in. (3124 mm)

wide, they had been cross-rolled, and hence, the CVN values are indicative

of the toughness in both the transverse and longitudinal directions (3).

The cracks in webs did not show any evidence of cleavage or brittle

fracture.

. Visual and Fractographic Analysis of Failure Surfaces

None of the fracture surfaces exhibited any cleavage or brittle frac-

ture characteristics.

The fractographic examination of failure surface revealed the presence

of striations which verified the existence of fatigue crack propagation (3).

Figure 15 sho~~s the fatigue striations found using the electron microscope

on the surface of the cracked weld shown in Fig. 7. Figure 15 shows the

striations in Region 1 adjacent to the stiffener near the point of crack

initiation at a magnification of 19000X. The striatio~ spacing is roughly

10-15 micro-inches (2.5-4.0 micro~meters) and height of the photograph is

about 0. 0001 in. (. 0025 mm). -266-

Page 270: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 6

On the basis of the striation spacings observed on the surface of several

cracks between 1000 and 10,000 cycles of stress were needed to propagate the

crack (3).

Crack Growth (Initiation and Propagation) and Probable Causes of Fracture/Failure

· The field inspection, visual and fractographic examination of the crack

surfaces of sample cores showed that the cause of crack formation was cyclic

loading or fatigue (3). Fatigue cracks developed at the end of stiffeners

as a result of large cyclic out-of-plane bending stresses in the short gap

between the stiffener end and the flange-to-web fillet weld. The small out-

of-plane movements of the top flange relative to the bottom flange due to

cyclic swaying motion of the girder occurred during rail transportation to the

bridge site and/or wind induced motions while in storage. The effects of the

relative lateral deformation between the two flanges would be concentrated in

the gaps between the end of the transverse stiffener and web-to-flange fillet

weld (see also Fig. 14).

The stiffener welds ~ere terminated very close to the web-to-flange weld.

The residual stresses due to stiffener-web welds, will create high tensile

residual stresses between the stiffener end and the flange (3). The presence

of residual tensile stresses in the gap means that each cycle of web bending

stress is effective in causing crack growth at the ends of the stiffeners

(2,3). The cracks followed the direction of the cyclic bending stress and

propagated in planes parallel to the longitudinal direction of the girder.

-267-

Page 271: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 7

3. CONCLUSIONS/RECOMMENDATIONS

Conclusions Regarding Fracture/Failure

The cracks at the end of stiffener welds in the main girders of the

Cuyahoga River Bridge exhibited the characteristics of fatigue cracks. No

cleavage or brittle crack propagation was observed (3). All cracks were caused

by large cyclic out-of-plane bending stresses in the gap between stiffener ends

and the flange due to the swaying motion of the girder during rail transit to

the site and wind induced motions during storage (?,3).

The cracks are primarily parallel to the longitudinal direction of the

girder and to the nominal bending stresses. The high toughness of web material

and the orientation of fatigue cracks indicate tnat there is no danger of

sudden brtttle fracture of the main girders. Construction and erection loads

should have no effect on the cracks (2,3). Hence, it was concluded that

repairs can be made while the erection and construction are continued.

Recommendations for Repair/Fracture Control

In order to prevent possible subsequent crack growth during the service

life of the Cuyahoga River Bridge the following repair procedures were used ( 3}.

(1) Cracks between Stiffener Welds and Webs: Since these cracks are

parallel to the stress field, then need not be repaired. The short length of

the weld cracked from the web at the end of the stiffener has no significant

influence on the performance of the web stiffeners and there will not be any

crack propagation under subsequent traffic loads.

(2) Cracks in the Stiffener Helds: The cracks, t·hat have propagated into

the ~eld near the stiffener end should be repaired by grinding out the crack.

The ground out region should be checked by non-destructive inspection to insure

re=~~al of the crack.

-268-

Page 272: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

(3) and (4) Cracks Propagated into the Web Plate: These cracks are

of concern during the service life of the structure and further propagation

in the \veb or into the flange must be prevented.

This can be accomplished by drilling 7/16 in. {11 mm) holes at the

end or the tip of each crack as shmm ·in Fig. 16d. The cylindrical surface

of the hole should be ground smooth.

8

Sample Plug Holes: The holes cut into the web to prevent removal of the

sample plugs will serve as crack arrestors and should remain provided the

crack tip has not extended into the web plate. To eliminate any remaining

crack tips, holes can be drilled adjacent to the plug holes as shown in Fig .. l6d.

These holes can be ground smooth, painted, and filled up with special non­

corrosive filler.

4. ACTUAL REPAIR/FRACTURE CONTROL EFFORTS

Ohio-DOT and the contractor of the Cuyahoga River Bridge superstructure

concurred with the recommendations given in (3) regarding the repair and

fracture control.

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

No adverse effects are <.::Xpected.

6. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

The original total cost of the structure (or total bid price) is

$19,747,802.36 in 1972 which includes the superstructure only. The sub-

structures were contracted separately.

The total cost of the field inspect:on and repair was $169,495.28.

-26S.-

Page 273: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 9

REFERENCES

1. Inter-Office Communication, Ohio-DOT (from J. D. Jones, Shop Supervisory Engineer to B. Pfeifer, Engineer of Bridges, dated Apr~l 4, 1973.

2. Letter from J. W. Fisher to J. P. Richley, Director, Ohio-DOT, dated September 10, 1973.

3. Fisher, J.W., Yen, B.T. and Pense, A.W. ''Report on Structural and Fractographic Investigation of Cracked Stiffener Details on Girders for Bridge over Cuyahoga River (No. CUY-80-1843 L&R)".

4. File Copy of the April 25, 1973 Meeting in the Construction Bureau of the Ohio-DOT. (D. S. O'Connor, Assistant D~vision Bridge Engineer).

-270-

Page 274: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 1 General View of Cuyahoga River Bridge (No. CUY-80-1843)

-271-

Page 275: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

rv -.I l.l I

11 •IU9dJr r ·YU!Ir

l • '"'',. l. c'l~-

/!!l!!~-.H.:....!fi!!..Jf..!!fl---rr ' fv C II JII II' '""7"''J.I'tW li•

---liff&iiM--

Fig. 2

r

l .I

t.I.A!l. k•l•.· t··rt~#•

•.tcJl!

