fr formulation
TRANSCRIPT
-
7/31/2019 Fr Formulation
1/39
FORMULATION OF
PROJECT REPORTAND APPRAISAL
-
7/31/2019 Fr Formulation
2/39
DEMAND FORECAST
PEAK DEMAND BY END OF XIAND XII PLAN IS PROJECTEDAS 1,57,107 MW AND 2,12,759
MW RESPECTIVELY.
TO MEET THE PROJECTED
DEMAND, OVER 61,513 MW ISTO BE ADDED DURING XI PLANPERIOD.
-
7/31/2019 Fr Formulation
3/39
PRESENTATION OUTLINE
Power sector - Key Issues
NTPC in Indian Power Sector Project Report Formulation
-
7/31/2019 Fr Formulation
4/39
Declining trend of capacity additionw.r.t. growth in demand leading topersisting peeking as well as energyshortages.
Poor financial health of State PowerUtilities and under utilization ofexisting capacity
Increasing Cost of Power
Grid In-discipline
Inefficient Operation
POWER SECTOR KEY ISSUES
-
7/31/2019 Fr Formulation
5/39
GENERATING CAPACITY 1,45,588 MWFUEL MIX
Nuclear
4,120 MW
(2.8%)
Thermal
93,115 MW
(64.0%)
Hydro36,159MW
(24.8%)
Renewable
12,194MW(8.4%)
In addition, Captive generating capacity ( above 1 MW) of approximately 23,350 MW(as on 31.03.08)
# Includes SHP 2120 MW, Wind - 8580 MW, Biogas 1406 MW, Urban/ Industrial waste 88 MW
etc.Source : CEA
Coal + Lignite 77,199 MW
Gas 14,716 MW
Diesel 1,200 MW
POWER INFRASTRUCTURE IN INDIA(end July.08)
#
-
7/31/2019 Fr Formulation
6/39
Central
Sector
33%
State
Sector
52%
Private
Sector
15%
(75,655 MW)
(48,611 MW)(21,322 MW)
Source: CEA
POWER INFRASTRUCTURE IN INDIA(end July.08)
GENERATING CAPACITY 1,45,588 MW
In addition, Captive generating capacity ( above 1 MW) of approximately 23,350 MW(as on 31.03.08)
-
7/31/2019 Fr Formulation
7/39
TRANSMISSION & NATIONAL GRID
CENTRAL SECTOR TRANSMISSION PLAN : PERFORMANCE
At thebeginning
of Xth Plan
AdditionDuring
Xth Plan
Atbeginning
of XIth Plan
AdditionDuring 2007-
08
Transmission Network (ckm) 41,217 25,362 66,579 6,559
Transformation Capacity
(MVA)
31,441 23,290 54,731 14,075
Sub-stations (Nos.) 68 35 103 24
Inter regional transfer
capacity (200 kV and above)
(MW)
5,000 9,100 14,100 2,100 *
* Targeted capacity by end of XIth Plan 37,000 MW
-
7/31/2019 Fr Formulation
8/39
High Potential for Growth ofIndian Power SectorParameters 1990-91 2003-04 2004-05
Per Capita Consumption(kWh)
332 566 606
PLF (%) 53.8 72.7 74.8
Energy Shortage (%) 7.9 7.1 7.3
Peaking Shortage (%) 15.5 11.2 11.7
Per Capita Consumption in kWh (2002)China : 1484 Brazil : 2183Malaysia : 3234 USA : 13456
Source: UN Development Program, Human Development Indicators, 2005
PROJECTED PER CAPITA CONSUMPTION IN 2012 : 932
-
7/31/2019 Fr Formulation
9/39
HYDRO THERMAL NUCLEAR TOTAL
CENTRALSECTOR
10969 19065 3160 33194
STATESECTOR 4964 14610 0 19574
PRIVATESECTOR
2064 12845 0 14909
TOTAL 17997 46520 3160 67677
-
7/31/2019 Fr Formulation
10/39
NEW CAPACITY ADDITION OF NTPC
NTPCS CORPORATE PLAN ENVISAGECAPACITY ADDITION OF 22,400 MWDURING XI PLAN TO BECOME 50,000 MWCOMPANY BY 2012 AND CAPACITYADDITION OF 25,000 MW DURING XIIPLAN TO BECOME 75,000 MW PLUS
COMPANY BY 2017.
