Frequently Down Link Survey Report Gazipur Sub-Center

Summit Communications Limited

Page 2: Frequently Down Link Survey (2)

Frequently Down Link Survey Report, Gazipur Sub-Center

Last 3 Weeks Network Availability Report Under Gazipur Sub-Center

Week Link Name Duration Reason

W1

GPSDR22 to GPSDR09 3.32

OH fiber cut by third party

GPSDR37 to GPKLK04-

PAGG 2.37

OH fiber cut by excavator during road expansion work by R&H authority

GPSDR22 to GPSDR49 3.29

Core problem

GPSDR35_2-AGG to

GPSDR105.86

Fiber cut by e/p broken near Shimultoli-Shalna Railgate. Delayed due to PDB

activity.

PUBAIL-HO to GPSDR06 9.38

Fiber stolen at Boshugao. Delayed due to another link rectification and police

restriction

W2

GPSDR35_2-AGG to

GPSDR102.52 Fiber burnt by X-FORMER blast, delayed as

DESCO was working

GPKLK13 to GPKLK11 11.74 Core problem. Delayed due to OTDR

machine problem

GPSDR39 to GPSDR60

0.93Single core break

GPSDR20 to GPSDR57

2.69Single core break

PUBAIL-HO to GPSDR20

2.83Fiber cut due to city corporation activity

Week Link Name Duration Reason

W3

GPSDR40 to GPSDR11

3.53Singlr core break due to high tension

GPSDR22 to GPSDR49

7.93

Fiber core problem. Delay due to team was engaed at another link.

GPKLK10 to GPSDR09

3.88

OF cut by electric pole broken. Delay due to dependency on new pole installation of by

power authority.

GPKLK04-PAGG to GPSDR37-Ring103 and

GPKLK04-PAGG to GPSDR40-Ring104 and

GPKLK04-PAGG to Savar-POP and GPKLK04-

PAGG to GPSDR35-AGG

13.18All the OH fiber cut by R&H authority during flyover constructions work and Electric pole

shifting by power authority at Konabari. Delay due to restrictions of Police, R&H authority.

GPKLK04-PAGG to GPSDR35-

AGG and GPKLK04-PAGG

to Savar-POP

3.92All the OH fiber cut by power authority during Electric pole shifting at Konabari. Delay due to

restrictions of power authority.

GPKLK10 to GPSDR09 1.93 OF cut by third party during their maintenance

activity.

Page 3: Frequently Down Link Survey (2)

Frequently Down Link Survey Report, Gazipur Sub-Center

Reason For Outage:i) Road expansion work ongoing.ii) Electric pole shifting ongoing by power

authority.iii) Flyover construction work ongoing at

Konabari area.

Link Name:i) GPKLK04-PAGG to GPSDR35-AGGii) GPKLK04-PAGG to Savar-POPiii) GPKLK04-PAGG to GPSDR40iv) GPKLK04-PAGG to GPSDR37

Photo-2: Flyover construction workPhoto-1: Electric pole shifting ongoing

Road crossing

cable

Action Plan:i) We have shifted our OH cable to

newly installed electric pole on the another side of road to avoid road crossing.

ii) Deployed approx. 1 KM new OF for each link.

iii) For the remaining portions, we guided to vendor team to follow-up on R&H and Power authority’s activity.

Photo-3: Road expansion & Flyover constructions work at the same place at Konabari.

Photo-4: We have shifted OH cable to this newly installed electric pole.

Newly installed

E/P

Page 4: Frequently Down Link Survey (2)

Frequently Down Link Survey Report, Gazipur Sub-Center

Action Plan:i) We have shifted our OH cable to newly

installed electric pole. A few portions is pending due to dependency on completion of R&H and Power authority activities. After completion of power authorities activity, we will shift another portions of OH cable to newly deployed electric pole.

Reason For Outage:i) Power authority & R&H cut all the OH

cable during electric pole shifting and transformer installation.

ii) They are doing this activity in daily basis.

Photo-5: Electric pole shifting & Flyover constructions work ongoing at the remaining portions of GPKLK04 to GPSDR35, GPKLK04 to GPSDR40 and GPKLK04 to Savar POP link. We will shift OH cable from old pole to new pole after completion of power authorities activity.