PNOPOSfD

Plan and Elevation of Cuyahoga River Bridge (No. CUY-80-1843)

Page 276: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

('-.)

"'' l-'-' I

l!_~cl!.L:!~~-~-"!'l..IL__ I',_,,,._, '"~'-~I t;11~,.· .,.,...,....,. A 1 .. II

(liPtO[AS i,C,r & 0-UNITS t,S S4 .,,.,_dltl~ S'rtfYtiHI'I .,._ .,;t/1 •f ~,.. .. ,...,.... .., .,.~ .. , ,. .,.,., _,,,,.,.,,,., . ., ,.·,..,

Fig. 3.a

. CIAD£"5 A,O,£ 8 H -UNITS I. J 8 4 #rkr•H1t1,. St1m1Nrl ~.- Mil el t,..un..-.. -- fllfJ'""' ,. ,.,,., ,,,,,.,,,., • ., ~-.,..

Typical Main Girders

Page 277: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I 10 '-l L~

I

IJel•''

~lml/.1-

Jl.!.,~h '"'!!f!f d•I().()(J() ".txJI./1#69(h} 1

•"-'r• d- 11/rb tl~pllt "' ~rl II/. d•.ttlfl(tl ,.,, /r,,,,, .. II¥ "''l'"'"f •' liN _., d,,.,, ,.,.,.1(111"·

3T 7,.H

er-r er-s er-4

cr-2, cr-5, cr-•

Qlfto[A W£8 TRANSITION 0£TAIL

N.t•: o,,.,,lltr"' or~ __,,_.,.H P'6'•11~1 or i'<'Y"~TW/1(1#/01" lo ,,_ •.

, .. , .. s-- r,_,.,h, ,,.,. . u,,' ,. s,._, rnm

,., ... t.,.,., .,.,_.,.. ,.f'U,,., '" ,.. ,,,.,.,., •llfl• •f J-l•r• I, 4, f, 1, 6, 1~, II •nil II ~ •f tit• rt,.r ~rt~eerr•- ., lefll •Ill•• •I fll••• ~f•r• ,.,.

ronn•'""' I-f.,• I ,.,.rr,..

IN" Sir,,.,.,- .S~r"'9 .'

1$" a.p (W,_, or ~~··udr"flttll Stdl'(,.,.,, t. l'tlnlll•l• wwfiM Jr,..,,.,.. .....

.,.,.,,.w.£1~=+

Fig. 3. b Typical Cross Sections and Diaphragms

Page 278: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

.. . ........ -.-..:.. ·-.-. -~

--

~-;~:""~~----:---- . ... ;.:.·>···

. ~~ ::::~·~;;~: ::.:'··-~-::~ :i:;:;> ... ,~·-. :-::-:.. .:·. ~-. · .. -~ ... ''.··. ~- -;.~~~j;~<~ :· ... ,:·~~-. ~

. ·-=·~~...,:~:--:·.-: . :7:""·" >-:~~- --·--..;.- -.

Fig. 4 Typical Cracks at End of Transverse Stiffener and Stiffener-to-Web Fillet Welds

-275-

Page 279: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

- -Girder 1204 CL

Web

l}: AA

Longitudinal stiffeners at 0/5.

2 Transverse stiffeners on both sides ot CB 1 near side only at other locations.

3 ·9in. weld return at end of stiffener web weld.

4 All crocks ore only visible on the near side of web. No through crocks observed. ·

Fjg. 5 Typical Cracks in Girder 1204 CL of Cuyahoga River Bridge (CUY-80-1843)

-276-

Page 280: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Stiff.

Crock

CROSS SECTION

WEB Crock Between

))))J_)))_)j.Jj

FLANGE

ELEVAT-ION

Fig. 6 Schematic of Crack Growth between Transverse Stiffener Weld and Web -- Crack Type (1)

-277-

Page 281: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

. -_}

-- ----~ ..

·. -::-:~·-.-=--_ _,....--_.·:·

-... -··. ;.~:.-:::.:·o:---

Fig. 7 Sample Plug from Girder 1204 CL . (Note crack in weld and crack between weld and web) (Note Fig. 5 for location of sample plug)

Fig. 8 Nacro-etched Section of Stiffener Weld showing crack between weld and web -- Crack Type (1)

-278-

Page 282: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

v v ~ v

'-' v \,.., ..._;

'-' '-..J v ...._,

v v AA \,.., Stiff. v Web v

"-o.J J

'-' J Stiff.

Crock

) J _)· _j _) _) _) _) ~

Flange Flange

C'•oss Section Elevation

Fig. 9 Schematic of Crack Growth at End of Stiffener into Weld and Web -- Crack Type (2)

-279-

Page 283: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 10 Macro-etched Section of Weld and Web Showing Crack Surface in l~eld (see also Fig. 7)

-280-

Page 284: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

~

'-"

'-' v

'-' v '-' Stiff.

v J AA '-" .._,! J Web

'-"

Stiff.

Crock

) "J J. _) _) J J _j JJ j

Flange Flange

Cross Section Elevation

Fig. 11 Schematic of Crack Growth into Web at End of Stiffener Welds Crack Type (3)

-281-

Page 285: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 12 Macro.:.etched Section of Right Portion of Saw Cut Sample Plug from Girder 1102G

(Note Crack Growth Into and Up Web)

-282-

Page 286: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Flat Cor

AA

Steel Strop

!\

12 x 12 Wood Blocks

N ole: Two point support for

transportation. AA above

wheels of two end cars

or the middle cor.

1" ~Rod

A A

L _j

Flat Cars

Fig. 13 Tie Down Arrangement for Larger Girder During Rail Shipment

-283-

Page 287: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

120"

Relative Moment ---- of Top Flange

±~ -n-I I I I I I I ~8 I I I I I I

stiff.

