fr formulation

Upload: sam

Post on 05-Apr-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Fr Formulation

    1/39

    FORMULATION OF

    PROJECT REPORTAND APPRAISAL

  • 7/31/2019 Fr Formulation

    2/39

    DEMAND FORECAST

    PEAK DEMAND BY END OF XIAND XII PLAN IS PROJECTEDAS 1,57,107 MW AND 2,12,759

    MW RESPECTIVELY.

    TO MEET THE PROJECTED

    DEMAND, OVER 61,513 MW ISTO BE ADDED DURING XI PLANPERIOD.

  • 7/31/2019 Fr Formulation

    3/39

    PRESENTATION OUTLINE

    Power sector - Key Issues

    NTPC in Indian Power Sector Project Report Formulation

  • 7/31/2019 Fr Formulation

    4/39

    Declining trend of capacity additionw.r.t. growth in demand leading topersisting peeking as well as energyshortages.

    Poor financial health of State PowerUtilities and under utilization ofexisting capacity

    Increasing Cost of Power

    Grid In-discipline

    Inefficient Operation

    POWER SECTOR KEY ISSUES

  • 7/31/2019 Fr Formulation

    5/39

    GENERATING CAPACITY 1,45,588 MWFUEL MIX

    Nuclear

    4,120 MW

    (2.8%)

    Thermal

    93,115 MW

    (64.0%)

    Hydro36,159MW

    (24.8%)

    Renewable

    12,194MW(8.4%)

    In addition, Captive generating capacity ( above 1 MW) of approximately 23,350 MW(as on 31.03.08)

    # Includes SHP 2120 MW, Wind - 8580 MW, Biogas 1406 MW, Urban/ Industrial waste 88 MW

    etc.Source : CEA

    Coal + Lignite 77,199 MW

    Gas 14,716 MW

    Diesel 1,200 MW

    POWER INFRASTRUCTURE IN INDIA(end July.08)

    #

  • 7/31/2019 Fr Formulation

    6/39

    Central

    Sector

    33%

    State

    Sector

    52%

    Private

    Sector

    15%

    (75,655 MW)

    (48,611 MW)(21,322 MW)

    Source: CEA

    POWER INFRASTRUCTURE IN INDIA(end July.08)

    GENERATING CAPACITY 1,45,588 MW

    In addition, Captive generating capacity ( above 1 MW) of approximately 23,350 MW(as on 31.03.08)

  • 7/31/2019 Fr Formulation

    7/39

    TRANSMISSION & NATIONAL GRID

    CENTRAL SECTOR TRANSMISSION PLAN : PERFORMANCE

    At thebeginning

    of Xth Plan

    AdditionDuring

    Xth Plan

    Atbeginning

    of XIth Plan

    AdditionDuring 2007-

    08

    Transmission Network (ckm) 41,217 25,362 66,579 6,559

    Transformation Capacity

    (MVA)

    31,441 23,290 54,731 14,075

    Sub-stations (Nos.) 68 35 103 24

    Inter regional transfer

    capacity (200 kV and above)

    (MW)

    5,000 9,100 14,100 2,100 *

    * Targeted capacity by end of XIth Plan 37,000 MW

  • 7/31/2019 Fr Formulation

    8/39

    High Potential for Growth ofIndian Power SectorParameters 1990-91 2003-04 2004-05

    Per Capita Consumption(kWh)

    332 566 606

    PLF (%) 53.8 72.7 74.8

    Energy Shortage (%) 7.9 7.1 7.3

    Peaking Shortage (%) 15.5 11.2 11.7

    Per Capita Consumption in kWh (2002)China : 1484 Brazil : 2183Malaysia : 3234 USA : 13456

    Source: UN Development Program, Human Development Indicators, 2005

    PROJECTED PER CAPITA CONSUMPTION IN 2012 : 932

  • 7/31/2019 Fr Formulation

    9/39

    HYDRO THERMAL NUCLEAR TOTAL

    CENTRALSECTOR

    10969 19065 3160 33194

    STATESECTOR 4964 14610 0 19574

    PRIVATESECTOR

    2064 12845 0 14909

    TOTAL 17997 46520 3160 67677

  • 7/31/2019 Fr Formulation

    10/39

    NEW CAPACITY ADDITION OF NTPC

    NTPCS CORPORATE PLAN ENVISAGECAPACITY ADDITION OF 22,400 MWDURING XI PLAN TO BECOME 50,000 MWCOMPANY BY 2012 AND CAPACITYADDITION OF 25,000 MW DURING XIIPLAN TO BECOME 75,000 MW PLUS

    COMPANY BY 2017.

