Frequently Down Link Survey Report Gazipur Sub-Center
Summit Communications Limited
Frequently Down Link Survey Report, Gazipur Sub-Center
Last 3 Weeks Network Availability Report Under Gazipur Sub-Center
Week Link Name Duration Reason
W1
GPSDR22 to GPSDR09 3.32
OH fiber cut by third party
GPSDR37 to GPKLK04-
PAGG 2.37
OH fiber cut by excavator during road expansion work by R&H authority
GPSDR22 to GPSDR49 3.29
Core problem
GPSDR35_2-AGG to
GPSDR105.86
Fiber cut by e/p broken near Shimultoli-Shalna Railgate. Delayed due to PDB
activity.
PUBAIL-HO to GPSDR06 9.38
Fiber stolen at Boshugao. Delayed due to another link rectification and police
restriction
W2
GPSDR35_2-AGG to
GPSDR102.52 Fiber burnt by X-FORMER blast, delayed as
DESCO was working
GPKLK13 to GPKLK11 11.74 Core problem. Delayed due to OTDR
machine problem
GPSDR39 to GPSDR60
0.93Single core break
GPSDR20 to GPSDR57
2.69Single core break
PUBAIL-HO to GPSDR20
2.83Fiber cut due to city corporation activity
Week Link Name Duration Reason
W3
GPSDR40 to GPSDR11
3.53Singlr core break due to high tension
GPSDR22 to GPSDR49
7.93
Fiber core problem. Delay due to team was engaed at another link.
GPKLK10 to GPSDR09
3.88
OF cut by electric pole broken. Delay due to dependency on new pole installation of by
power authority.
GPKLK04-PAGG to GPSDR37-Ring103 and
GPKLK04-PAGG to GPSDR40-Ring104 and
GPKLK04-PAGG to Savar-POP and GPKLK04-
PAGG to GPSDR35-AGG
13.18All the OH fiber cut by R&H authority during flyover constructions work and Electric pole
shifting by power authority at Konabari. Delay due to restrictions of Police, R&H authority.
GPKLK04-PAGG to GPSDR35-
AGG and GPKLK04-PAGG
to Savar-POP
3.92All the OH fiber cut by power authority during Electric pole shifting at Konabari. Delay due to
restrictions of power authority.
GPKLK10 to GPSDR09 1.93 OF cut by third party during their maintenance
activity.
Frequently Down Link Survey Report, Gazipur Sub-Center
Reason For Outage:i) Road expansion work ongoing.ii) Electric pole shifting ongoing by power
authority.iii) Flyover construction work ongoing at
Konabari area.
Link Name:i) GPKLK04-PAGG to GPSDR35-AGGii) GPKLK04-PAGG to Savar-POPiii) GPKLK04-PAGG to GPSDR40iv) GPKLK04-PAGG to GPSDR37
Photo-2: Flyover construction workPhoto-1: Electric pole shifting ongoing
Road crossing
cable
Action Plan:i) We have shifted our OH cable to
newly installed electric pole on the another side of road to avoid road crossing.
ii) Deployed approx. 1 KM new OF for each link.
iii) For the remaining portions, we guided to vendor team to follow-up on R&H and Power authority’s activity.
Photo-3: Road expansion & Flyover constructions work at the same place at Konabari.
Photo-4: We have shifted OH cable to this newly installed electric pole.
Newly installed
E/P
Frequently Down Link Survey Report, Gazipur Sub-Center
Action Plan:i) We have shifted our OH cable to newly
installed electric pole. A few portions is pending due to dependency on completion of R&H and Power authority activities. After completion of power authorities activity, we will shift another portions of OH cable to newly deployed electric pole.
Reason For Outage:i) Power authority & R&H cut all the OH
cable during electric pole shifting and transformer installation.
ii) They are doing this activity in daily basis.