Flange

Trajectories of Stress .1 to Crock

Fig. 14 Out-of-Plane Motion of Girder Web

-284-

8

Page 288: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 15 Fatigue Crack Striations in Region 1 (see sketch and Fig. 7) --Height of the phato about 0.0001 in. - 19000X

-285-

Page 289: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

(a)

Drill 7;,6" II!

))))))

(c)

) ) ) ) _)

(b)

).) )j)~.

))))_))

FIGURE 18 SCHEMATIC OF SUGGESTED REPAIR PROCEDURES

Plug Hole

Fig. 16 Schematic for Suggested Retrofit/Repair Procedures

-286-

Page 290: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

10. FLOOR B~~ CONNECTION PLATES

One of the most common sources of fatigue cracks during the past

seven or eight years is the cracking in the web gaps at the ends of floor

beam connection plates. These plates have been welded to the web and

often the compression flange of the main longitudinal girders, but have

not been attached to the tension flange. At least 28 bridge structures

have developed cracks at these connections.

Distortion of the transverse connection plate web gap .in the longi­

tudinal girders occurs as a result of deformation in the floor beam. The

floor beam end rotation caused by bending of the floor beam and the rela­

tive end movements creates large cyclic stress conditions that leads to

rapid development of fatigue cracks when the structure is on a high volume

road. Even less heavily traveled bridges crack with time.

A detailed discussion of two typical cases is provided hereafter for

bridges I.D. 13 and I.D. 58. The Poplar Street Bridge (I.D. 13), was

one of the first bridge structures that exhibited cracking in the web

·gap at floor beam connection plates.

After discovery of similar web cracks in floor bea~girder bridges in

· 1978, Iowa DOT conducted a detailed survey of 39 structures with comparable

details. The Polk County Bridge near Des Moines (I.D. 58) is typical of

the type o.f structure and illustrates· the cracking that developed and the

retrofit proceudres used to correct the condition. Twenty-one of the 39

structures in Iowa were found to have some evidence of cracking.

Cracks have been found in at least six states with this type of bridge

and general detail at the floor beam girder connections.

-287-

Page 291: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

10.1 FATIGUE/FRACTURE ANALYSIS

OF

"POPLAR STREET COMPLEX" BRIDGES

--.A Brief Summary

I.D. No. 13

Town/City/etc. East St.

Railway/Highway/Avenue I-55 and

County St. Clair

State/Province Illinois

Louis

I-70

County

Owner Illinois-DOT

-288-

Page 292: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief bescription of Structure

The Poplar Street Complex Bridges are located on the east bank of the

Mississippi River in East St. Louis, Illinois. The complex is one of the

largest and busiest interchanges in the State of Illinois. It serves as

a focal point for Interstate Highways I-55, I-70 and U. S. Route 40 which

join and cross the Mississippi River. It starts with the Poplar Street

Bridge over the Mississippi River on the west and ends northeast of

Broadway in East St. Louis, as shown in Fig. 1. It consists of several

ramps and viaducts consisting of multispan continuous two girder type of

bridges, as shown in Fig. 2.

The majority of the two-girder I-beam bridges in the complex are on

horizontal curves with radii approximately 1800 ft. (550 m). The tor­

sional and side-sway (transverse) rigidty of the system are provided by

closely spaced transverse floor beams which are rigidly connected to the

two main girders. The floor beams support the longitudinal stringers

and the reinforced concrete deck, .as shown in Fig. 3.

Brief History of the Bridge and Cracking

The Poplar Street Complex Bridges were designed in 1964. The entire

complex was designed by a consulting engineering firm for the Illinois

Department of Highways Bridge Division. The design of the welded details

and transverse stiffeners conformed to the AASHO and State of Illinois

design specifications and current practice in effect in 1964 and throughout

the design period. The structures were built between 1967 and 1971.

-289-

Page 293: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

In late 1973, the complex was inspected in depth for the firsi time

by a bridge inspection team from the Illinois Department of Transportation.

During this inspection, several types of cracks and web buckling were dis­

covered and reported (1). The fatigue cracks consisted of the following

conditions (1,2,3):

Fatigue cracks in the bottom "web gap" region of main girders

at floor beam connection plates

Fatigue cracks in the upper "web gap" region of main girders

at floor beam connection plates

Fatigue cracks in the girder webs at the ends of bearing

stiffeners of the main girders.

These latter cracks were located at the ends of the continuous main

girders. In addition to these cracks, there were instances of web buckling

at the girder end supports a few inches above the bottom flange (1,2,4).

-290-

Page 294: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

2. FAILURE MODES AND FAILURE ANALYSIS

Location of Fracture, Failure Modes and Stages

The general location of the fatigue cracks were predominantly near

the supports or adjacent to the piers of the bridges in the complex. These

cracks can be grouped into three general types as follows (2,3,4):

1. Fatigue cracks in the web in the bot tom "web gap" region between

the lower end of the floor beam-to-main girder connecting plate

and the bottom flange of the main girder (web cracks in lower or

bottom "web gap" region) (see Fig. 4).

2. Fatigue cracks in the web in the upper "web gap" region between

the top end of the floor beam to girder connecting plate and the

top flange of the main girder (web cracks in the top or upper

"web gap" region) (see Fig. 5).

3. Fatigue cracks at the ends of bearing stiffeners which were also

used as floor bea~to-girder connection plate.

Types 1 and 3 web cracks were near the end supports of the main

·girders. However, Type 2 web cracks were only observed at the upper end

of the floor beam connecting plates which were located in the negative

moment regions. There were no web cracks detected in the positive moment

regions of the spans.

Type 1 web cracks were first observed at the end of the girder under

the end of floor beam connecting plate which was positioned 7 in. (18 em)

toward the center of the span from the center of the be~ring stiffeners.

Most of these cracks started near the lo~er end of the vertical connecting

-291-

Page 295: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

plate and extended in both directions in the girder web as shown in Fig. 4.

The longest crack was 19 in. (48 em) long. Occasionally two cracks were

observed at the same location; one immediately under the lower end of

connecting plate, the other among the edge of the web-to-flange weld toe.