Old electric

pole with our OH cable

Newly installed

pole

Link Name:i) GPKLK04-PAGG to GPSDR35-AGGii) GPKLK04-PAGG to Savar-POPiii) GPKLK04-PAGG to GPSDR40iv) GPKLK04-PAGG to GPSDR37

Page 5: Frequently Down Link Survey (2)

Frequently Down Link Survey Report, Gazipur Sub-Center

Action Plan:i) We have deployed approx. 1.2 KM new

OF recently to improve fiber conditions.

ii) We will shifted our OH cable from old electric pole to newly deployed pole.

iii) We are maintaining continuous communications with power authority to follow-up their activities. Thus we can reduced the outage time.

Reason For Outage:i) OH cable’s conditions is not

satisfactory. ii) R&H and Power authority cut all the

OH cable from pole during electric pole shifting and Flyover constructions activity.

iii) Maintenance/Rectifications being delay due to River crossing cable.

Photo 1-2: River crossing OH cable of ‘GPSDR40 to GPSDR11’ link

River crossing OH cable

Old Electric

pole

Newly deployed

pole

Link Name:i) GPSDR40 to GPSDR11

Photo: 1

Photo: 2

Page 6: Frequently Down Link Survey (2)

Frequently Down Link Survey Report, Gazipur Sub-Center

Action Plan:i) We have shifted OH cable to

newly installed pole for the completed portion of pole shifting.

ii) Permanent solutions is not possible at this time due to R&H and Power authority not completed their activity.

Reason For Outage:i) Electric pole shifting ongoing at

Konabari area due to road expansion work in daily basis.

ii) OH fiber cut several times by R&H and power authority during their activity.

Photo 3-4: Shifted OH cable of ‘GPSDR40 to GPSDR11’ link

Link Name:i) GPSDR40 to GPSDR11.

Photo: 3

Photo: 4 Photo: 5

Old E/P

New E/P

Old E/P

New E/P with our

OF

Pole shifting

ongoing for another portion

Photo 5: Pending area of pole shifting. Work ongoing by daily basis

Page 7: Frequently Down Link Survey (2)

Frequently Down Link Survey Report, Gazipur Sub-Center

Action Plan:i) We need new fiber to stable this

link by improving cable conditions and reducing TJ.

ii) OH cable laid and fixed as possible better way.

iii) Used medicine to avoid core cut by Ant.

Reason For Outage:i) OH cable conditions is not

satisfactory. Also Enormous numbers of TJ exists at this link.

ii) Due to inadequate numbers of electric pole OH cable laid through the Trees. Thus the OH cable cut frequently during Tree cutting, Windy weather and several times core cutting by Ant inside of TJ box..

Photo 1-2: OH cable laid through the Trees due to inadequate numbers of electric pole

Link Name:i) GPSDR49 to GPSDR22

Photo: 1 Photo: 2

Our OH cable through Trees

Absence of electric

pole

Page 8: Frequently Down Link Survey (2)

Frequently Down Link Survey Report, Gazipur Sub-Center

i) R&H activity ongoing by daily basis.ii) During road expansion Power authority also shift old electric pole to new pole. Its also ongoing by daily basis.iii) Due to road expansion and Flyover constructions activity at Konabri, Team surviving heavy traffic jam from

‘Gazipur chowrasta to Konabari’ and ‘Vogra bypass road to Konabari’ road. Thus the Team movement being delay. Most of the frequently down links are on these way.

iv) OH cable condition is not satisfactory for some links.v) There was also river crossing OH cable for GPSDR40 to GPSDR11 link. Which required more time during any

rectifications. To reduce rectifications time we have done a meeting regarding smooth operations such as quick response by field team after getting SMS from NOC, Reducing the repeated link down, Separate team for Day & Night schedule with our OH vendor JF optical services Ltd.

Common causes for the frequent link down and delay rectifications for last 3 weeks:

Page 9: Frequently Down Link Survey (2)

Frequently Down Link Survey Report, Gazipur Sub-Center