Small or medium scale focused research project (STREP)Date of preparation: 01.01.2011.
Work programme topic addressed: ICT 2011.2.1 Cognitive Systems and Robotics (a)Name of the coordinating person: Radović Petar, Nikola Ranković
Small or medium-scale focused research project (STREP) proposal
ICT Call 7FP7-ICT-2011-7
Petar Radović, Nikola Ranković, 1/4/2011
2 / 18
Table of contents Project partnersProject abstractConcept and objectivesThe overall strategy of the work planGantt chartWork package listDeliverable listList of milestonesSummary effort tablePert chartEthical issues
Petar Radović, Nikola Ranković, 1/4/2011
Participant no. Participant organisation name Part. short name
Country
1 (Coordinator) University of Belgrade, Mathematical Faculty, http://www.matf.rs
MAT Serbia
2 University of Belgrade, Faculty of Electrical Engineering, http://www.etf.g.ac.rs
ETF Serbia
3 Technische Universiteit Eindhoven, http://www.tue.nl
TUE Netherlands
4 Softkinetic, http://www.softkinetic.com SK Belgium
5 GoalEurope, http://www.goaleurope.com GE Germany
6 MEDIApro, http://www.mediapro.es MEDIA Spain
7 Philips Research, http://www.research.philips.com
PR Netherlands
8 Our Space d.o.o, http://www.ourspace.si SPACE Slovenia
3 / 18
Project partners
Petar Radović, Nikola Ranković, 1/4/2011
Latest advances in Computer Vision Goal:
◦ Affordable◦ Easily accessible
Potential to transform Open access is the key Final product:
◦ HW Prototype of a standard◦ SDK
4 / 18
Project abstract
Petar Radović, Nikola Ranković, 1/4/2011
Developing a computer vision system Along with software development kit A new standard Possibly mass-produced at a low cost
5 / 18
Concept and objectives
Petar Radović, Nikola Ranković, 1/4/2011
Click icon to add picture
6 / 18
High-level representation of concepts and objectives
existing technology
existing algorithms
development of new tools & integration
means for manufacture of affordable
devices
SDK development
end products
Petar Radović, Nikola Ranković, 1/4/2011
The project is organized in 9 work packages:◦ WPO Project management◦ WP1 Development of Use Cases◦ WP2 Development of System Architecture◦ WP3 Hardware Details◦ WP4 Software Details◦ WP5 Proof of Concept Implementation◦ WP6 Testing◦ WP7 Dissemination◦ WP8 SDK release to third-parties
7 / 18
The overall strategy of the work plan
Petar Radović, Nikola Ranković, 1/4/2011
8 / 18
Gantt
chart
FEB MAR APR MAY JUN JUL AVG SEP OCT NOV DEC JAN
Petar Radović, Nikola Ranković, 1/4/2011
9 / 18
Work package listWork
package
No
Work package title Type of activity
Lead partic
no.
Lead partic. short name
Person-
months
Startmonth
Endmonth5
WP0 Project management MGT 1 GE 72 M1 M12WP1 Development of Use
CasesRTD 1 SK 10 M1 M1
WP2 Development of System Architecture
RTD 1 TUE 16 M1 M4
WP3 Hardware Details RTD 2 ETF, PR 12 M2 M3WP4 Software Details RTD 2 MAT, SK 16 M2 M3WP5 Proof of Concept
ImplementationRTD 2 SK, PR 10 M5 M5
WP6 Testing of the ACCOV system
RTD/DEM 1 MAT, ETF, TUE
120 M6 M9
WP7 Informing the scientific and technical environment, investors and market
DEM 1 MEDIA 60 M6 M12
WP8 Public release of the SDK RTD/DEM 2 PR, MAT 60 M9 M12TOTAL 376
Petar Radović, Nikola Ranković, 1/4/2011
Del. no. Deliverable name WP no. Nature Dissemination
level
Delivery date
(projected
month)D0.1 Minutes from each Steering
Committee meetingWP0 R PU M1, M6, M12
D0.2 Project handbook including quality management plan (at the kick-off meeting)