The former was shorter in length than the latter. The Type 2 web cracks

in the upper gap regions were found in the negative moment·regions (see

Fig. S) where the floor beam connection plate was not welded to the tension

flange.

The Type 3 cracks occurred at bearing stiffeners which were also used

as a connecting plate for the end floor beam at a few supports or piers.

These cracks were observed at the top end of the bearing stiffener which

was not welded to the top flange.

In addition to the fatigue cracks, web buckling was also observed at

the end of several girders. This buckling of the \veb occurred a few b.ches

above the bottom flange and was often associated with the separation of

the top bearing plate from the bottom flange of the girder due to the

seized expansion bearings. In some cases, web cracking developed above

the web-to-bottom flange weld toe. This crack started ·at the end of the

girder and progressed horizontally toward the bearing stiffeners.

Cyclic Loads and Stresses (Known or Field Recorded)

The mainline ISS and 170 east and westbound structures were subjected

to 5250 ADTT (multi units per structure) in 1980. Several of the ramps

experience about 200 ADTT. The ADTT has varied between 4000 and· 5250 since

the mainline structures was opened in 1967.

-292-

Page 296: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

In order to determine which mode of displacement was causin~ the web

cracking, a series of field measurements were conducted in July, 1975. The

web gaps at several floor beams were selected for the strain measurements.

Some of the typical locations were (2):

1. At the end of the girder where the floor beam connected to a

connection plate 6 in. (152 mm) away from the bearing stiffener.

2. At the end of the girder where the floor beam connected directly

to the bearing stiffener.

3. At intermediate floor beams

At the floor beam-bearing stiffener connection, gages were placed at

each end of the connection plate-bearing stiffener~ All other strain

gages were placed near the web gap between the end of the connection plate

and the tension flange as illustrated in Fig. 6.

Behavior at End Supports

When the connection plate also served as a bearing stiffener, it was

not welded to the flange at either end. No crack had formed at the lower

gap, however, cracks had developed at the upper end of stiffener-connection

plate. The strain gradient and stress range spectrum at the lower gap

were relatively small, i.e. the adjusted root-mean-square stress range was

5rRMS

SrRMS

6.54 ksi, while at the upper gap the adjusted stress range was

14.4 ksi, as can be seen in Fig. 7. Figure 8 shows the time-

-stress response at the end support and at interior floor beam connections.

At the end reaction the. stress range was always-less than 5 ksi

.;.;hich indicated that cracking wou1d not develop, and none '..Jas observed.

-293-

Page 297: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Since the connection plate at the end reaction was welded to the top

flange, no movement could occur and no damage was detected.

Behavior at Interior Floor Beams (Positive Moment Region)

The connection plates were tight fitted to the tension flange and

welded to the top compressi-on flange in the positive moment regions. A

stiffener was also welded to the outside web surface and cut short of the

flange by about 5/8 in. (16 rnm), as shown in Fig. 5. No cracks were

observed in the positive moment regions. The strain gage meaasurements

indicated that stresses were below the fatigue limit, as can be seen in

Fig. 8.

Behavior of Floor Beams (Negative Moment Region)

In the negative moment regions where the connection plates were not

welded to the top flange, cracks developed. The strain measurements indi­

cated that the stress range at the weld toe was high even at the end of

cracked "webs, as can be seen in Fig. 8. At the bottom gap, the connection

plates were welded to the flange, and no cracks were detected.

Behavior at Interior Supports

The strain measurements at interior supports showed that web gap

strains were small and comparable to those at interior floor beams at

positive moment regions. The reason for this is that at the interior sup­

port, there is a concentrated reaction force which creates frictional

resistance bet~een the ends of the connection plate and the flanges:

-294-

Page 298: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

However, at least one location experienced a large crack at an in.terior

support, as can be seen in Fig. 9. This crack was discovered in January

1978. No retrofit holes have been installed at the interior support.

Temperature and Environmental Effects (Known or Field Recorded)

These effects did not appear to play a significant role in the

fatigue cracks that developed in the main girder webs of the Poplar Street

complex. However, the thermal movement of the girders caused the girder

to bend because of the seized expansion bearing. This resulted in a sepa­

ration between the bottom flange and the top bearing plate and contributed

to web buckling, as illustrated in Fig. 10.

Material "Fracture, Mechanical and Chemical Properties"

l~o information was acquired as it was not considered to contribute to

the development of fatigue cracks in girder webs.

Visual and Fractographic Analysis

No crack samples were removed from the girder web.

-295-

Page 299: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

3. CONCLUSIONS/RECOMHENDATIONS

Conclusions Regarding the Fracture/Failure

The cracks in the web gaps between the end of the floor beam connec­

tion plates and the gi·rder flanges are all fatigue related. These fatigue

cracks have resulted from cyclic out-of-plane web bending stresses due to

out-of-plane displacement of the web in the gap region, as shown in Fig .. 6.

The severity of this displacement was greatest at the end bearing, at the

top flange of intermediate floor beams in the negative moment regions of

the girder, and at the top flange of interior supports. This was confirmed

by field test measurements in typical gap regions under actual traffic

conditions (2). The rotation of the floor beam which ·was rigidly connected

to the main girder pushed the web out-of-plane, v."hich caused high cyclic

stresses along the toe of the web-to-flange welds and the stiffener connec­

tion plate ends.

The longitudinal orientation of the cracks in girder web relative to

the stresses from loading are such that they do not affect the girder

strength. However, corrective repairs were needed to prevent the cracks

from growing perpendicular to the stresses in girder webs.

Recommendation for Repair/Fracture Control

Based on the observed behavior at the Popl.ar Street Complex, the fol­

lowing procedures for repair and corrective action were used (2):

-296-

Page 300: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

At Girder Ends:

1. In general, welding the floor beam connection plates to the

flanges would prevent the relative displacement that occurred

between the end of the connection plate and the girder flange.

Figure 11 shows retrofit procedures for the cracked and buckled

ends.

2. At the ends of the existing web cracks along the weld toe of the

web-to-flange connections (at either top or bottom flange) 5/8 in.

(16 mm) holes were drilled through the web, as shown in Fig. lla.