IMPLEMENTATION OF INTEGRATED POWERPROJECTS WITH CAPTIVE MINING.
ALL ACTIVITIES W.R.T. PREPARATION OFFRS AND STATUTORY CLEARANCES/APPROVALS FOR THE ABOVE CAPACITYPOWER PROJECTS SHALL BE CARRIED OUTIN-HOUSE.
-
7/31/2019 Fr Formulation
11/39
Allocation of Coal MinesSl.
No.
BlockName
Geo. Res.(Mt)
Mine Cap.(Mtpa)
Explor-ation
Status
Ant. Yearof Coal
Production
IdentifiedPower Plant
1 Tillaipalli 965 15 Drilling tobe taken up
2011-12 Lara (4000MW)(now being
considered forDarlipali)
2 Kerandari 228 8 DrillingCompleted;
GR to bemade
2011-12 Barh-II andTanda-II
3 ChattiBariatu
243 5 GRavailable
2010-11
4 Dulunga 260 5 7000mdrilling left
2011-12 Darlipalli (3200MW)
5 Chhatra-saal
150 3 2000 mdrilling left
2013-14 Shortfall ofSingrauliRegion
6 Brahmini(Chichro
Patsimal)
1900+356 20 Drilling tobe taken up
2013-14 Kahalgaon &Farakka Expn.
-
7/31/2019 Fr Formulation
12/39
FEASIBILITY REPORT FORMULATION
TECHNICAL
ENVIRONMENTALISSUES
POWERDEMAND-SUPPLY GAP
COMMERCIAL
-
7/31/2019 Fr Formulation
13/39
STAGES OF PLANNINGCONSTRUCTION STAGE
INVESTMENT DECISION
STATUTORY CLEARANCES
EVALUATION & APPRAISAL ENVIRONMENTAL
TECHNO ECONOMIC
COST ESTIMATE
FEASIBILITY REPORT/ OTHER INPUTS
DETAILED PROJ REPORT CIVIL, MECH, ELECT & C&I INPUTS
BASIC ENGGSITE SPECIFIC STUDIES/INVESTIGATIONS
PROJECT SITE SELECTION/PRE-FEASIBILITY STUDIES
FEASIBLITY
-
7/31/2019 Fr Formulation
14/39
Proper siting of thermal power plantsreduce the cost of project, cost ofpollution control measures and alsoreduces the damage to natural and
human environment.
Due consideration needs to be given totopography, geology, hydrology,
meteorology, fuel storage, ash disposaletc. in the selection of site.
-
7/31/2019 Fr Formulation
15/39
Selection of environmentally acceptablesites for thermal power projects isguided by Siting Criteria of Ministry ofEnvironment & Forests (MOEF) which
cover the following:
Prime Agricultural Land and ForestLand may not be converted into an
industrial site.
-
7/31/2019 Fr Formulation
16/39
At least 25 kms from the projectedgrowth boundary of Major Settlement/Metropolitan cities (3,00,000population).
Acquisition of land should be minimumbut sufficient to provide for a green belt.
At least 500 meters from the High TideLine (HTL) in coastal areas.
-
7/31/2019 Fr Formulation
17/39
At least 500 meters from NationalHighways, Railway lines and flood plainor modified flood plain of riverinesystems.
The chimney should not fall within theapproach funnel of the runway of thenearest airport.