WP0 R PU M1
D0.3 Periodic reports at periods specified in the Grant Agreement
WP0 R PU M1, M3, M6, M9, M12
D0.4 Signed Consortium Agreement WP0 R PU M1D0.5 Audit certificates for each
participant at times stated in the contract
WP0 R PU M12
D0.6 Final reports at the conclusion of the project (final activity report, final management report, supplementary final reports and a report on distribution between participants of the final payment)
WP0 R PU M12
10 / 18
Deliverable list (WP0)
Petar Radović, Nikola Ranković, 1/4/2011
11 / 18
Deliverable list (WP1 – WP6)D1.1 Top level Use Case
diagramsWP1 O PU M1
D1.2 Detailed Use Case diagrams
WP1 O PU M1
D2 Architecture Specification WP2 R RE M2D3.1 Report on HW built into the
systemWP3 R PU M3
D3.2 Report on Communication system built into the system
WP3 R PU M3
D4.1 Procedure details WP4 R PU M2D4.2 Algorithmic details WP4 R PU M2D4.3 Report on SW built into the
systemWP4 R PU M3
D5.1 CMMI and system schemes WP5 R CO M5D5.2 Documented code WP5 R PU M5D6.1 Report on testing results
(MAT)WP6 R PU M6, M7, M8, M9
D6.2 Report on testing results (ETF)
WP6 R PU M6, M7, M8, M9
D6.3 Report on testing results (TUE)
WP6 R PU M6, M7, M8, M9
Petar Radović, Nikola Ranković, 1/4/2011
12 / 18
Deliverable list (WP7 – WP8)D7.1 Dissemination Plan WP7 R RE M6D7.2 Project promotional
materialsWP7 R PU M6, M8, M10,
M12D7.3 E-bulletin/newsletter
releasedWP7 R PU M6, M7, M8,
M9, M10, M11, M12
D7.4 2 Workshop reports WP7 R PU M6, M12D7.5 2 Seminar reports WP7 R PU M6, M12D7.6 Report on participation
on international conferences
WP7 R PU M12
D7.7 Scientific articles WP7 R PU M12D7.8 Articles published in
local mediaWP7 R PU M7, M11
D8.1 SDK Checklist WP8 R RE M10, M11, M12
D8.2 SDK published online (and possibly updated)
WP8 O PU M11, M12
Petar Radović, Nikola Ranković, 1/4/2011
13 / 18
List of milestonesMilestone number
Milestone name Work package(s) involved
Expected date Means of verification
M0.1 Kick-off meeting WP0 M1 Minutes from kick-off meeting
M0.2 Consortium agreement signed
WP0 M1 Consortium Agreement with partner signatures
M0.3 Project shut-down – all deliverables
achieved
WP0 M12 Final deliverables report
M1 Finished Use Cases
WP1 M1 Use Case documentation
M2 System architecture
defined
WP2 M3 Architecture specification
M3 HW details defined and
clarified
WP3 M3 HW report
M4 SW details defined and
clarified
WP4 M3 SW report
M5 System tested in real life scenarios
WP5 M5 CMMI and code documentation
M6 System performance test
WP6 M6-M10 Reports on the testing results
M7 SDK Version 1 released
WP8 M11 SDK published online
Petar Radović, Nikola Ranković, 1/4/2011
14 / 18
Summary effort tablePartic
. no.Partic. short name
WP0 WP1 WP2 WP3 WP4 WP5 WP6 WP7 WP8 Total person months
1 MAT 2 1 4 0 12 0 38 2 26 85
2 ETF 2 0 4 8 0 0 38 2 5 59
3 TUE 2 0 8 0 0 0 38 2 5 55
4 SK 2 1 0 0 4 5 0 4 4 20
5 GE 58 0 0 0 0 0 0 2 0 60
6 MEDIA 2 0 0 0 0 0 0 42 0 44
7 PR 2 0 0 4 0 5 6 4 20 41
8 SPACE 2 8 0 0 0 0 0 2 0 12
Total 72 10 16 12 16 10 120 60 60 376
Petar Radović, Nikola Ranković, 1/4/2011
Click icon to add picture
15 / 18
Pert chart
WP0
WP1
WP2
WP3
WP4
WP5
WP6
WP8
WP7
Petar Radović, Nikola Ranković, 1/4/2011
No direct ethical, legal, social and safety issues
May arise with the training data Consent asked beforehand “I CONFIRM THAT NONE OF THE ABOVE
ISSUES APPLY TO MY PROPOSAL”
16 / 18