3. The web cracks at the ends of connection plates or stiffener­

connection plates were also drilled to prevent cracks from

propagating.

4. The cracks were gouged and welded up to the hoie and then the

surfaces were painted.

At Interior Floor Beams and Interior Supports:

1. Holes should be drilled at the end of the cracks similar to the

case shown in Fig. 12, and the crack should be grouted with an

epoxy and painted over to prevent rust formation. Two holes

were drilled near the ends of the crack along the web-flange

weld, as shown in Fig. 12. Holes were also drilled on each side

of the stiffener to permit the crack to develop between them and

accommodate out-of-plane displacements. This will not likely

prevent rusting, because of the continued relative movements of

the crack surfaces.·

-297-

Page 301: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Crack Growth (Initiation and Propagation)

and Probable Causes of Cracking

The measurements at all floor beam locations indicated that the pri­

mary stresses occurring in the web gap regions were due to an out-of-plane

movement of the girder web. This resulted from the rotation of the ends

of the floor beams as they "were loaded by traffic passing over the bridge

structure. Since the floor beam connection· plates were welded to the main

girder web, and in some cases the compression flange, the floor beam end

rotation was transmitted into the web by the connection plate. The connec­

tion plate stiffened most of the region of the web where it was attached.

Consequently, the rotation of the ends of the floor beam forced the web

gap to deform, as sho~~ schematically in Fig. 6. This resulted in-high

stresses in the web gap regions where the upper and lower flanges of the

main girder were restrained against twisting. Fatigue cracks developed

at the end of the stiffener welds and along the toe of web-to-flange welds.

4. ACTUAL REPAIR/FRACTURE CONTROL EFFORTS

The recommendations were implemented by the Illinois-DOT in 1975-76.

Holes were drilled in the girder webs at 751 locations, as shown sche­

matically in Fig. 12. Ninety-seven of these lo.cations were known to have

cracks. In addition, at the girder ends, the stiffeners were welded to

the tension flanges, as shown in Fig. 11. Figure 13 shows the retrofitted

ends of two girders. Also apparent are the neoprene bearings that were

installed in place of the rocker supports. The large crack sho\m i~ Fig. 9

V.'as repaired by installing splice plates ,,,hich can be seen in Fig. 14;

-298-

Page 302: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

All web cracks were parallel to the primary bending stresses in the

girder web. After the corrective action and repairs were performed, no

adverse effects are expected. Routine inspection should permit any crack

initiation at the drilled holes to be detected. The retrofit of the web

cracks was carried out in 1975-76. No cracks have reinitiated from the

drilled holes up to 1981.

6. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

The original construction cost of the Poplar Street complex

was $18,185,555.

The repairs to the girder ends, the drilling of.holes at inter­

mediate floor beams in the negative moment regions and the replace-·

ment of bearings cost $3,387,730.80

The large crack found at the pier of Ramp C was retrofitted by

district maintenance per~onnel at an estimated cost of $38,522.16.

-299-

Page 303: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

7. REFERENCES

1. Bureau of Design, Bridge and Traffic Structures Section "Investigation Report on Poplar Street Complex Bridge, East St. Louis, St. Clair County, Illinois11 . Illinois Department of Transportation Report, June 1974.

2. Fisher, J. W. 11 Report on Investigation of the Girder Web Crackings at Floor Beam Connection Plates of Poplar Street Complex" prepared for H. W. Lochner, Inc., Consulting Engineers, Chicago, Illinois, October 1975.

3. Fisher, J. W. 11Fatigue Cracking in Bridges from Out-of-Plane Dis­

placements11 Canadian Journal of Civil Engineering, Vol. 5, No. 4, 1978, pp. 542-556.

4. Hsiang, W. "Repair of Poplar Street Complex Bridges in East St. Louis" Transportation Research Record 664, Bridge Engineering Vol. I (Preceedings of a Conference by Transportation Research Board, September 25-27, 1978, pp. 110-119)

-300-

Page 304: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 1 Layout of the Poplar Street Approaches

-301-

Page 305: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I w 0 I·J I

I ~ :

. t~11r A 29 ·: ~;;~ : :;~;·r·.~ .: .. ~ ·

t ROddw•IJ H ·~.: . : . -~

. : ..

Std. 78+44 £/. 468.34'

.. ·.: ~6~. '('le~ ~(2'W~/d•d Glrd~r3 Cvrvet:J) ,. ' ' ' ' l

. ".' ·~ ~- . . I •:·

Fig. 2 Typical Plan and Elevation of ~ ~tion of Poplar Street Structure

tPier Aj

st ... 83 l/. 45

( Pier ~3

Page 306: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

~ 5rr. ~ 5tr.

PLAN

Fl FZ F4 · FS

. I

Fl. I'm. &0 .thru ti3 ~ KF 182

Ft Bm. 64 thrt.l 68 .36 W' /54 Fl. 13m. 54 .36 w- 1&0

Fl Brn.55 fhrv~ 361'F!70

ELEVATION

INTER lOR FLOOR BEAM ~.54 TI-IRU 68

Fig. 3 T,Ypical Cross-Section of Poplar Street Approaches Showing Floor Beam-Girder Connection

-303-

r CDnn.c rio~ !Mhll su .Jh. Nc . .J44

Page 307: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

""-

--...., (

~ v

'~--·

(a) Schematic of Detail

• • , .. I •• • • I• • I• • I• • • • I. • I• •

(b) Photograph of End Reaction

Fig. 4 Cr-ack in h1eb Near End Support

-304-

Page 308: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

~-·~·.· ..... ·:·.~ .... r---oo'

F.:; I• . I• .

~ I• . I • . . .

~ '• . I. . I• . , . . t --

(a) Schematid of Negative Moment Detail

r··.- .. , ... -.-:. > -~~

:-: .--

.. --;-.-

~~- -·· ,. i ~

(b) Photograph of Crack on Outside Web Surface

Fig. 5 Crack in Web of Negative Moment Region

-305-

~

I

I

Page 309: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Distortion at Web Gop

Strain Gciges Near Web Gap

~--------------~~

~I

Fig. 6 .Schematic of Distortion in Web Gap and Location of Strain Gages

-306-

Page 310: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Cf) LLJ u z LLJ a: a: ::> u (.)