    IMPLEMENTATION OF INTEGRATED POWERPROJECTS WITH CAPTIVE MINING.

    ALL ACTIVITIES W.R.T. PREPARATION OFFRS AND STATUTORY CLEARANCES/APPROVALS FOR THE ABOVE CAPACITYPOWER PROJECTS SHALL BE CARRIED OUTIN-HOUSE.

  • 7/31/2019 Fr Formulation

    11/39

    Allocation of Coal MinesSl.

    No.

    BlockName

    Geo. Res.(Mt)

    Mine Cap.(Mtpa)

    Explor-ation

    Status

    Ant. Yearof Coal

    Production

    IdentifiedPower Plant

    1 Tillaipalli 965 15 Drilling tobe taken up

    2011-12 Lara (4000MW)(now being

    considered forDarlipali)

    2 Kerandari 228 8 DrillingCompleted;

    GR to bemade

    2011-12 Barh-II andTanda-II

    3 ChattiBariatu

    243 5 GRavailable

    2010-11

    4 Dulunga 260 5 7000mdrilling left

    2011-12 Darlipalli (3200MW)

    5 Chhatra-saal

    150 3 2000 mdrilling left

    2013-14 Shortfall ofSingrauliRegion

    6 Brahmini(Chichro

    Patsimal)

    1900+356 20 Drilling tobe taken up

    2013-14 Kahalgaon &Farakka Expn.

  • 7/31/2019 Fr Formulation

    12/39

    FEASIBILITY REPORT FORMULATION

    TECHNICAL

    ENVIRONMENTALISSUES

    POWERDEMAND-SUPPLY GAP

    COMMERCIAL

  • 7/31/2019 Fr Formulation

    13/39

    STAGES OF PLANNINGCONSTRUCTION STAGE

    INVESTMENT DECISION

    STATUTORY CLEARANCES

    EVALUATION & APPRAISAL ENVIRONMENTAL

    TECHNO ECONOMIC

    COST ESTIMATE

    FEASIBILITY REPORT/ OTHER INPUTS

    DETAILED PROJ REPORT CIVIL, MECH, ELECT & C&I INPUTS

    BASIC ENGGSITE SPECIFIC STUDIES/INVESTIGATIONS

    PROJECT SITE SELECTION/PRE-FEASIBILITY STUDIES

    FEASIBLITY

  • 7/31/2019 Fr Formulation

    14/39

    Proper siting of thermal power plantsreduce the cost of project, cost ofpollution control measures and alsoreduces the damage to natural and

    human environment.

    Due consideration needs to be given totopography, geology, hydrology,

    meteorology, fuel storage, ash disposaletc. in the selection of site.

  • 7/31/2019 Fr Formulation

    15/39

    Selection of environmentally acceptablesites for thermal power projects isguided by Siting Criteria of Ministry ofEnvironment & Forests (MOEF) which

    cover the following:

    Prime Agricultural Land and ForestLand may not be converted into an

    industrial site.

  • 7/31/2019 Fr Formulation

    16/39

    At least 25 kms from the projectedgrowth boundary of Major Settlement/Metropolitan cities (3,00,000population).

    Acquisition of land should be minimumbut sufficient to provide for a green belt.

    At least 500 meters from the High TideLine (HTL) in coastal areas.

  • 7/31/2019 Fr Formulation

    17/39

    At least 500 meters from NationalHighways, Railway lines and flood plainor modified flood plain of riverinesystems.

    The chimney should not fall within theapproach funnel of the runway of thenearest airport.

  • 7/31/2019 Fr Formulation

    18/39

    Basic Inputs:-

    Land

    Water

    Fuel

  • 7/31/2019 Fr Formulation

    19/39

    LANDLocation & Approach

    Requirement

    Site Specific Data

    Siting Criteria of MOEF

    Land Use PlanLand cost

  • 7/31/2019 Fr Formulation

    20/39

    WATER

    Source

    Requirement

    Quality Parameters

    Drawl point

  • 7/31/2019 Fr Formulation

    21/39

    FUEL Fuel source

    Quality Parameters

    Requirement

    Fuel Transportation

    Cost

  • 7/31/2019 Fr Formulation

    22/39

    NEW PROJECT DEVELOPMENT

    FEASIBILITY

    REPORT

    IDENTIFICATION OF

    POTENTIAL SITES

    STATUTORY

    CLEARANCES/

    COMMITMENTS

    SITE SPECIFIC STUDIES

    / INVESTIGATION

    DETAILED SITE

    SELECTION &

    PRE-FR

    SITE CLEARANCE OF

    MOEF

    COST ESTIMATES &

    FINANCIAL ANALYSIS

    FINANCIAL

    APPRAISAL BY FIsINVESTMENT APPROVAL OF

    THE PROJECT

  • 7/31/2019 Fr Formulation

    23/39

  • 7/31/2019 Fr Formulation

    24/39

    Approval of Terms Of Reference (TOR) for EIAstudy as per new Gazette notification of MOEFdated 14.09.06