Photo-5: Electric pole shifting & Flyover constructions work ongoing at the remaining portions of GPKLK04 to GPSDR35, GPKLK04 to GPSDR40 and GPKLK04 to Savar POP link. We will shift OH cable from old pole to new pole after completion of power authorities activity.
Old electric
pole with our OH cable
Newly installed
pole
Link Name:i) GPKLK04-PAGG to GPSDR35-AGGii) GPKLK04-PAGG to Savar-POPiii) GPKLK04-PAGG to GPSDR40iv) GPKLK04-PAGG to GPSDR37
Frequently Down Link Survey Report, Gazipur Sub-Center
Action Plan:i) We have deployed approx. 1.2 KM new
OF recently to improve fiber conditions.
ii) We will shifted our OH cable from old electric pole to newly deployed pole.
iii) We are maintaining continuous communications with power authority to follow-up their activities. Thus we can reduced the outage time.
Reason For Outage:i) OH cable’s conditions is not
satisfactory. ii) R&H and Power authority cut all the
OH cable from pole during electric pole shifting and Flyover constructions activity.
iii) Maintenance/Rectifications being delay due to River crossing cable.
Photo 1-2: River crossing OH cable of ‘GPSDR40 to GPSDR11’ link
River crossing OH cable
Old Electric
pole
Newly deployed
pole
Link Name:i) GPSDR40 to GPSDR11
Photo: 1
Photo: 2
Frequently Down Link Survey Report, Gazipur Sub-Center
Action Plan:i) We have shifted OH cable to
newly installed pole for the completed portion of pole shifting.
ii) Permanent solutions is not possible at this time due to R&H and Power authority not completed their activity.
Reason For Outage:i) Electric pole shifting ongoing at
Konabari area due to road expansion work in daily basis.
ii) OH fiber cut several times by R&H and power authority during their activity.
Photo 3-4: Shifted OH cable of ‘GPSDR40 to GPSDR11’ link
Link Name:i) GPSDR40 to GPSDR11.
Photo: 3
Photo: 4 Photo: 5
Old E/P
New E/P
Old E/P
New E/P with our
OF
Pole shifting
ongoing for another portion
Photo 5: Pending area of pole shifting. Work ongoing by daily basis
Frequently Down Link Survey Report, Gazipur Sub-Center
Action Plan:i) We need new fiber to stable this
link by improving cable conditions and reducing TJ.
ii) OH cable laid and fixed as possible better way.
iii) Used medicine to avoid core cut by Ant.
Reason For Outage:i) OH cable conditions is not
satisfactory. Also Enormous numbers of TJ exists at this link.
ii) Due to inadequate numbers of electric pole OH cable laid through the Trees. Thus the OH cable cut frequently during Tree cutting, Windy weather and several times core cutting by Ant inside of TJ box..
Photo 1-2: OH cable laid through the Trees due to inadequate numbers of electric pole
Link Name:i) GPSDR49 to GPSDR22
Photo: 1 Photo: 2
Our OH cable through Trees
Absence of electric
pole
Frequently Down Link Survey Report, Gazipur Sub-Center
i) R&H activity ongoing by daily basis.ii) During road expansion Power authority also shift old electric pole to new pole. Its also ongoing by daily basis.iii) Due to road expansion and Flyover constructions activity at Konabri, Team surviving heavy traffic jam from
‘Gazipur chowrasta to Konabari’ and ‘Vogra bypass road to Konabari’ road. Thus the Team movement being delay. Most of the frequently down links are on these way.
iv) OH cable condition is not satisfactory for some links.v) There was also river crossing OH cable for GPSDR40 to GPSDR11 link. Which required more time during any
rectifications. To reduce rectifications time we have done a meeting regarding smooth operations such as quick response by field team after getting SMS from NOC, Reducing the repeated link down, Separate team for Day & Night schedule with our OH vendor JF optical services Ltd.
Common causes for the frequent link down and delay rectifications for last 3 weeks:
Frequently Down Link Survey Report, Gazipur Sub-Center