0

50

40

LL. 20 0

0 z

Sr RMS = 14.4 ksi (N =324)

9 18 27 36

STRESS RANGE, ksi

Fig. 7 Stress Range Histogram of Web Gap

-30 7-

Page 311: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

w 0 OJ I

6 seconds

=

19 ksi

. I Floor beam Connection Plate

(a) Response at Interior Floorbeam In Positive Moment Region

(b) Response at Web Gop Near End Reaction

(c) Response 4" From Web Gop at Interior Floorbeom in Negative Moment Region

Fig. 8 Typical Stress-Time Plots for Web Gaps

Page 312: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 9 Largest Crack at Interior Support

I c

I

Fig. 10 Web Buckling at End Support

-309-

Page 313: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

--I "'•Mho ', '

Dill! 13 ,, ,_ til ;--

I £~"' Cnd/ -;::_-, j_?_l

1111 .. ,,It ~~~ .,,,.,., ""' lllfi'MH ,..._

,.,, •.O.SI "'nt••

-

(a) Retrofit for Cracked Girder Ends

i '" I

I

I

,,,,

. - ~ I611521L mm

L • ;o

'"'"' •.O.SI .. ~

(b) Retrofit for Repair of Buckled Webs

Fig. 11 Retrofit Procedures for Girder Ends

-310-

Page 314: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I L·J f-' f-' I

rv411

Fatigue Crocks

Drilled Hole At Crock Tip

Fig. 12 Retrofit Holes at Fatigue Crack Tips

A-A

Page 315: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Fig. 13 Retrofitted Girder End Showing Stiffeners and Elastometic Be.arings

Fig. 14 Splice Plates Installed at Lare Web Crack

-312-

Page 316: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

10.2 FATIGUE/FRACTURE ANALYSIS

OF

DES MOINES (POLK COUNTY) BRIDG~

.-- A Brief Summary --

I.D. No. 58

Town/City/etc. Four Mile Twp. and Des Moines, Iowa

Railway/Highway/Avenue: Iowa Route 163

County Polk County, Iowa

State/:rovince Iowa

Owner Iowa-DOT

-313-

Page 317: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 1

1. DESCRIPTION AND HISTORY OF THE BRIDGE

Brief.Description of Structure:

The Des Moines (Polk County) Bridge carries east and westbound traffic

over th~ Chicago Rock Island and Pacific Railroad (C.R.I. and P.R.R.)

tracks and the East Four Mile Creek on Route 163. The bridge is located

near Des Moines, Iowa. Th~ east and westbound bridges are two similar,

but separate structures.

Each skew bridge structure is composed of two continuous welded

girders with transverse stiffeners 590 ft. long supporting a 30 ft. road­

way. The east end span is 91ft. -0 in. long, and the west end span is

118 ft. - 0 in. long. The two interior spans are. each 127 ft. - 0 in. long.

The slab is 7-1/4 in. thick reinforced concrete supported by two 18 WF 45

stringers and the two main girders (see Fig. 1). The floor slab includes

one-half inch wearing surface. The plan and elevation of the bridge are

given in Figs. 1 and 2. Typical intermediate and pier cross sections are

shown in Fig. 3.

The two main girder webs are 74 in. deep. The floor beams supporting

the stringers have 48 in. x 5/16 in. web plates with alternating trans­

verse stiffeners.

The Des Moines Bridge was designed for H20-SK loading. There was

19 lb./sq. ft. of roadway added for future wearing surface. The design

is based on the 1961 AASHO Specifications and 1960 Iowa-DOT Standard Speci~

fications and current Special Provisions and Supplemental Specifications.

All members were fabricated from A36 steel.

-314-

Page 318: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 2

Brief History of the Structure and Cracking:

The Des Moines Bridge was constructed in 1962 and opened to traffic

in 1963 (Ref. 1). The volume of truck traffic crossing the bridge in 1979

was 500 vehicles per day (Ref. 1).

In 1979, several fatigue cracks were discovered in the webs of main

girders of the Des Moines Bridge (Ref. 2). These cracks were in the

negative moment regions along the upper web-to-flange fillet welds above

the floor beam connecting plate. Several vertical cracks were observed

in the fillet welds joining the floor beam connecting plates to the girder

web (Ref. 2) and in the web several inches below the web flange connection.

-315-

Page 319: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

2. FAILURE MODES AND FAILURE ANALYSIS

Location of Fracture, Failure Modes and Stages:

Several web cracks were discovered by the Iowa-DOT personnel in 1979

(Ref. 2) in the negative moment regions of the main girders of the Des

Moines Bridge. All cracks were detected in the floor beam connection

plates nearest to the skew~d piers in the negative moment regions. Two

types of web cracks were observed: (1) Horizontal fatigue cracks in the

main girder webs along the toe of the web-to-flange fillet welds. These

cracks were 3 to 6 in. long and are shown schematically in ·Fig. 5.

3

Figure 6 shows photographs of the inside and outside web surfaces indicat­

_ing cracking has developed on each side of the web plate. (2) Vertical

weld cracks were also observed at the top ends of the floor beam connect­

ing plate, as shown in Figs. 5 and 6. At several locations these cracks

stopped after propagating downward for an i.nch or so and intersected the

second web crack shown in Fig. 6.

On-site examination of the web cracks in the main girders of the

Des Moines Bridge indicated that. all were fatigue cracks (Ref. 1). The

principal cause of the cracking is the out-of-plane deformation of the

girder webs in the small gaps at the ends of the floor beam connection

plates. The fatigue crack development in the girder webs in the negative

moment regions is a result of the. web being forced out-of-plane by the

floor beam end rotation in the small gaps between the end of the floor

beam connec~ion plates and web-to-flange welds (Refs. 1,2). Since the

slab constrains the girder top flange at these locations, and the con­

nection plate has its strong·axis perpendicular to the web,end rotation of

-316-

Page 320: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 4

the floor beam forces the web out-of-plane. When the gap is very small,

the resulting. ~yclic stresses are very high along the upper end of the

connection plate weld. This causes the welds to crack and separateS the

connection plate end from the web. As the vertical cracks in the connec­

tion plate welds increase in length, the web deforms, and this results in

high out-of-plane bending stresses. This also causes web cracks to form

several inches below the web-to-flange weld from the double curvature

bending in the gap. In skewed bridges the out-of-plane movement is more

severe because of the different vertical displacements at the two ends of

the floor beams (Ref. 1).