-
7/31/2019 Fr Formulation
18/39
Basic Inputs:-
Land
Water
Fuel
-
7/31/2019 Fr Formulation
19/39
LANDLocation & Approach
Requirement
Site Specific Data
Siting Criteria of MOEF
Land Use PlanLand cost
-
7/31/2019 Fr Formulation
20/39
WATER
Source
Requirement
Quality Parameters
Drawl point
-
7/31/2019 Fr Formulation
21/39
FUEL Fuel source
Quality Parameters
Requirement
Fuel Transportation
Cost
-
7/31/2019 Fr Formulation
22/39
NEW PROJECT DEVELOPMENT
FEASIBILITY
REPORT
IDENTIFICATION OF
POTENTIAL SITES
STATUTORY
CLEARANCES/
COMMITMENTS
SITE SPECIFIC STUDIES
/ INVESTIGATION
DETAILED SITE
SELECTION &
PRE-FR
SITE CLEARANCE OF
MOEF
COST ESTIMATES &
FINANCIAL ANALYSIS
FINANCIAL
APPRAISAL BY FIsINVESTMENT APPROVAL OF
THE PROJECT
-
7/31/2019 Fr Formulation
23/39
-
7/31/2019 Fr Formulation
24/39
Approval of Terms Of Reference (TOR) for EIAstudy as per new Gazette notification of MOEFdated 14.09.06
Land Commitment (State Govt.) Water Commitment (State Govt.) Fuel Commitment (SLC-LT) Fuel Transportation Clearance (Min. of
Railways)
Defence Clearance (Min. of Defence) Comfort Letters from Beneficiaries Resolution in Respective REB Meeting in
respect of Absorption of Power from theProject
-
7/31/2019 Fr Formulation
25/39
Associated Transmission System (ATS)Clearance
NOC from Airports Authority of India Minutes of Public Consultation from SPCB Concurrence of Central Water Commission/
MOWR on Water Availability Environmental Clearance from Ministry of Env.
and Forests
FORMULATION OF FR / DPR
-
7/31/2019 Fr Formulation
26/39
Tie-up of Basic Inputs
Conduct Site Specific Studies/Investigations
Basic Engg./System Finalisation
Technical Inputs (Write up, BOQ,Drawings)
Inputs other than Technical
Clearances / Commitment Financing Plan
Cost Estimates
FORMULATION OF FRs/ DPRs
FORMULATION OF FR / DPR
-
7/31/2019 Fr Formulation
27/39
Financial Appraisal by FIs post FR/DPR Finalisation
TEC of CEA Pre and Post ElectricityAct- 2003 Scenario
Development of Infrastructure Financial Appraisal by FIs prior to
Investment Decision
Statutory Clearances/ Commitments
FORMULATION OF FRs/ DPRs
FEASIBILITY REPORT CONTENTS
-
7/31/2019 Fr Formulation
28/39
Executive Summary
Introduction
Demand Analysis and Justification
Feasibility Studies Layout Systems
Civil Works
Mechanical Systems Electrical Systems
Control & Instrumentation Systems
FEASIBILITY REPORT- CONTENTS
FEASIBILITY REPORT CONTENTS
-
7/31/2019 Fr Formulation
29/39
Environmental Aspects
Technical Data & Bill of Quantity
Cost Estimate & Financial Analysis
Project Implementation Manpower training & Placement
Operation & Maintenance Philosophy
Marketing Philosophy List of Annexure
List of Exhibits
FEASIBILITY REPORT- CONTENTS
INFRASTRUCTURE DEVELOPMENT
-
7/31/2019 Fr Formulation
30/39
Initiate activities for land acquisitionunder Land Acquisition Act
Construction of Boundary Wall/Fencing of the acquired land
Construction of Site Office, Storesand other temporary building tofacilitate construction activities
Site Levelling of Plant incl. PriorityArea of Township
Construction Power & Start-up Power
INFRASTRUCTURE DEVELOPMENT
INFRASTRUCTURE DEVELOPMENT
-
7/31/2019 Fr Formulation
31/39
Construction Water Scheme
Communication & EDP facilities
Training Centre, Public InformationCentre and other R&R activities
Primary Health Care
Establishment of Security Complex
INFRASTRUCTURE DEVELOPMENT
INVESTMENT APPROVAL
-
7/31/2019 Fr Formulation
32/39
Availability of Infrastructure
All clearances/ commitments inposition
PPAs signed with beneficiaries
ATS finalised and would beimplemented matching power projectschedule.
