FREMONT UNIFIED S C H O O L D I S T R I C T
Hopkins Middle School Conversion
October 30, 2019
2
Transforming Hopkins Junior High School
• Incoming sixth-graders in year 2022-23
• Design based on capacity of 1,352
• Recently received enrollment numbers
will be analyzed; design capacity can
be adjusted
3
Assessment – Site
• Inadequate main campus entry
• Site path of travel not fully ADA compliant
• Maintenance heavy landscaping
• Campus flooding
• Worn site features and furnishings
• Poor pick-up and drop-off circulation
• Insufficient parking
• Portable classrooms located across
parking lot
4
Assessment – Architectural
• Degradation of building exterior
• Outdated classrooms
• Extensive dry rot at building eaves
• Toilet room and buildings not ADA
compliant
• Outdated food service facilities and
equipment
• Clogged roof drains and ponding water
• Lack of a true multipurpose building
• Undersized gym and locker, unused
showers
5
Assessment – Structural, Mechanical,
Electrical and Plumbing (MEP) System
• Inadequate electrical service
• Mechanical systems at the end of
useful life
• Inefficient lighting, at the end of useful
life
• Inadequate campus Information
Technology network
• Worn campus infrastructure
• Outdated public address system and
clock
• Outdated fire alarm system
6
Transforming an Existing Campus
• New campus entry
• Improved parking, drop-off and pick-
up
• Construct student union and optional
music room
• Construct two-story classroom
building
• Expanded administration
• Modernize existing buildings
• Middle School Conversion fall 2022
7
LEGEND
NEW CONSTRUCTION
VERY MINOR MODERNIZATION
MINOR MODERNIZATION
MODERATE MODERNIZATION
MAJOR MODERNIZATION / RECONFIGURED
PLAY YARD/SITE ENHANCEMENT
MODERATE SITE ENHANCEMENT
FUTURE PORTABLES
REMOVED PORTABLES
Housed in Existing Permanent Structures 931
Housed in Existing Temporary Portables 0
Housed in New Permanent Structures 421
Total Capacity 1,352
Estimated Project Cost (1,352 Capacity) $ 68,874,728
Design Option 11,352 Capacity
Net Classroom add = 3
8
LEGEND
NEW CONSTRUCTION
VERY MINOR MODERNIZATION
MINOR MODERNIZATION
MODERATE MODERNIZATION
MAJOR MODERNIZATION / RECONFIGURED
PLAY YARD/SITE ENHANCEMENT
MODERATE SITE ENHANCEMENT
FUTURE PORTABLES
REMOVED PORTABLES
Housed in Existing Permanent Structures 964
Housed in Existing Temporary Portables 0
Housed in New Permanent Structures 388
Total Capacity 1,352
Estimated Project Cost (1,352 Capacity) $ 82,388,131
Design Option 2A1,352 Capacity + More Mod + Music Classroom
Net Classroom add = 3
9
LEGEND
NEW CONSTRUCTION
VERY MINOR MODERNIZATION
MINOR MODERNIZATION
MODERATE MODERNIZATION
MAJOR MODERNIZATION / RECONFIGURED
PLAY YARD/SITE ENHANCEMENT
MODERATE SITE ENHANCEMENT
FUTURE PORTABLES
REMOVED PORTABLES
Housed in Existing Permanent Structures 964
Housed in Existing Temporary Portables 0
Housed in New Permanent Structures 388
Total Capacity 1,352
Estimated Project Cost (1,352 Capacity) $ 84,061,263
Design Option 2BOption 2A + Larger Student Union
Net Classroom add = 3
10
Option 11,352 Capacity
Option 2A 1,352 Capacity + More
Modernization + New Music Classroom
Option 2BOption 2A + Larger Student Union
Estimate
Budget
Difference
Est. (1,352 Enrollment)
$ 68,874,728
$ 68,100,344
$ (774,384)
$ 68,874,728
$ 82,388,121
$ 68,100,344
$ (14,278,787)
$ 82,388,121
$ 84,061,263
$ 68,100,344
$ (15,960,919)
$ 84,061,263
Options &
Budget
11
Middle School Conversion Budget
• Board authorized additional $45.5 million for Centerville
and Hopkins middle school conversion projects
• Board authorized Option 2d for Centerville, using $19.7
million from the additional allocation
• $25.8 million remains unallocated
12
TBD
• Receive Board input on desired options
• Reevaluate number of classrooms
• Receive Board approval to move into
schematic design
• Procure construction manager
• Procure lease-lease back contractor
Next Steps
13
Reference Slides
14
Very Minor Minor Modernization Moderate Modernization Major Modernization
Architectural • Repair roofing, caps• Patch & paint ceilings, walls• Accessibility compliance –
bathrooms, door hardware, thresholds, casework
• Repair dry rot
• Everything in +• Paint 100%
• Everything in +• Replace selective
replacement of classroom wall finishes, flooring
• Upgrade locker rooms • Selective replacement of
casework
• Everything in +• Replace full roofing• Replace all doors and
windows• New non-bearing
walls, interior finishes.• New casework
Structural None None, unless necessary to support new HVAC units
Same as Everything in
Mechanical None Replace outdated HVAC w/new efficient units
Replace outdated HVAC w/new efficient units
• Everything in +• Full mech. upgrade
Electrical Replace/repair non-functioning and non-compliant fixtures, switches, receptacles, etc.
• Everything in +• Replace fixtures in poor
condition
• Everything in +• New wiring, lighting,
controls, life safety at reconfigured areas
• Everything in +• Full electrical upgrade
Plumbing None Replace & relocate fixtures where necessary
Replace & relocate fixtures where necessary
• Everything in +• Full plumbing
upgrade
/ Reconfigured
Modernization Scope
15
Design Approach
16
Design Approach
17
Design Approach