Cyclic Loads and Stresses (Known or Field-Recorded):

The ADTT is known to be 500 vehicles in 1979 (2.). No stress me.asure­

ments are available.

Temperature and Environmental Effects (Known or Field-Recorded):

Temperature and other environmental effects do not appear to have

contributed to the development of cracks. The cracks were developed from

stresses as a result of truck traffic. They occur from out-of-plane

diSplacements in the girder web gaps at floor beam connection plates in

negative moment regions.

-317-

Page 321: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

Haterial "Fracture, Hechanical, Chemical Properties"

Analysis in Failure Regions:

No material tests were carried out other than those reported on the

mill reports. No Charpy V-Notch tests are available.

Visual and Fractographic Examination:

5

Only visual observations were made on the cracks detected in the welds

and web.

-318-

Page 322: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 6

3. CONCLUSIONS AND RECO~lliENDATIONS

Conclusions Regarding Fracture/Failure:

The Type 1 and 2 cracks discovered in the main girders of the

Des Moines Bridges were all fatigue cracks. Each of these skew bridges

consists of two main girders with floor beams and stringers. The fatigue

cracks developed where the·floor beams next to the piers are connected tq

the main girders. The floor beams next to the piers are bolted to

intermediate stiffeners or connecting plates nine inches away from bearing

stiffeners. The cracks are caused by the out-of-plane displacements of

the girder web in the negative moment regions at floor beam connecting

plates. ~.;relded to the web (see also Fig. 7). The. horizontal cracks at the

toes of the flange-web fillet weld developed where the web out-of-plane

displacements were relatively large because of the skewed bridge

configuration.

Vertical cracks along the connection plate girder web welds developed ..

from the upper end of these welds. In several cases, further horizontal

cracks developed in the web. These resulted from double curvature bend-

ing resulting from the out-of-plane displacement of the girder web due to

rotations of the floor beam connection plates under cyclic traffic

loads (1,3).

Both types of cracking are shown schematically in Fig. 7.

-319-

Page 323: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448 7

Recommendations for Repair/Fracture Control:

There are several ways to retrofit the fatigue cracks that developed

in the main girder webs of the Des Moines Bridge. These are as follows (1):

(a) One possibility is to weld the floor beam connection plates

to the top flange of the girder in the negative moment regions

as shown in Fig. 8. This provides a fatigue Category C condi-·

~ion (3). Welding the connection plates to the top flange

would minimize the relative out-of-plane movement of the

girder web in the negative moment region. Some difficulties

may develop in obtaining good welds under field conditions.

In addition, holes should be drilled in the web at the ends

of all existing cracks to prevent further crack propagation.

(b)· An alternate solution j_s to re.move part of the connecting

plate and opposite web stiffener, so that a significant gap

exists between the end of the transverse plate and the re­

strained tension flange. This solution is shown schematically

in Fig. 9.

Additionally, all web cracks should have holes drilled at

their ends in order to arrest further fatigue crack growth.

-320-

Page 324: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

4. ACTUAL REPAIR/FRACTURE CONTROL EFFORTS

The information and data for the retrofit of the Des Moines (Polk

County) Bridge w~re provided by Iowa-DOT. After visual and dye penetra­

tion i~spection of the fatigue cracks, the following retrofit scheme was

used (4):

(a) In the negative moment regions, the top portion of the stiff­

ener (which is also the connecting plate for the floor beam

or diaphragms) was removed by flame-cutting, and the surfaces

were ground smooth as shown in Figs. 9 and 10.

(b) There were 3/4 in. ¢ holes drilled at the ends of the cracks

in order to arrest further growth. This is.shown in Fig. 11.

(c) In the negative moment regions at the piers, the pier stiff­

eners were bolted to the girder top flange using ~ clip angle

on each side of the stiffener. In order to facilitate this

repair, a rectangular section of the reinforced concrete

deck above the pier stiffener was cut out in order to drill

holes in the top flange and install the bolts. After install­

ation of the bolts, the holes were filled with concrete, as

shown in Fig. 12.

5. POSSIBLE ADVERSE EFFECTS OF REPAIR

No adverse behavior is expected from the retrofit.

-321-

8

Page 325: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

Proj. 448

6. ACTUAL OR ESTIMATED REPAIR/REHABILITATION COSTS

Cost of Investigation:

This was approximately $3000.

Cost of Repair/Rehabilitation:

Cost of retrofitting the Des Moines (Polk County) Bridge in 1980 was

$35,900.

Original Cost of the Bridge:

The construction contract for the bridge was $438,952 in 1964.

7. REFERENCES

(1) Fisher, J. W. "Letter-Report" dated October 16, 1979 to C. A. Pestotnik, Bridge Engineer, Iowa-DOT.

(2) Pestotnik, C. A. Letter dated September 28, 1979 from C. A. Pestotnik, Bridge Engineer, Iowa-DOT to J. W. Fisher.

(3) Fisher, J. W. INSPECTING STEEL BRIDGES FOR FATIGUE DAMAGE, Fritz Engineering Laboratory Report No. 386-15(81), March 1981, pp.· 28-29.

(4) Office of Materials, Iowa Department of Transportation VISUAL, DYE PENETRATION INSPECTION.AND RETROFIT REPORT, May 31, 1980.

-322-

9

Page 326: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

' r w .9 , 0 L <fl: ; 01 J''

-5 L·> II 1-.J I

(,J

I

o~:.!l'-4:\ ' ,~~n;~ \

r~-- ~~=--- )~----~-~--_._~+--~------=---~~~~~;c.=~~~ .. ..