Financial Appraisal by FIs prior toInvestment Decision
INVESTMENT APPROVAL
SCHEDULE FOR PROJECT FORMULATION ACTIONS Th l
-
7/31/2019 Fr Formulation
33/39
SCHEDULE FOR PROJECT FORMULATION ACTIONS ThermalZero Date - Project Initiation and Identification of Potential Sites
Main Plant Award relatedactivities (Month from zero date)
Green Field Expn.Project
Investment Approvalactivities (Month fromzero date)
GreenField
Expn.Project
Specs. Preparation 10 7
Site Selection/Pre FR 3 0
FSC for Main Plant 13 10
FR Preparation 12 9
Studies/Investigationsand Statutory Clearances
10 7
Financial Appraisal 12 9
FR Finalisation 13 10
Public Hearing (SPCB) 15 12
NIT 14 11
Environmental Clearance 19 16
OBD 17 14
Financial Appraisal 18 15
Main Plant Package Award 20 17Investment Approval 19 16
-
7/31/2019 Fr Formulation
34/39
-
7/31/2019 Fr Formulation
35/39
Project Name Capacity(MW)
Location Capacity Addition(MW)
Kahalgaon-II 1500 Bhagalpur(Bihar) 1000
Sipat-II 1000 Bilaspur (Chhattisgarh) 1000
Sipat-I 1980 Bilaspur (Chhattisgarh) 1980
Barh-I 1980 Patna (Bihar) 1980
Bhilai JV 500 Bhilai (Chhattisgarh) 500
Korba-III 500 Korba (Chhattisgarh) 500
Farakka-III 500 Murshidabad (W. B.) 500
NCTPP-II 980 Gautam Budh Nagar (U. P.) 980Simhadri-II 1000 Visakhapatnam (A. P.) 1000
Aravali JV withHPGCL & IPGCL
1500 Jajjar (Haryana) 1500
Ennore-JV with TNEB 1500 Thiruvallur (Tamil Nadu) 1500
Bongaigaon 750 Kokhrajhar (Assam) 750
North Karanpura 1980 Chatra & Hazaribagh (Jharkhand) 1320
Barh-II 1320 Patna (Bihar) 1320
Nabinagar JV withRlys.
1000 Aurangabad (Bihar) 750
Vindhachal-III 1000 Sidhi (M.P.) 1000
Mauda 1000 Nagpur (Maharashtra) 1000
Rihand-II 1000 U.P. 1000
Muzafferpur II 500 Bihar 500
XI PLAN PROJECTS (THERMAL GAS)
-
7/31/2019 Fr Formulation
36/39
XI PLAN PROJECTS (THERMAL-GAS)
Project Name Capacity(MW) Location CapacityAddition(MW)
Kawas CCPP, Stage-II* 1300 Surat (Gujarat) 1300
J. Gandhar CCPP, Stage-II* 1300 Bharuch (Gujarat) 1300
Total 2,600 2,600
* To be taken up after fuel availability is ascertained.
XI PLAN PROJECTS (HYDRO)
-
7/31/2019 Fr Formulation
37/39
XI PLAN PROJECTS (HYDRO)
Project Name Capacity(MW) Location CapacityAddition(MW)
Koldam 800 Bilaspur (H.P.) 800
Loharinag Pala 600 Uttarkashi (Uttaranchal) 600
Tapovan Vishnugad 520 Chamoli (Uttaranchal) 520
-
7/31/2019 Fr Formulation
38/39
Project Name Location Capacity(MW)
ThermalMarakkanam Villupuram (Tamil Nadu) 4000
Cheyyur Kanchipuram (Tamil Nadu) 2000/2400
Aravali-II, Jhajjar, Haryana 1000
Vindhyachal-IV Sidhi (M.P) 500
Rihand-III Sonbhadra (UP) 500
Darlipali Sundergarh (Orissa) 3200
Gajmara Dhenkanal (Orissa) 3200
Lara Raigarh (Chhattisgarh) 4000
Derang Angul (Orissa) 2400
New Nabinagar JV with BSEB Aurangabad (Bihar) 2640
Tanda-II Ambedkar Nagar (U.P.) 1000
Rajiv Gandhi CCPP (Kayamkulam) Allappuzha (Kerala) 1980
Meja STPP JV with PURVUN Allahabad (Uttar Pradesh) 1980
Nuclear 2000
Total 27,200
PROJECTS UNDER CONSIDERATION
-
7/31/2019 Fr Formulation
39/39
PROJECTS UNDER CONSIDERATION
Project Name Location Capacity
(MW)HYDRO
RupsiabagarKhasiabara
Uttaranchal 260
Etalin Ar. Pradesh 4000
Attunli Ar. Pradesh 500
Total 4760