    Land Commitment (State Govt.) Water Commitment (State Govt.) Fuel Commitment (SLC-LT) Fuel Transportation Clearance (Min. of

    Railways)

    Defence Clearance (Min. of Defence) Comfort Letters from Beneficiaries Resolution in Respective REB Meeting in

    respect of Absorption of Power from theProject

  • 7/31/2019 Fr Formulation

    25/39

    Associated Transmission System (ATS)Clearance

    NOC from Airports Authority of India Minutes of Public Consultation from SPCB Concurrence of Central Water Commission/

    MOWR on Water Availability Environmental Clearance from Ministry of Env.

    and Forests

    FORMULATION OF FR / DPR

  • 7/31/2019 Fr Formulation

    26/39

    Tie-up of Basic Inputs

    Conduct Site Specific Studies/Investigations

    Basic Engg./System Finalisation

    Technical Inputs (Write up, BOQ,Drawings)

    Inputs other than Technical

    Clearances / Commitment Financing Plan

    Cost Estimates

    FORMULATION OF FRs/ DPRs

    FORMULATION OF FR / DPR

  • 7/31/2019 Fr Formulation

    27/39

    Financial Appraisal by FIs post FR/DPR Finalisation

    TEC of CEA Pre and Post ElectricityAct- 2003 Scenario

    Development of Infrastructure Financial Appraisal by FIs prior to

    Investment Decision

    Statutory Clearances/ Commitments

    FORMULATION OF FRs/ DPRs

    FEASIBILITY REPORT CONTENTS

  • 7/31/2019 Fr Formulation

    28/39

    Executive Summary

    Introduction

    Demand Analysis and Justification

    Feasibility Studies Layout Systems

    Civil Works

    Mechanical Systems Electrical Systems

    Control & Instrumentation Systems

    FEASIBILITY REPORT- CONTENTS

    FEASIBILITY REPORT CONTENTS

  • 7/31/2019 Fr Formulation

    29/39

    Environmental Aspects

    Technical Data & Bill of Quantity

    Cost Estimate & Financial Analysis

    Project Implementation Manpower training & Placement

    Operation & Maintenance Philosophy

    Marketing Philosophy List of Annexure

    List of Exhibits

    FEASIBILITY REPORT- CONTENTS

    INFRASTRUCTURE DEVELOPMENT

  • 7/31/2019 Fr Formulation

    30/39

    Initiate activities for land acquisitionunder Land Acquisition Act

    Construction of Boundary Wall/Fencing of the acquired land

    Construction of Site Office, Storesand other temporary building tofacilitate construction activities

    Site Levelling of Plant incl. PriorityArea of Township

    Construction Power & Start-up Power

    INFRASTRUCTURE DEVELOPMENT

    INFRASTRUCTURE DEVELOPMENT

  • 7/31/2019 Fr Formulation

    31/39

    Construction Water Scheme

    Communication & EDP facilities

    Training Centre, Public InformationCentre and other R&R activities

    Primary Health Care

    Establishment of Security Complex

    INFRASTRUCTURE DEVELOPMENT

    INVESTMENT APPROVAL

  • 7/31/2019 Fr Formulation

    32/39

    Availability of Infrastructure

    All clearances/ commitments inposition

    PPAs signed with beneficiaries

    ATS finalised and would beimplemented matching power projectschedule.