Al\dofl'"\Cl.J'H~•~ q•IJIIZ'l Of'Q.~ori,on+o' : I .

•'

( t.:) 1 ), '1•1•: ~. J. o\hq1~) ... ~· \ ·'

..,.,. ,. .. i.

- /

__ •)(!:11:0.__ , ____ :__ '..!_1 ___ _

I / .,· ~· / • / t

~o·-n .'"' .. /- -- .. "" /

/ ,. .... .... ~ .. I~

....

, . ,o ..

;

• •• " "' .. .. ,y ·"' .. ,, ,, .. .... ... ...

•'" -A:!_vi-7 1-iqtc~~ ... , ---___ -- -fn J_--_-_-_----~ . ~~

• ---· \~ ! t-

Fig. 1 Plan of the Des Moines (Polk County) Bridge

*'

Page 327: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I w 1-.:J .l.' I

&8'~----

Fig. 2 Elevation and Side View of the Des Moines (Polk County) Bridge

Page 328: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

~ ·. -r-·~~~ ·. ,.-1:1___ ... 4:-o. . .l· _ _.-o _ · _ ~--___ ,._··_,G.'---

er.~o "·"'--.. -~-~i'E~ ·- ·----- ·.w:;. ti!Cne:>WWEAR'•-.-merr-N:IT'E• .. fb::rt-n ~ - ..

'- Q '*- flit ..rt+l ,.. ... crcl ~~crd- ..... ~ r t~ cia- b IJIId a -'d.

~-+-'7·\lt.

. -*-.ll•t• ..

Fig. 3 Typical Cross-Sections of Des Moines (Polk County) Bridge

-325-

Page 329: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

w ,,_)

{]'\

I

l I

I

I

I

- c~ y,.-',.,.5 r' "-. - I - I

·~o. f-)b!IT, rf:. F; . .:,•r1 t ?;er;: t / .. ler 5

/ /

/

<: .• <.:.. ./.-(,-) ,..4)

- •' . ,f...-· I ~)

I

:1 :'\ ~< c, . / / 7 ;'______.;. ____ +-/--'-----li/:....-------,11¥-/ ----1-;1

,/ /

/

Fig. 4 Crack Locations at Floor Beam Connecting Plates in Des Moines (Polk County) Bridge (Crack Locations are marked with a circle and number)

I

Page 330: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

J. ,- -- .··• I .. 1 . _,_~, _.._--1 ~· I.,., r) -- ··-·----· __ !_ --~·_: __ ..:_ ____ ~:": ".)

-.11)1 -7 c' Y'..., _. 1

-· t r )> - -· ~--. <- ''

I ' '

1

I l)r·s

l)7 .. I(J . . . 1 il

( ---. • 1-, 4 , ___ , L•.c,--..,. ______ f______ . ! . 1:- ... '

Fig. 5 Typical Cracks at Web-to-Flange Welds, at Top Ends of Stiffeners and Along the Toe of Stiffener-to-Web Welds (at Location 1)

-327-

Page 331: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

or::.·""·.·._·_._._ .... ,-_.-::._-'"""_-_.~·-::-::. . ..... __ ,_..-· ._ . -- . . ' • :""':···_-__ ,,--__ • -. ·-.• ··- ·!""'!"'_-.~~--.• -~- .: ·-·~

- -_ ~-:.-:o,:·:.~: . ·: ·-- '

. --- ·"-·

"' \I - -~· .. ..>1"--·

(a) Inside View of Web

'(f ·:.:-.:.~tc..: ..•

1 \ ~~: . .L ,~ -~l,'·I-~J'i--~'-, -

(b) Outside View of Web

Fig .. 6 Inside and O~tside Photographs of Typical Cracks at the floor beam connection plate (or stiffener) Location

-328-

Page 332: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

I f Flange

·----·-- '"" .... .

Hovement of connection plate stresses end

1

point of weld

? i 7

Connection Pate (Stiffener)

weld cradk

\

Fatigue Cracking of Weld from Lack of Fusion at Weld

~----~~~~ ------------~~~

Connection Plate (stiffener)

\

'·Cracks at Weld Toe

~u-- _ web

Fig. 7 Schematic of· Cracking in-Connection Plate-to-Web and at Toe of Flange-to-Web Weld

-329-

Page 333: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

w w 0 I

2 " 6. b ~. ,.

,/, r-----~-' ~A d f ,_...._______,IY">r7Ti7r.--rmr-;-~~-~,

: : : ~ · Weld to top flange 1 • , .~ (o~ bolt to top flange :' 'h:===~====:_:jl with clip angl~ : • 1 on both sides)

I • I I • • I • I

I • • I 1• Floor

Beam I •

I • • 1- - - -I

l\, [_-_-___... ____ ]

7 I I

Fig. 8 Recommended Retrofit Scheme for Treatment of Floor Beam Connection Plates - Alternative 1

cu,t back the • connection plate

l - - - -rc========---1 I • o

I,. • I I

I • ,

~. . . f I' • I

I o •

1 r Floor I, I

Be<Jm I • , I I I o L - - - .r:========

l

___.W I

Fig. g Recommended Retrofit Scheme for Treatment of Floor Beam Connection Plate - Alternative 2

Page 334: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

..

r - - ·- -

L._ .. c: .

-r .r I

•..: Z\,. .·.

(a) Cutting out of top portion of connection plate

(b) Grinding smooth of the cut connection plate

Fig. 10 Photographs of Actual Retrofit Detail (at connecting p}ate in ~egacive moment region)

-332.-

Page 335: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

"' - - ,";:" .... . :. .

Fig. 11 Drilling Holes at the Ends of Crack at Web-to-Flange Weld

-332-

Page 336: fRffZ li't~R~£$!1llh'}~Q '~Z.tmitlr.~J ~'il!digital.lib.lehigh.edu/fritz/pdf/448_2_81_.pdf · 2012-08-01 · These case studies are a part of this report. 17. KeyWords ... As part

..

Fig. 12

.I

f't f 'ctua1 Retro l. Photographs 0 "- at Piers)

.1 (Stiffeners De tal.

-333-

(a)

(b)