    Financial Appraisal by FIs prior toInvestment Decision

    INVESTMENT APPROVAL

    SCHEDULE FOR PROJECT FORMULATION ACTIONS Th l

  • 7/31/2019 Fr Formulation

    33/39

    SCHEDULE FOR PROJECT FORMULATION ACTIONS ThermalZero Date - Project Initiation and Identification of Potential Sites

    Main Plant Award relatedactivities (Month from zero date)

    Green Field Expn.Project

    Investment Approvalactivities (Month fromzero date)

    GreenField

    Expn.Project

    Specs. Preparation 10 7

    Site Selection/Pre FR 3 0

    FSC for Main Plant 13 10

    FR Preparation 12 9

    Studies/Investigationsand Statutory Clearances

    10 7

    Financial Appraisal 12 9

    FR Finalisation 13 10

    Public Hearing (SPCB) 15 12

    NIT 14 11

    Environmental Clearance 19 16

    OBD 17 14

    Financial Appraisal 18 15

    Main Plant Package Award 20 17Investment Approval 19 16

  • 7/31/2019 Fr Formulation

    34/39

  • 7/31/2019 Fr Formulation

    35/39

    Project Name Capacity(MW)

    Location Capacity Addition(MW)

    Kahalgaon-II 1500 Bhagalpur(Bihar) 1000

    Sipat-II 1000 Bilaspur (Chhattisgarh) 1000

    Sipat-I 1980 Bilaspur (Chhattisgarh) 1980

    Barh-I 1980 Patna (Bihar) 1980

    Bhilai JV 500 Bhilai (Chhattisgarh) 500

    Korba-III 500 Korba (Chhattisgarh) 500

    Farakka-III 500 Murshidabad (W. B.) 500

    NCTPP-II 980 Gautam Budh Nagar (U. P.) 980Simhadri-II 1000 Visakhapatnam (A. P.) 1000

    Aravali JV withHPGCL & IPGCL

    1500 Jajjar (Haryana) 1500

    Ennore-JV with TNEB 1500 Thiruvallur (Tamil Nadu) 1500

    Bongaigaon 750 Kokhrajhar (Assam) 750

    North Karanpura 1980 Chatra & Hazaribagh (Jharkhand) 1320

    Barh-II 1320 Patna (Bihar) 1320

    Nabinagar JV withRlys.

    1000 Aurangabad (Bihar) 750

    Vindhachal-III 1000 Sidhi (M.P.) 1000

    Mauda 1000 Nagpur (Maharashtra) 1000

    Rihand-II 1000 U.P. 1000

    Muzafferpur II 500 Bihar 500

    XI PLAN PROJECTS (THERMAL GAS)

  • 7/31/2019 Fr Formulation

    36/39

    XI PLAN PROJECTS (THERMAL-GAS)

    Project Name Capacity(MW) Location CapacityAddition(MW)

    Kawas CCPP, Stage-II* 1300 Surat (Gujarat) 1300

    J. Gandhar CCPP, Stage-II* 1300 Bharuch (Gujarat) 1300

    Total 2,600 2,600

    * To be taken up after fuel availability is ascertained.

    XI PLAN PROJECTS (HYDRO)

  • 7/31/2019 Fr Formulation

    37/39

    XI PLAN PROJECTS (HYDRO)

    Project Name Capacity(MW) Location CapacityAddition(MW)

    Koldam 800 Bilaspur (H.P.) 800

    Loharinag Pala 600 Uttarkashi (Uttaranchal) 600

    Tapovan Vishnugad 520 Chamoli (Uttaranchal) 520

  • 7/31/2019 Fr Formulation

    38/39

    Project Name Location Capacity(MW)

    ThermalMarakkanam Villupuram (Tamil Nadu) 4000

    Cheyyur Kanchipuram (Tamil Nadu) 2000/2400

    Aravali-II, Jhajjar, Haryana 1000

    Vindhyachal-IV Sidhi (M.P) 500

    Rihand-III Sonbhadra (UP) 500

    Darlipali Sundergarh (Orissa) 3200

    Gajmara Dhenkanal (Orissa) 3200

    Lara Raigarh (Chhattisgarh) 4000

    Derang Angul (Orissa) 2400

    New Nabinagar JV with BSEB Aurangabad (Bihar) 2640

    Tanda-II Ambedkar Nagar (U.P.) 1000

    Rajiv Gandhi CCPP (Kayamkulam) Allappuzha (Kerala) 1980

    Meja STPP JV with PURVUN Allahabad (Uttar Pradesh) 1980

    Nuclear 2000

    Total 27,200

    PROJECTS UNDER CONSIDERATION

  • 7/31/2019 Fr Formulation

    39/39

    PROJECTS UNDER CONSIDERATION

    Project Name Location Capacity

    (MW)HYDRO

    RupsiabagarKhasiabara

    Uttaranchal 260

    Etalin Ar. Pradesh 4000

    Attunli Ar. Pradesh 500

    Total 4760